dpr for hvds at ellahibagh_final
TRANSCRIPT
-
7/28/2019 DPR for HVDS at Ellahibagh_final
1/25
2
Minimization of Losses by Implementing High Voltage Distribution System
JAMMU & KASHMIR POWER
DEVELOPMENT DEPARTMENT (JKPDD),
PROJECT REPORT
FOR
HVDS IMPLEMENTATION
FOR
LT CONSUMERS OF ELLAHIBAGH & 90 FEET
ROAD ELECTRIC DIVISION-IV,
SUB-DIVISION, HAWAL / RAINAWARI.
-
7/28/2019 DPR for HVDS at Ellahibagh_final
2/25
2
Minimization of Losses by Implementing High Voltage Distribution System
CONTENTS
CHAPT DESCRIPTIONPAGES
FROM TO
01.00 GENERAL INTRODUCTION 03 05
02.00ADOPTION OF HIGH VOLTAGE DISTRIBUTIONSYSTEM (HVDS)
06 07
03.00ELECTRIC POWER INSTALLED CAPACITY, ITSAVAILABILITY & CONSUMPTION
08 09
04.00 IMPLEMENTATION STRATEGY 10 11
05.00BRIEF DESCRIPTION OF WORK AND ELECTRICALSYSTEM DESIGN CRITERIA
12 12
06.00 PROPOSED OVERALL SYSTEM PREVIEW 13 15
07.00 TECHNICAL DESCRIPTION 16 18
08.00 COST ESTIMATES 19 22
09.00 LIST OF STANDARDS 23 24
10.00 SUMMARY OF CONCLUSIONS 25 25
LIST OF SPECIFICATION DRAWINGS ENCLOSED
S.No. DRAWING NO. TITLE
01 DIV-IV/HVDS/REPORT/001PROPSED ARRANGEMENT OF HVDS
UNITS
02 DIV-IV/HVDS/REPORT/002 ARRANGEMENT OF ABC CABLE
03 DIV-IV/HVDS/REPORT/003 TYPICAL EARTHING PIT
01.00 GENERAL INTRODUCTION
-
7/28/2019 DPR for HVDS at Ellahibagh_final
3/25
2
Minimization of Losses by Implementing High Voltage Distribution System
01.01 Introduction to Distribution System
In general, electric power is generated at the power stations which are located at
the places quite away from the consumers; it is then delivered to the consumers through a
large network of transmission and distribution. Earlier, DC generators were connected to
the loads at same voltage for electricity distribution because there was no way of
changing DC voltage levels. Generally, DC generating plants used to be within desired
radius providing power supply to consumers & to avoid large and expensive conductors,
low voltages were used requiring less insulation and transmission network employed
copper which in turn, increased the losses
The present day electrical power system is AC. The power transformers installed
at power stations raises the generation voltage. to higher level (say 220KV or 132KV) for
electric power transmission. Electric power at 220KV is transmitted by three-phase, three-
wire overhead system to the outskirts of the city and this power is then received by the
primary Grid-station which reduces the voltage level further to 33KV. This voltage is
further stepped down to 11KV at secondary sub-station (Receiving stations) located at
some strategic points in the city. Transformers near the consumer localities step down the
Voltage level to lower level (415V, 3-phase 4-wire) to supply the loads thereby, distribution
of power to long distances became more economical and the distribution losses, size of
conductors got enhanced. The voltage between any two phases is 415V and between any
phase and neutral is 230V. This single-phase 230V is distributed to the residential and
commercial load and three-phase, 415V motor load is connected across the three-phase
lines directly. Most of the distribution sub-stations are pole mounted type. Conductors
require for the distribution may be carried on overhead pole lines or can be buried
underground in densely populated areas.
01.02 Existing low voltage distribution system (LVDS)
The existing distribution system in India employs large three-phase 11KV main distribution
feeders with three-phase spur lines and three-phase distribution transformers
transforming 11KV into 400V. Distribution system with low voltage employs four corecables and long low tension lines and multiple loads fed from a bulk power transformer
resulting in the increase in system losses affecting voltage profile and performance of
distribution system. Low voltage distribution is done either by three-phase four-wire, three
phase five-wire, single phase three-wire and single phase two-wire low tension lines.
Generally, in the process of supplying electricity to the consumers, energy losses occur
due to technical and commercial losses. The technical losses are mainly caused by the
energy dissipated in the conductors and equipment used for transformation, transmission
and distribution of power. The commercial losses are caused by pilferage, errors in themeter reading or defective meters and in the estimation of unmetered energy supply.
-
7/28/2019 DPR for HVDS at Ellahibagh_final
4/25
2
Minimization of Losses by Implementing High Voltage Distribution System
These losses depend on the load density, energy pattern used and configuration of
transmission and distribution system.
01.03 Reasons for High Technical and Commercial Losses
Improper load management resulting in overloading of conductor and
transformers. Also, the pumping loads and industrial loads in areas results in low
power factor which in turn, increases the losses.
Inadequate investment in transmission and distribution system resulting in the
overloading of the distribution system.
Undesired location of distribution transformers increases the overall length of
distribution network causing low voltage at the consumers point.
Employment of poor workmanship and use of inferior quality equipment in areasand in industrial loads in urban areas are some factors greatly affecting the
process of distribution network.
