aa 78 Maulana Ahmed Ali Road

Near Minar-e-Pakistan Lahore, Pakistan

COMMENCEMENT OF

CONSTRUCTION Dr Engr Javed Yunas Uppal

0300-410-7717 [email protected]

Dr A Q Khan Hospital

Location Plan

Dr A Q Khan Hospital

Perspective View

Mohsin-e Pakistan

Dr A Q Khan

Dr A Q Khan Hospital

Salient Features

Floor area = 190,000 sft Basement

Lower Ground Floor

Upper Ground Floor

First Floor

Second Floor

Third Floor

Site Layout Plan

Basement Floor Plan

Basement Floor Plan Functions 149’-6”x189’-6”= 28,474 sft

Basement Parking for 35 cars + 70 motor cycles

Generator Electrical Room, Mechanical Room, Storage, Lifts 4 nos, Stairs 3 Nos,

Male supporting Female supporting

Security, Drive ways

Lower Ground Floor Plan

Lower Ground Floor Functions 149’-6”x189’-6”= 27,163 sft

Lower Ground Floor

Pathology Lab, Blood Bank, ECG, CT Scan,

X-ray, Ultra Sound, Heart and Lung Lab,

Pharmacy, CSSD,

Laundry, Waitin,g Ramp

Upper Ground Floor Plan

Upper Ground Floor Functions 149’-6”x189’-6”= 29,851 sft

Upper Ground floor

Consulting, Waiting, Lobby,

Entrance, Executive Check-up,

Emergency, Minor OT,

Emergency Theatres,

ENT, Surgery, Supplies

First Floor Plan

First Floor Functions 27,427 sft

First Floor

Male Female Surgical Wards, Paeds Ward,

CCU, ICU, Neo Natal, Male Orthopaedic,

X-ray, General Ward, Recovery Monitoring,

Pre Anesthesia, Labour Room

Ots, Anesthesia, Gynae

Second Floor Plan

Second Floor Functions 27,887 sft

Second Floor

Private Rooms 16 Nos,

VIP Rooms 16 Nos,

Male Medical Ward,

Female Medical,

Ward, Isolation

Third Floor Plan

Third Floor Functions 27,887 sft

Third Floor

Male Ward, Female Ward,

Beds Normal -23 Nos

Beds Upper- 6 Nos

Cross Section

Cost Up to Foundation Exc for Foundation 540,000 cft @ 3.50 = Rs 1,890,000 Excavation trenches 5,700 cft @ 4.00 = Rs 22,800 Filling with sand 40,000 cft@ 6.00 = Rs 240,000 Eartfill 10,000 cft @ 3.0 = Rs 30,000 Disposal earth outside 55,000 cft @ 2 = Rs 110,000 Laying earth within 480,000 cft @ 2 = Rs 960,000 Termite control 46,000 sft @ 1.5 = Rs 69,000 Lean concrete 1:4:8 13,000 cft @150 = Rs 1,950,000 RCC in foundation 75,000 cft @ 300 = Rs 22,500,000 Steel to upper gr floor 243,750 kg @ 125 = Rs 30,468,750 Total up to foundation

= Rs 58,240,550

Quantities Up to Foundation Cement = 13,885 bags x 530 = Rs 7,359,050

Sand = 35,200 cft x 6 = Rs 211,200

Aggregate = 70,400 cft x 35 = Rs 2,464,000

Steel = 243,750 kg x100= Rs24,375,000

Cost of Waterproofing in Foundation Waterproofing ret walls 12,500 sft @ 6= Rs 75,000

Waterproofing raft 28,000 sft @ 5 = Rs 140,000

Water stopper 1,000 Rft @ 15 = Rs 15,000

Brickwork in found 2,500 cft @ 100 = Rs 250,000

Total of Waterproofing in Foundatio = Rs 480,000

Quantities in Waterproofing Foundation

Membrane waterproofing at ret walls= 12,500 sft

Membrane waterproofing in raft = 28,000 sft

Water stopper = 1,000 Rft

Bricks = 35,000 Nos

Cost of Basement Slab, Lower Gr &

Upper Gr Fl Slab Grey Str RCC basement slab 75,000 cft @30 = Rs 22,500,000

lower gr & upper

gr fl slab

Steel basement 487,500 kg @ 125 = Rs 30,468,750

slab lower gr & upper

gr fl slab

Total up to upper ground floor = Rs 52,968,750

Quantities Up to Upper Gr Fl Slab Cement = 12,750 bags x 530 = Rs 6,757,500

Sand = 30,000 cft x 6 = Rs 180,000

Aggregate = 60,000 cft x 35 = Rs 2,100,000

Steel = 243,750 kg x 100= Rs24,375,000

First, Second and Third Floor Slabs RCC first floor 24,000 cft @ 300 = Rs 7,200,000

RCC 2nd floor 24,000 cft @ 300 = Rs 7,200,000

RCC 3rd floor 25,000 cft @ 300 = Rs 7,500,000

Steel 3 floors237,250 kg @ 150 = Rs 35,587,500

Grey str upto 3rd floor = 57,487,000

Quantities Up to 1st,2nd & 3rd Fl Slab Cement = 12,410 bags x 530 = Rs 6,577,300

Sand = 29,200 cft x 6 = Rs 175,200

Aggregate = 58,400 cft x 35 = Rs 2,044,000

Steel = 237,250 kg x100= Rs23,725,000