Team Structures and Project Performance in the Design-Build / Integrated
Project Delivery Marketplace
Mark E. Alpert, P.E., DBIA CH2M HILL
![Page 2: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/2.jpg)
Agenda• Introduction• Team Structure– Engineer-lead– Integrated design-build without self-performance– Integrated design-build with self-performance– Constructor-led– Other markets
• Owners’ Team Structure Preferences• Implications for Companies Going Forward
![Page 3: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/3.jpg)
Introduction: teams must have a design-build mindset
3
Engineer+ Constructor+ Design-Build Mindset= DESIGN-BUILD
Engineer+ Constructor
≠ DESIGN-BUILD
Engineer Constructor
![Page 4: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/4.jpg)
OWNERS’ DELIVERY PREFERENCES
![Page 5: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/5.jpg)
5
Typical Design-Build Team Structures• Engineer-lead
• Integrated design-build without self-performance
• Integrated design-build with self-performance
• Contractor-lead
![Page 6: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/6.jpg)
6
Engineer-Lead
• Will require clear division of responsibility between engineer and contractor
• Technical complexity– New/unproven/cutting edge technology
• Stringent project requirements– Increased effluent quality, consent decree mandate
• Unique commercial requirements• Owner preference of approach in team
structure
David L. Tippin Water Treatment Facility, Tampa. FL2002 DBIA Water Systems Quality Award
![Page 7: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/7.jpg)
Contractor-led
• Will require clear division of responsibility between contractor and engineer
• Normal structure for transportation market• Project risk is lower than a complex processing facility• Greater site constraints/challenges• Past experience with project owner• Larger project bonding requirements?• Legislation mandating self-performanceSouthern Delivery System Water Treatment Plant and
Finished Water Pump StationColorado Springs, Colorado
![Page 8: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/8.jpg)
• Single firm with full project responsibility• May or may not be schedule-driven• Owner wants input into subcontractor/vendor
selection• Greater involvement from local market • Legislation may not allow self-performance• Simple team structure with single point of
accountability• Must meet security for performance requirements
Integrated design-build without self-performance
Bonita Springs East Water Reclamation Facility, Bonita Springs, FL. 2008 DBIA Excellence Award for Projects over $15 Million
![Page 9: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/9.jpg)
• Technical and procurement expertise required• Local or state legislation or policy mandates self-
performance• Self-performance potentially cheaper than
subcontracted work• Must be able to manage all project risks
successfully • Project cost is critical• Must meet security for performance requirements
Integrated design-build with self-performance
Spokane County Regional Water Reclamation Facility, Spokane, WA2012 DBIA National Water/Wastewater Award
![Page 10: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/10.jpg)
Implications for Practioners
• Decide what structure fits best for your firm
• Identify personnel who can be effective with selected structure and project requirements
• Define what’s a “good deal” for your firm and how much are you willing to invest to win
• Define what risk is acceptable to your firm
• Inform insurance companies and banks of different business approach
• What additional business infrastructure is needed to be successful
10
Planning Market Deliver
![Page 11: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/11.jpg)
Get Smart on What Clients Expect
• Performance guarantees• Cost of work• Financial risk and margin
expectations
• Transparency in pricing• Design for design-build• Project management –
add the right talent
11
Planning Market Deliver
![Page 12: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/12.jpg)
Deliver Work and Refine from Lessons Learned
• Choose experienced Design-Build Manager to lead firm’s team
• Commit core experienced resources to projects
• Establish pricing criteria that is market based and meets firm’s business goals
• Standardized systems and tools to control, cost, scope, and schedule
• Accountability will be key in performance
12
Planning Market Deliver
![Page 13: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/13.jpg)
Significant Opportunities for Design-Build Delivery
![Page 14: Team Structures and Project Performance in the Design-Build Marketplace](https://reader036.vdocuments.net/reader036/viewer/2022062708/558975aad8b42a896d8b4609/html5/thumbnails/14.jpg)
Tailor your business to the market and mandated delivery structures that match
clients and opportunities. The future is bright for those firms that adapt
to the changing marketplace.