Transcript
Page 1: Sundaram Fasteners Review 1

ID Task Name Duration Start Finish Predecessors

1 33 KV dedicated supply for M/s. Sundaram FastenersLimited, Hosur from 230 KV TNEB substation

108 days Fri 11/2/12 Sat 3/30/13

2 33 KV Line and Bay extension works 101.63 days Fri 11/2/12 Thu 3/21/133 Receipt of PO 1 day Fri 11/2/12 Fri 11/2/124 Receipt of advance amount 1 day Fri 11/16/12 Fri 11/16/12 35 submission of application to TNEB 1 day Sat 11/10/12 Sat 11/10/12 36 Registration of application by TNEB 10 days Sat 11/10/12 Sat 11/24/12 57 conducting route survey and concluding on the BOM 5 days Sat 11/24/12 Sat 12/1/12 68 Receipt of EMD advice 15 days Sat 12/1/12 Sat 12/22/12 79 Payment of EMD amount to TNEB 2 days Sat 12/22/12 Wed 12/26/12 810 Ordering of materials 5 days Wed 12/26/12 Tue 1/1/13 911 Receipt of Developmental charges 15 days Wed 1/2/13 Tue 1/22/13 1012 Payment of developmental charges 3 days Tue 1/22/13 Fri 1/25/13 1113 Executing agreement with TNEB 2 days Fri 1/25/13 Tue 1/29/13 1214 Receipt of materials 20 days Tue 1/29/13 Sat 2/23/13 1315 Foundation for Poles 5 days Tue 2/26/13 Sat 3/2/13 1416 Erection of poles with cross arms 5 days Sat 3/2/13 Sat 3/9/13 1517 Stringing of line 5 days Sat 3/9/13 Sat 3/16/13 1618 Testing 3 days Sat 3/16/13 Thu 3/21/13 1719 33 KV works in substation 97 days Sat 11/3/12 Sat 3/16/1320 Ordering of major materials like Transformer

and VCB panels, Cables etc1 day Sat 11/17/12 Sat 11/17/12 3,4

21 Ordering of other materials 12 days Sat 11/3/12 Tue 11/20/12 322 Receipt of major materials 70 days Sat 11/17/12 Fri 2/22/13 2023 Receipt of other materials 20 days Tue 11/20/12 Tue 12/18/12 2124 Civil foundation for all equipments 15 days Tue 11/20/12 Tue 12/11/12 20,2125 Erection of Transformer 2 days Fri 2/22/13 Tue 2/26/13 22,23,2426 Erection of VCB panels 2 days Fri 2/22/13 Tue 2/26/13 22,23,2427 Erection of other equipment and cable laying 10 days Fri 2/22/13 Thu 3/7/13 22,23,2428 Earthing works 5 days Fri 3/8/13 Thu 3/14/13 25,26,2729 Cable termination works 3 days Fri 3/8/13 Tue 3/12/13 25,26,2730 Testing 2 days Thu 3/14/13 Sat 3/16/13 28,2931 CEIG works 107 days Sat 11/3/12 Sat 3/30/1332 Submission of drawings 20 days Sat 11/3/12 Fri 11/30/12 333 Getting drawing approval 30 days Fri 11/30/12 Thu 1/10/13 3234 Arranging for inspection 5 days Sat 3/16/13 Sat 3/23/13 30,3335 Getting safety certificate 5 days Sat 3/23/13 Sat 3/30/13 3436 TNEB energising supply 3 days Sat 3/23/13 Thu 3/28/13 34,1837 Handing over 2 days Thu 3/28/13 Sat 3/30/13 36,18

18%

20%100%

100%100%

70%100%

0%0%

100%0%

0%0%

0%0%

0%0%

0%25%

100%

100%0%

100%20%

0%0%

0%0%

0%0%

0%0%

0%0%

3/303/283/30

Oct Nov Dec Jan Feb Mar Apr4th Quarter 1st Quarter 2nd Quarter

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 1

Project: sundaram fastenersDate: Thu 11/29/12

Top Related