Download - Unexpected Contamination Finds Protocol
Unexpected Contamination Finds Protocol New Sydney Fish Market (Stage 2) Construction Works Prepared for: Multiplex 22 Bridge Road Glebe NSW 2037 5 March 2021
Distribution
s18417_004_rpt_ufp i
Distribution
Unexpected Contamination Finds Protocol, New Sydney Fish Market (Stage 2) Construction Works
5 March 2021
Revision Status Recipient Copies
0 Final Mitch Pelling Senior Project Engineer Multiplex
PDF/ Hard Copy
Disclaimer and Limitations 1 This document is confidential and has been prepared by Senversa for use only by its client and for the specific purpose
described in our proposal which is subject to limitations. No party other than Senversa’s client may rely on this document without the prior written consent of Senversa, and no responsibility is accepted for any damages suffered by any third party arising from decisions or actions based on this document. Matters of possible interest to third parties may not have been specifically addressed for the purposes of preparing this document and the use of professional judgement for the purposes of Senversa’s work means that matters may have existed that would have been assessed differently on behalf of third parties.
2 Senversa prepared this document in a manner consistent with the level of care and skill ordinarily exercised by members of Senversa’s profession practicing in the same locality under similar circumstances at the time the services were performed.
3 Senversa requires that this document be considered only in its entirety, and reserves the right to amend this report if further information becomes available.
4 This document is issued subject to the technical principles, limitations and assumptions provided in Section 7.0.
Senversa Pty Ltd ABN: 89 132 231 380 Level 5, The Grafton Bond Building, 201 Kent St, Sydney NSW 2000 tel: + 61 2 8252 0000; fax: + 61 3 9606 0074 www.senversa.com.au
Primary Author
Project Manager
Zoe Smith Senior Environmental Scientist
Emma Walsh Senior Associate Environmental Scientist
Technical Peer
Review Project
Director
Alex Latham Principal
Melissa Porter Senior Principal
Contents
s18417_004_rpt_ufp ii
Contents
List of Acronyms ...................................................................................................................................................................... iii
1.0 Introduction................................................................................................................................................................... 1 1.1 Background and Context ............................................................................................................................................. 1
1.1.1 Development ...................................................................................................................................................... 1 1.1.2 Environmental Management ............................................................................................................................... 1
1.2 UFP Objective ............................................................................................................................................................... 2
2.0 Environmental Management Requirements ................................................................................................................ 4 2.1 Key Relevant Legislation and Guidelines ................................................................................................................... 4 2.2 Relevant Conditions of Approval ................................................................................................................................. 4 2.3 Other Relevant Conditions ........................................................................................................................................... 5
3.0 Potential Unexpected Finds and Characteristics ....................................................................................................... 7 3.1 Unexpected Find Definition .......................................................................................................................................... 7 3.2 Potential Unexpected Finds Characteristics ............................................................................................................... 7
4.0 Unexpected Finds Procedure ...................................................................................................................................... 9 4.1 Management of Unexpected Finds .............................................................................................................................. 9 4.2 Unexpected Finds Procedure ...................................................................................................................................... 9
5.0 Environmental Control Measures and Compliance .................................................................................................. 11 5.1 Roles and Responsibilities ........................................................................................................................................ 11 5.2 Training ....................................................................................................................................................................... 11 5.3 Monitoring and Inspection ......................................................................................................................................... 11 5.4 Auditing ....................................................................................................................................................................... 11 5.5 Reporting .................................................................................................................................................................... 12 5.6 Non-conformance ....................................................................................................................................................... 12
