draft basic assessment report: the proposed …...the linear length of the existing eskom 132 kv...
TRANSCRIPT
BASIC ASSESSMENT REPORT
1
DRAFT BASIC ASSESSMENT REPORT:
The Proposed Development of a 132 kV Powerline and Associated
Sub-station on the Remaining Extent of the Farm Kapstewel No.
436, Remaining Extent of Farm No. 437, Remaining Extent of Farm
No. 588, Remaining Extent of Farm No. 589, Remaining Extents of
Portions 8 & 14 of Farm No. 589 and Remaining Extent of Portions 3
& 5 of the Farm Groenwater No. 453. The proposed
decommissioning and diversion of an existing Eskom Powerline on
the Remaining Extent of the Farm Groenwater No. 453 and
Remaining Extents of Portions 4 & 5 of the Farm Groenwater No.
453 within the Tsantsabane Local Municipality, Kimberley
Registration Division, Northern Cape Province.
Prepared for: Metsimatala CSP Solar Energy (Pty) Ltd
Prepared by: Enviroworks
August 2016
BASIC ASSESSMENT REPORT
2
Table of Contents
EXECUTIVE SUMMARY ...................................................................................................... 5 SECTION A: ACTIVITY INFORMATION ............................................................................. 13 1. PROJECT DESCRIPTION ........................................................................................... 13 2. FEASIBLE AND REASONABLE ALTERNATIVES ....................................................... 19 3. PHYSICAL SIZE OF THE ACTIVITY ........................................................................... 22 4. SITE ACCESS ............................................................................................................. 23 5. LOCALITY MAP ........................................................................................................... 23 6. LAYOUT/ROUTE PLAN ............................................................................................... 24 7. SENSITIVITY MAP ...................................................................................................... 24 8. SITE PHOTOGRAPHS ................................................................................................ 24 9. FACILITY ILLUSTRATION ........................................................................................... 25 10. ACTIVITY MOTIVATION .......................................................................................... 25 11. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES ............................ 38 12. WASTE, EFFLUENT, EMISSION AND NOISE MANAGEMENT .............................. 44 13. WATER USE ............................................................................................................ 47 14. ENERGY EFFICIENCY ............................................................................................ 47 SECTION B: SITE/AREA/PROPERTY DESCRIPTION ....................................................... 48 15. GRADIENT OF THE SITE ........................................................................................ 50 16. LOCATION IN LANDSCAPE .................................................................................... 51 17. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE ................. 51 18. GROUNDCOVER ..................................................................................................... 52 19. SURFACE WATER .................................................................................................. 52 20. LAND USE CHARACTER OF SURROUNDING AREA ............................................ 53 21. CULTURAL/HISTORICAL FEATURES .................................................................... 54 22. SOCIO-ECONOMIC CHARACTER .......................................................................... 57 23. BIODIVERSITY ........................................................................................................ 60 SECTION C: PUBLIC PARTICIPATION.............................................................................. 66 24. ADVERTISEMENT AND NOTICE ............................................................................ 66 25. DETERMINATION OF APPROPRIATE MEASURES ............................................... 66 26. ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES ............................. 68 27. COMMENTS AND RESPONSE REPORT ................................................................ 68 28. AUTHORITY PARTICIPATION ................................................................................ 68 29. CONSULTATION WITH OTHER STAKEHOLDERS ................................................ 69 SECTION D: IMPACT ASSESSMENT ................................................................................ 70 30. IMPACTS THAT MAY RESULT FROM THE PLANNING AND DESIGN, CONSTRUCTION, OPERATIONAL, DECOMMISSIONING AND CLOSURE PHASES AS WELL AS PROPSOED MANAGEMENT OF IDENTIFIED IMPACTS AND PROPSOED MITIGATION MEASURES .................................................................................................. 70 31. CONSTRUCTION PHASE........................................................................................ 73 32. OPERATIONAL PHASE ........................................................................................... 91 33. E NVIRONMENTAL IMPACT STATEMENT ........................................................... 106 SECTION E: RECOMMENDATION OF PRACTITIONER ................................................. 109 SECTION F: APPENDICES…………………………………………………………………….111
BASIC ASSESSMENT REPORT
3
(For official use only)
File Reference Number:
Application Number:
Date Received:
Basic assessment report in terms of the Environmental Impact Assessment Regulations, 2014, promulgated in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended.
Kindly note that: 1. This basic assessment report is a standard report that may be required by a competent authority
in terms of the EIA Regulations, 2014 and is meant to streamline applications. Please make sure that it is the report used by the particular competent authority for the activity that is being applied for.
2. This report format is current as of 08 December 2014. It is the responsibility of the applicant to ascertain whether subsequent versions of the form have been published or produced by the competent authority
3. The report must be typed within the spaces provided in the form. The size of the spaces provided is not necessarily indicative of the amount of information to be provided. The report is in the form of a table that can extend itself as each space is filled with typing.
4. Where applicable tick the boxes that are applicable in the report.
5. An incomplete report may be returned to the applicant for revision.
6. The use of “not applicable” in the report must be done with circumspection because if it is used in respect of material information that is required by the competent authority for assessing the application, it may result in the rejection of the application as provided for in the regulations.
7. This report must be handed in at offices of the relevant competent authority as determined by each authority.
8. No faxed or e-mailed reports will be accepted.
9. The signature of the EAP on the report must be an original signature.
10. The report must be compiled by an independent environmental assessment practitioner.
11. Unless protected by law, all information in the report will become public information on receipt by the competent authority. Any interested and affected party should be provided with the information contained in this report on request, during any stage of the application process.
12. A competent authority may require that for specified types of activities in defined situations only parts of this report need to be completed.
13. Should a specialist report or report on a specialised process be submitted at any stage for any part of this application, the terms of reference for such report must also be submitted.
BASIC ASSESSMENT REPORT
4
14. Two (2) colour hard copies and one (1) electronic copy of the report must be submitted to the competent authority.
15. Shape files (.shp) for maps must be included in the electronic copy of the report submitted to the competent authority.
BASIC ASSESSMENT REPORT
5
EXECUTIVE SUMMARY
Project description and location
Metsimatala CSP Solar Energy (Pty) Ltd intends to construct a 150 MW CSP (parabolic
trough) facility and associated substation on the Remaining Extent of the Farm Groenwater
No. 453 as well as Remaining Extent of Portions 4 & 5 of the Farm Groenwater No. 453. An
Environmental Authorisation application has been submitted for the above mentioned project
and a Scoping and EIA process is in progress.
This current proposed project for which Environmental Authorisation is now being applied for
this has two main objectives namely:
To construct a suitable 132 kV powerline and associated substation for the
transmission of the electricity generated from the proposed CSP facility to the
Managanore sub-station. The farm extents on which the powerline will be situated are
discussed under project location below.
To decommission and divert a section of the existing Eskom powerline, which currently
runs through the middle of the footprint of the proposed CSP facility, around its outer
boundary. The diversion of the existing powerline is compulsory in order to
accommodate and reroute the line around the footprint area of the proposed CSP
Plant. The farm extents on which the powerline will be diverted are discussed under
project location below.
The anticipated duration of the construction phase of the proposed project will be
approximately 24 months.
Proposed new 132 kV powerline and Metsimatala Solar substation
The linear length of the proposed new 132 kV powerline to be constructed will be
approximately 26 km. The proposed powerline will consist of a linear series of pylons
(towers) which will be situated approximately 100 m - 200 m apart. The exact distance
between and locations of pylons will be dependent on site specific terrain and soil conditions.
This will only be determined during the final design stage. The tower type to be used will be
determined during the final design stages of the powerline (based on load and other
calculations). It is however envisaged that the bird friendly Single Steel Pole tower type (e.g.
ESKOM D-DT 7641, D-DT 7649) will be used in combination with the Steel Lattice towers at
bend points and where greater distances need to be spanned. The Single Steel Pole tower
type is between 18 m and 25 m in height and the Steel Lattice tower type is between 25m
and 29 m in height. The distribution substation will be approximately 173 m X 173.5 m in size
and will be situated on the CSP facility footprint.
BASIC ASSESSMENT REPORT
6
Decommissioning and diversion of existing powerline
The linear length of the existing Eskom 132 kV powerline to be decommissioned is
approximately 3.4 km while the length of the proposed new 132 kV powerline (diverted
section) to be constructed around the outer boundary of the CSP facility is approximately 4.6
km. The diverted section will consist of a linear series of pylons (towers) which will be
situated approximately 100 m - 200 m apart. The exact distance between and locations of
pylons will be dependent on site specific terrain and soil conditions. This will only be
determined during the final design stage. The tower type to be used will be determined
during the final design stages of the powerline (based on load and other calculations). It is
however envisaged that the bird friendly Single Steel Pole tower type (e.g. ESKOM D-DT
7641, D-DT 7649) will be used in combination with the Steel Lattice towers at bend points
and where greater distances need to be spanned. The Single Steel Pole tower type is
between 18 m and 25 m in height and the Steel Lattice tower type is between 25 m and 29
m in height. A diagram of the tower type is attached as Appendix C.
Servitudes/corridors with a width of 32 m are proposed for each power line route alternative.
This will allow a degree of flexibility when determining the final route alignment for the
proposed 132 kV power line.
The proposed new 132 kV powerline and associated substation will be constructed on
Remaining Extent of the Farm Kapstewel No. 436, Remaining Extent of Farm No. 437,
Remaining Extent of Farm No. 588, Remaining Extent of Farm No. 589, Remaining Extents
of Portions 8 & 14 of Farm No. 589 and Remaining Extents of Portions 3 & 5 of the Farm
Groenwater No. 453.
The proposed section of the existing Eskom powerline to be decommissioned and diverted
as well as the new proposed section to be constructed around the outer boundary of the
CSP facility are situated on the Remaining Extent of Farm Groenwater No. 453 and
Remaining Extents of Portions 4 & 5 of the Farm Groenwater No. 453.
The farms are all situated approximately between 21 km and 27 km north-east of the town of
Postmasburg and between 17 km and 43 km north-east of the town of Lime Acres in the
Northern Cape Province. The farm falls inside the Tsantsabane Local Municipality which, in
turn, forms part of the greater ZF Mgcawu District Municipality.
BASIC ASSESSMENT REPORT
7
Legislation
The proposed project triggers the following listed activities as per the National Environmental
Management Act (Act 107 of 1998) Environmental Impact Assessment Regulations, 2014
(Government Notices R983, R984 and R985 in Government Gazette No. 38282 of 04
December 2014):
GNR 983
o 11, 12 & 19
GNR 985
o 4, 12 & 14
Report Structure
This report is set out as followed:
Section A: Activity Description provides an overview of the development proposal and
listed activities which are triggered in terms of listing notices GN R. 983 and R. 985; of
the EIA Regulations, 04 December 2014.
Section B: Description of Receiving Environment provides detail on the affected
landscape in its present state. A range of aspects relating to the biophysical (e.g.
geology, soil surface and sub-surface water and biodiversity), socio-economic and
historic and cultural character of the immediate route and surrounding area are
described herein, whilst applicable legislation, policy and guidelines considered are
recognised.
Section C: Public Participation describes the consultation component of this study
between the EAP and Interested or Affected Parties (I&APs) and organs of state.
Regulatory requirements of this process are discussed, with a summary of consultation
made with state departments and comments and response given. Comment periods
were afforded to parties, with an initial registration period provided to parties.
Section D: Impact Assessment, Management, Mitigation and Monitoring Measures,
describe how the proposed development may impact on the geographical and physical,
biodiversity, socio-economic and historical and cultural aspects of the receiving
environment. Resource uses of the proposed development phases, attributed to waste
and emissions, water use, power supply and energy efficiency are further discussed.
Section E: Recommendation of the EAP provides, based on such findings as various
site surveys, impact assessment, investigation of alternatives and the review of
strategic policy to consider the needs and desirability, the outgoing opinion of the EAP
is detailed. Any noteworthy recommendations emanating from the study are described
here.
BASIC ASSESSMENT REPORT
8
Section F: Appendices lists all supportive documents enclosed with this report, after
which declarations of the Applicant, EAP and Specialist Parties are given.
Public Participation Process
A comprehensive Public Participation Process (PPP) will be undertaken with all stakeholders
and Interested and Affected Parties (I & AP’s), including the relevant Organs of State and
competent authority (Department of Environmental Affairs DEA) as identified.
The PPP will be conducted in accordance with the requirements of Regulation 41 of the EIA
Regulations, 2014 and the designated Public Participation Officer will ensure that the PPP is
facilitated in a manner which ensures reasonable opportunity for all stakeholders and
registered I & AP’s to comment and provide input on the proposed project.
Notifications have been placed in two local free, newspapers (Ghaap newspaper on 29
July 2016 and Kalahari Bulletin on 21 July 2016).
Site notices have been placed at the entrance to the proposed site location on 15
August 2016, Postmasburg Municipal Offices, public library as well as the entrance to
the Metsimatala local informal settlement.
Copies of the report have been placed at the Postmasburg Municipal Offices and the
public library on 15 August 2016.
A comprehensive list of stakeholders was identified during the PPP of the proposed
CSP facility. This list will be utilised for the purposes of the powerline PPP as well.
A notification email was sent to all stakeholders and I & AP’s on 12 August 2016.
Environmental Impact Statement
Proposed new 132 kV powerline
Ecology
The impacts of both the two alternative route corridors for the proposed powerline are fairly
similar. There are some sensitive systems which would be affected by the proposed
powerline routes. They include the rocky outcrops of the Kuruman Mountain Bushveld
(SVk10) and the episodic streams as well small wetlands/pans on the plains between the
rocky ridges.
No Red or Orange data species were found to occur along the powerline routes or
substation footprint although a protected species namely Olea europaea subsp. africana
BASIC ASSESSMENT REPORT
9
occur on the rocky outcrops while Acacia erioloba, Acacia haematoxylon and Boscia
albitrunca occur on sandy plains.
From an ecological perspective either route alternative 1 or 2 can be utilised due to their
relatively similar impacts. Although the preferred alternative powerline route crosses through
a small portion classified as a Critical Biodiversity Area as well as a small portion classified
as an Ecological Support Area (see Appendix A for Sensitivity map) it is recommended from
an ecological perspective that route alternative 1 (preferred) be approved due to it running a
shorter distance to the Manganore substation.
Avifauna
For the Grid Connection, the residual impacts of habitat destruction, collision and
electrocution were all found to have a medium significance rating after mitigation, with all
other impacts having a low rating. This indicates that either route alternative is acceptable
from an avifaunal perspective with neither being preferred.
Heritage
From an archaeological and cultural heritage perspective neither of the powerline
alternatives, poses a threat to any potentially significant sites. It is therefore recommended
that development of the approved powerline proceed without the developer having to comply
with additional heritage compliance requirements pertaining to lithic Stone Age deposits,
such as Phase 2 mitigation, prior to construction impact.
There are also no major palaeontological grounds to halt the development of the preferred
Alternative Route 1 or 2, but it is advised that sites marked for erection of pylons or
construction of associated infrastructure, which will require excavation into fresh bedrock
sediments of the Campbellrand and Asbestos Hills Subgroup, is mapped and recorded prior
to the construction phase of the development.
No major impacts were identified for either of the powerline alternatives and substation
footprint and by implementing the recommended mitigation measures, the impacts will be
adequately reduced to acceptable levels.
BASIC ASSESSMENT REPORT
10
Decommissioning and diversion of existing powerline
Ecology
The impacts of both the two alternative route corridors for the diversion of the existing
powerline are similar and low. It is thereof recommended that the preferred alternative 1 be
approved.
Avifauna
For the line diversion, similar ratings were obtained as for the new powerline, and both route
alternatives are therefore acceptable, with alternative two being slightly preferred only as it
runs along the main tar road. Alternative 1 is however also acceptable.
Heritage
Although route alternative 1 passes in the proximity of identified significant cemetery site
MVIA 3, the site will not be impacted by the proposed powerline diversion. In fact, the
mitigations measures imposed will assist in the improvement of the integrity of the identified
site. Route alternative 2 for the diversion of the existing power line may potentially traverse
Griquatown Formation iron stones (Vad) considered to be of moderate palaeontological
sensitivity.
No major impacts were identified for either of the powerline diversion alternatives and by
implementing the recommended mitigation measures, the impacts will be adequately
reduced to acceptable levels.
Conclusion After careful consideration of the findings and outcomes during the Basic Assessment
process, Enviroworks is of the opinion that based on all information that was captured in this
report; the proposed development will not lead to unacceptable impacts or fatal flaws and
should be considered plausible in the framework of NEMA. It is indicated that the majority of
the anticipated impacts are rated as low to medium while the impacts rated as medium-high
to high (avifaunal) can be adequately addressed through the various mitigation measures
and reduced to an acceptable level.
Enviroworks also recommend that the preferred route layout alternative 1 for the new
proposed powerline and the substation be considered and approved as well as the preferred
route layout alternative 1 for the decommissioning and diversion of the existing powerline
due to its lesser impacts.
