- The Premier Supplier of BWT Expertise -
BWM Summit Athens - June, 2016
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Agenda
• OceanSaver USCG Type Approval Progress
• OceanSaver Technology
• Operational Challenges
• Pre vs Post USCG Approval - Impact on the OceanSaverIMO Type approved BWTS – General Impacts
• References – Owners, Vessels and BWTS capacites
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
About OceanSaver AS -
• Norwegian company founded 2003
• Branch offices-Shanghai & Pusan
• IMO Type Approval by DNV-GL, ABS
• EX approval in principal for Tankers
• Safe Gas Handling H2 (DNV-GL approved)
• 12 months corrosion testing by DNV-GL; according to IMO and NACE
• Lloyds Register ISO 9001:2008
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
USCG Final Type Approval Testing (Landbased & Ship-
board) Successfully Concluded
Contracted DNV-GL as IL – LOI submitted December 2014
Land-based testing at DHI, Denmark
All tests successfully PASSED, November 2015
Ship-board tests – BC 2x2000m3/hr BWTS
All tests successfully PASSED, May 2016
Aim to submit application - June 2016
Expected USCG Type Approval - Q3,2016
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Agenda
• OceanSaver USCG Type Approval Progress
• OceanSaver Technology
• Operational Challenges
• Pre vs Post USCG Approval - Impact on the OceanSaver IMO Type approved BWTS – General Impacts
• References – Owners, Vessels and BWTS capacites
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
OceanSaver Mark II BWTS
Filtration
Disinfection
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
C2E Unit with
heater
C2E Feed filter
C2E
Feed
pump
A.P Tank
Sea
Chest
Ballast
pump
Main filter
Disinfectan
t
H2 Exhaust fan
TRO
sensor
System arrangement
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
C2E Unit with
heater
C2E Feed filter
C2E
Feed
pump
A.P Tank
Sea
Chest
Ballast
pump
Main filter
Disinfectan
t
TRO-N
Stand-by
unit
H2 Exhaust fan
TRO
sensor
System arrangement
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
De-ballasting -
Reduced OPEX
No treatment
Gravity discharge
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Filter Technology -
• 40 micron screen filter with up to 97 % efficiency
• Automatic self-cleaning
• Filter capacity 50 – 3.500 m3/h
• EX- version for pump room installation
• Horizontal or vertical execution
• Well proven technology developed for BWTS application
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
C2E Disinfectant unit -
In-house design and assembly
rectifiers
Membrane cell & H2
management systemControl system
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Principle layout Tanker with pump room
H2 exhaust fan
C2E Disinfectant
unit with heater and
DNV approved
H2 management.
C2E feed water
Disinfectant from C2E
Aft peak tank filter
Ballast water
main filter
TRO
neutra-
lization
unit
TRO sensor
C2E feed water filter
G/S pump
C2E
feed
pump
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Principle layout Tanker with submerged ballast pump
H2 exhaust
fan
C2E Disinfectant
unit with heater and
DNV approved
H2 management.
Disinfectant from C2E
Weather protection house
In engine room: TRO sensor
TRO neutra-
lization unit
Ballast water
main filter
- C2E feed pump
- C2E feed water filter
- Aft peak feed filter
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other personConfidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Principle layout Bulk-carrier
H2 exhaust fan
C2E Disinfectant
unit with heater and
DNV approved
H2 management.
C2E feed water
Disinfectant from C2E
C2E feed water filter
Ballast water
main filter
TRO neutra-
lization unit
TRO sensor
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Agenda
• OceanSaver USCG Type Approval Progress
• OceanSaver Technology
• Operational Challenges
• Pre vs Post USCG Approval - Impact on the OceanSaver IMO Type approved BWTS – General Impacts
• References – Owners, Vessels and BWTS capacites
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Operational Challenges
• Lack of crew training – OceanSaver training program
• System robustness vs Alarm philosophy
New alarm limits and delays decided based on
compliance, safety and component specifications
Reduction of alarms causing system shutdowns
• Software updates
Access to signals from the disinfectant unit provides
the system with more information on the status of
the operation
• Spares onboard
• Follow BWTS preservation and maintenance procedures
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Operational Challenges
• Follow OS BWTS design requirements during installation
• Cause & Effect Analysis (FMECA), Hazop, ECR and NCR processes
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Agenda
• OceanSaver USCG Type Approval Progress
• OceanSaver Technology
• Operational Challenges
• Pre vs Post USCG Approval - Impact on the OceanSaver IMO Type approved BWTS –General Impacts
• References – Owners, Vessels and BWTS capacites
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Pre vs Post USCG Approval
- Impact on the OceanSaver system
• OceanSaver MK II IMO standard approved system has
been subject to USCG Type Approval assessment including;
General evaluation against the USCG Rules.
15 land-based tests covering three salinities.
9 land-based tests including an alternative filter .
5 shipboard tests
Component testing including all essential electric
components.
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Pre vs Post USCG Approval
- Impact on the OceanSaver system
• OceanSaver MK II combined USCG and IMO - Impacts of USCG assessments to the system:
• Revision of automation system:
• Dosage levels and thus energy consumption remain unchanged for operations in marine and brackish water. Dosage starting point revised.
• Approved system will include approval for operations in fresh water (previously not a part of the IMO standard). Thus:
Dosage sequence for operations in fresh water is established.
Neutralisation procedure updated to encounter for fresh water operations.
