North Temple Viaduct Detours
North Temple viaduct closure and construction begins April 18. Construction will take 18 months
Alternative A• Westbound detour – 300 West to 600 North to 900 West
Alternative B• Eastbound detour – 900 West to 400 South to 300 West
![Page 3: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/3.jpg)
UTA Bus Routes
UTA bus routes that travel North Temple will be rerouted beginning April 4. For specific route information visit www.rideuta.com
![Page 4: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/4.jpg)
When Is the Airport Line Being Built?
![Page 5: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/5.jpg)
North Temple Construction - Phases
Phase 1Phase 2
Phase 3Phase 4
Phase 5
![Page 6: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/6.jpg)
North Temple Phasing – Spring 2010
North Temple Phasing – Spring/Summer 2010
![Page 7: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/7.jpg)
North Temple Phasing – Summer/Fall 2010
North Temple Phasing – Spring 2011
![Page 8: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/8.jpg)
North Temple Phasing – Summer 2011
![Page 9: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/9.jpg)
Downtown Phasing – Spring 2012 – Fall 2012
![Page 10: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/10.jpg)
Communications and Marketing
• Weekly construction updates• Regular one-on-one visits to corridor properties• Comprehensive marketing plan
• Milestone events • Direct mail• Radio• Billboards• Print
• Looking for others ways to communicate construction information
![Page 11: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/11.jpg)
Airport Construction & Viaduct Open House
Thursday, March 185 p.m. to 7 p.m.
UTA FrontLines Headquarters669 West 200 South
![Page 12: UTA Airport TRAX Line North Temple Viaduct & Construction Phasing](https://reader035.vdocuments.net/reader035/viewer/2022062417/551a28c75503463e778b4688/html5/thumbnails/12.jpg)
Thank youMatt Sibul, UTA Airport TRAX Project Manager: 801-236-4731
Chad Saley, UTA Public Involvement: 801-287-2290Bill Knowles, Downtown Salt Lake Ombudsman: 801-580-2626
24-Hour Construction Issue Hotline: 1-888-800-8854www.rideuta.com