Old equipments are not maintained, repaired and upgraded properly. Even,
capacitors for power factor correction are not installed.
Loss of power is done by deteriorated wires and services.
Improper testing and calibration of meters, changing sequence of terminal wiring
and current transformer ratio reduces the recording.
Loads are widely dispersed and low tension lines run for long distances to feed small
loads. Low voltage distribution network results in large faults leading to the frequent
interruptions in supply and distribution transformer failures due to low tension fault
currents. This distribution system is unsuitable to serve in densely populated areas.
Monitoring of low voltage feeders is very difficult and low voltage feeders have
considerable voltage drop which is a cause of high current losses beyond loading
limits.
01.04 Drawbacks of LVDS
-
7/28/2019 DPR for HVDS at Ellahibagh_final
5/25
2
Minimization of Losses by Implementing High Voltage Distribution System
Higher losses, poor tail end voltages, more fluctuations in voltage and frequent cuts
fuse blowouts.
Due to frequent faults, more failures in distribution transformer and its maintenance
and repair requires high expenditure. Due to delay in replacement of failed distribution
transformers, there is a great loss & burden on state exchequer & huge public outcry.
Unauthorized hooking or tapping the bare conductors of low tension feeder or
tampered service lines and monitoring of low voltage feeders is really very difficult.
In case of any failure in three-phase large capacity distribution transformer, entire unit
is to be replaced which consumes more time.
After analyzing the pros and cons of low voltage distribution system, it is clear
that there is a great need to reduce the losses in the existing distribution
network. Some measures can be taken to minimize the technical as well ascommercial losses to some extent and that are:
Identification of weakest areas in the distribution system and strengthening them so as
to draw the maximum benefits by way of extracting more revenue of the limited
resources available.
The increase in the load density increases the current density in same proportion
which in turn, increases the need of more transforming centers, so a proper strategy is
required to be carried out in order to overcome the drawbacks of low voltage
distribution system.
In existing LVDS, lengthy 11 kV LT lines are laid Minimization of Losses by
Implementing High Voltage Distribution System employing three-phase DTRs of
capacity 630kVA, 500kVA, 400kVA, 100 KVA or 63kVA feeding large number of
consumers resulting in poor tail end voltages, high losses, frequent faults, cuts. DTR
failures causing loss besides huge public outcry. To overcome all these problems,
implementation of high voltage distribution system is considered as the best move to
enhance the performance of distribution system
02.00 ADOPTION OF HIGH VOLTAGE DISTRIBUTION SYSTEM (HVDS)
-
7/28/2019 DPR for HVDS at Ellahibagh_final
6/25
2
Minimization of Losses by Implementing High Voltage Distribution System
The losses in Indian Power System are around 51.80%% and are inherent during the
processing and delivery of power in existing distribution network. Switching over to three
phase HVDS maintains better voltage profiles and reliability of supply to the consumers. In
HVDS, power is distributed mainly through high voltage lines. This system employs the
combination of 11KV three-phase and single phase configuration small capacity
distribution transformers (5KVA, 6.3kVA, 10KVA, 16KVA, 25kVA) extending supply to 3 to
5 consumers with least low tension lines, preferably insulated overhead cable system
thereby, reducing losses, overloading and distribution transformer failure and improving
the efficiency of the system. This system selects copper wound transformers with very
less no-load loss in order to provide mechanical stability to winding
02.01 Conversion of LVDS into HVDS
To improve quality of supply and to reduce losses HVDS is recommended. HVDS is
constructed by converting the existing low tension lines to single phase system. 11 KV
lines are extended to as nearer to the loads as possible and erect small size either single
phase transformers or three phase transformers of available capacities with NO or least
LT line.Unavoidable short LT lengths to be covered by insulated wires like ABC (AerialBunched Cables). HVDS can be single phase and one neutral (continuous neutral from
sub-station), two-phase two-wire (rigidly earthed natural system) or three-phase small
rating transformers with three-phase high voltage system. With three phases to neutral
system, a continuous earth wire is required to be drawn from 11KV/0.430kV sub-station
and earth wire is to be earthed at all the poles. The neutral of the distribution transformer
is also earthed on high and low voltage sides. On the secondary side of the transformer,
voltage is 230V. The single phase transformer used can be oil filled or dry type.
02.02 Benefits with HVDS
The registered customers feel ownership not allowing others to meddle with low
tension network. Thus, the chances of running unauthorised hooking of loads will be
prevented due to short and insulated low tension lines minimising pilferage and
improving quality of supply. Due to reduction in KVA capacity, voltage drop on low voltage lines is negligible
thereby, improving voltage profile.
The excellent voltage will reduce installation of automatic voltage regulators & thus will
minimize fluctuations in voltages.
In the event of any fault, only limited no. of customers will be affected increasing the
reliability of the system.
Less space is required for transformer installation and routing of HT
transmission line
-
7/28/2019 DPR for HVDS at Ellahibagh_final
7/25
2
Minimization of Losses by Implementing High Voltage Distribution System
Failure of distribution transformer will be eliminated due to the short length low tension
lines and use of aerial bunched cables.
In case of damage of unit, failed unit can be replaced quickly and it will be easy to
erect and transport too.
Meter tampering becomes very difficult
High quality of power supply earns total consumer satisfaction.
