Download - Today’s (12.7) Report LIU Qian. East EC is ready, we are going to install the EC TOF next Monday
Transcript
The upper distribution boxThe main bundle
New position,Direction: west to east(safer, and easier to connect with fibers)
Old position,Direction: North to south
The extra length of fibers areover-under coiled.
Conclusion
• We only finished the 12 bundles installation. (since the people who helped me install the fibers are employed temporarily, for now only one IHEP employee and I are installing the bundles. But that’s OK, since we don’t want to push it in a hurry.)
• The bottom box has been installed. We’ll try to finish the rest bundles in this weekend.
• Next Monday we’ll begin to install the EC TOF of east side.