![Page 1: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/1.jpg)
Alan Torres New Nuclear Deployment
SCANA/South Carolina Electric & Gas
NUCLEAR | South Carolina’s Clean Energy Solution
VC Summer Unit 2/3 Update
1
![Page 2: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/2.jpg)
CV Assembly
MAB
Contractor Support
Personnel
Unit 3
Unit 2 Storage
HLD
Cooling Towers
VC Summer 2 & 3 – Construction Site 2014
2
![Page 3: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/3.jpg)
3
Placement of the Containment Vessel Bottom Head
Placement of Containment Vessel Ring 1
Placement of Module CA-20
3
Unit 2 Nuclear Island
![Page 4: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/4.jpg)
4
Unit 2 NI/TB from Southeast Corner
4
Unit 2 Nuclear Island
Unit 2 NI from Southwest Corner
4
![Page 5: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/5.jpg)
5
• Four Courses
• A lower and an Upper Equipment Hatch
• A lower and an Upper
Personnel Hatch
• An external Stiffener
Unit 2 Containment Vessel Lower Ring
5
![Page 6: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/6.jpg)
6
![Page 7: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/7.jpg)
7
![Page 8: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/8.jpg)
8
Containment Vessel Concrete Layers
Layer A
NI Basemat
Layer B Layer C
Pedestal Layer 1
8
![Page 9: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/9.jpg)
9
WaterBoxes
CH-80
Condenser A
CH-81B
Condenser B
Condenser C CH-81A
Turbine Building Layout
CH-82
CH-81C
9
![Page 10: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/10.jpg)
10
Condenser C
CH81B CH81A CH80
Condenser B
U2 Turbine Building
Condenser A
CH82
10 10
![Page 11: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/11.jpg)
11
Feedwater Heaters
U2 Turbine Building Eastside
Continued Progress on Turbine Building
11
![Page 12: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/12.jpg)
12
U2 Turbine Building Northside
12
![Page 13: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/13.jpg)
13
13
Unit 2 Nuclear Island • Place Concrete in CA20 • Fabricate and Set CA05—CVS / Access Tunnel / PXS-B Walls • Fabricate and Set CA01—Steam Generator and Refueling Canal • Fabricate and Set CA02 —IRWST / Pressurizer Wall • Fabricate and Set CA03 —IRWST Southwest Walls • Set First-Floor Mechanical Modules • Start Shield Building
Turbine Building • Complete Condenser component installation • Complete foundation at Elevation 100’0” • Start First-Bay foundation
Upcoming 2014 Construction Milestones
13
![Page 14: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/14.jpg)
14
Unit 3 Nuclear Island
CVBH
Column line 1 wall
Column line I wall
14
![Page 15: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/15.jpg)
15
Unit 3 Nuclear Island
Column line 1 wall Column line
N wall
15
![Page 16: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/16.jpg)
16
Unit 3 Containment Vessel Bottom Head
16
![Page 17: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/17.jpg)
17
Unit 3 Turbine Building Area
17
Circ Water Risers
Circ Water Pipes
![Page 18: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/18.jpg)
18 18
Upcoming 2014 Construction Milestones
18 First Quarter 2014 | Earnings Conference Call
Unit 3 Nuclear Island • Set Containment Vessel Bottom Head (CVBH) • Grout CVBH • Place first level of concrete in CVBH • Fabricate and Set CA04—Reactor Vessel Cavity • Place Auxiliary Building walls – A2 Elevation (66’6”-82’6”) Turbine Building • Complete Backfill • Install 82’6” basement foundation and walls • Fabricate and install Condenser components • Install CH Structural Steel modules
18
![Page 19: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/19.jpg)
19
• Unit 2 FNC, 3/11/13, 7000 cubic yards of concrete
• Unit 2 CR10 set, 4/3/13
• Unit 2 Containment Vessel Bottom Head placed, 5/22/13
• Unit 3 FNC, 11/4/13
• Unit 2 CV Ring 1
• Unit 3 CV Bottom Head
• Switchyard energized
• Cooling Tower 2A structure erected
• Unit 2 Turbine Building Basemat & Basement Walls placed
• Unit 2 Condensers set 12/30/13
• Unit 2 CH80 & CH82 steel set
Units 2 & 3 Construction Milestones – Completed
19
![Page 20: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/20.jpg)
20
Units 2 & 3 Accumulator Tanks Unit 3 Core Makeup Tanks
Units 2 Turbine Waterbox Unit 2 Turbine Stator 20
![Page 21: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/21.jpg)
21
• Assembly weight with oil - 529,800lbs each
• 3 in service, 1 spare
• 12,720 gallons each
• Stored Air Filled
Unit 2 Main Step Up Transformers - 230/26kV
21
![Page 22: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/22.jpg)
22
Lesson Learned
• Green NCV of 10 CFR Part 50, Appendix B, Criterion VII “for failure to assure purchased equipment met procurement and ITAAC requirements”
• Vendor provided the average wall thickness and average outer diameter, but did not provide/retain the data that supported the average
• The average values were used to obtain the “calculated volume” of the accumulator tanks
• Error required the tanks to be re-measured onsite
• ITAAC team is now more involved in the procurement process to ensure documentation will support ITAAC closure
22
![Page 23: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –](https://reader034.vdocuments.net/reader034/viewer/2022050216/5f623ac856bf0d598551fdbe/html5/thumbnails/23.jpg)
23
Questions
23