draft environmental impact assessment report - dobaspet 4th phase draft eia... · draft...

174
DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4 th Phase in the villages Yedehalli, Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, Avverahalli, K.G.Srinivasapura, Billanakote, Nelamangala Taluk, Bangalore Rural District, Karnataka Submitted to Karnataka State Pollution Control Board (KSPCB) Head Office Address: Karnataka State Pollution Control Board "Parisara Bhavan", #49,4th & 5th Floor, Church Street, Bangalore-560001 Project Proponent Karnataka Industrial Area Development Board (KIADB) KIADB Office 14/3, 2nd Floor, R.P. Building, Nrupathunga Road, Bangalore-560 001 Project Consultant M/s. ABC Techno Labs India Private Ltd MES Road, Muthyalanagar, Bangalore-560054 Ph: 080-23457777 Fax: 080-23453737 Email: [email protected] Web: www.abctechnolab.com

Upload: others

Post on 17-Jun-2020

14 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DRAFT

ENVIRONMENTAL IMPACT ASSESSMENT

REPORT

For

Avverahalli Dobaspet Industrial Area 4th

Phase in

the villages Yedehalli, Chandana Hosahalli,

Honnenahalli, Kengal Kempohalli, Avverahalli,

K.G.Srinivasapura, Billanakote, Nelamangala

Taluk, Bangalore Rural District, Karnataka

Submitted to

Karnataka State Pollution Control Board (KSPCB)

Head Office Address: Karnataka State Pollution Control Board "Parisara Bhavan", #49,4th & 5th Floor, Church Street, Bangalore-560001

Project Proponent

Karnataka Industrial Area Development Board (KIADB)

KIADB Office 14/3, 2nd Floor, R.P. Building, Nrupathunga Road, Bangalore-560 001

Project Consultant

M/s. ABC Techno Labs India Private Ltd

MES Road, Muthyalanagar, Bangalore-560054 Ph: 080-23457777

Fax: 080-23453737

Email: [email protected]

Web: www.abctechnolab.com

Page 2: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

i

TABLE OF CONTENTS

1. INTRODUCTION ....................................................................................................................... 1

1.1 PROFILE OF THE PROJECT PROPONENT ................................................................................................... 1

1.2 PROJECT LOCATION ................................................................................................................................ 2

1.3 NEED AND JUSTIFICATION OF PROJECT ................................................................................................... 3

1.4 REGULATORY FRAME WORK ................................................................................................................... 3

1.5 EIA CONSULTANT .................................................................................................................................... 4

1.6 PURPOSE OF THE REPORT ....................................................................................................................... 4

1.7 OBJECTIVE OF STUDY .............................................................................................................................. 5

1.8 SCOPE AND METHODOLOGY OF THE STUDY ........................................................................................... 5

1.9 APPROVED TOR FOR EIA STUDY BY MOEF .............................................................................................. 6

1.10 PLAN OF ACTION ................................................................................................................................ 6

1.11 REPORT .............................................................................................................................................. 7

2. PROJECT DESCRIPTION ........................................................................................................ 8

2.1 PROJECT BACKGROUND .......................................................................................................................... 8

2.2 JUSTIFICATION FOR SELECTING PROPOSED PROJECT SITE ..................................................................... 10

2.3 EXISTING LAND USE PATTERN ............................................................................................................... 10

2.4 EXISTING INFRASTRUCTURE ................................................................................................................. 10

2.5 PROJECT LOCATION & CONNECTIVITY .................................................................................................. 11

2.6 ENVIRONMENTAL SETTING OF THE SITE ............................................................................................... 14

2.7 OCCUPANCY DETAILS ............................................................................................................................ 14

2.8 WATER SUPPLY ..................................................................................................................................... 15

2.9 SEWAGE GENERATION .......................................................................................................................... 15

2.10 SOLID WASTE GENERATION, COLLECTION, TRANSPORT AND DISPOSAL ........................................... 19

2.11 POWER DETAILS ............................................................................................................................... 21

3. DESCRIPTION OF THE ENVIRONMENT .......................................................................... 22

3.1 INTRODUCTION .................................................................................................................................... 22

3.2 SCOPE OF THE BASELINE STUDY ............................................................................................................ 22

Page 3: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ii

3.3 TEMPERATURE...................................................................................................................................... 28

3.4 WIND PATTERN AT THE PROPOSED SITE ............................................................................................... 31

3.5 RAINFALL .............................................................................................................................................. 34

3.6 TOPOGRAPHY OF THE SITE ................................................................................................................... 35

3.7 EXISTINGLAND USE OF THE SITE ........................................................................................................... 37

3.8 WATER BODIES ..................................................................................................................................... 37

3.9 GEOMORPHOLOGY AND SOIL TYPES ..................................................................................................... 38

3.10 HYDROGEOLOGY .............................................................................................................................. 42

3.11 GROUND WATER QUALITY ............................................................................................................... 43

3.12 NATURAL HAZARD VULNERABILITY .................................................................................................. 44

3.13 AIR ENVIRONMENT .......................................................................................................................... 45

3.14 NOISE ENVIRONMENT ...................................................................................................................... 51

3.15 WATER ENVIRONMENT .................................................................................................................... 55

3.16 SOIL ENVIRONMENT ........................................................................................................................ 60

3.17 ECOLOGICAL ENVIRONMENT............................................................................................................ 64

3.16 ENVIRONMENTAL SENSITIVITY ......................................................................................................... 66

3.17 SOCIO- ECONOMIC PROFILE ............................................................................................................. 66

3.18 EXISTING STATUS OF INDUSTRIAL AREAS IN THE DISTRICT BANGALORE RURAL .............................. 72

3.19 RESETTLEMENT AND RELOCATION ................................................................................................... 75

4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES ............ 76

4.1 INTRODUCTION .................................................................................................................................... 76

4.2 ENVIRONMENTAL ASPECTS AND IMPACTS ANALYSIS ........................................................................... 77

4.3 IMPACTS DURING CONSTRUCTION PHASE ............................................................................................ 79

4.4 IMPACTS DURING OPERATION PHASE .................................................................................................. 86

4.5 ENVIRONMENTAL MITIGATION AND ENHANCEMENT MEASURESDURING CONSTUCTION PHASE ........ 88

4.6 ENVIRONMENTAL MITIGATION AND ENHANCEMENT MEASURES DURING OPERATION PHASE ........... 96

5. ENVIRONMENTAL MONITORING PROGRAM ............................................................ 108

5.1 GENERAL............................................................................................................................................. 108

5.2 OBJECTIVES OF ENVIRONMENTAL MONITORING PLAN ...................................................................... 108

Page 4: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

iii

5.3 SUGGESTED ENVIRONMENTAL MONITORING PLAN ........................................................................... 110

6. ADDITIONAL STUDIES...................................................................................................... 112

6.1 RISK ASSESSMENT .............................................................................................................................. 112

6.2 HAZARD IDENTIFICATION ................................................................................................................... 112

6.3 Hazard Assessment and Evaluation .................................................................................................... 113

6.4 DISASTER MANAGEMENT PLAN (DMP) ............................................................................................... 114

6.5 HAZARDOUS CONTROL MEASURES ..................................................................................................... 116

6.6 RISK AND EMERGENCY PREPAREDNESS PLAN ..................................................................................... 122

6.7 EMERGENCY PREPAREDNESS TRAINING ............................................................................................. 123

6.8 FIRST AID AND EMERGENCY PROCEDURES ......................................................................................... 125

7. PROJECT BENEFITS ........................................................................................................... 126

7.1 SIGNIFICANCE OF THE PROPOSED PROJECT ........................................................................................ 126

7.2 IMPACT ON PHYSICAL INFRASTRUCTURE ............................................................................................ 126

7.3 IMPACT ON SOCIO – ECONOMIC FACTORS ......................................................................................... 127

7.4 EMPLOYMENT POTENTIAL .................................................................................................................. 127

8. ENVIRONMENTAL MANAGAEMENT PLAN ................................................................. 128

8.1 INTRODUCTION .................................................................................................................................. 128

8.2 ENVIRONMENTAL MANAGEMENT CELL .............................................................................................. 129

8.3 ENVIRONMENTAL MANAGEMENT PLAN DURING CONSTRUCTION PHASE.......................................... 131

8.4 ENVIRONMENTAL MANAGEMENT PLAN DURING OPERATIONAL PHASE ............................................ 134

8.5 BUDGETARY PROVISION ..................................................................................................................... 139

9. ADDITIONAL CORPORATE ENVIRONMENTAL RESPONSIBILITY ...................... 141

9.1 INTRODUCTION .................................................................................................................................. 141

9.2 AIMS AND OBJECTIVES: ...................................................................................................................... 142

9.3 FUNCTIONS: ........................................................................................................................................ 142

9.4 KIADB - As a Premier Industrial Area Developer ................................................................................. 142

10. SUMMARY & CONCLUSION ......................................................................................... 144

10.1 INTRODUCTION .............................................................................................................................. 144

Page 5: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

iv

10.2 ENVIRONMENTAL SETTING OF THE SITE ......................................................................................... 144

10.3 SITE CONNECTIVITY ........................................................................................................................ 145

10.4 PROJECT SITE AREA ........................................................................................................................ 145

10.5 WATER REQUIREMENT OF THE SITE ............................................................................................... 146

10.6 WASTEWATER GENERATION .......................................................................................................... 147

10.7 SOLID WASTE GENERATION ........................................................................................................... 147

10.8 POWER REQUIREMENT .................................................................................................................. 147

10.9 BASELINE STUDY ............................................................................................................................ 148

10.10 ENVIRONMENTAL MANAGEMENT SYSTEM AND ENVIRONMENTAL MONITORING PLAN ............... 149

10.11 ENVIRONMENTAL MONITORING PROGRAM .................................................................................. 150

10.12 CONCLUSION .................................................................................................................................. 151

11. DISCLOSURE OF CONSULTANTS ............................................................................... 152

11.1 ABC TECHNO LABS INDIA PRIVATE LIMITED ................................................................................... 152

11.2 OUR SERVICES ................................................................................................................................ 152

11.3 STUDY TEAM .................................................................................................................................. 154

Page 6: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

v

LIST OF TABLES

Table 1.1: Project Details ................................................................................................................................. 1 Table 2.1: The project land use details ............................................................................................................. 8 Table 2.2: Site Salient Features ...................................................................................................................... 14 Table 2.3: Raw Water Quality ........................................................................................................................ 16 Table 2.4: Treated Effluent Quality for Secondary Treatment Plant and Tertiary Treatment ......................... 16 Table 2.5: Type of waste from Industrial Phase and Non Industrial Phase ..................................................... 20 Table 2.6: Estimated Solid Waste Quantity from Avverahalli Industrial Area ................................................ 21 Table 3.1: Various Environmental Attributes ................................................................................................. 22 Table 3.2: Frequency and Monitoring Methodology ...................................................................................... 23 Table 3.3: Udupi District Weather Report for September, 2013 ..................................................................... 28 Table 3.4: Udupi District Weather Report for October, 2013 ......................................................................... 28 Table 3.5: Udupi District Weather Report for November, 2013 ...................................................................... 29 Table 3.6: Udupi District Weather Report for December, 2013 ...................................................................... 30 Table 3.7: Wind data (2013) ........................................................................................................................... 31 Table 3.8: Rainfall data from 2008 to 2012 .................................................................................................... 35 Table 3.9: The project land use details ........................................................................................................... 37 Table 3.10: List of water bodies located near to Project Site .......................................................................... 38 Table 3.11: Earthquakes in India .................................................................................................................... 45 Table 3.12: Ambient Air Quality Monitoring Locations .................................................................................. 46 Table 3.13: Techniques for Ambient Air Quality Monitoring .......................................................................... 48 Table 3.14: Summary of Ambient Air Monitoring........................................................................................... 49 Table 3.15: Noise Monitoring Locations ......................................................................................................... 52 Table 3.16: Ambient Noise Levels Recorded in the Study Area dB(A) ............................................................. 54 Table 3.17: Ambient Noise Standards [dB (A)] ............................................................................................... 54 Table 3.18: Water Sampling Locations ........................................................................................................... 56 Table 3.19: Results for Ground water Analysis ............................................................................................... 58 Table 3.20: Soil Sampling Locations ............................................................................................................... 61 Table 3.21: Soil Analysis Results .................................................................................................................... 62 Table 3.22: Standard Soil Classifications ........................................................................................................ 62 Table 3.23: Floristic Composition in the Study Area ....................................................................................... 65 Table 3.24: Fauna Present in the Study Area .................................................................................................. 65 Table 3.25: Socio – Economic Status of the Study Area as per Census 2001 ................................................... 69 Table 3.26: Existing land status of industries in the Bangalore rural district .................................................. 72 Table 3.27: Industrial estates developed in the district .................................................................................. 73 Table 3.28: List of the units in & Nearby Area ................................................................................................ 74 Table 4.1: Activity - Impact Identification Matrix ........................................................................................... 78 Table 4.2: Emission Factors for Various Construction Equipment’s ................................................................ 81 Table 4.3: Pollutants Released From Light Duty Trucks .................................................................................. 82 Table 4.4: Construction Fugitive Dust Emission Factors ................................................................................. 82 Table 4.5: Construction Equipment Noise Emission Levels ............................................................................. 83 Table 4.6: Emission Limits for DG Sets Prescribed By CPCB ............................................................................ 92 Table 4.7: Calculation of the Size of the Collection Space and Storage Tank .................................................. 98 Table 4.8: Values of run-off coefficient ........................................................................................................ 101 Table 4.9: RWH Computation....................................................................................................................... 101 Table 5.1: Environmental Monitoring Schedule ........................................................................................... 111 Table 6.1: Preliminary Hazard Analysis for Process and Storage Areas......................................................... 114 Table 6.2: Preliminary Hazard Analysis for the Whole Plant in General ....................................................... 114 Table 6.3: First Aid for Burns ........................................................................................................................ 125 Table 8.1: EMP &Environmental Management Cost .................................................................................... 140 Table 10.1: Site Salient Features .................................................................................................................. 144 Table 10.2: Details of the site connectivity .................................................................................................. 145 Table 10.3: Land use Breakup of the proposed project ................................................................................ 145 Table 10.4: Estimated Solid Waste Quantity from Avverahalli Industrial Area ............................................. 147 Table 10.5: Environmental Monitoring Program .......................................................................................... 150 Table 11.1: Study Team ................................................................................................................................ 154

Page 7: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

vi

LIST OF FIGURES

Figure 1.1: Location of the Project ................................................................................................................... 2 Figure 2.1: Location of the Project site ............................................................................................................. 9 Figure 2.2: Connectivity to the site ................................................................................................................ 12 Figure 2.3: Road Connectivity Layouts ........................................................................................................... 13 Figure 2.4: Water Balance Flow Sheet ............................................................................................................ 15 Figure 2.5: Flow Diagram for Water Cycling in Industrial Area ....................................................................... 19 Figure 3.1: Satellite Imagery of the site (10 Km radius) .................................................................................. 24 Figure 3.2: Topo map 5 & 10 km radius showing the project location and nearest habitats ........................... 25 Figure 3.3: Satellite Imagery showing the project location and Road Connectivity ........................................ 26 Figure 3.4: LandUse/ Land Cover 5 & 10 km radius showing the project location & surrounding features ..... 27 Figure 3.5: Wind rose for the month of October ............................................................................................ 32 Figure 3.6: Wind rose for the month of November ........................................................................................ 33 Figure 3.7: Wind rose for the month of December ......................................................................................... 34 Figure 3.8: Rainfall Data From 2008-2012 ...................................................................................................... 35 Figure 3.9: Topo map 5, 10 & 15 km radius showing the project location and surrounding features .............. 36 Figure 3.10: water bodies near to Project Site ............................................................................................... 38 Figure 3.11: Drainage and Hydrography Monitoring of Bangalore Rural District ............................................ 40 Figure 3.12: Drainage map of Project Site ...................................................................................................... 41 Figure 3.13: Hydrogeology Map of Bangalore Rural District ........................................................................... 42 Figure 3.14: Ground Water Quality of Bangalore Rural District ...................................................................... 43 Figure 3.15: Seismic Zonation Map of India ................................................................................................... 44 Figure 3.16: Ambient Air Quality Monitoring Locations ................................................................................. 47 Figure 3.17: Graphical Representation of PM10 & PM2.5 ................................................................................. 50 Figure 3.18: Graphical Representation of NOx& SO2 ....................................................................................... 51 Figure 3.19: Noise Monitoring Locations ........................................................................................................ 53 Figure 3.20: Graphical Representation of Noise Levels .................................................................................. 55 Figure 3.21: Water Sampling Locations .......................................................................................................... 57 Figure 3.22: Soil Sampling Locations .............................................................................................................. 61 Figure 3.23: Texture Classification of Soil Samples ......................................................................................... 63 Figure 3.24: Nutrient Content of Soil Samples ............................................................................................... 63 Figure 3.25: Literacy Rate in the Honnenahalli village ................................................................................... 70 Figure 3.26: Distribution of Work force in the proposed Project Site ............................................................. 71 Figure 4.1: Two Broad Areas of Rainwater Harvesting ................................................................................... 98 Figure 4.2: Rain Water Harvesting Pit .......................................................................................................... 102 Figure 8.1: Environmental Management Cell ............................................................................................... 129 Figure 9.1: Organisation Chart ..................................................................................................................... 141 Figure 10.1: water balance flow sheet ......................................................................................................... 146

Page 8: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

vii

COMPLIANCE TO TERMS OF REFERENCE GIVEN BY STATE ENVIRONMENTAL IMPACT ASSESSMENT AUTHORITY, KARNATAKA Ref: Lr. No KSEAC/MEETING/2013 dated 06.04.2013

Introduction Chapter-1

1. Executive summary of the project- giving a prima facie idea of the objectives of the proposal, use of resources, justification, etc. In addition, it should provide a compilation of EIA report including EMP and post-project monitoring plan in brief.

The land and the proof for land ownership consolidated document for entire area is enclosed as Annexure I and Please refer Chapter-1 for other details.

Project description Chapter-2

2. Details of the industries, for which the estate is being planned and their proposed capacities of installation, if available. In the absence of complete details, indicate the type of industries and capacity being considered.

List of industries not available, only Orange and Green Category industries are allotting for this project.

3. Land requirement for the project including the peripheral greenbelt inside the boundary.

Please refer Table 2.1: The project land use details

4. Justification for selecting the proposed size of the IEs.

Please refer Content 2.2: JUSTIFICATION FOR SELECTING PROPOSED PROJECT SITE

5. Details on strategy being followed for development of IE.

6. Layout map of estate indicating processing zones, admin area, roads, plots, green belt, common utilities area, etc., shall be shall be shown along with contour map. Landscape plan including open spaces may be described.

Layout map is enclosed as Annexure VI

7. Classify the proposed industries based on their pollution potential to the extent possible i.e., A1 to A4 categories for air pollution and W1 to W4 categories for water pollution – CPCB Guidance may be referred for classification.

All the industries come under Orange & Green category. Present industries are not allotted by KIADB.

8. Backward and forward linkages of the IEs (availability of input resources and markets for the products/by-products and anticipated benefits for the regional development).

Please refer chapter 2

9. Details of Infrastructure Development within the IE and in the region.

Page 9: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

viii

10. Details on known industrial activity-specific proposed processes, resource consumption and rejects assessment.

11. Details on estimated quantity of fuel required, fuel type, nature, source and transportation.

12. Details on estimated water balance taking into account conservation measures, reuse and recycling of treated effluents.

Please refer Figure 2.7: Water balance flow sheet

13. Individual and/or common facilities for waste collection, treatment, recycling and disposal (all effluent, emission and refuse including MSW, and hazardous wastes).

Please refer Content: 2.10: SOLID WASTE GENERATION, COLLECTION, TRANSPORT AND DISPOSAL Table 2.6: Estimated Solid Waste Quantity from Avverahalli Industrial Area

14. Commitment from the concerned authorities regarding availability of power, water and sewerage network.

Please refer Content: 2.9: SEWAGE GENERATION 2.10: SOLID WASTE GENERATION, COLLECTION, TRANSPORT AND DISPOSAL 2.11: POWER DETAILS

15. Details of Solid Waste management including arrangements for hazardous waste management and e-waste.

Please refer Content: 2.10: SOLID WASTE GENERATION, COLLECTION, TRANSPORT AND DISPOSAL Table 2.5: Type of waste from Industrial Phase and Non Industrial Phase

16. Details on provisions made for safety in storage of materials, products and wastes.

Please refer chapter 2

17. Details on use of local building materials. The provision of fly ash Notification should be kept in view.

18. Detailed plan of treated water disposal, reuse and utilization/management.

19. In case of site leveling involving quarrying, details thereof.

20. Any litigation pending against the project and/or any direction/ order passed by any Court of Law related to the environmental pollution and impacts in the last two years, if so, details thereof.

Description of the environment Chapter- 3 21. The project study area for EIA studies

shall be up to a distance of 10km from the boundary of the proposed IE.

Please refer Figure 3.1: Satellite Imagery of the site (10 Km radius)

Page 10: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ix

22. Location of the project site and nearest habitats with distances from the project site to be demarcated on a topo sheet (1:50,000 scale).

Please refer Figure 3.2: Topo map 5 & 10 km radius showing the project location and nearest habitats

23. Land use based on satellite imagery including location specific sensitivities such as national parks/ wildlife sanctuary, villages, industries, etc. for the study area.

Please refer Figure 3.4: LandUse/ Land Cover 5 & 10 km radius showing the project location & surrounding features Figure 3.10: water bodies near to Project Sit

24. Demography details of all villages falling within the study area.

Please refer Content 3.19: SOCIO- ECONOMIC PROFILE

25. Topography details of the project area. Please refer Content 3.6 Topography of site Figure 3.5: Topo maps 5, 10 & 15 km radius showing the project location and surrounding features

26. Anticipated pollution loads from each of the known composition of industrial units. Cumulative waste water quantity and pollution loads, total solid/ hazardous waste generation etc.

Please refer Chapter2

27. Details of rainwater harvesting and how it will be used in the IE & outfall.

28. The baseline data to be collected from the study area w.r.t. different components of environment viz. air, noise, water, land, and biology and socio-economic. Actual monitoring of baseline environmental components shall be strictly according to the parameters prescribed in the ToR after considering the proposed coverage of parameters by the proponent in draft ToR and shall commence after finalization of ToR by the competent Authority.

29. Identification of existing potential sources of pollution in the study area.

30. Present and projected population; present and proposed land use; planned development activities, issues relating to squatting and relocation, community structure, employment, distribution of income, goods and services; recreation; public health and safety; cultural peculiarities, aspirations and attitudes shall be explored in study.

Page 11: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

x

31. Details regarding availability of social infrastructure and future projections, details of facilities such as sanitation, fuel, restroom etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

32. Detailed study of the hydrological and geo-hydrological conditions of the project area including a contour plan indicating slopes and showing drainage pattern and outfall.

33. Information regarding surface hydrology and water regime and impact of the same, if any due to the project.

34. Examine soil characteristics, topography, and rainfall pattern and soil erosion.

35. Details on surface water quality of nearby water sources and other surface drains.

36. Details of ground water quality in and around the IE.

37. Examine water quality with reference to President Organic pollutants, if relevant.

38. Details on water quality for parameters such as pH, temperature (◦C), Oil and grease*, Cyanide* (as CN), Ammoniacal nitrogen* (as N), Phenolic compounds* (as C6H5OH), Hexavalent Chromium*, Total chromium *,Copper*, Nickel*, Lead*, Arsenic*, Mercury*, Cadmium*, Selenium*, Fluoride*, Boron*, Radioactive Materials*, Alfa emitters*, Hc/ml*, Beta emitters*, Hc/ml*, etc. (*- As applicable). These parameters to be determined depend on the type of industries coming in industrial estates.

39. Details on existing ambient air quality and expected, stack and fugitive emissions for PM10, PM 2.5, SO2*, NOx*, O3, suspended particulates, VOC, Mercury, etc., and evaluation of the adequacy of the proposed pollution control devices to meet standards for point sources and to meet AAQ standards. (* - As applicable and these parameters to be determined depends on the type of industries coming in

Please refer content: 3.13 AIR ENVIRONMENT

Page 12: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

xi

industrial estates).

40. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any wind roses.

41. Mathematical modeling for calculating the dispersion of air pollutants and ground level concentration along with emissions from boilers.

42. Details on noise levels at sensitive/commercial receptors.

Please refer content: 3.14 NOISE ENVIRONMENT

43. Site-specific meteorological data including mixing heights and secondary data for future predictions.

Please refer Chapter 3

44. One season site-specific data excluding monsoon season.

45. Proposed baseline monitoring network for the consideration and approval of the Component Authority.

46. Fuel analysis to be provided (sulphur, ash content and mercury). Details of auxiliary fuel, if any including its quality, storage, etc., should also be given.

47. Examine entry/exit of the project including the crossings from the highway and provisions of service roads on the basis of traffic density studies and analysis.

48. Climatic conditions of the study area shall be monitored for hourly wind speed, wind direction, relative humidity, ambient dry and wet bulb temperatures and precipitation.

49. Ecological status (terrestrial and aquatic) of the study area such as habitat type and quality, species, diversity, rarity, fragmentation, ecological linkage, age abundance, etc.

Page 13: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

xii

50. If ecologically sensitive attributes fall within the study area, proponent shall describe the sensitivity (distance, area and significance) and propose the additional points based on significance for review and acceptance by the EAC/SEAC. Ecological sensitive attribute include:

National parks

Wild life sanctuaries Game reserve

Tiger reserve/elephant reserve/turtle nesting ground

Mangrove area

Wetlands

Reserved and protected forests, etc.

Any other closed / protected area under the Wild Life (protection) Act, 1972, any other locally applicable.

51. If any incompatible land use attributes fall within the study area, proponent s hall describe the sensitivity (distance, area and significance) and propose the additional points based on significance for review and acceptance by the EAC/SEAC. Ecological sensitive attribute include:

Public water supply areas from rivers/surface water bodies, from ground water

Scenic areas/ tourism areas/hill resorts

Religious places, pilgrim centers that attract over 10lakh pilgrims a year

Protected tribal settlements (notified tribal areas where industrial activity is not permitted)

Monuments of national significance, World Heritage Sites

Cyclone, Tsunami prone areas (based on last 25 years);

Airport areas

Any other feature as specified by the State or local government and other features as locally applicable, including prime agricultural lands,

Page 14: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

xiii

pastures migratory corridors, etc.

52. If the location falls in Valley, specific issues connected to the natural resources management shall be studied and presented.

53. If the location falls in CRZ area: A CRZ map duly authenticated by one of the authorized agencies demarcating LTL,HTL, CRZ area, location of the project and associate facilities w.r.t. CRZ, coastal features such as mangroves, if any.

Provide the CRZ map in 1:10000 scale in general cases and in 1:5000 scales for specific observations.

Proposed site for disposal of dredged material and environmental quality at the point of disposal/impact areas.

Fisheries study should be done w.r.t. Benthos and Marine organic material and coastal fisheries.

Anticipated environmental impacts

and mitigation measures

Chapter-4

54. Anticipated generic environmental impacts due to this project which may be evaluated for significance and based on corresponding likely impacts VECs may be identified. Baseline studies may be conducted for all the concerned VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.

Please refer content: 4.2: ENVIRONMENTAL ASPECTS AND IMPACTS ANALYSIS 4.3: IMPACTS DURING CONSTRUCTION PHASE 4.4: IMPACTS DURING OPERATION PHASE 4.5: ENVIRONMENTAL MITIGATION AND ENHANCEMENT MEASURES DURING constructional PHASE 4.6: ENVIRONMENTAL MITIGATION AND ENHANCEMENT MEASURES DURING OPERATIONAL PHASE

55. While identifying the likely impacts, also include the following for analysis of significance and required mitigation measures:

Impacts due to transportation of raw materials and end products on the surrounding environment.

Impacts on surface water, soil, groundwater, drainage due to project activities

Impacts due to air pollution

Impacts due to odour pollution

Impacts due to noise

Impacts due to fugitive emissions

Impact on health of workers due to

Page 15: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

xiv

proposed project activities

56. Proposed odour control measures.

57. Examine in detail the proposed site with reference to possible impact of infrastructure covering water supply, pipelines, roads, storm water drainage, sewerage, power, temporary waste storage facilities, treated waste water disposal (land/sewer/surface water bodies), common facilities, etc.

58. Environmental condition scenarios shall be developed based on industrial activities and pollution potentials.

59. Details of traffic density vis-à-vis impact on the ambient air.

60. Cumulative impact on regional supportive capacity shall be studied in terms of population density, water supply, sewerage, storm water drainage, power supply, educational facilities, medical facilities, public transport, traffic, housing for EWS, and community facilities, etc.

61. Details on positive and negative impacts, direct and indirect impacts, induced impacts.

62. Project activities and impacts shall be represented in matrix form with separate matrices for pre and post mitigation scenarios.

63. Traffic management plan including parking and loading/unloading area may be described traffic survey should be carried out on week days and weekends and also analyze the anticipated traffic increase.

64. Odour mitigation plan may be described. Also make provision of green cover as a measure for mitigation of dust and noise and buffer between habitation and industry

65. Rain water harvesting proposals should be made with due safeguards for ground water quality. Maximize recycling of water and utilization of rain water.

Page 16: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

xv

66. Temporary plans for the housing of construction labor within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile Sewage Treatment Plant (STP), safe drinking water, medical health care, crèche, etc.

67. Proposed measures for occupational safety and health of the workers.

68. Impact of the project on local infrastructure of the area such as road network and whether any additional infrastructure would need to be constructed and the agency responsible for the same with time frame.

69. Action plan for the green belt development – species, width of plantations, planning schedule etc. within the boundary around the IE in accordance to CPCB published guidelines.

70. In case of likely impact from the proposed project on the surrounding reserve forests, plan for the conservation of wild fauna in consultation with the State Forest Department.

