RELACION DE PRODUCCION AVANCE DE LABORES DE DESARROLLO HORIZONTALES Y VERTICALES PARA LA UNIDAD MINERA "TOMA LA MANO"MES : ABRIL
PARA LABORES DE DESARROLLO HORIZONTALES (GALERIA DE 6'*7')SECCION 3.9 m2
ALTURA DE TAJO(H) 17 mLONGITUD DE TAJO 60 m
P.E 3.2 TM/m3ANCHO MINIMO MINABLE 1 m
VOLUMEN 1,020 m3TONELAJE 3,264 TM
NUMERO DE GUARDIAS 2 guardias NUMERO DE DIAS TRABAJADOS 27 diasPRODUCCION MENSUAL 1800 TM/MES
PRODUCCION DIARIA 67 TM/diaPRODRUCCION/AVANCE = 54.40
CALCULO DEL AVANCE MENSUAL= 33.09
PARA LABORES DE DESARROLLO VERTICLAES(CHIMENEA DE 4'*4')SECCION 1.48 m2
ALTURA DE TAJO(H) 12 mLONGITUD DE TAJO 60 m
P.E 3.2 TM/m3ANCHO MINIMO MINABLE 0.9 m
VOLUMEN 648 m3TONELAJE 2074 TM
NUMERO DE GUARDIAS 2 guardias NUMERO DE DIAS TRABAJADOS 27 dias
PRODUCCION MENSUAL 1800 TM/MESPRODUCCION DIARIA 67 TM/dia
PRODUCCION/AVANCE = 172.8CALCULO DEL AVANCE MENSUAL= 10.41666667
PARA LABORES DE DESARROLLO VERTICLAES(CHIMENEA DE DOBLE COMPARTIMIENTO de 4'*4' )SECCION 2.22 m2
ALTURA DE TAJO(H) 8 mLONGITUD DE TAJO 40 m
P.E 3.2 TM/m3ANCHO MINIMO MINABLE 1 m
VOLUMEN 320 m3TONELAJE 1024 TM
NUMERO DE GUARDIAS 2 guardias NUMERO DE DIAS TRABAJADOS 27 dias
PRODUCCION MENSUAL 1800 TM/MESPRODUCCION DIARIA 67 TM/dia
![Page 4: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/4.jpg)
PRODUCCION/AVANCE = 128 TM/mlCALCULO DEL AVANCE MENSUAL= 14 ml/mes
TAJEOSECCION 30 m2
ALTURA DE TAJO(H) 30 mLONGITUD DE TAJO 60 m
P.E 3.2 TM/m3ANCHO MINIMO MINABLE 1 m
VOLUMEN 1800 m3TONELAJE 5760 TM
NUMERO DE GUARDIAS 2 guardias NUMERO DE DIAS TRABAJADOS 27 dias
PRODUCCION MENSUAL 1800 TM/MESPRODUCCION DIARIA 67 TM/dia
PRODRUCCION/AVANCE = 96CALCULO DEL AVANCE MENSUAL= 18.75
![Page 5: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/5.jpg)
RELACION DE PRODUCCION AVANCE DE LABORES DE DESARROLLO HORIZONTALES Y VERTICALES PARA LA UNIDAD MINERA "TOMA LA MANO"MES : ABRIL
PARA LABORES DE DESARROLLO HORIZONTALES (GALERIA DE 6'*7')
TM/mlml/mes
PARA LABORES DE DESARROLLO VERTICLAES(CHIMENEA DE 4'*4')
TM/mlml/mes
PARA LABORES DE DESARROLLO VERTICLAES(CHIMENEA DE DOBLE COMPARTIMIENTO de 4'*4' )
![Page 6: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/6.jpg)
P=E=K=
NºT=
TM/mlml/mes
![Page 7: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/7.jpg)
RELACION DE PRODUCCION AVANCE DE LABORES DE DESARROLLO HORIZONTALES Y VERTICALES PARA LA UNIDAD MINERA "TOMA LA MANO"MES : ABRIL
P= 7.90 E= 0.45K= 2NºT= 25 TALADROS
P= 5E= 0.45K= 2NºT= 14 TALADROS
P= 6E= 0.45K= 2
NºT= 18 TALADROS
CALCULO DEL NUMERO DE TALADROS
CALCULO DEL NUMERO DE TALADROS
CALCULO DEL NUMERO DE TALADROS
![Page 8: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/8.jpg)
21.90890230.45
2108.6864496 TALADROS
CALCULO DEL NUMERO DE TALADROS
![Page 9: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/9.jpg)
RELACION DE PRODUCCION AVANCE DE LABORES DE DESARROLLO HORIZONTALES Y VERTICALES PARA LA UNIDAD MINERA "TOMA LA MANO"MES : ABRIL
![Page 10: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/10.jpg)
![Page 11: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/11.jpg)
RELACION DE PRODUCCION AVANCE DE LABORES DE DESARROLLO HORIZONTALES Y VERTICALES PARA LA UNIDAD MINERA "TOMA LA MANO"MES : ABRIL
![Page 12: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/12.jpg)
![Page 13: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/13.jpg)
ELABORACION DEL PLANEAMIENTO POR CUADROS PROGRAMADOS DE LA CIA MINERA "TOMA LA MANO"
PARA LABORES DE DESARROLLO HORIZONTALES (GALERIAS)1. PERFORACION
PRODUCCION MENSUAL = 940.58 TM/MES P.E.= 3.2 TM/m3
3.78 m2LONGITUD DEL BARRENO = 6'
RENDIMIENTO DE LAS PERFORADORAS= 80% C/UDIAMETRO DE TALADRO= 34 mm
ESPACIAMIENTO = 0.4 mSEPARACION = 0.4 m
GUARDIA= 8 hTIEMPO NOMINAL(Tn)= 8 h
