Download - Project Progress Ppt
3 Double Height Basements completed ahead of schedule. (18,900 Sq. Ft.)
Podium with Swimming pool completed.
Transfer Slab at 5.2m height, 1.2m depth expected completion 7 days ahead of schedule.
Over all project: 30+ days ahead of schedule.
Organization Chart
Mr. Nitin Agresar Sr. VP & Head Projects
Mr. Amesh Dharmale Sr. Project Manager
Mr. Shivram Desai Sr. Site Engr.
Mr. Sachin Mangutkar Storekeeper
Execution DepartmentBackbone of the project
Responsibilities Assure timely completion of the project. Assure Best possible quality Assure safe and clean workplace
Support System: Design Department Stores Department Purchase Department Contracts Department MEP & Services
HOUSEKEEPING AND SAFETY
Preparation of project specific HSE Plan ,HIRA Register for site
Induction Training to All workers & staff .
Sub contractor foreman refresher Training
Safety Committee & its meeting.
Safety Inspection of mechanical equipment
Power Tools & Hand tools safety.
SAFETY EQUIPMENT
Following of SOPs Electrical safety – Provision
of Earthing, ELCB,Hot Work safety Inspection of Temporary
structures Peripheral & lift duct
barricadingFall Protection - Safety
net Provision.
Shuttering from World Class “RMD KWICKFORM” used for speed and quality
Best in class machinery from German Wacker Neuson ,Bosh & DeWault used for the project.