71. For identifying the mitigation measures, please refer Chapter III for source control and treatment. Besides typical mitigation measures which may also be.

Analysis of alternative resources and

technologies

No new alternatives are required for this

project

72. Comparison of alternate sites considered and the reasons for selecting the proposed site. Conformity of the site with the prescribed guidelines in terms of CRZ, river, highways, railways, etc.

No new alternatives are required for this project

73. Evaluate alternative disposal modes of effluent and solid wastes, from the point of view of disposal points and associated impacts.

74. All kinds of resources both renewable and non-renewable shall be taken into account.

75. Details on improved technologies.

Environmental monitoring program Chapter-5

Page 17: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

xvi

76. Monitoring programme for pollution control at source.

Please refer Content: 5.2: OBJECTIVES OF ENVIRONMENTAL MONITORING PLAN 5.3: SUGGESTED ENVIRONMENTAL MONITORING PLAN Table 5.1: Environmental Monitoring Schedule

77. Monitoring pollutants at receiving environment for the appropriate notified parameter- air quality, groundwater, surface water, etc. during operational phase of the project.

78. Specific programme to monitor safety and health protection of workers.

79. Appropriate monitoring network has to be designed and proposed, to assess the possible residual impacts on VECs.

80. Details of in-house monitoring capabilities and the recognized agencies if proposed for conducting monitoring

Additional studies Chapter-6

81. Details on risk assessment and damage control during different phases of the project and proposed safeguard measures.

Please refer Content 6.1: RISK ASSESSMENT 6.2: HAZARD IDENTIFICATION 6.3: DISASTER MANAGEMENT PLAN (DMP) 6.4: HAZARDOUS CONTROL MEASURES 6.5: RISK AND EMERGENCY PREPAREDNESS PLAN 6.4: EMERGENCY PREPAREDNESS TRAINING 6.5: FIRST AID AND EMERGENCY PROCEDURES Table 6.1: Preliminary Hazard Analysis for Process and Storage Areas Table 6.2: Preliminary Hazard Analysis for the Whole Plant in General Table 6.3: First Aid for Burn

82. Details on socio-economic development activities such as commercial property values, generation of Jobs, education, social conflicts, cultural status, accidents, etc.

83. Proposed plan to handle the socio-economic influence on the local community. The plan should include quantitative dimension as far as possible.

84. Details on compensation package for the people affected by the project, considering the socio-economic status of the area, homestead oustees, land oustees and landless labourers.

85. Public hearing should be conducted as per the prescribed procedure. Points identified in the public hearing and commitment of the project proponent to the same. Detailed action plan addressing the issues raised, and the details of necessary allocation of funds.

86. The historical importance of the area shall also be examined on the study. While this analysis is being conducted, it is expected that an assessment of public perception of the proposed development

Page 18: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

xvii

be conducted.

87. Describe the application of industrial ecology concept for planning of IEs. Explore possibility of utilizing waste of one unit as raw material for the other units.

88. Specific chemical emergency response and proposed rescue system.

89. Details on corporate social responsibility proposal.

Environmental management plan Chapter-8

90. Administrative and technical organizational structure to ensure proposed post –project monitoring programme for approved mitigation measures.

Please refer Content 8.2:ENVIRONMENTAL MANAGEMENT CELL 8.3:EMP DURING CONSTRUCTION PHASE 8.4:ENVIRONMENTAL MANAGEMENT PLAN DURING OPERATIONAL PHASE 8.5: BUDGETARY PROVISION Figure 8.1: Environmental Management Cell Table 8.1: EMP &Environmental Management Cost

91. EMP devised to mitigate the adverse impacts of the project should be provided along with item –wise cost of its implementation (capital and recurring costs).

92. Allocation of resources and responsibilities for plan implementation.

93. Details of the emergency preparedness plan and on-site and off-site disaster management plan.

ADDITIONAL CORPORATE

ENVIRONMENTAL RESPONSIBILITY

Chapter-9

94. Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report.

Please refer Content 9.2: AIMS AND OBJECTIVES: 9.3: FUNCTIONS : 9.4: KIADB - AS A PREMIER INDUSTRIAL AREA DEVELOPER Figure 9.1: Organisation Chart

95. Does the Environmental Policy prescribe for standard operating process/procedures to bring into foals any infringement/ deviation/ violation of the environmental or forest norms / conditions? If so, it may be detailed in the EIA.

96. What is the hierarchical system or Administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions? Details of this system may be given.

Page 19: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

xviii

97. Does the company have a system of reporting of non-compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA report.

LIST OF ANNEXURES

ANNEXURES DESCRIPTION

Annexures I Land Documents

Annexures II Approved TOR

Annexures III Estimated Project Cost

Annexures IV Water NOC received from KIADB

Annexures V letter of STP, CETP and Solid Waste Management NOC received from KIADB

Annexures VI Power NOC received from KIADB

Annexures VII Layout Plan

Page 20: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

INTRODUCTION

Page 1

1. INTRODUCTION

1.1 PROFILE OF THE PROJECT PROPONENT

Karnataka Industrial Areas Development Board (KIADB) is a wholly owned infrastructure

agency of Government of Karnataka, set up under Karnataka Industrial Areas Development

Act of 1966. This Board functions as per statutory provisions, rules and regulations enacted

there under. The Board comprises of senior government officers in their ex-officio

capacities. KIADB holds pride in being the first government organisation in Karnataka to

obtain ISO 9001 certification in the year 1997.

The KIADB is following now ISO 9001:2000 module covering its functions of Land

Acquisition, Development and Allotment functions in Nelamangala Taluk and Bangalore

Rural district.

KIADB has so far developed 141 industrial areas in 28 districts of the State. KIADB has

proposed to develop Avverahalli Industrial Area at Dobaspet 4th Phase in the villages of

Yedehalli, Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, Avverahalli,

K.G.Srinivaspura, Billanakote, Nelamangala Taluk, and Bangalore Rural District.

Table 1.1: Project Details

Sl. No Particular Details

1. Project Proponent Karnataka Industrial Area Development (KIADB)

2. Project Name Establishment of Avverahalli Industrial Area at

Dobaspet 4th Phase

3. Project Location In the villages Yedehalli, Chandana Hosahalli,

Honnenahalli, Kengal Kempohalli, Avverahalli,

K.G.Srinivasapura, Billanakote, Nelamangala Taluk,

Bangalore Rural District, Karnataka.

4. Land Requirement 360.57 Hectares (891.25 Acres)

5. Schedule & Category 341.65Hectares (844.23 Acres)

6. Total Cost of the project 7 (C) & B category

Page 21: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

INTRODUCTION

Page 2

1.2 PROJECT LOCATION

The proposed project site is located at Dobaspet 4th Phase in the villages Yedehalli,

Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, Avverahalli, K.G.Srinivasapura,

Billanakote, Nelamangala Taluk, Bangalore Rural District, Karnataka. The project location is

shown in Figure 1.1.

Figure ‎1.1: Location of the Project

Page 22: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

INTRODUCTION

Page 3

1.3 NEED AND JUSTIFICATION OF PROJECT

The Dobaspet area is probably the industrialized area in the State of Karnataka and as such

there is not only influx of industries but also due to creation of new industries more workers

and man power have joined this places leading to a substantial increase in the population.

The project will generate direct and indirect employment opportunities for the local people.

The plant will create additional employment during construction & operational phase.

Additionally, certain works like security will be outsourced on contract. The secondary

employment in the form of providing services to the employed manpower will also be

developed in the neighboring villages.

Raw materials can be sourced locally. Hence the cost for procurement is less

Increase in Market & Business Establishment facilities

The State Government will benefit through revenue recovery from excise duty.

1.4 REGULATORY FRAME WORK

As per the Ministry of Environment & Forests (MOEF), Government of India EIA Notification

2006 and as amended on December 1, 2009, prior environmental clearance if necessary

before commissioning of the plant. The proposed project is covered under Schedule 7(c)

Category 'B' as per the Schedule of EIA Notification and hence requires environmental

clearance from MOEF.

Public hearing shall be conducted for the project as per provisions of Environmental Impact

Assessment Notification, 2006 and the issues raised by the public shall be addressed in the

EIA/EMP. More Applicable laws rules and acts:

The Water (Prevention and Control of Pollution) Act, 1974. (Amended 1988)

The Water (Prevention and Control of Pollution) Cess Act, 1977. (Amended 1991)

Air (Prevention and Control of Pollution) Act, 1981. (Amended 1987)

The Environmental (Protection) Rules 1986. (Amended 2002)

The Environmental (Protection) Act, 1986.

The hazardous Waste (Management & Handling) Rules, 1989 Under E.P.A. Act, 1986

(Amended 2000; 2003 & 2008)

E- Waste (Management & Handling) Rules, 2011

Page 23: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

INTRODUCTION

Page 4

1.5 EIA CONSULTANT

The proponents have engaged M/s ABC Techno Labs India Pvt. Ltd. Bangalore to carry out

EIA study.

1.6 PURPOSE OF THE REPORT

Every anthropogenic activity has some impact on the environment that often has a harmful

effect on the environment. However, mankind as it is developed today cannot live without

taking up these activities for their food, security and other daily needs. Therefore,

harmonious developmental activities with proper environmental consideration are essential

for any developmental activity. Environmental Impact Assessment (EIA) is an important tool

and essential technique available with the planners by which information about the

environmental effects of a project is clearly understood. This Environmental Impact

Assessment (EIA) study undertaken is mainly focused on identification of environmental

aspects of the project site, its impact on pre and post commissioning. A detailed prediction

of all environmental impacts associated with the various activities during the construction

and operation phases of the proposed plant and suggesting suitable measures to navigate

the observed adverse environmental impacts.

In other words, we can say that the purpose of an EIA is to determine the potential

environmental, social and health effects of a proposed development. It is a systematic

examination of the environmental consequences of projects, policies, plans and programs.

Its main aim is to provide decision-makers with an account of the implications of alternative

courses of action before a decision is made.

The Ministry of Environment and Forest (MOEF), Government of India in its latest

Notification (dated 14th September, 2006) on EIA directs that on and from the date of

publication of new Notification construction of new projects or activities or the expansion or

modernization of existing projects or activities listed in the Schedule should undertake the

EIA/EMP study before any construction work. The Schedule of this Notification has

mentioned that activities like building / construction projects / area development projects /

townships require ‘Environmental Clearance’ from the State Level Authority.

Page 24: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

INTRODUCTION

Page 5

1.7 OBJECTIVE OF STUDY

The objectives of the study are:

To establish the existing environmental settings of the project area based on

information obtained from primary data and compilation of secondary data from

published literature

To evaluate potential environmental impacts from the project during

construction and operational phases and identify appropriate mitigation

measures

To prepare an effective Environment Management Plan for proper

implementation and monitoring of mitigation measures

To develop post study monitoring programme

1.8 SCOPE AND METHODOLOGY OF THE STUDY

Preparation of relevant application in consultation with the client and Submission of

Form 1, IA & Conceptual Plan to MOEF to obtain Terms of Reference;

Presentation to the Expert Appraisal Committee (EAC) for approval of the Terms of

Reference in connection with the application submitted;

Conducting Environmental Impact Assessment (EIA) Studies for establishing the

initial baseline data on environmental parameters like air, water, noise level, land

use pattern, soil data, micrometeorological data, existing level of traffic and

communication, biological and archaeological components of study area and socio

economic data in the study region. The normal practice is to carry out the study for a

period of one season except monsoon. (i.e., Three Months);

Preparation of Environmental Impact Assessment (EIA) Report after Identification of

areas of concern and measures of their possible impact for the proposed project

&proposing appropriate Environmental Management & monitoring Plan;

Submitting the final EIA Report by incorporating Terms of References in consultation

with the client to the State Expert Appraisal Committee for Environmental Clearance;

and

Final presentation to SEAC and obtaining Environmental Clearance;

Page 25: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

INTRODUCTION

Page 6

1.9 APPROVED TOR FOR EIA STUDY BY MOEF

The application for the scoping of the said project has been submitted to the SEAC & SEIAA

Presentation for the scoping of the project (Terms of Reference (TOR) approval for EIA

study) was held on 14/March/2013. SEAC has issued the TOR for the EIA study on

06/April/2013. Copy of the issued TOR has been annexed as Annexure – II.

1.10 PLAN OF ACTION

The following is the broad work plan of the consultant.

Collection and collation of relevant data / information relating to the project

from the concerned departments, agencies and identification of information

gaps if any.

Review and analysis of secondary data collected as above to delineate the

baseline status of various environmental components and socio economic

parameters.

During the EIA study the applicable legal, policy and institutional frameworks will

also be addressed. Additionally the environmental standards pertaining to air

quality, water quality, noise emission and sewage/effluent discharge will be

considered for selection of appropriate mitigation measures to maintain the

assimilative capacity of environment. In a nutshell such standards will be used as

a control mechanism to limit the possible impacts to environment.

Monitoring of Ambient Air Quality, Water Quality, Noise and soil quality at

different locations within 15 Km radius of the project site leading to the firming

up of information on the identified issues / constraints and possible mitigation

measures thereof.

Discussions with various stake holders in the project to identify their views /

concerns / expectations, their knowledge base with respect to the proposed

project, their roles, etc. The outcome of such discussions would be complied and

consolidated for incorporation in the report.

Based on the assessment of impacts, proper mitigation measures shall be incorporated for

the construction and operation phase of the project, along with Management plan,

Monitoring plan and budget provisions for various Environmental aspects of the project.

Page 26: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

INTRODUCTION

Page 7

1.11 REPORT

The environmental assessment report will be concise and limited to significant

environmental issues. The main text will focus on findings, conclusions and recommended

actions supported by summaries of the data collected and citations for any references used

in interpreting those data. The environmental assessment report will be organized according

to the outline below.

Chapter 1:-INTRODUCTION

Chapter 2:-PROJECT DESCRIPTION

Chapter 3:-DESCRIPTION OF THE ENVIRONMENT

Chapter 4:-ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Chapter 5:- ENVIRONMENTAL MONITORING PROGRAM

Chapter 6:- ADDITIONAL STUDIES

Chapter 7:- PROJECT BENIFITS

Chapter 8:-ENVIRONMENTAL MANAGEMENT PLAN

Chapter 9:- ADDITIONALCORPORATE ENVIRONMENTAL RESPONSIBILITY

Chapter 10:- SUMMARY & CONCLUSION

Chapter 11:- DISCLOSURE OF CONSULTANTS ENGAGED

Page 27: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 8

2. PROJECT DESCRIPTION

2.1 PROJECT BACKGROUND

The proposed development of of Avverahalli Industrial Area of 844.23 Acres plot area at

Dobaspet 4th Phase in the villages of Yedehalli, Chandana Hosahalli, Honnenahalli, Kengal

Kempohalli, Avverahalli, K.G.Srinivaspura, Billanakote, Nelamangala Taluk, and Bangalore

rural District. KIADB has also acquired lands to cater the specific needs of individual

industrial units (Single Unit Complexes). Industries which are allotting come under orange &

red category. Total Cost Balance Sheet of the project is enclosed in Annexure III and Project

layout including survey numbers is enclosed in Annexure VII.

The project land use details are given below in Table 2.1.

Table ‎2.1: The project land use details

S.No Description Acres % of Land Use

1 Industries 416.65 49.35

2 Commercial 24.54 2.91

3 Amenity 19.03 2.25

4 Utility 23.89 2.83

5 Residential 43.24 5.12

6 Park 77.97 9.24

7 Buffer 183.96 9.95

8 Truck Parking 41.38 4.90

9 Road 113.57 13.45

Total Area 844.23 100

The proposed industrial area will include following infrastructure facilities:

Industrial Plots STP & CETP

Approach roads Power Sub-Stations

Internal roads with storm water drains Solid Waste Incinerator

Page 28: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 9

Power supply and street lighting Rain Water Harvesting System

Water supply network Public utilities

Parking/Buffer zone area. Green Belt Development

Housing complex Commercial

This chapter includes all the details of the project and its specific activities that will be

considered for investigation of the significant adverse impacts, the report also provides

specific measures that shall be put into practice to minimize the impact on the environment.

The site map showing the Project location is shown in Figure 2.1.

Figure 2.1: Location of the Project site

Page 29: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 10

2.2 JUSTIFICATION FOR SELECTING PROPOSED PROJECT SITE

The Dobespet area is probably the industrialized area in the State of Karnataka and as such

there is not only influx of industries but also due to creation of new industries more workers

and man power have joined this places leading to a substantial increase in the population.

The project will generate direct and indirect employment opportunities for the local people.

The plant will create additional employment during construction & operational phase.

Additionally, certain works like security will be outsourced on contract. The secondary

employment in the form of providing services to the employed manpower will also be

developed in the neighboring villages.

Raw materials can be sourced locally. Hence the cost for procurement is less

Increase in Market & Business Establishment facilities

The State Government will benefit through revenue recovery from excise duty.

2.3 EXISTING LAND USE PATTERN

The district has 81268 hectares of forests, which constitutes (13.88%) of the total

geographical area of the district (585431 ha). The fallow land in the district is around 39426

ha. Net area sown during the year is 2005-06 was around 318211 ha. And 8163 hectares of

land was sown more than once.

2.4 EXISTING INFRASTRUCTURE

a) Infrastructure

Industrial Areas in 6 places and 2 Industrial Estates in the district. In addition KIADB

has proposed to establish in an Industrial Area and Industrial Estate are proposed in

the district.

Suvarna Karnataka Development Corridor proposes a Readymade

Garment Zone, Food Processing Zone and Media & Entertainment Zone covering the

District.

b) Industry Profile

Huge scope for industrial growth and development in milk and milk products, food

processing, silk weaving industries aerospace industries for manufacturing of

aerospace components, sub- assemblies etc.

Page 30: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 11

Presence of many construction and infrastructure related industries such as bricks,

tiles and stoneware manufacturing

Power loom cluster in Doddaballapura in Bangalore Rural

c) Key Industries

Aerospace, Engineering & Allied Industries

SericultureAgro, Food Processing& Horticulture

Other focus sectors are- Information Technology, Pharmaceuticals,

AutomobilesTextiles, Tourism.

d) Educational Institutions

2 Engineering colleges, 1 medical college, 1 polytechnic and 2 ITIs in Bangalore Rural

District.

The prominent educational institutions are:

SSS Institute of Technology, Byranayakanahalli, Nelamangala Taluk.

JCS Industrial training Institute, Nelamangala.

SJM Polytechnic Nelamangala.

e) Tourism

Sivagange: This destination’s spring water is considered to be very sacred, while the

hillock is populated with a few temples.

Siddaganga mutt: Sree Siddaganga Mutt is an ancient ashram in Tumkur, which is

situated amidst a serene and colourful landscape.

2.5 PROJECT LOCATION & CONNECTIVITY

The project site is located in the villages of Yedehalli, Chandana Hosahalli, Honnenahalli,

Kengal Kempohalli, Avverahalli, K.G.Srinivaspura, Billanakote, Nelamangala Taluk, and

Bangalore rural District. The area lies in the northern latitude of 13°12’56.1” and eastern

longitude of 77°14’27.5”.

a) Rail – Proposed site is around 1.3 Km from Dobaspet railway station

b) Airport - Proposed site is 44.0 Km from Bangalore International airport

The road connectivity layout is given in Figure 2.2 and the road connectivity inside the

project site Layout is given in Figure 2.3.

a) The Existing road connectivity

East: NH4 mumbai to Chennai

Page 31: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 12

West: SH 3 Kanankapura – Ramamagara- Magadi- Pavagadi Road

South: The road which is connecting the NH4 and SH3

Figure ‎2.2: Connectivity to the site

Page 32: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 13

b) Internal Roads

The development of industrial area includes construction of 45m wide roads, 30m wide

roads, 24m wide roads, 18m wide roads, 15m wide roads and 12m wide roads. Three main

major of roads are proposed for the internal road transportation network and four miners.

The major 30 m wide road is connecting NN4 and SH3 and 45 m wide road is connecting 30

m wide road and NH4 and Proposed STRR BMRDA 90 m wide for the project, which is

adjacent to the project site. The miner roads 24 m, 18m, 15 m wide and 12m wide roads are

connected to major roads. The Road Network Layout is given in Figure2.3

Figure ‎2.3: Road Connectivity Layouts

Page 33: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 14

2.6 ENVIRONMENTAL SETTING OF THE SITE

The proposed site of highlights and salient features is given below in Table 2.2.

Table ‎2.2: Site Salient Features

Selection criteria Details

Elevation above Mean Sea Level 900 m

Climatic Conditions Max. Temp. 34.0o C

Min. Temp. 15.0o C

Average Rainfall: 859.6 mm

Land availability 844.23 Acres

Nearest Highway NH 4 adjacent to Eastern side

SH 3 adjacent to Western side

Nearest Railway station Dobaspet -1.3 Km (N)

Nearest airport Bangalore Airport- 44.0 Km (E)

Nearest Town / City Nelamangala – 15.0 Km

Bengaluru – 35.0 Km

Topography Plain

Archaeologically important places Nil within 15km radius

National parks/ Wildlife Sanctuaries Nil within 15km radius

Water Bodies/Rivers Lekkanahalli Kere

Kuluvanahalli Kere

Devara Kere

Muddalinganahalli kere

Thyamagondluamami kere

Tavare kere

1.6 Km (E)

2.4 Km (SE)

3.3 Km (W)

5.5 Km (NE)

4.5 Km (E)

5.6 Km (E)

Reserved/ Forests Nil within 15km radius

Seismicity The study area falls under seismic zone-II

Defense Installations Nil in 10 km radius

2.7 OCCUPANCY DETAILS

Total 1800 to 2000 manpower requirement at the construction Period, Inclusive of

Workmen, Supervisors, Engineers, Architects and Managers.

Page 34: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 15

2.8 WATER SUPPLY

The estimated water demand during the construction phase is 250 KLD (approx.), 90 KLD for

labors and 160 KLD for construction activities and water demand during the operation

phase is 11.5 MLD. During construction phase the water required will be sourced from

tanker supply and the water for the operation phase is drawn from Hemavathi River for

project needs. To this effect a letter of Water NOC received from KIADB are enclosed in

Annexure IV. Water Balance for the proposed project is given in Figure 2.4.

Figure ‎2.4: Water Balance Flow Sheet

2.9 SEWAGE GENERATION

Quantity of sewage generated during the construction phase will be 81 KLD. Sewage during

construction phase will be treated in smaller size/packaged (portable type) Sewage

Treatment Plant (STP) which will be based on Submerged Aerobic Fixed Film Reactor (SAFF).

During operation phase sewage generated will be treated in the Sewage Treatment Plant

(STP) planned in 4.7 Ac provided for STP. The estimated Sewage generations during

operation phase, 2.16 MLD. The treated water shall be reused in toilet flushing, gardening

Page 35: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 16

etc. and the wastewater generated from the industries is 7 MLD, which is treated in their

respective Effluent Treatment Plants (ETP) on the bases of advance and zero discharge

concept. The treated water is reuse for industries like cooling, heat exchangers, boilers,

cleaning equipment’s etc. To this effect a letter of STP & CETP Management NOC received

from KIADB are enclosed in Annexure V

a) Design Parameters

i. Raw Waste Water Quality

Table ‎2.3: Raw Water Quality

S.No Parameter Value Unit

1. Ph 6.5 –7.8 ---

2. Biological Oxygen Demand (BOD5) 600 mg/l

3. Chemical Oxygen Demand (COD) 1200 mg/l

4. Total Suspended Solids (TSS) 650 mg/l

5. Oil & Grease 100 mg/l

6. Total Coliform 1 x 106 MPN / 100 ml

7. Residual Chlorine NIL Mg/l

8. Temperature Ambient Degree Celsius

9. Total Kjeldahl Nitrogen (TKN as N) 100 mg/l

10. Ammonia Nitrogen (as N) 80 mg/l

11. Total Phosphorous (TP) 15 mg/l

ii. Treated Water Quality

The treated effluent quality to be guaranteed as per the standards prescribed by CPCB is as

below:

Table ‎2.4: Treated Effluent Quality for Secondary Treatment Plant and Tertiary Treatment

S.No Parameters

[Concentration in mg/l except pH & Temperature]

Into inland surface waters

On Land for Irrigation

Marine Coastal Areas

1 pH 5.5-9.0 5.5-9.0 5.5-9.0

Page 36: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 17

S.No Parameters

[Concentration in mg/l except pH & Temperature]

Into inland surface waters

On Land for Irrigation

Marine Coastal Areas

2 BOD (3days at 27°C) 30 100 100

3 Oil & Grease 10 10 20

4 Temperature Shall not exceed 40 °C in any section of the stream within 15 meters down steam from the effluent outlet

- 45 °C at the point of discharge

5 Suspended solids 100 200 (a) For process waste water-

100

(b) For cooling water

effluent, 10% above total

suspended matter of

effluent cooling water

6 DissolvedSolids(inorganic) 2100 2100 -

7 Total residuechlorine 1.0 - 1.0

8 Ammonical nitrogen(AsN) 50 - 50

9 Total Kjeldahl nitrogen(asN)

100 - 100

10 Chemical OxygenDemand 250 - 250

11 Arsenic(asAs) 0.2 0.2 0.2

12 Mercury(asHg) 0.01 - 0.01

13 Lead (asPb) 0.1 - 1.0

14 Cadmium (asCd) 1.0 - 2.0

15 Total Cadmium (asCr) 2.0 - 2.0

16 Copper(asCu) 3.0 - 3.0

17 Zinc(asZn) 5.0 - 15

18 Selenium(as Se) 0.05 - 0.05

19 Nickel (asNi) 3.0 - 5.0

Page 37: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 18

S.No Parameters

[Concentration in mg/l except pH & Temperature]

Into inland surface waters

On Land for Irrigation

Marine Coastal Areas

20 Boron (asB) 2.0 2.0 -

21 Percent Sodium - 60 -

22 Cyanide (asCN) 0.2 0.2 0.2

23 Chloride (asCl) 1000 600 -

24 Fluoride (asF) 2.0 - 15

25 Sulphate (asSO4) 1000 1000 -

26 Sulphide (asS) 2.8 - 5.0

27 Pesticides Absent Absent Absent

28 Phenoliccompounds (asC6H5OH)

1.0 - 5.0

Note: All efforts should be made to remove color and unpleasant odor as far as possible.

b) Design Scheme for Dual Plumbing System

Background of Phases 1 Development

For sustainable development, the dual plumbing of potable and non-potable water supply

system is designed for catering the demand of Industrial.

Design Philosophy for Dual Plumbing System

The proposed development will require water for different purposes i.e, drinking, flushing,

irrigation etc. The water usage can be classified into the following categories-

Potable water supply Non-potable water supply

Water for domestic use (other than non-potable use)

Water for firefighting.

Potable water for industrial and residential use.

Water for flushing purposes

Water for Landscape irrigation

AC make up water

Dual water supply line is proposed for the development consisting of water supply for

potable water use and non-potable water use. This will reduce the pressure on the

requirement of fresh water and also enable no discharge of treated sewage into the storm

Page 38: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 19

water drainage for disposal. The potable water will be supplied with the quality as per IS:

10500, 1991 standards.

The non-potable water will be supplied from the elevated reclaimed water reservoir after

the tertiary treatment of the sewage through ETP and STP. The demand for different types

of water usage is considered as per NBC: 2005 (National Building Code). The proposed water

flow diagram of water cycling is shown in following Figures 2.8 for industrial applications.

Figure ‎2.5: Flow Diagram for Water Cycling in Industrial Area

2.10 SOLID WASTE GENERATION, COLLECTION, TRANSPORT AND DISPOSAL

a) General

The manufacturing/ production sections will produce the Industrial fraction of waste and

the non-production sections such as administration buildings, green spaces, roads and the

working population will generate the Municipal waste. The quantities of waste likely to be

generated from the proposed project have been estimated on the basis of population and

land use characteristics. For management of Industrial waste individual industrial units may

Page 39: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 20

consider having an agreement with the nearest Treatment, Storage, Disposal Facility (TSDF)

operator to dispose the hazardous waste and 5.8 Ac is provided for Solid Waste &

Incinerator for operational phase. TSDF sites generally have land filling and incineration

facilities are available within their premises.

The industries generating solid waste have to manage such waste by themselves and are

required to seek authorizations from Karnataka Pollution Control Boards under relevant

rules. To this effect a letter of Solid Waste Management NOC received from KIADB are

enclosed in Annexure V.

Table ‎2.5: Type of waste from Industrial Phase and Non Industrial Phase

Industrial waste

Auto Ancillary Hazardous and non-hazardous waste including Waste oil, Batteries, Aerosol cans, Bleaches, Kitchen drain cleaning agents, Car batteries, Oil filters and car care products, Chemicals, solvents and their empty containers, Cosmetic items, Chemical based Insecticides and containers, Light bulbs, tube lights, CFLs, paints, oils, lubricants, glues, thinners, pesticides and herbicides and their empty containers, photographic chemicals, Styrofoam, soft foam packaging from new equipment, Thermometers, mercury containing products, Commercial and Industrial Packaging Film

Food & FMCG

Electronic & White Goods

Logistics

Ready Built factories (RBF)

ETP Sludge Dried hazardous sludge

Non Industrial waste

Amenities Centre Paper, cardboard, plastics, wood, food wastes

Canteen Paper, cardboard, plastics, wood, food wastes, glass, metals

Utilities Sludge, silt, street sweeping , paper, plastics

Transportation/ Parking Waste oil, lubricants, coolants, paper,, etc

Green/ Open space Dry and wet Leaves, Tree- trimmings, Grass

a) Waste Quantification

The quantities of waste likely to be generated from the industrial and non-industrial phases

have been estimated on the basis of population and land use characteristics. Table 2.6

presents the estimated solid waste quantities from the proposed project.

b) Industrial Solid Waste

Management of Industrial Solid Waste (ISW) is not the responsibility of Rural Local Bodies/

Municipalities. The industries generating solid waste have to manage such waste by

Page 40: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT DESCRIPTION

Page 21

themselves and are required to seek authorizations from Karnataka Pollution Control Boards

under relevant rules.

