REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS
(TTR)
supported byTTR Plenary Day
Vienna, 25 September 2019
![Page 2: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/2.jpg)
2
TTR pilots
![Page 3: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/3.jpg)
3
TTR Pilots: Topics
− Aim of the pilots, organisational set-up
− Phase 1 of pilots and first achievements
− Phase 2 of pilots and first findings
− Q&A
![Page 4: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/4.jpg)
4
Introduction to TTR Pilots
In order to test the new approach to capacitymanagement developed in TTR, several pilotshave been launched:
- Test the innovative components in real life
- To improve the process
- Definition and specification of data referencemodel for capacity
- To detect pressure points
- To use lessons learned for full TTR rollout
The focus when selecting the pilots was on RFC lines: Possibility of own rules thanks to FCA (Framework for Cap. Allocation, 913/2010/EU).
![Page 5: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/5.jpg)
5
Introduction to TTR Pilots
The pilot itself will be conducted in three phases:
- Phase 1: Capacity partitioning andcapacity planning
- Phase 2: Capacity publication and capacity requests for TT 2020
- Phase 3: Running timetable 2020
![Page 6: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/6.jpg)
6
Introduction to TTR Pilots
TTR overall structure:
![Page 7: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/7.jpg)
7
TTR Pilots: Achievements (I)
− Development of functioning organisations for the respective pilots
− Good cooperation thanks to highly motivated IMs
− Broad-based willingness ofstakeholders (Ministries, ports/terminals, Regulatory Bodies,applicants) to participate in thepilots
Ex.: Organisation of Pilot Antwerp - Rotterdam
![Page 8: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/8.jpg)
8
TTR Pilots: Achievements (II)
− Creation of Cap. Models with the support of applicants for TT 2020
− Publication of available capa-city for TT 2020 in Jan. 19
− Availability of a tool (PCS) forplacing the first RollingPlanning requests in Aug. 19
− First requests for RollingPlanning Cap. for TT 2020received
![Page 9: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/9.jpg)
9
TTR Pilots: Achievements (III)
− Publication of a “Pilot Information Document”
Pilot Information Document focusses on thedescription of the new TTR concepts that aretested in the pilot.
![Page 10: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/10.jpg)
10
TTR Pilots: Achievements (IV)
− Development of a ECMT (tool for visualising Cap. Model)
![Page 11: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/11.jpg)
11
TTR Pilots: Lessons Learned (I)
− Management attention is crucial for the success of the pilots
− Planning and coordination of TCRs respecting 2012/34 Annex VII is still difficult
− Benefits for passenger RUs must be tested as well
− Ministries of Transport and Regulatory Bodies are required to implement strategic thinking (not only based on existing laws) and allow tests
− Need for increased resources for IT implementation (nat. and internat. level)
− Commercial Conditions required to influence applicants’ path requesting behaviour and IMs’ allocation processes (incentive to respect agreed processes)
− Multi-annual validity of a Rolling Planning request require legal backing
![Page 12: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/12.jpg)
12
TTR Pilots: Lessons Learned (II)
Path requests for TT 2020:
− Capacity Model was built based on announcements from applicants with their needs for Annual TT and Rolling Planning traffic
− Pilots published PaPs (as required by 913/2010) and Rolling Planning Cap. in January 2019, based on these announcements
− Experiences:
o Applicants requested PaPs for pre-announced Rolling Planning Cap.
o Applicants requested Internat. Rolling Planning Cap. as Annual TT traffic by using national tools (Pilot Antwerp-Rotterdam)
o Paths were requested in time windows where no capacity was published in the Cap. Model
− TTR pilot message has not clearly beeing understood by applicants even they were deeply involved as member of the Pilot Advisory Board
![Page 13: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/13.jpg)
13
Findings in the TTR Pilots− Absence of (harmonised) rules on capacity partitioning phase constitutes a
risk − Example: Some IMs are concerned that RBs may e.g. challenge their capacity
model/split.
− Different interpretation of Directive 2012/34 leads to heterogenous national legal frameworks and/or (uncoordinated) RB action that may hamper a harmonised implementation of TTR.
− Example 1: diverging opinions regarding the possibility to set aside capacity for rolling planning requests lead to legal uncertainty e.g. in case of an annual TT request conflicting with safeguarded RP capacity
− Example 2: national capacity allocation frameworks are in some MS enshrined in law and much more detailed than EU law, limiting the IM’s ability to implement TTR
− Example 3: diverging national law and RB decisions on commercial conditions (FR vs DE vs IT etc.) make it difficult, if not impossible, for IMs to agree on a common set of CCs
![Page 14: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/14.jpg)
14
TTR Pilot Antwerp – Rotterdam
− Creation of Capacity Model
• Applicants had difficulties to make a traffic forecast, proposed to take IMs own historical data.
• Inclusion of TCRs:
− Asset/construction departments of ProRail and Infrabel exchanged information/data for the first time for the mid-term planning.
− Stability of TCR planning, but not all TCRs need to be planned in Annual Timetable
− TCRs on other lines with an impact on the pilot line
• Splitting of available capacity was a challenge. What are the shares for Pre-arranged Paths/PaPs (legally still required), Annual Timetable and Rolling Planning Cap.?
