draft environmental study report for the phase 2...
TRANSCRIPT
FINAL ENVIRONMENTAL STUDY REPORT FOR THE PHASE 2 CONNECTING 17 REMOTE FIRST NATION COMMUNITIES PROJECT SECTION 3.0: PROJECT DESCRIPTION
November 2018 Report No. 18102677 GAL-005-REP-V1
APPENDIX 3.11B Access Roads Refinement Analysis
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1 i
Table of Contents
3.11B-1.0 INTRODUCTION .............................................................................................................................................. 1
3.11B-2.0 METHOD FOR THE ANALYSIS OF ACCESS PLAN REFINEMENTS ........................................................... 1
3.11B-3.0 RESULTS ........................................................................................................................................................ 2
3.11B-3.1 Red Lake Subsystem ..................................................................................................................................... 3
3.11B-3.1.1 Red Lake Transmission Line Extension ...................................................................................................... 3
3.11B-3.1.2 Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station (Segment Q-
T) ................................................................................................................................................................ 5
3.11B-3.1.3 Connection to Poplar Hill First Nation (Segment S-R) .............................................................................. 10
3.11B-3.1.4 Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station
(Segment T-Z) .......................................................................................................................................... 15
3.11B-3.1.5 Connection to Deer Lake First Nation (Segment U-T) .............................................................................. 20
3.11B-3.1.6 Connection to McDowell Lake First Nation (Segment V-X) ...................................................................... 24
3.11B-3.1.7 Connection to Keewaywin First Nation (Segment V-Y) ............................................................................. 28
3.11B-3.1.8 Connection to North Spirit Lake First Nation (Segment Z-V) .................................................................... 33
3.11B-3.1.9 Connection to Sandy Lake First Nation (Segment Z-W) ........................................................................... 37
3.11B-3.2 Pickle Lake Subsystem ................................................................................................................................ 43
3.11B-3.2.1 Connection to Ebane/Pipestone Junction Switching Station (Segment B-C) ............................................ 43
3.11B-3.2.2 Connection to North Caribou Lake First Nation (Segment C-D) ............................................................... 45
3.11B-3.2.3 Connection to Kingfisher Lake First Nation (Segment C-J) ...................................................................... 50
3.11B-3.2.4 Connection to Muskrat Dam First Nation (Segment D-E) ......................................................................... 55
3.11B-3.2.5 Connection to Bearskin Lake First Nation (Segment E-F) ........................................................................ 60
3.11B-3.2.6 Connection to Sachigo Lake First Nation (Segment E-G) ......................................................................... 64
3.11B-3.2.7 Connection to Wunnumin Lake First Nation (Segment J-I) ....................................................................... 69
3.11B-3.2.8 Connection to Wawakapewin First Nation (Segment J-K) ........................................................................ 73
3.11B-3.2.9 Connection to Kasabonika First Nation (Segment K-L) ............................................................................ 77
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1 ii
3.11B-3.2.10 Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation (Segment K-M-N) ............... 81
REFERENCES 86
TABLES
Table 3.11B-2: Access Plan Refinement Analysis – Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station (Segment Q-T) .................................................................................................. 5
Table 3.11B-3: Access Plan Refinement Analysis – Connection to Poplar Hill First Nation (Segment S-R) ...................... 10
Table 3.11B-4: Access Plan Refinement Analysis – Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station (Segment T-Z) ................................................................................................ 15
Table 3.11B-5: Access Plan Refinement Analysis – Connection to Deer Lake First Nation (Segment U-T) ...................... 20
Table 3.11B-6: Access Plan Refinement Analysis – Connection to McDowell Lake First Nation (Segment V-X) .............. 24
Table 3.11B-7: Access Plan Refinement Analysis – Connection to Keewaywin First Nation (Segment V-Y) .................... 28
Table 3.11B-8: Access Plan Refinement Analysis – Connection to North Spirit Lake First Nation (Segment Z-V) ............ 33
Table 3.11B-9: Access Plan Refinement Analysis – Connection to Sandy Lake First Nation (Segment Z-W) ................... 37
Table 3.11B-10: Access Plan Refinement Analysis – Connection to Ebane/Pipestone Junction Switching Station (Segment B-C) ........................................................................................................................................................... 44
Table 3.11B-11: Access Plan Refinement Analysis – Connection to North Caribou Lake First Nation (Segment C-D) ....... 46
Table 3.11B-12: Access Plan Refinement Analysis – Connection to Kingfisher Lake First Nation (Segment C-J) .............. 50
Table 3.11B-13: Access Plan Refinement Analysis – Connection to Muskrat Dam First Nation (Segment D-E) ................. 55
Table 3.11B-14: Access Plan Refinement Analysis – Connection to Bearskin Lake First Nation (Segment E-F) ................ 59
Table 3.11B-15: Access Plan Refinement Analysis – Connection to Sachigo First Nation (Segment E-G) ......................... 64
Table 3.11B-16: Access Plan Refinement Analysis – Connection to Wunnumin Lake First Nation ..................................... 69
Table 3.11B-17: Access Plan Refinement Analysis – Connection to Wawakapewin First Nation (Segment J-K) ............... 73
Table 3.11B-18: Access Plan Refinement Analysis – Connection to Kasabonika First Nation (Segment K-L) .................... 77
Table 3.11B-19: Access Plan Refinement Analysis – Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation (Segment K-M-N) ........................................................................................................................... 82
ANNEXES
ANNEX A Metric Tables
ANNEX B Revised Access Plan Figures
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-1
3.11B-1.0 INTRODUCTION
The access plan assessed in the Draft Environmental Study Report (ESR) described the development of new
access roads and upgrades to existing access roads to facilitate the construction and operation and maintenance
phases of the Project. It was predicted in the Draft ESR that up to 70% of all access roads defined for the Project
would be permanent. Section 3.11 Project Refinements from Draft ESR discusses improvements made to the
Project since the Draft ESR was issued, including refinements to the access roads (i.e., access plan) across the
Project. As part of the refinements, Wataynikaneyap is proposing a revised access plan for the Project that only
includes a permanent footprint. This permanent footprint has been minimized by emphasizing access within the
Project’s transmission line right-of-way (ROW; i.e., 40-m-wide corridor alignment), and by maximizing the
utilization of existing winter and all-season access roads in their current condition. The revised access plan also
better aligns with existing winter roads that are visible on imagery recently acquired via LiDAR and the most current
information shared on plans for First Nation community roads. The revised access plan also avoids wet areas that
are better understood through the analysis of recently acquired LiDAR information. Off-ROW access is still defined
as part of the refined access plan but only when on-ROW access is inhibited by large waterbodies and where the
installation of water crossings is not practical, or where physical obstacles such as steep slopes exist. There are
also some sections of the ROW where access is only possible during winter time, unless helicopters are used for
access.
This appendix provides an analysis of the changes to the access plan for the Project, compared with the access
plan assessed in the Draft ESR. This comparative analysis uses the metrics defined for consideration of corridor
alternatives described in Appendix 3.10A, which correlates the Ministry of Natural Resources and Forestry (MNRF)
Class EA screening criteria with the environmental criteria defined for this environmental assessment (see
Section 4.0 of the Final ESR), including consideration of results of engagement with First Nation communities,
land use planning, and available baseline environmental spatial data.
3.11B-2.0 METHOD FOR THE ANALYSIS OF ACCESS PLAN REFINEMENTS
The objectives of this section is to discuss the rationale for the refinement of the access plan for the Project defined
in the Draft ESR, provide an analysis of environmental metrics for the areas of the refined Project access plan
compared with an equivalent section of the Project access plan identified in the Draft ESR, and characterize any
differences in the potential environmental effects of the change compared with the assessment provided in the
Draft ESR.
The following five key factors were considered in the analysis of the corridors:
natural environment;
land use and resource management;
socio-economic and cultural;
Aboriginal interest; and
technical, including constructability and relative cost which is derived primarily from technical constraints.
Cost was not considered as the sole or overriding justification.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-2
The metrics that were considered in the analysis are presented in Annex A. The reported metrics represent publicly
available datasets and datasets collected for the Project relevant to the study areas for the analysis of the access
plan refinements, consistent with the assessment of corridor alternatives presented in Section 3.10 and
Appendix 3.10A of the Final ESR.
Mitigation measures summarized for the Project in Section 9.0 Environmental and Social Management Plan of the
Final ESR are applicable in all work areas for the Project.
3.11B-3.0 RESULTS
This section presents the comparative analysis for each segment of the Project for which the access plan has
been revised with an equivalent section of the access plan assessed in the Draft ESR. Specifically, this includes
the following areas:
Red Lake Subsystem
Red Lake Transmission Line Extension
Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station
(Segment Q-T)
Connection to Poplar Hill First Nation (Segment S-R)
Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station
(Segment T-Z)
Connection to Deer Lake First Nation (Segment U-T)
Connection to McDowell Lake First Nation (Segment V-X)
Connection to Keewaywin First Nation (Segment V-Y)
Connection to North Spirit Lake First Nation (Segment Z-V)
Connection to Sandy Lake First Nation (Segment Z-W)
Pickle Lake Subsystem
Connection to Ebane/Pipestone Junction Switching Station (Segment B-C)
Connection to North Caribou Lake First Nation (Segment C-D)
Connection to Kingfisher Lake First Nation (Segment C-J)
Connection to Muskrat Dam First Nation (Segment D-E)
Connection to Bearskin Lake First Nation (Segment E-F)
Connection to Sachigo Lake First Nation (Segment E-G)
Connection to Wunnumin Lake First Nation (Segment J-I)
Connection to Wawakapewin First Nation (Segment J-K)
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-3
Connection to Kasabonika First Nation (Segment K-L)
Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation (Segment K-M-N)
The revised access plan for the Project is shown in Annex B (Figures 3.11B-1 to 3.11B-93). The metric tables
used to support the access plan refinement analysis are presented in Annex A. The access plan footprints were
evaluated by comparing the presence of features within or where applicable, adjacent to the access roads, and
by highlighting discernable differences between them.
The modified access plan for the Project may be further refined during detailed design in an effort to avoid sensitive
features, through use existing access roads, to the extent practical. Efforts will be made to reduce environmental
effects associated with the preferred access plan for the Project, and Wataynikaneyap with their contractor(s) will
commit to implementing mitigation measures identified in the ESR and adhere to all permits and approvals required
for the Project.
3.11B-3.1 Red Lake Subsystem
3.11B-3.1.1 Red Lake Transmission Line Extension
Access roads had not been identified specifically for the Red Lake transmission line extension as part of the Draft
ESR. As part of the Final ESR, an access plan has been defined for Red Lake transmission line extension which
consists of an additional 15.7 km of proposed new access roads (see Annex B, Figure 3.11B-1 and 3.11B-2).
However, this access plan includes primarily an access road within the 40-m-wide ROW (i.e., 15.2 km of the
access road is on-ROW). Only 0.5 km of the access plan is comprised of proposed new access roads outside of
the ROW.
The high-level baseline characterization for the access road footprint for the Red Lake transmission line extension
is presented in Table 3.11B-1. Since an access road footprint had not been defined as part of the Draft ESR for
the Red Lake transmission line extension, a metrics comparison between access road footprints cannot be
presented for this segment of the Project. Instead, Table 3.11B-1 only presents metric values for the access road
footprint defined for the Final ESR. The full set of analysis metrics that were considered for the high-level baseline
characterization of the access plan for the Red Lake transmission line extension are presented in Annex A. No
bald eagle nests, potential bat hibernacula features, or potential wolverine den habitat were observed in the access
road footprint during field surveys in 2016 and 2017.
Since most of the access plan for the Red Lake transmission line extension identified in the Final ESR includes a
proposed on-ROW access road, it is important to note that the any disturbance effects associated with the on-
ROW access road are bounded by the disturbance effects that were assessed in the Draft ESR for the 40-m-wide
ROW for this segment of the Project. Although the ROW alignment has been refined slightly in areas along this
segment of the Project for the Final ESR, this ROW re-alignment was minimal. The proposed off-ROW access
roads for this segment of the Project span over a short distance (i.e., 0.5 km) and are located adjacent to or near
the ROW. It is predicted that the disturbance effects predicted for the ROW will also bound the potential
disturbance effects associated with the off-ROW access roads. On and off-ROW access roads required for the
Project in this area connects to a network of existing access roads including the Nungesser Road, opening new
access in some areas.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-4
The potential effects of the Project that includes the revised access plan for the Red Lake transmission line
extension is predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration
of implementation of the of the commitments and monitoring in Section 12.0 and the environmental and social
management plan in Section 9.0. Therefore, Wataynikaneyap will be implementing the revised access plan
discussed herein for the Red Lake transmission line extension.
Table 3.11B-1: Access Plan Refinement Analysis – Red Lake Transmission Line Extension
Key Factors
Access Plan Refinements
Red Lake Transmission Line Extension Refined Access Plan
Technical Size
Access roads are 15.7 km in length:
▪ 15.2 km of access roads within the ROW
▪ 0.5 km of access roads outside of the ROW
The access road footprint has an area of 9.4 ha.
Existing Infrastructure
The access road footprint crosses one existing road.
Existing roads cross the access road footprint once.
The access road footprint crosses one other linear corridor.
Natural Environment Wetlands(a)
Area of mapped wetlands in the access road footprint is 0.7 ha.
Waterbodies and Watercourses(b)
The access road footprint crosses seven watercourses.
Vegetation(c)
The access road footprint crosses:
▪ 6.7 ha of natural landcover (terrestrial);
▪ 0.2 ha of anthropogenic disturbance; and
▪ 0.0 ha of natural disturbance
Wildlife
The access road footprint crosses 5.6 ha of potential suitable moose habitat.
The access road footprint crosses 6.2 ha of potential suitable bald eagle habitat.
The access road footprint crosses 5.5 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 0.2 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 6.1 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 0.1 ha of mapped potential habitat supporting provincially tracked wildlife species.
Threatened and endangered species or their Habitat (Caribou (Boreal population))
There is 9.4 ha of Category 3 habitat in the access road footprint.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 7.0 ha of potential suitable habitat for wolverine.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 5.3 ha of potential suitable maternity roosting habitat for little brown myotis.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-5
Table 3.11B-1: Access Plan Refinement Analysis – Red Lake Transmission Line Extension
Key Factors
Access Plan Refinements
Red Lake Transmission Line Extension Refined Access Plan
Land Use, Resource Management
Land Designations
There are 10 non-OTN trails crossed by the access road footprint for a total length of 192.1 m.
The access road footprint crosses seven mining claims for a total area of 3.0 ha
Socio-Economic Tourism and Recreation
The access road footprint crosses two bait harvesting areas (BHA) for a total area of 9.4 ha.
Archaeology and Cultural Heritage
The access road footprint crosses 0.2 ha of land with archaeological potential.
Aboriginal considerations
Traditional Land and Resource Use (TLRU)
No TLRU features classified as “avoid” were identified within the access road footprint based on currently available data.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
3.11B-3.1.2 Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station (Segment Q-T)
This segment of the Project extends from the Pikangikum Transformer Station to the Deer Lake Junction Switching
Station. The revised access plan for this segment of the Project is shown in Annex B (Figures 3.11B-8 to 3.11B-
11 and Figures 3.11B-14 to 3.11B-17). The high-level baseline characterization for the revised access road
footprint for the connection from Pikangikum Transformer Station to the Deer Lake Junction Switching Station
(Segment Q-T) is presented in Table 3.11B-2. Changes made in the access plan for this segment of the Project
between the Draft and Final ESR includes changes to the on-ROW access due to realignments made to the 40-
m-wide ROW, and also include defining additional off-ROW access around wet areas or obstacles such as steep
slopes or large waterbodies where the installation of crossings is not practical. The metrics for the access road
footprint initially identified for this segment in the Draft ESR, the metrics for the access road footprint proposed in
the Final ESR, and a comparison between the two are also presented in Table 3.11B-2. The full set of analysis
metrics that were considered are presented in Annex A. Generally, habitat for wildlife criteria is similarly abundant
and distributed along both access road footprints. No bald eagle nests, potential bat hibernacula features, or
potential wolverine den habitat were observed along either of the access road footprints during field surveys in
2016 and 2017.
It should be noted that much of this Project segment follows an approved forestry road under the Whitefeather
Forest Management Plan. Should any portion of that forestry road be constructed, Project access will be re-
evaluated so that it is in proximity to the forestry road. North of the boundary of the Whitefeather Forest, there are
no existing roads in the vicinity of the Project, so more areas of off-ROW access around wet areas and obstacles
are identified.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-6
Table 3.11B-2: Access Plan Refinement Analysis – Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station (Segment Q-T)
Key Factors
Road Refinements
Access Plan Comparison
Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station
(Segment Q-T)
QT1 (Refined Access Plan)
QT2 (Preliminary Access Plan)
Technical Size
Access roads are 131.7 km in length.
The access road footprint has an area of 78.9 ha.
Size
Access roads are 122.4 km in length.
The access road footprint has an area of 73.4 ha.
QT1 is longer and has a larger area compared to QT2.
Technical (cont'd) Existing Infrastructure
The access road footprint crosses one existing road.
Existing roads cross the access road footprint twice.
Existing Infrastructure
The access road footprint crosses one existing road.
Existing roads cross the access road footprint 14 times.
The access road footprint for QT1 is crossed fewer times by existing roads than QT2.
Natural Environment Wetlands(a)
The access road footprint crosses 6.6 ha of mapped wetlands.
Wetlands(a)
The access road footprint crosses 9.5 ha of mapped wetlands.
No discernable difference between QT1 and QT2, although QT1 intersects a slightly smaller area of mapped wetlands than QT2.
Waterbodies and Watercourses(b)
The access road footprint crosses 46 mapped watercourses.
The access road footprint crosses five mapped waterbodies(c) for an area of 0.1 ha.
Waterbodies and Watercourses(b)
The access road footprint crosses 47 mapped watercourses.
The access road footprint crosses five mapped waterbodies(c) for an area of 0.3 ha.