It is estimated that approximately 756 Kg/day (0.76 TDP) of total industrial waste will be

generated. This waste can be classified as Hazardous Industrial Waste & Non-hazardous

Industrial Waste likely to be generated from Avverahalli Industrial area at Dobaspet 4th

Phase.

c) Municipal Solid Waste

The Avverahalli Industrial area at Dobaspet 4th Phase Development will also generate

Municipal Solid Waste (MSW) from Non-Manufacturing/ non-production sections of the

Industrial Units such as Administration blocks, Canteen, Toilets, Utilities, etc due to the

working population in that area along with waste generated from Green spaces, roads,

parking areas.

The estimated quantity of Municipal waste likely to be generated from Avverahalli Industrial

area is 2665 Kg/day (2.7 TPD) and 300 Kg/day sludge from STP.

Table ‎2.6: Estimated Solid Waste Quantity from Avverahalli Industrial Area

S. No

Solid Waste Bio- Degradable,

in Kg/day

Recyclable, in Kg/day

Non- biodegradable,

in Kg/day

Total waste from different phases,

in Kg/day

1. Industrial Waste

340 91 325 756

2. Municipal Waste

1199 320 1146 2,665

3. STP Sludge 300 300

Total Solid Waste, in Kg/day

1,368 1839 411 1,471

2.11 POWER DETAILS

The power requirement for the proposed development is 63.3 MVA and 10.2 Ac provided

for Sub Station. The source of power will be from KIADB. To this effect a letter of Power

NOC received from KIADB is enclosed in Annexure VI.

Page 41: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 22

3. DESCRIPTION OF THE ENVIRONMENT

3.1 INTRODUCTION

Baseline Environmental Studies have been conducted within the project site to determine

the existing status of various Environmental attributes viz., Climatic and Atmospheric

conditions, Air, Water, Noise, Soil, Hydro geological, Land use pattern, Ecological and Socio-

Economical environment, prior to setting up of the proposed project. This study would help

to undertake corrective mitigation measures for protection of the environment on account

of any change deviation of attributes due to activities of the proposed project.

3.2 SCOPE OF THE BASELINE STUDY

An area around the project site is considered as the study area for the purpose of the

baseline studies. Primary data on Water, Air, Land, Flora, Fauna & Socio-Economic data

were collected by a team of Engineers and Scientists. Secondary data was collected from

various Departments of State/Central Government Organizations, Semi-Government and

Public Sector Organizations. Table 3.1 gives various environmental attributes considered for

formulating environmental baseline and Table 3.2 gives the frequency and monitoring

methodology for various environmental attributes.

Table ‎3.1: Various Environmental Attributes

S. No.

Attribute Parameter Source of Data

1 Land Use Trend of land use change for different categories

Topo sheet

2 Water Quality

Physical, Chemical and Biological parameters

Water samples are collected at six locations during this study period

3 Ambient Air Quality

RSPM, SPM, SO2 and NOx Ambient air quality monitoring at six locations

4 Noise levels Noise levels in dB(A)

Noise level monitoring at six locations

5 Ecology Existing terrestrial flora and fauna within the 10 km radius of project influence area

Secondary sources and Field survey

6 Geology Geological history Secondary sources

7 Soil Soil types and samples analyzed for physical and chemical parameters.

Data collected from secondary sources and soil sample analysis at five

Page 42: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 23

locations

8 Socio economic Aspects

Socio-economic characteristics of the affected area

Based on field survey and data collected from secondary sources

Table ‎3.2: Frequency and Monitoring Methodology

Attributes Sampling Measurement

Method Remarks

Network Frequency

A. Air Environment

Particulate Matter (PM10)

Requisite locations in the project influence area

24 hourly

Gravimetric (High- Volume with Cyclone)

As per CPCB standards under November 18th 2009 Notification for NAAQS

Particulate Matter (PM 2.5)

Gravimetric (High- Volume with Cyclone)

Oxides of Sulphur (SO2) Requisite locations in the project influence area 24 hourly

EPA Modified West &Gaeke method

NOx Arsenite Modified, Jacob &Hochheiser

B. Noise

Hourly equivalent noise levels

Requisite locations in the project influence area

Once

Instrument : Noise level meter

IS: 4954 1968

C. Water

Parameters for water quality: pH, temp, turbidity, Total hardness, total alkalinity, chloride, sulphate, nitrate, fluoride, sodium, potassium, Electrical Conductivity, Ammonical nitrogen, Nitrate-Nitrogen total phosphorus, , BOD, COD, Calcium, Magnesium, Total Dissolved Solids, Total Suspended Solids

Set of grab samples At requisite locations for ground and surface water

Once Samples for water quality collected and analyzed as per IS : 2488 (Part 1-5) methods for sampling and testing of Industrial effluents Standard methods for examination of water and wastewater analysis published by American Public Health Association.

D. Land Environment

Parameter for soil quality: pH, texture,

Requisite soil samples be

Once

Collected and analyzed as per soil

Page 43: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 24

electrical conductivity, organic matter, nitrogen, phosphate, sodium, calcium, potassium and Magnesium.

collected as per BIS specification within project influence area

analysis reference book, M.L.Jackson

Google map showing 10 Km radius showing the project location and surrounding features is given in Figure 3.1.

Figure 3.1: Satellite Imagery of the site (10 Km radius)

Page 44: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 25

Topo maps showing 5 & 10 km radius showing the project location and nearest habitats

Figure 3.2.

Figure ‎3.2: Topo map 5 & 10 km radius showing the project location and nearest habitats

Page 45: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 26

Satellite Imagery Showing the project location and Road connectivity Figure 3.3.

Figure ‎3.3: Satellite Imagery showing the project location and Road Connectivity

Page 46: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 27

LandUse/ Land Cover showing 5 & 10 km radius showing the project location and

surrounding features Figure 3.4.

Figure 3.4: LandUse/ Land Cover 5 & 10 km radius showing the project location &

surrounding features

Page 47: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 28

3.3 TEMPERATURE

High relative humidity between 60 and 85% prevail throughout the year. Higher rates of

relative humidity are observed between August and October i.e., 71 to 85%. In the months

of Feb, the humidity is lower i.e., around 60%. The minimum and maximum temperature is

15°C &34°C. The Bangalore District Weather Report for the monitored month of September

2013 to December 2013 is given in Table 3.3, 3.4, 3.5& 3.6.

Source: IMD Panambur & District Groundwater Brochure, Udupi District, Karnataka, Ministry

of Water Resources, Central Ground Water Board.

Table ‎3.3: Udupi District Weather Report for September, 2013

Table ‎3.4: Udupi District Weather Report for October, 2013

Summary Air Temp. (o C ) Relative

Humidity (% ) Wind Speed

(Kmph) Max Min

20-09-2013 28 19 82 6

21-09-2013 28 19 76 4

22-09-2013 28 19 66 6

23-09-2013 28 19 63 6

24-09-2013 28 19 66 4

25-09-2013 28 19 65 4

26-09-2013 28 19 62 4

27-09-2013 28 19 55 4

28-09-2013 28 19 67 4

29-09-2013 28 19 60 6

30-09-2013 28 19 72 5

Monthly Average

28 19 66.7 4.81

Summary Air Temp. (o C ) Relative

Humidity (% ) Wind Speed

(Kmph) Max Min

01-10-2013 28 19 71 4

02-10-2013 28 19 66 4

03-10-2013 28 19 67 5

04-10-2013 28 19 60 6

05-10-2013 28 19 60 6

06-10-2013 28 19 65 5

07-10-2013 28 19 67 4

08-10-2013 28 19 76 3

09-10-2013 28 19 76 2

10-10-2013 28 19 69 4

11-10-2013 28 19 60 4

Page 48: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 29

Table ‎3.5: Udupi District Weather Report for November, 2013

12-10-2013 28 19 65 6

13-10-2013 28 19 67 6

14-10-2013 28 19 62 4

15-10-2013 28 19 72 3

16-10-2013 28 19 72 3

17-10-2013 28 19 70 1

18-10-2013 28 19 64 2

19-10-2013 28 19 67 2

20-10-2013 27 18 77 0

21-10-2013 27 18 81 2

22-10-2013 27 18 85 2

23-10-2013 27 18 82 3

24-10-2013 27 18 83 3

25-10-2013 27 18 76 2

26-10-2013 27 18 74 3

27-10-2013 27 18 75 3

28-10-2013 27 18 84 2

29-10-2013 27 18 70 1

30-10-2013 27 18 73 1

31-10-2013 27 18 67 1

Monthly Average 27.6 18.6 71.0 3.1

Summary Air Temp. (o C ) Relative

Humidity (% ) Wind Speed

(Kmph) Max Min

01-11-2013 27 18 67 2

02-11-2013 27 18 77 3

03-11-2013 27 18 74 3

04-11-2013 27 18 68 3

05-11-2013 27 18 67 2

06-11-2013 27 18 64 5

07-11-2013 27 18 63 2

08-11-2013 27 18 63 2

09-11-2013 27 18 61 2

10-11-2013 27 18 61 3

11-11-2013 27 18 64 1

12-11-2013 27 17 66 0

13-11-2013 27 17 66 0

14-11-2013 27 17 61 1

15-11-2013 26 17 57 1

16-11-2013 26 17 81 2

17-11-2013 26 17 79 3

18-11-2013 26 17 79 4

19-11-2013 26 17 72 2

Page 49: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 30

Table ‎3.6: Udupi District Weather Report for December, 2013

20-11-2013 26 17 63 1

21-11-2013 26 17 60 1

22-11-2013 26 17 58 0

23-11-2013 26 17 81 2

24-11-2013 26 17 81 2

25-11-2013 26 16 76 2

26-11-2013 26 16 71 2

27-11-2013 26 16 63 0

28-11-2013 26 16 60 1

29-11-2013 26 16 72 1

30-11-2013 26 16 64 2

Monthly Average 26.4 17.1 67.9 1.83

Summary Air Temp. (o C ) Relative

Humidity (% ) Wind Speed

(Kmph) Max Min

01-12-2013 26 16 71 2

02-12-2013 26 16 69 3

03-12-2013 26 16 62 2

04-12-2013 26 16 62 3

05-12-2013 26 16 58 2

06-12-2013 26 16 50 2

07-12-2013 26 16 59 1

08-12-2013 26 16 60 1

09-12-2013 26 16 50 1

10-12-2013 26 16 34 1

11-12-2013 26 16 36 1

12-12-2013 26 16 57 2

13-12-2013 26 16 64 2

14-12-2013 26 16 69 3

15-12-2013 26 16 54 1

16-12-2013 27 15 46 0

17-12-2013 27 15 61 0

18-12-2013 27 15 64 1

19-12-2013 27 15 61 2

20-12-2013 27 15 59 1

Monthly Average

26.25 15.75 57.3 1.55

Page 50: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 31

3.4 WIND PATTERN AT THE PROPOSED SITE

Climatologically data were collected from the nearest Bangalore IMD station to understand

the wind pattern of the area. Predominant wind direction and wind speed data, based on

observation at nearest Bangalore IMD stations for the period 12 months, is given in Table

3.7.

Table ‎3.7: Wind data (2013)

Month Mean wind speed (Kmph) Annual

January 4.9

February 5.0

March 5.7

April 6.5

May 7.8

June 4.5

July 3.1

August 5.1

September 3.5

October 5.8

November 4.0

December 4.6

Source: IMD Bangalore.

Mean wind speed and wind directions are as under,

3.1 Kmph min (July)

7.8 Kmph max (May)

Wind rose for the month of October to December are given in Figures 3.5, 3.6 & 3.7.

Page 51: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 32

Figure 3.5: Wind rose for the month of October

Page 52: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 33

Figure ‎3.6: Wind rose for the month of November

Page 53: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 34

Figure ‎3.7: Wind rose for the month of December

3.5 RAINFALL

The climate in Bangalore rural district is quite salubrious, with three different seasons. The

pre-monsoon starts from January to May. This period can be divided into winter (January to

February) and summer (March-May). Winter is characterized by generally clear skies and

very little rainfall. From April onwards erratic thunderstorms occur in the area which

increases during May. The temperature is lowest during December and January.

Page 54: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 35

The mean annual rainfall of the district is 824 mm. Doddaballapur taluk receives the lowest

rainfall of 680 mm where as Hoskote and Nelamangala taluk receives the highest rainfall 0f

776 mm. Tables 3.8 and depicted in Figures 3.8 respectively.

Table ‎3.8: Rainfall data from 2008 to 2012

Year Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec

2008 0.0 2.1 100.9 15.2 100.7 11.8 149.1 223.0 103.9 150.4 25.2 2.3

2009 0.0 0.0 17.3 11.7 92.4 96.3 30.0 101.5 258.1 23.2 31.3 20.0

2010 0.0 0.0 18.5 42.4 114.0 141.4 145.6 148.4 108.9 86.1 149.1 11.2

2011 0.0 2.5 2.7 88.7 97.5 47.4 106.1 230.6 61.9 130.2 26.7 5.2

2012 0.0 0.0 4.3 57.7 108.2 20.4 73.2 138.3 47.6 79.6 106.8 14.4

Figure ‎3.8: Rainfall Data From 2008-2012

3.6 TOPOGRAPHY OF THE SITE

The topographic setting of the city has radial slopes towards east and west with a smooth

ridge running north to south; rainfall over the ridge area gets divided and flows east or west

into the three gentle slopes and valleys of Koramangala–Challagatta, Hebbal and

Vrishabavathi. Doddabettahalli 1,062 m (3,484.3 ft) is the highest point on this ridge. These

naturally undulating terrain of hills and valleys, lends itself perfectly to the development of

0

50

100

150

200

250

300

Rai

nfa

ll in

mm

Months

Rainfall Data from 2008-2012

2008

2009

2010

2011

2012

Page 55: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 36

lakes that can capture and store rainwater. Small streams are formed by each valley starting

with the ridge at the top. A series of shallow tanks varying in size are developed. The gentle

topography has also good potential of ground water development.

Figure 3.9: Topo map 5, 10 & 15 km radius showing the project location and surrounding

features

Page 56: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 37

3.7 EXISTINGLAND USE OF THE SITE

The district has 81268 hectares of forests, which constitutes (13.88%) of the total

geographical area of the district (585431 ha). The fallow land in the district is around 39426

ha. Net area sown during the year is 2005-06 was around 318211 ha. And 8163 hectares of

land was sown more than once.

The proposed plot area 341.65 ha (844.23 Acres) is spread in the Villages of Yedehalli,

Chandana Hosahalli, Honnenahalli, KengalKempohalli, Avverahalli, K.G.Srinivasapura,

Billanakote, NelamangalaTaluk, Bangalore Rural District. The land is vacant and it contains

bushes and shrubs.

This land is acquired by Karnataka Industrial areas Development Board (KIADB) as per the

following policies and acts

a) Karnataka Export Promotion Policy

b) Karnataka Industrial Policy 2009-14

c) The Karnataka Industrial Areas Development Act, 1966.

Table ‎3.9: The project land use details

S.No Description Acres % of Land Use

1 Industries 416.65 49.35

2 Commercial 24.54 2.91

3 Amenity 19.03 2.25

4 Utility 23.89 2.83

5 Residential 43.24 5.12

6 Park 77.97 9.24

7 Buffer 183.96 9.95

8 Truck Parking 41.38 4.90

9 Road 113.57 13.45

Total Area 844.23 100

3.8 WATER BODIES

List of water bodies located near to this project site is given in below Table 3.10 and

showing in Figure 3.10.

Page 57: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 38

Table ‎3.10: List of water bodies located near to Project Site

S.no Name of Lake Distance & Location

1. Lekkanahalli Kere 1.6 Km (E)

2. Kuluvanahalli Kere 2.4 Km (SE)

3. Devara Kere 3.3 Km (W)

4. Muddalinganahalli kere 5.5 Km (NE)

5. Thyamagondluamami kere 4.5 Km (E)

6. Tavare kere 5.6 Km (E)

Figure ‎3.10: water bodies near to Project Site

3.9 GEOMORPHOLOGY AND SOIL TYPES

Physiographycally the district can be divided in to rocky upland, plateau and flat-topped hills

at an elevation of about 900 m. amsl. Flat-topped Laterite hills are seen in the northern part

at an elevation of 900 m. a msl. The pediplains form major part of the district underlain by

Page 58: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 39

gneisses and granites with the highest pediplain in the range of 850m and 950m amsl. Rocky

upland pediplain and plateau constitute erosional topography. Major part of the pediplain is

dissected by streamlets flowing in southerly direction. In northern part of

Doddaballpurtaluk, the pediplains have northerly slope dissected by various streamlets. The

major part of the district lies in Cauvery basin.

Important rivers draining the area are Cauvery, south Pennar, North Pennar and palar,

Cauvery with its tributaries like Kanva, Arkavathi and Shimsha draining the area. The other

important rivers Kumudavathi Pinakini. The tributaries of Pennar River, drain northeastern

part of the district. The drainage pattern is trellis to sub-dendratic. The drainage map of the

district is presented as Igglur Anecut project is a medium irrigation project in operation with

about 4380 hectares of command area in Chennapatnataluk, Manchanabele reservoir

project with about 3846 hectares of command area in Ramanagaamtaluk and Arkavathi

Reservoir project with about 4957 hectares of command area in Kanakapurataluk. About

13057 hectares of land is under irrigation from minor irrigation tanks and about 1341

hectares of land is under lift irrigation in the district. The other important rivers

Kumudavathi and Pinakini. The tributaries ofPennar River, drain northeastern part of the

district. The drainage pattern is trellis to sub-dendratic.

The soils of Bangalore Rural districts are broadly classified in to four categories viz (i). Loamy

soil (ii) Lateritic soil (iii) Lateritic gravelly soil and (iv)Red sandy soil. Red loamy soils generally

occur on hilly to undulating land slope on granite and granite gneisses. Lateritic soil occurs in

undulating terrain forming plain to gently sloping topography of peninsular gneiss region.

Lateritic gravelly soils occur in upland regions of lateritic soils, Red sandy soil occurs in

undulating land slopes. These soils are derived from acidic rocks granites and granitic gneiss.

Source:District Groundwater Brochure, Bangalore Rural District, Karnataka, Ministry of

Water Resources, Central Ground Water Board.

Page 59: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 40

Figure ‎3.11: Drainage and Hydrography Monitoring of Bangalore Rural District

Page 60: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 41

Figure ‎3.12: Drainage map of Project Site

Page 61: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 42

3.10 HYDROGEOLOGY

Geology of the Bangalore rural district is broadly described under two groups (i) the

dominating Archaean crystalline formation comprising peninsular gneissic complex with a

small patch of horn blend schist in the northern part and intrusive closepet granite all along

the western part of the district (ii) smaller stretches of unconsolidated sediments. The

granite gneisses are mainly of migmatitic type, highly banded in composition from granite to

diorite. The Hydrogeology map of the district is presented as Fig-3. The ground water occurs

in the open spaces of weathered fractured gneisses and granites. In these rocks the water

bearing and yielding properties are primarily due to weathering and fracturing. In the

weathered zone, ground water occurs under water table conditions and in the fractured and

jointed formations it occurs under semi confined conditions. In Laterite ground water occurs

under phreatic condition. Alluvium along the river courses, though limited in thickness and

aerial extent possess substantial ground water potential.

Figure 3.13: Hydrogeology Map of Bangalore Rural District

Page 62: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 43

3.11 GROUND WATER QUALITY

The Electrical conductivity values are in the major part of the district are in the range

between 750 to 1000 micro mhos. In Nelamangala taluk, the EC varies from 500 to 750

micro mhos. In northern part of Devenahalli taluk, EC values of more than 2000 micromhos

/cm are observed. Flouride content more than the permissible limit is observed in

Nelamangala, Doddaballapura and Devenahalli taluk. Chloride problem in the district

(Chloride content more than 250 to 1000mg/L) are observed in Nelamangala,

Doddaballapur, Devenahalli and in Hoskotetaluks.

The proposed project site comes under Nelamangala Taluk which is identified as a semi

critical Zone. Figure 3.14 gives the detailed ground water quality of Bangalore Rural District.

Figure 3.14: Ground Water Quality of Bangalore Rural District

Page 63: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 44

3.12 NATURAL HAZARD VULNERABILITY

a) Seismicity

The Geological Survey of India has identified Bangalore Rural District as least earthquake-

prone region and categorized in Seismic II Zone. The Seismic zonation map of India is given

in Figure 3.15.

Figure ‎3.15: Seismic Zonation Map of India

Page 64: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 45

List of occurrence of major Earthquakes are given below in Table 3.11.

Table ‎3.11: Earthquakes in India

Date Magnitude Latitude Longitude Location

8 October 2005 7.6 34.432 73.537 Kashmir-Kohistan

26 December 2004 9.2 03.295 95.982 Sumatra-Andaman

26 January 2001 7.7 23.422 70.310 Bhuj, Gujarat

29 March 1999 6.4 30.511 79.421 Chamoli, Uttarakhand

22 May 1997 5.8 30.511 79.421 Jabalpur, Madhya Pradesh

30 September 1993 6.2 18.089 76.473 Killari, Maharashtra

20 October 1991 6.8 30.769 78.791 Uttarkashi, Uttarakhand

20 August 1988 6.9 26.719 86.626 UdaypurGahri, Nepal

11 December 1967 6.5 17.540 73.840 Koyna, Maharashtra

30 May 1935 7.8 28.870 66.400 Quetta, Balochistan

15 January 1934 8.1 26.600 86.800 Nepal-Bihar border

27 August 1931 7.3 29.200 67.600 Mach, Balochistan

2 July 1930 7.1 25.800 90.200 Dhubri, Assam

8 July 1918 7.1 24.500 91.000 Srimongal, Bangladesh

4 April 1905 7.8 32.100 76.400 Kangra, Himachal Pradesh

12 June 1897 8.1 25.500 91.000 Shillong Plateau, Meghalaya

10 January 1869 7.4 25.500 91.000 Cachar-Manipur

26 August 1833 7.6 27.700 85.700 Eastern Nepal

16 June 1819 8.2 23.000 69.000 Allah Bund, Gujarat

Source: www.ASC-India.org

So it is clear that the proposed site is not prone to earthquake &it’s in stable zone.

3.13 AIR ENVIRONMENT

The prime objective of baseline air monitoring is to evaluate the existing air quality of the

area. This will also be useful for assessing the conformity to standards of the ambient air

quality during the construction and operation of the proposed project. This section

describes the selection of sampling locations, methodology adopted for sampling, analytical

techniques and frequency of sampling. The results of ambient air monitoring carried out in

the 10 locations of the study area. The results of ambient air monitoring carried out during

Page 65: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 46

the study during the month of September, October and November 2013. The methodology

adopted for Air quality survey is given below.

a) Selection of Sampling Locations

The baseline status of the air quality in the study area has been assessed through a

scientifically designed ambient air quality monitoring network. The design of monitoring

network in the air quality surveillance has been based on the following considerations;

Meteorological conditions

Topography of the study area

Locations where air quality is likely to be impacted as a result of localized

activities or disturbances & Site Specific Conditions

Ambient Air Quality Monitoring (AAQM) stations were set up at Seven locations with

due consideration to the above mentioned points. The locations of the selected stations are

given in Table 3.12 and shown in in Figure 3.16.

Table ‎3.12: Ambient Air Quality Monitoring Locations

Location Code Location Latitude & Longitude

Direction* Distance in

Km* Elevation

Q1 Project Site, Dobaspet

N-13º12’26.90” E-77º14’58.67”

- - 3069

Q2 Hossahalli

N-13º12’09.28” E-77º16’38.00”

ESE 3.04 2986

Q3 Pemmanahalli

N-13º14’01.31” E-77º16’02.98”

NNE 3.41 3041

Q4 Agalakuppa

N-13º13’50.18” E-77º13’48.16”

NW 3.35 3085

Q5 Thyamagondulu

N-13º13’02.22” E-77º18’08.98”

ENE 5.76 2931

Q6 Basavapatna

N-13º08’46.10” E-77º14’38.66”

S 6.85 3057

Q7 Veersagara

N-13º13’00.85” E-77º12’10.76”

WNW 5.22 2997

Page 66: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 47

Figure ‎3.16: Ambient Air Quality Monitoring Locations

b) Instruments for Sampling

Respirable Dust Samplers were used for monitoring Total Suspended Particulate Matter

(TSPM), Respirable fraction (<10 microns) and gaseous pollutants like SO2 and NOx.

c) Sampling and Analytical Techniques

The air inlet has a circular symmetry so that air entry is unaffected by wind direction and is

designed to keep out rain, insects and very large particles. The inlet section immediately

leads to an impactor stage designed to trap particles with an aerodynamic diameter larger

than 10 microns. Thus the air stream in the down tube consists of only medium and fine

particulates. The streamlined air flow of the down tube is accelerated through the nozzle of

the well-shapedimpactor designed to trap medium size particulates with an aerodynamic

diameter between 2.5 and 10 microns. To avoid sampling errors due to the tendency of

small particles to bounce off the impaction surface a 37mm diameter GF/A paper immersed

Page 67: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 48

in silicone oil is used as an impaction surface. The air stream leaving the WINS impactor

consists of microns. These fine particles are collected on a special Teflon membrane filter of

47 mm diameter. Modified West and Gaeke method (IS – 5182 part – II, 1969) has been

adopted for estimation of SO2 and Arsenite Modified Jacob &Hochheiser has been adopted

for estimation of NOX.

d) Calibration

Calibration charts have been prepared for all gaseous pollutants. The calibration is carried

out whenever new absorbing solutions are prepared and used.

Table ‎3.13: Techniques for Ambient Air Quality Monitoring

S.No Parameter Technique Minimum Detectable

Limit (µg / m3)

1 Particulate Matter(PM10)

Respirable Dust Sampler (Gravimetric method)

1.0

2 Particulate Matter(PM2.5)

Respirable Dust Sampler (Gravimetric method)

1.0

3 Sulphur Dioxide West and Gaeke 5.0

4 Nitrogen Oxide Jacob &Hochheiser 5.0

e) Presentation of Data

Various statistical parameters like the average, maximum and minimum values have been

computed from the observed raw data for all the AAQ monitoring stations. These are

compared with the standards prescribed by Central Pollution Control Board (CPCB) for

residential and Industrial zone. Pollutant specific monitoring results indicating levels of

PM10, PM2.5, SO2 and NOx with respect to applicable standards are presented in Table 3.14.

Page 68: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 49

Table ‎3.14: Summary of Ambient Air Monitoring

Code Location PM 10 PM 2.5 SO2 NOx

Min Max Avg 98

per

Min Max Avg 98

per

Min Max Avg 98

per

Min Max Avg 98

per

Q1 Project Site,

Dobaspet 48 63 55.4 60.2 23 34 28.6 33.6 5.5 7.2 6.3 7.1 13.8 16.4 15.1 16.2

Q2 Hossahalli 51 67 59.1 66.8 22 37 29.7 36.5 5.8 8.2 7.1 8.1 15.6 19.7 17.3 19.5

Q3 Pemmanahalli 55 71 63.4 70.5 25 36 30.7 35.7 5.5 7.6 6.5 7.5 14.2 18.3 16.2 18.1

Q4 Agalakuppa 48 59 53.7 58.6 21 29 25.1 28.4 5.2 6.1 5.7 6.0 12.2 15.6 14.9 15.3

Q5 Thyamagondulu 52 64 58.2 63.7 23 31 27.2 30.8 5.4 6.6 6.0 6.5 13.7 16.4 15.1 16.1

Q6 Basavapatna 45 54 49.5 53.7 20 27 23.6 26.7 5.2 6.0 5.6 5.9 11.8 14.6 13.2 14.4

Q7 Veersagara 42 55 48.4 54.6 18 26 22.1 25.7 5.0 5.8 5.4 5.7 10.7 13.4 12.2 13.3

CPCB Standards

Industrial /Residential /

Rural and Other Area

100 60 80 80

Page 69: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 50

f) Observation

PM10 – A maximum value of 63.4µg/m3 was observed at Near Pemannahali (Q3). A

minimum of 48.4µg/m3 was observed at Veersagara (AAQ7).The 24 hours applicable limit

for industrial/residential/rural areas is 100µg/m3, the sampled locations are within the

prescribed limit.

PM2.5 – The maximum value of 30.7µg/m3 was observed at Near Pemannahali (Q3). A

minimum of 22.1µg/m3 was observed at Veersagara (AAQ7).The 24 hours applicable limit is

60µg/m3 for industrial/residential/rural areas, the sampled locations are within the

prescribed limit.

Figure ‎3.17: Graphical Representation of PM10 & PM2.5

SO2 - The maximum value of 7.1µg/m3 was observed at Near Hasahallli (Q2). A minimum of

5.4µg/m3 was observed at Veersagara(Q7). The 24 hours applicable limit is 80µg/m3 for

industrial/residential/rural areas, the sampled locations are within the prescribed limit.

NOX - The maximum value of 17.3µg/m3 was observed at Hasahallli(Q2). A minimum of

12.2µg/m3 was observed at Veersagara (Q7). The 24 hours applicable limit is 80µg/m3 for

industrial/residential/rural areas, the sampled locations are within the prescribed limit.

0

10

20

30

40

50

60

70

µg/

m3

Sample locations

Graphical Representation of PM10 & PM2.5

PM10

PM2.5

Page 70: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 51

Figure ‎3.18: Graphical Representation of NOx& SO2

The air quality data in the monitored area within the project site is within the prescribed

limit.

3.14 NOISE ENVIRONMENT

The most common and universally accepted scale is the ‘A’ weighted scale which is

measured as dB (A). The Environmental Impact Assessment of noise from the construction

activity and vehicular traffic can be undertaken by taking into consideration various factors

like potential damage to hearing, physiological responses, and annoyance and general

community responses. The environmental impact of noise can have several effects varying

from Noise Induced Hearing Loss (NIHL) to annoyance depending on loudness of noise.