BASIC ASSESSMENT REPORT
11
ABBREVIATIONS
BA Basic Assessment
CARA Conservation of Agricultural Resources Act (Act 43 of 1983)
CEL Cost Estimate Letter
CIA Cumulative Impact Assessment
CO₂ Carbon Dioxide
CO₂e Carbon Dioxide Equivalent
CPA Communal Property Association
CRR Comments and Responses Report
CSP Concentrated Solar Power
DAFF Department of Agriculture, Forestry and Fisheries
DEA Department of Environmental Affairs
DENC Department of Environment and Nature Conservation
DM District Municipality
DMR Department of Mineral Resources
DoE Department of Energy
DSR Draft Scoping Report
DWS Department of Water and Sanitation
EA Environmental Authorisation
EAP Environmental Assessment Practitioner
ECO Environmental Control Officer
EIA Environmental Impact Assessment
EIR Environmental Impact Report
EMPr Environmental Management Programme
FSR Final Scoping Report
Ha Hectares
HTF Heat Transfer Fluid
I & APs Interested and Affected Parties
IDP Integrated Development Plan
IPP Independent Power Producer
kV Kilovolt
LED Local Economic Development
LM Local Municipality
LSA Late Stone Age
MAP Mean Annual Precipitation
MASL Metres Above Sea Level
BASIC ASSESSMENT REPORT
12
MLL Minimum living level
MSA Middle Stone Age
MVA Megavolt ampere
MW Megawatt
NCPSDF Northern Cape Provincial Spatial Development Framework
NDP National Development Plan
NEMA National Environmental Management Act (Act 107 of 1998)
NEMBA National Environmental Management: Biodiversity Act (Act 10 of 2004)
NEMWA National Environmental Management: Waste Act (Act 59 of 2008)
NERSA National Energy Regulator of South Africa
NFA National Forests Act (Act 84 of 1998)
NHRA National Heritage Resources Act (Act 25 of 1999)
NIP National Infrastructure Plan
NWA National Water Act (Act 36 of 1998)
PFS Pre-feasibility Study
PPP Public Participation Process
PUC Point of Utility Connection
PoSEIA Plan of Study for Environmental Impact Assessment
REIPPP Renewable Energy Independent Power Producers Procurement Programme
SAHRA South African Heritage Resources Agency
SDF Spatial Development Framework
SIA Social Impact Assessment
SIP Strategic Integrated Project
ToR Terms of Reference
UNFCCC United Nations Framework Convention on Climate Change
VIA Visual Impact Assessment
WRYCM Water Resource Yield Computer Model
WULA Water Use Licence Application
BASIC ASSESSMENT REPORT
13
SECTION A: ACTIVITY INFORMATION
Has a specialist been consulted to assist with the completion of this section? NO
If YES, please complete the form entitled “Details of specialist and declaration of interest” for the specialist appointed and attach in Appendix I. 1. PROJECT DESCRIPTION
a) Describe the project associated with the listed activities applied for Project description: Metsimatala CSP Solar Energy (Pty) Ltd intends to construct a 150
MW CSP (parabolic trough) facility and associated substation on the Remaining Extent of
the Farm Groenwater No. 453 as well as Remaining Extent of Portions 4 & 5 of the Farm
Groenwater No. 453. An Environmental Authorisation application has been submitted for
the above mentioned project and a Scoping and EIA process is in progress.
This current proposed project for which Environmental Authorisation is now being applied
for this has two main objectives namely:
To construct a suitable 132 kV powerline and associated substation for the
transmission of the electricity generated from the proposed CSP facility to the
Manganore sub-station. The farm extents on which the powerline will be situated
are discussed under project location below.
To decommission and divert a section of the existing Eskom powerline, which
currently runs through the middle of the footprint of the proposed CSP facility,
around its outer boundary. The diversion of the existing powerline is compulsory in
order to accommodate and reroute the line around the footprint area of the
proposed CSP Plant. The farm extents on which the powerline will be diverted are
discussed under project location below.
The anticipated duration of the construction phase of the proposed project will be
approximately 24 months.
Proposed new 132 kV powerline and Metsimatala Solar substation
The linear length of the proposed new 132 kV powerline to be constructed will be
approximately 27 km. The proposed powerline will consist of a linear series of pylons
(towers) which will be situated approximately 100 m - 200 m apart. The exact distance
between and locations of pylons will be dependent on site specific terrain and soil
conditions. This will only be determined during the final design stage. The tower type to be
used will be determined during the final design stages of the powerline (based on load and
BASIC ASSESSMENT REPORT
14
other calculations). It is however envisaged that the bird friendly Single Steel Pole tower
type (e.g. ESKOM D-DT 7641, D-DT 7649) will be used in combination with the Steel
Lattice towers at bend points and where greater distances need to be spanned. The Single
Steel Pole tower type is between 18 m and 25 m in height and the Steel Lattice tower type
is between 25 m and 29 m in height.
The distribution substation will be approximately 173 m X 173.5 m in size and will be
situated on the CSP facility footprint. It will include transformer bays which will contain
transformer oils. Bunded racking will be constructed to ensure that any oil spills will be
adequately attenuated and prevented from release into the environment. For health and
safety purposes, the substation shall be securely fenced to prevent unauthorized access.
Where the substation is beside the line, the connection to the line will be connected via
drop down conductors. Where the line is remote from the substation the connection will be
by MV 66/132 kV overhead line, using either pole or pylon construction depending on the
voltage.
The Substation will include the following;
- 2 bay switching station, and
- Control Plant with protection, metering, telecontrol and SCADA (Supervisory Control and
Data Acquisition), DC and Telecomms.
Decommissioning and diversion of existing powerline
The linear length of the existing Eskom 132 kV powerline to be decommissioned is
approximately 3.4 km while the length of the proposed new 132 kV powerline (diverted
section) to be constructed around the outer boundary of the CSP facility is approximately
4.6 km. The diverted section will consist of a linear series of pylons (towers) which will be
situated approximately 100 m - 200 m apart. The exact distance between and locations of
pylons will be dependent on site specific terrain and soil conditions. This will only be
determined during the final design stage. The tower type to be used will be determined
during the final design stages of the powerline (based on load and other calculations). It is
however envisaged that the bird friendly Single Steel Pole tower type (e.g. ESKOM D-DT
7641, D-DT 7649) will be used in combination with the Steel Lattice towers at bend points
and where greater distances need to be spanned. The Single Steel Pole tower type is
between 18 m and 25 m in height and the Steel Lattice tower type is between 25 m and 29
BASIC ASSESSMENT REPORT
15
m in height. A diagram of the tower type is attached as Appendix C.
Servitudes/corridors with a width of 32 m are proposed for each power line route
alternative. This will allow a degree of flexibility when determining the final route alignment
for the proposed 132 kV power line.
Project location: The proposed new 132 kV powerline and associated substation will be
constructed on Remaining Extent of the Farm Kapstewel No. 436, Remaining Extent of
Farm No. 437, Remaining Extent of Farm No. 588, Remaining Extent of Farm No. 589,
Remaining Extents of Portions 8 & 14 of Farm No. 589 and Remaining Extent of Portions 3
& 5 of the Farm Groenwater No. 453.
The proposed section of the existing Eskom powerline to be decommissioned and diverted
as well as the new proposed section to be constructed around the outer boundary of the
CSP facility are situated on the Remaining Extent of Farm Groenwater No. 453 and
Remaining Extents of Portions 4 & 5 of the Farm Groenwater No. 453.
The farms are all situated approximately between 21 km and 27 km north-east of the town
of Postmasburg and between 17 km and 43 km north-east of the town of Lime Acres in the
Northern Cape Province. The farm falls inside the Tsantsabane Local Municipality which,
in turn, forms part of the greater ZF Mgcawu District Municipality.
b) Provide a detailed description of the listed activities associated with the project as
applied for
Listed activity as described in GN R.983, 984, 985
Description of project activity Government Notice R983 – Listing Notice 1 of 2014
11
The development of facilities or infrastructure for the
transmission and distribution of
electricity-
outside urban areas or industrial complexes with a
capacity of more than 33 but less than 275 kilovolts.
A 132 kV powerline and
associated Metsimatala Solar
substation will be constructed
on the Remaining Extent of
the Farm Kapstewel No. 436,
Remaining Extent of Farm
No. 437, Remaining Extent of
Farm No. 588, Remaining
BASIC ASSESSMENT REPORT
16
Extent of Farm No. 589
Remaining Extents of
Portions 8 & 14 of Farm No.
589 and Remaining Extent of
Portions 3 & 5 of the Farm
Groenwater No. 453. The
linear length of the proposed
new 132 kV powerline to be
constructed will be
approximately 27 km. The
distribution substation will be
approximately 173 m X 173.5
m in size and will be situated
on the CSP facility footprint.
A section of the existing
Eskom 132 kV powerline
running through the
Remaining Extent of Farm
Groenwater No. 453 and
Portion 5 of the Farm
Groenwater No. 453 will be
decommissioned and
diverted around the outer
boundary of the proposed
CSP plant to be constructed.
The linear length of the
existing Eskom 132 kV
powerline to be
decommissioned is
approximately 3.4 km while
the length of the proposed
new 132 kV powerline
(diverted section) to be
constructed around the outer
boundary of the CSP facility
is approximately 4.6 km. The
diverted section of the
powerline will traverse the
Remaining Extent of Farm
Groenwater No. 453 and
Portions 4 & 5 of the Farm
Groenwater No. 453.
BASIC ASSESSMENT REPORT
17
12 The development of:
xii) infrastructure or structures with a physical
footprint of 100 square meters or more;
where such development occurs-
a) Within a watercourse
c) if no development setback exists, within 32
meters of a watercourse, measured from the
edge of a watercourse.
The proposed powerline is
located in close proximity to
and will cross various
seasonal watercourses.
Pylons and other
infrastructure, exceeding 100
m², may need to be placed
within 32 metres of a
watercourse. The
servitude/corridor of the
proposed powerline will be
32 m wide and the area sizes
at watercourse crossings will
therefore exceed 100 m².
The decommissioning and
diversion of the existing
Eskom 132 kV powerline will
not be located in close
proximity to and will not cross
any seasonal watercourses.
19 The infilling or depositing of any material of more
than 5 cubic metres into, or the dredging, excavation,
removal or moving of soil, sand, shells, shell grit,
pebbles or rock of more than 5 cubic metres from –
(i) a watercourse;
Construction activities for the
new proposed 132 kV
powerline may take place in
close proximity to a
wetland/watercourse.
Construction activities for the
decommissioning and
diversion of the existing
Eskom 132 kV powerline will
not take place in close
proximity to any
wetland/watercourse.
Government Notice R985 – Listing Notice 3 of 2014
Description of project activity
4 The development of a road wider than 4 metres with
a reserve less than 13,5 metres.
(a) In Free State, Limpopo, Mpumalanga and
Northern Cape provinces:
(ii) Outside urban areas, in:
(ee) Critical Biodiversity areas as identified in
systematic biodiversity plans adopted by the
competent authority or in bioregional plans
Existing roads and farm
tracks will mainly be used. If
additional site roads are
required they will be
constructed with a width of
more than 4 m. A small
portion of the proposed
development route/corridor
traverses an area classified
BASIC ASSESSMENT REPORT
18
as CBA.
The decommissioning and
diversion of the existing
Eskom 132 kV powerline will
not cross through any CBA’s.
12 The clearance of an area of 300 square metres or
more of indigenous vegetation except where such
clearance of indigenous vegetation is required for
maintenance purposes undertaken in accordance
with the maintenance management plan.
(d) In Northern Cape:
(ii). Within critical biodiversity areas identified in
bioregional plans;
The proposed 132 kV
powerline servitude/corridor
will be 32 m wide and will
cross through a CBA 1 area
where the total surface size
of the crossing sections will
be more than 300 m².
The decommissioning and
diversion of the existing
Eskom 132 kV powerline will
not cross through any CBA’s.
14 The development of –
(xii) infrastructure or structures
with a physical footprint of
10 square metres or more;
Where such development occurs –
(a) within a watercourse;
(a) In Northern Cape
(ii) Outside urban areas, in:
(ff) Critical biodiversity areas or ecosystem service
areas as identified in systematic biodiversity plans
adopted by the competent authority or in
bioregional plans;
The proposed 132 kV
powerline servitude/corridor
will be 32 m wide and will
cross through a CBA 1 area
where the total surface size
of the crossing sections will
be more than 10 m².
The decommissioning and
diversion of the existing
Eskom 132 kV powerline will
not cross through any CBA’s.
BASIC ASSESSMENT REPORT
19
2. FEASIBLE AND REASONABLE ALTERNATIVES
“alternatives”, in relation to a proposed activity, means different means of meeting the general purpose and requirements of the activity, which may include alternatives to— (a) the property on which or location where it is proposed to undertake the activity; (b) the type of activity to be undertaken; (c) the design or layout of the activity; (d) the technology to be used in the activity; (e) the operational aspects of the activity; and (f) the option of not implementing the activity. Describe alternatives that are considered in this application as required by Appendix 1 (3)(h), Regulation 2014. Alternatives should include a consideration of all possible means by which the purpose and need of the proposed activity (NOT PROJECT) could be accomplished in the specific instance taking account of the interest of the applicant in the activity. The no-go alternative must in all cases be included in the assessment phase as the baseline against which the impacts of the other alternatives are assessed. The determination of whether site or activity (including different processes, etc.) or both is appropriate needs to be informed by the specific circumstances of the activity and its environment. After receipt of this report the, competent authority may also request the applicant to assess additional alternatives that could possibly accomplish the purpose and need of the proposed activity if it is clear that realistic alternatives have not been considered to a reasonable extent. The identification of alternatives should be in line with the Integrated Environmental Assessment Guideline Series 11, published by the DEA in 2004. Should the alternatives include different locations and lay-outs, the co-ordinates of the different alternatives must be provided. The co-ordinates should be in degrees, minutes and seconds. The projection that must be used in all cases is the WGS84 spheroid in a national or local projection. Powerline alternatives
Two (2) route servitude/corridor alternatives were considered for the proposed new 132 kV
powerline. These are as follows:
Alternative 1 (Preferred): approximately 27.0 km – (running straight from the
proposed Metsimatala substation to the Manganore Substation)
Alternative 2: approximately 31.5 km – (the majority will run along an existing
Eskom 132 kV powerline to the Manganore Substation)
A new Metsimatala Solar substation will be developed in the middle of the proposed CSP
facility footprint from where the powerline will be connected. The distribution substation will
be approximately 173 m X 173.5 m in size and will be situated on the CSP facility footprint.
BASIC ASSESSMENT REPORT
20
Existing Eskom 132 kV powerline decommissioning and diversion alternatives
Two (2) route servitude/corridor alternatives were considered for the decommissioning and
diversion of the existing Eskom powerline. These are as follows:
Alternative 1 (Preferred): approximately 4.6 km – (around the eastern and northern
outer boundary of the proposed CSP facility)
Alternative 2: approximately 5.4 km – (around the southern and western outer
boundary of the proposed CSP facility)
The decommissioning and diversion of the existing powerline is compulsory in order to
accommodate and reroute the line around the footprint area of the proposed CSP facility.
The Locality map that indicates the route corridor of the proposed powerline (Alternatives 1
& 2) as well as the route corridor of the existing Eskom powerline decommissioning and
diversion (Alternatives 1 & 2) is provided in Appendix A.
A technical diagram/technical layout plan of the proposed pylon type to be used is provided
in Appendix C.
a) Site alternatives
In the case of linear activities:
Proposed new 132 kV powerline:
Latitude (S): Longitude (E): Alternative 1 (preferred)
Starting point of the activity 28°16’59.62’’S 23°17’49.62’’E
Middle/Additional point of the activity 28°12’39.85’’S 23°12’55.17’’E
End point of the activity 28°07’56.06’’S 23°06’12.85’’E
Alternative 2
Starting point of the activity 28°16’59.62’’S 23°17’49.62’’E
Middle/Additional point of the activity 28°10’49.30’’S 23°17’51.92’’E
End point of the activity 28°07’56.06’’S 23°06’12.85’’E
Decommissioning and diversion of existing 132 kV powerline:
Alternative 1 (preferred)
Starting point of the activity 28°17’27.21’’S 23°18’23.77’’E
Middle/Additional point of the activity 28°16’22.94’’S 23°18’22.67’’E
End point of the activity 28°16’21.46’’S 23°16’45.36’’E
Alternative 2
Starting point of the activity 28°17’45.21’’S 23°18’48.94’’E
BASIC ASSESSMENT REPORT
21
Middle/Additional point of the activity 28°18’07.63’’S 23°17’08.95’’E
End point of the activity 28°16’37.54’’S 23°17’08.12’’E
For route alternatives that are longer than 500m, please provide an addendum with co-ordinates taken every 250 meters along the route for each alternative alignment.
These final coordinates will be provided in the Final BA Report.
The positions and coordinates for the placement of the pylons will only be determined during the final
design phase.
In the case of an area being under application, please provide the co-ordinates of the corners of the site as indicated on the lay-out map provided in Appendix A of this form. n/a b) Lay-out alternatives
Alternative 1 (preferred alternative)
Description Lat (DDMMSS) Long (DDMMSS)
n/a
Alternative 2
Description Lat (DDMMSS) Long (DDMMSS)
n/a
c) Technology alternatives
Alternative 1 (preferred alternative)
n/a
Alternative 2
n/a
d) Other alternatives (e.g. scheduling, demand, input, scale and design alternatives)
Alternative 1 (preferred alternative)
n/a
Alternative 2
n/a
e) No-go alternative The no-go alternative addresses the scenario of the status-quo remaining the same, with no development on the proposed site. The no-go alternative would entail that the current land use does not change.
Advantages
The negative environmental impacts associated with the proposed project and its
alternatives will be avoided if the proposed project is not implemented. No significantly high
rating impacts were however identified by any specialists.
BASIC ASSESSMENT REPORT
22
Disadvantages
If the proposed project does not go ahead, the proposed CSP facility will not have an
adequate way of distributing its generated electricity into the local grid. The new 132 kV
powerline construction and existing 132 kV powerline decommissioning and diversion is
crucial for the successful operation of the proposed CSP facility. The local communities will
forego the significant economic benefits which the project will have on the area such as
immediate additional employment opportunities and revenue streams during the
construction phase and most importantly, sustainable capacity building (skills, experience
and resources development) for the future. The development of alternative renewable
energy sources and distribution of generated electricity is crucial within the context of South
Africa’s current energy crisis as well as the commitment towards greenhouse gas emission
reductions. The current electricity shortage within the Metsimatala area will continue if the
no-go alternative is considered.
The no-go option would not be preferable as the existing and proposed residential areas
require adequate electricity provision, which can be supplied by this proposed
development. The proposed development of the 132 kV powerline has been assessed in
this report against the no-go option. The no-go alternative is not considered a preferred
alternative.