Smaller size conductors can be employed and accidents due to touching of snapped
conductors reduced as the breaker trips at substation
Capacities of single phase units can be selected to avoid the laying of low tension
lines because these units are available in ratings from 5 KVA to 25 KVA. Also, single
phase loads will not contribute to the high unbalances so they can be connected on
individual transformers dividing them.
Unauthorized connections get totally eliminated in HVDS & Consumers become
accountable and responsible. The enclosed Figure 1 gives elementary idea of how
HVDS eliminates unauthorized connection in such system as compared to LVDS.
Thus by implementing HVDS, a continuous watch can be kept on the reduction in input
units and the amount of energy saved in terms of money thus, the billing and collection
efficiency increases and the problem of frequent failure of power due to failure of
distribution transformer will be reduced considerably.
02.03 HVDS Implemented in Areas
HVDS in Kashmir region has been implemented in 90 Feet road Soura of Electric Division
IV, of Hawal Sub-division where high voltage line is extended to the load point and
supply is tapped off thru three-phase or single phase HVDS transformers. Under this low
tension lines were completely replaced by way of installing 28Nos of single phase HVDS
units & One No. 25kVA HVDS unit. These all measures were adopted only to improve the
viability of the distribution system.
H.V.D.S.besides can be implemented straight away in places where new constructions
are emerging & thus those areas can be electrified in view of its technical superiority.
03.00 ELECTRIC POWER INSTALLED CAPACITY, ITS AVAILABILITY &
CONSUMPTION
-
7/28/2019 DPR for HVDS at Ellahibagh_final
8/25
2
Minimization of Losses by Implementing High Voltage Distribution System
The total energy input for the financial year 2012-13 for sub-division has been viewed to
be 1865.81 & as such seem to be having an increasing trend . The increasing trend in
energy consumption can be attributed to various factors like increase of connected load &
consequent maximum demand & not but the least unauthorized use of electric power by
consumers remaining unaccounted because of easy access to LT network & thus
resorting to illegal pilferage of power & loss in revenue thereafter.
The Electric sub-division Hawal looks after HT/LT network of all feeders emanating from 8
receiving stations enlisted below:
S.NO RECEIVING STATION NO. OF FEEDERS
01 SOURA (2X10 + 6.3) 05
02 BAGWANPORA (2X10) 03
03 BAMK(3X6.3) 0504 ELLAHIBAGH (2X6.3) 02
05 OWNTABAWAN (2X6.3) 02
06 LAL BAZAR (10 + 5) 03
07 ZOONIMER (1X6.3) 01
08 MUGHAL MASJID (2X10)06(ONLY 2 FEEDERS
PERTAINING TO HAWAL)
The sub-division has a consumer base of total consumer base of 20,887 of various
categories, domestic, commercial, State/Central, Industrial, Bulk etc. The numbers of total
domestic consumers are 17,786 who are provided power supply mostly thru LT network
from local distribution transformers. However, after detailed survey was conducted in
Jurisdiction of Hawal sub-division it was decided that a pilot project in form of HVDS be
selected to reduce Transmission & commercial losses to a certain level. The area
selected for implementation of HVDS was 90 feet road Soura. 28Nos. of 16kVA HVDS
units, on single pole structures with 2-phase 11kV HT supply transforming into 230V that
is directly provided to consumers thru 20sq. mm twin core cable. The meter box fixed to
same pole houses 3 Nos. of single phase meters is sealed from outside. After success of
this project it is proposed that the scheme be extended further for achieving desired
objectives. The objective of less distribution losses due to less LT conductor
length and lower current on the HT side was achieved.
-
7/28/2019 DPR for HVDS at Ellahibagh_final
9/25
2
Minimization of Losses by Implementing High Voltage Distribution System
figure showing HVDS implementation in 90 Feet Road
-
7/28/2019 DPR for HVDS at Ellahibagh_final
10/25
2
Minimization of Losses by Implementing High Voltage Distribution System
04.00 IMPLEMENTATION STRATEGY
The total No. of Installations to be covered in the said scheme is 432. Keeping a provision
of 4 kW/consumer including load growth, it has been proposed to install 111 No.s of 25
kVA Capacity, 3-Phase 11KV/230V Copper Wound HVDS Units. These units will be
mounted on frame of 9m long SP-33 Steel Tubular Poles, along with 6X1 Panel type
meter boxes fitted with suitable accessories like MCBs, Single Phase Digital Energy
Meters etc. The consumer shall be provided with 20 mm Twin core PVC Flat Aluminum
Cable as service line. The areas proposed for implementation of HVDS scheme are listed
in Chapter 07.00.
The existing HT line (Feeder 5) emanating from receiving station Soura is proposed to
be extended further along 90 feet road Soura. The feeder terminates on road at Lane No
06 of Iqbal Colony Soura that besides marks end of existing HVDS. It is proposed to
extend feeder further for lanes & by lanes on existing areas were complete
implementation of HVDS was missed in earlier phase. Complete details are reproduced
below 06.01. LT lines existent in said areas from various distribution transformers
tabulated below will after implementation of this scheme get completely eliminated. It is
proposed 0.05ACSR conductor will be utilized for HT lines on main roads while ABC
Cables of various sizes terminated thru heat shrinkable termination kits will be used in
lanes & by lanes. The conductor formation & clearance of 11kV lines will be maintained as
per the standard enclosed in figures A-16 & A-13. Suspension of ABC cables in lanes &
by lanes is proposed to be as per figure 2(a) enclosed here in list of drawings. Complete
details of earthing arrangement of sub-stations & HT poles are enclosed here in figure F-
10 & F-12. 11kV link sets on HT frame are to be incorporated along various sections to
isolate those areas on occurrence of faults & to facilitate charging of rest of feeder.