TIEMPO EFECTIVO(Te)= Tn*Eff. Mec. Eff.Op= 5.12 hDatos tomados en el frente de trabajo
Desatado de rocas flojas = 25 minIinstalacion de la maquina perforadora = 20 min
Desinstalacion de la maquina perforadora=Carguio y Chispeo =
LONGITUD DE TALADRO= 6'*0,80 1.44 mDETERMINACION DEL TIEMPO DE PERFORACION(Tp)=
velocida de penetracion = 0.305 m/minciclo operativo
Acoplamineto de la barra = 0.5 minextraccion de la barra = 0.3 min
Desacomplamiento de la barra = 0.5 minMovimiento del equipo = 2 minUbicación para perforar = 1 min
ciclo total= 4.3 min
TIEMPO DE Penetracion /TALADRO= 4.72 minTIMPO DE PERFORACION POR TALADRO = 9.02 min
VELOCIDAD DE PERFORACION POR TALADRO= 0.16 m/minCALCULO DE LA PRODUCCION POR TALADRO:Volumen movido por taladro = 0.23 m3
produccion nominal por taladro= 0.74 TM/talVELOCIDAD DE PRODUCCION POR TALADRO= 0.08 TM/min
DETERMINACION DEL TIEMPO EFECTIVO POR GUARDIAHORAS NOMINALES POR GUARDIA = 8 h
RENDIMIENTO DEL EQUIPO = 0.8MANTENIMIENTO PROMEDIO= 0.5 h
LABORES DE DESARROLLO DE SECCION 6'X7'=
![Page 14: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/14.jpg)
MOVILIZACION PROMEDIO POR DISPARO = 20 minTE/Gd= 5.57 hrs 334 min/dg
calculo de la produccion por guardiaP/gd= 27.30 TM/gd
calculo de la produccion nominal por dia considerando que se trabajan en dos guardias por dia tendremos
PN/dia= 54.59 calculo de la produccion real
PR/Dia 43.67 TMDprograma de perforacion
Numero de guardias= 2 guardias Longitud de taladro= 1.44 mavance mensual = 27 m/mesavance por dia = 2.88 m/dia
PP= 9.38 dias/mes 9.00 dias/mes
2. ANALISIS DE CONCIDERACIONES TECNICAS PARA VOLADURACALCULO DEL NUEMRO DE TALADROS TIEMPO DE CARGUIO POR TALADRO=
NºT= 1,276.00 Taladros/mes CALCULO DE PROGRAMA DE CARGUIO
tiempo de carguio de los taladros TCT= 4,466.00 min/mes 74.43 h/mes
conciderando 8 horas efctivas pr guardia TCT= 9.30 guardias/mesPV= 9.00 dias/mes
3.ANALISIS DE LAS CONCIDERACIONES TECNICAS-PROGRAMA DE LIMPIEZA capaciadad del carro = 1.5 TON
CONSIDERACIONES TECNICAS DE OPERACIÓN velocidad promedio de acarreo= 3 km/hrvelocidad promedio de retorno= 5 km/hrdistancia promedio de operación= 82 m
ciclo operativo del equipo de acarreotiempo de chuteo(incluyendo apertura y cierre y ubicación de carros =maniobra para descarga =
descarga del mineral al ore pass =total =
analisis programaticotiempo de acarreo de viaje= 2.46 min
tiempo tota de viaje = 11.46 min/viajeNumero de viajes por hora = 5.24 viajes/hora 5.00
![Page 15: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/15.jpg)
tiempo muerto= 1.8 hr/guardiahoras de trabajo por guardia= 8 hr/guardiahora real de trabajo del carro= 6.2 hr/guardia
horas real de trabajo del carro por dia= 12.4 hr/diadescarga del carro por dia= 93.00 TM/dia
programa de limpieza= 10 dias/mes
![Page 16: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/16.jpg)
ELABORACION DEL PLANEAMIENTO POR CUADROS PROGRAMADOS DE LA CIA MINERA "TOMA LA MANO"
P.E= 3.2 TM/m3SECCION= 6'*7' 3.78 m2VOLUMEN= 5.44 m3
LONGITUD DE TALADRO = 6'*0,8 1.44 mTONELAJE= 17.42 TM
DIAS TRABAJADOS = 27NUMERO DE GUARDIAS = 2
PRODUCCION MENSUAL 940.58 TM/Mes
15 mim40 min
![Page 17: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/17.jpg)
0.33 h
TIEMPO DE CARGUIO POR TALADRO= 3.5 min/TAL
7 min1 min1 min9 min
viajes/hora
![Page 18: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/18.jpg)
![Page 19: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/19.jpg)
![Page 20: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/20.jpg)
![Page 21: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/21.jpg)
![Page 22: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/22.jpg)
ELABORACION DEL PLANEAMIENTO POR CUADROS PROGRAMADOS DE LA CIA MINERA "TOMA LA MANO"