The impact of noise sources on surrounding community depends on:

Characteristics of noise sources (instantaneous, intermittent or continuous in

nature). It can be observed that steady noise is not as annoying as one which is

continuously varying in loudness;

The time of day at which noise occurs, for example high noise levels at night in

residential areas are not acceptable because of sleep disturbance; and

The location of the noise source, with respect to noise sensitive land use, which

determines the loudness and period of exposure.

0

2

4

6

8

10

12

14

16

18

20

µg/

m3

Monitoring Locations

Graphical Representation of Nox & So2

Page 71: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 52

Noise survey was conducted at 6 locations in the near the project site to assess the

background noise levels in different zones viz., Residential, Industrial, Commercial and

Silence zones. The main objective of noise monitoring in the study area is to establish the

baseline noise levels and assess the impact of the total noise expected to be generated in

the surrounding areas by the proposed plant. The methodology involved in monitoring noise

is given below.

a) Identification of Sampling Locations

A preliminary reconnaissance survey was undertaken to identify the major noise generating

sources in the area. The noise monitoring has been conducted at six locations in the study

area. The environment setting of noise monitoring locations is given in below Table 3.15 and

shown in Figure 3.19.

Table ‎3.15: Noise Monitoring Locations

Location Code Location Latitude & Longitude Direction* Distance

N1 Project Site, Dobaspet N-13º12’26.90”

E-77º14’58.67” - -

N2 Hossahalli N-13º12’09.28”

E-77º16’38.00” ESE 3.04

N3 Pemmanahalli N-13º14’01.31”

E-77º16’02.98” NNE 3.41

N4 Thyamagondulu N-13º13’02.22”

E-77º18’08.98” ENE 5.76

N5 Shivaganga N-13º10’49.16”

E-77º13’47.11” SSW 3.80

N6 Dobaspet N-13º13’35.92”

E-77º14’24.42” NNW 2.34

Page 72: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 53

Figure ‎3.19: Noise Monitoring Locations

b) Instrument Used for Monitoring

Noise levels were measured using a sound level meter. The sound level meter measures the

Sound Pressure Level (SPL), the Maximum Sound Pressure Level (max) and the equivalent

continuous noise level (Leq) by switching on the corresponding function mode.

c) Method of Monitoring

Sound Pressure Level (SPL) measurements were taken at all locations, with an interval of 1

minute over a period of one hour for 24 hours. The day noise levels have been monitored

during 6 am to 10 pm and night noise levels during 10 pm to 6 am at all the locations

covered in the study area. Noise levels were recorded every one minute in the following

manner. To obtain noise levels at 8 AM, noise readings, with setting at ‘A’ response – slow

mode, were recorded continuously for 60 minutes. All the readings were obtained for 24

Page 73: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 54

hours. These readings were later tabulated and the frequency distribution table was

prepared.

Lday: Average noise levels between 6.00 hours to 22.00 hours.

Lnight Average noise levels between 22.00 hours to 6.00 hours.

d) Presentation of Results

The summary of computed ambient noise level parameters like Lday and Lnight, for all the

sampling locations are presented in Table 3.16 and compared to the standards specified by

CPCB mentioned below in Table 3.17 Graphical representation of the Noise levels is

indicated in Figure 3.20.

Table ‎3.16: Ambient Noise Levels Recorded in the Study Area dB(A)

Table ‎3.17: Ambient Noise Standards [dB (A)]

Ambient Noise Standards L day L night

Industrial Area 75 70

Commercial Area 65 55

Residential Area 55 45

Silence Zone 50 40

e) Observations

Day Time Noise Level :- Noise levels during day time were found to be in the range

47.3 – 53.8 dB (A). The maximum noise level was observed to be 53.2 dB (A) at

Location code

Sample location Lday dB(A) Lnight dB(A) Leq dB(A)

N1 Project Site, Dobaspet 51.7 43.5 50.2

N2 Hossahalli 49.2 41.6 47.8

N3 Pemmanahalli 50.6 42.7 49.1

N4 Thyamagondulu 53.8 43.9 52.2

N5 Shivaganga 47.3 41.4 46

N6 Dobaspet 53.1 42.2 51.5

Page 74: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 55

Thyamagondulu (N4) and a minimum of 51.5 dB (A) was observed at Shivaganga

(N5). The monitored locations during the Day time are under the prescribed limit.

Night Time Noise Levels: - Noise levels observed to fall in the range 41.4- 43.9 dB (A)

during the night time. Maximum noise level of 43.7 dB (A) was observed at

Thyamagondulu (N4) and a minimum of 41.6 dB (A) at Shivaganga (N5). The

monitored locations during the night time are under the prescribed limit.

Figure ‎3.20: Graphical Representation of Noise Levels

The Noise Level data in the monitored area near project site is below the prescribed limit.

3.15 WATER ENVIRONMENT

Selected water quality parameters of ground water resources within the study area have

been considered for assessing the water environment. To assess the water quality of the

study area, six ground water sampling locations were selected.

0

20

40

60

80

100

120

dB

(A

)

Sampling Locations

Graphical Representation of Noise Levels During Day and Night

L night

L day

Page 75: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 56

a) Selection of Sampling Locations

Some general criteria for selecting appropriate sampling sites will be summarized under the

following points:

Always have a reference station up-stream of all possible discharge points. The usual

purpose of a monitoring exercise is to determine the degree of man induced

pollution, and the damage that is caused. The reference station serves to assess the

situation with respect to background water quality and biological aspects,

Sampling stations should be located upstream and downstream of significant

pollution outfalls.

b) Water Sampling Locations

Water samples were collected from 6 Ground Water sampling locations. These samples

were collected as grab samples and were analyzed for various parameters. The water

sampling locations are listed below in Table 3.18 and shown in Figure 3.21.

Table ‎3.18: Water Sampling Locations

Location Code

Location Geographical Location

Direction* Distance* Type of water

W1 Project Site, Dobaspet

N-13º12’26.90” E-77º14’58.67”

- - Ground Water

W2 Hossahalli N-13º12’09.28” E-77º16’38.00”

ESE 3.04 Ground Water

W3 Pemmanahalli N-13º14’01.31” E-77º16’02.98”

NNE 3.41 Ground Water

W4 Agalakuppa N-13º13’50.18” E-77º13’48.16”

NW 3.35 Ground Water

W5 Thyamagondulu N-13º13’02.22” E-77º18’08.98”

ENE 5.76 Ground Water

W6 Veersagara N-13º13’00.85” E-77º12’10.76”

WNW 5.22 Ground Water

Page 76: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 57

Figure ‎3.21: Water Sampling Locations

c) Presentation of Results

The water sampling results water samples are given in Table 3.19 respectively. The analysis

results are compared with the standards for drinking water as per IS: 10500 – 1983

“Specification for drinking Water”.

Page 77: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 58

Table ‎3.19: Results for Ground water Analysis

Parameters Unit Limit as per Is 10500 :

1991 W1 W2 W3 W4 W5 W6

1 Colour Hazen APHA 21st EDITION 5 Nil Nil Nil Nil

2 Odour - APHA 21st EDITION Unobjectionable No Odour Observed

No Odour Observed

No Odour Observed

No Odour Observed

3 pH at 25°C - IS : 3025 Part 11- 1983 (Reaff: 2002)

6.5-8.5 8.20 6.62 6.58 7.42

4 Electrical Conductivity,

μS/cm IS : 3025 Part 14- 1984 (Reaff: 2002)

Not Specified 694 266 484 1074

5 Turbidity NTU IS : 3025 Part 10-1984 (Reaff: 2002)

1 BDL (<0.5) 1.0 BDL (<0.5) BDL (<0.5)

6 Total Dissolved Solids

mg/l IS : 3025 Part 16-1984 (Reaff: 2003)

500 363 136 268 643

7 Total Hardness as CaCO3

mg/l IS : 3025 Part 21-1983 (Reaff: 1998)

200 225 22 86 389

8 Total Alkalinity as CaCO3

mg/l IS : 3025 Part 23- 1986(Reaff:2003)

200 240 60 74 268

9 Chloride as Cl

mg/l IS : 3025 Part 32-1988 (Reaff: 2003)

250 56 30 90 99

10 Sulphate as SO4

mg/l APHA 21st EDI-4500- SO4

2- E 200 7.2 6 27 76

11 Fluoride as F mg/l APHA 21st EDI-4500- 1.0 1.32 0.82 0.66 1.9

Page 78: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 59

Parameters Unit Limit as per Is 10500 :

1991 W1 W2 W3 W4 W5 W6

F B&D

12 Nitrate as NO3

mg/l APHA 21st EDI-4500- NO3

- B 45 19 12 16 7

13 Ammonia as N

mg/l APHA 21st EDI-4500- NH3 B&C

0.5 BDL(<0.05) BDL(<0.05) BDL(<0.05) 0.22

14 Phosphate as PO4

mg/l IS : 3025 Part 31-1988 (Reaff:2002)

Not Specified 0.05 0.21 0.14 0.36

15 Sodium as Na

mg/l IS : 3025 Part 45-

1993 (Reaff:2003) Not Specified 50 23 66 123

16 Potassium as K

mg/l IS : 3025 Part 45-

1993 (Reaff:2003) Not Specified 5.1 5 8.2 4.1

17 Calcium as Ca

mg/l IS : 3025 Part 40-

1991 (Reaff:2003) 75 60 14 22 103

18 Magnesium as Mg

mg/l APHA 21st EDITION 30 18 6 7.5 32

19 Iron as Fe mg/l IS : 3025 Part 53-2003

0.3 BDL(<0.05) BDL(<0.05) 0.11 0.18

20 Chemical Oxygen Demand

mg/l IS:3025:Part-58:2006

Not Specified BDL(<4) BDL(<4) BDL(<4) BDL(<4)

Page 79: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 60

d) Observations

The analysis results of ground water samples indicate that the average pH ranges in between

6.45 -8.19, TDS of 510 mg/l was found in WNW Pemanahalli (W3), correspondingly the

hardness, alkalinity, chlorides & sulphates were also average. Iron value of 0.1mg/l, was found

in Veersagara. The groundwater at project site is comparatively good and with some treatment,

can be used for domestic purpose.

3.16 SOIL ENVIRONMENT

It is essential to determine the potential of soil in the area and identify the current impacts of

urbanization and industrialization on soil quality and also predict impacts due to the proposed

construction. Accordingly, a study of assessment of baseline soil quality was carried out.

a) Data Generation

For studying soil quality of the region, six sampling locations were selected to assess the

existing soil conditions in and around the project area representing various land use conditions.

The physical and chemical concentrations were determined. The samples were collected from

these different depths viz., 30cm, 60cm and 100cm.

The present study of the soil quality establishes the baseline characteristics and this will

help in future in identifying the incremental concentrations if any, due to the operation of the

proposed plant. The sampling locations have been identified with the following objectives:

To determine the baseline soil characteristics of the study area

To determine the impact of industrialization on soil characteristics and

To determine the impact on soils more importantly from agricultural productivity

point of view.

Six locations near the proposed Project site were

selected for soil sampling. At each location, soil samples were

collected from three different depths viz., 30cm, 60cm, and

100cm below the surface. The samples were analyzed for

physical and chemical characteristics. The samples have been

analyzed as per the established scientific methods for Physio-

Chemical parameters.

Page 80: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 61

b) Soil Sampling Locations

The details of the sampling locations selected for soil sampling are given in Table 3.20 and the

map showing the same given below in Figure 3.22.

Table ‎3.20: Soil Sampling Locations

Location Code

Location Latitude & Longitude Direction* Distance*

S1 Project Site, Dobaspet

N-13º12’26.90” E-77º14’58.67”

- -

S2 Hossahalli

N-13º12’09.28” E-77º16’38.00”

ESE 3.04

S3 Pemmanahalli

N-13º14’01.31” E-77º16’02.98”

NNE 3.41

S4 Thyamagondulu

N-13º13’02.22” E-77º18’08.98”

ENE 5.76

S5

Shivaganga N-13º16’49.16” E-77º13’47.11”

SSW 3.80

S6 Dobaspet

N-13º13’35.92” E-77º14’24.42”

NNW 2.34

*with respect to site

Figure ‎3.22: Soil Sampling Locations

Page 81: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 62

c) Presentation of Results

The results of the soil analysis are tabulated in Table 3.21and Standard soil classification

is given in Table 3.22.

Table ‎3.21: Soil Analysis Results

S.No Test Parameters S1 S2 S3 S4 S5 S6

1 pH 7.31 7.54 6.94 6.72 7.48 6.84

2 Electrical conductivity,

mS/cm 0.108 0.136 0.122 0.066 0.184 0.075

3 Available Nitrogen, mg/kg 12.2 9.6 13.7 10.7 15.2 16.4

4 Available Phosphorous,

mg/kg 39.6 45.2 29.7 41.5 52.4 37.8

5 Available Potassium, mg/kg 128 172 136 98 194 150

6 Exchangeable Calcium as

Ca,m.eq / 100g 3.05 3.76 3.94 2.78 4.12 3.36

7 Exchangeable Magnesium as

Mg, m.eq/100g 2.78 3.11 3.52 2.42 3.76 2.89

8 Exchangeable Sodium as

Na, m.eq / 100g 0.57 0.61 0.81 0.72 1.07 0.91

9 Organic matter (%) 0.22 0.18 0.31 0.26 0.14 0.25

10 Texture Classification Sandy Loam

Sandy Loam

Loam Loam Sandy Loam

Loam

11 Sand (%) 67.2 53.7 45.6 38.1 62.5 42.6

12 Clay (%) 17.8 8.6 25.6 21.8 12.4 12.8

13 Silt (%) 15 37.7 28.8 40.1 25.1 44.6

Table ‎3.22: Standard Soil Classifications

Chemical Parameters

Ranking

Very Low Low Moderate High Very High

pH <4, very Strongly Acidic

4-5, Strongly Acidic

5-8, Ideal for Plant Growth

8-9 Strongly Basic

>9 Very Strongly Basic

Electrical conductivity (μS/cm)

<2000, Non saline

2000-4000 Saline

4000-8000 Moderately Saline

8000-16000 Highly Saline

>16000 Extremely Saline

Total Nitrogen (%)

<0.05 Very Low

0.05-0.15 Low

0.15-0.25 Moderate

0.25-0.5 High

>0.5 Very High

Total Phosphorous (mg/kg)

<5 Very Low

5-10 Low 10-30 Moderate

30-60 High >60 Very High

Page 82: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 63

Sodium (mg/kg)

- <200 Non Sodic

200-500 Moderate

>500 Sodic

Potassium (mg/kg)

- <150 Low 150-250 Moderate

250-800 High

>800 Very High

Calcium (mg/kg)

- <1000 Low 1000-2000 Moderate

>2000 High -

Magnesium (mg/kg)

<40 Very Low

40-100 Low 100-300 Moderate

>300 High -

% Organic Matter

0.5-1.0 Very Low

1.0-2.0 Low 2.0-3.0 Moderate

3.0-5.0 High >5 Very High

Figure ‎3.23: Texture Classification of Soil Samples

Figure ‎3.24: Nutrient Content of Soil Samples

0

10

20

30

40

50

60

70

80

(%)

Sample Locations

Texture Classification

Sand (%)

Clay (%)

Silt (%)

0

50

100

150

200

250

(mg/

kg)

Sample Locations

Nutrient content

Nitrogen

Phosphorous

Potassium

Page 83: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 64

d) Baseline Soil Status

The Graphical representations of the Soil texture, Nutrient content are given are represented

above. It has been observed that the pH of the soil ranges from 6.72 -7.54 indicating that the

soil is ideal for plant growth. The nitrogen values are in the range of 9.6 -16.4 mg/kg and the

potassium values range between 98 -194 mg/kg, which indicate that the soils have moderate

quantities of potassium. The soil from the study area shows moderately fertility.

3.17 ECOLOGICAL ENVIRONMENT

The ecological survey has been done to establish the baseline ecological conditions of the

study area to assess the potential ecological impacts of the proposed project on ecology, to

develop adequate and feasible mitigation measures to keep ecological impacts within

acceptable limits, and to prepare comprehensive management plan.

There are no wild life sanctuaries/parks within 15 km radius of the project site. The area did

not record the presence of any critically threatened species. The records of Botanical Survey

of India and Forest Department also did not indicate presence of any high endemic or

vulnerable species in this area.

a) Methodology

Assessment of the existing vegetation types in the core and buffer zones has been done using

standard procedures. The terrain of the impact zone is chiefly plain and in some places gentle

undulations are observed.

The Biodiversity studies were already carried out in the entire study area. The study of

flora is conducted as per the guidelines of the Ministry of Environment and Forests,

Government of India (Anonymous 1994), with respect to the scope and objectives. The study

involved in collection of primary data by conducting survey in the field, examination of floral

and faunal records in previously published reports and records, and analysis of the

information in view of the possible alteration in environment of the proposed project site. For

the survey of fauna both direct and indirect observation methods were used.

b) Biological Environment

There is no threat to the Biodiversity due to the proposed project. The proposed project site is

a vacant land with some shrubs and herbs. No major trees are present at the site. Most of the

species are indigenous and naturalized. The floristic composition with the scientific names is

Muttukadu Backwaters

Page 84: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 65

tabulated in Table 3.23. There are no rare and endangered species within the study area of

the project site.

Table ‎3.23: Floristic Composition in the Study Area

Sl. No Botanical Name Local Name

1 Acacua Arabica Gobli

2 Acacia Ferruginea Kaggali

3 Acacia Leucophloea Banni

4 Acacia Concinna Seege

5 Acacia Suma Bilijali

6 Abutilon Indica Thubbergida

7 AlangumLamrkil Ankola

8 Albizzia Amara Chukkiau

9 Azadirachta Bevu

10 PartheniumHystresporus Congress Grass

11 Bambus bamboos Big Bamboo

12 Cymbopogonnardus Citronella Grass

13 Delbergialatifolia Beete

14 Emblicaofficinal;is (Phylanthusembilca) Amla, Nalli

15 MangiferaIndica Mavu

i. Fauna in the study area

Field studies are conducted to assess fauna in the study area. Within the site at many places

mud crabs was found and also at many places within the site, snakes, scorpions etc. could be

noticed. On the basis of field studies and secondary sources, there are no endangered animal

species present in the study area. List of animals present in the study area are given below in

Table 3.24.

Table ‎3.24: Fauna Present in the Study Area

Scientific Name Common Name

Aves

Corvussplendens House crow

Page 85: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 66

Pycnonotusjokokus White browed bulbul

Pycnonotuscafer Red vented bulbul

Dicrurusmacrocercus Black drongo

Gallus sonneratii Grey jungle fowl

Reptiles

Ptyasmucosus Rat Snake

Nerodiapiscator Fresh water snake

CalotesVersicolor Garden lizard

Saurialacertidae Lizard

Amphibian

Ranahexadactyla Frog

Ranatigrina Bull frog

Mammals

Funambulusspp Squirrel

Rattusnorvegicus Field mouse

Feliscatus Cat

CannisFamiliaris Dog

Rattusrattus Rat

3.16 ENVIRONMENTAL SENSITIVITY

Proposed project site falls under the survey of India Topo-sheet no. 66 D/2. As per MoEF

guideline, 10 Km radius from the project site is considered as study area for evaluating

environmental sensitivity. The description of the environmental sensitivity of the proposed

site is given below;

i. National Parks and Wild Life Sanctuaries

There is no wild life sanctuary, national park or bird sanctuary with in the 15 km radius of the

project site.

ii. Reserve Forests

There are no Reserve Forests within the 15 km radius of the proposed project site.

3.17 SOCIO- ECONOMIC PROFILE

Socio- Economic status of the population is an indicator for the development of the region.

Any developmental project of any magnitude will have a bearing on the living conditions and

Page 86: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 67

on the economic base of population in particular and the region as a whole. Similarly, the

proposed activities will have its share of socio-economic influence in the study area. The

section delineates the overall appraisal of society relevant attributes. The data collection for

evaluation of impact of proposed project on socioeconomic aspects in the study area has

been done through primary household survey and through the analysis of secondary data

available for study area.

a) Methodology

The methodology adopted in assessment of socio-economic condition is as given below;

To assess socio-Economic conditions of the Population.

Analysis of the identified social attributes like population distribution, availability

of public utilities etc., through CD of Census of India 2001 and Census 2011.

Primary household survey to assess the present status of population of the study

area.

b) Sources of Information

As per the scope of this study, the information on socio-economic aspects has been gathered

and compiled from several secondary sources. These include Taluk Office, Collectorate,

Agriculture Department, Irrigation Department, Central Ground Water Board, Directorate of

Census Operation, Karnataka etc. The demographic data has mainly been compiled from the

CD of Census of India 2001. The socio-economic details are briefly described in following

sections.

c) Social Profile

Sociological aspects include human settlement, demographic and socio-economic aspects and

infrastructure facilities available in the study area. The economic aspects include agriculture

and occupational structure of workers.

The Proposed project site for development Industrial Estates is located in an area of 844.23

Acres is spread in villages namely Yedehalli, Chandana Hosahalli, Honnenahalli, Kengal

Kempohalli, Avverahalli, K.G.Srinivaspura, Billanakote which falls in Nelamangala Taluk,

Bangalore Rural District, Karnataka. This Integrated Industrial Estates proposes to have all

basic infrastructure facilities like separate Sub-Station for power supply, separate telephone

exchange and High Speed Data Connectivity. The District comprises of 4 taluks, 98 village

panchayats and 951 villages.

Page 87: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 68

d) Settlement Pattern

The proposed project site is located at Bangalore Rural District, Karnataka. The study area is

decided as an area within 10 km radius from the proposed area. Altogether, there are 14

villages in the study area were near the study area.

The following are the villages around the site, where the socio-economic study were

carried out,

1. Yedehalli 2. Chandana Hosahalli

3. Honnenahalli 4. Kengal Kempohalli

5. Avverahalli 6. K.G. Srinivasapura

7. Billanakote 8. Pemannahalli

9. Agalakupa 10. Thyamagondulu

11. Veersagara 12. Vaddarpalya

13. Nijagal 14. Hossahalli

e) Population

The total population in the district is 1881514 (as per 2001 census), out of which rural

population constitutes 1474118 and urban population constitutes 407396. The schedule cast

population constitutes 323636 lakhs and the schedule tribe population constitutes 54333. The

sex ratio in the district is 955 females for every 1000 males. And the density of population is

323 per sq.km. The main occupation of the people in the district is cultivation and most of

them are agricultural laborers. The literacy rate is 61.9% in rural parts of which male literacy

rate is 72.4% and 51.1% is female literacy rate. And in urban parts of the district the literacy

rate is 76.2 % of which male literacy rate is 81.9% and female literacy rate is 70.10%. Socio

economic of the study area is given below in Table 3.25

Page 88: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 69

Table ‎3.25: Socio – Economic Status of the Study Area as per Census 2001

Village

No. of HH

Population SC Population ST Population Sex

Ratio Literat

es Total

Workers

Cultivators Agricultural

Laborers Workers in

HH industries

Total Male Female Male Female Male Female Male Female Male Female

Male Female

Yedehalli 130 581 279 302 88 96 1 1 924 388 225 27 2 1 1 6 1

Chandana Hosahalli 45 231 119 112 16 17 0 0 1063 123 87 22 3 0 0 0 1

Honnenahalli 265 1123 537 586 303 333 16 21 916 736 410 87 65 154 15 8 4

Kengal Kempohalli

283 1221 643 578 134 106 23 21

1124

697 639 220 72 3 3 1 1

Avverahalli 80 319 158 161 99 111 5 1 981 189 155 32 7 1 1 0 0

K.G. Srinivasapura 55 246 128 118 42 40 0 0 1085 162 126 41 1 0 0 1 1

Billanakote 333 1359 719 640 59 57 35 33 1123 943 566 165 51 92 59 4 2

Pemannahalli 179 666 353 313 77 76 11 3 1128 438 261 50 1 3 3 1 0

Agalakupa 281 1239 613 626 141 163 176 174 979 806 606 179 94 16 44 3 0

Thyamagondulu 1918 8160 4151 4009 700 657 58 56 1035 5952 3341 344 90 245 138 175 99

Veersagara 110 442 221 221 19 25 5 1 1000 282 229 117 69 4 6 5 0

Vaddarpalya 15 68 32 36 16 17 0 0 888 42 21 11 0 5 1 0 0

Nijagal 74 312 158 154 44 52 3 0 1025 195 193 51 10 7 2 2 0

Hossahalli 147 614 343 271 20 13 36 36 1266 401 226 144 5 3 0 1 0

Page 89: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 70

f) Education and Literacy Profile

Literacy is an important indicator to assess the Human Development Index of the area.

Overall literacy rate for the Honnenahalli village is 65 %. Literacy rate of Honenahalli village

is presented in Figure 3.25.

Figure ‎3.25: Literacy Rate in the Honnenahalli village

g) Economic Structure

Economic aspects of the study area include the economical structure of the people of the

surrounding area. The geographical location, natural resources, business and employment,

industries and manpower play vital role in the economic development of any region. It can

be predicted that economic structure of the study area will be improved with time, due to

the proposed Integrated Industrial Township, which will provide employment opportunities.

The population can be divided into two groups in terms of employment.

Workers and

Non-workers

Workers are further categorized into Main workers and Marginal workers. Main worker is a

person who has worked last year for six months or more. Marginal worker is a person who

has worked last year for less than six months. Non-worker is a worker who did not work at

all during the reference period of one year. The distribution of workers is given in Figure

3.26.

0

400

800

Male Female

Po

pu

lati

n in

Nu

mb

ers

Literacy rate in Honnenahalli Village

Population

Literates

Illiterates

Page 90: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 71

Figure ‎3.26: Distribution of Work force in the proposed Project Site

h) Industrial Profile

In Bangalore rural Huge scope for industrial growth and development in milk and milk

products, food processing, silk weaving industries aerospace industries for manufacturing of

aerospace components, sub- assemblies etc.

Presence of many construction and infrastructure related industries such as bricks, tiles and

stoneware manufacturing, Ragi, Paddy Maize is the major cereals grown. Banana, Grapes,

Mango, Guava are the major fruits crops in Bangalore Rural District.

Apart from Agriculture the industries, trade and commerce occupy a prominent position in

the economy of the district. Bangalore Rural District is one of the most vital and vibrant

district in terms of industrial development in the state.

Industrial Areas in 6 places and 2 Industrial Estates in the district.

0

200

400

600

800

1000

1200

1400

Po

pu

lati

n in

Nu

mb

ers

Work force Distribution

Population

Non Workers

Total Workers

Main Workers

MarginalWorkers

Page 91: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 72

Suvarna Karnataka Development Corridor proposes a Readymade Garment Zone,

Food Processing Zone and Media & Entertainment Zone covering the District.

3012 Acres of Land Bank in Nelamangala, Hoskote, Devanahalli Taluk.

Enormous scope for enhancement of productivity in agricultural and horticultural

production.

Improved seed varieties, advanced agricultural technology and mechanization are

the key areas of investment in the region.

Huge scope for contract farming with technology and knowledge transfer initiatives.

Horticulture segment in food processing is the thrust area in Bangalore Rural.

There is huge scope for spice processing industry as well as jam/jelly and juice

segment.

3.18 EXISTING STATUS OF INDUSTRIAL AREAS IN THE DISTRICT BANGALORE RURAL

Source: KIADB- Bangalore

Existing land status of industries in the Bangalore rural district is given in below Table 3.26

and 3.27.

Table 3.26: Existing land status of industries in the Bangalore rural district

Table ‎3.26: Existing land status of industries in the Bangalore rural district

S No.

Name of the Estate

Land acquired (In Hectare)

Land Developed (In Hectare)

Prevailing rate per Sqm

Numbers Formed

Numbers Allotted

Numbers Vacant

No. of units in production

Plots Sheds/flats

Plots

Sheds/flats

Plots Sheds /flat

Plots

Sheds /flats

1 Doddaballapur

20.26 20.26 2930 6 104 6 104 0 0 2 95

2 Hoskote 16.85 16.85 2580 32 69 28 65 4 4 10 42

3 TOTAL

Sl.No Area Acres

1 Bangalore Aerospace Park with Aerospace SEZ near BIAL 985

2 Basettihalli Doddaballapura IA 3rd Phase 736

Page 92: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 73

Large Scale Industries / Public Sector undertakings

Table ‎3.27: Industrial estates developed in the district

Sl No Name & Address of the unit Area of working

1 Cadbury India Pvt. Ltd.Jodihanumanapalya, Kunigal 36th KM Stone, Nelmangala Tq.

Nelamangala

2 Dakshin Foundry Pvt. Ltd., Biswanahalli Village, Nelamangala, B’lore (R) trict.

Nelamangala

3 Denso Kirloskar (I) Pvt. Ltd. 30th KM. Tumkur Road, N.H. 4,

Nelamangala

4 Karle International Unit (2)Mallarabanawadi Village, Kunigal Road, Nelamangal Tq.

Nelamangala

5 Kirloskar Electric Co., Ltd..Govenahalli, Nelamangala tq

Nelamangala

6 Kurlon Ltd. Unit- Dobespet, Nel Tq. Nelamangala

7 LM Glass Fiber India Ltd., Dabaspet Industrial area, Nelamangala Tq.

Nelamangala

8 M/ s Karle Exports Ltd, Unit(1) Kunigal Road, Nelamangala

Nelamangala

9 M/s Kemweell Bio Pharma Pvt Ltd., T.Begur, N H-4, Nelamangala.

Nelamangala

10 M/s Magod Laser Machining Pvt Ltd., Dobaspet Industrial Area Nelamangal

Nelamangala

11 M/S Powerica Ltd, Bommanahalli, Tumkur Road, Nelamangala Tq

Nelamangala

12 M/S Tata Tea Ltd, Malngattanahalli, Nel. Tq. Nelamangala

13 M/S V-3 Engineers, Deganahalli, Nelamangal Tq. Nelamangala

14 M/S Vintac Ltd, Boodihal village, Nelamangal Taluk Nelamangala

15 Metropol Overseas Ltd., Survey No. 100, Hydalu Village, Nelamangala taluk

Nelamangala

16 Payne (India) Pvt.Ltd., 2nd PH, Dobbospet Industrial Area, Nelamangala Tq.

Nelamangala

17 Pepsi Co India Holdings Ltd. 34th K.M, Stone, NH4, TEPPADA & Thonachinakuppe Village, Nel. Tq.

Nelamangala

18 Sami Labs Ltd., Phase-11,KIADB 1A, Dobbaspet, Nelamangala Tq.

Nelamangala

19 Swan Silk Ltd. Plot No.169,Bypass Road, Nelamangala

3 Doddaballapura Apparel park –I& II Phase 459

4 Dobbaspet Stage I, II and IV, Nelamangala Taluk 1225

5 Sompura Stage I and II Nelamangala 721

6 Hoskote IA 402

7 IT/BT park 67.5

Page 93: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 74

NelamangalaTq.

