Project Status Report Date: Friday 1 July 2016 The Project Construction of a two level 116 bed hospital. Current Status Works carried out this week: Lay fire and potable water services Lay main sewer drain Lay stormwater drains Formwork construction to building one, second and third floor suspended slabs Scaffold erection around building one and building two Place and tie reo bar to building one, level two suspended slab Prepare and pour building one, level two suspended slab roof area Installation of site power trenching and laying of conduit On site subcontractors: C & V Concreters carrying out concrete pours to level two suspended slabs Project Plumbing averaging 24 men a day carrying out works to: 1. main sewer drains; 2. fire and potable water services lines; The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments PALMERSTON REGIONAL HOSPIT

Upload: phamhuong

Post on 01-Feb-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Project Status ReportDate: Friday 1 July 2016

The ProjectConstruction of a two level 116 bed hospital.

Current Status

Works carried out this week:

Lay fire and potable water services

Lay main sewer drain

Lay stormwater drains

Formwork construction to building one, second and third floor suspended slabs

Scaffold erection around building one and building two

Place and tie reo bar to building one, level two suspended slab

Prepare and pour building one, level two suspended slab roof area

Installation of site power trenching and laying of conduit

On site subcontractors:

C & V Concreters carrying out concrete pours to level two suspended slabs

Project Plumbing averaging 24 men a day carrying out works to:

1. main sewer drains;

2. fire and potable water services lines;

3. stormwater drains.

NT Scaffold – Erecting scaffold to buildings one and two

NT Proform P/L – Averaging 36 men a day on site. Carrying out formwork construction of buildings one, level two and three suspended slabs and building one, level two to three columns.

Man hours worked on site for week 20 June 2016 to 24 June 2016 were 4960 hrs.

OHS Incidents: Nil.

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments

PALMERSTON REGIONAL HOSPITAL

Environmental Controls:

Main access road to site has been spray sealed to ensure sufficient dust control measures are in place.

Site watering to manage dust control. Head works road construction progressing and monitored. Fire break maintenance and management implemented, managed and

inspected weekly throughout dry season.

Works for the forthcoming week:

Lay main sewer drains

Lay stormwater drains

Lay potable and fire service water mains

Continue formwork erection for building one, level three suspended slabs

Concrete pour to building one, level two suspended slab

Scaffold erection to buildings one and two

Continuation of site power trenching and laying of conduit.

Future Trade Packages pending award: Electrical services Mechanical services Hydraulic services Block work Lift services

Current trade packages awarded to local firms:

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments

Bulk excavation & site clearing Allan King & Sons

Boundary fencing & gates Totem Fencing P/L

Footings & columns C & V Concrete P/L

Site survey & set out works Bennett & Bennett P/L

Quantity surveying services QS Services P/L

Early works hydraulic services Project Plumbing P/L

Tower crane High Rise & Rigging P/L

Reinforcement supply One Steel Darwin P/L

Site surveillance camera Intech NT

Genset fuel supply Mini Tankers P/L

Formwork NT Pro Form P/L

Concrete supply HB Concrete Darwin P/L

Reinforcement supply One Steel Darwin

Concrete place C & V Concreters NT P/L

Reinforcement fix Reo Fast NT P/L

Concrete pumping Darwin Concrete Pumping P/L

Early works electrical Nilsen NT

Site accommodation NT Link P/L

Rubbish removal VEOLIA Environmental Darwin

Civil early works - stormwater Allan King & Sons P/L

Traffic control Core Staff NT P/L

Scaffold NT Scaffold

Site amenities cleaning & consumable

Corestaff NT & Shemrock Chemicals

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments

Headworks to hospital entrance road.

Headworks to hospital entrance road.

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments

Placed & tied reo bar to Building 2, level 2 suspended slab

Concrete pour to Building 2, level 2 suspended slab.

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments

Concrete finishing to Building 2, level 2 suspended slab.

Placed and tied reo bar to HV cable pits.

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments

Level 2 to 3, column construction building 1.

Installation of fire main and potable water services.

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments

Building 1, level 3 suspended slab construction works.

Column concrete pouring with kibble.

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments

New Palmerston Regional Hospital sign on the Stuart Highway.

The Palmerston Regional Hospital project is jointly funded by the Australian and Northern Territory Governments