No discernable difference between QT1 and QT2
Areas of Natural and Scientific Interest (ANSI)
The access road footprint crosses 3.7 ha of Candidate ANSI.
Areas of Natural and Scientific Interest (ANSI)
The access road footprint crosses 2.5 ha of Candidate ANSI.
No discernable difference between QT1 and QT2; although QT1 crosses a slightly larger area of candidate ANSI.
Vegetation(d)
The access road footprint crosses:
▪ 67.2 ha of natural landcover (terrestrial);
▪ 1.2 ha of anthropogenic disturbance; and
▪ 10.3 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 62.9 ha of natural landcover (terrestrial);
▪ 1.2 ha of anthropogenic disturbance; and
▪ 8.8 ha of natural disturbance.
No discernable difference between QT1 and QT2 but QT1 intersects slightly more natural landcover (terrestrial) than QT2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-7
Table 3.11B-2: Access Plan Refinement Analysis – Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station (Segment Q-T)
Key Factors
Road Refinements
Access Plan Comparison
Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station
(Segment Q-T)
QT1 (Refined Access Plan)
QT2 (Preliminary Access Plan)
Natural Environment (cont'd)
Wildlife Habitat
The access road footprint crosses 39.3 ha of potential suitable moose habitat.
The access road footprint crosses 0.2 ha of potential suitable horned grebe habitat.
The access road footprint crosses 35.7 ha of potential suitable bald eagle habitat.
The access road footprint crosses 23.8 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 30.5 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 34.6 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 2.4 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife
The access road footprint crosses 37.8 ha of potential suitable moose habitat.
The access road footprint crosses 0.4 ha of potential suitable horned grebe habitat.
The access road footprint crosses 30.0 ha of potential suitable bald eagle habitat.
The access road footprint crosses 26.0 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 27.3 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 30.7 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 2.0 ha of mapped potential habitat supporting provincially tracked wildlife species.
No discernable difference between QT1 and QT2; however, Q1 crosses slightly larger areas of potential suitable habitat for moose, bald eagle, common nighthawk, and olive-sided flycatcher, and mapped potential habitat supporting provincially tracked wildlife species. Q1 crosses slightly smaller areas of potential suitable habitat for horned grebe and Canada warbler.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-8
Table 3.11B-2: Access Plan Refinement Analysis – Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station (Segment Q-T)
Key Factors
Road Refinements
Access Plan Comparison
Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station
(Segment Q-T)
QT1 (Refined Access Plan)
QT2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 4.8 ha of mapped Category 1 (nursery) habitat.
The access road footprint crosses 31.9 ha of mapped Category 2 habitat.
The access road footprint crosses 42.2 ha of mapped Category 3 habitat.
The access road footprint crosses 4.2 ha of caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 5.2 ha of mapped caribou (Boreal population) travel corridors (Fall – November).
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 4.6 ha of mapped Category 1 (nursery) habitat.
The access road footprint crosses 34.8 ha of mapped Category 2 habitat.
The access road footprint crosses 34.0 ha of mapped Category 3 habitat.
The access road footprint crosses 4.2 ha of mapped caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 5.2 ha of mapped caribou (Boreal population) travel corridors (Fall – November).
No discernable difference between QT1 and QT2, although QT2 crosses a smaller area of mapped Category 1 and 3 habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 77.5 ha of suitable wolverine habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 71.7 ha of suitable wolverine habitat.
No discernable difference between QT1 and QT2.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 9.0 ha of suitable maternity roosting habitat for little brown myotis
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 7.0 ha of suitable maternity roosting habitat for little brown myotis
No discernable difference between QT1 and QT2, although QT2 crosses a slightly smaller area of suitable maternity roosting habitat compared to QT1.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-9
Table 3.11B-2: Access Plan Refinement Analysis – Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station (Segment Q-T)
Key Factors
Road Refinements
Access Plan Comparison
Connection from Pikangikum Transformer Station to Deer Lake Junction Switching Station
(Segment Q-T)
QT1 (Refined Access Plan)
QT2 (Preliminary Access Plan)
Land Use, Resource Management
Land Designations
The access road footprint crosses two non-OTN trails for a total length of 12.6 m.
Land Designations
The access road footprint crosses two non-OTN trails for a total length of 13.5 m.
No discernable difference between QT1 and QT2.
Socio-Economic Tourism and Recreation
The access road footprint crosses one BHA for a total area of 9.5 ha.
Tourism and Recreation
The access road footprint crosses one BHA for a total area of 13.6 ha
No discernable difference between QT1 and QT2.
Archaeology and Cultural Heritage
The access road footprint crosses 0.7 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint crosses 0.6 ha of land with archaeological potential.
No discernable difference between QT1 and QT2.
Aboriginal considerations
Traditional Land and Resource Use (TLRU)
No TLRU features classified as “avoid” were identified within the access road footprint based on currently available data.
Traditional Land and Resource Use (TLRU)
No TLRU features classified as “avoid” were identified within the access road footprint based on currently available data.
No discernable difference between QT1 and QT2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-3, the refined access plan proposed in the Final ESR (QT1) presents a similar key factor
metrics when compared with the preliminary access plan (QT2) presented in the Draft ESR; however, the access
road footprint for QT1 is larger than the footprint for QT2. The increased size in the access road footprint for QT1
has a slight increase in the key factor metrics presented in relation to QT2 (e.g., potential suitable habitat for some
wildlife criteria, as noted above), but not enough for the differences in metrics to be discernable. The revised
access road footprint for QT1 mainly includes on-ROW access similar to QT2; however, the 40-m-wide ROW
alignment for QT1 has been shifted in areas as design of the Project has evolved since the Draft ESR. This re-
alignment of the ROW is minimal and located within the limits of work assessed for the ROW in the Draft ESR. In
the Draft ESR, upgrades to existing access roads were defined as part of the primary access plan for QT2, where
the Project is located in proximity to existing roads. For QT1 this is no longer the case with primary access along
the ROW instead. Where off-ROW access is defined to connect to existing roads or to avoid wet areas or
obstacles, the access road segments are adjacent to or in close proximity to the ROW, so the potential effects
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-10
associated with disturbance off-ROW are predicted to be bound by the disturbance effects predicted for the ROW
itself.
Overall, the changes in the access road footprint has resulted in SR1 to cross a smaller area of mapped wetlands,
potential suitable habitat for horned grebe and Canada warbler, and mapped Category 2 habitat for caribou (Boreal
population). The changes also result in SR1 to cross a slightly larger area of candidate ANSI, natural landcover
(terrestrial), potential suitable habitat for moose, bald eagle, common nighthawk, and olive-sided flycatcher,
mapped potential habitat supporting provincially tracked wildlife species, and mapped Category 1 and 3 habitat
for caribou (Boreal population).
The potential effects of the Project that include the revised access footprint are predicted to reach the same
conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration of implementation of the commitments
and monitoring in Section 12.0 and the environmental and social management plan in Section 9.0. Therefore,
Wataynikaneyap will be implementing the QT1 access road footprint for the connection from the Pikangikum
Transformer Station to the Deer Lake Junction Switching Station (Segment Q-T).
3.11B-3.1.3 Connection to Poplar Hill First Nation (Segment S-R)
This segment of the Project extends from the Poplar Hill Junction Switching Station to the Transformer Station in
Poplar Hill First Nation. The revised access plan for this segment of the Project is shown in Annex B
(Figure 3.11B-11 to 3.11B-13). The high-level baseline characterization for the revised access road footprint for
the connection to Poplar Hill First Nation (Segment S-R) is presented in Table 3.11B-3. Changes made in the
access plan for this segment of the Project between the Draft and Final ESR includes changes to the on-ROW
access due to realignments made to the 40-m-wide ROW, and include defining additional off-ROW access around
wet areas or obstacles such as steep slopes or large waterbodies where the installation of crossings is not
practical. The metrics for the access road footprint initially identified for this segment in the Draft ESR, the metrics
for the access road footprint proposed in the Final ESR, and a comparison between the two are also presented in
Table 3.11B-3. The full set of analysis metrics that were considered are presented in Annex A. Generally, habitat
for wildlife criteria is similarly abundant and distributed along both access road footprints. No bald eagle nests or
potential wolverine den habitat features were observed along either of the access road footprints during field
surveys in 2016 and 2017.
It should be noted that much of this Project segment follows an approved forestry road under the Whitefeather
Forest Management Plan. Should any portion of that forestry road be constructed, Project access will be re-
evaluated so that it is in proximity to the forestry road.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-11
Table 3.11B-3: Access Plan Refinement Analysis – Connection to Poplar Hill First Nation (Segment S-R)
Key Factors
Road Refinements
Access Plan Comparison Connection to Poplar Hill First Nation
(Segment S-R)
SR1 (Refined Access Plan)
SR2 (Preliminary Access Plan)
Technical Size
Access roads are 41.7 km in length. Of this length, 8 km include new off-ROW access. The rest is on-ROW access.
The access road footprint has an area of 25.1 ha.
Size
Access roads are 32.4 km in length. All the access roads are on-ROW.
The access road footprint has an area of 19.5 ha.
SR1 has longer access roads and the access road footprint is larger than SR2.
Technical (cont'd) Existing Infrastructure
The access road footprint crosses two existing roads.
Existing roads cross the access road footprint once.
Existing Infrastructure
The access road footprint does not cross any existing roads.
SR2 does not cross any existing roads.
Natural Environment
Wetlands(a)
The access road footprint crosses 2.9 ha of mapped wetlands.
Wetlands(a)
The access road footprint crosses 2.3 ha of mapped wetlands.
No discernable difference between SR1 and SR2
Waterbodies and Watercourses(b)
The access road footprint crosses 11 mapped watercourses.
Waterbodies and Watercourses(b)
The access road footprint crosses 10 mapped watercourses.
No discernable difference between SR1 and SR2
Areas of Natural and Scientific Interest (ANSI)
The access road footprint crosses 5.3 ha of Candidate ANSI.
Areas of Natural and Scientific Interest (ANSI)
The access road footprint crosses 4.2 ha of Candidate ANSI.
No discernable difference between SR1 and SR2 although SR1 intersects slightly more area of ANSIs than SR2.
Vegetation(c)
The access road footprint crosses:
▪ 22.3 ha of natural landcover (terrestrial);
▪ 0.4 ha of anthropogenic disturbance; and
▪ 1.9 ha of natural disturbance.
Vegetation(c)
The access road footprint crosses:
▪ 17.6 ha of natural landcover (terrestrial);
▪ 0.3 ha of anthropogenic disturbance; and
▪ 1.5 ha of natural disturbance.
No discernable difference between SR1 and SR2 although SR1 intersects slightly more natural landcover (terrestrial) than SR2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-12
Table 3.11B-3: Access Plan Refinement Analysis – Connection to Poplar Hill First Nation (Segment S-R)
Key Factors
Road Refinements
Access Plan Comparison Connection to Poplar Hill First Nation
(Segment S-R)
SR1 (Refined Access Plan)
SR2 (Preliminary Access Plan)
Natural Environment (cont'd)
Wildlife
The access road footprint crosses 13.8 ha of potential suitable moose habitat.
The access road footprint crosses 13.7 ha of potential suitable bald eagle habitat.
The access road footprint crosses 9.5 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 8.7 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 13.7 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 2.4 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife
The access road footprint crosses 10.6 ha of potential suitable moose habitat.
The access road footprint crosses 10.9 ha of potential suitable bald eagle habitat.
The access road footprint crosses 7.1 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 7.3 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 10.7 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 1.3 ha of mapped potential habitat supporting provincially tracked wildlife species.
No discernable difference between SR1 and SR2, although SR2 crosses a slightly smaller area of potential suitable habitat for moose, bald eagle, Canada warbler, common nighthawk, olive-sided flycatcher and mapped habitat supporting provincially tracked wildlife species.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-13
Table 3.11B-3: Access Plan Refinement Analysis – Connection to Poplar Hill First Nation (Segment S-R)
Key Factors
Road Refinements
Access Plan Comparison Connection to Poplar Hill First Nation
(Segment S-R)
SR1 (Refined Access Plan)
SR2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 15.0 ha of mapped Category 2 habitat.
The access road footprint crosses 10.4 ha of mapped Category 3 habitat.
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 10.9 ha of mapped Category 2 habitat.
The access road footprint crosses 8.5 ha of mapped Category 3 habitat.
No discernable difference between SR1 and SR2, although SR1 intersects slightly more mapped Category 2 and 3 habitat than SR2.
Threatened and endangered species or their habitat (Wolverine)
The access road footprint crosses 24.1 ha of suitable wolverine habitat.
Threatened and endangered species or their habitat (Wolverine)
The access road footprint crosses 19.1 ha of suitable wolverine habitat.
No discernable difference between SR1 and SR2, although SR2 crosses a slightly smaller area of suitable wolverine habitat.
Threatened and endangered species or their habitat (Little brown myotis)
The access road footprint crosses 6.8 ha of suitable little brown myotis maternity roosting habitat.
The access road footprint is in close proximity to one potential bat hibernacula feature that was observed during the 2016 and 2017 field programs.
Threatened and endangered species or their habitat (Little brown myotis)
The access road footprint crosses 5.4 ha of suitable little brown myotis maternity roosting habitat.
No potential bat hibernacula features were observed within the access road footprint.
No discernable difference between SR1 and SR2, although SR1 is in close proximity to one potential bat hibernacula feature and crosses a slightly larger area of potential suitable maternity roosting habitat.
Socio-Economic Archaeology and Cultural Heritage
The access road footprint crosses 0.4 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint crosses 0.4 ha of land with archaeological potential.
No discernable difference between PH1 and PH2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-14
Table 3.11B-3: Access Plan Refinement Analysis – Connection to Poplar Hill First Nation (Segment S-R)
Key Factors
Road Refinements
Access Plan Comparison Connection to Poplar Hill First Nation
(Segment S-R)
SR1 (Refined Access Plan)
SR2 (Preliminary Access Plan)
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
Poplar Hill
▪ One trapline and a natural feature (rapids) are crossed by the access road footprint.
▪ A fish spawning area and a trapping area are crossed by the access road footprint.
Traditional Land and Resource Use (TLRU)
Poplar Hill
▪ One trapline and a natural feature (rapids) are crossed by the access road footprint.
▪ A fish spawning area and a trapping area are crossed by the access road footprint.
No discernable difference between SR1 and SR2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-11, the refined access plan proposed in the Final ESR (SR1) presents a slight increase
in the key factor metrics presented when compared with the preliminary access plan (SR2) presented in the Draft
ESR. This is attributed to the larger access road footprint for SR1, which has increased in comparison to SR2 due
to the additional off-ROW access defined for SR1. Although the metrics increased slightly across all key factors
for SR1, the difference in metrics is not considered to be discernable in relation to SR2. However, it is noted that
SR1 is in close proximity to a potential bat hibernacula feature, specifically an access road defined off-ROW.
The revised access road footprint for SR1 mainly includes on-ROW access similar to SR2; however, the 40-m-
wide ROW alignment for SR1 has been shifted in areas as design of the Project has evolved since the Draft ESR.
This re-alignment of the ROW is minimal and primarily located within the limits of work assessed for the ROW in
the Draft ESR. The additional off-ROW access that has been identified for SR1 is adjacent to or in close proximity
to the ROW, so the potential effects associated with disturbance off-ROW are predicted to be bound by the
disturbance effects predicted for the ROW itself. Overall, the changes in the access road footprint has resulted in
SR1 to cross a slightly larger area of candidate ANSI, natural landcover (terrestrial), potential suitable and mapped
habitat for all wildlife criteria, and mapped potential habitat supporting provincially tracked wildlife species.
Although there are slight increases in key factor metrics, the potential effects of the Project that include the revised
access footprint are predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in
consideration of implementation of the commitments and monitoring in Section 12.0 and the environmental and
social management plan in Section 9.0. This includes applying mitigation in relation to bat hibernacula (e.g., timing
restrictions for Project construction). Therefore, Wataynikaneyap will be implementing the SR1 access road
footprint for the connection to Poplar Hill First Nation (Segment S-R).
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-15
3.11B-3.1.4 Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station (Segment T-Z)
This segment of the Project extends from the Deer Lake Junction Switching Station to the Sandy Lake Junction
Switching Station. The revised access plan for this segment of the Project is shown in Annex B (Figures 3.11B-8
to 3.11B-11, Figure 3.11B-17, Figure 3.11B-19 and Figure 3.11B-20). The high-level baseline characterization for
the revised access road footprint for the connection to the Sandy Lake Junction Switching Station (Segment T-Z)
is presented in Table 3.11B-4. Changes made in the access plan between the Draft and Final ESR includes
primary access within the 40-m-wide ROW rather than via nearby existing winter roads, and off-ROW spur roads
to connect the on-ROW access to the existing winter road. In some locations, additional off-ROW access includes
diversions around wet areas or obstacles such as steep slopes or large waterbodies where the installation of
crossings is not practical also. The metrics for the access road footprint initially identified for this segment in the
Draft ESR, the metrics for the access road footprint proposed in the Final ESR, and a comparison between the
two are also presented in Table 3.11B-4. The full set of analysis metrics that were considered are presented in
Annex A. Generally, habitat for wildlife criteria is similarly abundant and distributed along both access road
footprints. No bald eagle nests, potential wolverine den habitat or potential bat hibernacula features were observed
along either of the access road footprints during field surveys in 2016 and 2017.
Table 3.11B-4: Access Plan Refinement Analysis – Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station (Segment T-Z)
Key Factors
Road Refinements
Access Plan Comparison
Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station
(Segment T-Z)
TZ1 (Refined Access Plan)
TZ2 (Preliminary Access Plan)
Technical Size
Access roads are 32.3 km in length.
The access road footprint has an area of 19.4 ha.
Size
Access roads are 28 km in length.
The access road footprint has an area of 16.8 ha.
TZ2 has shorter access roads and covers a smaller area.
Existing Infrastructure
The access road crosses one existing road.
Existing roads cross the access road footprint once.
There is one other linear corridor that crosses the access road footprint.
Existing Infrastructure
The access road crosses four existing roads.