Given the volume of investment, a phased approach is to be adopted to cover the entire
population under HVDS. To begin with, defaulting consumers and pilfer prone pockets
are identified and connected load of each load block comprising such errant consumers
worked out. Priority of implementation of HVDS is first given to upcoming areas wherenew construction along with installation with huge load blocks is observed. Losses
attributable to pilferage will reduce significantly, thereby making the investments
productive, while voltage conditions improved, thereby arresting damage of transformers.
More significantly, compelling circumstances created for unauthorized consumers to
regularize their supply, as the HV lines will be out of bounds for dishonest abstraction of
electricity. Elimination of pilferage will lead to virtual nullification of the peak power loss,
thereby freeing up capacity to serve regular loads. Concurrently, consumer accountability
will increase, resulting in moral ownership of the transformer dedicated to a group ofconsumers. The illustration is depicted in fig-1 enclosed here.
-
7/28/2019 DPR for HVDS at Ellahibagh_final
11/25
2
Minimization of Losses by Implementing High Voltage Distribution System
Table: Abstract of Implementation (Sub-div hawal)
S.No Particulars No.
1. No. of Installations 432
2. No. of HVDS Units 111
3. No of Consumers per HVDS Unit 4
4. No. of 1-Phase Digital KWh Meters 432
5. Average Load per Consumer (kW) 6
Table: Abstract of Implementation (Sub-div Rainawari)
S.No
Particulars No.
1. No. of Installations 275
2. No. of HVDS Units 69
3. No of Consumers per HVDS Unit 4
4. No. of 1-Phase Digital KWh Meters 275
5. Average Load per Consumer (kW) 6
-
7/28/2019 DPR for HVDS at Ellahibagh_final
12/25
2
Minimization of Losses by Implementing High Voltage Distribution System
05.00 BRIEF DESCRIPTION OF WORK AND ELECTRICAL SYSTEM DESIGN
CRITERIA
05.01 The prevailing practice of HVDS in Kashmir Valley is to use a single conductor or
two conductors for HVDS transformer. The other terminal of LT winding of the single-
phase transformer is grounded locally. This connection is nothing but Single Wire Earth
Return System (SWER). An elementary idea of SWER system is enclosed here in figure
title SWER System. REC has recently issued Standard Technical Specification
(Specification No. 75/2005) for 5kVA HVDS Transformers, wherein it has been made clear
that in case of single phase 11/sqrt (3) HVDS transformers, 3 ph., 4 Wire system at 11kV
(with separate neutral wire running continuously from 33/11kV sub-station) shall be
adopted and proper earthling of neutral wire separately at both ends shall be ensured. In
view of this following guideline for construction of HVDS substations have been issued:
The standard rating of HVDS transformers shall be 5, 6.3, 10 & 16kVA for 11/3
(Phase to Neutral) transformers and 10 & 16kVA for 11kV (Phase to Phase)
transformers. (REC Specification no. 50/1987 & 75/2005)
5kVA transformers will be of great help in feeding small habitations were small loads
are to be supplied in rural areas. Also 5kVA transformers can be used as a dedicated
transformer for every consumer in urban area. (Foreword to REC Specification no.
75/2005)
The 3 phase and 2 phase HVDS transformers shall be fed from 3 wire 11kV system inconventional manner. However in case of single phase HVDS transformers (11/3 kV
primary), 3 Ph, 4 wire system at 11kV with separate neutral wire running continuously
from 33/11kV sub-station shall be adopted and proper earthling of neutral wire
separately at both ends shall be ensured. (REC Specification no. 50/1987 & 75/2005)
The transformers shall be mounted on single poles. The neutral wire shall be of
minimum size ACSR/AAAC recommended for 11kV by REC (eg ACSR 7/2.11mm,
20mm2 aluminum area)( REC Specification no. 1/1970 revised 1993)
The neutral shall be run on LT shackle insulators installed on 11kV pole directly
through D-clamps. The point of attachment of neutral wire shall be 800mm
below lowermost 11kV phase conductors.( REC Specification no. A-16)
The single phase HVDS transformers shall be distributed equally on the 3
phases of 11kV system to ensure balancing of load at 33/11kV substation
feeding the single phase HVDS system
-
7/28/2019 DPR for HVDS at Ellahibagh_final
13/25
2
Minimization of Losses by Implementing High Voltage Distribution System
06.00 PROPOSED OVERALL SYSTEM PREVIEW
06.01 The following areas have thereby been selected for HVDS implementation:A) Name of Existing Distribution transformer & Feeder :: 400kVA 90 Feet Road
(F3 of R/s Soura)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS (25kVA)
units selected
Total No. of consumers
on proposed HVDS
01 90 Feet road near Chinar 02Nos.7 consumers & a 3-phase
installation
02Towards Owntabawan
prior to Chinar Tree01Nos. 04 consumers
03 90 Feet road near shops 03Nos. 10 consumers
04 Prior to Abu bakr Lane 01No. 05 consumers
B) Name of Existing Distribution transformer & Feeder :: 400kVA Azad Colony
(F1 of R/s Ellahibagh)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) units
selected
Total No. of consumers
on proposed HVDS
01 Iqbal colony lane no. 02 04Nos. 16 consumers
02Iqbal colony lane no. 03 05Nos. 17 consumers.
