Download - QUOVADIS GRANT - Agreement EIE/031/S07.38597
1Consortium meeting, December 14, 2006
QUOVADISGRANT - Agreement EIE/031/S07.38597
Quality Management Organisation, Validation of standards, Developments and Inquiries for SRF
PROGRESS REPORT FOR WP1, WP8 and WP9
Ispra, December 14 2006
Project supported by
Consortium meeting, December 14, 20062
Work Packages
WP 1 – Co-ordination and Management
WP 2 – A holistic approach for quality management and classification
WP 3 – Organisation of validation exercises
WP 4 – Sampling
WP 5 – Physical parameters
WP 6 – Chemical parameters
WP 7 – Biological parameters
WP 8 – Data collection
WP 9 – Dissemination
3Consortium meeting, December 14, 2006
WP 1 - Co-ordination and management• UP TO NOW all expected deliverable has been produced and send to the Commission.
• Two positive feedback by the Commission concerning the QUOVADIS progress
letter From Commission related to the period 01/01/2005 - 30/06/2005letter From Commission related to the period 01/07/2005 - 31/12/2005
• Problem for the publication of the final version of the TSs to be validated will be charge on the QUOVADIS web site
Consortium meeting, December 14, 20064
WP 1 - Co-ordination and management
• The second amendment necessary following the transfer of the QUOVADIS Project from CESI to CESI RICERCA in being active
Some word about CESI RICERCA
• Relevant document published on the website for ASC to give indication about the work done
• All the TS to be validated will be soon charge on the QUOVADIS web site
5Consortium meeting, December 14, 2006
WP 1 - Co-ordination and managementDELIVERABLES DUE BY THE END OF DECEMBER 2006
Contribution expected by each WP leader not later than December 15, 2006, because they will be included in the Interim Report for the payment
MONTH WP WP TITLE DELIVERABLE CONTENTTYPE OF
DOCUMENT NUMBER
19 WP 9.1 Ow n dissemination D9.1.4
Results and follow -up of the f irst dissemination conference including slide
packages, presentations, w ritten abstracts, posters, dissemination material, etc. Technical Report 38
20 WP 2Quality management and
classif ication D2.4 European database on SRF production
Technical Report, including an Excel based data base 8
24 WP 1Co-ordination and
Management D1.3 Progress Report Synthetic Report 3
24 WP 9.2 Common Dissemination D9.2.2
Abstract, including regular updates. Project presentation slides, packages presentation,
w ritten abstracts, posters, dissemination material, etc. Presentational material including abstracts, visuals including
photographic material, interview s Technical Report 39
6Consortium meeting, December 14, 2006
WP 1 - Co-ordination and managementINTERIM PAYMENT
• Period covered: January 2005 - October 2006
• Dead lime for delivering: December 31, 2006
• Forms to be fill in and guideline available at the QUOVADIS Website
7Consortium meeting, December 14, 2006
WP 8 - Data CollectionActivity done by CENERG
CENERG analysed the documents related to waste management in Poland:• Data from the Main Statistic Office for the year 2006,• Publication from the Ministry of Environment, • Energy Market Agency (ARE SA).According to this documents CENERG started update data on waste generation, management and market potential for solid recovery fuels in Poland.Collected synthetic information on waste production and consumption during last decade from 1990-2004, to present simplified balance of waste energy use.
8Consortium meeting, December 14, 2006
WP 8 - Data CollectionActivity done by CENERG
Many contacts with Czech Republic, Slovak Republic, Baltic area (Lithuania, Latvia and Estonia), Bulgaria, Hungary and Romania to try to update the data already collected.Contact with Municipal Solid Waste (MSW) incineration plant located in Warsaw. In the MSW plant the municipal waste are segregated, than they are partly recycled, composted or combusted. The energetic fraction is combusted with moving grate boiler. Flue gasses are completely combusted with the support of gas or oil.The incineration capacity amounts to 50 000 tonnes per year, ca. 150 tonnes per day. The available incineration capacity amounts to ca. 260 000 tonnes per year.
9Consortium meeting, December 14, 2006
WP 9 - Dissemination
• Organisation of the dissemination events that results in the schedule given at the QUOVADIS web site
• The second dissemination meeting and Workshop:
“Waste Management and Solid Recovered Fuels Potential in the Enlarged European Union
Larnaca (Cyprus), June 22-23, 2006”
Proceeding are in progress and will be published on the QUOVADIS website
10Consortium meeting, December 14, 2006
CESIricerca
A new player in the electric sector research
11Consortium meeting, December 14, 2006
Our history
Since 2000, ENEL Research Division has been moved in CESI, substantially widening the business area
CESI (Centro Elettrotecnico Sperimentale Italiano) was founded in 1956 by Italian utilities and manufacturers
12Consortium meeting, December 14, 2006
Establishing CESI RICERCA
• Since January 1st, 2006, transfer of the “research” branch of CESI to the the new company
• Four hundred technicians and researchers and their main laboratories
• Mission: public interest research for the electrical system
• Focus: applied experimental research • Shareholders: mainly public operators (ENEA 51 % of
the stock) and other public sectors research Institutes (in the near future)