Existing roads cross the access road footprint twice.
There is one other linear corridor that crosses the access road footprint.
No discernable difference between TZ1 and TZ2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-16
Table 3.11B-4: Access Plan Refinement Analysis – Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station (Segment T-Z)
Key Factors
Road Refinements
Access Plan Comparison
Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station
(Segment T-Z)
TZ1 (Refined Access Plan)
TZ2 (Preliminary Access Plan)
Natural Environment Wetlands(a)
The access road footprint crosses 0.3 ha of mapped wetlands.
Wetlands(a)
The access road footprint crosses 3.7 ha of mapped wetlands.
TZ1 crosses a smaller area of mapped wetlands.
Waterbodies and Watercourses(b)
The access road footprint crosses five mapped watercourses.
The access road footprint does not cross any mapped waterbodies(c).
Waterbodies and Watercourses(b)
The access road footprint crosses seven mapped watercourses.
The access road footprint crosses two mapped waterbodies(c) for an area of 0.1 ha.
No discernable difference between TZ1 and TZ2.
Vegetation(d)
The access road footprint crosses:
▪ 18.9 ha of natural landcover (terrestrial);
▪ 0.0 ha of anthropogenic disturbance; and
▪ 0.0 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 16.3 ha of natural landcover (terrestrial);
▪ 0.0 ha of anthropogenic disturbance; and
▪ 0.4 ha of natural disturbance.
No discernable difference between TZ1 and TZ2, although TZ2 crosses a slightly smaller area of natural landcover (terrestrial).
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-17
Table 3.11B-4: Access Plan Refinement Analysis – Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station (Segment T-Z)
Key Factors
Road Refinements
Access Plan Comparison
Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station
(Segment T-Z)
TZ1 (Refined Access Plan)
TZ2 (Preliminary Access Plan)
Natural Environment (cont'd)
Wildlife
The access road footprint crosses 9.8 ha of potential suitable moose habitat.
The access road footprint does not habitat potential suitable for horned grebe.
The access road footprint crosses 4.3 ha of potential suitable bald eagle habitat.
The access road footprint crosses 6.9 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 5.3 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 4.6 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 15.0 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife
The access road footprint crosses 7.7 ha of potential suitable moose habitat.
The access road footprint crosses 0.1 ha of potential suitable horned grebe habitat.
The access road footprint crosses 3.1 ha of potential suitable bald eagle habitat.
The access road footprint crosses 7.1 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 3.6 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 0.6 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 12.1 ha of mapped potential habitat supporting provincially tracked wildlife species
No discernable difference between TZ1 and TZ2, although TZ2 crosses a slightly smaller area of suitable habitat for moose, bald eagle, common nighthawk, olive-sided flycatcher and potential habitat supporting provincially tracked wildlife species.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-18
Table 3.11B-4: Access Plan Refinement Analysis – Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station (Segment T-Z)
Key Factors
Road Refinements
Access Plan Comparison
Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station
(Segment T-Z)
TZ1 (Refined Access Plan)
TZ2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 0.8 ha of mapped Category 2 habitat.
The access road footprint crosses 18.7 ha of mapped Category 3 habitat.
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 1.0 ha of mapped Category 2 habitat.
The access road footprint crosses 15.6 ha of mapped Category 3 habitat.
No discernable difference between TZ1 and TZ2, although TZ2 crosses a slightly smaller area of Category 3 habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 19.4 ha of potential suitable wolverine habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 16.7 ha of potential suitable wolverine habitat.
No discernable difference between TZ1 and TZ2, although TZ2 crosses a slightly smaller area of suitable wolverine habitat.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 0.7 ha of potential suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 0.6 ha of potential suitable maternity roosting habitat for little brown myotis.
No discernable difference between TZ1 and TZ2.
Land Use, Resource Management
Land Designations
The access road footprint crosses one non-OTN trail for a total length of 10.0 m.
Land Designations
The access road footprint crosses one non-OTN trail for a total length of 10.0 m.
No discernable difference between TZ1 and TZ2.
Socio-Economic Archaeology and Cultural Heritage
The access road footprint crosses 0.4 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint crosses 1.2 ha of land with archaeological potential.
No discernable difference between TZ1 and TZ2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-19
Table 3.11B-4: Access Plan Refinement Analysis – Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station (Segment T-Z)
Key Factors
Road Refinements
Access Plan Comparison
Connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station
(Segment T-Z)
TZ1 (Refined Access Plan)
TZ2 (Preliminary Access Plan)
Aboriginal considerations
Traditional Land and Resource Use (TLRU)
Deer Lake First Nation
▪ The access road footprint crosses one trapline, a fish spawning area and moose hunting area is crossed by the access footprint.
Sandy Lake First Nation
▪ A community hunting area is crossed by the access road footprint.
North Spirit Lake First Nation
▪ A summer trail and trapping area is crossed by the access road footprint.
Traditional Land and Resource Use (TLRU)
Deer Lake First Nation
▪ The access road footprint crosses one trapline, a fish spawning area and moose hunting area is crossed by the access footprint.
Sandy Lake First Nation
▪ A community hunting area is crossed by the access road footprint.
North Spirit Lake First Nation
▪ A summer trail and trapping area is crossed by the access road footprint.
No discernable difference between TZ1 and TZ2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-4, the refined access plan proposed in the Final ESR (TZ1) presents a minor increase
in some key factor metrics presented when compared with the preliminary access plan (TZ2) presented in the
Draft ESR. It should be noted that the 40-m-wide transmission line alignment of this segment of the Project
generally runs parallel to the existing winter road between Deer Lake First Nation and North Spirit Lake First Nation
and parallel to the existing winter road to Sandy Lake First Nation. Access along these existing winter roads was
included in the preliminary access plan presented in the Draft ESR; it was therefore captured in the access footprint
of TZ2, explaining the relatively similar technical key factor metrics presented in Table 3.11B-4. Overall, the
changes in the access road footprint has resulted in TZ1 to cross less area of mapped wetlands, fewer
watercourses, and slightly less area with archaeological potential. TZ1 crosses a slightly larger area of natural
landcover (terrestrial), mapped potential habitat supporting provincially tracked wildlife species, potential suitable
habitat for most wildlife species, and mapped Category 3 habitat for caribou (Boreal population). However, since
most of the access plan for TZ1 includes on-ROW access, the disturbance required for TZ1 will overlap with the
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-20
disturbance required for the ROW and therefore decrease the size of the overall Project footprint for this segment
of the Project.
Although there are increases in some key factor metrics, the potential effects of the Project that include the revised
access footprint are predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in
consideration of implementation of the commitments and monitoring in Section 12.0 and the environmental and
social management plan in Section 9.0. Therefore, Wataynikaneyap will be implementing the TZ1 access road
footprint for the connection from Deer Lake Junction Switching Station to Sandy Lake Junction Switching Station
(Segment T-Z).
3.11B-3.1.5 Connection to Deer Lake First Nation (Segment U-T)
This segment of the Project extends from the Deer Lake Junction Switching Station to the Transformer Station in
Deer Lake First Nation. The revised access plan for this segment of the Project is shown in Annex B (Figures
3.11B-17 and 3.11B-18). The high-level baseline characterization for the revised access road footprint for the
connection to the Deer Lake First Nation Transformer Station (Segment U-T) is presented in Table 3.11B-5.
Changes made in the access plan between the Draft and Final ESR includes access within the 40-m-wide ROW
rather than via nearby existing winter roads as well as defining additional off-ROW access spurs between the
ROW and the existing winter road, and around wet areas or obstacles such as steep slopes or large waterbodies
where the installation of crossings is not practical. The metrics for the access road footprint initially identified for
this segment in the Draft ESR, the metrics for the access road footprint proposed in the Final ESR, and a
comparison between the two are also presented in Table 3.11B-5. The full set of analysis metrics that were
considered are presented in Annex A. Generally, habitat for wildlife criteria is similarly abundant and distributed
along both access road footprints. No bald eagle nests or potential bat hibernacula features were observed along
either of the access road footprints during field surveys in 2016 and 2017.
Table 3.11B-5: Access Plan Refinement Analysis – Connection to Deer Lake First Nation (Segment U-T)
Key Factors
Road Refinements
Access Plan Comparison Connection to Deer Lake First Nation
(Segment U-T)
UT1 (Refined Access Plan)
UT2 (Preliminary Access Plan)
Technical Size
Access roads are 25 km in length.
The access road footprint has an area of 15.0 ha.
Size
Access roads are 24.6 km in length.
The access road footprint has an area of 14.8 ha.
No discernable difference between UT1 and UT2
Existing Infrastructure
The access road crosses four existing roads.
Existing roads cross the access road footprint twice.
The access road crosses one other linear corridor.
Existing Infrastructure
The access road crosses four existing roads.
Existing roads cross the access road footprint twice.
The access road crosses two other linear corridor.
No discernable difference between UT1 and UT2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-21
Table 3.11B-5: Access Plan Refinement Analysis – Connection to Deer Lake First Nation (Segment U-T)
Key Factors
Road Refinements
Access Plan Comparison Connection to Deer Lake First Nation
(Segment U-T)
UT1 (Refined Access Plan)
UT2 (Preliminary Access Plan)
Natural Environment Wetlands(a)
The access road footprint crosses 0.3 ha of mapped wetlands.
Wetlands(a)
The access road footprint crosses 0.7 ha of mapped wetlands.
No discernable difference between UT1 and UT2.
Natural Environment (cont’d)
Waterbodies and Watercourses(b)
The access road footprint crosses four mapped watercourses.
The access road footprint does not cross any waterbodies(c).
Waterbodies and Watercourses(b)
The access road footprint crosses six mapped watercourses.
The access road footprint crosses four mapped waterbodies(c) for an area of 0.3 ha.
UT1 intersects fewer watercourses and waterbodies than UT2.
Vegetation(d)
The access road footprint crosses:
▪ 11.5 ha of natural landcover (terrestrial);
▪ 0.2 ha of anthropogenic disturbance; and
▪ 3.2 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 10.0 ha of natural landcover (terrestrial);
▪ 0.1 ha of anthropogenic disturbance; and
▪ 4.1 ha of natural
disturbance.
No discernable difference between UT1 and UT2.
Wildlife
The access road footprint crosses 4.8 ha of potential suitable moose habitat.
The access road footprint crosses 0.1 ha of potential suitable horned grebe habitat.
The access road footprint crosses 5.0 ha of potential suitable bald eagle habitat.
The access road footprint crosses 3.9 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 6.3 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 5.3 ha of potential suitable olive-sided flycatcher habitat.
Wildlife
The access road footprint crosses 7.7 ha of potential suitable moose habitat.
The access road footprint crosses 0.4 ha of potential suitable horned grebe habitat.
The access road footprint crosses 4.3 ha of potential suitable bald eagle habitat.
The Projec0.0t footprint crosses 4.8 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 6.3 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 4.9 ha of potential suitable olive-sided flycatcher habitat.
No discernable difference between UT1 and UT2, although UT2 crosses a slightly smaller area of potential suitable habitat for moose, bald eagle and olive-sided flycatcher.
UT1 crosses a slightly smaller area of potential suitable habitat for horned grebe and Canada warbler.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-22
Table 3.11B-5: Access Plan Refinement Analysis – Connection to Deer Lake First Nation (Segment U-T)
Key Factors
Road Refinements
Access Plan Comparison Connection to Deer Lake First Nation
(Segment U-T)
UT1 (Refined Access Plan)
UT2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road crosses 9.6 ha of mapped Category 2 habitat.
The access road footprint crosses 5.3 ha of mapped Category 3 habitat.
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 10.2 ha of mapped Category 2 habitat.
The access road footprint crosses 4.4 ha of mapped Category 3 habitat.
No discernable difference between UT1 and UT2.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 14.7 ha of suitable wolverine habitat.
One area representing potential den habitat was observed in proximity to the access road footprint during 2016 and 2017 field surveys.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 14.1 ha of suitable wolverine habitat.
No areas representing potential den habitat were observed within the access road footprint during 2016 and 2017 field surveys.
No discernable difference between UT1 and UT2. However, UT1 is proximity to an area representing potential den habitat for wolverine.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 0.3 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 0.2 ha of suitable maternity roosting habitat for little brown myotis.
No discernable difference between UT1 and UT2.
Socio-Economic Archaeology and Cultural Heritage
The access road footprint crosses 0.4 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint crosses 1.4 ha of land with archaeological potential.
UT1 crosses a smaller area of land that has archaeological potential compared to UT2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-23
Table 3.11B-5: Access Plan Refinement Analysis – Connection to Deer Lake First Nation (Segment U-T)
Key Factors
Road Refinements
Access Plan Comparison Connection to Deer Lake First Nation
(Segment U-T)
UT1 (Refined Access Plan)
UT2 (Preliminary Access Plan)
Aboriginal considerations
Traditional Land and Resource Use (TLRU)
Deer Lake First Nation
▪ The access footprint crosses two traplines, fish spawning areas, moose hunting and crossing areas and plant harvesting areas.
Traditional Land and Resource Use (TLRU)
Deer Lake First Nation
▪ The access footprint crosses two traplines, fish spawning areas, moose hunting and crossing areas and plant harvesting areas.
No discernable difference between UT1 and UT2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-5, the refined access plan proposed in the Final ESR (UT1) presents very similar key
factor metrics when compared with the preliminary access plan (UT2) presented in the Draft ESR. It should be
noted that the 40-m-wide transmission line alignment of this segment of the Project generally runs parallel to the
existing winter road between the Deer Lake Junction Switching Station and Deer Lake First Nation. This existing
winter road was included in the preliminary access plan presented in the Draft ESR; it was therefore captured in
the access footprint of UT2, explaining the relatively similar technical key factor metrics presented in Table 3.11B-
5. Overall, the changes in the access road footprint has resulted in UT1 to cross less area of mapped wetlands,
fewer watercourses, a smaller area of suitable moose habitat, a smaller area of Category 2 caribou (Boreal
population) habitat and slightly smaller area with archaeological potential. UT1 crosses a slightly larger area of
natural landcover (terrestrial), Category 3 caribou (Boreal population) habitat, and habitat suitable for wolverine.
However, since most of the access plan for UT1 includes on-ROW access, the disturbance required for UT1 will
overlap with the disturbance required for the ROW and therefore decrease the size of the overall Project footprint
for this segment of the Project. Moreover, one area representing potential den habitat for wolverine was observed
in proximity to the access road footprint during 2016 and 2017 field surveys
Although there are increases in some key factor metrics, the potential effects of the Project that include the revised
access footprint are predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in
consideration of implementation of the commitments and monitoring in Section 12.0 and the environmental and
social management plan in Section 9.0. This includes applying mitigation to limit disturbance to active wolverine
dens if active den sites are observed during Project construction. Therefore, Wataynikaneyap will be implementing
the UT1 access road footprint for the connection to Deer Lake First Nation (Segment U-T).
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-24
3.11B-3.1.6 Connection to McDowell Lake First Nation (Segment V-X)
This segment of the Project extends from the North Spirit Lake Transformer Station to the Transformer Station in
McDowell Lake First Nation. The revised access plan for this segment of the Project is shown in Annex B
(Figures 3.1B1-28 to 3.11B-31). The high-level baseline characterization for the revised access road footprint for
the connection to the McDowell Lake First Nation Transformer Station (Segment V-X) is presented in Table 3.11B-
6. The few changes made in the access plan for this segment of the Project between the Draft and Final ESR
includes access within the 40-m-wide ROW as well as defining additional off-ROW access around wet areas or
obstacles such as steep slopes or large waterbodies where the installation of crossings is not practical. The metrics
for the access road footprint initially identified for this segment in the Draft ESR, the metrics for the access road
footprint proposed in the Final ESR, and a comparison between the two are also presented in Table 3.11B-6. The
full set of analysis metrics that were considered are presented in Annex A. Generally, habitat for wildlife criteria is
similarly abundant and distributed along both access road footprints. No bald eagle nests or potential hibernacula
habitat features were observed along either of the access road footprints during field surveys in 2016 and 2017.
Table 3.11B-6: Access Plan Refinement Analysis – Connection to McDowell Lake First Nation (Segment V-X)
Key Factors
Road Refinements
Access Plan Comparison Connection to McDowell Lake First Nation
(Segment V-X)
VX1 (Refined Access Plan)
VX2 (Preliminary Access Plan)
Technical Size
Access roads are 48.8 km in length.
The access road footprint has an area of 29.3 ha.
Size
Access roads are 43.6 km in length.
The access road footprint has an area of 26.2 ha.
No discernable difference between VX1 and VX2.
Existing Infrastructure
There are 5 existing roads that cross the access road footprint.
Existing roads cross the access road footprint 2 times.
Existing Infrastructure
There are 8 existing roads that cross the access road footprint.
Existing roads cross the access road footprint 2 times.
VX1 crosses fewer existing roads than the VX2 assessed in the Draft ESR.
Natural Environment Wetlands(a)
Area of mapped wetlands within the access road footprint is 4.8 ha.
Wetlands(a)
Area of mapped wetlands within the access road footprint is 5.9 ha.
No discernable difference between VX1 and VX2
Waterbodies and Watercourses(b)
The access road footprint crosses 13 mapped watercourses.
The access road footprint crosses one mapped waterbody(c) for an area of 0.0 ha
Waterbodies and Watercourses(b)
The access road footprint crosses 13 mapped watercourses.
The access road footprint crosses one mapped waterbody(c) for an area of 0.0 ha
No discernable difference between VX1 and VX2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-25
Table 3.11B-6: Access Plan Refinement Analysis – Connection to McDowell Lake First Nation (Segment V-X)
Key Factors
Road Refinements
Access Plan Comparison Connection to McDowell Lake First Nation
(Segment V-X)
VX1 (Refined Access Plan)
VX2 (Preliminary Access Plan)
Natural Environment (cont'd)
Areas of Natural and Scientific Interest (ANSI)
The access road footprint 14.0 ha of Candidate ANSI.
Areas of Natural and Scientific Interest (ANSI)
The access road footprint intersects 11.1 ha of Candidate ANSI.