03 Iqbal colony lane no. 05 05Nos. 17 consumers.
04 Iqbal colony lane no. 06 03No. 12 consumers
05 Shah faisal colony lane no. 01 03Nos. 10 consumers
06 Shah faisal colony lane no. 02 05Nos. 20 consumers
C) Name of Existing Distribution transformer & Feeder :: 630kVA Housing
Colony (F1 of R/s Ellahibagh)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) units
selected
Total No. of consumers
on proposed HVDS
01 Along Road on 90 Feet road 04 Nos. 15 consumers
02 Towards Housing Colony 02 Nos. 08 consumers.
03 Adjacent to govt. Park 06 Nos. 22 consumers.
04 Adjacent PHE pump 02No. 06 consumers
-
7/28/2019 DPR for HVDS at Ellahibagh_final
14/25
2
Minimization of Losses by Implementing High Voltage Distribution System
05Adjacent to 630kVA Housing
Colony08Nos. 30 consumers
06Ahead of 630kVA Housing
Colony04 Nos. 16 consumers
07Prior to 400kVA Housing
colony07Nos 28 consumers
08 Other side of park 02Nos 08 Consumers
D) Name of Existing Distribution transformer & Feeder :: 250kVA UsmaniaColony (F1 of R/s Ellahibagh)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) units
selected
Total No. of consumers
on proposed HVDS
01 Usmania colony lane no. 03 02Nos. 08 Consumers
02 Lane Masjid Aashiya 02Nos. 08 Consumers.
03On road adjacent to existing
250kVA Usmania Colony01Nos. 04 consumers.
04 Usmania Colony Lane - A 09No. 35 consumers
F) Name of Existing Distribution transformer & Feeder :: 630kVA Village (F1 ofR/s Ellahibagh)
S.No.
Areas to be electrified inproposed HVDS scheme
No. of HVDS
(25kVA) unitsselected
Total No. of consumerson proposed HVDS
01 Towards Habbak Grid 11 Nos. 46 Consumers
02 Near Airtel Tower on road 02 Nos. 9 Consumers.
G) Name of Existing Distribution transformer & Feeder :: 250kVA al-NoorColony (F1 of R/s Ellahibagh)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) unitsselected
Total No. of consumers
on proposed HVDS
01 Near Orange Crche 04Nos. 16 Consumers
02In vicinity of 250kVA Al-
Noor05 Nos. 20 Consumers.
03Houses in vicinity of Open
area09 Nos. 34 consumers.
-
7/28/2019 DPR for HVDS at Ellahibagh_final
15/25
2
Minimization of Losses by Implementing High Voltage Distribution System
Areas to be electrified in proposed HVDS scheme of S/D Rainawari
A) Name of Existing Distribution transformer & Feeder :: 250kVA Sheeshbagh(F3 of R/s Habbak)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) units
selected
Total No. of consumers
on proposed HVDS
01 Along Lanes & By-lanes 11 Nos. 45 Consumers
B) Name of Existing Distribution transformer & Feeder :: 100kVA Green Colony(F3 of R/s Habbak)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) units
selected
Total No. of consumers
on proposed HVDS
01 Along Lanes & By-lanes 6 Nos. 24 consumers
C) Name of Existing Distribution transformer & Feeder :: 250kVA AkhzarAvenue (F3 of R/s Habbak)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) units
selected
Total No. of consumers
on proposed HVDS
01 Along Lanes & By-lanes 10 Nos. 38 consumers
D) Name of Existing Distribution transformer & Feeder :: 250kVA Burzubagh (F3
of R/s Habbak)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) units
selected
Total No. of consumers
on proposed HVDS
01 Along Lanes & By-lanes 17 Nos. 68 consumers
E) Name of Existing Distribution transformer & Feeder :: 250kVA MadinaColony (F3 of R/s Habbak)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) units
selected
Total No. of consumers
on proposed HVDS
01 Along Lanes & By-lanes 10 Nos. 40 consumers
F) Name of Existing Distribution transformer & Feeder :: 400kVA Rangpora (F3of R/s Habbak)
S.No
.
Areas to be electrified in
proposed HVDS scheme
No. of HVDS
(25kVA) units
selected
Total No. of consumers
on proposed HVDS
01 Along Lanes & By-lanes 15 Nos. 60 consumers
-
7/28/2019 DPR for HVDS at Ellahibagh_final
16/25
2
Minimization of Losses by Implementing High Voltage Distribution System
07.00 TECHNICAL DESCRIPTION
Based on the preliminary field survey conducted & above discussed
considerations following are the list of materials along with their brief technical
specifications:
07.01 Aerial Bunched Cable
Aerial Bunched Cable (11 KV) weather proof of Sizes 3X120sq.mm. 3x95sq.mm,
3x70sq.mm, 3x50sq.mm, 3x35sq.mm can be used for 11kV HT tap lines,
proposed for lanes & by lanes where HVDS is proposed.
07.02 Outdoor type Distribution Transformers
The standard proposed ratings of transformers utilised can be 10, 16, 25kVA. Oil
Immersed naturally cooled 3 phase 11 kV/433 - 250 V distribution transformers for
outdoor use pole mounted.