PARA LABORES DE DESARROLLO Y PREPARACION VERTICALES(CHIMENEA )
1. PERFORACION PRODUCCION MENSUAL = 292.51 TM/Mes
P.E= 3.2 TM/m3
LONGITUD DEL BARRENO = 5'RENDIMIENTO DE LAS PERFORADORAS= 80% C/UDIAMETRO DE TALADRO= 34 mm 1.339pulESPACIAMIENTO = 0.4 mSEPARACION = 0.4 m
* CALCULO DE TIEMPO EFECTIVO / GUARDIAGUARDIA= 8 h
TIEMPO NOMINAL(Tn)= 8 hTIEMPO EFECTIVO(Te)= Tn*Eff. Mec. Eff.Op= 5.12 h
Datos tomados en el frente de trabajoDesatado de rocas flojas = 45 mininstalacion de la maquina perforadora = 28 minDesinstalacion de la maquina perforadora= 18 min Carguio y Chispeo = 33 minLONGITUD DE TALADRO= 1.22 m
*DETERMINACION DEL TIEMPO DE PERFORACION(Tp)=
velocida de penetracion = 0.305 m/min DATO
ciclo operativo Acoplamineto de la barra = 0.6 minextraccion de la barra = 0.4 minDesacomplamiento de la barra = 0.6 minMovimiento del equipo = 1 minUbicación para perforar = 1 min
ciclo total= 3.6 min
1.22/0.305 4 min*TIEMPO DE PERFORACION POR TALADRO = 7.6 min*VELOCIDAD DE PERFORACION POR TALADRO= 0.16 m/min
*CALCULO DE LA PRODUCCION POR TALADRO:
LABORES DE DESARROLLO DE SECCION 4'*4'
5'*0,80
* TIEMPO DE PENETRACION /TALADRO= TPEN
TPEN=
![Page 23: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/23.jpg)
Volumen movido por taladro = 0.20 m3produccion nominal por taladro= 0.62 TM
*VELOCIDAD DE PRODUCCION POR TALADRO= 0.08 TM/min
*DETERMINACION DEL TIEMPO EFECTIVO POR GUARDIA
HORAS NOMINALES POR GUARDIA = 8 hrsRENDIMIENTO DEL EQUIPO = 80%MANTENIMIENTO PROMEDIO= 0.5 hrsMOVILIZACION PROMEDIO POR DISPARO 20 min 0.33 TE/gd. 5.57 hrs 334 min.
*CALCULO DE LA PRODUCCION / GUARDIAP/gd= 27.47 TM/gd*CALCULO DE PRODUCCION NOMINAL POR DIAconsiderando que se trabajan en 2 guardias por dia tendremos PN/dia= 54.94 TMD*CALCULO DE PRODUCCION REAL PRODUCCION POR TALADRO AL 80%PR/Dia 43.95 TMD
*PROGRAMA DE PERFORACION
PP= 7 Dias/Mes
2. ANALISIS DE CONCIDERACIONES TECNICAS PARA VOLADURA
NºT= 468.28 Taladros/mes
*CALCULO DE PROGRAMA DE CARGTIEMPO DE CARGUIO DE LOS TALADROS
TCT= 5,619.38 min/mes 93.66 h/mesTIEMPO EFECTIVO POR GUARDIA = 7 Hrs/Grd.*TIEMPO EFECTTIVO CARGUIO DE TALADROS (
TCT= 13.38 guardias/mesPV= (13.38 grd/mes)/(2 dias/ grd)
PV= 7 dias/mes
3.-ANALISESCDE LAS CONCIDERACIONES TECNICAS TECNICAS PROGRAMADAS DE LIMPIEZA
capaciadad del carro = 1.5 TON DATO*CONSIDERACIONES TECNICAS DE OPERACIÓN
292.51 TM/Mes/38.84TMD
*CALCULO DEL NUEMRO DE TALADROS
292.51 TM/Mes/0.62 TM/TAL.
![Page 24: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/24.jpg)
velocidad promedio de acarreo= 3 km/hrvelocidad promedio de retorno= 5 km/hrdistancia promedio de operación= 82 m*CICLO OPERATIVO DEL EQUIPO DE ACARREOtiempo de chuteo(incluyendo apertura y cierre y ubicación de carros maniobra para descarga =descarga del mineral al ore pass =
Total =*ANALISIS PROGRAMATItiempo de acarreo de viaje= 2.46 mintiempo tota de viaje = 23.26 min/viajeNumero de viajes por hora = 2.58 viajes/hora tiempo muerto= 5.4 hr/guardia 3.00 horas de trabajo por guardia= 8 hr/guardiahora real de trabajo del carro= 2.6 hr/guardiahoras real de trabajo del carro por dia= 5.2 hr/diadescarga del carro por dia= 23.40 TM/dia
programa de limpieza= 13 dias/mes
![Page 25: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/25.jpg)
ELABORACION DEL PLANEAMIENTO POR CUADROS PROGRAMADOS DE LA CIA MINERA "TOMA LA MANO"
PARA LABORES DE DESARROLLO Y PREPARACION VERTICALES(CHIMENEA )
Datos Generales Para La PerforacionP.E=
SECCION=VOLUMEN=
LONGITUD DE TALADRO =TONELAJE= 5.4168
DIAS TRABAJADOS =NUMERO DE GUARDIAS =
PRODUCCION MENSUAL
BURDEN Longitud Espaciamiento0.4 1.22 0.4
4'*4'
![Page 26: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/26.jpg)
DESIDAD DE MINERAL3.2
hrs
PRODUCCION POR TALADRO AL 80% Dato
TIEMPO DE CARGUIO POR TALADRO= 12 min/ Tal.