Paragraphs 3 – 13 below should be completed for each alternative. 3. PHYSICAL SIZE OF THE ACTIVITY
a) Indicate the physical size of the preferred activity/technology as well as alternative
activities/technologies (footprints): Alternative: Size of the activity:
Alternative 1 (preferred alternative) n/a m2
Alternative 2 n/a m2
Alternative A3 (if any) n/a m2
or, for linear activities: Proposed new 132 kV powerline Alternative: Length of the activity:
Alternative 1 (preferred alternative) 27 000 m
Alternative 2 31 500 m
Alternative 3 n/a
BASIC ASSESSMENT REPORT
23
Decommissioning and diversion of existing 132 kV powerline Alternative: Length of the activity:
Alternative 1 (preferred alternative) 4600 m
Alternative 2 5400 m
Alternative 3 n/a
b) Indicate the size of the alternative sites or servitudes (within which the above footprints
will occur): Proposed new 132 kV powerline Alternative: Size of the site/servitude:
Alternative 1 (preferred alternative) Width 32 m; Size 86.4 ha
Alternative 2 Width 32 m; Size 100.8 ha
Alternative 3 n/a
Decommissioning and diversion of existing 132 kV powerline Alternative:
Size of the site/servitude:
Alternative 1 (preferred alternative) Width 32 m; Size 14.72 ha
Alternative 2 Width 32 m; Size 17.28 ha
Alternative 3 n/a
4. SITE ACCESS
Does ready access to the site exist? YES
If NO, what is the distance over which a new access road will be built n/a
Describe the type of access road planned: Existing roads and farm tracks will mainly be used.
Include the position of the access road on the site plan and required map, as well as an indication of the road in relation to the site. 5. LOCALITY MAP
An A3 locality map must be attached to the back of this document, as Appendix A. The scale of the locality map must be relevant to the size of the development (at least 1:50 000. For linear activities of more than 25 kilometres, a smaller scale e.g. 1:250 000 can be used. The scale must be indicated on the map.). The map must indicate the following:
an accurate indication of the project site position as well as the positions of the alternative sites, if any;
indication of all the alternatives identified;
closest town(s;)
road access from all major roads in the area;
road names or numbers of all major roads as well as the roads that provide access to the site(s);
all roads within a 1km radius of the site or alternative sites; and
BASIC ASSESSMENT REPORT
24
a north arrow;
a legend; and
locality GPS co-ordinates (Indicate the position of the activity using the latitude and longitude of the centre point of the site for each alternative site. The co-ordinates should be in degrees and decimal minutes. The minutes should have at least three decimals to ensure adequate accuracy. The projection that must be used in all cases is the WGS84 spheroid in a national or local projection).
See Appendix A for the A3 Locality map 6. LAYOUT/ROUTE PLAN
A detailed site or route plan(s) must be prepared for each alternative site or alternative activity. It must be attached as Appendix A to this document. The site or route plans must indicate the following:
the property boundaries and numbers of all the properties within 50 metres of the site;
the current land use as well as the land use zoning of the site;
the current land use as well as the land use zoning each of the properties adjoining the site or sites;
the exact position of each listed activity applied for (including alternatives);
servitude(s) indicating the purpose of the servitude;
a legend; and
a north arrow.
See Appendix A for the A3 Locality/Layout/Route map 7. SENSITIVITY MAP
The layout/route plan as indicated above must be overlain with a sensitivity map that indicates all the sensitive areas associated with the site, including, but not limited to:
watercourses;
the 1:100 year flood line (where available or where it is required by DWS);
ridges;
cultural and historical features;
areas with indigenous vegetation (even if it is degraded or infested with alien species); and
critical biodiversity areas. The sensitivity map must also cover areas within 100m of the site and must be attached in Appendix A.
See Appendix A for the A3 Sensitivity and vegetation maps 8. SITE PHOTOGRAPHS
Colour photographs from the centre of the site must be taken in at least the eight major compass directions with a description of each photograph. Photographs must be attached under Appendix B to this report. It must be supplemented with additional photographs of relevant features on the site, if applicable.
See Appendix B for Photo report
BASIC ASSESSMENT REPORT
25
9. FACILITY ILLUSTRATION
A detailed illustration of the activity must be provided at a scale of at least 1:200 as Appendix C for activities that include structures. The illustrations must be to scale and must represent a realistic image of the planned activity. The illustration must give a representative view of the activity.
See Appendix C for technical drawings of the proposed pylon type to be used 10. ACTIVITY MOTIVATION
Motivate and explain the need and desirability of the activity (including demand for the activity):
1. Is the activity permitted in terms of the property’s existing land use rights?
YES Please explain
The surrounding area is characterised by mostly vacant natural veld, which is used for livestock grazing. The farms are classified as stock farms either with or without dwellings. There is already an existing 132 kV powerline present on the relevant farms.
The diversion of the existing Eskom 132 kV powerline will also merely be a relocation of an existing line which is already present on the property.
A change in land use will not be required as the 132 kV powerline servitude will be considered as special use within the existing land use rights.
2. Will the activity be in line with the following?
(a) Provincial Spatial Development Framework (PSDF) YES Please explain
The proposed project falls within the Northern Cape Province. The Free State Growth and
Development Pillars, which is contained in the Northern Cape Provincial Spatial
Development Framework (NCPSDF), has set its own set of drivers with long-term
programmes which discusses the improved quality of life and states that basic
infrastructure should be expanded or maintained or order to achieve the desired quality of
life improvement.
The proposed project will contribute to this in the following ways:
By providing new basic electricity infrastructure at a local level;
By providing Bulk Services; and
By improving technical capacity of local municipalities for sustainable local
infrastructure.
Therefore, the proposed project will be in line with the NCPSDF in terms of the improvement of quality of life.
BASIC ASSESSMENT REPORT
26
(b) Urban edge / Edge of Built environment for the area YES Please explain
Neither the proposed development of the new 132 kV powerline or the diversion of the
existing Eskom 132 kV powerline will compromise the urban edge as they are linear
activities which have no restrictions in terms of the urban edge.
(c) Integrated Development Plan (IDP) and Spatial Development Framework (SDF) of the Local Municipality (e.g. would the approval of this application compromise the integrity of the existing approved and credible municipal IDP and SDF?).
YES Please explain
The proposed development is situated within the Tsantsabane Local Municipality. An overview of challenges, development priorities and opportunities of the above mentioned municipality indicates that service delivery is one of the key focus areas in the Integrated Development Plan (IDP).
KPA 1 of Tsantsabane Municipality: Service Delivery.
Physical Infrastructure and Energy Efficiency – to ensure efficient infrastructure and energy supply that will contribute to the improvement of quality of life for all citizens of Tsantsabane.
The proposed development will contribute to the IDP and SDF by providing electricity to households, business and service providers, etc., within the municipal area and therefore adhering to the bulk service supply of the municipality. The proposed project will also serve as a solution to forthcoming potential overloading and as a result thereof, electricity losses and interruptions.
(d) Approved Structure Plan of the Municipality YES Please explain
The IDP of the Tsantsabane Municipality is the only structure plan available. The proposed development is for service infrastructure and therefore will not have any undesired effect on the Municipalities’ Structure Plans. It will in fact contribute positively to the local requirements.
(e) An Environmental Management Framework (EMF) adopted by the Department (e.g. Would the approval of this application compromise the integrity of the existing environmental management priorities for the area and if so, can it be justified in terms of sustainability considerations?)
NO Please explain
The district municipality EMF was taken into consideration when developing the local Tsantsabane IDP. KPA 2 discusses safety and the environment which needs to be managed responsibly and sustainably.
The proposed development would not compromise the integrity of the environmental management priorities for the area. No environmental fatal flaws were identified by the specialists and it was determined that the impacts can be mitigated to an acceptable level. In addition, the development would result in socio-economic considerable benefits for the local community.
BASIC ASSESSMENT REPORT
27
(f) Any other Plans (e.g. Guide Plan) YES Please explain
The proposed development is aligned with Eskom’s Integrated Strategic Electricity Planning (ISEP) process, which is destined to provide energy and demand forecasting for up to 20 years into the future. As part of this process, data is gathered on supply- and demand-side costs and performances. Then the mix of these options and the timing of their use are optimised to meet the load forecast with suitable reliability, taking into account risks and assessment criteria.
The proposed development is also in line with the National Integrated Resource Plan (NIRP) which aims at providing a long-term, cost-effective resource plan for meeting electricity demand, which is consistent with reliable electricity supply and environmental, social and economic policies.
3. Is the land use (associated with the activity being applied for) considered within the timeframe intended by the existing approved SDF agreed to by the relevant environmental authority (i.e. is the proposed development in line with the projects and programmes identified as priorities within the credible IDP)?
YES Please explain
The proposed development is situated within the Tsantsabane Municipality. The municipality has set some goals within the IDP to address service delivery issues like the electricity backlog and other service.
KPA 1 pertains to service delivery in terms of physical infrastructure and energy efficiency while KPA 2 discusses the need for local economic development. These are two major and high priority objectives of the local municipality in order to improve the current status and condition of the local municipality.
The proposed project will directly benefit both these high priority KPA’s in the short as well as the long term future through job creation and economic stimulation together with necessary sufficient local electricity provision.
4. Does the community/area need the activity and the associated land use concerned (is it a societal priority)? (This refers to the strategic as well as local level (e.g. development is a national priority, but within a specific local context it could be inappropriate.)
YES Please explain
In line with national electricity generation and job creation priorities, the construction of the proposed CSP facility and associated 132 kV powerline will provide significant benefit to the local community.
Benefits will firstly come in the form of employment and skills development opportunities primarily during the construction but also subsequent operational phases which will assist in the alleviation of unemployment in the area. Secondly, the more stable and constant supply of adequate electricity to the local areas will assist in the improvement of livelihoods and quality of living of the local communities. The project will therefore provide a financial as well as social benefit to the area.
BASIC ASSESSMENT REPORT
28
5. Are the necessary services with adequate capacity currently available (at the time of application), or must additional capacity be created to cater for the development? (Confirmation by the relevant Municipality in this regard must be attached to the final Basic Assessment Report as Appendix I.)
YES Please explain
This proposed development itself forms part of enabling the provision of a “necessary
service” in terms of sufficient local electricity supply. The construction of the 132 kV
powerline and diversion of the existing line will therefore beneficially add to the energy
capacity of the local area.
The Municipality has confirmed that they will be able to accommodate the water supply
required for the construction and operation of the CSP facility and powerline.
See Appendix I for confirmation letter from the Municipality.
6. Is this development provided for in the infrastructure planning of the municipality, and if not what will the implication be on the infrastructure planning of the municipality (priority and placement of services and opportunity costs)? (Comment by the relevant Municipality in this regard must be attached to the final Basic Assessment Report as Appendix I.)
YES Please explain
The improvement and maintenance of electricity distribution infrastructure is a high priority
KPA for the local municipality and the proposed 132 kV powerline development will
significantly contribute in a positive way to the infrastructure planning and improvement
within the local municipality.
7. Is this project part of a national programme to address an issue of national concern or importance?
YES Please explain
One objective regarding electricity distribution within the National Development Plan (NDP)
is that the proportion of people with access to the electricity grid should rise to at least 90
% by 2030, with non-grid options available for the rest. Resolving maintenance and the
refurbishment of backlogs is one of the actions set out in the NDP to solve this issue. This
proposed project will therefore assist in positively contributing to the improvement of the
national electricity supply situation.
BASIC ASSESSMENT REPORT
29
8. Do location factors favour this land use (associated with the activity applied for) at this place? (This relates to the contextualisation of the proposed land use on this site within its broader context.)
YES Please explain
The proposed location for the CSP facility has a very high solar radiation and the
topography of the area is virtually flat with little contours or gradient. For this reason, the
location is perfectly suited for the proposed CSP facility. The associated powerline needs
to connect the CSP facility to the nearest Managanore substation in order to feed into the
local power grid. The most appropriate route for the powerline would be to run as straight
and short distance as far as possible in order to minimise the environmental impact on the
area. The location and route chosen for the powerline is therefore favourable in achieving
the desired objective of electricity distribution into the local grid while minimising the
environmental impact as far as possible. The local agricultural land-use of mostly grazing
will not be adversely affected once the pylons have been constructed as the actual
footprint of natural areas transformed by the project will not be of significant size.
9. Is the development the best practicable environmental option for this land/site?
YES Please explain
The current environmental land-use capability is already low. Once the pylons have been
constructed the area will again be available for agricultural utilisation mainly in the form of
livestock grazing as is current practice. The project will not adversely affect the current
land-use capability and environmental potential. The development of the powerline is
essential in the success of the proposed CSP facility.
10. Will the benefits of the proposed land use/development outweigh the negative impacts of it?
YES Please explain
The benefits of the proposed project will significantly outweigh the potential negative
impacts thereof. The proposed project will contribute to improving the socio-economic
conditions of the area. Local job creation, skills development, improved livelihood and
quality of life as well as adequate local electricity supply are significant local benefits while
the need for additional clean energy generation and supply will significantly benefit on a
national level. The negative impacts on the existing environment will be minimal due to the
fact that the proposed powerline will be constructed along an existing power line.
Therefore, the environment has already been exposed to similar activities and the
aesthetic feel of the environment will not be greatly affected from a visual perspective. The
Ecological Impact Assessment as well as an Avifaunal Impact Assessment conducted by
specialists yielded negative impacts on the ecology and the birdlife of relatively low
significance and impacts identified can also be suitably mitigated to acceptable levels.
BASIC ASSESSMENT REPORT
30
11. Will the proposed land use/development set a precedent for similar activities in the area (local municipality)?
NO Please explain
There are other solar power facilities in the area which also have powerlines which connect
them to the power grid in order to distribute their electricity generated. The proposed
powerline development will form part of a distribution network required for electricity
transmission in the area. Distribution networks are usually upgraded and changed over
time in order to optimise efficiency and adjust to the changes in requirements and
demands. It is therefore possible that the network may be altered in the future. The new
powerline will also run along the already existing line indicating that the area has been
approved for similar activities.
12. Will any person’s rights be negatively affected by the proposed activity/ies?
NO Please explain
The proposed project activities will not have a negative effect on any person’s rights; it will
in fact improve the socio-economic conditions of the area and subsequently improve
livelihood and quality of life for the local community.
13. Will the proposed activity/ies compromise the “urban edge” as defined by the local municipality?
NO Please explain
The proposed project will be constructed outside the urban edge of Metsimatala as
indicated by the SDF of the municipality. Infrastructure for the provision of services would
therefore not alter or impact the urban edge.
BASIC ASSESSMENT REPORT
31
14. Will the proposed activity/ies contribute to any of the 17 Strategic Integrated Projects (SIPS)?
YES Please explain
The National Government recently adopted an Infrastructure Plan that is intended to
transform the economic landscape of South Africa, create a significant number of new
jobs, strengthen the delivery of basic services to the people of South Africa and support
the integration of African economies.
The Infrastructure Plan of South Africa sets out the challenges and enablers, which South
Africa needs to respond to, in the building and developing of relevant infrastructure.
Based on the work of the Presidential Infrastructure Coordination Commission (PICC),
seventeen Strategic Integrated Projects (SIPs) have been developed and approved to
support economic development and address service delivery in the poorest provinces.
Each SIP is comprised of a large number of specific infrastructure components and
programmes.
The proposed development of the powerline will contribute to SIP 6 and 10.
SIP 6 regarding integrated municipal infrastructure projects, include projects that:
Develop national capacity to assist the 23 least resourced districts (19 million
people) to address all the maintenance backlogs and upgrades required in water,
electricity and sanitation bulk infrastructure; and
SIP 10, regarding electricity transmission and distribution for all, includes projects that:
Expand the transmission and distribution network to address historical imbalances,
provide access to electricity for all and support economic development; and
Align the 10-year transmission plan, the services backlog, the national broadband
roll-out and the freight rail line development to leverage off regulatory approvals,
supply chain and project development capacity.1
The aim of the project is to expand the transmission and distribution network to address
the current electricity imbalance and provide access to electricity for the existing
Metsimatala residential area.
15. What will the benefits be to society in general and to the local communities?
Please explain
The proposed development will provide an additional supply of electricity to the local area
in which it is proposed. The construction and subsequent operation of the proposed
development will also provide a significant financial boost to the area in terms of job
creation and skills development. The current imbalance in the electricity supply within the
surrounding areas will be restored and it will add to a higher quality of life to residents. The
capacity for the potential development of new residential areas will also be created once
the proposed electrical services development is completed. This will enhance the
economic development process within the area. The generation and distribution of clean
renewable energy will provide a benefit to society in general.
BASIC ASSESSMENT REPORT
32
16. Any other need and desirability considerations related to the proposed activity?
Please explain
As discussed earlier, the project is firstly needed in order for the proposed CSP facility to
be able to connect into the local power grid and adequately distribute electricity generated.
Without the construction of the proposed powerline, the functionality of the CSP facility will
be severely compromised.
The project will contribute to national clean renewable energy generation targets and
initiatives. It will provide a socio-economic boost to the area through job creation and skills
development and improve the livelihood and quality of life of local the community through
adequate electricity generation and provision.
17. How does the project fit into the National Development Plan for 2030? Please explain
The key point in Chapter 4 of The National Development Plan (NDP) of 2030, is that South Africa needs to maintain and expand its electricity, water, transport and telecommunication infrastructure in order to support economic growth and social development goals. The plan further envisages that, by 2030, South Africa will have an energy sector that promotes inter alia, economic growth and development through adequate investment in energy infrastructure.
The proposed project will fit into the NDP of 2030 through the construction and improvement of electricity infrastructure that will promote electricity supply to the proposed development area in the future. This will also be beneficial to the residents within the area as this will contribute to their livelihood and quality of life. The project will also form part of clean renewable energy generation and targets to be reached.
18. Please describe how the general objectives of Integrated Environmental Management as set out in section 23 of NEMA have been taken into account.