07.03 Cable Boxes
The transformer shall be fitted with suitable LV cable box having non-magnetic
material gland plate with appropriate sized single compression brass glands on LV
side for cable termination.
07.04 FITTINGS
The following standard fittings shall be provided:
Rating and terminal marking plates, non-detachable.
Earthing terminals with lugs
Lifting lugs for main tank and top cover
Terminal connectors on the HV/LV bushings {for bare terminations only}.
Thermometer pocket with cap.
Air release device
HV bushings - 3 Nos.
LV bushings - 4 Nos.
Pulling lugs
Radiators - No. and length to be mentioned (as per heat dissipation
calculations)
Lightning arrestors on HT side - 3 No.
Prismatic level gauge. Drain cum sampling valve.
-
7/28/2019 DPR for HVDS at Ellahibagh_final
17/25
2
Minimization of Losses by Implementing High Voltage Distribution System
Top filter valve
Oil filling hole and drain plug on the conservator.
Silica gel breather
Base channel 75x40 mm
Pressure relief device or explosion vent.
7.5 Steel tubular poles for overhead power lines
Steel Tubular stepped type/swaged type poles for overhead power lines
confirming to IS: 2713 of 1980 are proposed. Pole shall be provided with earthing
arrangements. A though hole of 14 mm diameter be provided in each pole at a
height of 300 mm above the planting depth. The pole shall be quoted with black
bituminous paint confirming to IS: 158 of 1968 read with latest amendments
throughout, internally and externally upto level which goes inside the earth. The
Remaining portion of the exterior shall be painted one coat or red- oxide primer as
specified in IS; 2074 of 1979 read with latest amendments
Designation as per IS: 2713 Part II
1. 410-SP-56 11 Mtrs. Long S.T. pole.
2. 410-SP-33 9.0 Mtr. Long ST Pole.
7.6 11 KV D.O. fuse unit (one set of 3 nos.)
The D.O. Fuses are intended for use on transformers for protection/isolation of the
same during overload or fault conditions. the drop out fuse shall conform to IS:
9385 (Part- I) to III) as amended from time to time. The drops out fuses are
required with Post Insulators. These shall be suitable for mounting on the
structure. The bracket/channel hardware for DO Fuses shall be provided with
adequate sizes of nuts, bolts and washer for mounting on the structures. The rated
voltage shall be 11KV for 11KV DO Fuses. The rated lightning impulse withstandsvoltage both for positive and negative polarities shall be as given below:
To earth and between poles 1015KV Peak
Across the isolating distance of fuse base 85KV Peak
RATED ONE MINUTE POWER FREQUENCY WITHSTAND VOLTAGE (DRY
AND WET) VALUES FOR THE FUSE BASE
a) To earth and between poles : 28KV Peak
b) Across the isolating distance of fuse base : 32KV PeakThe rated breaking capacity shall be 8KA (A symmetrical).
-
7/28/2019 DPR for HVDS at Ellahibagh_final
18/25
2
Minimization of Losses by Implementing High Voltage Distribution System
7.7 11 KV A.B. Switch (G O Switch).
The 11KV AB switches shall conform to IS: 9920 (Part-I to IV). The 11KV Air
Break Switches are required with two poles in each phase. The AB Switches shallbe with phase coupling shaft, operating rod and operating handle. It shall be
manually gang operated and vertically break and horizontal mounting type. a
normal current rating of 400 Amps and for continuous service at the system
voltage specified as under:
11 KV AB Switch : 11KV + 10% continuous 50 C/s solidly grounded earthed
neutral system
The complete set of three phase AB Switches shall have stacks of post
insulators. 11KV AB Switches : 3 No. 11KV Post Insulator per stack
7.8 11 KV Gapless Lightening Arrestors (Station Type &
Line Type).
Single phase outdoor metal oxide type gapless surge arresters for use in
effectively earthed system with the transformer neutral effectively earthed with
normal voltage of 11KV for 9KV Lightning arrestors. The rated voltage of Arrestors
shall be 9KV (rms) for 11KV system. Current impulse withstand level The 9 KV
arrestors shall withstand 18 impulse of long duration current with a peak level of
75 Amp & duration 1000 micro secs. 30KV arrestors shall meet the duty
prescribed in line discharge Class-I of IEC TC-37. The arrestor for 11KV system to
be provided with a suitable disconnecting device. This shall be connected in series
with the ground lead and should not affect the sealing system of the arrestor. The
disconnecting device shall conform to the requirement specified in IS:3070 (Part-II)
1993 & IEC 99-4 (1991-II) clause 5.12, 7.6.3.
-
7/28/2019 DPR for HVDS at Ellahibagh_final
19/25
2
Minimization of Losses by Implementing High Voltage Distribution System
08.00 COST ESTIMATION
The detailed quantities of various works to be executed under the scheme have
been worked out based on preliminary field survey and above discussed
considerations details of which are enclosed. A tentative cost estimate has been
prepared for the scheme mainly on the basis of cost data available in Electric
Division-IV, Khanyar. The detailed cost estimate is enclosed herewith.
Annexure A: Estimate for HVDS Units.