6.0 Review and Improvement ........................................................................................................................................... 13
7.0 Principles and Limitations of Investigation .............................................................................................................. 14
Table 2.1: Key Relevant Legislation, Regulations, Guidelines and Policy ............................................................................ 4 Table 2.2: Relevant CoA ........................................................................................................................................................... 4 Table 2.3: Other Conditions ...................................................................................................................................................... 6 Table 3.1: Unexpected Finds and Characteristics of Contamination ..................................................................................... 7 Table 4.1: Unexpected Finds Procedure .................................................................................................................................. 9 Table 5.1: Dewatering roles and responsibilities .................................................................................................................. 11
Figures Figure 1: Site Location Plan
Appendix A: RAP Unexpected Finds Procedure
List of Acronyms
s18417_004_rpt_ufp iii
List of Acronyms
Acronym Definition
ACM Asbestos containing material
AS Australian Standard
ASS Acid Sulfate Soil
ASSMP Acid Sulfate Soil Management Plan
ANZECC Australian and New Zealand Environment and Conservation Council
BTEX Benzene, toluene, ethylbenzene, xylenes
CEMP Construction Environmental Management Plan
CoA Conditions of Approval
CoPC Contaminant of potential concern
CLM Act Contaminated Land Management Act 1997
EMS Environmental Management System
EPA Environment Protection Authority (NSW)
HMMP Hazardous Materials Management Plan
MSDS Material Safety Data Sheet
NEPC National Environment Protection Council
NEPM National Environment Protection Measure
NHMRC National Health and Medical Research Council
OCP Organochlorine Pesticides
OPP Organophosphate Pesticides
PAH Polycyclic aromatic hydrocarbons
PC Principal Contractor
PCB Polychlorinated Biphenyl
PCE Tetrachloroethene
PFAS Per- and polyfluoralkyl substances (PFAS)
PPE Personal Protective Equipment
RAP Remedial Action Plan
RPD Relative percentage difference
SAR Site Audit Report
SAS Site Audit Statement
List of Acronyms
s18417_004_rpt_ufp iv
Acronym Definition
SWMP Soil and Water Management Plan
UFP Unexpected Contaminated Finds Protocol
UST Underground storage tank
Introduction
s18417_004_rpt_ufp
1
1.0 Introduction
The NSW State Government engaged Multiplex as the Principal Contractor (PC) to construct the new Sydney Fish Market (Stage 2). The project is located at 1A-1C Bridge Road, Glebe and part of 56-60 Pyrmont Bridge Road, Pyrmont NSW; herein referred to as the ‘site’ (shown on Figure 1).
Senversa has been engaged by Multiplex to prepare an Unexpected Contaminations Finds Protocol (UFP) for the New Sydney Fish Market (Stage 2) Project. The UFP forms a sub-plan part of the Construction Environmental Management Plan (CEMP1) prepared by Multiplex. The UFP is required to document the management procedures and controls to mitigate potential environmental and human health impacts associated with unexpected contamination and asbestos finds that may be encountered during construction works.
1.1 Background and Context
1.1.1 Development
In June 2020, the New Sydney Fish Market was declared a State Significant Development (SSD 8925) under Section 5.1 of the Environmental Planning and Assessment Act 1979 (EP&A Act). The development broadly comprises the construction, use and operation of a new Sydney Fish Market.
The development application was approved by the Minister for Planning and Public Spaces on 12 June 2020 subject to conditions of approval (CoA), further discussed in Section 2.2.
1.1.2 Environmental Management
The overall Environmental Management System (EMS) for the project is described in Section 2 of the CEMP and has been designed by Multiplex to align with standards detailed below. The EMS consists of environmental plans, including this UFP, and the procedures, protocols, and tools as set out in the CEMP. The CEMP has been developed to document the overarching environmental management strategies and procedures that will be adopted during construction of the project to meet Australian Standards for:
• Quality Management Systems (AS/NZS ISO 9001) • Environmental Management Systems (AS/NZS ISO 14001:2015) • Occupations Health and Safety Management Systems (AS/NZS 4801:2001)
The CEMP applies to all construction works associated with the project and consists of:
• An overview of the Environmental Management Systems (EMS). • Organisation structure for environmental management. • Legislative requirements. • Sub-plans to manage processes. • Processes to monitor and evaluate environmental performance.
The UFP forms part of the Multiplex environmental management framework for the project, as described in Section 2.2 of the CEMP. An outline of the various management sub-plans in the CEMP is provided in Figure 1-1 (below).
It is noted that acid sulfate soils (ASS) are not considered an unexpected find as they are known to be on site. As such, management of ASS is not discussed in this UFP, however are detailed within the CEMP and ASS Management Plan.
1 Multiplex (2021), Construction Environmental Management Plan – New Sydney Fish Market, undated.
Introduction
s18417_004_rpt_ufp
2
The preparation and implementation of an UFP is a requirement of the CoA (refer Section 2.2). Preparation and implementation of the UFP also forms a condition of Site Audit Statement (SAS2) and associated Site Audit Report (SAR) prepared under the Contaminated Land Management Act 1997 (CLM Act) for the site. Further discussion of these conditions and requirements is provided in Section 2.0.