3.-ANALISESCDE LAS CONCIDERACIONES TECNICAS TECNICAS PROGRAMADAS DE LIMPIEZA
TM/m3
![Page 27: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/27.jpg)
16 min2.8 min
2 min
20.8 min
viajes/hora
![Page 28: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/28.jpg)
ELABORACION DEL PLANEAMIENTO POR CUADROS PROGRAMADOS DE LA CIA MINERA "TOMA LA MANO"
Datos Generales Para La PerforacionP.E= 3 TM/m3
1.48 m2 1.81 m3
1.22 mTM
272
PRODUCCION MENSUAL 292.51 TM/Mes
4'
![Page 29: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/29.jpg)
![Page 30: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/30.jpg)
![Page 31: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/31.jpg)
ELABORACION DEL PLANEAMIENTO POR CUADROS PROGRAMADOS DE LA CIA MINERA "TOMA LA MANO"
PARA LABORES DE DESARROLLO CHIMENEAS DE DOBLE COMPARTIMIENTO1. PERFORACION
PRODUCCION MENSUAL = 784.24 TM/MES P.E.= 3 TM/m3
3.72 m2LONGITUD DEL BARRENO = 5'
RENDIMIENTO DE LAS PERFORADORAS= 80% C/UDIAMETRO DE TALADRO= 34 mm
ESPACIAMIENTO = 0.6 mSEPARACION = 0.6 m
GUARDIA= 8 hTIEMPO NOMINAL(Tn)= 8 h
TIEMPO EFECTIVO(Te)= Tn*Eff. Mec. Eff.Op= 5.12 hDatos tomados en el frente de trabajo
Desatado de rocas flojas = 30 minIinstalacion de la maquina perforadora = 25 min
Desinstalacion de la maquina perforadora=Carguio y Chispeo =
LONGITUD DE TALADRO= 5'*0,80 1.22 mDETERMINACION DEL TIEMPO DE PERFORACION(Tp)=
velocida de penetracion = 0.305 m/minciclo operativo
Acoplamineto de la barra = 0.5 minextraccion de la barra = 0.3 min
Desacomplamiento de la barra = 0.5 minMovimiento del equipo = 2 minUbicación para perforar = 1 min
ciclo total= 4.3 min
TIEMPO DE Penetracion /TALADRO= 4.00 minTIMPO DE PERFORACION POR TALADRO = 8.30 min
VELOCIDAD DE PERFORACION POR TALADRO= 0.15 m/minCALCULO DE LA PRODUCCION POR TALADRO:Volumen movido por taladro = 0.44 m3
produccion nominal por taladro= 1.32 TM/talVELOCIDAD DE PRODUCCION POR TALADRO= 0.16 TM/min
DETERMINACION DEL TIEMPO EFECTIVO POR GUARDIAHORAS NOMINALES POR GUARDIA = 8 h
RENDIMIENTO DEL EQUIPO = 0.8MANTENIMIENTO PROMEDIO= 0.5 h
MOVILIZACION PROMEDIO POR DISPARO = 20 min
LABORES DE DESARROLLO DE SECCION 5'X8'=
![Page 32: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/32.jpg)
TE/Gd= 5.57 hrs 334 min/dg
calculo de la produccion por guardiaP/gd= 53.02 TM/gd
calculo de la produccion nominal por dia considerando que se trabajan en dos guardias por dia tendremos
PN/dia= 106.04 calculo de la produccion real
PR/Dia 84.83 TMDprograma de perforacion
Numero de guardias= 2 guardias Longitud de taladro= 0.6 mavance mensual = 8 m/mesavance por dia = 1.2 m/dia
PP= 6.67 dias/mes 7.00 dias/mes
2. ANALISIS DE CONCIDERACIONES TECNICAS PARA VOLADURACALCULO DEL NUEMRO DE TALADROS TIEMPO DE CARGUIO POR TALADRO=
NºT= 595.00 Taladros/mes CALCULO DE PROGRAMA DE CARGUIO
tiempo de carguio de los taladros TCT= 3,570.00 min/mes 59.50 h/mes
conciderando 8 horas efctivas pr guardia TCT= 7.44 guardias/mesPV= 7.00 dias/mes
3.ANALISIS DE LAS CONCIDERACIONES TECNICAS-PROGRAMA DE LIMPIEZA capaciadad del carro = 1.5 TON
CONSIDERACIONES TECNICAS DE OPERACIÓN velocidad promedio de acarreo= 3 km/hrvelocidad promedio de retorno= 5 km/hrdistancia promedio de operación= 82 m
ciclo operativo del equipo de acarreotiempo de chuteo(incluyendo apertura y cierre y ubicación de carros =maniobra para descarga =
descarga del mineral al ore pass =total =
analis programaticotiempo de acarreo de viaje= 2.46 min
tiempo tota de viaje = 15.46 min/viajeNumero de viajes por hora = 3.88 viajes/hora 4.00
tiempo muerto= 3 hr/guardia
![Page 33: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/33.jpg)
horas de trabajo por guardia= 8 hr/guardiahora real de trabajo del carro= 5 hr/guardia
horas real de trabajo del carro por dia= 10.0 hr/diadescarga del carro por dia= 60.00 TM/dia
programa de limpieza= 13 dias/mes