Tentative Estimate for Design, Supply, Testing & Commissioning of 25 KVA 11 KV/240VHVDS Units in 90 feet Road & Ellahibagh
S.NoParticular (Supply ,erection ,testing &
commissioning of following items)Unit Qty
Rate/Unit Rate/Unit
(Rs) (Rs)
1
Supply, Erection, Testing & Commissioningof 9 Mtr Long Steel Tublar YST 240 of 155-1161 of design as per IS-2713, 410 SP33as per IS-2713.
No 412 9500.00 3914000.00
2
Digging of pit disposal of earth andproviding and laying of cement concretingin1:2:4 ratio for bottoming of pole structure
1' above 6" from below pole base uptoground level &1 around the pole in M-15mix pole upto ground level)
Job 206 1500.00 309000.00
3
Providing, Erection, Fixing, Testing &Commissioning of MS Channel Iron75x40x40x6' long (206 No.) duly fabricatedas per site requirement and painted withtwo coats of Red oxide and Al. Paint.
Kg 2682.12 60.00 160927.20
4
Providing, Erection, Fixing, Testing &Commissioning of MS Angle Iron 50x50x6'long (206 No.) duly fabricated as per siterequirement and painted with two coats of
Red oxide and Al. Paint.
Kg 3386.64 60.00 203198.40
5Providing & Fixing of 11 KV Pin Insulatorswith pins
No 412 90.00 37080.00
6Providing & Fixing of GI Earthing Strip 25x3mm.
Kg 2060 80.00 164800.00
7Providing & Fixing of pipe earthing /Rodearthing complete as per REC standard
Kg 206 1500.00 309000.00
8Structure painting & fluorscent displaywriting of poles
No 206 100.00 20600.00
9 Providing & Fixing of Earthing Boots. No 2556 50.00 127800.00
10
Providing & Fixing of PG clamps for making
connections at take off points. No 206 40.00 8240.00
-
7/28/2019 DPR for HVDS at Ellahibagh_final
20/25
2
Minimization of Losses by Implementing High Voltage Distribution System
11Providing & Fixing of Guys along with guyinsulators, Guy rods with turn bucklescomplete.
No 20 1500.00 30000.00
12Providing & Fixing of MS Channel iron75x50x50x6 mm 9 long for transformer dulyfabricated & welded with pole.
kg 24139.1 60.00 1448344.80
13 Providing & Fixing of lighting arrestor set Set 206 1800.00 370800.00
14 Providing & Fixing of Drop out fuse set No 206 1200.00 247200.00
15 Providing & Fixing of G.O.S No 206 3800.00 782800.00
16
Providing, Erection, Mounting, Poistioning,Testing & Commissioning includingscaffolding sets of 25 KVA 11 KV/240Copper wound HVDS transformer.
No 206 20000.00 4120000.00
17Providing, Laying, Fixing & ConnectingService line 50 mm single core Al.cable
Km 3 52000.00 156000.00
18 Providing & Fixing Meter Box (Panel Type6x1 Meters) with Bus Bars etc.complete No 206 4200.00 865200.00
19Providing, Laying, Fixing & ConnectingService line of 10 mm Twin core Al. flatcable.
Km 12 15000.00 180000.00
20 Providing & Fixing of Anti Climbing device No 206 100.00 20600.00
21 Providing & Fixing of Danger plate No 206 50.00 10300.00
22Providing & Fixing of 40/63 Amp MCB DP(ISI Mark)
No 206 250.00 51500.00
23 Earthing of Poles & Substation Complete. Job 206 3500.00 721000.00
24 Providing & Fixing of Sundry Nuts, Bolts,Washers, etc,. Kg 500 80.00 40000.00
25Providing & fixing of MS Angle Iron braces(50x50x6mm 10m long) duly fabricated.
Kg 283.889 60.00 17033.32
Total 14315423.72
-
7/28/2019 DPR for HVDS at Ellahibagh_final
21/25
2
Minimization of Losses by Implementing High Voltage Distribution System
Annexure B: Estimate for HT Tap Line for HVDS Units.
Tentative Estimate for Supply, Erection, Testing & Commissioning of 11KV HT Linefor 25 KVA 11 KV/240V HVDS Units in Ellahibagh & 90 Feet Road Soura
Part (A)
S.No.Particular (Supply, Erection, testing &
commissioning of following items)Qty. Unit
Rate/uni
tAmount
1
Providing, Erection, Testing &Commissioning of 9mts Steel Tubularpoles SP-33 complete with base plateand top cap including fabrication of polesite requirement, loading, un-loading,dragging, carriage upto working site asper IS Standard.
60 Job 14300.00 858000.00
2
Digging of pit disposal of earth andproviding and laying of cement
concreting in1:2:4 ratio for bottoming ofpole structure 1' above 6" from belowpole base upto ground level &1 aroundthe pole in M-15 mix pole upto groundlevel)
60 Job 1700.00 102000.00
3
Providing, Erection, fixing, testing &commissioning of MS Channel Iron75x40x40x6' long (40 No.) for fabricatingV-Cross as per site requirement andpainted with two coats of Red oxide andAl. Paint.
400 Kg 74.00 29600.00
4Providing & Fixing of U-Clamps for fixingof Pin insulators of flat iron 35x4 mm.