1.2 UFP Objective
The objective of this UFP is to document the management responsibilities, controls and procedures to mitigate potential environmental and human health impacts associated with unexpected contamination and asbestos finds that may be encountered during construction works.
2 Tom Onus – Ramboll (2020), Site Audit Statement – Revised Remediation Action Plan, The New Sydney Fish Market, Pyrmont NSW, dated 13 August 2020.
Introduction
s18417_004_rpt_ufp 3
Figure 1-1 – Fish Markets Construction Project EMS
Remediation Action Plan
Remedial Works Plan/REMP
CEMP
Dewatering Plan Unexpected Finds Procedure
Stormwater Management Plan
Microbat Management Plan
Acid Sulfate Soil Management Plan Traffic Control Plans
Construction Heritage
Management Plan
Construction Noise and Vibration
Management plan
Soil and Water Management Plan
Waste Management Plan
Construction Air Quality Management
Plan
Water Quality Managment Plan
Hazardous Materials Managment Plan
Environmental Management Requirements
s18417_004_rpt_ufp
4
2.0 Environmental Management Requirements
2.1 Key Relevant Legislation and Guidelines
The CEMP (Section 1.8) identified relevant legislation, regulation, guidelines, and approvals, licences and permits, with key references relevant to the UFP listed below.
Table 2.1: Key Relevant Legislation, Regulations, Guidelines and Policy
Reference
Legislation
• Contaminated Lands Management Act 1997 • Protection of the Environment Operations Act 1997
• Environmental Planning and Assessment Act 1979
Guidelines and Standards
• Australian and New Zealand Guidelines for Fresh and Marine Water Quality (ANZG, 2018) (note: these guidelines supersede ANZECC (2000) referenced in CoA)
• NSW EPA (2014) Waste Classification Guidelines
• National Environment Protection Council, 1999. National Environment Protection (Assessment of Site Contamination) Measure, amended 2013 (ASC NEPM)
• Safe Work Australia, 2018. Code of Practice: How to safely remove asbestos.
• NSW EPA (1995) Contaminated Sites: Sampling Design Guidelines, September 1995.
•
2.2 Relevant Conditions of Approval
The CoA relevant to this UFP are listed in Table 2.2 below.
Table 2.2: Relevant CoA
CoA No. Condition Requirements Applicability
B80 “(b) provide details demonstrating compliance with the relevant legislation, particularly with regard to the removal of asbestos and hazardous waste, the method of containment and control of emission of fibres to the air.”
Applicable where asbestos is identified as an unexpected find.
B92 “Prior to the commencement of works, an Unexpected Contamination Finds Protocol (UFP) prepared by a suitably qualified and experienced expert shall be prepared. The protocol should include detailed procedures for identifying and dealing with unexpected contamination, asbestos and other unexpected finds. The Applicant should ensure that the procedure includes details of who will be responsible for implementing the unexpected finds procedure and the roles and responsibilities of all parties involved. The UFP must be submitted to the Certifier and EPA. The UFP must be implemented for the duration of construction works.”
Applies to all works across the site
Environmental Management Requirements
s18417_004_rpt_ufp
5
CoA No. Condition Requirements Applicability
B93 “Prior to the commencement of works, the Applicant must engage an EPA-accredited Site Auditor to prepare interim audit advice which comments on: (a) The Data Gap Assessment- The New Sydney Fish Market 1A to 1C Bridge Road, Glebe NSW, Revision A (dated 12 March 2019) prepared by JBS&G Australia Ply Ltd for UrbanGrow1h NSW Development Corporation which comments on the appropriateness of the assessment and the assessment's conclusions; (b) Whether the characterisation of the site is sufficient to ensure any asbestos containing materials in soils and at ground surface are managed appropriately; NSW Government Department of Planning, Industry and Environment 23 New Sydney Fish Market - Stage 2 (SSD 8925). ( c) Whether the Hazardous Materials Management Plan, prepared by JBS&G ( dated 8 April 2019), requirements for managing asbestos at ground surface and in soils are appropriate.”