The required Basic Assessment (BA) in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998) (NEMA) was undertaken for the proposed powerline, in order to investigate and assess any potential environmental impacts associated with the development prior to implementation. Alternatives were identified and the potential mitigation measures of impacts to acceptable levels were also assessed during the Basic Assessment. As part of the BA process, specialist studies were conducted to evaluate the actual and potential impacts that the proposed development could have on the biophysical environment, within the study area. In line with the general objectives of Integrated Environmental Management, the risks and consequences of the various corridor alternatives were assessed and mitigation measures were recommended by each specialist in order to minimise the negative impacts to acceptable levels and maximise the benefits of the proposed project.
In addition, a comprehensive Public Participation Process (PPP) will be undertaken as part of the Basic Assessment, which will involve informing of and consultation with various interested and affected parties, key stakeholders and organs of state, including national, provincial, district and local authorities, relevant government departments, parastatals and NGO’s. This PPP will ensure they are afforded sufficient time and information in order to make informed comments on the proposed project. These processes will ensure that all provisions of the Act are considered and as such that the principle of Integrated Environmental Management is adhered to.
BASIC ASSESSMENT REPORT
33
19. Please describe how the principles of environmental management as set out in section 2 of NEMA have been taken into account.
BASIC ASSESSMENT REPORT
34
Through the undertaking of a Basic Assessment process by a competent Environmental Assessment Practitioner, informed by guidelines, the consideration of impacts and alternatives (advantages and disadvantages coupled thereto) has been made. Moreover, the conducting of a public participation process and specialist investigations form part of this basic assessment process, whilst mitigation measures and the needs and desirability of the proposed project were interrogated. This ensured that all provisions of the Act were considered and as such integrated environmental management were accounted for as follows:
(2) Environmental Management must place people and their needs at the forefront of its concern, and serve their physical, psychological, developmental, cultural heritage and social interests equitably.
The goal of this Basic Assessment is to identify and adequately mitigate potential socio-economic impacts in order to meet the terms of Section 24 of the Constitution. The project will have considerable socio-economic benefits such as job creation, skills development and transfer as well as adequate local electricity provision.
(3) Development must be socially, environmentally and economically sustainable.
The overall goal of this Basic Assessment is to predict, identify and manage potential positive and negative impacts in the socio-economic, cultural-heritage and biophysical environments. This must be done in order to meet the needs of present generations without compromising the needs of future generations (sustainable development). The distribution and local provision of electricity will be a continuous and sustainable process while environmental impacts will be acceptably mitigated.
(4)(a) Sustainable development requires the consideration of all relevant factors including the following:
i. That the disturbance of ecosystems and loss of biological diversity are
avoided, or, where they cannot be altogether avoided, are minimised and
remedied;
ii. that pollution and degradation of the environment are avoided, or, where
they cannot be altogether avoided, are minimised and remedied;
iii. that the disturbance of landscapes and sites that constitute the nation´s
cultural heritage is avoided, or where it cannot be altogether avoided, is
minimised and remedied;
iv. that waste is avoided, or where it cannot be altogether avoided, minimised
and reused or recycled where possible and otherwise disposed of in a
responsible manner;
v. that the use and exploitation of non-renewable natural resources is
responsible and equitable, and takes into account the consequences of the
depletion of the resource;
vi. that the development, use and exploitation of renewable resources and the
ecosystems of which they are part do not exceed the level beyond which
their integrity is jeopardised;
vii. that a risk-aversive and cautious approach is applied, which takes into
account the limits of current knowledge about the consequences of
decisions and actions; and
viii. that negative impacts on the environment and on people´s environmental
rights be anticipated and prevented, and where they cannot be altogether
prevented, are minimised and remedied.
An Environmental Management Program Report (EMPr) was compiled to mitigate and manage all activities during the planning, construction and operational phases.
BASIC ASSESSMENT REPORT
35
(b) Environmental management must be integrated, acknowledging that all elements of
the environment are linked and interrelated, and it must take into account the effects of
decisions on all aspects of the environment and all people in the environment by
pursuing the selection of the best practicable environmental option.
All aspects, including socio-economic, cultural-heritage and biophysical was evaluated and
assessed in order to identify and minimize potential negative impacts which will give effect to
Integrated Environmental Management, as set out in Chapter 5 of NEMA, 1998.
(c) Environmental justice must be pursued so that adverse environmental impacts shall
not be distributed in such a manner as to unfairly discriminate against any person,
particularly vulnerable and disadvantaged persons.
A public participation process will be undertaken in terms of Section 41 of the NEMA EIA
Regulations, which came into effect on 4 December 2014, in order to give effect to Section
32 of the Constitution in such a way that adherence is given to Section 24 of the
Constitution.
(d) Equitable access to environmental resources, benefits and services to meet basic
human needs and ensure human wellbeing must be pursued and special measures
may be taken to ensure access thereto by categories of persons disadvantaged by
unfair discrimination.
The proposed project will serve as an alternative energy option to reduce the impact on a
constrained electricity grid.
(e) Responsibility for the environmental health and safety consequences of a policy,
programme, project, product, process, service or activity exists throughout its life cycle.
The EMPr will be applicable throughout the lifecycle of the project.
(f) The participation of all interested and affected parties in environmental governance
must be promoted, and all people must have the opportunity to develop the
understanding, skills and capacity necessary for achieving equitable and effective
participation, and participation by vulnerable and disadvantaged persons must be
ensured.
A comprehensive public participation process will be undertaken in terms of Section 41 of
the NEMA EIA Regulations, which came into effect on 4 December 2014, in order to give
effect to Section 32 of the Constitution in such a way that adherence is given to Section 24
of the Constitution.
(g) Decisions must take into account the interests, needs and values of all interested and
affected parties, and this includes recognising all forms of knowledge, including
traditional and ordinary knowledge.
The competent authority/Department Environmental Affairs’ (DEA) decision making process
has to be in accordance with the above.
BASIC ASSESSMENT REPORT
36
(h) Community wellbeing and empowerment must be promoted through environmental
education, the raising of environmental awareness, the sharing of knowledge and
experience and other appropriate means.
(i) The social, economic and environmental impacts of activities, including disadvantages
and benefits, must be considered, assessed and evaluated, and decisions must be
appropriate in the light of such consideration and assessment.
This Basic Assessment Report gives effect to Section 5 of NEMA whereby all social,
economic and environmental impacts of activities were considered, assessed and evaluated
in order to determine the most appropriate mitigation.
(j) The right of workers to refuse work that is harmful to human health or the environment
and to be informed of dangers must be respected and protected.
Human rights will be taken into account during all phases of the proposed project.
(k) Decisions must be taken in an open and transparent manner, and access to
information must be provided in accordance with the law.
The decision will take place in an open and fair manner to give effect to Section 32 of the
Constitution. I & AP’s will be notified of the final decision in terms of the requirements as set
out in Section 41 of the NEMA EIA Regulations, 2014.
(l) There must be intergovernmental coordination and harmonisation of policies,
legislation and actions relating to the environment.
All relevant governmental authorities will be considered during the Basic Assessment
process to give their inputs on the project.
(m) Actual or potential conflicts of interest between organs of state should be resolved
through conflict resolution procedures.
Actual or potential conflicts of interest between organs of state will be adequately managed
in order to attempt to resolve through conflict resolution procedures.
(n) Global and international responsibilities relating to the environment must be
discharged in the national interest.
(o) The environment is held in public trust for the people, the beneficial use of
environmental resources must serve the public interest and the environment must be
protected as the people´s common heritage.
Through the appointment of various specialists, mitigation measures have been determined
to ensure that the impacts of the proposed project are reduced to acceptable levels.
(p) The costs of remedying pollution, environmental degradation and consequent adverse
health effects and of preventing, controlling or minimising further pollution,
environmental damage or adverse health effects must be paid for by those responsible
for harming the environment.
BASIC ASSESSMENT REPORT
37
An EMPr was compiled in order to prevent or minimize any potential negative impacts to the
environment. It will be the responsibility of the applicant and associated contractor to adhere
to all measures set out in the EMPr, in order to give effect to Section 28 (1) of NEMA.
(q) The vital role of women and youth in environmental management and development
must be recognised and their full participation therein must be promoted.
(r) Sensitive, vulnerable, highly dynamic or stressed ecosystems, such as coastal shores,
estuaries, wetlands, and similar systems require specific attention in management and
planning procedures, especially where they are subject to significant human resource
usage and development pressure.
A Sensitivity map containing all vulnerable vegetation, significant water courses and
ecosystems was created in order to ensure that the potential impacts of the proposed project
on such areas will be minimised as far as reasonably possible.
BASIC ASSESSMENT REPORT
38
11. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES
List all legislation, policies and/or guidelines of any sphere of government that are applicable to the application as contemplated in the EIA regulations, if applicable:
Title of legislation, policy or guideline
Applicability to the project Administering authority
Date
Legislation
Constitution of the
Republic of South Africa,
Act No. 108 of 1996
The constitution
recognises the right to a
safe and healthy
environment for all citizens
of the republic. As such,
this forms a guiding
principle of environmental
management.
South African
Government
1996
National Environmental
Management Act (Act
107 of 1998) (NEMA), as
amended, and the EIA
Regulations of 4
December 2014
promulgated in terms of
Section 24(5) of NEMA
and Listing Notices
(Government Notice No.
R. 983 and 985)
The proposed project
triggers activities that
would require
environmental
authorisation to be granted
as set out in GN R No. 983
and GN R No. 985.
Department of
Environmental
Affairs (DEA)
1998,
2014
National Environmental
Management Biodiversity
Act (Act 10 of 2004)
(NEMBA)
Under NEMBA the project
proponent is required to
take appropriate
reasonable measures to
limit the impacts on
biodiversity, to obtain
permits if required and to
invite SANBI to provide
Department of
Environmental
Affairs (DEA) and
South African
National
Biodiversity Institute
(SANBI)
2004
BASIC ASSESSMENT REPORT
39
Title of legislation, policy or guideline
Applicability to the project Administering authority
Date
commentary on any
documentation resulting
from the proposed
development.
National Forests Act (Act
84 of 1998)
The aim of the National
Forests Act is to promote
the sustainable usage,
management and
development of forests for
the benefit of all in South
Africa. The Act also makes
special provisions for the
protection of specific
forests and tree species
which duly require formal
protection in order to
ensure their prolonged
existence.
The National Forests Act
was therefore utilised to
determine the potential
presence of any protected
forests or tree species in
the proposed project area
in order to ensure that the
correct processes are
followed for the approval
of any listed activities for
which a permit may be
necessary regarding such
forests or species, should
it be required.
Department of Agriculture, Forestry and Fisheries (DAFF)
1998
Northern Cape Nature
Conservation Act (Act 9
This Act also makes
provision for the protection Department of Environment and
2009
BASIC ASSESSMENT REPORT
40
Title of legislation, policy or guideline
Applicability to the project Administering authority
Date
of 2009) and sustainable utilisation
of wild animals, aquatic
biota and plants on a
provincial scale in the
Northern Cape Province.
It is therefore used in
conjunction with NEMBA
and the National Forests
Act to determine the
ecological/biodiversity
significance, value and
subsequent management
of the proposed project
area. The Act is also used
to determine the potential
presence of any
provincially protected
species in the proposed
project area in order to
ensure that the correct
processes are followed for
the approval of any listed
activities for which a
permit may be necessary
regarding such species,
should it be required.
Nature Conservation in the Northern Cape Province
National Heritage
Resources Act (Act 25 of
1999) (NHRA)
In terms of section 38 of
the NHRA, Heritage
Impact Assessment (HIA)
is triggered by the
proposed project due to
the linear activity
exceeding 300 m.
South African
Heritage Resources
Association
(SAHRA).
1999
BASIC ASSESSMENT REPORT
41
Title of legislation, policy or guideline
Applicability to the project Administering authority
Date
A case must be opened on
the South African Heritage
Resources Association
(SAHRA) website.
National Water Act (Act
36 of 1998) (NWA)
The development takes
place within a 500 m
radius of a watercourse,
and therefore a water use
license is required with
regards to water uses (c)
and (i) of the NWA.
Department of
Water Affairs and
Sanitation (DWS)
1998
Conservation of
Agricultural Resources
Act (Act No. 43 of 1983)
(CARA)
CARA aims to provide for
the protection and control
over utilisation of the
country’s agricultural
resources in order to
promote conservation of
soils, water and natural
vegetation as well as the
combatting of weeds and
invader plants.
CARA was therefore used
for determining the
agricultural significance,
value and subsequently
the adequate management
of the proposed project
area.
Department of
Agriculture,
Forestry and
Fisheries (DAFF)
and the Department
of Agriculture, Land
Reform and Rural
Development in the
Northern Cape
Province
1983
National Veld and Forest Fire Act, Act No. 101 of 1998
The purpose of the NVFFA
is to prevent and combat
veld, forest and mountain
fires throughout the
Department of Agriculture, Forestry and Fisheries
1998
BASIC ASSESSMENT REPORT
42
Title of legislation, policy or guideline
Applicability to the project Administering authority
Date
Republic. As such, fire
prevention as an aspect of
the EMPr must be
accounted for.
Guidelines
Public Participation
Guideline, 2012
In terms of NEMA, the
Public Participation
Process is required as part
of the Basic Assessment
for this project.
Department of
Environmental
Affairs
2012
Impact Assessment
Guidelines, 2002
To evaluate the
significance of
environmental impacts of
the proposed project.
Department of
Environmental
Affairs
2002
Specialist Studies
Guidelines, 2002
To gather information on
the positive and negative
impacts associated with
the project alternatives. To
determine
recommendations for
mitigation actions that may
either enhance potential
benefits or minimize
harmful effects.
Department of
Environmental
Affairs
2002
Guidelines for
Environmental
Management Plans, 2004
An Environmental
Management Programme
should be included as part
of the BA for this project.
Department of
Environmental
Affairs
2004
Tsantsabane Municipality
Integrated Development
Plan (IDP)
Each municipality is
required to produce an
IDP which would address
Tsantsabane
Municipality
2014/2015
BASIC ASSESSMENT REPORT
43
Title of legislation, policy or guideline
Applicability to the project Administering authority
Date
pertinent issues relevant to
their municipality.
Common concerns include
municipal transformation
and development, and
service delivery and
infrastructural
development. With regards
to the latter, electricity,
amongst other municipal
services, is highlighted as
a priority issue warranting
attention, in particular the
provision of access to
electricity to affected
communities and the
improvement of the
electricity infrastructure
(mini-subs, cables).
Integrated Strategic
Electricity Planning
(ISEP), 2005
The ISEP provides a
framework for Eskom to
investigate a wide range of
new supply-side and
demand-side technologies
with a view to optimising
investments and returns.
Eskom 2005
BASIC ASSESSMENT REPORT
44
12. WASTE, EFFLUENT, EMISSION AND NOISE MANAGEMENT
a) Solid waste management
Will the activity produce solid construction waste during the construction/initiation phase?
YES
If YES, what estimated quantity will be produced per month? Unknown
How will the construction solid waste be disposed of (describe)? All solid waste collected shall be disposed of at the registered/licensed municipal landfill site. Skip waste containers and waste collection bins will be maintained on site and the contractor will arrange for them to be collected regularly when needed and transported to the licensed landfill site. Waste separation will be implemented. Under no circumstances will waste be burned or buried on site. No solid waste shall be produced during operation phase.
Where will the construction solid waste be disposed of (describe)? All construction rubble will be disposed of by the contractor at the registered/licensed municipal landfill site
Will the activity produce solid waste during its operational phase? NO
If YES, what estimated quantity will be produced per month? n/a
How will the solid waste be disposed of (describe)?
n/a
If the solid waste will be disposed of into a municipal waste stream, indicate which registered landfill site will be used.
n/a
Where will the solid waste be disposed of if it does not feed into a municipal waste stream (describe)?
n/a
If the solid waste (construction or operational phases) will not be disposed of in a registered landfill site or be taken up in a municipal waste stream, then the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA.
Can any part of the solid waste be classified as hazardous in terms of the NEM:WA? NO
If YES, inform the competent authority and request a change to an application for scoping and EIA. An application for a waste permit in terms of the NEM:WA must also be submitted with this application.
Is the activity that is being applied for a solid waste handling or treatment facility? NO
If YES, then the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. An application for a waste permit in terms of the NEM:WA must also be submitted with this application.
BASIC ASSESSMENT REPORT
45
b) Liquid effluent
Will the activity produce effluent, other than normal sewage, that will be disposed of in a municipal sewage system?
NO
If YES, what estimated quantity will be produced per month? n/a m3
Will the activity produce any effluent that will be treated and/or disposed of on site? NO
If YES, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA.
Will the activity produce effluent that will be treated and/or disposed of at another facility?
NO
If YES, provide the particulars of the facility:
Facility name: n/a
Contact person:
Postal address:
Postal code:
Telephone: Cell:
E-mail: Fax:
Describe the measures that will be taken to ensure the optimal reuse or recycling of waste water, if any:
n/a
c) Emissions into the atmosphere
Will the activity release emissions into the atmosphere other that exhaust emissions and dust associated with construction phase activities?
NO
If YES, is it controlled by any legislation of any sphere of government? NO
If YES, the applicant must consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. If NO, describe the emissions in terms of type and concentration: Dust and vehicle, construction machine emissions during the construction phase of the proposed development will be the only emissions released into the atmosphere.
d) Waste permit
Will any aspect of the activity produce waste that will require a waste permit in terms of the NEM:WA?
NO
If YES, please submit evidence that an application for a waste permit has been submitted to the competent authority e) Generation of noise
Will the activity generate noise? YES
If YES, is it controlled by any legislation of any sphere of government? NO
BASIC ASSESSMENT REPORT
46
Describe the noise in terms of type and level: The proposed construction of the new 132 kV powerline and decommissioning and diversion of the existing Eskom 132 kV powerline will generate noise during the construction phase. Noise will be generated during vegetation clearing activities, by vehicles transporting equipment, and by construction activities around the powerline. These impacts are not considered to be significant enough to warrant a formal noise impact assessment. During the operational phase, the powerline may produce a corona (low ‘buzzing’ or ‘crackling’ noise). A corona can be caused by water droplets forming on a conductor resulting in the breakdown of air molecules perceived as the crackling noise. However, corona rings will be used on conductors to prevent/reduce the noise. In addition, the transformer within the substation will also produce a low level humming noise. There are however no significant settlements or homesteads in the immediate/close vicinity which will be affected by this type of noise. To ensure that the noise generated during the construction phase is minimised, the following mitigation measures are proposed (these will be included in the Environmental Management Programme for the project, attached as Appendix G):
All equipment used on site shall be fitted with suitable silencers to control noise pollution;
The following will prevail:
Unless otherwise specified by the EO/ECO, normal working hours will apply (i.e. from 06h30 to 17h00, Mondays to Fridays);
Ensure that employees and staff conduct themselves in an acceptable manner while on site, both during work hours and after hours;
No loud music will be permitted on site or in the site camp.