![Page 34: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/34.jpg)
ELABORACION DEL PLANEAMIENTO POR CUADROS PROGRAMADOS DE LA CIA MINERA "TOMA LA MANO"
P.E= 3.2 TM/m3SECCION= 5'*8' 3.72 m2VOLUMEN= 4.54 m3
LONGITUD DE TALADRO = 5'*0,8 1.22 mTONELAJE= 14.52 TM
DIAS TRABAJADOS = 27NUMERO DE GUARDIAS = 2
PRODUCCION MENSUAL 784.24 TM/Mes
18 min40 min
0.33 h
![Page 35: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/35.jpg)
TIEMPO DE CARGUIO POR TALADRO= 6 min/TAL
11 min2.5 min
2 min13 min
viajes/hora
![Page 36: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/36.jpg)
![Page 37: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/37.jpg)
ELABORACION DEL PLANEAMIENTO POR CUADROS PROGRAMADOS DE LA CIA MINERA "TOMA LA MANO"
PARA LABORES DE DESARROLLO HORIZONTALES (TAJEO)1. PERFORACION
PRODUCCION MENSUAL = 3,732.48 TM/MES P.E.= 3.2 TM/m3
15 m2LONGITUD DEL BARRENO = 6'
RENDIMIENTO DE LAS PERFORADORAS= 80% C/UDIAMETRO DE TALADRO= 34 mm
ESPACIAMIENTO = 0.4 mSEPARACION = 0.4 m
GUARDIA= 8 hTIEMPO NOMINAL(Tn)= 8 h
TIEMPO EFECTIVO(Te)= Tn*Eff. Mec. Eff.Op= 5.12 hDatos tomados en el frente de trabajo
Desatado de rocas flojas = 30 minIinstalacion de la maquina perforadora = 25 min
Desinstalacion de la maquina perforadora= 18 minCarguio y Chispeo = 40 min
LONGITUD DE TALADRO= 6'*0,80 1.44 mDETERMINACION DEL TIEMPO DE PERFORACION(Tp)=
velocida de penetracion = 0.305 m/minciclo operativo
Acoplamineto de la barra = 0.5 minextraccion de la barra = 0.3 min
Desacomplamiento de la barra = 0.5 minMovimiento del equipo = 2 minUbicación para perforar = 1 min
ciclo total= 4.3 min
TIEMPO DE Penetracion /TALADRO= 4.72 min/taladroTIMPO DE PERFORACION POR TALADRO = 9.02 min
VELOCIDAD DE PERFORACION POR TALADRO= 0.16 m/minCALCULO DE LA PRODUCCION POR TALADRO:Volumen movido por taladro = 0.23 m3
produccion nominal por taladro= 0.74 TM/talVELOCIDAD DE PRODUCCION POR TALADRO= 0.08 TM/min
DETERMINACION DEL TIEMPO EFECTIVO POR GUARDIAHORAS NOMINALES POR GUARDIA = 8 h
RENDIMIENTO DEL EQUIPO = 0.8MANTENIMIENTO PROMEDIO= 0.5 hMOVILIZACION PROMEDIO POR DISPARO = 20 min
LABORES DE DESARROLLO DE SECCION 1X15=
![Page 38: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/38.jpg)
TE/Gd= 5.57 hrs 334 min/dg
calculo de la produccion por guardiaP/gd= 27.30 TM/gd
calculo de la produccion nominal por dia considerando que se trabajan en dos guardias por dia tendremos
PN/dia= 54.59 calculo de la produccion real
PR/Dia 43.67 TMDprograma de perforacion
Numero de guardias= 2 guardias Longitud de taladro= 1.44 mavance mensual = 24.39 m/mesavance por dia = 2.88 m/dia
PP= 8.47 dias/mes 8.00 dias/mes
2. ANALISIS DE CONCIDERACIONES TECNICAS PARA VOLADURACALCULO DEL NUEMRO DE TALADROS TIEMPO DE CARGUIO POR TALADRO=
NºT= 1,159.67 Taladros/mes CALCULO DE PROGRAMA DE CARGUIO
tiempo de carguio de los taladros TCT= 4,058.85 min/mes 67.65 h/mes
conciderando 8 horas efctivas pr guardia TCT= 8.46 guardias/mesPV= 8.00 dias/mes
3.ANALISIS DE LAS CONCIDERACIONES TECNICAS-PROGRAMA DE LIMPIEZA capaciadad del carro = 1.5 TON
CONSIDERACIONES TECNICAS DE OPERACIÓN velocidad promedio de acarreo= 3 km/hrvelocidad promedio de retorno= 5 km/hrdistancia promedio de operación= 50 m
ciclo operativo del equipo de acarreotiempo de chuteo(incluyendo apertura y cierre y ubicación de carros =
descarga del mineral al ore pass =total =
analis programaticotiempo de acarreo de viaje= 1.5 min
tiempo tota de viaje = 4 min/viajeNumero de viajes por hora = 15.00 viajes/hora 15.00
tiempo muerto= 1.8 hr/guardiahoras de trabajo por guardia= 8 hr/guardia
![Page 39: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/39.jpg)
hora real de trabajo del carro= 6.2 hr/guardiahoras real de trabajo del carro por dia= 12.4 hr/diadescarga del carro por dia= 279.00 TM/dia
programa de limpieza= 13 dias/mes
![Page 40: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/40.jpg)