No discernable difference between VX1 and VX2
Vegetation(d)
The access road footprint crosses:
▪ 20.8 ha of natural landcover (terrestrial);
▪ 2.0 ha of anthropogenic disturbance; and
▪ 6.3 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 18.2 ha of natural landcover (terrestrial);
▪ 2.0 ha of anthropogenic disturbance; and
▪ 5.7 ha of natural disturbance.
No discernable difference between VX1 and VX2
Wildlife
The access road footprint crosses 4.8 ha of potential suitable moose habitat
The access road footprint crosses 5.4 ha of potential suitable bald eagle habitat
The access road footprint crosses 7.4 ha of potential suitable Canada warbler habitat
The access road footprint crosses 20.6 ha of potential suitable common nighthawk habitat
The access road footprint crosses 5.9 ha of potential suitable olive-sided flycatcher habitat
Wildlife
The access road footprint crosses 7.7 ha of potential suitable moose habitat
The access road footprint crosses 3.1 ha of potential suitable bald eagle habitat
The access road footprint crosses 8.9 ha of potential suitable Canada warbler habitat
The access road footprint crosses 17.8 ha of potential suitable common nighthawk habitat
The access road footprint crosses 3.2 ha of potential suitable olive-sided flycatcher habitat
VX1 crosses a smaller area of potential suitable habitat for moose.
VX2 crosses a smaller area of potential suitable habitat for bald eagle and olive-sided flycatcher.
No discernable difference in area of potential suitable habitat intersected for Canada warbler and common nighthawk between VX1 and VX2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-26
Table 3.11B-6: Access Plan Refinement Analysis – Connection to McDowell Lake First Nation (Segment V-X)
Key Factors
Road Refinements
Access Plan Comparison Connection to McDowell Lake First Nation
(Segment V-X)
VX1 (Refined Access Plan)
VX2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 2.3 ha of mapped Category 1 (nursery) habitat
The access road footprint crosses 26.4 ha of mapped Category 2 habitat.
The access road footprint crosses 0.7 ha of mapped Category 3 habitat.
The access road footprint crosses 6.0 ha of mapped caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 9.0 ha of mapped caribou (Boreal population) travel corridors (Fall – November)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 2.3 ha of mapped Category 1 (nursery) habitat
The access road footprint crosses 23.4 ha of mapped Category 2 habitat.
The access road footprint crosses 0.4 ha of mapped Category 3 habitat.
The access road footprint crosses 5.7 ha of mapped caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 8.8 ha of mapped caribou (Boreal population) travel corridors (Fall – November)
No discernable difference between VX1 and VX2
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 27.1 ha of potential suitable wolverine habitat.
One area representing potential den habitat was observed within the access road footprint during 2016 and 2017 field surveys.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 23.9 ha of potential suitable wolverine habitat.
One area representing potential den habitat was observed within the access road footprint during 2016 and 2017 field surveys.
No discernable difference between VX1 and VX2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-27
Table 3.11B-6: Access Plan Refinement Analysis – Connection to McDowell Lake First Nation (Segment V-X)
Key Factors
Road Refinements
Access Plan Comparison Connection to McDowell Lake First Nation
(Segment V-X)
VX1 (Refined Access Plan)
VX2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 0.6 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 3.1 ha of suitable maternity roosting habitat for little brown myotis.
VX1 crosses a smaller area of suitable maternity roosting habitat for little brown myotis.
Socio-Economic Archaeology and Cultural Heritage
The access road footprint crosses 0.2 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint crosses 0.2 ha of land with archaeological potential.
No discernable difference between VX1 and VX2
Aboriginal considerations
Traditional Land and Resource Use (TLRU)
McDowell Lake First Nation
▪ The access footprint crosses, one trapline and a fish spawning area.
North Spirit Lake First Nation
▪ The access footprint crosses one trapline a fish spawning area and an area of cultural significance.
Traditional Land and Resource Use (TLRU)
McDowell Lake First
Nation
▪ The access footprint crosses, one trapline and a fish spawning area.
North Spirit Lake First Nation
▪ The access footprint crosses, one trapline a fish spawning area and an area of cultural significance.
No discernable difference between VX1 and VX2
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses.
d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-28
As shown in Table 3.11B-6, the refined access plan proposed in the Final ESR (VX1) presents very similar key
factor metrics when compared with the preliminary access plan (VX2) presented in the Draft ESR. It should be
noted that there are limited existing access roads within this segment of the Project, as primarily new off-ROW
access roads, which would access short (>1 km) sections of the ROW, was proposed in the access plan presented
in the Draft ESR, whereas the access plan proposed for the Final ESR would rely primarily on-ROW access,
explaining the slight increases in some key factor metrics presented in Table 3.11B-6. Overall, the changes in the
access road footprint has resulted in VX1 to cross less area of mapped wetlands, fewer watercourses, and a
smaller area of suitable maternity roosting habitat for little brown myotis. VX2 crosses a slightly smaller area of
suitable habitat for bald eagle, olive-sided flycatcher and wolverine. For all the other metrics, there were minor
variations in the areas crossed by each of the access road footprints, leading to no discernable differences
between the two.
Although there are increases in some key factor metrics, the potential effects of the Project that include the revised
access footprint are predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in
consideration of implementation of the commitments and monitoring in Section 12.0 and the environmental and
social management plan in Section 9.0. This includes applying mitigation to limit disturbance to active wolverine
dens if active den sites are observed during Project construction. Therefore, Wataynikaneyap will be implementing
the VX1 access road footprint for the connection to McDowell Lake First Nation (Segment V-X).
3.11B-3.1.7 Connection to Keewaywin First Nation (Segment V-Y)
This segment of the Project extends from the North Spirit Lake Transformer Station to the Transformer Station in
Keewaywin First Nation. The revised access plan for this segment of the Project is shown in Annex B
(Figure 3.11B-28 and Figures 3.11B-32 to 3.11B-36). The high-level baseline characterization for the revised
access road footprint for the connection to the Keewaywin First Nation Transformer Station (Segment V-Y) is
presented in Table 3.11B-7. Changes made in the access plan for this segment of the Project between the Draft
and Final ESR includes access within the 40-m-wide ROW rather than via nearby existing winter roads/high ground
winter roads. The metrics for the access road footprint initially identified for this segment in the Draft ESR, the
metrics for the access road footprint proposed in the Final ESR, and a comparison between the two are also
presented in Table 3.11B-7. The full set of analysis metrics that were considered are presented in Annex A.
Generally, habitat for wildlife criteria is similarly abundant and distributed along both access road footprints. No
bald eagle nests, potential bat hibernacula features, or potential wolverine den habitat were observed along either
of the access road footprints during field surveys in 2016 and 2017.
Table 3.11B-7: Access Plan Refinement Analysis – Connection to Keewaywin First Nation (Segment V-Y)
Key Factors
Road Refinements
Access Plan Comparison Connection to Keewaywin First Nation
(Segment V-Y)
VY1 (Refined Access Plan)
VY2 (Preliminary Access Plan)
Technical Size
Access roads are 84.0 km in length.
The access road footprint has an area of 50.5 ha.
Size
Access roads are 73.4 km in length.
The access road footprint has an area of 44.1 ha.
VY1 has longer roads and a larger footprint than VY2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-29
Table 3.11B-7: Access Plan Refinement Analysis – Connection to Keewaywin First Nation (Segment V-Y)
Key Factors
Road Refinements
Access Plan Comparison Connection to Keewaywin First Nation
(Segment V-Y)
VY1 (Refined Access Plan)
VY2 (Preliminary Access Plan)
Technical (cont'd) Existing Infrastructure
The access road footprint crosses two existing roads.
Existing roads cross the access road footprint 13 times.
Existing Infrastructure
The access road footprint crosses four existing roads.
Existing roads cross the access road footprint 8 times
Existing roads cross VY1 more times than VY2.
Natural Environment Wetlands(a)
Area of mapped wetlands within the access road footprint is 6.2 ha.
Wetlands(a)
Area of mapped wetlands within the access road footprint is 4.8 ha.
No discernable difference between VY1 and VY2
Waterbodies and Watercourses(b)
The access road footprint crosses 25 mapped watercourses.
The access road footprint crosses one mapped waterbody(c) for an area of 0.0 ha
Waterbodies and Watercourses(b)
The access road footprint crosses 28 mapped watercourses.
The access road footprint crosses one mapped waterbodies(c) for an area of 0.1 ha.
No discernable difference between VY1 and VY 2. However, VY1 crosses slightly fewer watercourses and waterbodies than VY2.
Areas of Natural and Scientific Interest (ANSI)
The access road footprint intersects 19.9 ha of Candidate ANSI.
Areas of Natural and Scientific Interest (ANSI)
The access road footprint intersects 18.6 ha of Candidate ANSI.
No discernable difference between VY1 and VY2
Vegetation(d)
The access road footprint crosses:
▪ 42.7 ha of natural landcover (terrestrial);
▪ 0.2 ha of anthropogenic disturbance;
▪ 4.8 ha of natural disturbance; and
▪ 0.9 ha of mapped occurrences of provincially tracked vegetation species.
Vegetation(d)
The access road footprint crosses:
▪ 38.8 ha of natural landcover (terrestrial);
▪ 0.4 ha of anthropogenic disturbance;
▪ 4.4 ha of natural disturbance; and
▪ 0.0 ha of mapped occurrences of provincially tracked vegetation species
No discernable difference between VY1 and VY2. However, VY1 intersects slightly more natural landcover (terrestrial) than VY2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-30
Table 3.11B-7: Access Plan Refinement Analysis – Connection to Keewaywin First Nation (Segment V-Y)
Key Factors
Road Refinements
Access Plan Comparison Connection to Keewaywin First Nation
(Segment V-Y)
VY1 (Refined Access Plan)
VY2 (Preliminary Access Plan)
Natural Environment (cont'd)
Wildlife
The access road footprint crosses 20.3 ha of potential suitable moose habitat
The access road footprint crosses 0.0 ha of potential suitable horned grebe habitat.
The access road footprint crosses 19.7 ha of potential suitable bald eagle habitat
The access road footprint crosses 10.0 ha of potential suitable Canada warbler habitat
The access road footprint crosses 24.6 ha of potential suitable common nighthawk habitat
The access road footprint crosses 21.2 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 2.8 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife
The access road footprint crosses 16.2 ha of potential suitable moose habitat
The access road footprint crosses 0.1 ha of potential suitable horned grebe habitat.
The access road footprint crosses 15.6 ha of potential suitable bald eagle habitat
The access road footprint crosses 9.8 ha of potential suitable Canada warbler habitat
The access road footprint crosses 23.2 ha of potential suitable common nighthawk habitat
The access road footprint crosses 17.9 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 1.9 ha of mapped potential habitat supporting provincially tracked wildlife species
No discernable difference between VY1 and VY2, although VY2 crosses a smaller area of habitat potential suitable for moose, bald eagle, common nighthawk, olive-sided flycatcher and a smaller area of potential habitat supporting provincially tracked wildlife species.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-31
Table 3.11B-7: Access Plan Refinement Analysis – Connection to Keewaywin First Nation (Segment V-Y)
Key Factors
Road Refinements
Access Plan Comparison Connection to Keewaywin First Nation
(Segment V-Y)
VY1 (Refined Access Plan)
VY2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 36.5 ha of mapped Category 2 habitat.
The access road footprint crosses 14.0 ha of mapped Category 3 habitat
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 33.1 ha of mapped Category 2 habitat
The access road footprint crosses 10.9 ha of mapped Category 3 habitat
No discernable difference between VY1 and VY2, although VY2 crosses less mapped Category 2 and Category 3 caribou (Boreal population) habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 47.5 ha of potential suitable wolverine habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 43.2 ha of potential suitable wolverine habitat.
No discernable difference between VY1 and VY2.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 2.9 ha of potential suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 2.2 ha of potential suitable maternity roosting habitat for little brown myotis.
No discernable difference between VY1 and VY2.
Land Use, Resource Management
Land Designations
The access road footprint crosses two non-OTN trails for a total length of 0.1 km.
Land Designations
The access road footprint does not cross any non-OTN trails.
No discernable difference between VY1 and VY2
Socio-Economic Archaeology and Cultural Heritage
The access road footprint crosses 0.3 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint crosses 0.4 ha of land with archaeological potential.
No discernable difference between VY1 and VY2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-32
Table 3.11B-7: Access Plan Refinement Analysis – Connection to Keewaywin First Nation (Segment V-Y)
Key Factors
Road Refinements
Access Plan Comparison Connection to Keewaywin First Nation
(Segment V-Y)
VY1 (Refined Access Plan)
VY2 (Preliminary Access Plan)
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
Keewaywin First Nation
▪ The access footprint crosses winter and summer trails, gardening areas, moose calving and feeding areas, trapping areas and waterfowl areas.
North Spirit Lake First Nation
▪ The access footprint crosses winter and summer trails, frequently used land use areas, gardening areas, a moose feeding area, and trapping areas.
Traditional Land and Resource Use (TLRU)
Keewaywin First Nation
▪ The access footprint crosses winter and summer trails, gardening areas, moose calving and feeding areas, trapping areas and waterfowl areas.
North Spirit Lake First Nation
▪ The access footprint crosses winter and summer trails, frequently used land use areas, gardening areas, a moose feeding area, and trapping areas.
No discernable difference between VY1 and VY2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses.
d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-7, the refined access plan proposed in the Final ESR (VY1) presents a moderate
increase to key factor metrics when compared with the preliminary access plan (VY2) presented in the Draft ESR.
It should be noted that the 40-m-wide transmission line alignment of this segment of the Project generally runs
within the vicinity of a high-ground winter road development between North Spirit Lake First Nation and
Keewaywin First Nation. Limited existing access roads were identified in the access plan for this segment of the
Project in the Draft ESR, and new off-ROW access roads were proposed instead which would access short (i.e.,
less than 1 km) sections of the ROW. For the Final ESR, the revised access plan would rely primarily on on-ROW
access, which explains the moderate increase in key factor metrics presented in Table 3.11B-7. Table 3.11B-7.
Overall, the changes in the access road footprint has resulted in VY1 to cross a slightly larger area of mapped
wetlands, fewer watercourses, a larger area of natural landcover (terrestrial), and a slightly larger area of potential
suitable habitat for all wildlife criteria. However, since most of the access plan for VY1 includes on-ROW access,
whereas most of the access plan for VY2 included new off-ROW access, the disturbance required for VY1 will
overlap with the disturbance required for the ROW and therefore decrease the size of the overall Project footprint
for this segment of the Project.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-33
Although there are increases in some key factor metrics, the potential effects of the Project that include the revised
access footprint are predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in
consideration of implementation of the commitments and monitoring in Section 12.0 and the environmental and
social management plan in Section 9.0. Therefore, Wataynikaneyap will be implementing the VY1 access road
footprint for the connection to Keewaywin First Nation (Segment V-Y).
3.11B-3.1.8 Connection to North Spirit Lake First Nation (Segment Z-V)
This segment of the Project extends from the Sandy Lake Junction Switching Station to the Transformer Station
in North Spirit Lake First Nation. The revised access plan for this segment of the Project is shown in Annex B
(Figures 3.11B-17, 3.11B-19, 3.11B-20, 3.11B-27 and 3.11B-28). The high-level baseline characterization for the
revised access road footprint for the connection to the North Spirit Lake First Nation Transformer Station (Segment
Z-V) is presented in Table 3.11B-8. Changes made in the access plan for this segment of the Project between the
Draft and Final ESR includes access within the 40-m-wide ROW rather than via nearby existing winter roads, as
well as defining additional off-ROW access around wet areas or obstacles such as steep slopes or large
waterbodies where the installation of crossings is not practical. The metrics for the access road footprint initially
identified for this segment in the Draft ESR, the metrics for the access road footprint proposed in the Final ESR,
and a comparison between the two are also presented in Table 3.11B-8. The full set of analysis metrics that were
considered are presented in Annex A. Generally, habitat for wildlife criteria is similarly abundant and distributed
along both access road footprints. No bald eagle nests, potential bat hibernacula features, or potential wolverine
den habitat were observed along either of the access road footprints during field surveys in 2016 and 2017.
Table 3.11B-8: Access Plan Refinement Analysis – Connection to North Spirit Lake First Nation (Segment Z-V)
Key Factors
Road Refinements
Access Plan Comparison
Connection to North Spirit Lake First Nation (Segment Z-V)
ZV1 (Refined Access Plan)
ZV2 (Preliminary Access Plan)
Technical Size
Access roads are 37.9 km in length.
The access road footprint has an area of 21.0 ha.
Size
Access roads are 22.8 km in length.
The access road footprint has an area of 13.7 ha.
ZV2 is shorter with a smaller access road footprint compared to ZV1.
Existing Infrastructure
The access road footprint crosses one existing road.
Existing roads crosses the access road footprint one time.
The access road footprint crosses one other linear corridor.
Existing Infrastructure
The access road footprint crosses two existing roads.
Existing roads cross the access road footprint five times.
The access road footprint crosses four other linear corridors.
No discernable difference between ZV1 and ZV2.
Natural Environment Wetlands(a)
Mapped area of wetlands in the access road footprint is 2.4 ha.
Wetlands(a)
Area of mapped wetlands in the access road footprint is 4.3 ha.
No discernable difference between ZV1 and ZV2, although ZV1 crosses a smaller area of mapped wetland.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-34
Table 3.11B-8: Access Plan Refinement Analysis – Connection to North Spirit Lake First Nation (Segment Z-V)
Key Factors
Road Refinements
Access Plan Comparison
Connection to North Spirit Lake First Nation (Segment Z-V)
ZV1 (Refined Access Plan)
ZV2 (Preliminary Access Plan)
Natural Environment (cont'd)
Waterbodies and Watercourses(b)
The access road footprint crosses 10 mapped watercourses.
The access road footprint crosses two mapped waterbodies(c) for an area of 0.0 ha.
Waterbodies and Watercourses(b)
The access road footprint crosses five mapped watercourses.
