VALIDATION OF FLUIDIZIED BED DRYER
Content:
Why to validate?Parts of Equipment ValidationWho should do Equipment Validation?Equipment qualificationTypical process flow of solid dosage formValidation of fluid bed dryer
2
Why to validate?
Equipment validation is Vital for • Safety • Fewer interruptions of work • Lower repair costs • Elimination of premature replacement • Less standby equipment • Identification of high maintenance cost • Reduction of variation in results • Greater confidence in the reliability of results 3
Parts of Equipment Validation
EquipmentValidationEquipmentValidation
Installation Qualification (IQ)
Installation Qualification (IQ)
Operational Qualification (OQ)
Operational Qualification (OQ)
Performance Qualification (PQ)
Performance Qualification (PQ)
Design Qualification (DQ)
Design Qualification (DQ)
4
Who should do Equipment Validation? The vendor or the user?
The user has the ultimate responsibility for equipment qualification.
DQ should always be done by the user.While IQ for a small and low cost instrument is
usually done by the user, and IQ for large, complex and high cost instruments
should be done by the vendor.OQ can be done by either the user or the vendor.PQ should always be done by the user 5
Equipment qualification
Equipment qualification / validation includes following things :
• Design qualification (DQ)• Installation qualification (IQ)• Operational qualification (OQ)• Performance qualification (PQ)
6
Typical process flow of solid dosage form
Addition of raw material-active excipients
Preble bending-high speed mixer granulator
Granulating - high speed mixer granulator
Drying -fluid bed dryer-tray dryer
Tableting -high speed
rotary
Blending -v-blender
Addition of raw material-lubricant-disintegrants
Sizing -mill/sieve
7
Typical variable of drying process
Control variable
Initial temperature Load sizeDrying temperature programAir flow programDrying timeCooling time
Measured responses
Density Yield Moisture content
8
VALIDATION
9
fluid bed dryer
10
FBD control parameters
Fixed Variable(monitor)
Response (Test)
Bowl changePorosity of filter bagsBowl sieve
Inlet/exhaust air temperatureProduct temperatureDrying timeAir volumeHumidity of incoming air Humidity of exhaust air
Particle size distributionDensitiesLoss on dryingAssay
11
Installation Qualification(IQ)
Installation Procedure: After checking all the specifications as mentioned in
the selection criteria, service engineer of the manufacturer shall be called for commissioning, if necessary.
Authorized validation team shall carry out installation.Department Head of production, QA & engineering
shall evaluate installation report
12
Conti…Acceptance Criteria For Installation Qualification:The equipment shall fulfill the selection criteria & its
purpose of Application.Name of the manufacturer & supplier shall be as
mentioned in the Purchase orderThe manufacturer/supplier shall provide complete
equipment manual along with the equipmentAll recommended utilities of recommended
capacities are to be provided near the place of installation 13
Conti…
Revalidation CriteriaThe equipment shall be revalidated if;Location of the equipment is changed.There is change of spare/parts,major
maintenance or breakdown that have a direct effect on the performance of the equipment
14
Conti…
Conclusion:The equipment shall be considered qualified for
installation provided it meets all the parameters mentioned in the acceptance criteria.
After receiving installation report, it shall be evaluated & released for operational qualification, provided installation report is evaluated & the equipment is found meeting all parameters of acceptance criteria
15
Operational Qualification (OQ)
Training record Before initiating OQ ensure that SOP for Cleaning
and operation of FBD is available.
• Purpose: To train the qualification team for performing OQ
16
Conti…ProcedureInitiate the actual operation of the FBD to ensure
that machine is operating within specification.Check the OQ parameters against their
specifications.Observe the functioning of all controls available
on control panelRecord the observation Perform and attach report of heat distribution
study as per ` Heat distribution study procedure’ 17
Conti…
Acceptance criteria (Heat Distribution Study:)Temperature difference between all
thermocouples and set temperature should not differ by more than ± 5 °C.
All operating inputs provided on the equipment when tested shall-successfully comply
-meet tolerance limitThe equipment should successfully perform when
operated as per SOP18
Conti…
Critical gauges/indicators provided on the equipment---calibrated
The equipment when operated shall not - produce abnormal sound - show any discrepancy in its smooth operation.
19
Conti…
Revalidation Criteria:The equipment shall be revalidated if;Location of the equipment is changed.There is change of spare/ parts, major
maintenance or breakdown that have a direct effect on the performance of the equipment
Critical gauges shall be replaced or correctedAt normal revalidation schedule.
20
Performance Qualification(PQ)To check Heat Distribution by placing 10
thermocouples in geometric pattern with the FBD Shell and empty Product Container without any load to ensure heat distribution in the drying chamber
Heat distribution study will be performed at 65 ± 5°C for two hour after achieving the temperature on the controlling sensors to ensure proper heat distribution.
21
Conti…
ProcedureAfter completion of OQ initiate the PQ of FBD.The effectiveness of drying will be qualified by
determining reduction of % moisture content in drying process.
3 batches/ lots of any product will be taken for PQ of FBD.
At least 2.0 gm of sample is sampled for % MC check from the top, middle and bottom trays and will be reported 22
Conti…
In case of any deviation inform to department head for necessary action
Document the deviation details Deviation is acceptable or not will be decided -if yes -if not
23
Conti…
Acceptance criteriaThe reduction in moisture content after drying
should be as per the specification in the BMR % RSD of LOD should not be more than 6 %The equipment should produce intended outputs
with respect to quality & quantity consistently
24
Conti…
Revalidation Criteria:The equipment shall be revalidated if;Location of the equipment is changed.There is change of spare/ parts, major
maintenance or breakdown that have a direct effect on the performance of the equipment
At normal revalidation schedule.
25
Procedure for Drying Efficacy Study in Fluidized bed Dryer:
Ensure the cleaning of machine Load the wet mass in the FBD product container Set the process time & outlet temperature and
run the FBD.After completion of drying take out FBD bowl and
collect the sampleAt least 2.0 gm of sample is sampled for % MC
check from the top, middle and bottom trays and will be reported
26
Conti…
Sampling Procedure:Ware nose mask, hand gloves before sampling.Label the sample bag with details as Product
name, stage, date, time and signCollect app. 2.0 gms of dried material composite
sample in poly bag as per location shownRecord the details of analysis.
27