Strategic Planning for Contaminated Sediment Projects:
Setting the Course for Proper Project Execution
Howard L. CumberlandGeosyntec Consultants
October 24, 2012
![Page 2: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/2.jpg)
Talk Overview
Regulatory Considerations Conceptual Site Model Client Understanding and Developing the
Desired End-Game Strategy Agency Negotiations Project Completion
![Page 3: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/3.jpg)
Regulatory Considerations
Investigation/Disposal Clean Water Act
404, 401, 303d, NPDES CERCLA, RCRA, Promulgated State Programs Rivers and Harbors Act Marine Protection Resources and Sanctuary Act
Restoration Oil Pollution Act (OPA) – NRDA ESA, Wetlands
Tribes/Public
![Page 4: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/4.jpg)
Conceptual Site Model
![Page 5: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/5.jpg)
Strategy Development
Complexities require a strategy that is based on total project goals: Business objectives Regulatory and Stakeholder objectives Short- and long-term goals
Continually re-assessed and forward looking Continually discussed with Management and
Regulators
![Page 6: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/6.jpg)
Client Strategy What is the Business Strategy?
Operating property or Legacy Site Is there Insurance?
Many clients and regulators do not have sediment-specific technical expertise
Previous Owners Adjacent properties (PRPs) and are you
aligned? What is timing?
Can investigations be combined with new- or re-development?
Is property for Sell?
![Page 7: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/7.jpg)
Study Design – Strategic Planning
What are the Questions Being Asked by the Agencies? How Do We Answer the Questions?
How to Define and Agree on Objectives? How Sophisticated are the Data Needs?
What Are the Sources/Pathways? How many do you assess at once?
What Are the Ranges of Successful Outcomes?
![Page 8: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/8.jpg)
Data Needs
Multiple Pathways and contaminant sources (site and non-site related)
Source identification Nature and extent of contamination – horizontal and
vertical Contaminant fate and transport Hydrodynamics and hydrology Exposure pathways and biological receptors FS data needs Remedial Options CONTINUALLY ADD DATA AND RE-EVALUATE
CSM
![Page 9: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/9.jpg)
Formulate the Study Questions
What level of contamination is a concern, and over what area?
What are the Sources? What are the unknowns? What do you need to know in order to make
decisions about how to clean up or manage the site?
What are the perceptions of the agencies? What are the receptors? Are there Published/Accepted sediment risk
criteria? What might be the end game?
![Page 10: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/10.jpg)
Define the primary contaminants Determine which are yours Identify Your and other sources
• Historical operations• Current Operations• Stormwater other inputs
Identify and Evaluate COPCs
![Page 11: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/11.jpg)
Components of Sediment Investigation
PhysicalBiological
Chemical
• Water Use• Bathymetry
• Bearing Strength• Mixing Layer Depth
• Particle Size / Distribution
• Groundwater Interaction
• Hydrodynamics
• Toxicity• Human Fish Consumption
• Susceptible Species Assessment
• Indicator Species Analysis
• Habitat Stressor Analysis
• Emergent / Submergent Plants• Bioavailability
• Radiometric Dating• Biota Concentrations• Pore Water Analysis
• Surface/Vertical Contaminant
Concentrations• Contaminant
Speciation• Geochemistry
![Page 12: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/12.jpg)
Multiple PRPs
![Page 13: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/13.jpg)
![Page 14: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/14.jpg)
![Page 15: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/15.jpg)
![Page 16: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/16.jpg)
![Page 17: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/17.jpg)
Restrict Depth of Excavation
![Page 18: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/18.jpg)
![Page 19: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/19.jpg)
Joint Defense Agreement - Privileged and Confidential
2012
![Page 20: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/20.jpg)
1934
![Page 21: Strategic Planning for Contaminated Sediment Projects: Setting the Course for Proper Project Execution Howard L. Cumberland Geosyntec Consultants October](https://reader035.vdocuments.net/reader035/viewer/2022062412/5a4d1aff7f8b9ab0599860e5/html5/thumbnails/21.jpg)
Complex Sediment Sites Require: A Comprehensive and Integrated Project Strategy Experienced Multi-disciplinary Team Focus on Business and Regulatory goals to maintain positive momentum and direction
Conclusions