Applies to all works across the site
B95 “The Applicant must adhere to the management measures accepted or recommended by the site auditor.”
Refer to Section 2.3 below
B97 “The Applicant shall comply with any notification requirements to SafeWork NSW concerning the handling and removal of any asbestos.”
Applicable where asbestos is identified
C18 “Should any new information come to light during demolition or construction works which has the potential to alter previous conclusions about site contamination, the Department must be immediately notified, and works must cease. Works must not recommence on site until the Department confirms works can recommence.”
Applies to all unexpected finds
C37 “Removal of asbestos and other hazardous building materials must be undertaken by a suitably licensed contractor and an asbestos clearance certificate must be provided before waste classification, disposal or site validation is undertaken.”
Applicable where asbestos is identified as an unexpected find
2.3 Other Relevant Conditions
Other requirements or conditions in approved documents relevant to this UFP are listed in Table 2.3 below – these do not include related requirements under the CEMP or sub-plans (e.g. HMMP).
Environmental Management Requirements
s18417_004_rpt_ufp
6
Table 2.3: Other Conditions
Reference Condition Requirements Applicability
Remediation Action Plan (RAP3)
The RAP outlined the following requirements of site management and remediation works that have been considered in the development of this UFP: • Prevent exposure of contaminated soil, sediment and groundwater to the
human population whilst occupying, working on or using the site. • Appropriately manage and/or dispose of soil, water and sediment waste
disturbed during development activities in accordance with relevant EPA guidelines.
• Removal of potential ongoing sources of environmental contamination (unexpected finds such as historical sub-surface petroleum storage, if encountered);
• Given asbestos in soil has not currently been identified during limited intrusive investigation activities, should asbestos be identified, its occurrence will be assessed and managed via application of the Unexpected Finds Protocol outlined in Section 8.6 (of the RAP).
• Validation assessment requires Assessment and close out of any Unexpected Finds assessments.
• There is the potential that one or more USTs may be encountered during demolition of the pavements or subsequent earthworks. In the event of such an occurrence, the Unexpected Finds Protocol as presented in the RAP will be implemented and remedial actions defined EPA (2014b)4 implemented.
• In the event that oily materials are encountered, the provisions outlined in the unexpected finds protocol will be implemented, comprising inspection, testing and appropriate action as advised by the Remediation Consultant.
• The sampling frequency of the identified substance/materials shall meet the minimum requirements outlined in EPA (19955) in addition to those outlined in the RAP. In the event of an Unexpected Find, it is anticipated that the suitability of the implemented characterisation assessment and the proposed validation strategy be discussed with the site auditor prior to finalisation of the Unexpected Find works.
• Unexpected finds to be recorded in the material tracking plan, where encountered.
Applies to all works across the site
SAS or SAR Comments within the SAR and conditions within the SAS relevant to the UFP include: • Raised concerns regarding review of historic reports and potential for additional
underground storage tanks (UST’s) and other unexpected finds to be identified during demolition and construction works.
• Further assessment and characterisation of sediment, particularly in western area of the site was requested. This has since been addressed in the JBS&G (2021) Sediment Characterisation Assessment. No unexpected finds or changes to the RAP were identified during this investigation.
• Further assessment of soil on the eastern portion of the site (below current active Sydney Fish Market) to characterise material within this area were requested during demolition and construction. No intrusive investigations have been conducted in this area to date and there is potential for unexpected finds due to site history.
• PCB and PAH to be analysed on decommissioning of substation. Hazardous Materials Management Plan needs to be revised if ozone depleting substances are identified.
• Only one fragment of asbestos has been identified in soil during investigation works. The auditor noted that there was potential for further asbestos to be identified during demolition works based on site history. Further assessment of asbestos was requested when demolition is occurring.
Applies to all works across the site, however data gaps identified particularly below the substation and within the eastern landside area of the site.
3 JBS&G (2020) Remediation Action Plan, The new Sydney Fish Market, dated 8 July 2020. 4 NSW EPA (2014b), Technical Note: Investigation of Service Station Sites, dated April 2014. 5 NSW EPA (1995) Contaminated Sites: Sampling Design Guidelines, September 1995
Potential Unexpected Finds and Characteristics
s18417_004_rpt_ufp
7
3.0 Potential Unexpected Finds and Characteristics
3.1 Unexpected Find Definition
An unexpected find is defined as potential contaminated land or asbestos that was not previously identified in the EIS, RAP, CEMP (and sub-plans) or during pre-construction investigations.