20 TD Power Systems Pvt.Ltd, Doaspet Industrial Area, Nelamangala TQ

Nelamangala

21 United Breweries Ltd.Gangadaranapalya, Nelamangala Tq.

Nelamangala

22 Vijaya Steels Ltd. Gangadharana Palya, Nel. Tq. Nelamangala

23 Emmvee Solar Systems Pvt Ltd. No.70/3 Dabapet Industrial Area, Nelamangala, Pemmanahalli, Bangalore Rural District.

Nelamangala

24 Kurlon Ltd. No. 22& 23, KIADB Industrial Area, Dabapet, Nelamangala, Bangalore Rural District.

Nelamangala

25 Pacific Industries Ltd. Sy.No.13 NH-48, Kempalinganahalli, Nelamangala Taluk.

Nelamangala

Source: District Industry Centre a) Major Exportable Item

Garments, Automobile parts, Electronic goods, Granites, Opthalmic lenses,

b) Growth Trend

Trend in the growth in respect of Garments, Automobile parts, Granites and lenses exist in

this district.

c) Vendorisation / Ancillarisation of the Industry:

Ancillary units in the field of Automobile parts, Garments, Engg. Products can be developed

in this district.

d) Medium Scale Enterprises

Table ‎3.28: List of the units in & Nearby Area

1 Himatsingaseide Ltd. Veerapura, KIADB Indl. Area, D.B.

PuraTq.

Doddaballapura

2 HimathSinghaka Side Wovens Ltd.

Apperalpark,Doddaballapur.

Doddaballapura

3 Volvo India Pvt. Ltd., Yelachanahalli, Thavarekere,

HosakoteTq.

Hosakote

4 United Motors & Heavy Equipment Pvt Ltd. Plot

No.12A, Industrial Area, Chokkahalli, HoskoteTaluk.

Hosakote

5 Camson Biotechnologies Ltd, Sy No.132,

Madagondanahalli Village, DoddaballapurTaluk.

Doddaballapura

6 Kurlon Ltd. No. 22& 23, KIADB Industrial Area, Dabapet,

Nelamangala, Bangalore Rural District.

Nelamangala

7 Microtex India Ltd. Plot No.33, 2nd Cross, HokoteIndl

Area, Hoskore, Bangalore Rural District.

Hosakote

Page 94: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DESCRIPTION OF THE ENVIRONMENT

Page 75

Source: District Industry Centre, Bangalore Rural Dist e) Major Exportable Item

Silk and Automobile products

f) Infrastructure Facilities

Availability of infrastructure and facilities denote the level of overall development in the

study area. The District has many Engineering colleges, Medical College, Polytechnic

Software Companies and bussieness. The District is well connected by road NH-4

(Connecting Bangalore to Mumbai) and SH-3 Kanankapura – Ramamagara- Magadi-

Pavagadi Road.

3.19 RESETTLEMENT AND RELOCATION

There are certain pockets of lands owned by few personnel in the villages adjacent to our

project site and all the lands being purchased as well as the non-acquired properties within

the project area boundaries have no residences or structures on the site and involve no R&R

- "Resettlement and Relocation. Land developed by Karnataka Industrial areas Development

Board (KIADB).

We are in the process of identifying the owners of the non-acquired lands, once the land

owners are identified land acquisition will be done or alternate arrangement by proving

equivalent area or compensation will be made to the land owners. However we have

provided access roads and connectivity to each of private land within the boundary.

Hence there will not be any social issue regarding land usage.

Page 95: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 76

4. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES

4.1 INTRODUCTION Environmental Impact can be defined as “any alteration of environmental conditions or

creation of a new set of environmental conditions, adverse or beneficial, caused or induced

by the action or set of actions under consideration”. Generally, Environmental Impacts can

be classified as primary or secondary impacts. Primary impacts are those, which are

attributed directly by the project while secondary impacts are those, which are induced by

primary impacts and include the associated investments and changed patterns of the social

and economic activities by the action.

This section identifies and assesses the potential changes in the environment that could be

expected from the proposed project. The impacts have been predicted for the proposed

activities assuming that the impact due to the existing activities has already been covered

under base line environmental monitoring and continue to remains same till the operation

of the project. The proposed project activities would create impact on the environment in

two distinct phases i.e., Construction and Operation Phases.

The major impacts that could result from the implementation of project are felt on the land,

air, water, biological, socio-economic and aesthetic environments. These impacts result

from the modification of local environmental traits, arising from submergence of land,

change in land use, loss of biodiversity and changes in hydrological features such as

alteration of flow characteristics and ground water table and displacement of people. These

impacts are intended and unintended, positive and negative, and could be assessed only

through location and project specific studies executed in a holistic manner. Assessment here

refers to analyzing and evaluating the impacts on ecosystems and socio-economic systems.

Analyzing is the objective task of identifying impacts/concerns, taking measurement of

baseline conditions and predicting the changes to baseline conditions that are likely to occur

as a result of the proposed actions.

Evaluation here is a subjective or normative task, which depends on the application of the

human values. It involves determining the significance of the effects to the affected parties.

Page 96: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 77

The impacts on Air, Water, Soil, Noise and Ecology, Socio Economic of the surrounding

environment due to the activities carried out during the construction phase and Operational

Phase is given below.

Accordingly, each impact is classified by different given categories as follows:

i. Based on the nature of impact (primary or secondary),

ii. Duration of impact (long term or short term),

iii. Type of impact (positive or negative), and

iv. Degree of impact (significant or insignificant).

4.2 ENVIRONMENTAL ASPECTS AND IMPACTS ANALYSIS

The environmental impacts caused due to the development of the project can be

categorized as primary (direct) and secondary (indirect) impacts. Primary impacts are those

which are induced directly by the project whereas the secondary impacts are those which

are indirectly induced and typically include the associated investment and changing patterns

of social and economic activities due to the proposed action. Interaction of the project

activities with environmental attributes is presented as Activity-Impact matrix in Table 4.1.

Potential direct and indirect impacts of the project during construction phase will be the

following.

Loss of vegetation due to the cutting of trees

Loss of Topsoil due to Clearing & Grubbing of new alignment, Borrow area,

Construction of Camp, Material Stacking yard

Temporary impacts in terms of polluted environment on flora and fauna due to the

construction activities

Impact on the drainage pattern due to raised embankment, introduction of new

culverts and bridge constructions

Impact on Traffic Management System

Increased air pollution (including dust) during project road construction

Increased noise level due to the movement of vehicles and construction activities

Increased soil erosion

Spillage of oils and other hazardous materials

Pollution of surface and sub-surface water sources

Page 97: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 78

Pollution due to generation of Spoils and Solid Waste

Potential direct and indirect impacts of the project during operation phase are the

following.

Increased noise pollution due to the vehicular movement

Impact on natural drainage pattern of the project area

Pollution of water bodies and impacts on its ecosystem due to hazardous chemical

or oil spillage into the canals and streams.

The positive impacts of the project will be,

Reduced air pollution due to better service levels of the road

Improved safe and efficient connectivity

Generation of local employment during road construction

Improvement of local economy and industry due to better infrastructure facilities

Table ‎4.1: Activity - Impact Identification Matrix

S.No Activities

Impacts on

Physical Environment Biological

Environment Geology Topography

Air Water Noise Flora Fauna Natural

Drainage Soil

A. Construction Phase

1 Labour Camp Activities

-ve/t

2 Material Transport & Storage

-ve/t -ve/t

4 Drilling and Blasting -ve/t -ve/t -ve/t -ve/t

5 Earthwork -ve/p -ve/t -ve/t

6 Pavement Works -ve/t -ve/t -ve/t -ve/t -ve/t -ve/p

7 Use of Construction Equipment

-ve/t -ve/t -ve/t -ve/t

8 Plantation +ve/p +ve/p +ve/p

9 Drainage Works +ve/p

11 Culvert and Bridge Construction

-ve/t -ve/t -ve/p

12 Stripping of Topsoil -ve/t

Page 98: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 79

13 Debris Generation -ve/t -ve/t

14 Oil & Grease -ve/t

15 Construction in Rivers, Canal

-ve/t -ve/t -ve/t -ve/t -ve/t -ve/p -ve/p -ve/p

B. Operational Phase

1 Vehicular

Movement

-ve/p -ve/p -ve/p ve/p

Note: t - Temporary; p - Permanent. Impacts indicated in bold letters are Significant Impacts. The impacts caused due to proposed project activity are discussed in the following sections.

4.3 IMPACTS DURING CONSTRUCTION PHASE

The impacts on Air, Noise, Water, Soil, and Ecology of the surrounding environment due to

the activities carried out during the construction phase are discussed below.

i. Loss of Vegetation And Wildlife Habitat

During Construction there will be essentially entail the removal and loss of some, if not

most, of the existing trees and underlying grassland at the project site, and the permanent

erection of block and steel concrete structures associated with site new infrastructure. This

would constitute a loss of alternative land use, an irreversible commitment of land

resources, and thus a direct long-term impact.

The site was not extensively or heavily vegetated prior to construction and did not support

any significant ecological habitats or fauna. Therefore, the impacts from erecting the new

buildings are considered to be not significant in terms of habitat loss. Impact mitigation is

not required during the construction phase.

Landscaping of the site, after building completion, will see the introduction of plants and

trees that should offset any negative impacts associated with the removal and loss of

existing trees at the project site. The numbers and types of vegetation to be introduced

during the landscaping exercise are expected to be greater and more diverse than presently

obtains and these are expected to play a greater role in terms adding ecological value and

attracting birds and other terrestrial fauna during the operational phase of the project,

apart from being more pleasing aesthetically.

Page 99: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 80

ii. Modification of Drainage Pattern

The overall topography of the project site will be radically changed by the erection of

buildings and this will bring moderately significant change in the existing pattern of surface

drainage. Mainly, the impact will arise from the creation of impermeable surfaces (roofs,

pavements, etc.) and the corresponding reduction in the amount percolation in the soil and

capacity of the site to absorb rainfall.

iii. Erosion of Cleared Areas

Vegetation clearance and excavation works related to construction will expose soils in the

affected areas which could leave them vulnerable to erosion by surface run-off and create

the threat of water turbidity and sediment deposition in drains &nearby rivers. The

topography of the site and the pervious nature of the soils will cause erosive surface flows

during the construction works before landscaping and drainage works reduce the

susceptibility to soil erosion. Significant surface features such as gullies, streams or rivers in

close proximity to the site that could be affected by soil erosion.

iv. Materials Transportation

The various materials required for construction and building (e.g. Steel, Blocks, Lumber,

Marl, Asphalt, etc.) will be obtained from sources elsewhere and transported to the site.

Transportation of these materials, typically in over-laden and sometimes uncovered trucks,

usually results in undue road wear-and-tear. In the case of fine earth materials, dusting and

spillages occur on the roadways between source and site. Dusting degrades local air quality

and material spillages worsen road driving conditions and increase the risk of road

accidents. These occurrences represent indirect, short-term, reversible, negative impacts on

public health and safety related to the project.

v. Ambient Air Quality

During the construction phase the ambient air quality in and around the proposed project

site will have marginal adverse impacts due to the various activities which are part of

construction phase.

The various activities includes during construction phase such as site preparation, approach

roads, excavation, drilling, , foundation, tunneling, deployment of machinery, erection,

transportation, dumping will cause dust and gaseous emissions. The pollutant released

during the construction activities may cause immediate effect on the construction workers,

Page 100: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 81

directly exposed to them. Emission factors for various construction equipment’s are given in

Table 4.2.

Table ‎4.2: Emission Factors for Various Construction Equipment’s

Type of Construction Equipment

VOC

(g/hp- Hr)

CO

(g/hp- Hr)

Nox

(g/hp- Hr)

PM10

(g/hp- Hr)

PM 2.5 (g/hp-

Hr)

SO2

(g/hp- Hr)

CO2

(g/hp- Hr)

Water Truck 0.440 2.070 50490 0.410 0.400 0.740 536.000

Diesel Road Compactors 0.370 1.480 4.900 0.340 0.330 0.740 536.200

Diesel Dump Truck 0.440 2.070 5.490 0.410 0.400 0.740 536.000

Diesel Excavator 0.340 1.300 4.600 0.320 0.310 0.740 536.300

Diesel Trenchers 0.510 2.440 5.810 0.460 0.440 0.740 535.800

Diesel Bore/Drill Rigs 0.600 2.290 7.150 0.500 0.490 0.730 529.700

Diesel Cement & Mortar Mixers

0.610 2.320 7.280 0.480 0.470 0.730 529.700

Diesel Cranes 0.440 1.300 5.720 0.340 0.330 0.730 530.200

Diesel Graders 0.350 1.360 4.730 0.330 0.320 0.740 536.300

Diesel Tractors/ Loaders/Backhoes

1.850 8.210 7.220 1.370 1.330 0.950 691.100

Diesel Bull Dozers 0.360 1.380 4.760 0.330 0.320 0.740 536.300

Diesel Front End Loaders 0.380 1.550 5.000 0.350 0.340 0.740 536.200

Diesel Fork Lifts 1.980 75760 8.560 1.390 1.350 0.950 690.800

Diesel Generator Set 1.210 3.760 5.970 0.730 0.710 0.810 587.300

Source: USEPA 2005 Emission Facts

Temporary increase in air pollution will result from the use of construction equipment,

portable lights, and fugitive dust. Due to the short duration of the Planned Action, any

impacts on ambient air quality during construction activities are expected to be short term.

Air pollutants released from vehicles are given in Table 4.3 and the Construction Fugitive

Dust Emission Factors in given in Table 4.4.

Page 101: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 82

Table ‎4.3: Pollutants Released From Light Duty Trucks

Pollutants

Emission Factors Assumptions Pollutant concentration

Cars (g/mile)

Trucks (g/mile)

Mile/day Day/yr No. of Cars

No. of Trucks

Emissions from Cars (tns/yr)

Emissions from

Trucks (tns/yr)

Total (tns/yr

)

VOCs 1.36 1.61 40 120 3 20 0.034 0.26 0.294

CO 12.4 15.7 40 120 3 20 0.31 2.49 2.8

NOx 0.95 1.22 40 120 3 20 0.023 0.19 0.42

PM- 10 0.0052 0.0065 40 120 3 20 0.00 0.00 0.00

PM-2.5 0.0049 0.006 40 120 3 20 0.00 0.00 0.00

Source: USEPA 2005 Emission Facts

Table ‎4.4: Construction Fugitive Dust Emission Factors

Components Emission factor Unit Source

Construction Activities 0.19 ton PM 10 /acre- month MRI 1996; EPA 2001; EPA 2006

New Road Construction 0.42 ton PM 10 /acre- month MRI 1996; EPA 2001; EPA 2006

PM 2.5 emissions 0.10 (10% of PM10 emissions assumed to be PM2.5)

EPA 2001; EPA 2006

Control Efficiency 0.50 (assume 50% control efficiency for PM10 and PM2.5 emissions)

EPA 2001; EPA 2006

Source:

EPA 2001. Procedures Document for National Emissions Inventory, Criteria Air

Pollutants, 1985-1999. EPA-454/R-01-006.

EPA 2006. Documentation for the Final 2002 Nonpoint Sector (Feb 06 version)

National Emission Inventory for Criteria and Hazardous Air Pollutants.

MRI 1996. Improvement of Specific Emission Factors (BACM Project No. 1). Midwest

Research Institute (MRI)

vi. Materials Storage

The improper sitting and storage of sand, gravel, cement, etc., at the project site could lead

to fine materials being washed away into the adjacent environment during heavy rainfall

events. This would not only represent a waste of materials but would also contribute to

turbidity and sedimentation with negative impacts on water quality and the ecology of

Page 102: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 83

shallow marine environments. Hazardous and flammable materials (e.g. paints, thinner,

solvents, lubricants, fuels, etc.), improperly stored and handled onsite, are potential health

hazards for construction workers. Improper storage and handling of fuel and oil would

inevitably result in spillage during equipment refueling and maintenance exercises. Spilt

petrochemicals would have the potential to contaminate soil and inhibit plant growth on

the site.

vii. Noise Environment

Foundation work will involve land excavation, affecting environment by noise. Structural

work, deployment of machinery, approach of road construction and erection of roads will

result in noise and vehicular traffic. Material handling and transportation would also lead to

significant noise pollution. Continuous Exposure of workers to high sound levels may result

in annoyance, fatigue. Albeit annoying, this negative impact will be short-term (limited to

the duration of the road construction works) and is not considered to be a significant threat

to the health or wellbeing of humans. Distance will help to ameliorate noises. The

construction Equipment Noise Emission Levels is given below in Table 4.5

Table ‎4.5: Construction Equipment Noise Emission Levels

Equipment’s Typical Noise Level (DBa )

50 ft from Source

Air Compressor 81

Concrete Mixer 85

Concrete pump 82

Concrete Vibrator 76

Crane,Derrick 88

Crane,Mobile 83

Generator 81

Grader 85

Jack hammer 88

Loader 85

Pump 76

Rail saw 90

Rock drill 98

Page 103: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 84

Roller 74

Saw 76

Scraper 89

Shovel 82

Tie cutter 84

Tie handler 80

Tie inserter 85v

Truck 88d

A construction noise assessment for a major project is performed by comparing the

predicated noise levels with criteria established for the type of project. The approach

requires a descriptor, a standardized prediction method and set recognized criteria for

assessing impact. The descriptor used for construction noise as the Leq. This unit

appropriate for the following reasons.

It can used to describe noise level from operation of each piece of equipment

separately and is easy to combine to represent the noise level from all equipment

operating during a given period.

It can be used to describe the average the noise level during entire phase.

It can used to describe the average noise over all phases of the construction.

viii. Water Environment

Construction phase requires large quantities of water to be used in various processing such

as material preparation in equipment’s. Change in quality of water forms an important

concern associated the project particularly during the construction phase. Earth works,

crushing of stones, cutting and modification of the terrain, alteration of drainage systems

and soil erosion are the major factors that affect the water quality during construction

phase.

During rainy season, the runoff water joining the water sources from nearby areas of the

development sites will add more such debris and soil particles to enhance the level of

suspended solids in the water bodies. This will adversely affect the fishes and other aquatic

life forms apart from the human beings who are dependent on the surface water for their

daily use.

Page 104: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 85

Following are the most susceptible locations for contamination of water during

construction:

Waterlogged areas have water in them during the period of construction. Land fill

material may increase the turbidity of this water logged body and thereby may invite

vector of disease.

Surface and ground water resources close to construction material storage yard,

concrete mixer plants and maintenance sites of construction vehicles; and

Leakage of lubricant or spill may cause water pollution of surface and ground water

body.

Impact due to accidental spills or due to bad construction practice, will be short term

and low in magnitude and confined to the construction period only.

ix. Biological Environment

Dust emissions from the construction activity will affect the plant and animal respiration

activity. Construction activities change the natural environment. But it also creates a built

environment for the surrounding. Emissions such as PM10, PM2.5 NOx, SOx from D.G sets

and other vehicles may also cause respiration problem for the surrounding organisms. The

extent of the pollution will be about 2km form the project area.

x. Construction Waste Disposal

Solid waste generated during site preparation and construction work would include cut

vegetation and typical construction waste (e.g. wasted concrete, steel, wooden scaffolding

and forms, bags, waste earth materials, etc.). This waste would negatively impact the site

and surrounding environment if not properly managed and disposed of at an approved

dumpsite. Cleared vegetation burned onsite would generate smoke, possibly impacting

negatively on ambient air quality and human health. Vegetation and solid waste, if allowed

to accumulate in drainage ways, could cause localized pooling and flooding. Pooling of

water, in turn, would create conditions conducive to the breeding of nuisance and health-

threatening pests such as mosquitoes and rats. Poor construction waste management

constitutes a short-term, possibly long-term, negative impact.

xi. Socio Economic Environment

a) Positive Impacts

Income to the Equipment and Material suppliers

Page 105: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 86

This project will promote the procurement of equipment’s and machineries

for the various activities involved during the construction phase where it is

technically and commercially feasible.

Procurement of material suppliers for various activities involved in the

construction phase which will also promote the growth of the economy of

the local material suppliers in and around the proposed Project site.

Employment Opportunities

Proposed project will create employment opportunities to the local people

present around the Project Site.

At this stage it is not possible to accurately determine the number of workers

that will be employed on the site during the construction phase but it is

estimated that this number would be between 1800-2000 persons

throughout the construction phase. These levels of short-term employment

opportunities would have a positive impact on the local economy and on

regional unemployment.

b) Negative Impacts

OHS Risks to Construction Workers

During construction phase of the proposed project the employers are subject

to Health and Safety Risks.

To eradicate the Health and Safety risks to the employers Personal

Protective Equipment’s will be Provided

Ensuring good housekeeping and cleaning operations

Sanitation Facilities

Proper On Site Sanitation facilities will be provided for the employers

The wastewater generated during construction phase will be treated in the

Proposed Septic Tank and Soak Pit.

4.4 IMPACTS DURING OPERATION PHASE

The impacts on Ambient Air, Groundwater, Soil, Noise and Ecology of the surrounding

environment during the Operation phase are discussed below

i. Ambient Air Quality

The potential impact on air quality would mainly be from

Page 106: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 87

Combustion of fuel in standby Diesel Generators

The operation of diesel generators would be only during the power interruption

from supply from TNEB, when emissions due to combustion of fuel (High Speed

Diesel) will take place. The anticipated key air emissions from the project would be

particulate matter, oxides of nitrogen (NOX), Sulphur dioxide (SO2) and Carbon

monoxide (CO).

Vehicles plying for transportation of raw and finished materials(concrete, blocks etc,)

Emission of PM10, PM2.5, NOx, SOx from D.G set and Vehicular traffic and also dust

emission from vehicular movement may pollute the ambient air quality which in turn

cause breathing problem to the patients and student and employees.

ii. Noise Environment

Noise pollution is caused due to the various activities which involves the vehicular

movement, D.G sets etc.

iii. Water Environment

During the water will be purchased so there will not be any abstraction of ground water in

the project site. Disposal of domestic wastewater generated may also affect the quality.

Impacts due to Liquid waste from the proposed industries will also affect the water quality.

iv. Land Environment

Dumping of municipal solid waste & industrial waste on the land will affect the soil quality.

Poor garbage management would lead to unsanitary conditions including vermin and fly

infestation and odors as well as unsightly conditions. Although the means of solid waste

collection and disposal have not been determined, it is expected that garbage management

and good housekeeping will be practiced and that problems arising from the improper

storage of solid waste will therefore be avoided. Spillage of waste oil from the D.G set may

also have an impact on soil quality.

v. Biological Environment

The impact on terrestrial ecology will be due to emission of gaseous pollutants like NOX,

SO2 and hydrocarbons. The gaseous pollutants at a very low dose act as atmospheric

fertilizer for the vegetation. However, at higher doses, they are injurious to vegetation.

vi. Socio Economic Environment

The proposed project would provide employment opportunities and improved working

conditions for the workers employed at the facility both during construction and operation

Page 107: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 88

phase. The project will increase the economic activities around the area. The proposed

project would enhance the existing infrastructure in the area by providing a cleaner and

greener environment.

Impacts on Socio Economic Environment

During the operation stage of the project the healthcare workers may come

in contact with the infected and contaminated instruments and needles.

Community Health Risk to Improper waste management

4.5 ENVIRONMENTAL MITIGATION AND ENHANCEMENT MEASURESDURING

CONSTUCTION PHASE

i. Introduction

Mitigation is the implementation of measures designed to reduce the undesirable effects of

a proposed project on the environment. As companies and individuals we all have an

important role to play in protecting the environment, which is very sensitive to change and

once damaged can take a long time to recover.

For mitigation to be effective the following factors should be taken care of

The measure proposed must be achievable within time, resources and capabilities

The mitigation measures must correspond to impacts

Funding must be adequate over the life of the activity

Preventive mitigation is usually cheapest and most effective. It must be done at

design stage.

Mitigation measures can be categorized with respect to construction and operation phase.

For the mitigation of environmental impacts various environmental infrastructures have

been proposed and are given in following sections.

The mitigation measures on Air, Noise, Water, Soil, and Ecology of the surrounding

environment due to the activities carried out during the construction phase are discussed

below

ii. Mitigation for Loss of Vegetation and Wildlife Habitat

Landscaping of the site, after building completion, will see the introduction of plants and

trees that should offset any negative impacts associated with the removal and loss of

existing trees at the project site. The numbers and types of vegetation to be introduced

during the landscaping exercise are expected to be greater and more diverse than presently

Page 108: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 89

obtains and these are expected to play a greater role in terms adding ecological value and

attracting birds and other terrestrial fauna during the operational phase of the project,

apart from being more pleasing aesthetically.

iii. Mitigation for Modification of Drainage Pattern

Rainwater harvesting prevents the flooding of low-lying areas in the project

premises, Rain Water Harvesting System as described below sections

A basic surface drainage system can be provided for the site to avoid water runoff on

to the surrounding properties and roads, especially during the monsoon months.

If during excavation, water accumulates in the excavated areas, then it should be

pumped out and disposed off either in the municipal storm water drain or into

recharge soak pits of dry bore wells.

iv. Mitigation for Erosion of Cleared Areas

Non-structural measures mainly control the “vulnerability” component of flood risk, they

include:

Spatial planning policy with a presumption against development or

encroachment of economic activities onto flood plains.

Re-cover exposed soils with grass and other appropriate species as soon as

possible.

Temporarily bund exposed soil and redirect flows from heavy runoff areas that

threaten to erode or result in substantial surface runoff to adjacent marine

waters

Monitor areas of exposed soil during periods of heavy rainfall throughout the

construction phase of the project

Building regulations to control the additional runoff from any development in the

catchment outside the flood plain

Regulations to control increases in vulnerability to flooding and of flood plain use

Provision of effective warning systems with emergency response plans

Public education in flood risk and encouragement of personal measures to

reduce flood losses For control of flooding in urban areas, land use planning and implementation of adequate

capacity drainage network is essential. Drainage improvement shall be integrated into the

master plan for water management in the urban areas.

Page 109: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 90

v. Mitigation for Materials Transportation

All fine earth materials must be covered during transportation to the site to

prevent spillage and dusting. Trucks used for that purpose on the project should be

fitted with tailgates that close properly and with tarpaulins to cover the materials.

The cleanup of spilled earth and construction material on the main roads should be

the responsibility of the contractor and should be done in a timely manner (say

within 4 hours) so as not to inconvenience or endanger other road users. These

requirements should be included as clauses within contracts made with relevant

sub-contractors.

The transportation of lubricants and fuel to the site should only be done in the

appropriate vehicles and containers, i.e. fuel tankers and sealed drums.

As far as possible, transport of construction materials should be scheduled for off-

peak traffic hours. This will reduce the risk of traffic congestion and of road

accidents on the access roads to the site.

vi. Mitigation for Ambient Air Quality

a. Mitigation measures for Air Pollution

Site clearance, excavation and earthmoving

The working area for the uprooting of shrubs or vegetation or for the removal of

boulders or temporary or permanent structures shall be sprayed with water or a

dust suppression chemical immediately before, during and immediately after the

operation so as to maintain the entire surface wet.

Access road

Every main haul road shall be paved with concrete, bituminous materials,

hardcore or metal plates, and kept clear of dusty materials; or sprayed with

water or a dust suppression chemical so as to maintain the entire road surface

wet.

Construction equipment’s

All machineries to be used for construction purpose will be of highest standard

of reputed make and compliance of noise pollution control norms by these

equipment’s will be emphasized by company.

Acoustic laggings and silencers will be used in equipment’s wherever possible.

Page 110: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 91

Feasibility of putting up acoustic enclosure / temporary barrier around areas

with high noise levels will also be explored.

Transport vehicles and construction equipment’s / machineries will be properly

maintained to reduce air emissions.

Equipment’s will be periodically checked for pollutant emissions against

stipulated norms.

Exhaust vent of DG set will be kept at proper height to ensure quick dispersal of

gaseous emissions.

Use of vehicle

Immediately before leaving a construction site, every vehicle shall be washed

to remove any dusty materials from its body and wheels.

Where a vehicle leaving a construction site is carrying a load of dusty materials,

the load shall be covered entirely by clean impervious sheeting to ensure that

the dusty materials do not leak from the vehicle.

Excavation and earth moving

The working area of any excavation or earth moving operation should be

sprayed with water or a dusty suppression chemical immediately before,

during and immediately after the operation so as to maintain the entire surface

wet.

Stock Piles

All loose material either stocked or transported shall be provided with suitable

covering such as tarpaulin, etc.

Water sprinkling shall be done at the location where dust generation is

anticipated.

Over Burden (OB) waste dumps shall be sprayed with water as they are major

sources of air borne particulate matter/dust.