ELABORACION DEL PLANEAMIENTO POR CUADROS PROGRAMADOS DE LA CIA MINERA "TOMA LA MANO"
P.E= 3.2 TM/m3SECCION= 1*15 15 m2VOLUMEN= 21.60 m3
LONGITUD DE TALADRO = 6'*0,8 1.44 mTONELAJE= 69.12 TM
DIAS TRABAJADOS = 27NUMERO DE GUARDIAS = 2
PRODUCCION MENSUAL 3,732.48 TM/Mes
0.33 h
![Page 41: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/41.jpg)
TIEMPO DE CARGUIO POR TALADRO= 3.5 min/TAL
1.5 min1 min
2.5 min
viajes/hora
![Page 42: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/42.jpg)
![Page 43: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/43.jpg)
![Page 44: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/44.jpg)
![Page 45: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/45.jpg)
![Page 46: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/46.jpg)
PLANIFICACION DE OPERACIONES POR CUADROS PROGRAMADOS PARA LA MINA TOMA LA MANO (JULIO 2011)
LABORCRONOGRAMA (DIAS)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15GALERIA P V L P V L P V L P V L PCHIMENEA P V L P V L L P V L L P VCHIMENEA (DC) P V L L P V L L P V L L PTAJEO P V P V L L L P V P V P V L
![Page 47: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/47.jpg)
PLANIFICACION DE OPERACIONES POR CUADROS PROGRAMADOS PARA LA MINA TOMA LA MANO (JULIO 2011)
CRONOGRAMA (DIAS)16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
V L P V L P V L P V L P V L LL L P V L L P V L L P V L LV L L P V L L P V L L P V LL L L L P V P V P V L L L L L
![Page 48: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/48.jpg)
![Page 49: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/49.jpg)
ELABORACION DE CUADROS ESTADISTICOS PARA GALERIASPRODUCION POR MES 940.58 TM/Mes
PLANIFICACION DEL PERSONAL POR GUARDIAPERFORACION
PERFORISTA 1AYUDANTE DE PER. 1
TOTAL DE PERSONAS 2Nº GUARDIAS/DIA 2
PP 9 Dias/mes
VOLADURASUPERVISOR DE VOLADURA 1
CARDOR ( CHISPERO) 1AYUDANTE 1
TRANSPORTADOR DE EXPLOSIVO 1TOTAL DE PERSONAS 4
PV 9 Dias/mes
LIMPIEZADESATADORES 2
PALEROS 2CARREROS 4
TOTAL DE PERSONAS 8PL 10 Dias/mes
PROCESOS PRODUCTIVOSNUMERO DE PERSONAS POR MES
PERFORACION
Nº DE PERSONAS / Mes 36 h - gd/mes
VOLADURANº DE PERSONAS / Mes 72 h - gd/mes
LIMPIEZANº DE PERSONAS / Mes 160 h - gd/mes
EFICIENCIA DE LA LABORE.L 3.51 ml/ hg EL=940.58/(36+72+160) ml/hg
EFICIENCIA DE PERFORACION
Nº DE TALADROS 25 taladrosLT 1.83 m Long. Mensual Perf.= 25 taladros*1.83 metros
![Page 50: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/50.jpg)
LONGITUD MENSUAL PERFORADO 45.75 mEp= 940.58 TMM/45.75 Metros
EFICIENCIA DE PERFORACION 20.56 TM / Mp
EFICIENCIA DEL EXPLOSIVO DENSIDAD DEL EXPLOSIVO 1.16ØEXPLOSIVO 0.766 PULGADASFACTOR DE CONVERSION 0.34
DENSIDAD DE CARGA POR TALADRO 0.23 lb/pie
LONGITUD EFECTIVA DE CARGAFACTOR DE CORRECCION 0.9
LEC=Lt*FACTOR DE CORRECIÓNLEC=1.83m*0.90
LEC= 1.65
CONSUMO DE EXPLOSIVO POR MESDATO: Fp=1.05 CEM=LEC*N°taladros*Dc*Fp
CEM = 4,822.90 lb / mes
FACTOR DE POTENCIA FP=CEM/940.58TMM
FP = 5.13 lb/TM 2.33
EFICIENCIA DE LOS EQUIPOS DE LIMPIEZA1. EQUIPO DE CARGUIO :
Nº DE UNIDADES DE CARGUIO 1HORAS DE TRABAJO POR MES HTM=h/g*g/dia*dias/mes*N° de unidades
HTM=8*2*10*1160 hrs/mes
2. EFICIENCIA DE CARGUIOEC = 940.58TMM / 160hrs/mes 5.88 ml/ h - maq.
![Page 51: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/51.jpg)
ELABORACION DE CUADROS ESTADISTICOS PARA GALERIAS
EL=940.58/(36+72+160) ml/hg
Long. Mensual Perf.= 25 taladros*1.83 metros
![Page 52: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/52.jpg)
CEM=LEC*N°taladros*Dc*Fp
Kg/TM
HTM=h/g*g/dia*dias/mes*N° de unidades
![Page 53: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/53.jpg)
ELABORACION DE CUADROS ESTADISTICOS PARA CHIMENEAS
1.-PRODUCION POR MES 292.51 TM/Mes Nº GUARDIAS/DIA2.-PLANIFICACION DEL PERSONAL POR GUARDIA
PERFORACIONPERFORISTA 1
AYUDANTE DE PER. 1TOTAL DE PERSONAS 2 pers.