If blasting is required during the construction period of the 132 kV power line, the following guidelines will be followed:
The type, duration and timing of the blasting procedures will be planned with due cognisance of other land uses and structures in the vicinity;
The local landowners and communities will be adequately informed ahead of any blasting event;
The use of nitrate-free explosives will be favoured wherever possible (i.e. methods including drilling and black powder, expanding mortar or old fashioned plugs and feathers);
Noise mufflers and/or soft explosives will be used by staff during blasting;
Appropriate measures to limit undesired flyrock will be taken;
Audible warning of a pending blast will be given at least 3 minutes in advance of a blast; and
All flyrock (of diameter 150mm and larger) which falls beyond the cleared working area, together with the rock spill, will be collected and removed.
BASIC ASSESSMENT REPORT
47
13. WATER USE
Please indicate the source(s) of water that will be used for the activity by ticking the appropriate box(es):
Municipal
If water is to be extracted from groundwater, river, stream, dam, lake or any other natural feature, please indicate the volume that will be extracted per month:
n/a
Does the activity require a water use authorisation (general authorisation or water use license) from the Department of Water Affairs?
YES
If YES, please provide proof that the application has been submitted to the Department of Water Affairs.
See Appendix I for the confirmation of water use letter received from the municipality.
The project requires a Water Use License from the Department of Water and Sanitation (DWS) for construction within 500m of a wetland. A pre-application meeting was conducted with DWS on 15 July 2016 and an application will be submitted to DWS (see proof of pre-application meeting in Appendix I).
The proof of application submission will be included in the Final Basic Assessment Report.
14. ENERGY EFFICIENCY
Describe the design measures, if any, which have been taken to ensure that the activity is energy efficient: The activity will not use electricity but rather distribute electricity to a substation from where it is divided into smaller voltages for distribution to end-users.
Describe how alternative energy sources have been taken into account or been built into the design of the activity, if any: Not applicable to this project given that the activity does not utilise electricity but rather distributes it.
BASIC ASSESSMENT REPORT
48
SECTION B: SITE/AREA/PROPERTY DESCRIPTION Important notes: 1. For linear activities (pipelines, etc) as well as activities that cover very large sites, it may be
necessary to complete this section for each part of the site that has a significantly different environment. In such cases please complete copies of Section B and indicate the area, which is covered by each copy No. on the Site Plan.
Section B Copy No. (e.g. A): n/a
2. Paragraphs 1 - 6 below must be completed for each alternative.
3. Has a specialist been consulted to assist with the completion of this section? YES
If YES, please complete the form entitled “Details of specialist and declaration of interest” for each specialist thus appointed and attach it in Appendix J. All specialist reports must be contained in Appendix D.
See specialist declarations of interest in Appendix J
See specialist reports in Appendix D Property description/physical address:
BASIC ASSESSMENT REPORT
49
Province Northern Cape Province
District Municipality
ZF Mgcawu District Municipality
Local Municipality Tsantsabane Local Municipality
Ward number(s) Hay Road Ward 3
All farms fall within the same district and local municipality
Farm name(s) and number(s)
Farm Kapstewel No. 436
Portion number(s) Remaining Extent
SG Code C 03100000000043600000
Farm name(s) and number(s)
Farm No. 437
Portion number(s) Remaining Extent
SG Code C 03100000000043700000
Farm name(s) and number(s)
Farm No. 588
Portion number(s) Remaining Extent
SG Code C 03100000000058800000
Farm name(s) and number(s)
Farm No. 589
Portion number(s) Remaining Extent
SG Code C 03100000000058900000
Farm name(s) and number(s)
Farm No. 589
Portion number(s) Portions 8
SG Code C 03100000000058900008
Farm name(s) and number(s)
Farm No. 589
Portion number(s) Portions 14
SG Code C 03100000000058900014
Farm name(s) and number(s)
Farm Groenwater No 453
Portion number(s) Remaining Extent
SG Code C 03100000000045300000
Farm name(s) and number(s)
Farm Groenwater No 453
Portion number(s) Portion 3
SG Code C 03100000000045300003
Where a large number of properties are involved (e.g. linear activities), please attach a full list to this application including the same information as indicated above.
BASIC ASSESSMENT REPORT
50
Farm name(s) and number(s)
Farm Groenwater No 453
Portion number(s) Portion 4
SG Code C 03100000000045300004
Farm name(s) and number(s)
Farm Groenwater No 453
Portion number(s) Portion 5
SG Code C 03100000000045300005
Current land-use zoning as per local municipality IDP/records:
The proposed project will traverse through land zoned as agricultural land (stock farm with or without dwellings).
In instances where there is more than one current land-use zoning, please attach a list of current land use zonings that also indicate which portions each use pertains to, to this application.
See Appendix E for current land uses
Is a change of land-use or a consent use application required? YES
See Appendix E for land owner consent letter letters. 15. GRADIENT OF THE SITE
Indicate the general gradient of the site. Proposed new 132 kV powerline: Alternative 1 (preferred):
Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5
Alternative 2:
Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5
Decommissioning and diversion of existing powerline: Alternative 1 (preferred):
Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5
Alternative 2:
Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5
BASIC ASSESSMENT REPORT
51
16. LOCATION IN LANDSCAPE
Indicate the landform(s) that best describes the site:
2.1 Ridgeline 2.4 Closed valley 2.7 Undulating plain / low hills X
2.2 Plateau 2.5 Open valley 2.8 Dune
2.3 Side slope of hill/mountain 2.6 Plain X 2.9 Seafront
2.10 At sea
17. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE
Is the site(s) located on any of the following? Proposed new 132 kV powerline: Alternative 1
(preferred): Alternative 2:
Shallow water table (less than 1.5m deep) YES YES
Dolomite, sinkhole or doline areas NO NO
Seasonally wet soils (often close to water bodies)
YES
YES
Unstable rocky slopes or steep slopes with loose soil
NO
NO
Dispersive soils (soils that dissolve in water) NO NO
Soils with high clay content (clay fraction more than 40%)
NO
NO
Any other unstable soil or geological feature NO NO
An area sensitive to erosion NO NO
Decommissioning and diversion of existing powerline: Alternative 1
(preferred): Alternative 2:
Shallow water table (less than 1.5m deep) NO NO
Dolomite, sinkhole or doline areas NO NO
Seasonally wet soils (often close to water bodies)
NO
NO
Unstable rocky slopes or steep slopes with loose soil
NO
NO
Dispersive soils (soils that dissolve in water) NO NO
Soils with high clay content (clay fraction more than 40%)
NO
NO
Any other unstable soil or geological feature NO NO
An area sensitive to erosion NO NO
If you are unsure about any of the above or if you are concerned that any of the above aspects may be an issue of concern in the application, an appropriate specialist should be appointed to assist in the completion of this section. Information in respect of the above will often be available as part of the
BASIC ASSESSMENT REPORT
52
project information or at the planning sections of local authorities. Where it exists, the 1:50 000 scale Regional Geotechnical Maps prepared by the Council for Geo Science may also be consulted. 18. GROUNDCOVER
Indicate the types of groundcover present on the site. The location of all identified rare or endangered species or other elements should be accurately indicated on the site plan(s).
Natural veld - good conditionE
Natural veld with scattered aliensE
Natural veld with heavy alien infestationE
Veld dominated by alien speciesE
Gardens
Sport field Cultivated land Paved surface Building or other structure
Bare soil
If any of the boxes marked with an “E “is ticked, please consult an appropriate specialist to assist in the completion of this section if the environmental assessment practitioner doesn’t have the necessary expertise. See Appendix D for specialist reports
19. SURFACE WATER
Indicate the surface water present on and or adjacent to the site and alternative sites? Proposed new 132 kV powerline: Alternative 1
(preferred): Alternative 2:
Perennial River No No
Non-Perennial River Yes Yes
Permanent Wetland No No
Seasonal Wetland Yes Yes
Artificial Wetland No No
Estuarine / Lagoonal wetland No No
If any of the boxes marked YES or UNSURE is ticked, please provide a description of the relevant watercourse. In accordance with the specialist report (See Appendix D), both alternatives 1 and 2 will cross a number of small seasonal watercourses. These streams are all classified as first order streams meaning they are headwater streams, which only flow when it is raining in their catchments. These seasonal streams are sodic sites with high concentrations of salts in them. Moderately modified. The Present Ecological Status (PES) of these watercourses have been classified as class C by the specialist meaning that loss and change of natural habitat and biota have occurred, but the basic ecosystem functions are still predominantly unchanged.
Both alternatives 1 and 2 will also pass in close proximity (within 500 m) to a number of small seasonal wetlands and salt pans.
BASIC ASSESSMENT REPORT
53
Decommissioning and diversion of existing powerline: Alternative 1
(preferred): Alternative 2:
Perennial River No No
Non-Perennial River No No
Permanent Wetland No No
Seasonal Wetland No No
Artificial Wetland No No
Estuarine / Lagoonal wetland No No
If any of the boxes marked YES or UNSURE is ticked, please provide a description of the relevant watercourse.
n/a
A water use license application will be submitted to the Department of Water and Sanitation (DWS) for developing within 500 m of a watercourse.
See Appendix I for proof of pre-application meeting for a WULA held with DWS on 15 July 2016.
20. LAND USE CHARACTER OF SURROUNDING AREA
Indicate land uses and/or prominent features that currently occur within a 500 m radius of the site and give description of how this influences the application or may be impacted upon by the application: Natural area Dam or reservoir Polo fields
Low density residential Hospital/medical centre Filling station H
Medium density residential School Landfill or waste treatment site
High density residential Tertiary education facility Plantation Informal residential A Church Agriculture
Retail commercial & warehousing Old age home River, stream or wetland
Light industrial Sewage treatment plantA Nature conservation area
Medium industrial AN Train station or shunting yard N Mountain, koppie or ridge
Heavy industrial AN Railway line N Museum
Power station Major road (4 lanes or more) N Historical building
Office/consulting room Airport N Protected Area
Military or police base/station/compound
Harbour Graveyard
Spoil heap or slimes damA Sport facilities Archaeological site
Quarry, sand or borrow pit Golf course Other land uses (describe)
If any of the boxes marked with an “N “are ticked, how will this impact / be impacted upon by the proposed activity? Specify and explain:
n/a
BASIC ASSESSMENT REPORT
54
If any of the boxes marked with an "An" are ticked, how will this impact / be impacted upon by the proposed activity? Specify and explain:
n/a
If any of the boxes marked with an "H" are ticked, how will this impact / be impacted upon by the proposed activity? Specify and explain:
n/a
Does the proposed site (including any alternative sites) fall within any of the following:
Critical Biodiversity Area (as per provincial conservation plan) YES
Core area of a protected area? NO
Buffer area of a protected area? NO
Planned expansion area of an existing protected area? NO
Existing offset area associated with a previous Environmental Authorisation? NO
Buffer area of the SKA? NO
If the answer to any of these questions was YES, a map indicating the affected area must be included in Appendix A (Sensitivity map).
See Appendix A for Sensitivity map 21. CULTURAL/HISTORICAL FEATURES
Are there any signs of culturally or historically significant elements, as defined in section 2 of the National Heritage Resources Act, 1999, (Act No. 25 of 1999), including Archaeological or paleontological sites, on or close (within 20m) to the site? If YES, explain:
NO
Noting significant within the proposed servitude area or in the immediate vicinity.
If uncertain, conduct a specialist investigation by a recognised specialist in the field (archaeology or palaeontology) to establish whether there is such a feature(s) present on or close to the site. Briefly explain the findings of the specialist:
BASIC ASSESSMENT REPORT
55
The Specialist Heritage Impact Assessments found no significant heritage artefacts or potential areas to be preserved or further investigated. See Appendix D for specialist reports.
Conclusion from Archaeological Impact Assessment Report
Seven archaeological and cultural heritage sites are situated within, or in proximity to the
approximate 150 m assessment corridor of the proposed Metsimatala 150MW CSP Solar
Energy Facility – Power Lines study site. Of the identified sites three constitute cemetery
sites, two of which, Site MVIA3 and MPL3, are located within the assessment corridor. Site
MPL1, a newly identified cemetery is situated more than 2 km from the proposed Power
Line Option A alignment. Three sites are classed as Colonial Period farmstead sites,
namely Sites MPL2, HH-PL1 and HH-PL2. All identified Colonial Period farmsteads are
situated in proximity to the assessment corridor only; none of the sites will be impacted by
development. Site G-S1, a Colonial Period/contemporary mining complex, is also situated
in proximity to the assessment corridor only and will not be impacted by development. The
two cemetery sites situated within the assessment corridor (Sites MVIA3 and MPL3)
need to be conserved: Formal conservation of Site MVIA3 is recommended, while
formal conservation measures are already in place at Site MPL3 – inferred to be the
result of heritage compliance relating to construction of the exiting power line. The
identification of three cemetery sites during the field assessment, cautions against the
possibility that poorly demarcated or unmarked graves may be discovered during the
course of construction. Realignment: Site MVIA3 is situated along proposed Realignment
Option A. Recommended conservation measures should suffice for purposes of
development.
Powerline:
Site MPL3 is situated along Power Line alternative 2. Permanent conservation measures,
complying with SAHRA Minimum Standards for site conservation are already in place,
inferred to be the result of heritage compliance relating to development of the existing
power line. From an archaeological and cultural heritage perspective neither of the power
line options, Power Line alternative 1 or Power Line alternative 2, poses a threat to
identified sites. It is therefore recommended that development of the approved power lines
proceed without the developer having to comply with additional heritage compliance
requirements pertaining to lithic Stone Age deposits, such as Phase 2 mitigation, prior to
construction impact.
BASIC ASSESSMENT REPORT
56
Conclusion from Palaeontological Impact Assessment Report
The footprints of route Alternatives 1 & 2 traverse Asbestos Hills (Vak, Vad), Quaternary
windblown sand and Campbellrand (Vgl) Subgroup strata, respectively considered to be of
moderate, low and moderate palaeontological sensitivity. Given the nature of the proposed
development (erection of pylons and creation of road servitudes), direct impact on potential
fossil heritage within the section mantled by Quaternary windblown sand is considered to be
low. This section is assigned a site rating of Generally Protected C (GP.C). Direct impact on
potential fossil heritage within the section underlain by Campbellrand (Vgl) and Asbestos
Hills (Vad, Vak) Subgroup strata, is considered to be low to moderate. There are no major
palaeontological grounds to halt the development of the preferred Alternative Route 1 or 2,
but it is advised that sites marked for erection of pylons or construction of associated
infrastructure, which will require excavation into fresh bedrock sediments of the
Campbellrand and Asbestos Hills Subgroup, is mapped and recorded prior to the
construction phase of the development. These sections are assigned a site rating of
Generally Protected B (GP.B).
Route alternative 2 for the diversion of the existing power line may potentially traverse
Griquatown Formation iron stones (Vad) considered to be of moderate palaeontological
sensitivity. The footprint is primarily mantled by a Quaternary windblown sand overburden
that is underlain by Postmasburg Group lavas and subordinate siliclastic sediments of the
Ongeluk Formation (Vo), considered to be of moderate palaeontological sensitivity. Given
the nature of the proposed development (erection of pylons and creation of road servitudes),
direct impact on potential fossil heritage within the section underlain by Griquatown
Formation, and mantled by Quaternary windblown sand is considered to be low. Direct
impact on potential fossil heritage within the section underlain by Postmasburg Group strata
is considered to be low. There are no major palaeontological grounds to halt this
development and it is exempted from further palaeontological investigation. The proposed
footprint is assigned a site rating of Generally Protected C (GP.C).
Route Alternative 2 for diversion of the existing power line traverses Asbestos Hills (Vak,
Vad), Postmasburg Group lavas and Quaternary windblown sand, respectively considered to
be of moderate and low palaeontological sensitivity. Given the nature of the proposed
development (erection of pylons and creation of road servitudes), direct impact on potential
fossil heritage within the section mantled by Quaternary windblown sand is considered to be
low. This section is assigned a site rating of Generally Protected C (GP.C). Direct impact on
potential fossil heritage within the section underlain Asbestos Hills (Vad, Vak) Subgroup
strata, is considered to be low to moderate. There are also no major palaeontological
BASIC ASSESSMENT REPORT
57
grounds to halt the development of Alternative Route 1 or 2, but it is advised that sites
marked for erection of pylons or construction of associated infrastructure, which will require
excavation into fresh bedrock sediments of the Asbestos Hills Subgroup, is mapped and
recorded prior to the construction phase of the development. These sections are assigned a
site rating of Generally Protected B (GP.B).
Will any building or structure older than 60 years be affected in any way?
NO
Is it necessary to apply for a permit in terms of the National Heritage Resources Act, 1999 (Act 25 of 1999)?
NO
If YES, please provide proof that this permit application has been submitted to SAHRA or the relevant provincial authority. 22. SOCIO-ECONOMIC CHARACTER
a) Local Municipality Please provide details on the socio-economic character of the local municipality in which the proposed site(s) are situated. Level of unemployment: According to the stats the unemployment figure has drastically reduced from 4466 in 2001 to 3795 in 2011 which shows a decrease of -15%. Employment has increased with 69% in 2011, which translates into more people working in 2011 than 2001. The proposed project will positively assist in further reducing unemployment by means of job creation and skills development mainly during the construction but also the subsequent operational phase of the proposed project.