For the purposes of this plan, contaminated land comprises land within the project area that meets the definition of contamination in Contaminated Land Management Act 1997. This includes asbestos.
Identified contaminated land, and pre-construction investigations to further assess contaminated land, in the project area is described in the CEMP and acid sulfate soil management plan (ASSMP).
3.2 Potential Unexpected Finds Characteristics
A summary and description of the types of unexpected finds that may be encountered during construction work in the project area is presented in Table 3.1 below.
Table 3.1: Unexpected Finds and Characteristics of Contamination
Potential Unexpected Find
Observed Characteristic Type of Contaminant / Issues
Petroleum hydrocarbons (e.g. fuels, oils and lubricants)
May be identified by either odour and/or visual indications of contamination. Petroleum hydrocarbon contamination may be identified by characteristic petrol, diesel or ‘oily’ odours (e.g. hydraulic oil) which may vary in strength from weak (just detectable) to very strong (easily detectable at a distance from the source). In soils, the odour may or may not be accompanied by specific areas of dark staining (black-grey) or larger scale discolouration of strata from a previously identified ‘natural colour’ (e.g. staining of orange and brown clay to dark grey and green.) May also be visible as a distinct coloured sheen on water within an excavation.
TRH, BTEX, PAH, lead
Buried dry waste materials May include a variety of construction and demolition waste materials including wood, plastic, metal fragments, building rubble (e.g. concrete, brick, asphalt, asbestos containing materials etc.).
Asbestos, heavy metals
Buried or surface bonded ACM, asbestos fines/friable asbestos
Cement-bound asbestos containing material (ACM) (e.g. compressed cement sheeting) may be present in building waste or pipes. Friable forms of asbestos including lagging and insulation.. Textured coatings and vinyl floor tiles may also contain asbestos. Asbestos fines and asbestos fibres are not typically visible to the unaided eye. Laboratory analysis is required to identify asbestos in soil.
Asbestos
Buried organic materials Such materials may be associated with decomposed plant matter found within the natural alluvial soils. Although this process is generally naturally occurring, by-products of the decomposing natural material should be considered if encountered.
Nutrients (ammonia, sulphates, phosphates), gaseous emissions (CH4, CO2, H2S)
Potential Unexpected Finds and Characteristics
s18417_004_rpt_ufp
8
Potential Unexpected Find
Observed Characteristic Type of Contaminant / Issues
Structures or conduits containing possible hazardous materials
Could be identified as follows: • A buried storage tank or former pipelines (typically metal,
concrete or plastic). • Deeper sand fill sometimes with visual/olfactory indications of
contamination. • Presence of small concrete footings surrounding by odorous of
visually impacted soils and/or groundwater.
TPH, BTEX, PAH, lead, asbestos
Ash or slag deposits Ash materials are typically light weight, grey and white sand and gravel sized particles (1mm to 10mm). Slag materials can be varied in consistency and colour and may comprise pale grey to blue/green/grey and be loose or cemented. Slag gravels can be very angular and appear to have a vesicular (i.e. ‘honeycomb’) texture.
PAH, heavy Metals, can generate alkaline leachate
Landfill type material Could include a combination of the other categories detailed in this table along with domestic (e.g. rag, clothing), clinical (e.g. sharps, human tissue or hair, laboratory specimens or culture), and/or putrescible waste (e.g. food scraps, nappies, animal waste).
Heavy metals, acids, ammonia, sulfides
Other unusual odours Other unusual odours that a different from surrounding soils. For instance, a sweet odour could indicate the presence of chlorinated hydrocarbon contamination.
Various
Per- and polyfluoralkyl substances (PFAS)
Foaming in waters (e.g. in excavations, dewatering sumps or discharge) with little agitation and minimal dissipation.
PFAS
Buried Drums Metal or plastic drums containing potentially unknown hazardous substances. It is noted that management of drum contents may require specialist hazmat contractors. Drums should not be opened to inspect contents until a qualified hazmat contractor has been engaged to assessed potential risks.