PP 7 Dias/mes
3.-PROCESOS PRODUCTIVOS
NUMERO DE PERSONAS POR MES
PERFORACION
Nº DE PERSONAS / Mes 28 Personas/mes
4.-EFICIENCIA DE LA LABOR Y DE PERFORACI
EFICIENCIA DE LA LABOR
Nº DE TALADROSE.L 1.37 m.t/h-gd LONGITUD DE TALADRO
Long. Mens. De Perf. =
E. P. =
5.-EFICIENCIA DEL EXPLOSIVO O FACTOR DE POTENCIA
DENSIDAD DE CARGA POR TALADRO
DENSIDAD DEL EXPLOSIVO 1.16 lb/pieØEXPLOSIVO 0.766 Pulg.FACTOR DE CONVERSION 0.34
DENSIDAD DE CARGA POR TALADRO 0.30 lb/pie
FACTOR DE POTENCIA
"Nº DE PER. / Mes = 2 x 2 x 8"
E. L. = 292.51/ 204
E. P. = 292.51/ 17.08
� . .�.� =�.�� � �.�
![Page 54: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/54.jpg)
F.P. = 17.73 / 292.5 = 0.05 LBS./ TM =
6.-EFICIENCIA DE LOS EQUIPOS DE LIMPIEZA
EQUIPOS DE ACAREONº DE UNIDADES DE CARGUIO 2
![Page 55: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/55.jpg)
ELABORACION DE CUADROS ESTADISTICOS PARA CHIMENEAS
Nº GUARDIAS/DIA 2 DATOS
VOLADURASUPERVISOR DE VOLADURA 1CARDOR ( CHISPERO) 1AYUDANTE 1TRANSPORTADOR DE EXPLOSIVO 1TOTAL DE PERSONAS 4 pers.
PV 7 Dias/mes
VOLADURA
Nº DE PERSONAS / Mes 56 personas/mes
EFICIENCIA DE PERFORACION
Nº DE TALADROS 14LONGITUD DE TALADRO 1.22 Mt.Long. Mens. De Perf. = 17.08 Mt.
E. P. = 17.13 TM/mp.
LONGITUD EFECTIVA DE CARGA
FACTOR DE CORRECCION 0.9LONGITUD DE TALADRO 1.22 mt
L.E.C. = 1.10 mt.
"Nº DE PER. / Mes = 4 x 2 x 7"
E. P. = 292.51/ 17.08
� . .�.� =�.�� � �.�
![Page 56: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/56.jpg)
0.02 Kg/tm dinamita
HORAS DE TRABAJO POR MES EFICIENCIA DE CARGUIO
104 hrs./mes 2.81
![Page 57: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/57.jpg)
LIMPIEZADESATADORES 2
PALEROS 1CARREROS 2
TOTAL DE PERSONAS 5 pers.
PL 13 Dias/mes
LIMPIEZA N- de personas totales / mes
Nº DE PERSONAS / Mes 130 personas/mes
CONSUMO DE EXPLOSIVO POR MES
CME = 16.00 Lbs/mes
"Nº DE PER. / Mes = 5 x 2 x 12"
��� . .=��� � � ��� � �� � ��
![Page 58: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/58.jpg)
EFICIENCIA DE CARGUIO
ml / h - maq.
![Page 59: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/59.jpg)
DATOS
N- de personas totales / mes214 personas/mes
![Page 60: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/60.jpg)
![Page 61: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/61.jpg)
ELABORACION DE CUADROS ESTADISTICOS PARA CHIMENEAS DE DOBLE COMPARTIMIENTOPRODUCION POR MES 784.24 TM/Mes
PLANIFICACION DEL PERSONAL POR GUARDIAPERFORACIONPERFORISTA 1
AYUDANTE DE PER. 1TOTAL DE PERSONAS 2
Nº GUARDIAS/DIA 2PP 7 Dias/mes
VOLADURASUPERVISOR DE VOLADURA 1
CARDOR ( CHISPERO) 1AYUDANTE 1
TRANSPORTADOR DE EXPLOSIVO 1TOTAL DE PERSONAS 4
PV 7 Dias/mes
LIMPIEZADESATADORES 2
PALEROS 1CARREROS 1
TOTAL DE PERSONAS 4PL 13 Dias/mes
PROCESOS PRODUCTIVOSNUMERO DE PERSONAS POR MES
PERFORACION
Nº DE PERSONAS / Mes 28 h - gd/mes
VOLADURANº DE PERSONAS / Mes 56 h - gd/mes
LIMPIEZANº DE PERSONAS / Mes 104 h - gd/mes
EFICIENCIA DE LA LABORE.L 4.17 TM/ h -gd
EFICIENCIA DE PERFORACION
Nº DE TALADROS 13LT 1.83 m
![Page 62: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/62.jpg)
LONGITUD MENSUAL PERFORADO 23.79 mEFICIENCIA DE PERFORACION 32.97 TM / Mp
EFICIENCIA DEL EXPLOSIVO DENSIDAD DEL EXPLOSIVO 1.16ØEXPLOSIVO 0.766 PULGADASFACTOR DE CONVERSION 0.34
DENSIDAD DE CARGA POR TALADRO 0.23 lb/pie
FACTOR DE CORRECCION 0.9LONGITUD EFECTIVA DE CARGA 1.65
CONSUMO DE EXPLOSIVO POR MES 2,507.91 lb / mes
FACTOR DE POTENCIA 3.20 lb/TM 1.45
EFICIENCIA DE LOS EQUIPOS DE LIMPIEZAEQUIPO DE CARGUIO
Nº DE UNIDADES DE CARGUIO 1HORAS DE TRABAJO POR MES 52 h./mes
EFICIENCIA DE CARGUIO 15.08 TM / h - maq.