Adapted from Tsantsabane Municipality IDP (2014-2015)
Economic profile of local municipality: The population figures in terms of census 2011 is 35 093 compared to 31 014 in 2001. The male population has increased by 24% while the female population has increased by only
BASIC ASSESSMENT REPORT
58
2.7% since 2001. These increases can be relatively influenced by job migration and other factors.
Adapted from Tsantsabane Municipality IDP (2014-2015)
Level of education: The statistics indicate that although there is a high number of students enrolling for primary school, a very low number of students actually complete Grade 12. This results in a significantly reduced low probability for employment. Only 5 % of those who enrolled for Grade 1 successfully proceed into tertiary education. Less than 15 % of the population has a tertiary qualification or have completed Grade 12.
It must, however, be mentioned that the education level is affected negatively by the urbanization process as it mostly involves matriculants and those with a better qualification who tend to move to the bigger cities for employment opportunities due to the lack of local job opportunities.
BASIC ASSESSMENT REPORT
59
Adapted from Tsantsabane Municipality IDP (2014-2015)
b) Socio-economic value of the activity
What is the expected capital value of the activity on completion? R 175 million
What is the expected yearly income that will be generated by or as a result of the activity?
Not applicable.
Will the activity contribute to service infrastructure? YES
Is the activity a public amenity? YES
How many new employment opportunities will be created in the development and construction phase of the activity/ies?
30 temporary jobs
What is the expected value of the employment opportunities during the development and construction phase?
R 3.6 million
What percentage of this will accrue to previously disadvantaged individuals? 60 % - 90 %
How many permanent new employment opportunities will be created during the operational phase of the activity?
None, once the construction is completed the powerline will be handed over to Eskom.
What is the expected current value of the employment opportunities during the first 10 years?
Not applicable as it will be transferred to Eskom.
What percentage of this will accrue to previously disadvantaged individuals? Not applicable as it will be transferred to Eskom.
BASIC ASSESSMENT REPORT
60
23. BIODIVERSITY
Please note: The Department may request specialist input/studies depending on the nature of the biodiversity occurring on the site and potential impact(s) of the proposed activity/ies. To assist with the identification of the biodiversity occurring on site and the ecosystem status consult http://bgis.sanbi.org or [email protected]. Information is also available on compact disc (cd) from the Biodiversity-GIS Unit, Ph (021) 799 8698. This information may be updated from time to time and it is the applicant/ EAP’s responsibility to ensure that the latest version is used. A map of the relevant biodiversity information (including an indication of the habitat conditions as per (b) below) and must be provided as an overlay map to the property/site plan as Appendix D to this report. a) Indicate the applicable biodiversity planning categories of all areas on site and indicate
the reason(s) provided in the biodiversity plan for the selection of the specific area as part of the specific category)
Systematic Biodiversity Planning Category If CBA or ESA, indicate the reason(s) for its selection in biodiversity plan
Critical Biodiversity Area (CBA)
Ecological Support
Area (ESA)
Other Natural
Area (ONA)
No Natural Area
Remaining (NNR)
The small area classified as a CBA (see
sensitivity map in Appendix A) where the
proposed powerline traverses, is due to
the presence of a NFEPA categorised
watercourse. The powerline will be
constructed across the watercourse and
should cause minimal impact.
ESA’s are included due to the fact that
less than 10 % of the surface has been
transformed or degraded. Belonging to
this category are mostly natural land that
are considered to represent prime
corridor areas.
Other Natural Areas are natural
vegetation that has not been classified as
CBA or ESA.
See Appendix A for the Sensitivity map indicating the presence of CBA’s and ESA’s b) Indicate and describe the habitat condition on site
Habitat Condition
Percentage of habitat
condition class (adding up to 100%)
Description and additional Comments and Observations
(including additional insight into condition, e.g. poor land management practises, presence of quarries,
grazing, harvesting regimes etc).
Natural % 80
Near Natural (includes areas with
low to moderate level %
20
BASIC ASSESSMENT REPORT
61
of alien invasive plants)
Degraded (includes areas
heavily invaded by alien plants)
%
Transformed (includes cultivation,
dams, urban, plantation, roads, etc)
%
c) Complete the table to indicate:
(i) the type of vegetation, including its ecosystem status, present on the site; and (ii) whether an aquatic ecosystem is present on site.
Terrestrial Ecosystems Aquatic Ecosystems
Ecosystem threat status as per the
National Environmental Management:
Biodiversity Act (Act No. 10 of 2004)
Critical Wetland (including rivers, depressions, channelled and unchanneled wetlands, flats,
seeps pans, and artificial wetlands)
Estuary Coastline Endangered
Vulnerable
Least Threatened YES NO NO
See Appendix A for the Vegetation map indicating the vegetation types
BASIC ASSESSMENT REPORT
62
d) Please provide a description of the vegetation type and/or aquatic ecosystem present on site, including any important biodiversity features/information identified on site (e.g. threatened species and special habitats)
BASIC ASSESSMENT REPORT
63
The following section was extracted from the specialist Ecological Impact
Assessment report (see Appendix D for full specialist report)
Vegetation Types
The four vegetation types through which the proposed powerline route crosses and the
Metsimatala Solar substation is situated are the Olifantshoek Plains Thornveld (SVk 13);
Kuruman Mountain Bushveld (SVk 10); Postmasburg Thornveld (SVk 14) and Kuruman
Thornveld (SVk 9). They are all classified as least threatened by Mucina & Rutherford,
2006.
The decommissioning and diversion of the existing Eskom powerline is situated in the
Olifantshoek Plains Thornveld (SVk 13); and the Kuruman Mountain Bushveld (SVk 10)
vegetation types which are both least threatened (Mucina & Rutherford, 2006).
The proposed powerline route also crosses through a small portion classified as a Critical
Biodiversity Area as well as a small portion classified as an Ecological Support Area (see
Appendix A for Sensitivity map). The reason for the CBA classification is due to the
presence of a NFEPA categorised watercourse.
Protected Species
The Ecological Impact Assessment identified a number of nationally and provincially
protected plant species in the vicinity of the proposed powerline route.
Shepherd’s Tree (Boscia albitrunca), the Camel Thorn (Acacia erioloba) and False Camel
Thorn (Acacia haematoxylon) are three nationally protected tree species which are present
in the proposed project area. If any individuals of these species are to be impacted by the
construction of the powerline, permits will firstly have to be obtained for the removal or
relocation of these individuals prior to the constriction activities.
The Ecological Impact Assessment identified a number of seasonal streams which the
proposed powerline route will cross as well as a number of seasonal pans and wetlands in
close proximity to the proposed powerline route. A water use license application will be
submitted due to the development activities crossing watercourses and taking place within
500 m of a watercourse.
Conclusion
There are some sensitive systems which would be affected by the proposed power line
routes. They include the rocky outcrops of the Kuruman Mountain Bushveld (SVk10) and
the episodic streams as well small wetlands/pans on the plains between the rocky ridges.
No Red or Orange data species were found to occur along the powerline routes although a
protected species namely Olea europaea subsp. africana occur on the rocky outcrops
while Acacia erioloba, Acacia haematoxylon and Boscia albitrunca occur on sandy plains.
From an ecological perspective either route alternative 1 or 2 can be utilised due to their
relatively similar impacts.
BASIC ASSESSMENT REPORT
64
The following section was extracted from the specialist Avifaunal Impact Assessment
report (see Appendix D for full specialist report)
Conclusion
Based on a thorough desk based study and three seasonal site surveys conducted over a
6 month period, it can be concluded that the project site has a moderate sensitivity in terms
of avifauna.
The species of most concern are the Critically Endangered White-backed Vulture and the
Endangered Martial Eagle. It was noted though that the former species was recorded on one
occasion only in the surveys conducted and has a generally low reporting rate in the SABAP
data considered. A pair of Martial Eagle was seen regularly in the summer and the
abundance and flight activity levels of all raptors and priority species recorded on the project
site was generally relatively low. Other species of concern included Lanner Falcon, Black-
chested Snake Eagle, Greater Kestrel, Northern Black Korhaan and Ludwig’s Bustard,
although the latter was not recorded on the project site during the surveys. Northern Black
Korhaan was relatively abundant and, although believed to be less at risk from burning
impacts, is at high risk from collisions with powerlines and disturbance and displacement
impacts.
Although a relatively diverse number of species and a high number of Red Data species
were found to be potentially present after examining the SABAP data, many of these species
were not recorded by monitoring, and many are unlikely to occur on the project site due to
unsuitable habitat. In most cases the frequency of records and the activity (especially flight
activity) of priority species and Red Data species on the project site was low. Vantage point
passage rates were also particularly low when compared with the specialists experience in
other parts of South Africa.
Commercial scale solar farms, and particularly CSP developments, are relatively new in
South Africa and little information therefore exists on the potential impacts of these
technologies on South African avifauna. Some information is available internationally which
shows that the main potential impacts may include: burning; collision; electrocution;
disturbance and displacement; habitat destruction; water pollution; and excessive use of
water. Impacts of associated infrastructure (e.g. the grid connection power lines) are
however well understood.
BASIC ASSESSMENT REPORT
65
For the Grid Connection, the residual impacts of habitat destruction, collision and
electrocution were all found to have a medium significance rating after mitigation, with all
other impacts having a low rating. This indicates that either route alternative is acceptable
from an avifaunal perspective with neither being preferred. Similar ratings were obtained for
the powerline diversion, and both route alternatives are acceptable, with alternative two
being slightly preferred only as it runs along the main tar road.
BASIC ASSESSMENT REPORT
66
SECTION C: PUBLIC PARTICIPATION 24. ADVERTISEMENT AND NOTICE
Publication name Ghaap newspaper & Kalahari Bulletin
Date published Ghaap: Friday 29 July 2016 & Kalahari Bulletin Thursday 21 July 2016
Site notice position Latitude Longitude Will be completed for Final BA Report submission
Date placed Will be completed for Final BA Report submission
Include proof of the placement of the relevant advertisements and notices in Appendix E1. See Appendix E for all proof in the Public Participation Process Report (the PPP
Report will be completed after conclusion of the PPP and will therefore only be submitted with the Final Basic Assessment Report)
25. DETERMINATION OF APPROPRIATE MEASURES
Provide details of the measures taken to include all potential I&APs as required by Regulation 41(2)(e) and 41(6) of GN 733.
A comprehensive Public Participation Process (PPP) will be undertaken with all stakeholders
and Interested and Affected Parties (I & AP’s), including the relevant Organs of State and
competent authority (Department of Environmental Affairs DEA) as identified.
The PPP will be conducted in accordance with the requirements of Regulation 41 of the EIA
Regulations, 2014 and the designated Public Participation Officer will ensure that the PPP is
facilitated in a manner which ensures reasonable opportunity for all stakeholders and
registered I & AP’s to comment and provide input on the proposed project.
Notifications have been placed in two local free, newspapers (Ghaap newspaper on 29
July 2016 and Kalahari Bulletin on 21 July 2016).
Site notices have will be placed at the entrance to the proposed site location,
Postmasburg Municipal Offices, public library as well as the entrance to the
Metsimatala local informal settlement.
Hardcopies of the report will be placed at the Postmasburg Municipal Offices and the
public library.
A comprehensive list of stakeholders was identified during the PPP of the proposed
CSP facility. This list will be utilised for the purposes of the powerline PPP as well.
A notification email will be sent to all stakeholders and I & AP’s.
BASIC ASSESSMENT REPORT
67
Key stakeholders (other than organs of state) identified in terms of Regulation 41(2)(b) of GN 733 Title, Name and Surname Affiliation/ key stakeholder status
Contact details (tel number or e-mail address)
M Mathobela Municipal Manager Postmasburg [email protected]
Cecile Mathe Municipal Environmental Officer [email protected]
Theys Julius Municipal Environmental Officer [email protected]
Andrea van Gense ESKOM [email protected]
Jolene van Wyk-Towell Department of Water and Sanitation [email protected]
Lerato Mokhoantle Department of Water and Sanitation [email protected]
K Bosman Ward counsilor (Ward 3) [email protected]
Kelly Hannie Northern Cape Department of Roads and Public Works [email protected]
Muhammad Essop DEA - Competent Authority [email protected]
Tsholo Makaudi NCDENC - Commenting Authority [email protected]
I Manyane Northern Cape Department of Social Development [email protected]
Phillip Hine SAHRA [email protected]
Kagisho Lekwene Landowner (Groenwater CPA) [email protected]
Denise SA Astronomy [email protected]
Harry Roberts SA Civil Aviation [email protected]
Vincent Muila DMR [email protected]
N Yede
Northern Cape Department of Agriculture, Land Reform and Rural Development [email protected]
Dennis Seemela NERSA [email protected]
Simon Gear BirdlifeSA [email protected]
Henning Myburg Agri Noordkaap [email protected]
Stanley Tshitwamulomoni Seoka Lekota
DEA: Biodiversity and Conservation Directorate
[email protected] [email protected]
Include proof that the key stakeholder received written notification of the proposed activities as Appendix E2. This proof may include any of the following:
e-mail delivery reports;
registered mail receipts;
courier waybills;
signed acknowledgements of receipt; and/or
or any other proof as agreed upon by the competent authority. See Appendix E for all proof in the Public Participation Process Report (the PPP
Report will be completed after conclusion of the PPP and will therefore only be submitted with the Final Basic Assessment Report)
BASIC ASSESSMENT REPORT
68
26. ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES
Summary of main issues raised by I&APs Summary of response from EAP
All issues raised during the PPP will be included into the Final Basic Assessment Report
27. COMMENTS AND RESPONSE REPORT
The practitioner must record all comments received from I&APs and respond to each comment before the Draft BAR is submitted. The comments and responses must be captured in a comments and response report as prescribed in the EIA regulations and be attached to the Final BAR as Appendix E3. See Appendix E for all proof in the Public Participation Process Report (the PPP
Report will be completed after conclusion of the PPP and will therefore only be submitted with the Final Basic Assessment Report)
28. AUTHORITY PARTICIPATION
Authorities and organs of state identified as key stakeholders:
Authority/Organ of State
Contact person (Title, Name and Surname)
Tel No e-mail
Municipal Manager Postmasburg
M Mathobela 053 313 7300 [email protected]
Municipal Environmental Officer
Cecile Mathe 083 388 6263 [email protected]
Municipal Environmental Officer
Theys Julius 083 634 1385 [email protected]
ESKOM Andrea van Gense
082 482 7579 [email protected]
Department of Water and Sanitation
Jolene van Wyk-Towell
054 338 5800 [email protected]
Department of Water and Sanitation
Lerato Mokhoantle
053 836 7600 [email protected]
Ward counsilor (Ward 3) K Bosman
053 313 7300/0781343101
Northern Cape Department of Roads and Public Works Kelly Hannie
053 839 2249
DEA - Competent Authority
Muhammad Essop 012 399 9406 [email protected]
NCDENC - Commenting Tsholo Makaudi 053 807 7300 [email protected]
BASIC ASSESSMENT REPORT
69
Authority
Northern Cape Department of Social Development I Manyane 053 874 4832 [email protected]
SAHRA Phillip Hine 021 462 4502 [email protected]
SA Astronomy Denise 021 447 0025 [email protected]
SA Civil Aviation Harry Roberts 011 545 1071 [email protected]
DMR Vincent Muila 053 870 1716 [email protected]
Northern Cape Department of Agriculture, Land Reform and Rural Development N Yede 053 838 9100 [email protected]
NERSA Dennis Seemela 012 4014794 [email protected]
Agri Noordkaap Henning Myburg 053 8329595 [email protected]
DEA: Biodiversity and Conservation Directorate
Stanley Tshitwamulomoni Seoka Lekota 012 399 9573
[email protected] [email protected]
Include proof that the Authorities and Organs of State received written notification of the proposed activities as appendix E4. In the case of renewable energy projects, Eskom and the SKA Project Office must be included in the list of Organs of State. See Appendix E for all proof in the Public Participation Process Report (the PPP
Report will be completed after conclusion of the PPP and will therefore only be submitted with the Final Basic Assessment Report)
29. CONSULTATION WITH OTHER STAKEHOLDERS
Note that, for any activities (linear or other) where deviation from the public participation requirements may be appropriate, the person conducting the public participation process may deviate from the requirements of that sub-regulation to the extent and in the manner as may be agreed to by the competent authority. Proof of any such agreement must be provided, where applicable. Application for any deviation from the regulations relating to the public participation process must be submitted prior to the commencement of the public participation process. A list of registered I & APs must be included as appendix E5. Copies of any correspondence and minutes of any meetings held must be included in Appendix E6. See Appendix E for all proof in the Public Participation Process Report (the PPP
Report will be completed after conclusion of the PPP and will therefore only be submitted with the Final Basic Assessment Report)
BASIC ASSESSMENT REPORT
70
SECTION D: IMPACT ASSESSMENT The assessment of impacts must adhere to the minimum requirements in the EIA Regulations, 2014 and should take applicable official guidelines into account. The issues raised by interested and affected parties should also be addressed in the assessment of impacts.
30. IMPACTS THAT MAY RESULT FROM THE PLANNING AND DESIGN, CONSTRUCTION, OPERATIONAL, DECOMMISSIONING AND CLOSURE PHASES AS WELL AS PROPSOED MANAGEMENT OF IDENTIFIED IMPACTS AND PROPSOED MITIGATION MEASURES
Provide a summary and anticipated significance of the potential direct, indirect and cumulative impacts that are likely to occur as a result of the planning and design phase, construction phase, operational phase, decommissioning and closure phase, including impacts relating to the choice of site/activity/technology alternatives as well as the mitigation measures that may eliminate or reduce the potential impacts listed. This impact assessment must be applied to all the identified alternatives to the activities identified in Section A (2) of this report. Methodology
The tables below indicate and explain the methodology and criteria used for the
evaluation of the Environmental Risk Ratings as well as the calculation of the final
Environmental Significance Ratings of the identified potential environmental impacts.
Each potential environmental impact is scored for each of the Evaluation
Components as per table below.