![Page 15: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/15.jpg)
15
TTR Pilot Antwerp – Rotterdam
− Capacity publication and requests for TT 2020
• On-time publication in an Excel-file (https://cms.rne.eu/ttr-communication-platform/rotterdam-
antwerp-library)
• TCR: up to 75% of published TCRs needed to be changed
• Participating key applicants have a different approach/vision on Rolling Planning
• Despite Rolling Planning Offer, 1/3 more requests for Annual Timetable 2020 than real usage in TT 2019 (… and based on last years’ experiences will be cancelled…)
• First intentions of applicants for placing Rolling Planning requests failed due to missing PCS experience.
![Page 16: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/16.jpg)
16
TTR Pilot Antwerp – Rotterdam
− Capacity Model for TT 2021
• First known TCRs already discussed between BE, NL and DE (rerouting)
• A two step approach is foreseen:
− X-11: Publication of Annual TT Cap., Rolling Planning volume for a standard day and known TCRs
− X-6: Rolling Planning Cap. for 365 days, update of TCRs (incl. inclusion of minor TCRs)
• Elaboration of Cap. Model with the support of ECMT
• Analysis of extension of pilot line from Antwerp via Brussels to Paris (inclusion of high-speed passenger trains)
![Page 17: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/17.jpg)
17
TTR Pilot RFC Atlantic
− Creation of Capacity Model• Inclusion of
− traffic data section by section fora normal day
− Regular-interval timetable
− Freight traffic matrix includingcapacity bandwidths
− 24-hour view of the model(bandwidths and TCRs)
• Aim to offer 8 paths for AnnualTimetable and 2 for RollingPlanning Traffic
![Page 18: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/18.jpg)
18
TTR Pilot RFC Atlantic
− Creation of Capacity Model for TT 2020 had to be stopped
• Due to high amount of TCRs with a negative impact on the foreseen capacity
• Low level of TT colleagues’ availability to study an axis view
• TT colleagues were not convinced that TTR will help them and tried to stick to former process which led to delays, lack of coordination and improper use of the capacity model
![Page 19: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/19.jpg)
19
TTR Pilot RFC Atlantic
− Capacity Model for TT 2021 & 2022
• Creation of models are still in progress. Nevertheless, process are still to be written and shared by all entities involved.
• Cap. Model TT 2021 for Atlantic pilot considers a single band with 5 long-distance paths each way (4 for Annual TT, 1 for Rolling Planning without any multiannual consideration)
• For now, risk still exists to have no commercial capacity for TT2021 due to too confiscatory TCRs.
![Page 20: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/20.jpg)
20
TTR Pilot Munich – Verona
− Creation of Capacity Model
• Inputs (cap. needs) of applicants: early announcements change massively from the first request at X-16 till the second request at X-9
• TTR-Pilot Brenner observed avery high variance ofannouncements from thedifferent applicants
• TCRs: IM planning process notstable. Hence, input for Cap.Model is too volatile
![Page 21: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/21.jpg)
21
TTR Pilot Munich – Verona
− Capacity publication and requests for TT 2020
• On-time publication in an Excel-file of pre-constructed system pathsfor Annual TT and capacity bands with Rolling Planning paths for everyweekday (https://cms.rne.eu/ttr-pilots-communication-platform/brenner-library)
• Customers indicate demandfor Rolling Planning also atAnnual TT deadline toensure the reservation forRolling Planning capacity
• Several requests for RollingPlanning capacity werealready placed
![Page 22: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/22.jpg)
22
TTR Pilot Munich – Verona
− Capacity Model for TT 2021
• Start of discussions on different ways to shift dynamic traffic from the Annual TT to Rolling Planning (incl. exchange of view for Rolling Planning capacity with applicants)
• Validation of Cap. Model based on early announcements as a base for Rolling Planning capacity is regarded as critical
− Other issue
• Discussion with German Regulatory Body regarding the treatment of the TTR pilot in the Network Statement
![Page 23: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/23.jpg)
23
TTR Pilot ÖBB Network
Capacity Model including system paths for Timetable 2021 is currently being developed and the possibility of technical implementation in path planning/scheduling is being examined.
![Page 24: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/24.jpg)
24
Experiences from TTR Pilots
o Common commercial conditions
o IT
o Legal framework (national)
The TTR Pilots showed: Several preconditions need to be provided!
Planning capacity needs to be predictable and reliable.
![Page 25: REDESIGN OF THE INTERNATIONAL TIMETABLING PROCESS (TTR)rne.eu/wp-content/uploads/2019-09-25_TTR_Plenary_Day... · 2019-10-31 · INTERNATIONAL TIMETABLING PROCESS (TTR) TTR Plenary](https://reader033.vdocuments.net/reader033/viewer/2022050403/5f8083daabf6e84a885c13c6/html5/thumbnails/25.jpg)
25
How to Support the Pilots?
− Implement /experiment with TTR process elements in your network− Capacity model is the key element and can be tested “outside” normal process
(applicable for lines/countries that are not yet involved in a pilot)
− Reduce national particularities by increasing the willingness to change national processes and adapt them with neighbours
− Start discussions between Regulators/Ministries, IMs and RBs about the adaptations that are needed for TTR on national level
The TTR team gladly shares its knowledge and helps in implementing tests of TTR items!