Various
Unexpected Finds Procedure
s18417_004_rpt_ufp
9
4.0 Unexpected Finds Procedure
The Multiplex Site Manager will retain the overall responsibility for implementing the unexpected finds procedure for all construction works undertaken within, or near, the project area.
4.1 Management of Unexpected Finds
Where unexpected contamination is identified or suspected by personnel involved in construction works within or near the project area, works will be temporarily suspended in the affected area. This area will be isolated to minimise the potential for disturbance of the affected material, soil and/or water. The Multiplex field personnel are to notify the Multiplex Site Manager or Project Manager who will then contact the Multiplex Environmental and Sustainability Manager who will be responsible for evaluation of the nature of the unexpected find.
The NSW EPA Accredited Site Auditor (the auditor) is to be notified in writing of the nature, extent, and proposed management of each unexpected find within 24 hours of discovery.
Due to the potential variability in both the nature and extent of an unexpected find, it is not possible to define specific remedial strategies for potential contamination associated with an unexpected find. However, the procedure described in Section 4.2 details a process for identifying and evaluating feasible options to manage an unexpected find.
4.2 Unexpected Finds Procedure
The unexpected Finds Protocol outlined in the RAP can be found in Appendix A. In the event that a person on-site identifies an unexpected find, Multiplex will undertake the actions presented in Table 4.1 below.
Table 4.1: Unexpected Finds Procedure
Step no. Description Action
1 Potential contaminated soil, groundwater or surface water, or ACM, is encountered during construction activities.
Cease work in the potentially impacted area as soon as it is safe to do so and move away from the area. Assess the potential immediate risk to worker health and surrounding environment posed by the unexpected find and assess if evacuation or assistance of emergency services is required.
2 Environmental management and work health safety management
Delineate an exclusion zone around the impacted area using fencing and/or appropriate barriers and signage. Additional control measures may be required for: • Odours and/or volatile compounds: odours suppression and no flames/sparks
signage. • Potential asbestos containing materials: if area is small cover with weighted
plastic sheeting or geofabric. For larger areas, use regular dust suppression as conditions require – refer to the Work Health and Safety Plan for required controls.
• Install environmental controls around the site to contain the contaminated material including diversion of water to minimise potential spread via surface water runoff in accordance with the Soil & Water Management Plan (SWMP).
• Personal Protective Equipment (PPE) will be worn if conditions have changed as per the relevant Material Safety Data Sheet (MSDS) and Multiplex worker safety requirements.
Unexpected Finds Procedure
s18417_004_rpt_ufp
10
Step no. Description Action
3 Assess the unexpected find
A Contaminated Land Consultant should assess the unexpected find and provide: • Preliminary assessment of the nature of suspected contamination and
immediate management controls if needed. • Advise what further assessment and/or remediation works are required and
how such works are to be undertaken in accordance with contaminated site regulations and guidelines – refer to the CEMP.
• The assessment may include a requirement to undertake a targeted site investigation to sample and analyse contaminated media.
Suspected or identified contamination will be characterised with consideration of ASC NEPM (NEPC, 2013) and soil material will be classified in accordance with the Waste Classification Guidelines (NSW EPA, 2014).
4 Management or mitigation action and reporting
Based on advice of the Contaminated Land Consultant, implement necessary management or mitigation actions to minimise risk to human health and the environment and to allow the construction activities to recommence. Record details of the unexpected find and the actions undertaken, including the following, and notify the auditor, landowner; local council and/or NSW EPA: • Location, nature and extent of unexpected find • Scope, methodology and results of any investigation. • Scope, methodology and outcomes from any remedial activities completed. • Results of any validation sampling or clearance certificates (i.e. for asbestos). • Implemented changes to risk control measures.
5 Recommence works The Contaminated Land Consultant will provide relevant information and recommendations to the Multiplex Environment and Sustainability Manager, particularly for considering any changes to existing site management plans. Recommence construction works once mitigation or remediation works have been implemented, sampling has validated that the remediation strategy has been successful and if it is then deemed safe to do so by the Multiplex Environment and Sustainability Manager and the auditor.
Environmental Control Measures and Compliance
s18417_004_rpt_ufp
11
5.0 Environmental Control Measures and Compliance
5.1 Roles and Responsibilities
In addition to those detailed in the CEMP, the roles and responsibilities presented in Table 5.1 are relevant to the UFP.