![Page 63: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/63.jpg)
ELABORACION DE CUADROS ESTADISTICOS PARA CHIMENEAS DE DOBLE COMPARTIMIENTO
![Page 64: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/64.jpg)
Kg/TM
![Page 65: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/65.jpg)
ELABORACION DE CUADROS ESTADISTICOS PARA CHIMENEAS DE DOBLE COMPARTIMIENTO
![Page 66: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/66.jpg)
![Page 67: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/67.jpg)
ELABORACION DE CUADROS ESTADISTICOS PARA TAJEOPRODUCION POR MES 3732.48 TM/Mes
PLANIFICACION DEL PERSONAL POR GUARDIAPERFORACION
PERFORISTA 2AYUDANTE DE PER. 2
TOTAL DE PERSONAS 4Nº GUARDIAS/DIA 2
PP 8 Dias/mes
VOLADURASUPERVISOR DE VOLADURA 1
CARDOR ( CHISPERO) 1AYUDANTE 1
TRANSPORTADOR DE EXPLOSIVO 1TOTAL DE PERSONAS 4
PV 8 Dias/mes
LIMPIEZADESATADORES 4
PALEROS 3CARREROS 3
TOTAL DE PERSONAS 10PL 13 Dias/mes
PROCESOS PRODUCTIVOSNUMERO DE PERSONAS POR MES
PERFORACION
Nº DE PERSONAS / Mes 64 h - gd/mes
VOLADURANº DE PERSONAS / Mes 64 h - gd/mes
LIMPIEZANº DE PERSONAS / Mes 260 h - gd/mes
EFICIENCIA DE LA LABORE.L 9.62 ml/ hg EL=3732.48/(64+64+260) ml/hg
EFICIENCIA DE PERFORACION
Nº DE TALADROS 109 taladrosLT 1.44 m Long. Mensual Perf.= 109 taladros*1.44 metros
![Page 68: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/68.jpg)
LONGITUD MENSUAL PERFORADO 156.96 mEp= 3732.48 TMM/156.96 Metros
EFICIENCIA DE PERFORACION 23.78 TM / Mp
EFICIENCIA DEL EXPLOSIVO DENSIDAD DEL EXPLOSIVO 1.16ØEXPLOSIVO 0.766 PULGADASFACTOR DE CONVERSION 0.34
DENSIDAD DE CARGA POR TALADRO 0.23 lb/pie1.35 lb/taladro
LONGITUD EFECTIVA DE CARGAFACTOR DE CORRECCION 0.9
LEC=Lt*FACTOR DE CORRECIÓNLEC=1.44m*0.90
LEC= 1.30
CONSUMO DE EXPLOSIVO POR MESDATO: Fp=1.05 CEM=LEC*N°taladros*Dc*Fp
CEM = 200.24 lb / mes
FACTOR DE POTENCIA FP=CEM/3732.48TMM
FP = 0.05 lb/TM
EFICIENCIA DE LOS EQUIPOS DE LIMPIEZA1. EQUIPO DE CARGUIO :
Nº DE UNIDADES DE CARGUIO 3HORAS DE TRABAJO POR MES HTM=h/g*g/dia*dias/mes*N° de unidades
HTM=10*2*13*3780 hrs/mes
2. EFICIENCIA DE CARGUIOEC = 3732.48TMM /780hrs/mes 4.79 ml/ h - maq.
![Page 69: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/69.jpg)
EL=3732.48/(64+64+260) ml/hg
Long. Mensual Perf.= 109 taladros*1.44 metros
![Page 70: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/70.jpg)
CEM=LEC*N°taladros*Dc*Fp
HTM=h/g*g/dia*dias/mes*N° de unidades
![Page 71: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/71.jpg)
PLANEAMIENTO POR CUADROS ESTADISTICOS PARA LA EMPRESA MINERA TOMA LA MANO ( JULIO 2011)
NPARAMETROS
CHIMENEAE.LABOR 1.37 TM/ h-g
E.PERFORACION 17.13 TM/ mp FACTOR DE POTENCIA 0.02 Kg /TM
CARGUIO 2.81TM / h - maq.
![Page 72: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/72.jpg)
PLANEAMIENTO POR CUADROS ESTADISTICOS PARA LA EMPRESA MINERA TOMA LA MANO ( JULIO 2011)
I V E L
GALERIA CHIMENEA DOBLE COMPARTIMIENTO TAJEO3.99 TM/ h -g 4.17 TM/ h -g 9.62 TM/h - g20.59TM/ mp 32.97 TM / mp 23.78 TM/mp2.33 Kg / TM 1.45 kg / TM 0.02Kg/TM
29.39 TM /h - maq. 15.08 TM / h- maq. 4.79 TM/h - maq.
![Page 73: Toma La Mano Cuadros Conteol](https://reader036.vdocuments.net/reader036/viewer/2022082213/577c77441a28abe0548b66bf/html5/thumbnails/73.jpg)
PLANEAMIENTO POR CUADROS ESTADISTICOS PARA LA EMPRESA MINERA TOMA LA MANO ( JULIO 2011)