Evaluation Component
Rating Scale and Description/criteria
MAGNITUDE of NEGATIVE IMPACT (at the
indicated spatial scale)
10 - Very high: Bio-physical and/or social functions and/or processes might be severely altered.
8 - High: Bio-physical and/or social functions and/or processes might be considerably altered.
6 - Medium: Bio-physical and/or social functions and/or processes might be notably altered.
4 - Low : Bio-physical and/or social functions and/or processes might be slightly altered.
2 - Very Low: Bio-physical and/or social functions and/or processes might be negligibly altered.
0 - Zero: Bio-physical and/or social functions and/or processes will remain unaltered.
10 - Very high (positive): Bio-physical and/or social functions and/or processes might be substantially
enhanced.
MAGNITUDE of POSITIVE IMPACT (at the
indicated spatial scale)
8 - High (positive): Bio-physical and/or social functions and/or processes might be considerably
enhanced.
6 - Medium (positive): Bio-physical and/or social functions and/or processes might be notably
enhanced.
4 - Low (positive): Bio-physical and/or social functions and/or processes might be slightly enhanced.
2 - Very Low (positive): Bio-physical and/or social functions and/or processes might be negligibly
enhanced.
0 - Zero (positive): Bio-physical and/or social functions and/or processes will remain unaltered.
BASIC ASSESSMENT REPORT
71
DURATION
5 - Permanent
4 - Long term: Impact ceases after operational phase/life of the activity > 60 years.
3 - Medium term: Impact might occur during the operational phase/life of the activity – 60 years.
2 - Short term: Impact might occur during the construction phase - < 3 years.
1 - Immediate
5 - International: Beyond National boundaries.
EXTENT
(or spatial scale/influence of impact)
4 - National: Beyond Provincial boundaries and within National boundaries.
3 - Regional: Beyond 5 km of the proposed development and within Provincial boundaries.
2 - Local: Within 5 km of the proposed development.
1 - Site-specific: On site or within 100 m of the site boundary.
0 - None
IRREPLACEABLE
loss of resources
5 – Definite loss of irreplaceable resources.
4 – High potential for loss of irreplaceable resources.
3 – Moderate potential for loss of irreplaceable resources.
2 – Low potential for loss of irreplaceable resources.
1 – Very low potential for loss of irreplaceable resources.
0 - None
REVERSIBILITY
of impact
5 – Impact cannot be reversed.
4 – Low potential that impact might be reversed.
3 – Moderate potential that impact might be reversed.
2 – High potential that impact might be reversed.
1 – Impact will be reversible.
0 – No impact.
PROBABILITY (of
occurrence)
5 - Definite: >95% chance of the potential impact occurring.
4 - High probability: 75% - 95% chance of the potential impact occurring.
3 - Medium probability: 25% - 75% chance of the potential impact occurring
2 - Low probability: 5% - 25% chance of the potential impact occurring.
1 - Improbable: <5% chance of the potential impact occurring.
Evaluation Component
Rating Scale and Description/criteria
CUMULATIVE
impacts
High: The activity is one of several similar past, present or future activities in the same geographical
area, and might contribute to a very significant combined impact on the natural, cultural, and/or socio-economic resources of local, regional or national concern.
Medium: The activity is one of a few similar past, present or future activities in the same geographical
area, and might have a combined impact of moderate significance on the natural, cultural, and/or socio-economic resources of local, regional or national concern.
Low: The activity is localised and might have a negligible cumulative impact.
None: No cumulative impact on the environment.
BASIC ASSESSMENT REPORT
72
Once the Environmental Risk Ratings have been evaluated for each potential
environmental impact, the Significance Score of each potential environmental impact
is calculated by using the following formula:
SS (Significance Score) = (magnitude + duration + extent + irreplaceable +
reversibility) x probability.
The maximum Significance Score value is 150.
The Significance Score is then used to rate the Environmental Significance of each
potential environmental impact as per table below. The Environmental Significance
rating process is completed for all identified potential environmental impacts both
before and after implementation of the recommended mitigation measures.
Significance Score
Environmental Significance
Description/criteria
125 – 150 Very high (VH) An impact of very high significance will mean that the project cannot proceed, and that impacts are irreversible, regardless of available mitigation options.
100 – 124 High (H) An impact of high significance which could influence a decision about whether or not to proceed with the proposed project, regardless of available mitigation options.
75 – 99 Medium-high (MH) If left unmanaged, an impact of medium-high significance could influence a decision about whether or not to proceed with a proposed project. Mitigation options should be relooked.
40 – 74 Medium (M) If left unmanaged, an impact of moderate significance could influence a decision about whether or not to proceed with a proposed project.
<40 Low (L) An impact of low is likely to contribute to positive decisions about whether or not to proceed with the project. It will have little real effect and is unlikely to have an influence on project design or alternative motivation.
+ Positive impact (+) A positive impact is likely to result in a positive consequence/effect, and is likely to contribute to positive decisions about whether or not to proceed with the project.
BASIC ASSESSMENT REPORT
73
31. CONSTRUCTION PHASE Environmental Risk and Significance Ratings for the Construction Phase
Bio-Physical Aspects
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Removal, destruction and transformation of natural vegetation, faunal and avifaunal habitats
Removal, destruction and transformation of natural vegetation, faunal and avifaunal habitats
Removal, destruction and transformation of natural vegetation, faunal and avifaunal habitats
Removal, destruction and transformation of natural vegetation, faunal and avifaunal habitats
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low -
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (33) Low (33) Low (33) Low (33) -
Proposed mitigation:
Strictly limit powerline construction and
development to the proposed project footprint.
Use existing roads as far as possible and limit
the number of additional roads constructed.
Strictly limit powerline construction and development to
the proposed project footprint.
Use existing roads as far as possible and limit the
number of additional roads constructed
-
BASIC ASSESSMENT REPORT
74
Cumulative impact post mitigation:
Low
Low
Low
Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (30) Low (30) Low (30) Low (30) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Removal, damage or destruction to protected species individuals
Removal, damage or destruction to protected species individuals
Removal, damage or destruction to protected species individuals
Removal, damage or destruction to protected species individuals
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low -
Significance rating of impact prior to mitigation (Low, Medium, Medium-High,
Low (34) Low (34) Low (30) Low (30) -
BASIC ASSESSMENT REPORT
75
High, or Very-High)
Proposed mitigation:
If any protected individuals are present
within the proposed development corridor, which might be impacted upon obtain
removal/relocation permits prior to the
commencement of any development
activities.
If any protected individuals are present within the proposed
development corridor, obtain removal/relocation permits
prior to the commencement of any development activities. -
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (32) Low (32) Low (28) Low (28) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Damage to a watercourse
Damage to a watercourse
Damage to a watercourse Damage to a watercourse
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to
Low Low 0 0
-
BASIC ASSESSMENT REPORT
76
mitigation:
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Medium (42)
Medium (42)
0
0
-
Proposed mitigation:
Ensure that no pylons are constructed within 32
m of a watercourse.
Protect the integrity of all watercourses during
the construction phase and do not alter the
beds and the banks or divert any watercourse.
From an ecological perspective either route alternative 1 or 2 can be utilised due to their relatively similar impacts. Although the preferred alternative powerline route crosses through a small portion classified as a Critical Biodiversity Area as well as a small portion classified as an Ecological Support Area (see Appendix A for Sensitivity map) it is recommended from an ecological perspective that route alternative 1 (preferred) be approved due to it running a shorter distance to the Manganore substation.
0
-
Cumulative impact post mitigation:
Low Low
0 0
-
Significance rating of impact after
Low (28) Low (28)
0 0
-
BASIC ASSESSMENT REPORT
77
mitigation (Low, Medium, Medium-High, High, or Very-High)
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Avifaunal habitat
destruction
Avifaunal habitat
destruction
Avifaunal habitat destruction
Avifaunal habitat destruction The proposed
development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Medium Medium Medium Medium
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Medium-High (75) Medium-High (65) Medium-High (65) Medium-High (65) -
Proposed mitigation:
A site specific Construction Environmental
Management Plan (CEMP) must be
implemented, which gives appropriate and
detailed description of how construction
activities must be conducted to reduce
unnecessary destruction of habitat. All
contractors are to adhere to the CEMP and
A site specific Construction Environmental Management Plan
(CEMP) must be implemented, which gives appropriate and detailed description of how construction activities must be conducted to reduce unnecessary destruction of habitat. All contractors are to adhere to the CEMP and should apply good environmental practice during construction
The minimum footprint areas of infrastructure should be
BASIC ASSESSMENT REPORT
78
should apply good environmental practice
during construction
High traffic areas and buildings such as
offices, batching plants, storage areas etc.
should, where possible be situated in areas
that are already disturbed;
Existing roads and farm tracks should be
used where possible;
The minimum footprint areas of infrastructure
should be used wherever possible, including
road widths and lengths;
No off-road driving;
Environmental Control Officers to oversee
activities and ensure that the site specific
construction environmental management
plan (CEMP) is implemented and enforced;
Following construction, rehabilitation of all
areas disturbed (e.g. temporary access
tracks and laydown areas) must be
undertaken and to this end a habitat
restoration plan is to be developed by a
specialist and included within the
Construction Environmental Management
Plan (CEMP).
used wherever possible, including road widths and lengths; Environmental Control Officers to oversee activities and
ensure that the site specific construction environmental management plan (CEMP) is implemented and enforced;
Following construction, rehabilitation of all areas disturbed (e.g. temporary access tracks and laydown areas) must be undertaken and to this end a habitat restoration plan is to be developed by a specialist
Cumulative impact post mitigation:
Medium Medium Medium Medium -
Significance rating of
Medium (65) Medium (60) Medium (60) Medium (60) -
BASIC ASSESSMENT REPORT
79
impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Avifaunal disturbance
and displacement
Avifaunal disturbance
and displacement
Avifaunal disturbance and
displacement
Avifaunal disturbance and
displacement
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Medium Medium Medium Medium
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Medium (68) Medium (68) Medium (45) Medium (45)
Proposed mitigation:
A site specific Construction Environmental
Management Plan (CEMP) must be
implemented, which gives appropriate and
detailed description of how construction
activities must be conducted. All contractors
are to adhere to the CEMP and should apply
A site specific Construction Environmental Management
Plan (CEMP) must be implemented, which gives appropriate
and detailed description of how construction activities must
be conducted. All contractors are to adhere to the CEMP
and should apply good environmental practice during
BASIC ASSESSMENT REPORT
80
good environmental practice during
construction.
Environmental Control Officers to oversee
activities and ensure that the site specific
construction environmental management
plan (CEMP) is implemented and enforced;
The appointed Environmental Control Officer
(ECO) must be trained by an avifaunal
specialist to identify the potential Red Data
species as well as the signs that indicate
possible breeding by these species. The
ECO must then, during audits/site visits,
make a concerted effort to look out for such
breeding activities of Red Data species, and
such efforts may include the training of
construction staff (e.g. in Toolbox talks) to
identify Red Data species, followed by
regular questioning of staff as to the regular
whereabouts on site of these species. If any
of the Red Data species are confirmed to be
breeding (e.g. if a nest site is found),
construction activities within 500 m of the
breeding site must cease, and an avifaunal
specialist is to be contacted immediately for
further assessment of the situation and
instruction on how to proceed.
Prior to construction, an avifaunal specialist
should conduct a site walkthrough, covering
the final road and power line routes as well
as the CSP layout, to identify any
nests/breeding/roosting activity of sensitive
species, as well as any additional sensitive
habitats. The results of which may inform the
final construction schedule in close proximity
to that specific area, including abbreviating
construction.
Environmental Control Officers to oversee activities and
ensure that the site specific construction environmental
management plan (CEMP) is implemented and enforced;
The appointed Environmental Control Officer (ECO) must be
trained by an avifaunal specialist to identify the potential Red
Data species as well as the signs that indicate possible
breeding by these species. The ECO must then, during
audits/site visits, make a concerted effort to look out for such
breeding activities of Red Data species, and such efforts
may include the training of construction staff (e.g. in Toolbox
talks) to identify Red Data species, followed by regular
questioning of staff as to the regular whereabouts on site of
these species. If any of the Red Data species are confirmed
to be breeding (e.g. if a nest site is found), construction
activities within 500 m of the breeding site must cease, and
an avifaunal specialist is to be contacted immediately for
further assessment of the situation and instruction on how to
proceed.
Prior to construction, an avifaunal specialist should conduct
a site walkthrough, covering the final road and power line
routes as well as the CSP layout, to identify any
nests/breeding/roosting activity of sensitive species, as well
as any additional sensitive habitats. The results of which
may inform the final construction schedule in close proximity
to that specific area, including abbreviating construction
time, scheduling activities around avian breeding and/or
movement schedules, and lowering levels of associated
noise.
BASIC ASSESSMENT REPORT
81
construction time, scheduling activities
around avian breeding and/or movement
schedules, and lowering levels of associated
noise.
Cumulative impact post mitigation:
Low Low Low Low
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (34) Low (34) Low (30) Low (30)
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Reduction of agricultural potential of land
Reduction of agricultural potential of land
Reduction of agricultural potential of land
Reduction of agricultural potential of land
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low
Significance rating of impact prior to
Low (36) Low (36) Low (36) Low (36) -
BASIC ASSESSMENT REPORT
82
mitigation (Low, Medium, Medium-High, High, or Very-High)
Proposed mitigation:
Strictly limit powerline construction and
development to the proposed project
footprint.
Use existing roads as far as possible and limit
the number of additional roads constructed.
Ensure adequate erosion control measures are
implemented to reduce the risk of soil erosion
during the construction phase.
Strictly limit powerline construction and development to
the proposed project footprint.
Use existing roads as far as possible and limit the
number of additional roads constructed.
Ensure adequate erosion control measures are
implemented to reduce the risk of soil erosion during the
construction phase.
-
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (33) Low (33) Low (33) Low (33) -
BASIC ASSESSMENT REPORT
83
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Dust generation and emissions
Dust generation and emissions
Dust generation and emissions
Dust generation and emissions
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (27) Low (27) Low (27) Low (27) -
Proposed mitigation:
Dust Management as well as Traffic
Management measures must be implemented
in order to manage and reduce unnecessary
traffic movement in the area and subsequently
decrease undesired dust emissions.
Dust Management as well as Traffic Management
measures must be implemented in order to manage and
reduce unnecessary traffic movement in the area and
subsequently decrease undesired dust emissions. -
Cumulative impact post mitigation:
Low Low Low Low -
Significance Low (24) Low (24) Low (24) Low (24) -
BASIC ASSESSMENT REPORT
84
rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Destruction of important heritage conservational sites
Destruction of important heritage conservational sites
Destruction of important heritage conservational cemetery sites (MVIA3 site)
Destruction of important heritage conservational cemetery sites (MVIA3 site)
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Medium Low
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (33) Low (33) Medium (42) Low (14) -
Proposed mitigation:
Upgrading of the cemetery boundary fence and
gates in order to implement access control to
the cemetery is recommended.
Upgrading of the cemetery boundary fence and gates in
order to implement access control to the cemetery is
recommended.
BASIC ASSESSMENT REPORT
85
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Positive (+8) Positive (+8) Positive (+8) Positive (+8) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Transformation of early Proterozoic palaeontological heritage
Transformation of early Proterozoic palaeontological heritage
Transformation of early Proterozoic palaeontological heritage
Transformation of early Proterozoic palaeontological heritage
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Medium (45) Medium (45) Medium (45) Medium (45) -
BASIC ASSESSMENT REPORT
86
Proposed mitigation:
It is advised that sites marked for erection of
pylons or construction of associated
infrastructure, which will require excavation
into fresh bedrock sediments of the
Campbellrand and Asbestos Hills Subgroup,
be mapped and recorded prior to the
construction phase of the development.
Ensure development is restricted to the project
footprint.
It is advised that sites marked for erection of pylons or
construction of associated infrastructure, which will
require excavation into fresh bedrock sediments of the
Campbellrand and Asbestos Hills Subgroup, be mapped
and recorded prior to the construction phase of the
development.
Ensure development is restricted to the project footprint.
-
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (39) Low (39) Low (39) Low (39) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Visual disturbance of
natural landscape and
sense of place
Visual disturbance of
natural landscape and
sense of place
Visual disturbance of natural
landscape and sense of
place
Visual disturbance of natural
landscape and sense of
place
The proposed development will not take place and as such this impact will not occur
BASIC ASSESSMENT REPORT
87
Cumulative impact prior to mitigation:
Medium Medium Medium Medium
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (39) Low (39) Low (39) Low (39) -
Proposed mitigation:
Strictly limit powerline construction and
development to the proposed project footprint.
Use existing roads as far as possible and limit
the number of additional roads constructed.
Adequate planning and management of
laydown areas
Strictly limit powerline construction and development to the
proposed project footprint.
Use existing roads as far as possible and limit the number
of additional roads constructed.
Adequate planning and management of laydown areas
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-
Low (33) Low (33) Low (33) Low (33) -
BASIC ASSESSMENT REPORT
88
High)
Socio-Economic Aspects
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Job creation,
empowerment and
skills development
Job creation,
empowerment and
skills development
Job creation, empowerment
and skills development
Job creation, empowerment
and skills development
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Positive Positive Positive Positive -
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Positive (+44) Positive (+44) Positive (+44) Positive (+44) -
Proposed mitigation:
None None
-
Cumulative impact post mitigation:
Positive Positive Positive Positive -
Significance rating of
Positive (+44) Positive (+44) Positive (+44) Positive (+44) -
BASIC ASSESSMENT REPORT
89
impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Influx of construction
workers and job
seekers and damage to
property
Influx of construction
workers and job
seekers and damage to
property
Influx of construction
workers and job seekers and
damage to property
Influx of construction
workers and job seekers and
damage to property
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low -
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Medium (44) Medium (44) Medium (44) Medium (44) -
Proposed mitigation:
A designated security company will be
appointed to ensure the safety of the facilities
during construction.