160 kg 74.00 11840.00
5 ABC Cable of Sizes 70/50/35 sq.mm 15 kms 9000.00 135000.00
6 11KV Pins along with Pin insulators. 180 No. 165.00 29700.00
7Providing, Fixing, Testing &Commissioning of earthing rods
60 No 480.00 28800.00
8
Providing, Fixing, Testing &Commissioning of Nuts & Bolts /washers(Galvanized of sorts)
165 Kg 92.00 15180.00
9Providing, Fixing, Testing &Commissioning of GI Wire for earthing.
150 Kg 90.00 13500.00
10
Providing, Erection, Testing &
commissioning of ACSR 0.05 conductor(Rabbit) Conductor as per latest ISStandard, including loading, un-loading,carriage upto working site.
7.20 Km 38000.00 273600.00
11Painting of poles/structure with 2 coats ofAl. & red oxide paint.
60 Job 300.00 18000.00
12 Earthing of Poles Complete. 60 Job 1750.00 105000.00
13
Providing & Fixing of Guys along withguy insulators, Guy rods with turnbuckles complete.
20 No. 1500.00 30000.00
Tota
l1650220.0
0
-
7/28/2019 DPR for HVDS at Ellahibagh_final
22/25
2
Minimization of Losses by Implementing High Voltage Distribution System
Annexure C: Estimate Single Phase Digital Energy Meters for HVDS Units.
Tentative Estimate for Supply, Erection, Testing & Commissioning of Single
Phase LT Digital Energy Meters for HVDS at University Campus, Hazratbal.
S.No.Particular (Supply, Erection, testing &
commissioning of following items)Qty. Unit
Rate/unit
(Rs.)
Amount
(Rs.)
1
Supply, Erection, Testing &
Commissioning of Single Phase,
AC, 2-Wire LT Digital Energy
Meters 240V, 50Hz, CI.1.0, kWh of
SPEM 01 Type as per IS:13779
standard along with 4 No.'sTamper proof Departmental Seals
and other accessories like Conduit,
Binding Wire, Aluminum Lugs,
PVC Tape etc. for LT Connections.
264 No.'s 1500.00 396000.00
Total: 396000.00
Table: Abstract of Total cost.
S.No Particulars Amount (Rs.)
1 On Account of 25 kVA HVDS Units.11722418.92
2 On Account of HT Tap Line for HVDS Units.1650220.00
3 On Account of 1-Phase Digital kWh Meters648000.00
Total:14020639
This is however only a tentative cost of the scheme based on preliminary data
which may vary during actual execution of the scheme.
-
7/28/2019 DPR for HVDS at Ellahibagh_final
23/25
2
Minimization of Losses by Implementing High Voltage Distribution System
09.00 APPLICABLE STANDARD:-
All the cables shall conform to the requirements of following standards with latest
Amendments, if any
S.No. IS Code Description
IS:7098(Part-2) 1985 with
latest amendments
Cross linked Polyethylene insulated Sheathed
Cables for working voltage from 3.3 KV up to and
including 33KV
IS:8130-1984Specification for conductors for Insulated electriccables
. IS:5831-1984Specification for PVC Insulation and sheath of
electric cables.
IS: 3975-1979
Specification for mild steel wires, strips and taps for
Armouring cables.
IS:10810-1984 Methods of test for cables.
IS:4905-1968 Methods for random sampling
IS:10418-1982 Wooden drum for electric cables
IS-7098 XLPE Cable
IS- 10810/1984 Methods of test for cables.
IS 8130/1984 Conductors for insulated cables
IS 10418/1982 Drums for electric cables
IS- 5831-1984Specification for PVC Insulation and sheath ofelectric cables.
IS-335 Specification for Transformer Oil
IS-5 Specification for colors for ready mixed paints
IS-104 Ready mixed paint. brushing zinc chromate, priming
IS-2099 Specification for high voltage porcelain bushing
IS-649Testing for steel sheets and strips and magneticcircuits
IS-457 Dimensions for clamping arrangements for bushingsIS-7421 Specification for Low Voltage bushings
IS-.347 Specification for Outdoor Bushings
IS-5484 Specification for Al Wire rods
IS-9335 Specification for Insulating Kraft Paper
IS-6600 Guide for loading of oil Immersed Transformers
I S-2362Determination of water content in 011 for porcelainbushing of transformer
IS-6162 Paper covered aluminum conductor
IS-6160Rectangular Electrical conductor for electricalmachines
-
7/28/2019 DPR for HVDS at Ellahibagh_final
24/25
2
Minimization of Losses by Implementing High Voltage Distribution System
IS-5561 Electrical power connector
IS-6103Testing of specific resistance of electrical insulatingliquids
IS-6262Method of test for power factor and dielectricConstant of electrical insulating liquids
IS-6792 Determination of electrical strength of insulating oil
IS-10028 Installation and maintenance of transformers.
10.0 Conclusion
-
7/28/2019 DPR for HVDS at Ellahibagh_final
25/25
Minimization of Losses by Implementing High Voltage Distribution System
The HVDS scheme has generated a learning curve, leading to formulation of a
new strategy of energy conservation and demand curtailment. This novel
approach is being pursued so as to reduce energy wastage and optimize the
power intake. Initial results indicate that the energy saving can be as much as
70%, even without reengineering of the suction and delivery system. Because of
reduced consumption, the consumers benefits by reducing his monthly
expenditure on electricity. An important corollary is that consumers support the
process and respond spontaneously to the change, which produces long term
gains to them and the utility.