OB waste dumps shall be reclaimed / afforested to bind the loose soil and to

prevent soil erosion.

DG Set

D.G. set should be placed in an acoustic enclosure.

D.G. set should be placed on the wooden platform to minimize the vibration.

Page 111: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 92

The green belt development will also help in reducing noise levels in the

campus.

The Central Pollution Control Board (CPCB) has issued emission limits for

generators upto 800 KW. The same are outlined in Table 4.6, and are

recommended to be followed.

Table ‎4.6: Emission Limits for DG Sets Prescribed By CPCB

Parameter Emission limits (gm/kwhr)

NOx 9.2

HC 1.3

CO 2.5

PM 0.3

Smoke limit* 0.7

Note: * Light absorption coefficient at full load (m-1).

Location of DG sets and other emission generating equipment should be

decided keeping in view the predominant wind direction so that emissions do

not effect nearby residential areas.

Stack height of DG sets to be kept in accordance with CPCB norms, which

prescribes the minimum height of stack to be provided with each generator set

to be calculated using the following formula:

H =h +0.2×ÖKVA

H = Total height of stack in meter

h = Height of the building in metres where the generator set is installed

KVA = Total generator capacity of the set in KVA

vii. Mitigation for Materials Storage

The stockpiling of construction materials should be properly managed and

controlled. Fine grained materials (sand, marl, etc.) should be stockpiled away

from surface drainage channels and features.

Low beams should be placed around the piles and/or tarpaulin used to cover

open piles of stored materials to prevent them from being washed away during

rainfall.

Page 112: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 93

Safe storage areas should be identified and retaining structures constructed prior

to the arrival of material.

Hazardous chemicals (e.g. fuels) should be properly stored in appropriate

containers and these should be safely locked away. Conspicuous warning signs

(e.g. ‘No Smoking’) should also be posted around hazardous waste storage and

handling facilities.

Refueling and maintenance of heavy construction vehicles at the site, should be

done at specified areas or makeshift "depots" where measures are in place to

deal with spillages and temporary storage of oily wastes. Preferably these depots

should be located in an area that would ultimately be permanently paved (e.g.

parking lots) thereby covering contaminated soil if any. The ground at the depot

site should be covered with a thick layer of marl to absorb any spillages.

Subsequently, this marl layer should be removed for proper disposal. In the

event of a large spill, the latter must be cleaned up immediately by excavating

the contaminated soil and removing it in a secure vehicle to an approved

disposal site.

In order to reduce ground contamination, an impervious sump or container

should also be placed under the spigots of fuel drums to collect drippings.

viii. Mitigation for Noise Environment

Construction activities that will generate disturbing sounds should be restricted

to normal working hours.

Workers operating equipment that generates noise should be equipped with

noise protection gear. Workers operating equipment generating noise levels

greater than 70

dBA continuously for 8 hours or more should use earmuffs. Workers

experiencing prolonged noise levels of 70 – 80 dBA should wear earplugs.

The construction activities will be restricted to the daytime and no construction

will be practiced during night.

Barricades will be provided around the construction site to confine noise within

the site.

Page 113: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 94

To reduce the impact of air and noise pollution and to provide a clean, healthy environment,

it has been proposed to create and maintain a green belt within the building complex and

along the roadsides.

ix. Mitigation for Water Environment

Excavation can be avoided during monsoon season

Check dams shall be provided to prevent construction runoff from the site to the

surrounding water bodies.

Pit latrines and community toilets with temporary soak pits and septic tanks shall

be constructed on the site during construction phase to prevent wastewater

from entering the ground water or surrounding water bodies.

To prevent surface and ground water contamination by oil/grease, leak proof

containers shall be used for storage and transportation of oil/grease.

Controlled withdrawal of groundwater during construction.

x. Mitigation for Biological Environment

The dust emissions will be suppressed by spraying water and then the activities

will be carried out.

Emissions from D.G sets and vehicles will be minimized by proper maintenance

and by avoiding use of adulterant fuels and will be maintained below the

standard limits prescribed by competent authority.

Important species of trees will be identified and marked and will be merged with

landscape plan.

xi. Construction Waste Disposal

A site waste management plan should be prepared by the contractor prior to

commencement of building. This should include the designation of appropriate

waste storage areas, collection and removal schedule, identification of approved

disposal site, and a system for supervision and monitoring. Preparation and

implementation of the plan must be made the responsibility of the building

contractor with the system being monitored independently.

Special attention should be given to minimizing and reducing the quantities of

solid waste produced during site preparation and construction. To reduce

organic waste, softer vegetation may be composted onsite and used for soil

amendment during landscaping.

Page 114: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 95

Most of the construction materials like soil, bricks, concrete will be reused in the

backfilling, road construction, sub-grade reparation etc. works. Metals, word

scraps & bitumen junks will be recycled either within site or outside with help of

the local authority. The measures like reusing materials on-site and /or donating

/selling salvaged items reduces waste, virgin material use and disposal cost.

Vegetation and combustible waste must not be burned on the site.

Reusable inorganic waste (e.g. excavated sand) should be stockpiled away from

drainage features and used for in filling where necessary.

Unusable construction waste, such as damaged pipes, formwork and other

construction material, must be disposed of at an approved dumpsite.

xii. Mitigation for Land Environment

The soil will be collected separately and preserved in stacks with side slopes not

exceeding 1:5. The topsoil (soil on the top 15 cm patch) will be preserved

separately in a stack covered by tarpaulin. Efforts will be made to reinstate the

soil for backfilling purposes. Topsoil will be reused for horticultural areas.

The spillage of oil from the machinery or cement residue from concrete mixer

plants might contaminate the soil if not properly collected and disposed off. Thus

most stringent safety and construction management norm will be implemented

at site.

xiii. Health & safety measures during construction phase

Construction related activities will be confined only to project site area, hence no

health related impact are envisaged within the project influenced area during

the construction stage and will be limited to occupant levels.

At the project site much direct exposure to dust generation and high noise

generation sources likely to cause occupant health related impact such as

asthma, bronchitis and noise induced hearing loss (NIHL) etc. on the construction

workers. In order to offset such effects, proper drinking water, sanitation and

first aid facility will be provided at the construction site, with trained shift

supervisors, which will ensure minimum adverse occupational health impacts on

the construction worker.

Page 115: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 96

4.6 ENVIRONMENTAL MITIGATION AND ENHANCEMENT MEASURES DURING OPERATION

PHASE

The mitigation measures for Ambient Air, Groundwater, Soil, Noise and Ecology of the

surrounding environment during the Operation phase are discussed below

ii. Ambient Air Quality

Use of low sulphur diesel will minimize the emissions from D.G set

Use of Clean fuel and proper maintenance of the vehicles will also minimize the

SPM, NOx, SOx from the exhaust of the vehicles.

Development of Green belt with specific species will help in reduce the PM levels

to be carried out.

Informatory sign shall be provided to encourage vehicle owners to maintain their

vehicle and follow the emission standards fixed by Government Authorities.

Location of DG sets and other emission generating equipment should be decided

keeping in view the predominant wind direction so that emissions do not effect

nearby residential areas.

iii. Noise Environment

Proper maintenance of the vehicles and record keeping on the same will reduce

the noise levels.

The noise produced by the D.G sets can be minimized by providing proper

acoustic enclosures and isolating the D.G set will ensure minimum noise at the

receiver’s end.

iv. Water Environment

Efficient Rainwater Management Plan will be adopted to reduce the impact due to surface

runoff

a) Rain Water Harvesting System

A rainwater harvesting system comprises components of various stages - transporting

rainwater through pipes or drains, filtration, and tanks for ground water recharge. As the

proposed facility will comprise only the roof top rain water for ground water recharge. The

runoff from the first spell of rain carries a relatively larger amount of pollutants from the air

and catchments surface so the system will be provided with a filtration pit consists of the

Page 116: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 97

layers of sand, gravel and pebbles of relevant sizes to remove the removable impurities

from the runoff water from the roof top.

Rainwater harvesting besides helping to meet the ever increasing demand for water, helps

to reduce the runoff which is choking storm drains, avoid flooding of roads, augment the

ground water storage and to control decline of water level, reduce groundwater pollution,

improve quality of groundwater and reduce soil erosion. Rainwater harvesting is viewed as a

water security measure with two broad types of program as given below,

Roof water harvesting and is rather a temporary measure, focusing on human needs

providing immediate relief from water scarcity. The capacity of the storage tank determines

the cost of the system and reliability of the system for assured water supply. A Demand-

supply analysis is required while designing water collection tanks. The factors such as

amount and frequency of rainfall, runoff coefficient of the collecting surface, number of

users, daily requirements and dearth period are important for calculating the size and

capacity of the storage tank. The method of calculation is depicted in Table. 4.7.

Page 117: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 98

Figure 4.1: Two Broad Areas of Rainwater Harvesting

Table ‎4.7: Calculation of the Size of the Collection Space and Storage Tank

Month

Rainfall in

mm

Water collected

from surface

area in litres

(multiplied by

runoff coefficient

of the surface)

Cumulative

water

collected in

litres

Monthly

demand

in litres

Cumulative

Demand in

Litres

Difference

between

cumulative

supply

and demand

Calendar

Months

Rainfall

data from

approved

sources

Water collected

during the month

from the

available

Water

collected

prior to the

current

Assuming

number

of members as 4

or 5 and per

Water

demand for

the current

month is

The value of

column four is

subtracted

from that of

Page 118: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 99

collection space

(runoff

coefficient is

0.75- 0.95 for

roof surfaces and

0.05 -0.35 for

various land

surfaces)

month is

added to the

previous

month

capita daily use

of 15 litres in the

case of

drinking and 40/

50 litres for

general domestic

purposes or

Irrigation

requirement of

the crops

added to the

previous

months

column six.

The greatest

resultant value

is considered

to be the size

of the storage

tank.

b) Ground Water Recharge

Excess Roof top rainwater can be diverted to the existing open / bore well after filtration.

Along with this, rainwater available in the open spaces around the building may be

recharged into the ground through the simple effective methods such as Percolation pits or

Recharge Trench. Generally these pits are filled with pebbles or brick pieces to avoid water

stagnation.

c) Need for Rainwater Harvesting

Rainwater harvesting and re-charging in to ground water provides increase of ground water

table. Rainwater harvesting prevents the flooding of low-lying areas in the factory premises,

Salinity if ground water is reduced.

d) Recharge structures

Rainwater may be charged into the groundwater aquifers through any suitable structures

like recharge pits. Area the size of the Percolation pit and Recharge trench will be provided

for the proposed.

v. Meteorological Data- Rainfall Details

Statistics indicate that the district receives rainfall under the influence of the South-west

monsoon period extending from June to September and North-east monsoon period

monsoon extending from October to December. The Northeast monsoon mainly contributes

to the rainfall in the area. The Southwest Monsoon rainfall is erratic.

Page 119: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 100

a) Rainfall Intensity

Rainfall intensity selected is for storm of duration equal to time of concentration (as per IRC-

SP 50) of site

i. Time of Concentration

Time of concentration is estimated as 0.5 hours, empirically based on distance of

furthest point from outlet of the site and average slope of this path (as per Kirpich

formula). For smaller duration storms, the contributing catchment area will reduce.

ii. Duration of storm

The selection of duration of storm for selection of rainfall intensity is 0.5 hours.

iii. Rainfall intensity

Using monthly rainfall data from 2008 to 2012. Estimated rainfall intensities 86 mm/hr.

b) Storm Water Runoff Estimate

Hydraulic design - This includes determination of storage capacity and storage

dimension (length, width and height) of the pond and dimensions of spillway for safe

disposal of excess inflow to the pond.

Design of Drain Section: Capacity of the drain is designed using Manning’s formula:

Q = 1/n*A*R2/3*S1/2

V = 1/n*R2/3*S1/2P

Q = Discharge in m3/sec

V = Mean velocity in m/sec

N = Manning’s rugosity coefficient

R = Hydraulic mean radius which is ratio of area flow to the wetted perimeter.

S= Gradient of drain bed

A=Area of flow cross section in m2

The maximum storm water runoff volume is obtained from entire site for selected peak

storm. The various co-efficient of runoff referred, is as shown in Table 4.8. Detention

storage required to absorb excess runoff volume in hours will be estimated for various

rainfall intensities.

Page 120: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 101

Table ‎4.8: Values of run-off coefficient

S No. Description of Surface Run-off coefficient, C

1 Roof Area 0.85

2 Road and Parking 0.75

3 15 m Buffer 0.15

4 Green Belt area 0.15

5 others 0.15

Table ‎4.9: RWH Computation

S.No Description Area in Sq.m Runoff Co-efficient

Avg rainfall per Annum(m)

Rain water quantity (cum/Annum)

1. Roof Area 8,65,404 0.85 0.86 6,32,610

2. Road and paved area

4,59,601.5 0.75 0.86 2,96,442.97

3. Buffer 3,39,774.1 0.15 0.86 43,830.9

4. Parks & Green area

6,56,683.4 0.15 0.86 84,712.2

5. others 10,95,338.8 0.15 0.86 1,412, 98.7

Total 34,16,478 11,98,894.77

c) Present Drainage

The proposed expansion activity includes the rain water harvesting system through RWH

structures like percolation pits and recharge trench for recharging the aquifers.

d) Percolation Pits

• Percolation pits at every 100 m intervals

• The top covered with perforated R.C.C. slab.

• The rain water collected in the terrace will be collected through a 150 mm PVC pipe

laid on the ground and may be allowed to fall in the pits.

• A network of storm water drains will be proposed all along the direction along the

main roads and cross roads

• Size would be 0.6 X 0.6 m box and depth of 0.8 m).

• Runoff from roads and paved / landscaped areas will be directed to storm water

drains.

• Water collected through drains is finally discharged into rain water harvesting drains.

Page 121: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 102

• Rain water harvesting pond will be provided (Capacity – 4000 m3)

Figure ‎4.2: Rain Water Harvesting Pit

e) Future Drainage

The whole storm management system for the study is divided into two components:

f) Inside drain management

Surface runoff from the site is collected by the road side drains which will be drained into

the central lakes and the channel. Excess runoff can be harvested in the two harvesting

sources identified. On top of it, there are number of existing wells which can be used for

Ground water recharging.

g) Peripheral Drain

Surface runoff from the upstream catchment will be channelized through the peripheral

drain and finally it will be channelized.

h) Surrounding Drainage

Management of surrounding drainage from the identified catchment area is planned as far

as possible along the natural drainage pattern.

iv. Storm Water Management within Site

Management of storm water within the site is planned as far as possible along the natural

pattern. Rainwater harvesting measures are suggested to absorb the excess storm water

runoff generated by the proposed development within the site itself. Quantity of storm

Page 122: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 103

water contributed by the site to the Channel (before and after development) is worked out.

If entire rainwater harvesting potential of site as assessed can be realized then runoff to

Rainwater Harvesting Potential

Since proposed locations of water bodies are in and around development, these can be used

for rainwater harvesting. They will also serve purpose of detention storage and absorb

excess runoff from the site.

v. Commercial Solid Waste Management

Out of total municipal waste, it is expected that approximately 45 % will be biodegradable,

12 % will be recyclable and rest 43% will be inert waste. Since the quantities of such

municipal waste is not likely to be huge, it is suggested that instead of installing a processing

or treatment plant/ unit such as compost plant or biomethanation plant, the Client could

discuss the matter with the local Municipality if they agree to collect this Municipal waste

and dispose as per Municipal Solid Waste (Handling and Management) Rules, 2000 on per

ton treatment charge basis.

vi. Industrial Waste and its Management

Out of the total industrial waste likely to be produced, it is estimated that approximately 45

% will be biodegradable, 12 % will be recyclable and rest 43% will be inert waste. In general,

it would be the responsibility of individual industrial units to collect, store and dispose the

hazardous waste generated within their premises as per the Hazardous Wastes

(Management, Handling and Transboundary Movement) Second Amendment Rules, 2009

and its base legislation. Schedule 1 of the said Rules mentions the list of processes that

generate hazardous waste along with the type of waste.

For management of Industrial waste individual industrial units may consider having an

agreement with the nearest Treatment, Storage, Disposal Facility (TSDF) operator to dispose

the hazardous waste. TSDF sites generally have landfilling and incineration facilities are

available within their premises.

vii. Non-Hazardous Industrial Waste and its Management

Out of the total industrial waste likely to be produced from manufacturing plants/ units in

Phase 4 of this Industrial development, it is estimated that approximately 760 Kg/day would

be non-hazardous in nature. This category of waste would not warrant any kind of special

Page 123: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 104

treatment or processing similar to the hazardous waste. Non Hazardous industrial wastes

should be stored and collected separately from the hazardous waste.

It is proposed that the individual Industrial units may consider stocking/ piling such waste

separately within their premises. Arrangements/ contracts may be considered with

authorized industrial waste collector which would collect such waste on an appropriate

frequency depending upon the quantities of waste production.

viii. Biological Environment

The emissions during the operation phase will be restricted within the proposed

project site. Development of adequate green belt at and around the project site

will help in reducing the impacts on the flora and fauna as the plant species will

act as air and noise pollution sink.

Thus, the impact on the terrestrial ecology of the area would be minimum during

the operational phase of the project

ix. Socio Economic Environment

a) Positive Impacts

Improved Medical Services at Healthcare facilities

In the proposed project newly improved medical facilities will be installed there by providing

advanced treatment options for the patients.

b) Negative Impacts

OHS Risks to Health care workers

Community Health Risk to Improper waste management

Ensure proper waste management practices as recommended in the study on

improvement of healthcare waste management facilities.

Ensure proper management of waste by engaging a Consultant to come up with

measures and guidelines in accordance with the healthcare waste management

plan.

x. Energy Conservation

Energy conservation is split into three stages of

o Predesigned,

o design and

Page 124: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 105

o Post design.

Industry is an energy intensive activity. Industrial sector is the largest consumer of

electricity on an average industries consume around 41.7% of the total power output

followed by the domestic (27.4%) and agricultural (2.5%) sectors. This large energy demand

has significant environmental impacts, particularly where energy is still largely derived from

fossil fuels, including increased air pollution (particulates, oxides of sulphur [SOX], and

oxides of nitrogen NOX), increased greenhouse gas (GHG) production, increased water

demand and other solid wastes.

While acknowledging these problems, the large energy requirements of the industrial

sector also provide us with an opportunity to reduce the overall environmental costs of

energy production across the state. By increasing overall energy efficiency and use of

renewable energy and incorporating green building and green transportation technologies,

it can be a model for energy-smart industrial development for the State and India as a

whole.

a) Optimize Energy Performance

Generally in all industrial and commercial projects, the load from heating, ventilation, and

air conditioning (HVAC) is a major load component about 40%–50% of the total load

estimate. A judicious mix of the right choice of equipment, a scheme to harness available

diversity , use of the right piping and pumping scheme, and sizing plant capacity to meet

diversified and practical requirements can be beneficial in terms of initial investment and

operations and maintenance expenditures. This will relieve the total system or extra burden

for design and execution inefficiency for the life of the project.

It is to be ensured that the project’s energy-related systems are installed, and calibrated

to perform according to the industry specific requirements, basis of design and construction

documents. Benefits of commissioning include reduced energy use, lower operating costs,

fewer contractor callbacks, better building documentation, improved occupant productivity

and verification that the systems perform in accordance with the project requirements.

Qualified individuals shall be given responsibilities to lead the commissioning process.

Qualified individuals are identified as those who possess a high level of experience in the

following areas:

Page 125: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 106

Energy systems design, installation and operation

Commissioning planning and process management

Hands-on field experience with energy systems performance, interaction, start-up,

balancing, testing, troubleshooting, operation and maintenance procedures

Energy systems automation control knowledge.

High efficient luminaries with low energy inputs and high luminous output in offices,

commercial buildings and public utility areas and for water heating solar heaters are

suggested to be provided. It is also suggested that the optimum luminous intensity lighting

arrangements shall be done at working areas, streets, parking spaces and open areas.

b) Renewable Energy

Sustainable energy is a form of energy that can potentially be kept up well into the future

without causing harmful repercussions for future generations. A number of types of energy

can be thought of as sustainable, and many Governments promote the use of sustainable

energy and the development of new types of energy generating technology which fit within

this model. Increasing rates of energy consumption around the world have led to a

corresponding rise in concerns about where this energy comes from.

c) Selection of Sustainable Energy Type

Selection of certain type of sustainable energy type is dependent on location and site

specific conditions. Geo-thermal energy is not available at project site or in the vicinity. The

wind intensity is not sufficient enough and involves high cost and space constraints. The

intensity of solar radiation in the project site is sufficiently high with annual sunny hours

being around 2461. The average daily sunny hours in Bangalore are 6.4 hr. The photovoltaic

based solar power production can be a sustainable source of energy with quick pay back

resource. So, in context to the above feasibility it is suggested to produce and use PV

generated electrical power as a supplement option.

d) Energy conservation techniques

The Energy Conservation Technology Strategy is premised on the need for long-term

planning when it comes to technology development in the energy field, as well as durable

public-private partnerships. Various energy conservation techniques and practices are used

all over the world to efficiently use and conserve the energy.

Page 126: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

Page 107

The Energy conservation techniques in industries and domestic use can be achieved by

reduction of Auxiliary power consumption. In industries and modern residential complexes a

substantial amount of energy is used for lighting, Air conditioning, heating and using

electrical equipments. Using some simple changes in the normal practice, a substantial

reduction in the energy usage can be achieved. These energy savings can be attained in the

following field.

a) Interior Lighting:

b) Office Equipment

c) Computer & Electronic (Operational) Equipment:

d) Air Conditioning:

e) Domestic Refrigeration, Heating & Ventilation:

f) External Lighting

g) Miscellaneous Equipment:

Recommendation based on energy efficiency, water efficiency and material efficiency are

made in this report. Further detailed recommendations on the efficient usage of the

resources and

Page 127: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MONITORING PROGRAM

Page 108

5. ENVIRONMENTAL MONITORING PROGRAM

5.1 GENERAL

An Environmental Monitoring Plan provides feedback about the difference between actual

environmental scenario and the impacts of the project on the environment and helps to

judge the adequacy of the mitigation measures in protecting the environment. The purpose

of environmental monitoring is to evaluate the effectiveness of implementation of

Environmental Management Plan (EMP) by periodically monitoring the important

environmental parameters within the impact area, so that any adverse effects are detected

and timely action can be taken.

5.2 OBJECTIVES OF ENVIRONMENTAL MONITORING PLAN

The key issues associated with the life cycle of a project are the monitoring of

environmental parameters. Three types of environmental monitoring are associated with

the project, which includes

a) Baseline monitoring

b) Effects/ Impacts monitoring and

c) Compliance monitoring.

a) Baseline monitoring - Baseline monitoring deals with the measurement of

environmental variables during a pre project period to determine existing conditions,

ranges of variation and process of change;

b) Effects/impact monitoring – It involves measurements of environmental variable

during construction and operation phase of the project to assess the impact that

may have been caused by the project.

c) Compliance monitoring- It takes the form of periodic sampling and continuous

measurements of level of pollutant emissions in the air, waste discharge on land or

water, level of noise to ensure that standards are met.

The basic objective of the environment monitoring program is:

Planning a survey and sampling program for systematic data/information collection

Conducting survey and sampling program

Analysis of samples and data/information collected, and interpretation of data and

information

Page 128: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MONITORING PROGRAM

Page 109

To ensure implementation of mitigation measures during project implementation;

To provide feedback to the decision makers about the effectiveness of their actions;

Environmental monitoring is carried throughout project operation to detect changes

in the key environmental quality parameters, which can be attributed to the project.

To determine the project’s actual environmental impacts so that modifications can be

made to mitigate the impacts;

To identify the need for enforcement action before irreversible environmental

damage occurs;

To provide scientific information about the response of an ecosystem to a given set of

human activities and mitigation measures;

Preparation of reports for submitting to management and statutory authorities

The results of the monitoring program used to evaluate the following

a. Extent and severity of the environmental impacts against the predicted

impacts;

b. Performance of the environmental protection measures or compliance with

pertinent rules and regulations

c. Trends in impacts and Overall effectiveness of the project EMP

Various physical, biological and social components identified as of particular significance in

affecting the environment at critical locations in various stages of the project have been

suggested as Performance Indicators (PIs) listed below shall be the focus for monitoring.

Air quality with respect to PM10, PM2.5 and CO;

Water quality with respect to DO, BOD and Coliform count;

Noise levels around sensitive locations; and

Replantation success / survival rate.

For each of the environmental components, the monitoring plan specifies the parameters to

be monitored; location of monitoring sites; frequency and duration of monitoring. The

monitoring plan also specifies the applicable standards, implementation and supervising

responsibilities

Page 129: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MONITORING PROGRAM

Page 110

5.3 SUGGESTED ENVIRONMENTAL MONITORING PLAN

The environmental monitoring plan for the proposed project has been developed in view of

the institutional, scientific and fiscal issues pertaining to the project. For developing the

monitoring plan, appropriate Value Ecosystem Components (VEC’s) which are likely to be

affected have been identified. For each component, suitable measurable environmental

indicators which are appropriate to the impact mechanism and scale of disturbance and

have a low natural variability, broad applicability and an existing data series have been

defined.

As per the guidelines of MOEF, environmental monitoring shall be required during

construction and operational phases. The schedule for monitoring ambient air quality,

ambient noise quality, ground water quality, and waste water quality both during the

construction and operation phases of the project is given in Table 5.1

Page 130: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MONITORING PROGRAM

Page 111

Table ‎5.1: Environmental Monitoring Schedule

S. No Particulars Monitoring Frequency

Duration of Sampling

Important Monitoring Parameters

1 Ambient Air Quality Monitoring

a

Project site Once in a 3 Months

24 hr continuously except CO

PM10, PM2.5, SO2, NO

x & CO

2 Stack Monitoring

a DG Set – Stack Once in a 3 Months

30 min SO2,

NOx, SPM, CO, CO2,

Temperature, Flow rate & Velocity of the gas

3 Ambient Noise Level

a Near DG set Once in a 3 Months

8 hr continuous with 1 hr interval

Noise level in dB(A)

4 Ground/Drinking Water Quality Monitoring

a Ground Water – at project site

Once in 3 Months

Grab Sampling Parameters specified under IS:10500, 1993

5 Sewage Quality Monitoring

a ETP Inlet Once in a Week

Grab Sampling Physical, Chemical & Biological Parameters specified under IS:2490:1982 b ETP

Outlet

6 Soil Quality

a At the green belt area

Once in a year

Samples were collected from three different depths viz., 30cm, 60cm, and 100cm below the surface

Parameter for soil quality: pH, texture, electrical conductivity, organic matter, nitrogen, phosphate, sodium, calcium, potassium and

Magnesium.

Page 131: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 112

6. ADDITIONAL STUDIES

6.1 RISK ASSESSMENT

The principal objective of the risk assessment study is to identify and quantify the major

hazards and the risk associated with various operations of the proposed project, which may

lead to emergency consequences (disasters) affecting the public safety and health. Based on

this information, an emergency preparedness plan is to be prepared to mitigate the

consequences. Industrial accidents result in great personal and financial loss. Many facilities

involve various manufacturing processes that have the potential for accidents which may be

catastrophic to the plant, work force, environment, or public.

Risk analysis involves the identification and assessment of risks; the neighboring populations

are exposed to as a result of hazards present in the plant operation. This requires a

thorough knowledge of failure probability, credible accident scenario, vulnerability of

populations etc. The risk analysis is often confined to maximum credible accident studies. In

this chapter, the identification of various hazards, maximum credible accident analysis, and

consequence analysis are addressed, which gives a broad identification of risks involved.

Based on the risk assessment, disaster management plan has been presented.

The major hazardous anticipated in the proposed project are illustrated below.

Hazardous pertaining to fires in project/plant area

Fire in diesel storage areas, garbage storage areas and disposal areas

Natural disasters viz. Earthquakes, flooding, etc

Electrical accidents

Flooding from man-made causes

6.2 HAZARD IDENTIFICATION

Identification of hazards in the proposed plant is of primary significance in the analysis,

Quantification and cost effective control of accidents involving chemicals and process. A

classical definition of hazard states that hazard is in fact the characteristic of

system/plant/process that presents potential for an accident. Hence all the components of a

system/plant/process need to be thoroughly examined to assess their potential for initiating

or propagating an unplanned event/sequence of events which can be termed as an

accident.

Page 132: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 113

6.3 Hazard Assessment and Evaluation

A preliminary hazard analysis is carried out to identify the major hazards associated with

storage and the process of the plant. This is followed by consequence analysis to quantify

these hazards.

Physical and Health Occupational Hazards in any Industry can be broadly classified into the

following categories:

I. Mechanical Risks

II. Electrical Risks

III. Fire/Explosion Risks

IV. High /low Temperature Exposure Risks

V. Toxic/Carcinogenic Chemicals Exposure Risks

VI. Corrosive/Reactive/Radioactive Chemicals Exposure Risks

a) Electrical Hazards

Electrical hazards leading to fire and explosion in switchgear and other equipment mainly

due to failure of circuit breakers, insulators, fuses, and poor maintenance etc. Nevertheless,

all these hazards lead to localized accidents only.

b) Fire Hazards

There could be other areas in the plant that have a potential for fire hazard and require

adequate firefighting equipment for example, the raw material storages. These are

considered here since uncontrolled fire may trigger the above emergencies due to domino

effect.

c) Toxic release

The proposed plant will use Sulfuric acid which is corrosive and toxic. If sulfuric acid will not

handle properly it will lead to toxicity and burns. Self-contained breathing apparatus will be

available in the premises in the event of leakage in case of emergency. Employees will be

trained in handling these self-contained breathing apparatus. Since the quantity of toxic

release will be on lower side, offsite implications of release are not envisaged.

d) Hazardous Chemicals Release

There are various hazardous chemicals (toxic and flammable), which will be used as raw

material for manufacturing of Single super phosphate in the plant. Separate storage area

will be provided for these chemicals and will be handled with at most care following the

safety norms for handling of hazardous chemicals.