The access road footprint does not cross any mapped waterbodies(c).
ZV1 intersects more waterbodies and watercourses than ZV2.
Areas of Natural and Scientific Interest (ANSI)
The access road footprint intersects 2.6 ha of Candidate ANSI.
Areas of Natural and Scientific Interest (ANSI)
The access road footprint does not intersect any area of Candidate ANSI.
ZV2 intersects a smaller area of Candidate ANSI compared to ZV1.
Vegetation(d)
The access road footprint crosses:
▪ 20.9 ha of natural landcover (terrestrial);
▪ 0.1 ha of anthropogenic disturbance; and
▪ 0.0 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 13.7 ha of natural landcover (terrestrial);
▪ 0.1 ha of anthropogenic disturbance; and
▪ 0.0 ha of natural disturbance.
ZV2 intersects a smaller area of natural landcover (terrestrial) than ZV1.
Wildlife
The access road footprint crosses 7.6 ha of potential suitable moose habitat
The access road footprint crosses 5.9 ha of potential suitable bald eagle habitat
The access road footprint crosses 5.8 ha of potential suitable Canada warbler habitat
The access road footprint crosses 10.7 ha of potential suitable common nighthawk habitat
The access road footprint crosses 6.9 ha of potential suitable olive-sided flycatcher habitat
Wildlife
The access road footprint crosses 2.9 ha of potential suitable moose habitat
The access road footprint crosses 2.3 ha of potential suitable bald eagle habitat
The access road footprint crosses 4.7 ha of potential suitable Canada warbler habitat
The access road footprint crosses 7.3 ha of potential suitable common nighthawk habitat
The access road footprint crosses 4.6 ha of potential suitable olive-sided flycatcher habitat
No discernable difference between ZV1 and ZV2, although ZV2 crosses a smaller area of habitat potential suitable for moose, bald eagle, Canada warbler, common nighthawk and olive-sided flycatcher.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-35
Table 3.11B-8: Access Plan Refinement Analysis – Connection to North Spirit Lake First Nation (Segment Z-V)
Key Factors
Road Refinements
Access Plan Comparison
Connection to North Spirit Lake First Nation (Segment Z-V)
ZV1 (Refined Access Plan)
ZV2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 12.5 ha of mapped Category 2 habitat.
The access road footprint crosses 8.5 ha of mapped Category 3 habitat.
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 10.8 ha of mapped Category 2 habitat.
The access road footprint crosses 2.9 ha of mapped Category 3 habitat
No discernable difference between ZV1 and ZV2, although ZV2 crosses a smaller area of mapped Category 2 and Category 3 habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 20.9 ha of potential suitable wolverine habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 13.7 ha of potential suitable wolverine habitat.
ZV2 crosses a smaller area of potential suitable wolverine habitat.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 3.1 ha of potential suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 1.7 ha of potential suitable maternity roosting habitat for little brown myotis.
No discernable difference, although ZV2 crosses a smaller area of potential suitable maternity roosting little brown myotis habitat.
Socio-Economic Archaeology and Cultural Heritage
The access road footprint crosses 0.3 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint crosses 0.4 ha of land with archaeological potential.
No discernable difference between ZV1 and ZV2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-36
Table 3.11B-8: Access Plan Refinement Analysis – Connection to North Spirit Lake First Nation (Segment Z-V)
Key Factors
Road Refinements
Access Plan Comparison
Connection to North Spirit Lake First Nation (Segment Z-V)
ZV1 (Refined Access Plan)
ZV2 (Preliminary Access Plan)
Aboriginal considerations
Traditional Land and Resource Use (TLRU)
North Spirit Lake First Nation
▪ The access footprint crosses winter and summer trails, a trapline, trapping areas, waterfowl hunting areas, fishing areas, fish spawning areas, plant harvesting areas and a wild rice area.
Sandy Lake First Nation
▪ The access footprint crosses a hunting area.
Traditional Land and Resource Use (TLRU)
North Spirit Lake First Nation
▪ The access footprint crosses winter and summer trails, a trapline, trapping areas and plant harvesting areas.
No discernable difference between ZV1 and ZV2, although ZV2 does not cross any identified traditional land use features from Sandy Lake First Nation.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses.
d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-8, the refined access plan proposed in the Final ESR (ZV1) presents a moderate increase
in key factor metrics presented when compared with the preliminary access plan (ZV2) presented in the Draft
ESR. It should be noted that the 40-m-wide transmission line alignment of this segment of the Project generally
runs parallel to the existing winter road between Deer Lake First Nation and North Spirit Lake First Nation. The
entirety of the access plan proposed for ZV2 included the use of the existing winter road (identified as “to be
upgraded” in the Draft ESR), and therefore was captured in the access footprint of ZV2. The revised access road
footprint of ZV1 includes on-ROW access where the alignment presented in the Final ESR deviates from the
existing winter road, which explains the increases in the key factor metrics presented in Table 3.11B-8. Overall,
the changes in the access road footprint has resulted in ZV1 to cross less area of mapped wetlands, a moderate
increase in the number of watercourses, and slight increases in natural landcover (terrestrial) and a slightly larger
area of potential suitable habitat for all wildlife criteria. However, since most of the access plan for ZV1 includes
on-ROW access, the disturbance required for ZV1 will overlap with the disturbance required for the ROW and
therefore decrease the size of the overall Project footprint for this segment of the Project.
Although there are increases in some key factor metrics, the potential effects of the Project that include the revised
access footprint are predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-37
consideration of implementation of the commitments and monitoring in Section 12.0 and the environmental and
social management plan in Section 9.0. Therefore, Wataynikaneyap will be implementing the TZ1 access road
footprint for the connection to North Spirit Lake First Nation (Segment T-Z).
3.11B-3.1.9 Connection to Sandy Lake First Nation (Segment Z-W)
This segment of the Project extends from the Sandy Lake Junction Switching Station to the Transformer Station
in Sandy Lake First Nation. The revised access plan for this segment of the Project is shown in Annex B
(Figures 3.11B-20 to 3.11B-26). The high-level baseline characterization for the revised access road footprint for
the connection to the Sandy Lake First Nation Transformer Station (Segment Z-W) is presented in Table 3.11B-9.
Changes made in the access plan for this segment of the Project between the Draft and Final ESR includes
primary access within the 40-m-wide ROW, with off-ROW access spurs defined to connect to existing winter roads,
rather than primary access via nearby existing winter roads. The metrics for the access road footprint initially
identified for this segment in the Draft ESR, the metrics for the access road footprint proposed in the Final ESR,
and a comparison between the two are also presented in Table 3.11B-9. The full set of analysis metrics that were
considered are presented in Annex A. Generally, habitat for wildlife criteria is similarly abundant and distributed
along both access road footprints. No bald eagle nests, potential bat hibernacula features, or potential wolverine
den habitat were observed along either of the access road footprints during field surveys in 2016 and 2017.
Table 3.11B-9: Access Plan Refinement Analysis – Connection to Sandy Lake First Nation (Segment Z-W)
Key Factors
Road Refinements
Access Plan Comparison Connection to Sandy Lake First Nation
(Segment Z-W)
ZW1 (Refined Access Plan)
ZW2 (Preliminary Access Plan)
Technical Size
Access roads are 96.8 km in length.
The access road footprint has an area of 58.3 ha.
Size
Access roads are 108.9 km in length.
The access road footprint has an area of 65.3 ha.
ZW2 is shorter and has a smaller footprint.
Existing Infrastructure
The access road footprint crosses two existing roads.
Existing roads cross the access road footprint five times.
The access road footprint crosses one other linear corridor.
Existing Infrastructure
The access road footprint crosses three existing road crosses.
Existing roads cross the access road footprint 11 times
The access road footprint crosses six other linear corridors.
ZW1 is crossed fewer times by existing roads and other linear corridors than ZW2.
Natural Environment Wetlands(a)
Area of mapped wetlands in the access road footprint is 8.0 ha.
Wetlands(a)
Area of mapped wetlands in the access road footprint is 21.8 ha.
ZW1 intersects less mapped wetlands than ZW2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-38
Table 3.11B-9: Access Plan Refinement Analysis – Connection to Sandy Lake First Nation (Segment Z-W)
Key Factors
Road Refinements
Access Plan Comparison Connection to Sandy Lake First Nation
(Segment Z-W)
ZW1 (Refined Access Plan)
ZW2 (Preliminary Access Plan)
Natural Environment (cont’d)
Waterbodies and Watercourses(b)
The access road footprint crosses six mapped watercourses.
Waterbodies and Watercourses(b)
The access road footprint crosses 22 mapped watercourses.
ZW1 intersects fewer watercourses than SL2.
Vegetation(c)
The access road footprint crosses:
▪ 54.9 ha of natural landcover (terrestrial);
▪ 1.6 ha of anthropogenic disturbance;
▪ 0.4 ha of natural disturbance; and
▪ 3.4 ha of mapped occurrences of provincially tracked vegetation species.
Vegetation
The access road footprint crosses:
▪ 58.5 ha of natural landcover (terrestrial);
▪ 2.0 ha of anthropogenic disturbance;
▪ 0.4 ha of natural disturbance;
▪ 4.0 ha of mapped occurrences of provincially tracked vegetation species
No discernable difference between ZW1 and ZW2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-39
Table 3.11B-9: Access Plan Refinement Analysis – Connection to Sandy Lake First Nation (Segment Z-W)
Key Factors
Road Refinements
Access Plan Comparison Connection to Sandy Lake First Nation
(Segment Z-W)
ZW1 (Refined Access Plan)
ZW2 (Preliminary Access Plan)
Natural Environment (cont’d)
Wildlife
The access road footprint crosses 39.2 ha of potential suitable moose habitat
The access road footprint crosses 0.1 ha of potential suitable horned grebe habitat
The access road footprint crosses 40.0 ha of potential suitable bald eagle habitat
The access road footprint crosses 13.2 ha of potential suitable Canada warbler habitat
The access road footprint crosses 11.7 ha of potential suitable common nighthawk habitat
The access road footprint crosses 38.9 ha of potential suitable olive-sided flycatcher habitat
The access road footprint crosses 3.4 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife
The access road footprint crosses 26.6 ha of potential suitable moose habitat
The access road footprint crosses 0.2 ha of potential suitable horned grebe habitat
The access road footprint crosses 23.9 ha of potential suitable bald eagle habitat
The access road footprint crosses 15.6 ha of potential suitable Canada warbler habitat
The access road footprint crosses 21.7 ha of potential suitable common nighthawk habitat
The access road footprint crosses 26.0 ha of potential suitable olive-sided flycatcher habitat
The access road footprint crosses 4.0 ha of mapped potential habitat supporting provincially tracked wildlife species
No discernable difference between ZW1 and ZW2, although ZW1 crosses a smaller area of potential suitable Canada warbler and common nighthawk habitat.
ZW2 crosses a smaller area of potential suitable habitat for moose, bald eagle, and olive-sided flycatcher.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-40
Table 3.11B-9: Access Plan Refinement Analysis – Connection to Sandy Lake First Nation (Segment Z-W)
Key Factors
Road Refinements
Access Plan Comparison Connection to Sandy Lake First Nation
(Segment Z-W)
ZW1 (Refined Access Plan)
ZW2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 5.6 ha of mapped Category 1 (nursery) habitat.
The access road footprint crosses 0.7 ha of mapped Category 1 (winter use) habitat.
The access road footprint crosses 0.1 ha of mapped Category 2 habitat.
The access road footprint crosses 51.9 ha of mapped Category 3 habitat.
The access road footprint crosses 3.6 ha of mapped caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 5.8 ha of mapped caribou (Boreal population) travel corridors (Fall – November).
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 6.0 ha of mapped Category 1 (nursery) habitat.
The access road footprint crosses 3.4 ha of mapped Category 1 (winter use) habitat.
The access road footprint crosses 2.3 ha of mapped Category 2 habitat.
The access road footprint crosses 53.6 ha of mapped Category 3 habitat.
The access road footprint crosses 4.1 ha of mapped caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 6.7 ha of mapped caribou (Boreal population) travel corridors (Fall – November).
No discernable difference between ZW1 and ZW2, although ZW1 crosses a smaller area of Category 2 habitat, and Spring travel corridors.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 55.3 ha of potential suitable wolverine habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 58.9 ha of potential suitable wolverine habitat.
No discernable difference between ZW1 and ZW2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-41
Table 3.11B-9: Access Plan Refinement Analysis – Connection to Sandy Lake First Nation (Segment Z-W)
Key Factors
Road Refinements
Access Plan Comparison Connection to Sandy Lake First Nation
(Segment Z-W)
ZW1 (Refined Access Plan)
ZW2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 12.8 ha of potential suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 8.8 ha of potential suitable maternity roosting habitat for little brown myotis.
ZW2 crosses a smaller area of potential suitable maternity roosting little brown myotis habitat.
Land Use, Resource Management
Land Designations
The access road footprint crosses two non-OTN trails for a total length of 15.0 m.
The access road footprint crosses 12 mining claims for a total area of 2.7 ha
Land Designations
The access road footprint crosses four non-OTN trails for a total length of 262.6 m.
The access road footprint crosses 10 mining claims for a total area of 3.3 ha.
No discernable difference between ZW1 and ZW2.
Socio-Economic Archaeology and Cultural Heritage
The access road footprint crosses 0.1 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint crosses 0.4 ha of land with archaeological potential.
No discernable difference between ZW1 and ZW2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-42
Table 3.11B-9: Access Plan Refinement Analysis – Connection to Sandy Lake First Nation (Segment Z-W)
Key Factors
Road Refinements
Access Plan Comparison Connection to Sandy Lake First Nation
(Segment Z-W)
ZW1 (Refined Access Plan)
ZW2 (Preliminary Access Plan)
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
Deer Lake First Nation
▪ The access footprint crosses one trapline, a fish spawning area and a moose hunting area.
North Spirit Lake First Nation
▪ The access footprint crosses winter and summer trails and trapping areas.
Sandy Lake First Nation
▪ The access footprint crosses five traplines, a caribou crossing, a winter wood cutting area, and trapping and hunting areas.
Traditional Land and Resource Use (TLRU)
Deer Lake First Nation
▪ The access footprint crosses one trapline, a fish spawning area and a moose hunting
area.
North Spirit Lake First Nation
▪ The access footprint crosses winter and summer trails and trapping areas.
Sandy Lake First Nation
▪ The access footprint crosses five traplines, a caribou crossing, a ski-doo route, a winter wood cutting area, and trapping and hunting areas.
No discernable difference between ZW1 and ZW2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-9, the refined access plan proposed in the Final ESR (ZW1) presents similar key factor
metrics when compared with the preliminary access plan (ZW2) presented in the Draft ESR. However, the access
road length and footprint for ZW1 is shorter and smaller. ZW1 has more existing road crossings within the access
road footprint, and this is attributed to the fact that the proposed access road for ZW1 is mostly on-ROW and
primarily follows the existing winter road from the Sandy Lake Junction Switching Station to Sandy Lake First
Nation, and the ROW crosses the existing winter road in several instances along its length. On the other hand, a
large proportion of the access plan proposed for ZW2 included the use of the existing winter road (identified as “to
be upgraded” in the Draft ESR). This resulted in less existing road crossings for ZW2. Overall, the changes in
the access road footprint has resulted in ZW1 crossing a smaller area of mapped wetlands, fewer watercourses
and waterbodies, a smaller area of natural landcover (terrestrial), and a smaller area of potential suitable habitat
for most wildlife species (besides moose, bald eagle, olive-sided flycatcher and maternity roosting habitat for little
brown myotis). For all the other metrics, there were minor variations in the areas crossed by each of the access
road footprints, leading to no discernable differences between the two.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-43
Although there are some increases in key factor metrics, the potential effects of the Project that include the revised
access footprint are predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in
consideration of implementation of the commitments and monitoring in Section 12.0 and the environmental and
social management plan in Section 9.0. Therefore, Wataynikaneyap will be implementing the ZW1 access road
footprint for the Connection to Sandy Lake First Nation (Segment Z-W).
3.11B-3.2 Pickle Lake Subsystem
3.11B-3.2.1 Connection to Ebane/Pipestone Junction Switching Station (Segment B-C)
This portion of the Project originates at the Phase 1 Pickle Lake Transformer Station in Central Patricia and follows
the existing NORT Road (former Highway 808; referred to herein as NORT Road) and the Goldcorp M1M
transmission line to the Ebane/Pipestone Junction Switching Station at the Musselwhite Mine turn-off. Access
roads had not been identified for Segment B-C as part of the Draft ESR, assuming that the NORT Road (an all-
season road) would provide the primary access, with an access route/track along the ROW used when required
only. As part of the Final ESR, an access plan has been defined for Segment B-C which consists of an additional
145.6 km of proposed new access roads. However, this access plan includes primarily an access road within the
40-m-wide ROW (i.e., 140.8 km of the access roads is on-ROW). Only 5.0 km of the access plan is comprised of
proposed new access roads outside of the ROW.
The revised access plan for this segment of the Project is shown in Annex B (Figures 3.11B-37 to 3.11B-45). The
high-level baseline characterization for the access road footprint for the connection to Ebane/Pipestone Junction
Switching Station (Segment B-C) is presented in Table 3.11B-10. Since an access road footprint had not been
defined as part of the Draft ESR for Segment B-C, a metrics comparison between access road footprints cannot
be presented for this segment of the Project. Instead, Table 3.11B-10 only presents metric values for the access
road footprint defined for the Final ESR. The full set of analysis metrics that were considered for the high-level
baseline characterization of Segment B-C are presented in Annex A. No bald eagle nests, potential bat hibernacula
features, or potential wolverine den habitat were observed access road footprint during field surveys in 2016
and 2017.