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Pre vs Post USCG Approval
- Impact on the OceanSaver system
General revisions:
• Components/Environmental:
• Minor changes to some components following
component/ environmental testing.
Vibration dampening of certain components.
Improved mountings of some components inside
cabinets.
Improvements to some sensor units mounting
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Pre vs Post USCG Approval
- General impacts
• Manuals:
• OceanSaver have revised all manuals to comply with the
sequence of content referred to in the USCG Rules. The
content is updated according to changes.
• Training manuals have been improved following
experiences from shipboard testing.
• A general observation:
The BWMS does not receive sufficient attention
when in use.
Operator follow conventional procedure even
though the system refer to an exact procedure.
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Pre vs Post USCG Approval
- General impacts
• USCG vs. VGP (2013):
• OceanSaver complies with relevant requirements also
with regards to VGP
• Vessels using an approved (IMO or USCG) BWMS is
subject to “self monirtoring” as follows:
Year 1 after installation – samples should be
taken, analysed and reported twice over the year.
Following year 1 – samples should be taken,
analysed and included in the annual report.
• The VGP and the USCG Rules refer to the same
discharge standard. The VGP does not require any
system-specific approval.
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Agenda
• OceanSaver USCG Type Approval Progress
• OceanSaver Technology
• Operational Challenges
• Pre vs Post USCG Approval - Impact on the OceanSaver IMO Type approved BWTS – General Impacts
• References – Owners, Vessels and BWTS capacites
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
References
Vessel Type BWTS Capacity System OrdersVLCC/Suezmax 2 x 3000 / 2500 m3/h MK I 21 Korea (HHI & DSME) & China (DSIC & SWS)
Suezmax 2 x 2500 m3/h MK I 2 Korea (HHI)
PCTC 2 x 600 m3/h MK I 2 Retrofit (China)
VLCC 2 x 3000 m3/h MK II 7 Korea (STX & DSME) & China (RSHI)
VLCC 1 x 3500 m3/h MK II 2 Japan (JMU)
Suezmax 2 x 2500 m3/h MK II 7 Korea (SHI & BSHI)
Aframax LR 1 & 2 2 x 2000 m3/h MK II 10 China ( COSCO & GSI)
Aframax LR 1 & 2 2 x 1800 m3/h MK II 4 Korea (Daehan)
Aframax LR 1 & 2 2 x 1500 m3/h MK II 2 Korea (HSHI)
Aframax LR 1 & 2 2 x 1000 m3/h MK II 6 Korea (STX)
Product / Chemical 2 x 1100 / 1000 m3/h MK II 4 Japan (Onomichi) & Korea (STX)
Product / Chemical 2 x 750 / 800 m3/h MK II 10 Korea (HMD & STX)
Bulk Carrier 2 x 3000 / 2500 m3/h MK II 23 China & Korea
Bulk Carrier 2 x 2000 m3/h MK II 1 Retrofit (China)
Bulk Carrier 2 x 1500 m3/h MK II 15 Japan (Oshima) & China (Hudong)
Bulk Carrier 2 x 1200 m3/h MK II 1 China (JEHI)
Bulk Carrier 2 x 800 m3/h MK II 8 Japan (Oshima) & Korea (SPP)
Bulk Carrier 1 x 800/ 830 / 1200 m3/h MK II 9 Japan (Oshima)
LNG 2 x 3000 m3/h MK II 2 Korea (DSME)
LNG 2 x 3200 / 3000 m3/h MK II 6 Retrofit (Singapore, Spain & Qatar)
LNG 2 x 3100 m3/h MK II 11 Korea (DSME)
LNG 2 x 2700 / 2500 m3/h MK II 6 China (Hudong) & Korea (HHI)
LPG 2 x 800 m3/h MK II
18 China (Shanghai) & Korea (HHI & HSHI) + 1
Retrofit (Singapore)
Total contracts 179
Commissioned
To be commissioned
110
69
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Owners Total no. of vesselsFrontline 2012 Ltd 28
BW Gas LPG Limited 18
U-Ming Marine Transport 16
NITC 12BP Shipping 11
Foremost Group 9
Gearbulk 8Teekay Shipping Ltd 8
Consolidated Marine Management 7
Oman Shipping 7
Ciner Shipping Ind. and Trading Inc 6
Transpetrol 4
Global Energy Maritime 4Pan Union 4
Taiwan Navigation 4
Capital Ship Management 4
ADM Harvest Shipping 3
Almi Tankers S.A 2
Chevron Shipping Co., LLC 2
Foremost Group 2
Berge Bulk 2
D&K 2
Knightbridge 2Samos Steamship Co. 2
Höegh Autoliners 2
Gungen Maritime & Trading 2
Shipping Corporation of India 1NYK LNG Shipmanagement / RasGas 1
Ta-Tong Marine Co., Ltd 1
CSL Group 1
Great Eastern Shipping Co., Ltd 1
Valles Steamship (Canada) Ltd. 1GDF Suez / ENGIE 1
Cargill 1
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Worldwide sales & service network
Japan
China
Singapore
India
Middle East
Greece
Netherlands
Brazil
Germany
TurkeyKorea
Italy
Norway
Canada & USA
Confidential – This document is for the use of the intended recipient only and should not be copied or distributed to any other person
Thank you for your attention!
www.oceansaver.com
- The Premier Supplier of BWT Expertise -