Page 133: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 114

Table ‎6.1: Preliminary Hazard Analysis for Process and Storage Areas

Sr. No. Block /Area Hazards Identified

1. Flammable chemical storage Fire, spontaneous Combustion

2. DG set Fire in cable galleries, short circuits in control

rooms and switch gears

3. Switch –yard control room

Fire in cable galleries and switchgear/control

room

4. Process reaction vessels

Fire due to accidental spill, Leakages of

flammable raw material from the equipment.

5. Power Transformer Explosion and fire

Table ‎6.2: Preliminary Hazard Analysis for the Whole Plant in General

PHA Category Description Plausible Hazard Provision

Environmental

Factors

If there is any leakage and

eventually of source of

ignition

All electrical fitting and

cables are provided as per

the specific standards.

Highly inflammable nature of

the chemicals may cause fire

hazard in the plant

All well designed fire

protection including dry

powder, CO2 and foam

extinguisher should be

provides.

Fire extinguisher of small size

and big size are provided at

all potential fire hazard

places. In addition fire

hydrant network is also

provided to required

locations in plant.

6.4 DISASTER MANAGEMENT PLAN (DMP)

Disaster is an unexpected event due to sudden failure of the system, external threats,

internal disturbances, earthquakes, fire and accidents. Thus an appropriate Disaster

Page 134: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 115

Management Plan (DMP) shall be prepared in consultation with the project proponent,

architect, service consultant and maintenance staff.

a) Preventive Action

Once the likelihood of a disaster is suspected, action has to be initiated to prevent a

failure. The project in-charge, responsible for preventive action should identify sources of

repair equipment’s, materials, labor and expertise for use during emergency.

The project in-charge should notify the officer for the following information:

Exit points for the public,

Safety areas

Nearest medical facilities.

b) Communication System

An efficient communication system is absolutely essential for the success of any disaster

management plan. This has to be worked out in consultation with local authorities

involving police and fire department, hospital department considering the following

points

Identify the relevant officials and institutions to be involved for the first,

second and third level of information;

Preparation of the telephone directory of these officials and making available

to all concerned;

Allotment of toll free number to a central communication centre.

Provide wireless communication tools to safety and security and

communication officers;

Empowering central communication centre with latest communication

equipment and tools.

c) Emergency Action Committee

To ensure coordinated action, an Emergency Action Committee shall be constituted. An

Emergency evacuation plan based on local needs and facilities available shall be

prepared. The broad content of plan shall include following:

Demarcation of the areas to be evacuated with priorities,

Safe area and shelters,

Security of property left behind in the evacuated areas,

Page 135: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 116

Functions and responsibilities of various members, and

Setting up of joint control action.

An elaborate firefighting arrangement is designed for the proposed project as

per the requirement of National Building Code Part-IV, which is detailed

below.

Emergencies can occur at any time usually without warning. When an emergency occurs,

the safety and prompt recovery of the College community depends on the preparedness

and careful response of our employees, students, patients, and visitors. The information

listed below provides basic emergency information to help individuals respond thoughtfully

in an emergency event.

6.5 HAZARDOUS CONTROL MEASURES

a) Fires

To increase the level of safety in compost yard and buildings, installation of smoke alarms or

automatic fire detection /alarm systems will be proposed at strategic locations as an early

warning of fire to the occupants. To prevent fire mishaps and to manage the emergency

situation during fire in the proposed project the following activities and precautions are

proposed.

• Emergency evacuation plan is important for all projects, and the same will be prepared

as per Fire & Safety rules.

• Regular mock drills will be carried out to create awareness on procedures to be

followed in times of emergency situation/evacuation

• It will be advised to keep oxygen cylinders, medical kits and masks to prevent smoke

inhalation especially for those with respiratory disorders for whom smoke inhalation

can be very dangerous.

• Plant manager will be advised to ensure that the firefighting equipment’s are in good

working conditions.

• The plant will be provided with sufficient firefighting gadgets (water, soil,

cylinders, etc)

Simple steps to be followed during emergency are as follows.

Page 136: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 117

Call the fire rescue department: During fire in plant, leave the premises by nearest available

exit. Call fire department and do not assume anyone else has called the fire department. If

your cloth catches fire, do not get panic or run, stop, drop and roll.

Cover your nose and mouth with a wet clean cloth: Stay calm cover your nose and mouth

with a wet, clean cloth to prevent smoke inhalation injury and choking. Never jump off or

attempt to climb down the side of tall structures as it will mean certain death.

Do not run: During a fire, smoke containing poisonous gases such as CO tends to rise up.

When you run in a smoke filled room, you tend to inhale the smoke faster. CO dulls the

senses and prevents clear thinking, leading to panic. To prevent being asphyxiated, dip

tissues or cloth in water and cover your noise with it.

Head-count of the occupants: During an emergency, make good use of the evacuation

procedure and help each other to reach out of plant/building safely. Ensure nobody is left

behind by doing a head-count of occupants. Visitors should read and understand the

evacuation plan before going into the plant/building area and ensure their safety.

b) Natural Disasters

Disasters occur without notice. Most disasters are natural such as earthquake, floods,

hurricanes, sandstorms, landslides, tsunamis and volcanoes. We have no way of stopping

them, but we can learn to deal with the difficult situations that arise due to them. During

disasters like floods, fire, earth quake, landslides, rescue beings at site. Even before external

help arrives, people affected by the disasters help each other.

The government and many voluntary organizations send teams of workers trained in rescue

operations to disaster-affected areas. These teams join hands with the local community

helpers such as doctors, nurses, social workers and policemen.

Temporary shelters are built for displaced people. Doctors and nurses provide medical aid.

They treat the wounded and work to control epidemics. Social workers collect food and

cloth from all over the country for the disaster-affected people. The police maintain law and

order. Media –persons help in spreading news about the victims and their conditions. They

also post advertisements that urge people to donate for victims.

In extreme conditions, the army and Air force organize rescue operations. They clear roads,

send medical teams and help to move people to safer places. The air force drops food,

Page 137: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 118

water and clothes in the affected areas. Organization like UN helps in providing aid during

massive disasters.

Individually, people from all over the world also come forward to help during a disaster.

They donate blood while many donate money. Some even reach the disaster affected places

to give an extra hand in the rescue operation. Families adopt children who have lost their

parents and thus give them a new home.

What you can do in case disaster strikes are given below

If there is a tornado, take shelter in a place without windows.

In an earthquake, remember to crouch under some heavy furniture or stand under

the doorframe for cover.

In case of a fire in the building, leave the building by nearby exit

If the site is flooded, then climb up to the roof.

Do not use the telephone, except to call for help, so as to leave telephone lines free

for the organization of response

Listen to the messages broadcast by radio and the various media so as to be

informed of development

Carry out the official instructions given over the radio or by loudspeaker

Keep a emergency kit ready. In all the different types of emergency, it is better to be

prepared than to get ready, to get information so as to get organized, to wait rather

that act too hastily

During floods turn off electricity to reduce the risk of electrocution

As soon as flood begins, take vulnerable people (old, children, sick, etc) to upper

floor

Beware of water contamination, wait until the water is declared safe before drinking

or boil the water before drinking

Clean and disinfect the room that is flooded

During storms and hurricanes do not go out in a car or a boat once the storm has

been announced

If caught outside in a storm, take refuge as quickly as possible in shelter (never under

a tree), if there is no shelter, lie down flat in a ditch.

Page 138: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 119

In a thunderstorm keep away from doors, windows, and electrical conductors,

unplug electrical appliances and aerials. Do not use any electrical appliances or the

telephone

During earthquake keep calm, do not get panic, People who are indoors should stay

there but move to the central part of the building, people who are outside should

stay there, keeping away from buildings to avoid collapsing walls and away from

electrical cables. Anyone in a vehicle should park it, keeping away from bridges and

buildings

During spread of clouds of toxic fumes, close doors and windows, seal any cracks or

gaps around windows and doors with adhesive tape. Organize a reserve of water (by

filling wash basins, baths, etc. Turn off ventilators and air conditioners.

c) Electrical Accidents

Electrical hazards can cause burns, shocks, and electrocution which can lead to serious

injury and even death. When dealing with potentially serious electrical hazards, stop and

think! Instead of taking a chance and risking your personal safety, call trained professionals

to handle problems. Many times people prefer to take electrical matters into their own

hands. Other small aspects of electrical repair in a business setting may be taken care of

without needing professional service technicians. If you do decide to take matters into your

own hands, safety precautions can avoid injuries and other losses.

i. Prevention of Electrical Accidents

Flexible cords connected to appliance should be wired to confirm to the international Colour

code. Colour of the insulation on the wire is

• Brown represents live wire,

• Blue represents neutral wire and

• Green/yellow stripes represent earth wire.

What you should look for when selecting an electrical appliance are given below

a) The appliance should be suitable for operation on local electrical supply of 240 volts

AC and frequency of 50 Hz.

b) The appliance should preferably be tested and certified by a national or reputed

standards testing authority

Page 139: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 120

c) Look for certified plugs on the flexible cords connected to the appliances. If the

appliance is double insulated and has a 2-pin plug, then it should be fitted with a

suitable certified plug.

d) An essential formality when buying any appliances is a duly completed guarantee

card with the dealer's/retailer's official stamp and details of the appliance (serial

number, etc.).

Safety precautions to be taken when using electrical appliances

a) Avoid using handheld appliances when your hand and/or body is wet.

b) Do not use or leave appliances where liquid can splash onto them.

c) Flexible cords connecting the appliance and the plug should be in good condition, if

the cord is frayed, chaffed, cut or melted, have the entire cord replaced by a

competent person.

d) Check accessories such as plugs attached to appliances for cracks and burnt marks

and have them replaced. If undue overheating occurs or burnt marks appear in any

electrical appliance, have it checked

Some common causes of electrical accidents in the house

a) Faulty wiring: This usually occurs when unauthorized extension or rewiring is done

by unqualified persons. Some of the usual faults are the omission of earth wires and

the reversing of the live and neutral wires. Without an earth wire, the exposed metal

parts of appliances may deliver a lethal shock to the user when a fault develops.

b) Improper flexible cords: This can be caused by connecting the flexible cord wrongly

to the plug. In the case of appliances which have exposed metallic parts, a 2-core

instead of a 3-core flexible cord is used. When the appliance is faulty, the exposed

metal parts may become live and a fatal accident could result.

c) Faulty appliance: Attempts to repair faults in electrical appliances by people not

trained to do so can result in accidental shock.

To prevent Electrical accidents, the following points should be kept in mind:

• All electrical wiring, rewiring or extension work must be carried out by licensed

electrical contractors. On completion, the contractors should test before electricity

supply is connected.

• Repair of appliances and replacement of flexible

• Cords should be carried out only by competent persons.

Page 140: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 121

• To ensure electrical safety in the house, a current-operated Earth Leakage Circuit

Breaker (ELCB) or Residual Current Circuit Breaker (RCCB) set to operate at a very

small leakage current is recommended. (This is usually marked 100mA or 0.1A on the

label). In case of dangerous electrical leakage to earth, it should automatically cur off

the supply of electricity.

• DO NOT repair your own electrical appliances. Engage the services of a competent

technician.

• DO NOT use multi-way adaptors. Over loading can cause fire. One socket outlet is for

one appliance only.

• DO NOT carry out wiring extension by yourself. Engage a licensed wiring contractor

for the work.

• DO NOT use a two-way lighting adaptor for any extension.

• DO NOT connect any electrical appliance to lighting outlets. A lighting outlet does

not have an earth wire to prevent danger.

• ENSURE the switch is in "OFF" position before changing bulbs.

• DO NOT make joints to lengthen the lead of the electrical appliances. If the lead wire

is worn out or too short, replace it with a new wire.

• DO NOT drive nails carelessly on the wall. There may be concealed wiring.

• USE individual socket outlet for every electrical appliance.

• KEEP AWAY from danger areas such as a substation for whatsoever reasons.

• CHECK before carrying out excavation work to prevent damaging any underground

cable. The operator may receive severe electric shock or even be electrocuted.

• TAKE PRECAUTION when working in the vicinity of overhead lines to avoid any

unforeseen incident.

• DO NOT meddle with any broken overhead wire. Report the matter immediately to

the nearest electric office.

• DO NOT climb any electric pole. You may receive an electric shock or get

electrocuted.

• DO NOT throw anything onto the overhead lines.

• NEVER attempt to retrieve anything stuck to overhead lines by whatever means.

• DO NOT climb transmission line towers. No one is safe from its high voltage shock.

• DO NOT erect any structure close to transmission lines.

Page 141: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 122

• DO NOT fly kites close to overhead lines.

• TAKE PRECAUTION when working in the vicinity of overhead lines to avoid any

unforeseen incident.

• NEVER stand on a damp or wet surface when using electrical equipment.

• USE a portable electrical tool, which is properly earthed.

• DO NOT tap electrical power without a proper plug.

• DO NOT use any electrical tool which has a damaged casing, cap, switch, lead or

plug.

• BEFORE using portable electrical appliances and tools, always check for:

o Worn or defective insulation

o Loose or broken connection

o Earth wire connection

6.6 RISK AND EMERGENCY PREPAREDNESS PLAN

Emergencies can occur at any time usually without warning. When an emergency occurs,

the safety and prompt recovery of the project site depends on the preparedness and careful

response of our workers, peoples and visitors. The information listed below provides basic

emergency information to help individuals respond thoughtfully in an emergency event.

a) Building Evacuation

The Department of Public Safety and Security will notify security officers, building

contractors and emergency preparedness coordinators to commence evacuation

procedures.

In the event of an emergency, all occupants are to vacate the buildings

immediately.

When notification occurs, all building occupants must evacuate from the

nearest marked exit and alert others within close proximity to do the same.

Assist mobility to impaired persons to the closest “area of rescue assistance”.

Use stairwells to exit the buildings. Do not use elevators in the event of a fire,

earthquake, or other emergencies where you could become confined inside.

Proceed outside to the nearest Emergency Assembly Point.

Provisions for individuals with disabilities.

Page 142: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 123

The landings inside of each stairwell and protected elevator lobbies are considered

safe areas for individuals with disabilities. It is routine procedure for emergency

personnel (i.e., fire department and police) to check these areas for individuals with

disabilities and/or injured persons. In the event of an evacuation, individuals with

disabilities located above or below the ground floor should be escorted to the

closest stairwell and a buddy should remain with that person until emergency

personnel arrive.

b) Training

It is a proven fact that human beings, when faced with adverse situations, tend to

react in the way for which they have trained and practiced. Therefore, it is

recommended that each area of the plan training periods in which the previously

listed procedures may be practiced. Emergency preparedness coordinator should

have regular meetings with people in their building to be certain everyone knows

what to do and what to expect, as much as possible. These meetings should be held

often enough to keep everyone properly informed.

The Project proponent will conduct mandatory Emergency Preparedness Training

sessions annually, in person or web-based. The training will be conducted through a

collaboration of the Office of the Associate Vice President for Administration,

Campus Operations, and Campus Safety and Security. Any change in building

contractors or emergency preparedness coordinators should be immediately

reported to both the Environmental management Cell and the Environmental Safety

Officer.

6.7 EMERGENCY PREPAREDNESS TRAINING

It is a proven fact that human beings, when faced with adverse situations, tend to react in

the way for which they have trained and practiced. Therefore, it is recommended that each

area the training periods in which the previously listed procedures may be practiced. Each

building contact and emergency preparedness coordinator should have regular meetings

with people in their building to be certain everyone knows what to do and what to expect,

as much as possible. These meetings should be held often enough to keep everyone

properly informed. Training sessions should be coordinated through the Environmental

Management Cell.

Page 143: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 124

Meetings and training sessions should be documented by the building contractors.

Documentation should include the attendee’s name, position with the date of training,

location training was held, and any other specific information in regards to what was

covered in the session. These records should be forwarded to the compliance Officer and to

Human Resources for inclusion in the employee’s personnel file.

There will be mandatory Emergency Preparedness Training sessions annually, in person or

web-based. The training will be conducted through a collaboration of the Office of the

Associate Vice President for Administration, Campus Operations, and Campus Safety and

Security. Any change in building contacts or emergency preparedness coordinators should

be immediately reported to both the Environmental management Cell and the

Environmental Safety Officer.

a) Training on Fire Fighting

An intensive Fire Fighting Program is regularly conducted once in a month. A one day

training program for Occupants and maintenance staffs will be conducted regularly once in a

month by the Fire department staffs. The training program includes Lecture Classes, wet

mock drill and First aid etc. Practical demonstrations on use of first aid fire extinguishers

followed by the wet mock drill with our hydrant system also form part of the program.

b) Equipment Checks

All firefighting equipment like valves, fire hydrants, pumps, monitors, etc., will be checked

weekly to detect defective parts and such parts would be immediately replaced.

c) Mock Drills

Mock drills will be conducted for training the persons and to check the performance of

persons and equipment’s and also to keep them fit for any emergency.

To extract persons from the debris of collapsed buildings / structure and save human

lives.

To cut off supplies of water, gas electricity to damaged buildings.

To take immediate steps as may be necessary for the temporary supports or demolition of

buildings and structures, the collapses of which is likely to endanger life.

Page 144: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL STUDIES

Page 125

6.8 FIRST AID AND EMERGENCY PROCEDURES

Burns are caused by dry heat such as fire, electricity, strong acids and alkalies.

Table ‎6.3: First Aid for Burns

Burns Covering Small Area Burn Covering Extensive Area

ii. Allow cold tap water to run gently over

the area or immerse in cold water.

iii. It may be necessary to cover with gauze

or a clean handkerchief, and bandage

i. Allow person to lie down.

ii. Cover burned areas with sterile

dressing or clean cloth and lightly

bandage.

iii. If clothing is adhering, do not

disturb; leave the clothing alone.

iv. Keep person warm. If person is

not nauseated, he may have sips

of water.

v. Arrange for immediate medical

care. (Call 108 for ambulance.)

Note: Do not user ointments, greases, pastes or powder on burned area. Do not

prick the blisters caused by burns.

Tetanus Immunisation : Protection against tetanus should be considered

whenever the skin is broken by injuries

Page 145: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT BENEFITS

Page 126

7. PROJECT BENEFITS

7.1 SIGNIFICANCE OF THE PROPOSED PROJECT

Karnataka Industrial Areas Development Board (KIADB) is a wholly owned infrastructure

agency of Government of Karnataka, set up under Karnataka Industrial Areas Development

Act of 1966.KIADB has so far developed 141 industrial areas in 28 districts of the State. This

Land is acquired by Karnataka Industrial areas Development Board (KIADB) as per the

following policies and acts

a) Karnataka Export Promotion Policy

b) Karnataka Industrial Policy 2009-14

c) The Karnataka Industrial Areas Development Act, 1966.

The district has 81268 hectares of forests, which constitutes (13.88%) of the total

geographical area of the district (585431 ha). The fallow land in the district is around 39426

ha. Net area sown during the year is 2005-06 was around 318211 ha. And 8163 hectares of

land was sown more than once. The Dobaspet area is probably the industrialized area in the

State of Karnataka and the proposed plot area 341.65 ha (844.23 Acres) is spread in the

Villages of Yedehalli, Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, Avverahalli,

K.G.Srinivasapura, Billanakote, Nelamangala Taluk, Bangalore Rural District. The land is

vacant and it contains bushes and shrubs.

According to many commentators, Karnataka could unleash its full potentials, provided it

improves the infrastructure facilities, which are at present not sufficient to meet the

growing demand of the economy and population. Therefore, infrastructure developments

such as construction of “Industrial Area Projects” are needed for a State like Karanataka.

7.2 IMPACT ON PHYSICAL INFRASTRUCTURE

The proposed industrial area will include following infrastructure facilities:

Industrial Plots STP

Approach roads Power Sub-Stations

Internal roads with storm water drains Solid Waste Incinerator

Power supply and street lighting Rain Water Harvesting System

Water supply network Public utilities

Parking/Buffer zone area. Green Belt Development

Housing Complex Commercial Complex

Due to the proposed project the following physical infrastructure improvements takes place:

Page 146: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

PROJECT BENEFITS

Page 127

1. The objective of the project is to develop Industries. During the operation phase of

the project, there will be rigorous movement of vehicles hence road improvement

will take place. However, the roads adjacent to the project site are in good

condition.

2. Residential improvements such as development of apartments, villas and individual

houses etc., will take place.

3. Water supply and sewerage lines connections will be improved.

Considering the above points, it can be concluded that the proposed project site is best

suited for the commercial activity.

7.3 IMPACT ON SOCIO – ECONOMIC FACTORS

The impacts on the socio – economic developments due to the proposed project is as

follows:

1. Due to the development of Industries, population from different states will migrate

towards the proposed project area. Due to this near to project site land value and

the house rent increases. Subsequently, economics status of the surrounding people

increases.

2. Employment opportunities for Engineers, Labours, security guards, housekeepers

etc., will be created due to the development of Industries Area.

7.4 EMPLOYMENT POTENTIAL

1. Due to creation of new industries more workers and man power have joined this

places leading to a substantial increase in the population.

2. The project will generate direct and indirect employment opportunities for the local

people. The plant will create additional employment during construction &

operational phase. Additionally, certain works like security will be outsourced on

contract.

3. The secondary employment in the form of providing services to the employed

manpower will also be developed in the neighboring villages.

• Raw materials can be sourced locally. Hence the cost for procurement is less

• Increase in Market & Business Establishment facilities

• The State Government will benefit through revenue recovery from excise

duty.

Page 147: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 128

8. ENVIRONMENTAL MANAGAEMENT PLAN

8.1 INTRODUCTION

The EMP need to be integrated in overall project planning process covering all phases of

project cycles i.e, location, design, construction and operation. Management by provision of

necessary safeguard in planning of the project itself can lead to reduction of adverse

environmental impacts due to project. This chapter spells out the set of measures to be

undertaken during project construction and operation to reduce or mitigate or bring down

the adverse environmental impacts to acceptable level based on the proposed

Environmental Management Plan.

The most reliable way to ensure that the plan will be integrated into the overall project

planning and implementation is to include the plan as an integral component of the project.

This will ensure that it receives funding and supervision along with other investment

components. For optimal integration of EMP into the project, there should be link for:

Funding;

Management, Training and

Monitoring

The purpose of the first link is to ensure that proposed actions are adequately financed. The

second link helps in embedding training, technical assistance, staffing and other institutional

strengthening items in the mitigation measures to implement the overall management plan.

The third provides a critical path for implementation and enables sponsors and the funding

agency to evaluate the success of mitigation measures, as part of project supervision and as

a means to improve future projects. For every use discussed in the above sections, the

implementing agency as well as staffing, equipment, phasing and budgeting have been

presented as far as possible. All required funds will be channelled through the project

authority.

Environmental Management Plan (EMP) will be established to monitor and to ensure the

proper functioning of the Proposed Project. The EMS will include the following:

Environmental Management Cell

Personnel Training on Environmental Awareness Program and Safety Issues

Page 148: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 129

8.2 ENVIRONMENTAL MANAGEMENT CELL

An organizational setup to be formed to ensure effective implementation of the mitigation

measures to minimize the impacts due to the activities carried out during Construction and

Operation phase of the Proposed Project and to execute the Environmental Monitoring

Plan.

The responsibilities of the Environmental Management Cell is given below

To implement the Mitigation measures

To assure regulatory compliance with all relevant rules and regulations

To ensure regular operation and maintenance of pollution control measures

To initiate environmental monitoring as per approved schedule

Maintain documentation of good environmental practices and applicable

environmental laws as ready reference

Coordination with regulatory agencies, external consultants, monitoring

laboratories.

Conducting Environmental Awareness Program for the patients and employees on

Safety issues, Water management, and Energy conservation.

The organizational set up of the Environmental Management Cell is shown in Figure8.1.

Figure ‎8.1: Environmental Management Cell

Page 149: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 130

The responsibilities of the Environmental Management Cell are as follows;

To implement the Mitigation measures;

To assure regulatory compliance with all relevant rules and regulations;

To ensure regular operation and maintenance of pollution control measures;

To initiate environmental monitoring as per approved schedule;

Maintain documentation of good environmental practices and applicable

environmental laws as ready reference;

Coordination with regulatory agencies, external consultants, monitoring

laboratories; Conducting Environmental Awareness Program for the employees on

Safety issues, Water management, and Energy conservation.

All developmental activities will bring some impacts associated with its origin, which can be

broadly classified as reversible, irreversible, long and short-term impacts. In this section an

endeavor has been made to identify various Environmental Impacts associated with the

proposed project both during construction and operational phase.

Based on the possible worst case emissions and waste generation from the proposed

project and also taking into consideration the baseline Environmental status at the

proposed project site, the environmental factors that may likely be affected (Impacts) are

assessed. Both instrumental (positive) and detrimental (negative) impacts are accounted for

this purpose. The prediction of impacts helps in the preparing a sound Environmental

Management Plan which has to be executed during operational and construction phase to

minimize the adverse impacts on the environmental quality.

The potential impacts on the environment from the proposed project are identified based

on the nature of the various activities associated not only with the project implementation

and operation, but also on the current status of the environmental quality at the project

site.

All the potentially significant environmental impacts from the project are grouped as below.

i. Air Environment

Impacts on ambient air quality

Impacts on ambient odour

Impacts on ambient noise

Page 150: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 131

ii. Water Environment

Impacts on surface water quality

Impacts on ground water

iii. Land Environment

Impacts on land use

Impacts on agriculture

iv. Socio Economics

Impacts on infrastructure

Impacts on employment

v. Indirect Impacts

Impacts on public health and safety

Impacts on cultural resources

Impacts on aesthetics

To study the existing status of the ambient air quality in the project area and its

surroundings few samples of air, water and soil will be collected and analyzed for important

parameters. Similarly noise levels will also be measured at some important locations.

8.3 ENVIRONMENTAL MANAGEMENT PLAN DURING CONSTRUCTION PHASE

i. Water and Wastewater Management

The environmental impacts during the construction phase are limited to construction phase

only. Water demand required for construction activity is 160 KLD and for construction labors

is 90 KLD (2000 Nos * 45 LPCD) and the same will be met through KIADB treated water

tankers.

Proper sanitation facilities will be provided to the construction workers. 100 toilets and 100

bathrooms will be provided for 500 labors.

81 KLD of sewage generated will be treated in Mobile STP. After treatment, treated

wastewater will be led into the existing line. Hence no unsanitary conditions will be created.

ii. Solid Waste Management

About 300 Kgs/day of solid waste will be generated from the labour campus and the same

will be handed over to the KIADB trucks.

Page 151: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 132

iii. Construction Debris Management

The debris will be generated due to the construction activity and the same will be used for

backfilling and for sub-base works of roads and pavements within the project site.

iv. Environmental Impacts due to Construction Activity and their Management

Measures

Environmental impacts due to the construction activity are:

Removal of topsoil due to excavation will lead to high water requirement for future

landscape purposes and will prevent the growth of native plant species.

Change in topography of the area will mean change in drainage patterns of the area.

Reduced ground water recharge due to increase of hard surfaces.

Construction activities create dust/air pollution

Heavy machinery used generates noise pollution

Urbanized areas lead to a temperature rise of 1-2o C due to higher absorptive

surfaces.

Implementing some site control measure during construction will reduce the environmental

impacts and reduce the nuisance levels to the surrounding areas from the construction site.

v. Measures to control site impacts

a) Site Clearance

Site clearing process will be phased to only areas that need excavation initially; this

will reduce the dust emission from currently unused areas.

Unused area will be vegetated by growing temporary groundcover plants or flower

beds.

b) Construction of Access Roads

Collaboration with municipal authorities for temporary/permanent road widening to

cater to the additional truck traffic and future traffic

Truck movement will be avoided during the morning and evening rush hours i.e.

before 10.00am and after 5.00pm.

Frequent water sprinkling will be done to reduce local dust emissions.

c) Noise Barriers

Sensitive neighboring sites will be identified and barriers will be erected to safeguard

those sides from impacts

Page 152: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 133

Noise protective equipment will be provided to the operator of the machine

Silencer/dampers will be attached to the equipment to reduce noise from the

equipment to surrounding areas.

Noise prone activities will be restricted during night time

d) Excavation

Excavation will be carried out in such a manner that it will not reduce slope stability

The top soil will be used for landscaping and leveling activities on site.

On windy days excavation activities will be avoided to reduce dust emissions

Excavated soil will be prevented from spilling out of the site boundaries on to

adjoining roads and properties.

e) Dust Emission during Construction

Site will be watered at least twice a day to reduce the dust emissions

Tree plantation program will be carried out along the approach roads and the

construction.

f) Drainage

Drainage system will be provided for the site to avoid water runoff on to the

surrounding properties and roads, especially during the monsoon months.

If during excavation, water accumulates in the excavated areas, it will be pumped

out and disposed off either in the municipal storm water drain or into recharge soak

pits of dry bore wells.

g) Maintenance of Vehicles

Construction vehicles will be properly maintained to minimize smoke in the exhaust

emissions

h) Material Loading and Unloading

All trucks hauling dirt, sand, soil or other loose material will be covered two feet free

board will be maintained.

Load and unload of trucks will be carried out on site.

i) Surrounding Areas

Adjacent roads of the site will be swept at least once a day that get soiled due to the

frequent movement of trucks to and fro from the site.

All outdoor lighting, will be designed, installed and operated to ensure that all direct

rays from project lighting are contained within construction site.

Page 153: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 134

j) Solid/Hazardous Waste Disposal

The hazardous materials used during construction phase may include petrol, diesel, welding

gas and paints. These materials will be stored and handled according to the KSPCB

guidelines.

Diesel and other fuels will be stored in separate enclosures.

Wherever possible, hazardous raw materials will be substituted by non-hazardous

materials for example cleaning solvent will be replaced with film – free

biodegradable cleaners. Usage of non chlorinated strippers instead of strippers

containing methylene chloride and substitution of water based paint for oil based

ones.