Since most of the access plan for Segment B-C identified in the Final ESR includes a proposed on-ROW access
road, it is important to note that the any disturbance effects associated with the on-ROW access road are bounded
by the disturbance effects that were assessed in the Draft ESR for the 40-m-wide ROW for this segment of the
Project. Although the ROW alignment has been refined slightly in areas along this segment of the Project for the
Final ESR, this ROW re-alignment was completed within the limits of work assessed in the Draft ESR. The
proposed off-ROW access roads for this segment of the Project span over a relatively short distance (i.e., 5.0 km)
and are located adjacent to or near the ROW. It is predicted that the disturbance effects predicted for the ROW
will also bound the potential disturbance effects associated with the off-ROW access roads.
The potential effects of the Project that include the revised access footprint for Segment B-C are predicted to reach
the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration of implementation of the
commitments and monitoring in Section 12.0 and the environmental and social management plan in Section 9.0.
Therefore, Wataynikaneyap will be implementing the revised access plan discussed herein for the connection to
Ebane/Pipestone Junction Switching Station (Segment B-C).
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-44
Table 3.11B-10: Access Plan Refinement Analysis – Connection to Ebane/Pipestone Junction Switching Station (Segment B-C)
Key Factors
Access Plan Refinements
Connection to Ebane/Pipestone Junction Switching Station (Segment B-C) Refined Access Plan
Technical Size
Access roads are 145.6 km in length:
▪ 140.8 km of access roads within the ROW
▪ 5.0 km of access roads outside of the ROW
The access road footprint is 87.5 ha.
Existing Infrastructure
Two existing roads crossed by the access road footprint.
Existing roads cross the access road footprint 25 times.
Two other linear corridors cross the access road footprint.
Natural Environment Wetlands(a)
8.7 ha of mapped wetlands in the access road footprint
Waterbodies and Watercourses(b)
Seven watercourses cross the access road footprint.
Two waterbodies cross the access road footprint across an area of 0.0 ha
Areas of Natural and Scientific Interest (ANSI)
2.9 ha of ANSI in the access road footprint
Vegetation(c)
The access road footprint crosses:
▪ 64.5 ha of natural landcover (terrestrial);
▪ 9.1 ha of anthropogenic disturbance; and
▪ 0.3 ha of natural disturbance.
Wildlife Habitat
The access road footprint crosses 43.7 ha of potential suitable moose habitat.
The access road footprint crosses 1.0 ha of potential suitable horned grebe habitat.
The access road footprint crosses 47.2 ha of potential suitable bald eagle habitat.
The access road footprint crosses 13.8 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 15.8 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 44.5 ha of potential suitable olive-sided flycatcher habitat
The access road footprint crosses 0.0 ha of mapped potential habitat supporting provincially tracked wildlife species.
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 2.3 ha of mapped Category 1 (nursery) habitat.
The access road footprint crosses 36.6 ha of mapped Category 2 habitat.
The access road footprint crosses 46.6 ha of mapped Category 3 habitat.
The access road footprint crosses 7.8 ha of mapped caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 5.2 ha of mapped caribou (Boreal population) travel corridors (Fall – November)
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 64.8 ha of potential suitable wolverine habitat.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-45
Table 3.11B-10: Access Plan Refinement Analysis – Connection to Ebane/Pipestone Junction Switching Station (Segment B-C)
Key Factors
Access Plan Refinements
Connection to Ebane/Pipestone Junction Switching Station (Segment B-C) Refined Access Plan
Natural Environment (con'd)
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 15.9 ha of potential suitable maternity roosting habitat for little brown myotis.
Land and Resource Use Land Designations
The access road footprint crosses 17 mining claims, for an area of 11.4 ha.
Socio-economic Archaeology and Cultural Heritage
The access road footprint crosses of 9.1 ha of land with archaeological potential.
Tourism and Recreation
The access road footprint crosses one BHA with an area of 38.7 ha.
Aboriginal Considerations Traditional Land and Resource Use (TLRU)
Kingfisher Lake First Nation
▪ The access road footprint crosses one trapline
Mishkeegogamang First Nation and Eabametoong First Nation
▪ A potential grave site identified by community members of Mishkeegogamang First Nation is crossed by the access road footprint. Wataynikaneyap will work with Mishkeegogamang First Nation to confirm the location of the burial site and to avoid or minimize potential effects to the burial site, as required.
▪ The access footprint also crosses areas where hunting/spade cabins locations have been identified by Mishkeegogamang First Nation and Eabametoong First Nation community members.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
3.11B-3.2.2 Connection to North Caribou Lake First Nation (Segment C-D)
This segment of the Project extends from the Ebane/Pipestone Junction Switching Station to the Transformer
Station in North Caribou Lake First Nation. The revised access plan for this segment of the Project is shown in
Annex B (Figures 3.11B-68 to 3.11B-75). The high-level baseline characterization for the revised access road
footprint for the connection to North Caribou Lake First Nation (Segment C-D) between segment C and segment
D of the Project is presented in Table 3.11B-11. The changes made in the access plan for this segment of the
Project between the draft and final ESR includes access within the 40-m-wide ROW rather than via nearby existing
winter roads and all-season roads as well as defining additional off-ROW access around wet areas or obstacles
such as steep slopes or large waterbodies where the installation of crossings is not practical. The metrics for the
access roads footprint initially identified for this segment of the Project in the Draft ESR, the metrics for the access
roads footprint proposed in the Final ESR, and a comparison between the two are also presented in
Table 3.11B-11. The full set of metrics considered are presented in Annex A. Generally, habitat for wildlife criteria
is similarly abundant and distributed along both access road footprints. No bald eagle nests or potential
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-46
bat hibernacula features were observed along either of the access road footprints during field surveys in 2016
and 2017.
Table 3.11B-11: Access Plan Refinement Analysis – Connection to North Caribou Lake First Nation (Segment C-D)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to North Caribou Lake First Nation
(Segment C-D)
CD1 (Refined Access Plan)
CD2 (Preliminary Access Plan)
Technical Size
Access roads are 123.6 km in length.
The access road footprint is 73.9 ha.
Size
Access roads are 39.5 km in length.
The access road footprint is 23.7 ha.
The access roads length and area of CD1 are longer and larger than CD2.
Existing Infrastructure
There are 2 existing roads crossed by the access road footprint.
Existing roads cross the access road footprint 63 times.
Existing Infrastructure
There are 2 existing roads crossed by the access road footprint.
Existing roads cross the access road footprint 3 times.
Existing roads cross CD1 more often than CD2.
Natural Environment Wetlands(a)
Area of mapped wetlands in the access road footprint is 6.9 ha.
Wetlands(a)
Area of mapped wetlands in the access road footprint is 6.9 ha.
No discernable difference between CD1 and CD2.
Waterbodies and Watercourses(b)
The access road footprint crosses 10 watercourses.
The access road footprint crosses 4 waterbodies(c) for an area of 0.0 ha
Waterbodies and Watercourses(b)
2 watercourses cross the access road footprint
The access road footprint does not cross any waterbodies(c).
CD1 intersects more watercourses and waterbodies than CD2.
Areas of Natural and Scientific Interest (ANSI)
There is 27.8 ha of mapped Candidate ANSI’s within the access road footprint
Areas of Natural and Scientific Interest (ANSI)
There is 6.3 ha of mapped Candidate ANSI’s within the access road footprint
The access road footprint of CD2 intersects less area of mapped Candidate ANSI than CD1.
Vegetation(d)
The access road footprint crosses:
▪ 50.5 ha of natural landcover (terrestrial);
▪ 18.6 ha of anthropogenic disturbance; and
▪ 3.8 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 23.6 ha of natural landcover (terrestrial);
▪ 0.1 ha of anthropogenic disturbance; and
▪ 0.0 ha of natural disturbance.
The access road footprint of CD2 intersects less natural landcover (terrestrial), anthropogenic disturbance, and natural disturbance than CD1.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-47
Table 3.11B-11: Access Plan Refinement Analysis – Connection to North Caribou Lake First Nation (Segment C-D)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to North Caribou Lake First Nation
(Segment C-D)
CD1 (Refined Access Plan)
CD2 (Preliminary Access Plan)
Natural Environment (cont'd)
Wildlife Habitat
The access road footprint crosses 34.5 ha of potential suitable moose habitat.
The access road footprint crosses 0.0 ha of potential suitable horned grebe habitat.
The access road footprint crosses 35.7 ha of potential suitable bald eagle habitat.
The access road footprint crosses 13.0 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 15.7 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 33.3 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 0.6 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife Habitat
The access road footprint crosses 12.8 ha of potential suitable moose habitat.
The access road footprint does not cross any habitat potential suitable for horned grebe.
The access road footprint crosses 12.6 ha of potential suitable bald eagle habitat.
The access road footprint crosses 10.9 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 7.2 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 15.3 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 0.9 ha of mapped potential habitat supporting provincially tracked wildlife species
The access road footprint of CD2 crosses less potential suitable habitat for moose, horned grebe, bald eagle, Canada warbler, common nighthawk and olive-sided flycatcher than CD1.
The access road footprint for CD2 crosses a smaller area of mapped potential habitat supporting provincially tracked wildlife species.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-48
Table 3.11B-11: Access Plan Refinement Analysis – Connection to North Caribou Lake First Nation (Segment C-D)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to North Caribou Lake First Nation
(Segment C-D)
CD1 (Refined Access Plan)
CD2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
There is 32.0 ha of mapped Category 2 habitat in the access road footprint
There is 42.0 ha of mapped Category 3 habitat in the access road footprint.
The access road footprint crosses 1.4 ha of mapped caribou (Boreal population) travel corridors (Fall – November)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
There is 6.1 ha of mapped Category 2 habitat in the access road footprint.
There is 17.6 ha of mapped Category 3 habitat in the access road footprint.
The access road footprint does not cross any mapped caribou (Boreal population) travel corridors.
The access road footprint for CD2 crosses fewer mapped caribou travel corridors and less mapped Category 2 and Category 3 caribou (Boreal population) habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 54.3 ha of potential suitable wolverine habitat.
No boulder fields or blowdown areas representing potential den habitat were observed within the access road footprint during 2016 and 2017 field surveys.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 23.6 ha of potential suitable wolverine habitat.
One area representing potential den habitat was observed within the access road footprint during 2016 and 2017 field surveys.
The access road footprint for CD2 crosses less mapped potential suitable wolverine habitat.
One area representing potential den habitat was observed within the access road footprint of NC2.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 9.8 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 8.0 ha of suitable maternity roosting habitat for little brown myotis.
The access road footprint for CD2 crosses less mapped potential suitable little brown myotis habitat.
Socio-economic Archaeology and Cultural Heritage
The access road footprint crosses 4.4 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint crosses 1.4 ha of land with archaeological potential.
The access road footprint for CD2 crosses a smaller area of land with archaeological potential.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-49
Table 3.11B-11: Access Plan Refinement Analysis – Connection to North Caribou Lake First Nation (Segment C-D)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to North Caribou Lake First Nation
(Segment C-D)
CD1 (Refined Access Plan)
CD2 (Preliminary Access Plan)
Aboriginal considerations
Traditional Land and Resource Use (TLRU)
Kingfisher Lake First Nation
▪ The access road footprint crosses one trapline and trapping areas.
North Caribou Lake First Nation
▪ The access road footprint crosses seven traplines, trapping areas, unknown burial sites and a sensitive cultural site.
Traditional Land and Resource Use (TLRU)
North Caribou Lake First Nation
▪ The access road footprint crosses four traplines, unknown burial sites and a sensitive cultural site.
The access road footprint for CD1 crosses additional Kingfisher Lake TLRU features and 3 additional North Caribou Lake traplines compared to CD2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-11, the refined access plan proposed in the Final ESR (CD1) presents a moderate
increase in the key factor metrics presented when compared with the preliminary access plan (CD2) presented in
the Draft ESR. It should be noted that the 40-m-wide transmission line alignment of this segment of the Project
generally follows the existing NORT Road and the current high-ground winter road to North Caribou Lake First
Nation and existing roads which does not require upgrades for utilization; it was therefore not captured in the
access footprint of CD2. The revised access road footprint of CD1 includes on-ROW access where the alignment
presented in the Final ESR deviates from NORT Road, which, in conjunction with the omission of the existing
NORT Road access in the footprint of CD2, explains the increases in the key factor metrics presented in Table
3.11B-11. In addition, an area representing potential wolverine den habitat was observed within the access road
footprint of CD2 during 2016 and 2017 field surveys; the access road footprint for CD1 is now routed away from
this area.
Although there are increases in key factor metrics, the potential effects of the Project that include the revised
access footprint are predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in
consideration of implementation of the commitments and monitoring in Section 12.0 and the environmental and
social management plan in Section 9.0. This includes applying mitigation to limit disturbance to active wolverine
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-50
dens if active den sites are observed during Project construction. Therefore, Wataynikaneyap will be implementing
the CD1 access road footprint for the connection to North Caribou Lake First Nation (Segment C-D).
3.11B-3.2.3 Connection to Kingfisher Lake First Nation (Segment C-J)
This segment of the Project extends from the Ebane/Pipestone Junction Switching Station to the Transformer
Station in Kingfisher Lake First Nation. The revised access plan for this segment of the Project is shown in Annex B
(Figures 3.11B-46 to 3.11B-52). The high-level baseline characterization for the revised access road footprint for
the connection to Kingfisher Lake First Nation (Segment C-J) is presented in Table 3.11B-12. Changes made in
the access plan for this segment of the Project between the Draft and Final ESR included the definition of access
within the 40-m-wide ROW rather than via the nearby all-season NORT road where it is paralleled by the line, as
well as defining additional off-ROW access around wet areas or obstacles such as steep slopes or large
waterbodies where the installation of crossings is not practical. The metrics initially identified for this segment of
the Project in the Draft ESR, the metrics for the access roads footprint proposed in the Final ESR, and a
comparison between the two are also presented in Table 3.11B-12. The full set of metrics considered are
presented in Annex A. Generally, habitat for wildlife criteria is similarly abundant and distributed both access road
footprints. No bald eagle nests, potential bat hibernacula features, or potential wolverine den habitat were
observed along either of the access road footprints during field surveys in 2016 and 2017.
Table 3.11B-12: Access Plan Refinement Analysis – Connection to Kingfisher Lake First Nation (Segment C-J)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Kingfisher Lake First Nation
(Segment C-J)
CJ1 (Refined Access Plan)
CJ2 (Preliminary Access Plan)
Technical Size
Access roads are 101.3 km in length.
The access road footprint has an area of 60.7 ha.
Size
Access roads are 69.2 km in length.
The access road footprint has an area of 41.4 ha.
The access roads length and area of CJ1 are longer and larger than CJ2.
Existing Infrastructure
There is 1 existing road crossed by the access road footprint.
Existing roads cross the access road footprint 19 times.
There are 2 other linear corridors that cross the access road footprint.
Existing Infrastructure
There is 1 existing road crossed by the access road footprint.
Existing roads cross the access road footprint once.
There are no other linear corridors that cross the access road footprint.
Existing roads cross CJ1 more often than CJ2.
Natural Environment Wetlands(a)
Area of mapped wetlands in the access road footprint is 8.4 ha.
Wetlands(a)
Area of mapped wetlands in the access road footprint is 9.0 ha
No discernable difference between CJ1 and CJ2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-51
Table 3.11B-12: Access Plan Refinement Analysis – Connection to Kingfisher Lake First Nation (Segment C-J)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Kingfisher Lake First Nation
(Segment C-J)
CJ1 (Refined Access Plan)
CJ2 (Preliminary Access Plan)
Natural Environment (cont'd)
Waterbodies and Watercourses(b)
The access road footprint crosses 13 watercourses.
The access road footprint crosses 5 waterbodies(c) for an area of 0.1 ha.
Waterbodies and Watercourses(b)
The access road footprint crosses 19 watercourses.
The access road footprint crosses 5 waterbodies(c) for an area of 0.2 ha.
No discernable difference between CJ1 and CJ2.
Areas of Natural and Scientific Interest (ANSI)
There is 1.9 ha of mapped Candidate ANSI’s within the access road footprint.
Areas of Natural and Scientific Interest (ANSI)
There is 1.7 ha of mapped Candidate ANSI’s within the access road footprint.
No discernable difference between CJ1 and CJ2.
Vegetation(d)
The access road footprint crosses:
▪ 45.5 ha of natural landcover (terrestrial);
▪ 6.1 ha of anthropogenic disturbance; and
▪ 8.3 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 40.9 ha of natural landcover (terrestrial);
▪ 0.1 ha of anthropogenic disturbance; and
▪ 0.3 ha of natural disturbance.
No discernable difference between CJ1 and CJ2, although CJ1 intersects slightly more natural landcover (terrestrial), anthropogenic disturbance, and natural disturbance than CJ2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-52
Table 3.11B-12: Access Plan Refinement Analysis – Connection to Kingfisher Lake First Nation (Segment C-J)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Kingfisher Lake First Nation
(Segment C-J)
CJ1 (Refined Access Plan)
CJ2 (Preliminary Access Plan)
Natural Environment (cont'd)
Wildlife Habitat
The access road footprint crosses 53.8 ha of potential suitable moose habitat
The access road footprint crosses 0.2 ha of potential suitable horned grebe habitat
The access road footprint crosses 23.8 ha of potential suitable bald eagle habitat
The access road footprint crosses 16.1 ha of potential suitable Canada warbler habitat
The access road footprint crosses 25.5 ha of potential suitable common nighthawk habitat
The access road footprint crosses 26.9 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 0.4 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife Habitat
The access road footprint crosses 41.2 ha of potential suitable moose habitat
The access road footprint does not cross any habitat potential suitable for horned grebe.
The access road footprint crosses 3.4 ha of potential suitable bald eagle habitat
The access road footprint crosses 30.9 ha of potential suitable Canada warbler habitat
The access road footprint crosses 7.3 ha of potential suitable common nighthawk habitat
The access road footprint crosses 17.2 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint does not cross any area of mapped potential habitat supporting provincially tracked wildlife species
The access road footprint of CJ2 crosses less potential habitat suitable for moose, horned grebe, bald eagle, common nighthawk and olive-sided flycatcher than CJ1.
The access road footprint of CJ1 crosses less potential suitable habitat for Canada warbler.