Table 5.1: Dewatering roles and responsibilities
Role Responsibility
Contaminated Land Consultant Assess requirements to mitigate impacts of unexpected find and follow procedures outlined in the RAP and this UFP.
Foreman and Environmental Officer Communicate discovery and nature of unexpected finds to contamination consultant.
5.2 Training
Personnel involved in construction works in the project area will be made aware of, and trained, in the recognition of potential unexpected finds. Training will be undertaken as a part of general site induction and refreshed periodically at toolbox meetings.
Training will provide general awareness for recognition of potential contamination and hazardous materials, so that works can be suspended temporarily to allow evaluation by an appropriately qualified person. Project workers will be trained in identifying the following:
• Soil that appears to be contaminated based on visual and olfactory indicators. • Asbestos (i.e. either bonded or friable). • Groundwater or surface water that appears to be contaminated based on visual and olfactory
observations (including potential hydrocarbon sheens on the water surface, free phase liquids such as petroleum fuel, discolouration etc.).
• Drums or USTs. • Fill containing waste (e.g. ash, slag, refuse, demolition materials).
Contaminated land, ASS and/or asbestos is expected in some project areas (refer to CEMP and ASSMP). The Multiplex Project Manager and/or Environmental and Sustainability Manager will be responsible for making the Site Manager aware of the nature of these prior to construction activities commencing in those areas.
5.3 Monitoring and Inspection
Monitoring and inspection will be conducted in accordance with section 9 of the CEMP. Results and actions of monitoring and inspection are to be recorded as specified within the CEMP.
5.4 Auditing
Internal and external audit requirements will be conducted as outlined within section 10.1 of the CEMP.
Environmental Control Measures and Compliance
s18417_004_rpt_ufp
12
5.5 Reporting
Reporting will be conducted as outlined within section 12 of the CEMP. As per the CEMP, all unexpected finds are to be recorded on the Multiplex Unexpected Finds Register.
5.6 Non-conformance
Non-conformances will be managed as outlined in section 10.2 of the CEMP.
Review and Improvement
s18417_004_rpt_ufp
13
6.0 Review and Improvement
This plan may be updated or revised if required. The procedure for review and approval of any updates or revisions will be in accordance with the procedure described in the CEMP.
Principles and Limitations of Investigation
s18417_004_rpt_ufp
14
7.0 Principles and Limitations of Investigation
The following principles are an integral part of site contamination assessment practices and are intended to be referred to when resolving any ambiguity or exercising such discretion as is accorded the user or site assessor.
Area Principle and Limitation
Elimination of Uncertainty
Some uncertainty is inherent in all site investigations. Furthermore, any sample, either surface or subsurface, taken for chemical testing may or may not be representative of a larger population or area. Professional judgment and interpretation are inherent in the process, and even when exercised in accordance with objective scientific principles, uncertainty is inevitable. Additional assessment beyond that which was reasonably undertaken may reduce the uncertainty.
Failure to Detect Even when site investigation work is executed competently and in accordance with the appropriate Australian guidance, such as the National Environment Protection (Assessment of Site Contamination) Amendment Measure (‘the NEPM’), it must be recognised that certain conditions present especially difficult target analyte detection problems. Such conditions may include, but are not limited to, complex geological settings, unusual or generally poorly understood behaviour and fate characteristics of certain substances, complex, discontinuous, random, or heterogeneous distributions of existing target analytes, physical impediments to investigation imposed by the location of services, structures and other man-made objects, and the inherent limitations of assessment technologies.
Limitations of Information
The effectiveness of any site investigation may be compromised by limitations or defects in the information used to define the objectives and scope of the investigation, including inability to obtain information concerning historic site uses or prior site assessment activities despite the efforts of the user and assessor to obtain such information.
Chemical Analysis Error
Chemical testing methods have inherent uncertainties and limitations. Senversa routinely seeks to require the laboratory to report any potential or actual problems experienced, or non-routine events which may have occurred during the testing, so that such problems can be considered in evaluating the data.
Level of Assessment
The investigation herein should not be considered to be an exhaustive assessment of environmental conditions on a property. There is a point at which the effort required to obtain information is outweighed by the time required to obtain that information, and, in the context of private transactions and contractual responsibilities, may become a material detriment to the orderly conduct of business. If the presence of target analytes is confirmed on a property, the extent of further assessment is a function of the degree of confidence required and the degree of uncertainty acceptable in relation to the objectives of the assessment.