Vehicle maintenance area will be designed to prevent contamination of ground

water by accidental spillage of oil.

8.4 ENVIRONMENTAL MANAGEMENT PLAN DURING OPERATIONAL PHASE

There are no negative impacts due to the proposed project on the environmental

parameters such as air, noise, land and water.

i. Air Quality Management

Major pollutants envisaged from the proposed project will be from the Industries and

vehicles movement. The major pollutants will be oxides of nitrogen, particulates and

sulphur-dioxide. The following methods of abatement will be employed for the air pollution

control board source level.

Use advance and proper methods to control and reduce air pollution from industries

Green belt development with specific species will reduce SPM levels

Use of clean fuel by the vehicles will reduce emission of pollutants

The emission from the slacks of Industries will be monitored for exit concentration of

Oxides of nitrogen and sulphurdioxide

Sampling ports will be provided in the slacks according to KSPCB guidelines.

ii. Noise Level Management

Some of the practices proposed for noise attenuation are as follows.

All noise generating source from the industries and DG Set for residential and

commercial will be equipped with appropriate noise control measures.

Sound levels will be consistent with local government regulations

Page 154: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 135

Ambient noise levels will be periodically monitored to determine compliance with

the norms.

Noise levels will also be monitored at point source for occupational noise exposure

and ensuring health risk.

iii. Water Demand and Supply

Two separate pipelines for the cold water supply for domestic purpose and treated water

supply for flushing purpose will be laid.

Sewage and domestic wastewater from soil pipes and sullage pipes will be led into the

sewage treatment plant. From the sewage treatment plant, water flows into the treated

water sump. From the treated water sump, a separate line will be laid which connects to the

WC and to the sprinklers.

During the operational phase, the water demand is 11.5 MLD will be Drawn from Hemavathi

River. The Water Noc is obtained from the KIADB.

iv. Wastewater Management

The estimated Sewage generations during operation phase 1.28 MLD and Trade Effluent

from industries is 4.8 MLD.

v. Sewage Treatment Plants

Quantity of sewage generated during the construction phase will be 81 KLD. Sewage during

construction phase will be Septic Tank.

During operation phase sewage generated will be treated in the Sewage Treatment Plant

(STP) planned in 4.7 Ac provided for STP. The estimated Sewage generations during

operation phase, 2.16 MLD. The treated water shall be reused in toilet flushing, gardening

etc. and the wastewater generated from the industries is 7 MLD, which is treated in their

respective Effluent Treatment Plants (ETP) on the bases of advance and zero discharge

concept. The treated water is reuse for industries like cooling, heat exchangers, boilers,

cleaning equipment’s etcadvance and zero discharge concept. The treated water is reuse for

industries like cooling, heat exchangers, boilers, cleaning equipment’s etc.

Page 155: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 136

vi. Solid Waste Management and Hazardous Waste Management

Project proponent will establish and maintain storage facilities in such a manner as they do

not create unhygienic and unsanitary conditions around it. Following criteria shall be taken

into account while establishing and maintaining storage facilities, namely

Storage facilities, to be set up by project proponent authorities or any other agency,

shall be so designed that wastes stored are not exposed to open atmosphere and

shall be aesthetically acceptable and user-friendly;

Storage facilities or ‘bins’ shall have ‘easy to operate’ design for handling, transfer

and transportation of waste. Bins for storage of bio-degradable wastes shall be

painted green, those for storage of recyclable wastes shall be printed white and

those for storage of other wastes shall be printed black;

Manual handling of waste shall be prohibited. If unavoidable due to constraints,

manual handling shall be carried out under proper precaution with due care for

safety of workers.

vii. Traffic Management Measures

Vehicle movement will be regulated inside the site with adequate roads and parking lots.

The layout plan of the proposed site has been planned to develop an internal road network

in such a manner that it integrates the whole proposed project in an interesting composition

to built masses and open spaces with a pedestrian dominated movement pattern. Entry

point to the proposed project site has been worked out keeping in view of the desired

movement of vehicles on the main approach road and road network around the site. Main

entry to the project is planned from the approach road on the northern and eastern side. An

adequately wide driveway to cater to one-way traffic has been planned inside the project

site.

viii. Fire Safety Measures:

Firefighting system to the proposed building is designed based on the recommendations of

NBC 2005. Following safety measures are envisaged.

Automatic detection and Alarm System

Manually Operated Electric Fire Alarm System

Automatic Sprinkler System

External Yard Hydrant

Wet Riser/ Hydrant

Page 156: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 137

Fire Extinguisher

Hose Reel

ix. Human Health and Safety Management Plan

The objective is to ensure that the health and safety of on – site personnel is proactively

managed during the construction stage of the project. Below given are the proposed project

related human health and safety environmental concerns and its management.

The primary concern on potential health risks for the construction workers and other

employees on site during construction are associated with drinking water quality.

The project would ensure safe potable water supply to the workers on site.

Construction site will be provided with a readily available first aid kit including an

adequate supply of sterilized dressing materials and appliances. Suitable transport to

take injured or sick person to the nearest hospital will be immediately provided.

The project will ensure the safe working of all workers. Workers will be provided

with safety gadgets and enforce to wear it during the construction work. This will

include protective foot wear, helmets and gloves to all workers employed for the

work on mixing, engaged in welding works; earplugs to workers exposed to loud

noise; safety belt to the labors working at higher platforms and face masks to avoid

dust.

The project will strictly follow the statutory child labor act. The project will also

ensure that no paint containing lead or lead products is used except in the form of

paste or readymade paint. Facemasks will be provided for use to the workers when

paint is applied in the form of spray. Adequate safety measures will be ensured for

workers during handling of materials at site.

The project will comply with all regulation regarding safe scaffolding, ladders,

working platforms, gangway, stairwells, excavations and safe means of entry and

exit.

The project will take adequate precautions to prevent danger from electrical

equipment’s. No material will be so stacked or placed to cause danger or

inconvenience to any person or the public.

All machines to be used in the construction will conform to the relevant Indian

Standard Code, it will be free from patent defect and will be kept in good working

condition, will be regularly inspected and properly maintained as per IS provision

Page 157: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 138

To maintain hygienic conditions in the site during construction phase, suitable toilet

facilities will be provided for workers separately. Also sewage generated during

construction phase will be treated in septic tank and soak pit to avoid impact on

ground water.

Work spots will be maintained clean and provided with optimum lighting.

x. Energy Saving Measures

Power savings methods are adopted as per energy conservation:

Use of loss transformers – total losses will be 1.19% of the rating of the transformers

Temperature sensors with visible temperature indicators in the switch boards

Check metering at various locations to check the power consumption and power loss

if any.

Suitable rating and size cables selection to limit the total power distribution losses

less than 1%

Solar water heater for pre – heating water required for bathing and cooking.

Use of high efficiency hybrid chillers (water and air cooled) and variable speed

drivers.

xi. DEVELOPMENT OF GREEN BELT

Green belt is plantation of trees for reducing the pollution as they absorb both gaseous and

particulate pollutant, thus removing them from atmosphere. Green plants form a surface

capable of absorbing air pollutants and forming sinks for pollutants. It balances the

ecological environment, prevents soil erosion, improves the aesthetic value of local

environment and provides possible habitats for birds and animals, thus creating hospitable

nature in urban areas. Greenbelts in and around urban areas have probably not saved any

lives, but they are important nonetheless to the ecological health of any given region. The

various plants and trees in greenbelts serve as organic sponges for various forms of

pollution, and as storehouses of carbon dioxide to help offset global warming.

a) Horticulture

While making choice of plant species for cultivation in green belts, weightage has to be

given to the natural factor of bio-climate. It is also presumed that the selected plants will be

grown as per normal horticultural practice.

A standard horticultural practice involves planting of saplings in proper dimensions for

smaller trees and shrubs. The pits are then filled with earth, sand, silt and manure in pre-

Page 158: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 139

determined proportions. The growing plants are cared for the first three years under

favorable conditions of climate and drainage. Hence it is safe to assume that trees and

bushes grown as green belt components in areas under human control will have overcome

the limitations imposed by soil characters to a great extent. Limitations imposed by climatic

conditions on the other hand cannot be overcome and hence will have to be taken into

account while selecting species for plantation in different bio-climatic conditions.

b) Plantation along Roadsides

Automobiles may be considered as ground level, mobile sources of pollution of both types-

gaseous as well as particulate. Components of green belts on road sides hence should be

both absorbers of gases as well as of dust particles, including even lead particulates. Choice

of plants for roadside plantations may be for containment of pollution and for formation of a

screen between traffic and roadside residences. This choice of plants should include shrubs

of height 1- 1.5 m and tree of 3-5 m height. The intermixing of trees and shrubs should be

such that the foliage area density in vertical is almost uniform. Since safety of traffic is a

major consideration, shrubs in roads will have to be short enough to be below the eye level

of motorists.

c) Plants for Green Belt Development

All tolerant plants are not necessarily good for green belts e.g. Xerophytes with sunken

stomata can withstand pollution by avoidance but are poor absorbers of pollutants due to

low gaseous exchange capacity. Therefore selection of plants is very important in green belt

development for effective removal of suspended particulate matter and for absorption of

gases. The Landscape Diagram of the proposed project will be planned after the allotments

of industries.

8.5 BUDGETARY PROVISION

Environmental monitoring and other mitigation measures as proposed in the above sections

shall be implemented by the Project Proponent during the construction and operation

period. The operational cost comes to around 38.5 Lakhs. The detailed budget provisions are

presented in Table 8.1.

Page 159: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ENVIRONMENTAL MANAGAEMENT PLAN

Page 140

Table ‎8.1: EMP &Environmental Management Cost

S.

No. Description of Item

Capital Cost(in Lakhs)

Operational Cost in

lakhs per annum

1 Construction of STP 120 10

2 Air Quality mitigation measure 20 1.5

3 Greenbelt Development 30 2

4 Energy Conservation measures 20 3

5 Solid Waste Management 15 3

6 Water conservation measures 100 3

7 Environmental monitoring --- 15

Total 305 38.5

Page 160: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL CORPORATE ENVIRONMENTAL RESPONSIBILITY

Page 141

9. ADDITIONAL CORPORATE ENVIRONMENTAL RESPONSIBILITY

9.1 INTRODUCTION

Karnataka Industrial Areas Development Board (KIADB) is a wholly owned infrastructure

agency of Government of Karnataka, set up under Karnataka Industrial Areas Development

Act of 1966.

This Board functions as per statutory provisions, rules and regulations enacted there under.

The Board comprises of senior government officers in their ex-officio capacities. The Board

of members meet regularly to take decisions and monitor the functions. KIADB holds pride

in being the first government organisation in Karnataka to obtain ISO 9001 certification in

the year 1997.

Now the KIADB is following ISO 9001:2000 module covering its functions of Land

Acquisition, Development and Allotment functions in Bangalore Urban and Rural districts.

Figure 9.1: Organisation Chart

Page 161: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL CORPORATE ENVIRONMENTAL RESPONSIBILITY

Page 142

9.2 AIMS AND OBJECTIVES:

Promote rapid and orderly development of industries in the state.

Assist in implementation of policies of Government within the purview of KIAD Act.

Facilitate in establishing infrastructure projects.

Function on “No Profit – No Loss” basis.

9.3 FUNCTIONS:

Acquire land and form industrial areas in the state.

Provide basic infrastructure in the industrial areas.

Acquire land for Single Unit Complexes.

Acquire land for Government agencies for their schemes and infrastructure project

9.4 KIADB - As a Premier Industrial Area Developer

KIADB has also acquired lands to cater the specific needs of individual industrial units (Single

Unit Complexes). The Board also acquires land for infrastructure projects of the

Government. We promote projects of public importance in joint venture with organizations

of international repute.

The vision of KIADB and world class infrastructure has made investors all over the world

take notice of Karnataka as the premier destination for their startups and ventures.

Till date, KIADB has formed 132 industrial areas spread all over the State, and acquired land

for nearly 400 Single Unit Complexes ensuring balanced industrial development in all

regions with well thought of infrastructures and unique features.

KIADB has formed industrial areas in all the districts of the State. So far it has formed

132 small and big industrial areas spread over the State covering about 40,000 acres.

KIADB has also provided land to about 400 standalone major industries (Single Unit

Complexes).

This apart, KIADB has envisaged several innovative projects like Agro -Tech Parks, Apparel

Parks, Food Parks, Auto Parks, Hardware Park, Bio-Tech Park, EPIPs, Sector Specific SEZs,

Growth Centers etc.

Page 162: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

ADDITIONAL CORPORATE ENVIRONMENTAL RESPONSIBILITY

Page 143

KIADB has so far developed 132 industrial areas in 28 districts of the State. A typical

industrial area developed by the Board will have following infrastructure facilities:

Approach roads and internal roads with storm water drains

Power supply and street lighting

Water supply

CETP/STP

Technical Training Centers and R&D centers

Common Facilities Centers to accommodate Banks, Post Offices, Telephone

Exchanges, Dispensaries and Canteens, among others

Power Sub-Stations

Hotels & Hospitals

Housing tenements to provide housing facility to the labour force working in the

industrial units.

Page 163: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

SUMMARY & CONCLUSION

Page 144

10. SUMMARY & CONCLUSION

10.1 INTRODUCTION

Karnataka Industrial Areas Development Board (KIADB) has proposed to develop 844.23

acres plot area of Avverahalli Industrial Area at Dobaspet 4th Phase In the villages

Yedehalli, Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, Avverahalli,

K.G.Srinivasapura, Billanakote, Nelamangala Taluk, Bangalore Rural District, Karnataka.

10.2 ENVIRONMENTAL SETTING OF THE SITE

The proposed site of highlights and salient features is given below in Table 10.1.

Table ‎10.1: Site Salient Features

Selection criteria Details

Elevation above Mean Sea Level 900 m

Climatic Conditions Max. Temp. 34.0o C

Min. Temp. 15.0o C

Average Rainfall: 859.6 mm

Land availability 360.57 Hectares (891.25 Acres)

Nearest Highway 341.65Hectares (844.23 Acres)

Nearest Railway station NH 4 adjacent to Eastern side, SH 3 adjacent to Western side

Nearest airport Dobaspet -1.3 Km (N)

Nearest Town / City Bangalore Airport- 44.0 Km (E)

Topography Nelamangala – 15.0 Km

Bengaluru – 35.0 Km

Archaeologically important places Plain

National parks/ Wildlife Sanctuaries Nil within 15km radius

Water Bodies/Rivers Lekkanahalli Kere

Kuluvanahalli Kere

Devara Kere

Muddalinganahalli kere

Thyamagondluamami kere

Tavare kere

1.6 Km (E)

2.4 Km (SE)

3.3 Km (W)

5.5 Km (NE)

4.5 Km (E)

5.6 Km (E)

Reserved/ Forests Nil within 15km radius

Page 164: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

SUMMARY & CONCLUSION

Page 145

Seismicity The study area falls under seismic zone-II

Defense Installations Nil in 10 km radius

10.3 SITE CONNECTIVITY

The proposed site is well connected by the roads, rail & waterways and the details of the

site connectivity is shown in below Table 10.2.

Table ‎10.2: Details of the site connectivity

Location Dobaspet

Nearest Railway Station Dobaspet -1.3 Km

Nearest City Bus Stop Dobaspet

Major roads NH 4 and SH 3

Nearest Airport Bangalore Airport- 44 Kms

Nearest Sea Port Mangalore 340 kms

10.4 PROJECT SITE AREA

Land use breakup of the proposed is given in below Table 10.3.

Table ‎10.3: Land use Breakup of the proposed project

S.No Description Acres % of Land Use

1 Industries 416.65 49.35

2 Commercial 24.54 2.91

3 Amenity 19.03 2.25

4 Utility 23.89 2.83

5 Residential 43.24 5.12

6 Park 77.97 9.24

7 Buffer 183.96 9.95

8 Truck Parking 41.38 4.90

9 Road 113.57 13.45

Total Area 844.23 100

The proposed industrial area will include following infrastructure facilities:

Industrial Plots STP & CETP

Approach roads Power Sub-Stations

Page 165: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

SUMMARY & CONCLUSION

Page 146

Internal roads with storm water drains Solid Waste Incinerator

Power supply and street lighting Rain Water Harvesting System

Water supply network Public utilities

Parking/Buffer zone area. Green Belt Development

Commercial Residential

10.5 WATER REQUIREMENT OF THE SITE

The estimated water demand during the construction phase is 250 KLD (approx.), 90 KLD for

labors and 160 KLD for construction activities and water demand during the operation phase

is 11.5 MLD. During construction phase the water required will be sourced from tanker

supply and the water for the operation phase is drawn from Hemavathi river for project

needs. A letter to this effect and the acknowledge received from KIADB. Water Balance for

the proposed project is given in Figure 10.1.

Figure ‎10.1: water balance flow sheet

Page 166: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

SUMMARY & CONCLUSION

Page 147

10.6 WASTEWATER GENERATION

Quantity of sewage generated during the construction phase will be 81 KLD. Sewage during

construction phase will be treated in smaller size/packaged (portable type) Sewage

Treatment Plant (STP) which will be based on Submerged Aerobic Fixed Film Reactor (SAFF).

During operation phase sewage generated will be treated in the Sewage Treatment Plant

(STP) planned in 4.7 Ac provided for STP. The estimated Sewage generations during

operation phase, 2.16 MLD. The treated water shall be reused in toilet flushing, gardening

etc. and the wastewater generated from the industries is 7 MLD, which is treated in their

respective Effluent Treatment Plants (ETP) on the bases of advance and zero discharge

concept. The treated water is reuse for industries like cooling, heat exchangers, boilers,

cleaning equipment’s etc

10.7 SOLID WASTE GENERATION

The quantities of waste likely to be generated from the industrial and non-industrial phases

have been estimated on the basis of population and land use characteristics. Table 10.4

presents the estimated solid waste quantities from the proposed project.

Table ‎10.4: Estimated Solid Waste Quantity from Avverahalli Industrial Area

S. No

Solid Waste Bio- Degradable,

in Kg/day

Recyclable, in Kg/day

Non- biodegradable,

in Kg/day

Total waste from different phases,

in Kg/day

1. Industrial Waste

340 91 325 756

2. Municipal Waste

1,199 320 1,146 2,665

3. STP Sludge 300 300

Total Solid Waste, in Kg/day

1,839 411 1,471 3,721

10.8 POWER REQUIREMENT

The power requirement for the proposed development is 63.3 KVA and 10.6 Ac provided for

Sub Station. The source of power will be from KIADB.

Page 167: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

SUMMARY & CONCLUSION

Page 148

10.9 BASELINE STUDY

Baseline Environmental Studies covering a 10 km radial distance from the project site have

been conducted for a period of three months from September 2013 to December2013 to

determine the existing status of various Environmental attributes viz., climatic and

atmospheric conditions, Air, Water, Noise, Soil, Hydro geological, Land use pattern,

Ecological and Socio-Economical environment, prior to setting up of the proposed project.

This study would help to undertake corrective mitigation measures for protection of the

environment on account of any change deviation of attributes due to activities of the

proposed project.

Air Environment- The ambient air quality monitoring was carried out at ten AAQM

locations, with a frequency of twice a week continuously for three months, to assess

the existing sub-regional air quality status in winter season. PM10, PM2.5, SO2 and NOx

were monitored on 24-hourly basis to enable the comparison with ambient air

quality standards prescribed by the Central Pollution Control Board.

PM10 – A maximum value of 63.4µg/m3 was observed at Near Pemannahali (AAQ3).

A minimum of 48.4µg/m3 was observed at Veersagara (AAQ7).The 24 hours

applicable limit for industrial/residential/rural areas is 100µg/m3, the sampled

locations are within the prescribed limit.

PM2.5 – The maximum value of 30.7µg/m3 was observed at Near Pemannahali

(AAQ3). A minimum of 22.1µg/m3 was observed at Veersagara (AAQ7).The 24 hours

applicable limit is 60µg/m3 for industrial/residential/rural areas, the sampled

locations are within the prescribed limit.

SO2 - The maximum value of 7.1µg/m3 was observed at Near Hasahallli (AAQ2). A

minimum of 5.4µg/m3 was observed at Veersagara(AAQ7). The 24 hours applicable

limit is 80µg/m3 for industrial/residential/rural areas, the sampled locations are

within the prescribed limit.

NOX - The maximum value of 17.3µg/m3 was observed at Hasahallli (AAQ2). A

minimum of 12.2µg/m3 was observed at Veersagara (AAQ7). The 24 hours applicable

limit is 80µg/m3 for industrial/residential/rural areas, the sampled locations are

within the prescribed limit.

Water Environment- Water samples were collected from seven sampling locations.

These samples were collected as grab samples and were analyzed for various

Page 168: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

SUMMARY & CONCLUSION

Page 149

parameters. The analysis results indicate that the ground water & surface water

standards are within desirable limits.

Noise Environment- The noise monitoring has been conducted at six locations in the

study area.

Day Time Noise Level - Noise levels during day time were found to be in the range

47.3 – 53.8 dB (A). The maximum noise level was observed to be 53.2 dB (A) at

Thyamagondulu (N4) and a minimum of 51.5 dB (A) was observed at Shivaganga

(N5). The monitored locations during the Day time are under the prescribed limit.

Night Time Noise Levels - Noise levels observed to fall in the range 41.4- 43.9 dB (A)

during the night time. Maximum noise level of 43.7 dB (A) was observed at

Thyamagondulu (N4) and a minimum of 41.6 dB (A) at Shivaganga (N5). The

monitored locations during the night time are under the prescribed limit.

The Noise Level data in the monitored area near project site is below the prescribed limit.

Soil Environment- It has been observed that the pH of the soil ranges from 6.72 -

7.54 indicating that the soil is ideal for plant growth. The nitrogen values are in the

range of 9.6 -16.4 mg/kg and the potassium values range between 98 -194 mg/kg,

which indicate that the soils have moderate quantities of potassium. The soil from

the study area shows moderately fertility.

10.10 ENVIRONMENTAL MANAGEMENT SYSTEM AND ENVIRONMENTAL MONITORING

PLAN

The Environmental Monitoring Programme is a vital process in successfully carrying out the

Environment Management Plan (EMP) for any construction project. Based on project

description, Environmental Baseline Data and Environmental Impacts, the Environmental

Management Plans are suggested of the following:

Institutional set up for EMP Implementation

Construction Safety and Occupational Health Management

Rain Water Harvesting

Solid waste Management

Hazardous waste Management

Green Belt Development & Management

Disaster Management Plan

Page 169: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

SUMMARY & CONCLUSION

Page 150

Risk and Emergency Preparedness Plan

Energy Management

10.11 ENVIRONMENTAL MONITORING PROGRAM

Table ‎10.5: Environmental Monitoring Program

S. No Particulars Monitoring

Frequency Duration of Sampling

Important Monitoring

Parameters

1 Ambient Air Quality Monitoring

A

Project site Once in a 3 Months 24 hr continuously

except CO

PM10, PM2.5, SO2, NO

x &

CO

2 Stack Monitoring

A DG Set – Stack Once in a 3 Months 30 min SO2,

NOx, SPM, CO, CO2,

Temperature, Flow rate

& Velocity of the gas

3 Ambient Noise Level

A Near DG set Once in a 3 Months 8 hr continuous with

1 hr interval

Noise level in dB(A)

4 Ground/Drinking Water Quality Monitoring

A Ground Water – at

project site

Once in 3 Months Grab Sampling Parameters specified

under IS:10500, 1993

5 Effluent Quality Monitoring

A ETP Inlet Once in a Month Grab Sampling Physical, Chemical &

Biological Parameters

specified under

IS:2490:1982

B ETP Outlet

6 Soil Quality

A At the

green belt

area

Once in a year Samples were

collected from three

different depths viz.,

30cm, 60cm, and

100cm below the

surface

Parameter for soil

quality: pH, texture,

electrical conductivity,

organic matter, nitrogen,

phosphate, sodium,

calcium, potassium and

Magnesium.

Page 170: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

SUMMARY & CONCLUSION

Page 151

10.12 CONCLUSION

Based on the environmental assessment, all possible environment aspects have been

adequately assessed and necessary control measures have been formulated to meet with

statutory requirements, in the preparation of the EIA-EMP. The proposed project has

positive impacts on the socio-economic environment of the study area. The unit will provide

direct and indirect employment for Technical, Skilled and unskilled personnel to the nearby

villages. Thus implementing this project will not have any significant negative impacts. Thus,

the proposed project is a welcome development and may be accorded environmental

clearance.

Page 171: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DISCLOSURE OF CONSULTANTS

Page 152

11. DISCLOSURE OF CONSULTANTS

11.1 ABC TECHNO LABS INDIA PRIVATE LIMITED

ABC Techno Labs India Private Limited an ISO 9001, ISO 14001 & OHSAS 18001 Certified

Company & leading Environmental Engineering & Consultancy Company. We are the first

firm to be accredited by NABET (National Accreditation Board for Education and Training),

Quality Council of India, as an EIA Consultant. We are equipped with in-house, spacious

laboratory, accredited by NABL (National Accreditation Board for Testing & Calibration

Laboratories), Department of Science & Technology, Government of India.

Since establishment our focus is on sustainable development of Industry and Environment

based on sound engineering practices, innovation, quality, R&D and most important is

satisfying customers need. The company has successfully completed more than 100’s

projects of variety of industries, in the field of pollution control. We are also dealing in the

projects of waste minimization and cleaner production technology. Our team of technocrats

and scientists are well experienced to deal with the Designing, Manufacturing, Fabrication,

Installation and Commissioning of Effluent/Wastewater Treatment Plants, Sewage

Treatment Plants, Combined Treatment Plants.

We are having a well experienced team of Scientists & Engineers who are looking after our

well-equipped analytical laboratory with a facility including analysis of physical, chemical

and biological parameters as per the requirements of the State Pollution Control Board and

our clients.

11.2 OUR SERVICES

i. ENVIRONMENTAL SERVICES

Environmental Impact Assessment (EIA)

Environmental Management Plan (EMP)

Social Impact Assessment (SIA)

Environmental Baseline data collection for Air, Meteorology, Noise, Water, Soil,

Ecology, Socio-Economic and Demography etc;

Environmental Monitoring

Socio Economic Studies

Page 172: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DISCLOSURE OF CONSULTANTS

Page 153

Resettlement & Rehabilitation Plan

Ecological & Human Health Risk Assessment Studies

Ecological Impact Assessment

Environmental Management Framework

Solid Waste Management

Hazardous Waste Management

Internship & Training

ii. TURNKEY PROJECTS

Water Treatment Plants

Sewage Treatment Plant

Recycling & Water Conservation Systems

Zero Discharge System

Other Services

Operation & Maintenance of Water & Waste Water Plants

Water & Waste Water Treatment Chemicals

Pilot Plant studies

Feasibility studies & preparation of budgetary estimates

iii. LABORATORY DIVISION

Chemical Testing

Environmental Testing

Microbiological Testing

Food Testing

iv. METALLURGICAL TESTING

Mechanical Test

Chemical Testing

Corrosion Testing

v. SECTORS WE SERVE

Mining of Minerals including Opencast/Underground mining

Thermal Power Plants

Mineral Beneficiation including Pelletisation

Metallurgical Industries ( Ferrous & Non Ferrous)

Page 173: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DISCLOSURE OF CONSULTANTS

Page 154

Chlor-alkali Industry

Textile- cotton & Man-made fiber

Coke Oven Plants/ Waste Heat Recovery

Synthetic Organic Chemical Industries

Sugar, Distilleries and Cogeneration

Integrated Paint Industries

Common Municipal Solid waste Management facility

Industrial Estates/ Parks/Complexes/Special Economic Zones

Common Effluent Treatment Plants

Building & Construction Projects,

Townships & Area Development Projects

The accreditation details of ABC TECHNO LABS INDIA PRIVATE LIMITED are given in

Annexure VI.

11.3 STUDY TEAM

ABC Techno Lab India Private Limited carried out this EIA. The multidisciplinary team

included expertise in Environmental Impact Assessment, Air pollution & Control measures,

Noise Control measures, Ecology and bio-diversity, Land use, Geology, Environmental

Chemistry and Socio-Economic planner.

The team members were:

Table ‎11.1: Study Team

Name Role

Dr. R.K.Jayaseelan EIA Coordinator – Team Leader

Functional area Expert – Land Use and Hydrology, ground water & water conservation

Dr. MuthiahMariappan Project Planning, implementation, Report review and validation. Functional area Expert – Solid waste & Hazardous Management

Dr. G. Sundar Senior Environmental Manager & Project Coordinator

Dr. N. Sukumaran Functional area Expert – Ecology & Bio-diversity

Mr. Vivek Mariappan Functional area Expert – Meteorology, Air Quality Modeling & Prediction

Page 174: DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT - Dobaspet 4th Phase Draft Eia... · DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Avverahalli Dobaspet Industrial Area 4th Phase in

DISCLOSURE OF CONSULTANTS

Page 155

Mrs. Geetha Shreeneevasakan Functional area Expert - Socio-Economic Expert

R. Rajendran Functional area Expert – Air pollution control and Noise

Mr. Senthil kumar Functional area Expert – Risk Hazards

Mr. Mohammed Haroon Siyech Project Engineer - Report of Analysis

Mr. K S Vishnu Teja Project Engineer - Report of Analysis

Ms. Sandhya Project Engineer – Documentation

Mr. Robson Chinnadurai Senior Chemist- Environmental Monitoring

Ms. L. Vidhya Devi Analyst & Environmental Chemist

Ms. VetriSelvi Analyst & Environmental Chemist

Ms. K. Narmatha Analyst & Environmental Chemist

Mr. ShafeerBabu Field Technician & Environmental Chemist

Mr. Y. Venkateshwaralu Field Technician

Mr. Sathish Field Technician

Mr. Suresh Anand Field Technician