A designated security company will be appointed to
ensure the safety of the facilities during construction. -
Cumulative Low Low Low Low -
BASIC ASSESSMENT REPORT
90
impact post mitigation:
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (24) Low (24) Low (24) Low (24) -
BASIC ASSESSMENT REPORT
91
32. OPERATIONAL PHASE Environmental Risk and Significance Ratings for the Operational Phase
Bio-Physical Aspects
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Continued destruction and transformation of natural vegetation, faunal and avifaunal habitats
Continued destruction and transformation of natural vegetation, faunal and avifaunal habitats
Continued destruction and transformation of natural vegetation, faunal and avifaunal habitats
Continued destruction and transformation of natural vegetation, faunal and avifaunal habitats
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low -
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (33) Low (33) Low (33) Low (33) -
Proposed mitigation:
Ensure no unnecessary expansion of the
project footprint occurs.
Ensure no unnecessary expansion of the project footprint
occurs. -
Cumulative impact post mitigation:
Low Low Low Low -
BASIC ASSESSMENT REPORT
92
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (30) Low (30) Low (30) Low (30) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Continued damage or destruction to protected species individuals
Continued damage or destruction to protected species individuals
Continued damage or destruction to protected species individuals
Continued damage or destruction to protected species individuals
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low -
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (34) Low (34) Low (30) Low (30) -
Proposed mitigation:
If any protected individuals remain on site
without removal/relocation permits being
issued, these individuals must be buffered off in
If any protected individuals remain on site without
removal/relocation permits being issued, these individuals
must be buffered off in order to prevent any potential
-
BASIC ASSESSMENT REPORT
93
order to prevent any potential damage to them. damage to them.
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (32) Low (32) Low (28) Low (28) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Continued damage to a watercourse
Continued damage to a watercourse
Continued damage to a watercourse
Continued damage to a watercourse The proposed
development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low
0 0
-
Significance rating of impact prior to mitigation (Low, Medium, Medium-High,
Medium (42) Medium (42)
0 0
-
BASIC ASSESSMENT REPORT
94
High, or Very-High)
Proposed mitigation:
Ensure that the constructed powerline and the
maintenance thereof during the operational
phase do not negatively impact within 32 m of a
watercourse.
Protect the integrity of all watercourses during
the operational phase and do not alter the beds
and the banks or divert any watercourse.
0
-
Cumulative impact post mitigation:
Low Low
0 0
-
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (28) Low (28)
0 0
-
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Avifaunal electrocution Avifaunal electrocution Avifaunal electrocution Avifaunal electrocution The proposed development will not take place and as such this impact will not occur
BASIC ASSESSMENT REPORT
95
Cumulative impact prior to mitigation:
Very High Very High Very High Very High
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Very High (130) Very High (130) High (104) High (104) -
Proposed mitigation:
Any grid connection power line/s must be of a
design that minimizes electrocution risk by using
adequately insulated ‘bird friendly’ monopole
structures, with clearances between live
components of 2 m or greater and which provide
a safe bird perch.
The pylon structures to be constructed must first
be approved by an avifaunal specialist who
should consult with the Endangered Wildlife
Trust’s (EWT) Wildlife and Energy Programme.
The operational monitoring programme for the site
must be in line with applicable guidelines and
must include regular (i.e at least every two
months) monitoring of the grid connection power
line and all new associated substations for
electrocution (and collision) mortalities. Any
mortalities should be reported to the EWT.
Any grid connection power line/s must be of a design that
minimizes electrocution risk by using adequately insulated
‘bird friendly’ monopole structures, with clearances between
live components of 2 m or greater and which provide a safe
bird perch.
The pylon structures to be constructed must first be
approved by an avifaunal specialist who should consult with
the Endangered Wildlife Trust’s (EWT) Wildlife and Energy
Programme.
The operational monitoring programme for the site must be
in line with applicable guidelines and must include regular
(i.e at least every two months) monitoring of the grid
connection power line and all new associated substations for
electrocution (and collision) mortalities. Any mortalities
should be reported to the EWT.
BASIC ASSESSMENT REPORT
96
Cumulative impact post mitigation:
Medium-High Medium-High Medium-High Medium-High -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Medium (50) Medium (50) Medium (50) Medium (50) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Avifaunal collision with
infrastructure
Avifaunal collision with infrastructure
Avifaunal collision with infrastructure
Avifaunal collision with infrastructure The proposed
development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
High High High High
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-
High (104) High (104) High (104) Medium-High (78)
BASIC ASSESSMENT REPORT
97
High)
Proposed mitigation:
Where possible, grid infrastructure should avoid
sensitive avifaunal habitats.
Where possible, grid infrastructure should follow
existing servitudes such as existing power lines,
roads and fences.
An avifaunal specialist must conduct a site walk
through of the final Grid Connection route and
pylon positions prior to construction to determine
if, and where, bird flight diverters (BFDs) are
required.
Install bird flight diverters as per the instructions of
the specialist following the site walkthrough, which
may include the need for modified BFDs fitted
with solar powered LED lights on certain spans.
The operational monitoring programme for the site
must be in line with applicable monitoring
guidelines and must include regular (i.e. at least
every two months) monitoring of the grid
connection power line for collision (and
electrocution) mortalities. Any mortalities should
be reported to the Endangered Wildlife Trust
(EWT).
Where possible, grid infrastructure should avoid sensitive
avifaunal habitats.
Where possible, grid infrastructure should follow existing
servitudes such as existing power lines, roads and fences.
An avifaunal specialist must conduct a site walk through of
the final Grid Connection route and pylon positions prior to
construction to determine if, and where, bird flight diverters
(BFDs) are required.
Install bird flight diverters as per the instructions of the
specialist following the site walkthrough, which may include
the need for modified BFDs fitted with solar powered LED
lights on certain spans.
The operational monitoring programme for the site must be
in line with applicable monitoring guidelines and must
include regular (i.e. at least every two months) monitoring of
the grid connection power line for collision (and
electrocution) mortalities. Any mortalities should be reported
to the Endangered Wildlife Trust (EWT).
Cumulative impact post mitigation:
Medium Medium Medium Medium
Significance rating of
Medium (72) Medium (72) Medium (72) Medium (42)
BASIC ASSESSMENT REPORT
98
impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Soil erosion Soil erosion Soil erosion Soil erosion
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (39) Low (39) Low (39) Low (39) -
Proposed mitigation:
Ensure adequate erosion control measures are
implemented to reduce the risk of soil erosion
during the operational phase.
Ensure adequate erosion control measures are
implemented to reduce the risk of soil erosion during the
operational phase. -
BASIC ASSESSMENT REPORT
99
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (33) Low (33) Low (33) Low (33) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Continued dust generation and emissions
Continued dust generation and emissions
Continued dust generation and emissions
Continued dust generation and emissions The proposed
development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (27) Low (27) Low (27) Low (27) -
BASIC ASSESSMENT REPORT
100
Proposed mitigation:
Continued Dust Management as well as Traffic
Management measures must be kept in place
in order to manage traffic movement in the
area during the entire operational phase and
subsequently decrease undesired dust
emissions.
Continued Dust Management as well as Traffic
Management measures must be kept in place in order to
manage traffic movement in the area during the entire
operational phase and subsequently decrease undesired
dust emissions. -
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (24) Low (24) Low (24) Low (24) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Continued deterioration of important heritage conservational sites
Continued deterioration of important heritage conservational sites
Continued deterioration of important heritage conservational sites
Continued deterioration of important heritage conservational sites
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Low Low Medium Low
BASIC ASSESSMENT REPORT
101
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (33) Low (33) Medium (42) Low (14) -
Proposed mitigation:
Continued maintenance and management to be
conducted once the upgrading of the cemetery
boundary fence and gates have been
completed.
Continued maintenance and management to be
conducted once the upgrading of the cemetery boundary
fence and gates have been completed.
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Positive (+8) Positive (+8) Positive (+8) Positive (+8) -
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Continued transformation of early Proterozoic palaeontological
Continued transformation of early Proterozoic palaeontological heritage
Continued transformation of early Proterozoic palaeontological heritage
Continued transformation of early Proterozoic palaeontological heritage
The proposed development will not take place and as such this
BASIC ASSESSMENT REPORT
102
heritage impact will not occur
Cumulative impact prior to mitigation:
Low Low Low Low
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Medium (45) Medium (45) Medium (45) Medium (45) -
Proposed mitigation:
Ensure no unnecessary expansion of the
project footprint occurs.
Ensure no unnecessary expansion of the project footprint
occurs. -
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (39) Low (39) Low (39) Low (39) -
BASIC ASSESSMENT REPORT
103
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Continued visual
disturbance of natural
landscape and sense of
place
Continued visual disturbance of natural landscape and sense of place
Continued visual disturbance of natural landscape and sense of place
Continued visual disturbance of natural landscape and sense of place
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Medium Medium Medium Medium
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Low (39) Low (39) Low (39) Low (39) -
Proposed mitigation:
Strictly limit powerline construction and
development to the proposed project
footprint.
Use existing roads as far as possible and limit
the number of additional roads constructed.
Strictly limit powerline construction and development to
the proposed project footprint.
Use existing roads as far as possible and limit the number
of additional roads constructed.
Cumulative impact post mitigation:
Low Low Low Low -
Significance rating of
Low (33) Low (33) Low (33) Low (33) -
BASIC ASSESSMENT REPORT
104
impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Socio-Economic Aspects
Route Alternative 2
Route Alternative 1 (preferred)
Diversion Alternative 1 (preferred)
Diversion Alternative 2
No-Go Alternative
Identified Environmental Impacts
Job creation,
empowerment and
skills development
Job creation,
empowerment and
skills development
Job creation, empowerment
and skills development
Job creation, empowerment
and skills development
The proposed development will not take place and as such this impact will not occur
Cumulative impact prior to mitigation:
Positive Positive Positive Positive -
Significance rating of impact prior to mitigation (Low, Medium, Medium-High, High, or Very-High)
Positive (+32)
Positive (+32) Positive (+32) Positive (+32)
-
Proposed mitigation:
None None
-
Cumulative Positive Positive Positive Positive -
BASIC ASSESSMENT REPORT
105
impact post mitigation:
Significance rating of impact after mitigation (Low, Medium, Medium-High, High, or Very-High)
Positive (+32)
Positive (+32) Positive (+32) Positive (+32)
-
BASIC ASSESSMENT REPORT
106
A complete impact assessment in terms of Regulation 19(3) of GN 733 must be included as Appendix F. See Appendix F for the full Impact Assessment Report
33. E NVIRONMENTAL IMPACT STATEMENT
Taking the assessment of potential impacts into account, please provide an environmental impact statement that summarises the impact that the proposed activity and its alternatives may have on the environment after the management and mitigation of impacts have been taken into account, with specific reference to types of impact, duration of impacts, likelihood of potential impacts actually occurring and the significance of impacts. Proposed new 132 kV powerline
Ecology
The impacts of both the two alternative route corridors for the proposed powerline are fairly
similar. There are some sensitive systems which would be affected by the proposed
powerline routes. They include the rocky outcrops of the Kuruman Mountain Bushveld
(SVk10) and the episodic streams as well small wetlands/pans on the plains between the
rocky ridges.
No Red or Orange data species were found to occur along the powerline routes or
substation footprint although a protected species namely Olea europaea subsp. africana
occur on the rocky outcrops while Acacia erioloba, Acacia haematoxylon and Boscia
albitrunca occur on sandy plains.
From an ecological perspective either route alternative 1 or 2 can be utilised due to their
relatively similar impacts. Although the preferred alternative powerline route crosses
through a small portion classified as a Critical Biodiversity Area as well as a small portion
classified as an Ecological Support Area (see Appendix A for Sensitivity map) it is
recommended from an ecological perspective that route alternative 1 (preferred) be
approved due to it running a shorter distance to the Manganore substation.
Avifauna
For the Grid Connection, the residual impacts of habitat destruction, collision and
electrocution were all found to have a medium significance rating after mitigation, with all
other impacts having a low rating. This indicates that either route alternative is acceptable
from an avifaunal perspective with neither being preferred.
Heritage
From an archaeological and cultural heritage perspective neither of the powerline
alternatives, poses a threat to any potentially significant sites. It is therefore recommended
that development of the approved powerline proceed without the developer having to
comply with additional heritage compliance requirements pertaining to lithic Stone Age
BASIC ASSESSMENT REPORT
107
deposits, such as Phase 2 mitigation, prior to construction impact.
There are also no major palaeontological grounds to halt the development of the preferred
Alternative Route 1 or 2, but it is advised that sites marked for erection of pylons or
construction of associated infrastructure, which will require excavation into fresh bedrock
sediments of the Campbellrand and Asbestos Hills Subgroup, is mapped and recorded
prior to the construction phase of the development.
No major impacts were identified for either of the powerline alternatives and Metsimatala Solar substation footprint and by implementing the recommended mitigation measures, the impacts will be adequately reduced to acceptable levels.
Decommissioning and diversion of existing powerline
Ecology
The impacts of both the two alternative route corridors for the diversion of the existing
powerline are similar and low. It is thereof recommended that the preferred alternative 1 be
approved.
Avifauna
For the line diversion, similar ratings were obtained as for the new powerline, and both
route alternatives are therefore acceptable, with alternative two being slightly preferred
only as it runs along the main tar road.
Heritage
Although route alternative 1 passes in the proximity of identified significant cemetery site
MVIA 3, the site will not be impacted by the proposed powerline diversion. In fact, the
mitigations measures imposed will assist in the improvement of the integrity of the
identified site. Route alternative 2 for the diversion of the existing power line may
potentially traverse Griquatown Formation iron stones (Vad) considered to be of moderate
palaeontological sensitivity.
No major impacts were identified for either of the powerline diversion alternatives and by
implementing the recommended mitigation measures, the impacts will be adequately
reduced to acceptable levels.
BASIC ASSESSMENT REPORT
108
No-go alternative (compulsory) The no-go alternative addresses the scenario of the status-quo remaining the same, with no development on the proposed site. The no-go alternative would entail that the current land use does not change.
Advantages
The negative environmental impacts associated with the proposed project and its
alternatives will be avoided if the proposed project is not implemented. No significantly high
rating impacts were however identified by any specialists.
Disadvantages
If the proposed project does not go ahead, the proposed CSP facility will not have an
adequate way of distributing its generated electricity into the local grid. The new powerline
construction and exiting line diversion is crucial for the successful operation of the
proposed CSP facility. The local communities will forego the significant economic benefits
which the project will have on the area such as immediate additional employment
opportunities and revenue streams during the construction phase and most importantly,
sustainable capacity building (skills, experience and resources development) for the future.
The development of alternative renewable energy sources and distribution of generated
electricity is crucial within the context of South Africa’s current energy crisis as well as the
commitment towards greenhouse gas emission reductions. The current electricity shortage
within the Metsimatala area will continue if the no-go alternative is considered.
The no-go option would not be preferable as the existing and proposed residential areas require adequate electricity provision, which can be supplied by this proposed development. The proposed development of the powerline has been assessed in this report against the no-go option. The no-go alternative is not considered a preferred alternative.
BASIC ASSESSMENT REPORT
109
SECTION E: RECOMMENDATION OF PRACTITIONER
Is the information contained in this report and the documentation attached hereto sufficient to make a decision in respect of the activity applied for (in the view of the environmental assessment practitioner)?
YES
If “NO”, indicate the aspects that should be assessed further as part of a Scoping and EIA process before a decision can be made (list the aspects that require further assessment).
If “YES”, please list any recommended conditions, including mitigation measures that should be considered for inclusion in any authorisation that may be granted by the competent authority in respect of the application.
General recommendations of the EAP
All mitigation measures recommended by the various specialists as per Section D
should be strictly implemented.
The EMPr should be approved by the DEA prior to construction and its implementation
should form part of the conditions of the Environmental Authorisation.
An Environmental Control Officer (ECO) must be appointed by the applicant/developer
to actively assist and undertake environmental compliance audits to ensure that the
construction phase of the development is acceptably implemented in an
environmentally responsible and sustainable manner in accordance with the
recommendations of the EMPr. The ECO must also ensure compliance with the
conditions of approval in the EA to be issued by the competent authority.
Vegetation species removal permits need to be obtained prior to the commencement of
construction from the relevant national or provincial department if required on site.
Conclusion After careful consideration of the findings and outcomes during the Basic Assessment
process, Enviroworks is of the opinion that based on all information that was captured in
this report; the proposed development will not lead to unacceptable impacts or fatal flaws
and should be considered plausible in the framework of NEMA. It is indicated that the
majority of the anticipated impacts are rated as low to medium while the impacts rated as
medium-high to high (avifaunal) can be adequately addressed through the various
mitigation measures and reduced to an acceptable level.
Enviroworks also recommend that the preferred route layout alternative 1 for the new
proposed 132 kV powerline and the Metsimatala Solar substation be considered and
approved as well as the preferred route layout alternative 1 for the decommissioning and
BASIC ASSESSMENT REPORT
110
diversion of the existing powerline due to its lesser impacts.
A comprehensive Public Participation Process will be conducted for public comment on the
draft Basic Assessment Report in order to provide all relevant parties with adequate time
for consideration.
Is an EMPr attached? YES NO
The EMPr must be attached as Appendix G. The details of the EAP who compiled the BAR and the expertise of the EAP to perform the Basic Assessment process must be included as Appendix H. If any specialist reports were used during the compilation of this BAR, please attach the declaration of interest for each specialist in Appendix I. Any other information relevant to this application and not previously included must be attached in Appendix J. ________________________________________ NAME OF EAP ________________________________________ _________________ SIGNATURE OF EAP DATE
BASIC ASSESSMENT REPORT
111
SECTION F: APPENDICES The following appendixes must be attached: Appendix A: Maps Appendix B: Photo Report Appendix C: Facility illustration(s) Appendix D: Specialist reports Appendix E: Public Participation Process Appendix F: Impact Assessment Appendix G: Environmental Management Programme (EMPr) Appendix H: Details of EAP and expertise Appendix I: Municipal Confirmation Appendix J: Specialist’s declaration of interest Appendix K - I & AP registration