Comparison with Subsequent Inquiry
The justification and adequacy of the findings of this investigation in light of the findings of a subsequent inquiry should be evaluated based on the reasonableness of judgments made at the time and under the circumstances in which they were made.
Data Useability
Investigation data generally only represent the site conditions at the time the data were generated. Therefore, the usability of data collected as part of this investigation may have a finite lifetime depending on the application and use being made of the data. In all respects, a future reader of this report should evaluate whether previously generated data are appropriate for any subsequent use beyond the original purpose for which they were collected, or are otherwise subject to lifetime limits imposed by other laws, regulations or regulatory policies.
Nature of Advice The investigation works herein are intended to develop and present sound, scientifically valid data concerning actual site conditions. Senversa does not seek or purport to provide legal or business advice.
Ferr
y R
oad
1 2
Wattle Street
Tram
Sto
p e
ntr
ance
s
Quarry S
treet
Bridge Lane
Bellevue Street
Fig Street
Wentw
orthPark
Road
Pyr
mon
t Bri
dge
Roa
d
Bridge R
oad
Western D
istributor
Sydney Fish M
arket waterfront
Wat
tle
Cre
scen
t
Western D
istributor
Taylor Street
Tram
Sto
p entra
nces
Pyrmont Brid
ge Road
DP120077
DP121496
DP1018801
DP1002139
DP1064339
DP550372
DP118572
DP610689
DP432716
DP118573
DP1064339
DP752049DP1076596
DP1018801
DP1018801
DP1033151
DP1115599
DP752049
SP75702
SP74234
DP1076596
SP74233DP870309
DP834973
DP125720
DP835794
DP834973
DP1027865
DP868833
DP1027865
DP734622
DP1198776
DP875889
DP827434
DP729635
DP868833
SP49302
DP870309
DP1012251
DP1012251
DP1008924
DP125720
DP3199
DP1027865
DP843679
DP1027254
SP51360
DP1064339
DP3199
DP74155
DP571484
DP836351
BLACKWATTLEBAY
Pat
h: S
:\01_
Jobs
\1.N
SW
_Job
s\S
1841
7_M
ULT
IPLE
X_F
ISH
MA
RK
ET
S_R
ED
EV
ELO
PM
EN
T\S
1841
7_00
3.ap
rx
Thi
s D
raw
ing
is S
ubje
ct to
CO
PY
RIG
HT.
No
port
ion
of th
is d
raw
ing
may
be
rem
oved
, ext
ract
ed, c
opie
d, e
lect
roni
cally
sto
red
or d
isse
min
ated
in a
ny fo
rm w
ithou
t the
prio
r w
ritte
n pe
rmis
sion
of S
enve
rsa.
Project:
Figure No:
Location:
Client:
Title:
Date:
Revision:
Scale:
Designed:
Drawn:
Checked:
File:
±
Level 5, 201 Kent Street,Sydney NSW 2000(02) 9994 8016www.senversa.com.au
Address:
Phone:Website:
S18417_003_F001
3/03/2021
0
(A3)
Notes:Cadastre and road data sourced from land.vic.gov.au (DELWP)Aerial imagery sourced from Nearmap Pty Ltd
Datum GDA 1994, Projection MGA Zone 55
New Sydney Fish Market (Stage 2) – DewateringManagement Plan
1
1A-1C Bridge Road, Glebe and Part of 56-60 PyrmontBridge Road, Pyrmont NSWMultiplex
Site Location PlanC. Smith
.
Z. SmithLegend
Approximate Seawall Extent
Stormwater Discharge
Heritage Stormwater Channel
Site Boundary
Property Cadastre0 40 80 120
Metres
1:1,750
© OpenStreetMap (and) contributors, CC-BY-SA
Site Location
Appendix A: RAP Unexpected Finds Procedure
s18417_004_rpt_ufp
Appendix A: RAP Unexpected Finds Procedure
tel: + 61 2 8252 0000 fax: + 61 3 9606 0074 [email protected] www.senversa.com.au Level 5, The Grafton Bond Building, 201 Kent St, Sydney NSW 2000 Senversa Pty Ltd ABN 89 132 231 380