The access road footprint for CJ2 does not cross any mapped potential habitat supporting provincially tracked wildlife species.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-53
Table 3.11B-12: Access Plan Refinement Analysis – Connection to Kingfisher Lake First Nation (Segment C-J)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Kingfisher Lake First Nation
(Segment C-J)
CJ1 (Refined Access Plan)
CJ2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 47.4 ha of Category 2 habitat
The access road footprint crosses 13.2 ha of Category 3 habitat
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 29.3 ha of Category 2 habitat
The access road footprint crosses 12.1 ha of Category 3 habitat
The access road footprint of CJ2 intersects less Category 2 and Category 3 habitat than CJ1.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 53.8 ha of suitable wolverine habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 41.2 ha of suitable wolverine habitat.
The access road footprint of CJ2 intersects less wolverine habitat than CJ1.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 4.1 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 3.3 ha of suitable maternity roosting habitat for little brown myotis.
The access road footprint of CJ2 intersects less little brown myotis habitat than CJ1.
Land and Resource Use
Land Designations
The access road footprint intersects 17 mining claims for an area of 4.8 ha
Land Designations
The access road footprint intersects 17 mining claims for an area of 4.2 ha
No discernable difference between CJ1 or CJ2
Socio-economic Archaeology and Cultural Heritage
The access road footprint intersects 1.2 ha of land with archaeological potential
Archaeology and Cultural Heritage
The access road footprint intersects 1.1 ha of land with archaeological potential.
No discernable difference between CJ1 or CJ2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-54
Table 3.11B-12: Access Plan Refinement Analysis – Connection to Kingfisher Lake First Nation (Segment C-J)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Kingfisher Lake First Nation
(Segment C-J)
CJ1 (Refined Access Plan)
CJ2 (Preliminary Access Plan)
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
Kingfisher Lake First Nation
▪ The access road footprint crosses seven traplines, crosses areas defined to include sensitive hunting areas, fur trapping areas, fish spawning areas, goose hunting areas and sensitive community areas.
Traditional Land and Resource Use (TLRU)
Kingfisher Lake First Nation
▪ The access road footprint crosses six traplines, crosses areas defined to include sensitive hunting areas, fur trapping areas, fish spawning areas, goose hunting areas and sensitive community areas.
No discernable difference between CJ1 or CJ2
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-12, the refined access plan proposed in the Final ESR (CJ1) presents a moderate
increase in the key factor metrics presented when compared with the preliminary access plan (CJ2) presented in
the Draft ESR. .CJ1 has more existing road crossings within the access road footprint, and this is attributed to the
fact that the proposed access road for CJ1 is mostly on-ROW and primarily follows the existing road from
Ebane/Pipestone Switching Station Junction to its end near Musselwhite Mine, and the ROW crosses the existing
road in several instances along its length. On the other hand, a large proportion of the access plan proposed for
CJ2 included the use of the existing road (identified as “to be upgraded” in the Draft ESR). This resulted in less
existing road crossings for JK2. In addition, the access JK1 crosses less watercourses than JK2, as the revised
access plan avoids wet areas that were better understood through the analysis of recently acquired LiDAR
information. Between Musselwhite Mine and Kingfisher Lake First Nation, both the Draft and Final ESR define
primarily on-ROW access.
Although there are increases in key factor metrics, the potential effects of the Project that include the revised
access plan are predicted to reach the same conclusions for the EA criteria in Sections 5.0 to 8.0; and in
consideration of implementation of the commitments and monitoring in Section 12.0 and the environmental and
social management plan in Section 9.0. Therefore, Wataynikaneyap will be implementing the CJ1 access plan for
the connection to Kingfisher Lake First Nation (Segment C-J).
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-55
3.11B-3.2.4 Connection to Muskrat Dam First Nation (Segment D-E)
This segment of the Project extends from the North Caribou Lake First Nation Transformer Station to the Muskrat
Dam Transformer Station. The revised access plan for this segment of the Project is shown in Annex B
(Figures 3.11B-75 to 3.11B-79). The high-level baseline characterization for the revised access road footprint for
the connection to Muskrat Dam First Nation (Segment D-E) is presented in Table 3.11B-13. Changes made in the
access plan for this segment of the Project between the Draft and Final ESR included the definition of access
within the 40-m-wide ROW rather than via nearby existing winter roads as well as defining additional off-ROW
access around wet areas or obstacles such as steep slopes or large waterbodies where the installation of
crossings is not practical. The metrics initially identified for this segment of the Project in the Draft ESR, the metrics
for the access roads footprint proposed in the Final ESR, and a comparison between the two are also presented
in Table 3.11B-13. The full set of metrics considered are presented in Annex A. Generally, habitat for wildlife
criteria is similarly abundant and distributed both access road footprints. No bald eagle nests, potential
bat hibernacula features, or potential wolverine den habitat were observed along either of the access road
footprints during field surveys in 2016 and 2017.
Table 3.11B-13: Access Plan Refinement Analysis – Connection to Muskrat Dam First Nation (Segment D-E)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Muskrat Dam First Nation
(Segment D-E)
DE1 (Refined Access Plan)
DE2 (Preliminary Access Plan)
Technical Size
Access roads are 92.4 km in length.
The access road footprint is 55.3 ha.
Size
Access roads are 94 km in length.
The access road footprint is 56.4 ha.
No discernable difference between DE1 and DE2
Existing Infrastructure
There are 2 existing road crossed by the access road footprint.
Existing roads cross the access road footprint 3 times.
There is 1 other linear corridor that crosses the access road footprint.
Existing Infrastructure
There is 1 existing road crossed by the access road footprint.
Existing roads cross the access road footprint 3 times.
There are 3 other linear corridors that crosses the access road footprint
No discernable difference between DE1 and DE2
Natural Environment Wetlands(a)
Area of mapped wetlands in the access road footprint is 11.0 ha.
Wetlands(a)
Area of mapped wetlands in the access road footprint is 36.0 ha.
DE1 intersects less area of mapped wetlands than DE2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-56
Table 3.11B-13: Access Plan Refinement Analysis – Connection to Muskrat Dam First Nation (Segment D-E)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Muskrat Dam First Nation
(Segment D-E)
DE1 (Refined Access Plan)
DE2 (Preliminary Access Plan)
Waterbodies and Watercourses(b)
The access road footprint crosses 14 watercourses.
The access road footprint crosses 3 waterbodies for an area of 0.1 ha(c).
Waterbodies and Watercourses(b)
The access road footprint crosses 24 watercourses.
The access road footprint crosses 2 waterbodies for an area of 0.0 ha(c).
DE1 intersects fewer watercourses than DE2
Natural Environment (cont’d)
Areas of Natural and Scientific Interest (ANSI)
There is 2.6 ha of mapped Candidate ANSI’s within the access road footprint.
Areas of Natural and Scientific Interest (ANSI)
There is 1.7 ha of mapped Candidate ANSI’s within the access road footprint.
No discernable difference between DE1 and DE2, however DE2 intersects slightly less mapped Candidate ANSI’s than DE1. No discernable difference between DE1 and DE2
Vegetation(d)
The access road footprint crosses:
▪ 44.2 ha of natural landcover (terrestrial);
▪ 0.1 ha of anthropogenic disturbance; and
▪ 7.3 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 50.4 ha of natural landcover (terrestrial);
▪ 0.3 ha of anthropogenic disturbance; and
▪ 2.9 ha of natural disturbance.
No discernable difference between DE1 and DE2. However, DE1 intersects slightly less natural landcover (terrestrial) than DE2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-57
Table 3.11B-13: Access Plan Refinement Analysis – Connection to Muskrat Dam First Nation (Segment D-E)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Muskrat Dam First Nation
(Segment D-E)
DE1 (Refined Access Plan)
DE2 (Preliminary Access Plan)
Wildlife Habitat
The access road footprint crosses 27.3 ha of potential suitable moose habitat
The access road footprint crosses 0.9 ha of potential suitable horned grebe habitat
The access road footprint crosses 18.2 ha of potential suitable bald eagle habitat
The access road footprint crosses 27.3 ha of potential suitable Canada warbler habitat
The access road footprint crosses 20.4 ha of potential suitable common nighthawk habitat
The access road footprint crosses 19.0 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 17.3 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife Habitat
The access road footprint crosses 13.5 ha of potential suitable moose habitat
The access road footprint does not cross any habitat potential suitable for horned grebe.
The access road footprint crosses 8.0 ha of potential suitable bald eagle habitat
The access road footprint crosses 25.2 ha of potential suitable Canada warbler habitat
The access road footprint crosses 17.6 ha of potential suitable common nighthawk habitat
The access road footprint crosses 20.0 ha of potential suitable olive-sided flycatcher habitat
The access road footprint crosses 10.8 ha of mapped potential habitat supporting provincially tracked wildlife species
DE2 crosses less habitat suitable for moose, bald eagle, common nighthawk and potential habitat supporting provincially tracked wildlife species.
No discernable difference between DE1 and DE2 in regard to horned grebe, Canada warbler, and olive-sided flycatcher potential suitable habitat.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-58
Table 3.11B-13: Access Plan Refinement Analysis – Connection to Muskrat Dam First Nation (Segment D-E)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Muskrat Dam First Nation
(Segment D-E)
DE1 (Refined Access Plan)
DE2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 47.3 ha of mapped Category 2 habitat.
The access road footprint crosses 8.0 ha of mapped Category 3 habitat.
The access road footprint crosses 7.1 ha of mapped caribou (Boreal population) travel corridors (Fall – November).
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 53.2 ha of mapped Category 2 habitat.
The access road footprint crosses 3.3 ha of Category 3 habitat.
The access road footprint crosses 10.0 ha of mapped caribou (Boreal population) travel corridors (Fall – November).
No discernable difference between DE1 and DE2. However, DE1 intersects slightly less Category 2 habitat and fewer caribou travel corridors while intersecting slightly more Category 3 habitat than DE2.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 51.5 ha of potential suitable wolverine habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 53.3 ha of potential suitable wolverine habitat.
No discernable difference between DE1 and DE2.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 8.9 ha of potential suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 4.6 ha of potential suitable maternity roosting habitat for little brown myotis.
DE2 crosses less suitable maternity habitat for little brown myotis than DE1.
Socio-economic Archaeology and Cultural Heritage
The access road footprint intersects 3.0 ha of land with archaeological potential.
Archaeology and Cultural Heritage
The access road footprint intersects 4.0 ha of land with archaeological potential.
No discernable difference between DE1 and DE2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-59
Table 3.11B-13: Access Plan Refinement Analysis – Connection to Muskrat Dam First Nation (Segment D-E)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Muskrat Dam First Nation
(Segment D-E)
DE1 (Refined Access Plan)
DE2 (Preliminary Access Plan)
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
Muskrat Dam First Nation
▪ The access road footprint crosses community aggregate sites, fishing areas, and duck hunting areas.
North Caribou Lake First Nation
▪ The access road footprint crosses two traplines.
Sachigo Lake First Nation
▪ The access road footprint crosses a fishing area.
Traditional Land and Resource Use (TLRU)
Muskrat Dam First Nation
▪ The access road footprint crosses community aggregate sites and duck hunting areas.
North Caribou Lake First Nation
▪ The access road footprint crosses two traplines.
No discernable difference between DE1 and DE2. However, DE2 does not cross any TLRU features identified by land users from Sachigo Lake First Nation.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-13, the refined access plan proposed in the Final ESR (DE1) presents similar key factor
metrics when compared with the preliminary access plan (DE2) presented in the Draft ESR. The DE2 access road
footprint was planned to follow existing winter roads removed from the ROW by several kilometres with
connections to the ROW to facilitate access, while the DE1 footprint now includes on-ROW access throughout this
segment. The ROW has been defined to align with the location of a planned future community all-season road.
Both access road footprints cross comparable areas of natural land cover and wildlife habitat, although DE1 does
cross a slightly larger area of suitable habitat for moose and suitable maternity roosting habitat for little brown
myotis. However, with the realignment away from existing winter roads and analysis of LiDAR information collected
in this area identifying the potential for wet conditions, DE1 crosses a smaller area of wetlands and total
watercourses, supporting the realignment of the DE1 access road footprint. Following future development of the
planned all-season road by the community, the current winter road corridor could be allowed to re-establish
vegetation. Aligning Project access with the ROW and the planned all-season road would be beneficial to reducing
the total number of linear corridors present in this area in the longer-term.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-60
The potential effects of the Project that include the revised access plan are predicted to reach the same
conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration of implementation of the commitments
and monitoring in Section 12.0 and the environmental and social management plan in Section 9.0. Therefore,
Wataynikaneyap will be implementing the DE1 access plan for the connection to Muskrat Dam First Nation
(Segment D-E).
3.11B-3.2.5 Connection to Bearskin Lake First Nation (Segment E-F)
This segment of the Project extends from the Muskrat Dam First Nation Transformer Station to the Bearskin Lake
First Nation Transformer Station. The revised access plan for this segment of the Project is shown in Annex B
(Figure 3.11B-79 and Figures 3.11B-89 to 3.11B-93). The high-level baseline characterization for the revised
access road footprint for the connection to Bearskin Lake First Nation (Segment E-F) is presented in Table 3.11B-
14. Changes made in the access plan for this segment of the Project between the Draft and Final ESR included
the definition of access within the 40-m-wide ROW rather than via nearby existing winter roads as well as defining
additional off-ROW access around wet areas or obstacles such as steep slopes or large waterbodies where the
installation of crossings is not practical. The metrics initially identified for this segment of the Project in the Draft
ESR, the metrics for the access roads footprint proposed in the Final ESR, and a comparison between the two are
also presented in Table 3.11B-14. The full set of metrics considered are presented in Annex A. Generally, habitat
for wildlife criteria is similarly abundant and distributed both access road footprints. No bald eagle nests, potential
bat hibernacula features, or potential wolverine den habitat were observed along either of the access road
footprints during field surveys in 2016 and 2017.
Table 3.11B-14: Access Plan Refinement Analysis – Connection to Bearskin Lake First Nation (Segment E-F)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Bearskin Lake First Nation
(Segment E-F)
EF1 (Refined Access Plan)
EF2 (Preliminary Access Plan)
Technical Size
Access roads are 75.2 km in length.
The access road footprint is 45.1 ha.
Size
Access roads are 80.3 km in length.
The access road footprint is 48.2 ha.
No discernable difference between EF1 and EF2.
Existing Infrastructure
There are 2 existing road crossed by the access road footprint.
Existing roads cross the access road footprint 9 times.
There is 1 other linear corridor that crosses the access road footprint.
Existing Infrastructure
There is 1 existing road crossed by the access road footprint.
Existing roads cross the access road footprint 1 time.
There is 2 other linear corridor that crosses the access road footprint.
EF1 is crossed more times by existing roads than EF2.
Natural Environment Wetlands(a)
Area of mapped wetlands in the access road footprint is 12.4 ha.
Wetlands(a)
Area of mapped wetlands in the access road footprint is 30.5 ha.
EF1 intersects less area of mapped wetlands than EF2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-61
Table 3.11B-14: Access Plan Refinement Analysis – Connection to Bearskin Lake First Nation (Segment E-F)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Bearskin Lake First Nation
(Segment E-F)
EF1 (Refined Access Plan)
EF2 (Preliminary Access Plan)
Natural Environment (cont’d)
Waterbodies and Watercourses(b)
The access road footprint crosses 12 watercourses.
The access road footprint crosses 5 waterbodies(c) are intersected by the access road footprint withfor an area of 0.1 ha
Waterbodies and Watercourses(b)
The access road footprint crosses 12 watercourses.
The access road footprint crosses 5 waterbodies(c) are intersected by the access road footprint withfor an area of 0.2 ha
No discernable difference between EF1 and EF2.
Areas of Natural and Scientific Interest (ANSI)
There is 19.5 ha of mapped Candidate ANSI’s within the access road footprint.
Areas of Natural and Scientific Interest (ANSI)
There is 14.4 ha of mapped Candidate ANSI’s within the access road footprint.
No discernable difference between EF1 and EF2 butBL2, however EF1 intersects slightly less area of ANSIs than EF2.
Vegetation(d)
The access road footprint crosses:
▪ 40.5 ha of natural landcover (terrestrial);
▪ 0.3 ha of anthropogenic disturbance; and
▪ 1.7 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 44.1 ha of natural landcover (terrestrial);
▪ 0.9 ha of anthropogenic disturbance; and
▪ 0.0 ha of natural disturbance.
No discernable difference between EF1 and EF2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-62
Table 3.11B-14: Access Plan Refinement Analysis – Connection to Bearskin Lake First Nation (Segment E-F)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Bearskin Lake First Nation
(Segment E-F)
EF1 (Refined Access Plan)
EF2 (Preliminary Access Plan)
Natural Environment (cont’d)
Wildlife Habitat
The access road footprint crosses 24.0 ha of potential suitable moose habitat.
The access road footprint crosses 0.2 ha of potential suitable horned grebe habitat.
The access road footprint crosses 19.0 ha of potential suitable bald eagle habitat.
The access road footprint crosses 14.6 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 13.7 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 21.5 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 7.8 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife Habitat
The access road footprint crosses 14.8 ha of potential suitable moose habitat.
The access road footprint crosses 0.4 ha of potential suitable horned grebe habitat.
The access road footprint crosses 9.1 ha of potential suitable bald eagle habitat.
The access road footprint crosses 24.0 ha of potential suitable Canada warbler habitat.
The access road footprint crosses 12.5 ha of potential suitable common nighthawk habitat.
The access road footprint crosses 23.4 ha of potential suitable olive-sided flycatcher habitat.
The access road footprint crosses 8.2 ha of mapped potential habitat supporting provincially tracked wildlife species.
EF1 crosses a smaller area of suitable habitat for horned grebe, Canada warbler, and mapped potential habitat supporting provincially tracked wildlife species.
