Final Presentation
CONTENTSIntroductionObjectiveMethodologyPrimary dataScaleDimension in reduced scaleResource usedSteps used to prepare 3-D modelDifficulties on Fieldwork BenefitsConclusions
INTRODUCTIONPanauti Hydropower Project is the third hydropower
project of Nepal.Located in Roshi river, Khopasi(Kavre), 35 km east of
Kathmandu.Commissioned during 1960-1965 by the joint effort of
USSR and Nepal government.An installed capacity of 2.4 MW.
OBJECTIVEStudy and prepare the 3-D model for the powerhouse and
switchyard of Panauti Hydropower Project.
Sub-objectives: To study the placement of general equipments inside.To know the surveying techniques, fieldwork, etc.
METHODOLOGY
Primary Data collection (measurements,
observations , etc.)
Start
Desk study Field study
Secondary Data collection (surfing
internet, library visit)
Model Preparation
Final report
PRIMARY DATAPowerhouse
Length=2475cm.
Breadth=1840cm.
Height=709cm.
SwitchyardLength=2740cm.
Breadth=1140cm.
Height of fence=244cm.
Height difference between powerhouse and switchyard=975cm.
Scale:The scale is reduced in the ratio 1:55 to include
powerhouse and switchyard in the plywood of 1*1 m
which further includes automatically staff house.
DIMENSIONS IN REDUCED SCALE:S.N.
Dimension Of : Dimension(cm)
1 Length of powerhouse 45
2 Breadth of powerhouse 33.5
3 Height of wall towards switchyard (powerhouse)
13
4 Height of wall towards river (powerhouse)
15
5 Height difference between powerhouse and switchyard from base to base
17.7
6 Length of switchyard 49.8
7 Breadth of the switchyard 20.7
8 Height of fence of switchyard 4.5
9 Height of the highest tower inside switchyard
12.9
RESOURCES USED• Instruments: Measuring Tape• Software: AutoCAD
Materials:
- Plywood - Net
- Thermo coal - Hammer
- Fevicol - Chisel
- Paint - Rip saw
- Buttons - Aluminium plate
- Wires - Aluminium and wire cutter
- Knife
STEPS USED TO PREPARE 3-D MODEL -wood works by rip saw and chisels
- cutting the thermo coal by knife -representing the wire by house wire -representing insulators by buttons -potential transformer and oil circuit breaker
by aluminium plate -fence of switchyard by net -towers by net and wood - transformers, turbines and generators by
thermo coal
ACTIVITIES Feb April May June July
weeks weeks weeks weeks week
1 2 3 1 2 3 1 2 3 4 1 2 3 1
Discussion on project and preparing proposal
Proposal presentation
Site visit and field work.
Materials Purchased
Mid Term Presentation
Model preparation including topography
Making and presenting report+model
DIFFICULTIES ON FIELDWORKCrossing the fence of switchyard was prohibited.Restriction of close observation of equipments and
machinery of the powerhouse.Cost overrun compared to forecasted.
RESULTSSurvey and Measurement of power house and switchyard2-D model of powerhouse and switchyard in AutoCAD3-D model (scale 1:55) with topography and details like
transformer, oil circuit breaker, isolator etc of switchyard and powerhouse.
BENEFITSWe learned the measuring techniques.Able to develop teamwork spirit and communication
skills.Learn the technique to make a 3-D modelKnowledge of proper execution and presentationKnowledge about some of the equipments inside
powerhouse and switchyard.
CONCLUSION:
We came to know about the team work. We prepared 2-dimensional model(Top view) of our project site. We got the theoretical and practical knowledge from this project.
Thank You!