EF2 crosses a smaller area of suitable habitat for moose, bald eagle, common nighthawk and olive-sided flycatcher.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-63
Table 3.11B-14: Access Plan Refinement Analysis – Connection to Bearskin Lake First Nation (Segment E-F)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Bearskin Lake First Nation
(Segment E-F)
EF1 (Refined Access Plan)
EF2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 28.3 ha of Category 2 habitat.
The access road footprint crosses 16.6 ha of Category 3 habitat.
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 31.1 ha of Category 2 habitat.
The access road footprint crosses 16.9 ha of Category 3 habitat.
No discernable difference between EF1 and EF2.No discernable difference between EF1 and EF2, however EF2 crosses slightly less Category 2 caribou (boreal population) habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 42.2 ha of suitable wolverine habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 44.1 ha of suitable wolverine habitat.
No discernable difference between EF1 and EF2.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 5.1 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 3.7 ha of suitable maternity roosting habitat for little brown myotis.
No discernable difference between EF1 and EF2, however EF2 crosses slightly less suitable maternity roosting habitat for little brown myotis.
Socio-economic Archaeology and Cultural Heritage
The access road footprint intersects 2.8 ha of land with archaeological potential in the access road footprint.
Archaeology and Cultural Heritage
The access road footprint intersects 6.5 ha of land with archaeological potential in the access road footprint.
No discernable difference between EF1 and EF2. EF1 intersects a smaller area of land with archaeological potential than EF2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-64
Table 3.11B-14: Access Plan Refinement Analysis – Connection to Bearskin Lake First Nation (Segment E-F)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Bearskin Lake First Nation
(Segment E-F)
EF1 (Refined Access Plan)
EF2 (Preliminary Access Plan)
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
Bearskin Lake First Nation
▪ The access road footprint crosses one trapline, a trapping area and a fish spawning area.
Muskrat Dam
▪ The access road footprint crosses a community aggregate resource.
Sachigo Lake First Nation
▪ The access road footprint crosses a trapline and a watershed protection area.
Traditional Land and Resource Use (TLRU)
Bearskin Lake First Nation
▪ The access road footprint crosses one trapline, a trapping area and a fish spawning area.
Muskrat Dam First Nation
▪ The access road footprint crosses a community aggregate resource.
Sachigo Lake First Nation
▪ The access road footprint crosses a trapline and a watershed protection area.
No discernable difference between EF1 and EF2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-14, the refined access plan proposed in the Final ESR (EF1) presents similar key factor
metrics when compared with the preliminary access plan (EF2) presented in the Draft ESR. EF1 indicated more
crossings of existing mapped roads within the access road footprint, and this is attributed to the fact that the
proposed access road for EF1 is mostly on-ROW and primarily follows the mapped existing winter roads from
Muskrat Dam First Nation to Bearskin Lake First Nation, and the ROW crosses the existing winter roads in several
instances along its length. On the other hand, a large proportion of the access plan proposed for EF2 included the
use of the existing winter road (identified as “to be upgraded” in the Draft ESR). This resulted in less existing road
crossings for EF2. Both Project footprints cross comparable areas of natural land cover and wildlife habitat,
although EF1 does cross a slightly larger area of suitable habitat for moose and suitable maternity roosting habitat
for little brown myotis. However, with the alignment of access within the 40-m-wide ROW rather than via nearby
existing winter roads/all season roads as well as defining additional off-ROW access around wet areas, EF1
intersects a moderately smaller area of wetlands compared to EF2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-65
The potential effects of the Project that include the revised access plan are predicted to reach the same
conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration of implementation of the commitments
and monitoring in Section 12.0 and the environmental and social management plan in Section 9.0. Therefore,
Wataynikaneyap will be implementing the EF1 access plan for the connection to Bearskin Lake First Nation
(Segment E-F).
3.11B-3.2.6 Connection to Sachigo Lake First Nation (Segment E-G)
This segment of the Project extends from the Muskrat Dam Transformer Station to the Transformer Station in
Sachigo Lake First Nation. The revised access plan for this segment of the Project is shown in Annex B
(Figures 3.11B-79 to 3.11B-88). The high-level baseline characterization for the revised access road footprint for
the connection to Sachigo Lake First Nation (Segment E-G) is presented in Table 3.11B-15. Changes made in the
access plan for this segment of the Project between the Draft and Final ESR included the definition of access
within the 40-m-wide ROW rather than aligning where possible with existing winter roads. The metrics for the
access road footprint initially identified for this segment in the Draft ESR, the metrics for the access road footprint
proposed in the Final ESR, and a comparison between the two are also presented in Table 3.11B-15. The full set
of analysis metrics that were considered are presented in Annex A. Generally, habitat for wildlife criteria is similarly
abundant and distributed along both access road footprints. No bald eagle nests or potential bat hibernacula
features were observed along either of the access road footprints during field surveys in 2016 and 2017.
Table 3.11B-15: Access Plan Refinement Analysis – Connection to Sachigo First Nation (Segment E-G)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Sachigo First Nation
(Segment E-G)
EG1 (Refined Access Plan)
EG2 (Preliminary Access Plan)
Technical Size
Access roads are 98.8 km in length.
The access road footprint is 59.4 ha.
Size
Access roads are 100 km in length.
The access road footprint is 60.0 ha.
No discernable difference between EG1 and EG2.
Existing Infrastructure
Three existing roads are crossed by the access road footprint.
Existing roads cross the access road footprint 17 times.
One other linear corridor crosses the access road footprint.
Existing Infrastructure
Three existing roads are crossed by the access road footprint.
Existing roads cross the access road footprint four times.
Four other linear corridors cross the access road footprint.
EG1 has more existing road crossings than EG2.
Natural Environment Wetlands(a)
24.1 ha of mapped wetlands in the access road footprint.
Wetlands(a)
34.5 ha of mapped wetlands in the access road footprint.
EG1 crosses less area of mapped wetlands.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-66
Table 3.11B-15: Access Plan Refinement Analysis – Connection to Sachigo First Nation (Segment E-G)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Sachigo First Nation
(Segment E-G)
EG1 (Refined Access Plan)
EG2 (Preliminary Access Plan)
Natural Environment (cont’d)
Waterbodies and Watercourses(b)
16 watercourses cross the access road footprint
One waterbody(c) is intersected by the access road footprint over an area of 0.1 ha
Waterbodies and Watercourses(b)
18 watercourses cross the access road footprint
One waterbody(c) is intersected by the access road footprint over an area of 0.0 ha
EG1 intersects fewer watercourses than EG2.
No discernable difference in relation to waterbody(c) crossings.
Vegetation
The access road footprint crosses(d):
▪ 53.0 ha of natural landcover (terrestrial);
▪ 2.9 ha of anthropogenic disturbance; and
▪ 1.6 ha of natural disturbance.
The access road footprint crosses 0.9 ha of mapped occurrences of provincially tracked vegetation species.
Vegetation
The access road footprint crosses(d):
▪ 50.3 ha of natural landcover (terrestrial);
▪ 3.3 ha of anthropogenic disturbance; and
▪ 6.1 ha of natural disturbance.
The access road footprint crosses 1.2 ha of mapped occurrences of provincially tracked vegetation species.
No discernable difference between EG1 and EG2; however, EG1 crosses a slightly larger area of natural landcover (terrestrial) and a slightly smaller area of mapped occurrences of provincially tracked vegetation species.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-67
Table 3.11B-15: Access Plan Refinement Analysis – Connection to Sachigo First Nation (Segment E-G)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Sachigo First Nation
(Segment E-G)
EG1 (Refined Access Plan)
EG2 (Preliminary Access Plan)
Natural Environment (cont’d)
Wildlife Habitat
The access road footprint crosses 20.7 ha of potential suitable moose habitat
The access road footprint does not cross any potential suitable horned grebe habitat
The access road footprint rosses 17.2 ha of potential suitable bald eagle habitat
The access road footprint crosses 30.3 ha of potential suitable Canada warbler habitat
The access road footprint crosses 15.7 ha of potential suitable common nighthawk habitat
The access road footprint crosses 28.2 ha of potential suitable olive-sided flycatcher habitat
The access road footprint crosses 31.2 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife Habitat
The access road footprint crosses 18.7 ha of potential suitable moose habitat
The access road footprint crosses 0.4 ha of potential suitable horned grebe habitat
The access road footprint crosses 19.1 ha of potential suitable bald eagle habitat
The access road footprint crosses 38.0 ha of potential suitable Canada warbler habitat
The access road footprint crosses 20.1 ha of potential suitable common nighthawk habitat
The access road footprint crosses 31.4 ha of potential suitable olive-sided flycatcher habitat
The access road footprint crosses 28.4 ha of mapped potential habitat supporting provincially tracked wildlife species
EG1 crosses less area of potential suitable habitat for all wildlife criteria (not threatened or endangered), except for moose.
No discernable difference between EG1 and EG2 in relation to mapped potential habitat supporting provincially tracked wildlife species within the access road footprint; however, EG1 crosses a slightly larger area.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-68
Table 3.11B-15: Access Plan Refinement Analysis – Connection to Sachigo First Nation (Segment E-G)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Sachigo First Nation
(Segment E-G)
EG1 (Refined Access Plan)
EG2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 3.6 ha of mapped Category 1 (nursery) habitat
The access road footprint crosses 27.6 ha of mapped Category 2 habitat
The access road footprint crosses 28.1 ha of mapped Category 3 habitat
The access road footprint does not cross any mapped caribou (Boreal population) travel corridors.
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 1.3 ha of mapped Category 1 (nursery) habitat
The access road footprint crosses 35.7 ha of mapped Category 2 habitat
The access road footprint crosses 23.0 ha of mapped Category 3 habitat
The access road footprint crosses 2.7 ha of mapped caribou (Boreal population) travel corridors (Spring – April).
No discernable difference between S1 and S2; however, EG1 crosses a slightly larger area of mapped Category 1 (nursery) habitat for caribou (Boreal population).
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 54.6 ha of suitable wolverine habitat.
One boulder field or blowdown area representing potential den habitat was observed within the access road footprint during 2016 and 2017 field surveys.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 59.3 ha of suitable wolverine habitat.
No boulder fields or blowdown areas representing potential den habitat were observed within the access road footprint during 2016 and 2017 field surveys.
EG1 crosses one observed area representing potential den habitat for wolverine, but overall crosses a slightly smaller area of potential suitable habitat for wolverine.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 12.0 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 14.9 ha of suitable maternity roosting habitat for little brown myotis.
No discernable difference between EG1 and EG2; however, EG1 crosses a slightly smaller area of potential suitable maternity roosting habitat for little brown myotis.
Socio-economic Archaeology and Cultural Heritage
0.7 ha of land with archaeological potential in the access road footprint
Archaeology and Cultural Heritage
1.2 ha of land with archaeological potential in the access road footprint
No discernable difference between S1 and S2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-69
Table 3.11B-15: Access Plan Refinement Analysis – Connection to Sachigo First Nation (Segment E-G)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Sachigo First Nation
(Segment E-G)
EG1 (Refined Access Plan)
EG2 (Preliminary Access Plan)
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
Sachigo Lake First Nation
▪ The access footprint crosses an old tractor trail, traplines, a campground, a caribou crossing area, a watershed protection area, and a sensitive area.
Traditional Land and Resource Use (TLRU)
Sachigo Lake First Nation
▪ The access footprint crosses an old tractor trail, traplines, a campground, a caribou crossing area, a watershed protection area, and a sensitive area.
No discernable difference between EG1 and EG2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-15, the refined access plan proposed in the Final ESR (EG1) presents similar key factor
metrics presented when compared with the preliminary access plan (EG2) presented in the Draft ESR. However,
one area of potential wolverine den habitat was observed within the access road footprint for EG1 during the 2016
and 2017 field surveys. The length of the access roads and the size of the access road footprint for both EG1 and
EG2 are relatively the same. EG1 has more existing road crossings within the access road footprint, and this is
attributed to the fact that the proposed access road for EG1 is mostly on-ROW and generally follows the existing
winter road to Sachigo Lake First Nation where the ROW approaches the community, and the ROW crosses the
existing winter road in several instances along its length. On the other hand, a large proportion of the access plan
proposed for EG2 included the use of existing access roads to upgrade, including the existing winter road to
Sachigo Lake First Nation. This resulted in less existing road crossings for EG2. Overall, the changes in the
access road footprint has resulted in EG1 to cross less area of mapped wetlands, fewer watercourses, slightly
less area of mapped occurrences of provincially tracked vegetation species, slightly less area of potential suitable
habitat for all wildlife criteria (except for moose and caribou (Boreal population)), and slightly less area with
archaeological potential. EG1 crosses a slightly larger area of natural landcover (terrestrial), mapped potential
habitat supporting provincially tracked wildlife species, potential suitable habitat for moose, and mapped Category
1 (nursery) habitat for caribou (Boreal population). However, since most of the access plan for EG1 includes on-
ROW access, the disturbance required for EG1 will overlap with the disturbance required for the ROW and
therefore decrease the size of the overall Project footprint for this segment of the Project.
The potential effects of the Project that include the revised access footprint are predicted to reach the same
conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration of implementation of the commitments
and monitoring in Section 12.0 and the environmental and social management plan in Section 9.0. This includes
applying mitigation to limit disturbance to active wolverine dens if active den sites are observed during Project
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-70
construction. Therefore, Wataynikaneyap will be implementing the EG1 access road footprint for the connection
to Sachigo Lake First Nation (Segment E-G).
3.11B-3.2.7 Connection to Wunnumin Lake First Nation (Segment J-I)
This segment of the Project extends from the Kingfisher Lake Transformer Station to the Transformer Station in
Wunnumin Lake First Nation. The revised access plan for this segment of the Project is shown in Annex B
(Figures 3.11B-52 to 3.11B-55). The high-level baseline characterization for the revised access road footprint
between segment J and segment I of the Project is presented in Table 3.11B-16. Changes made in the access
plan for this segment of the Project between the draft and final ESR includes adjustment of the access plan to
align with refinements to the ROW, and defining additional off-ROW access around wet areas or obstacles such
as steep slopes or large waterbodies where the installation of crossings is not practical. The metrics for the access
roads footprint initially identified for this segment of the Project in the Draft ESR, the metrics for the access roads
footprint proposed in the Final ESR, and a comparison between the two access road segments are also presented
in Table 3.11B-16. The full set of metrics considered are presented in Annex A. Generally, habitat for wildlife
criteria is similarly abundant and distributed along both corridors. No bald eagle nests or potential bat hibernacula
features were observed along either of the access road footprints during field surveys in 2016 and 2017.
Table 3.11B-16: Access Plan Refinement Analysis – Connection to Wunnumin Lake First Nation
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Wunnumin Lake First Nation
(Segment J-I)
JI1 (Refined Access Plan)
JI2 (Preliminary Access Plan)
Technical Size
Access roads are 56 km in length.
The access road footprint is 33.6 ha.
Size
Access roads are 59 km in length.
The access road footprint is 35.4 ha.
No discernable difference between JI1 and JI2.
Existing Infrastructure
There are 6 existing roads crossed by the access road footprint
Existing roads cross the access road footprint 14 times.
There is 1 other linear corridor that crosses the access road footprint.
Existing Infrastructure
There are 6 existing roads that crossed by the access road footprint.
Existing roads cross the access road footprint 11 times.
There are 3 other linear corridors crossed by the access road footprint.
No discernable difference between JI1 and JI2.
Natural Environment Wetlands(a)
Area of mapped wetlands in the access road footprint is 4.4 ha.
Wetlands(a)
Area of mapped wetlands in the access road footprint is 7.1 ha.
No discernable difference between JI1 and JI2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-71
Table 3.11B-16: Access Plan Refinement Analysis – Connection to Wunnumin Lake First Nation
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Wunnumin Lake First Nation
(Segment J-I)
JI1 (Refined Access Plan)
JI2 (Preliminary Access Plan)
Natural Environment (cont’d)
Waterbodies and Watercourses(b)
The access road footprint crosses 11 watercourses.
The access road footprint does not cross any waterbodies.
Waterbodies and Watercourses(b)
The access road footprint crosses 16 watercourses.
The access road footprint crosses six waterbodies for an area of 0.2 ha
JI1 intersects fewer watercourses and waterbodies than JI2.
Vegetation(c)
The access road footprint crosses:
▪ 15.5 ha of natural landcover (terrestrial);
▪ 0.1 ha of anthropogenic disturbance; and
▪ 0.0 ha of natural disturbance.
Vegetation(c)
The access road footprint crosses:
▪ 14.6 ha of natural landcover (terrestrial);
▪ 0.2 ha of anthropogenic disturbance; and
▪ 0.0 ha of natural disturbance.
No discernable difference between JI1 and JI2.
Wildlife
The access road footprint crosses 7.7 ha of suitable moose habitat
The access road footprint crosses 0.0 ha of suitable horned grebe habitat
The access road footprint crosses 7.7 ha of suitable bald eagle habitat
The access road footprint crosses 4.3 ha of Canada warbler habitat
The access road footprint crosses 7.4 ha of suitable common nighthawk habitat
The access road footprint crosses 8.1 ha of olive-sided flycatcher habitat
Wildlife
The access road footprint crosses 5.2 ha of suitable moose habitat
The access road footprint crosses 0.1 ha of suitable horned grebe habitat
The access road footprint crosses 5.2 ha of suitable bald eagle habitat
The access road footprint crosses 3.4 ha of Canada warbler habitat
The access road footprint crosses 8.4 ha of suitable common nighthawk habitat
The access road footprint crosses 6.1 ha of olive-sided flycatcher habitat
JI1 crosses a smaller area of suitable habitat for common nighthawk.
JI2 crosses a smaller area of suitable habitat for moose, bald eagle and olive-sided flycatcher.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-72
Table 3.11B-16: Access Plan Refinement Analysis – Connection to Wunnumin Lake First Nation
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Wunnumin Lake First Nation
(Segment J-I)
JI1 (Refined Access Plan)
JI2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 7.3 ha of Category 2 habitat.
The access road footprint crosses 26.3 ha of Category 3 habitat.
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 7.8 ha of Category 2 habitat.
The access road footprint crosses 27.6 ha of Category 3 habitat
No discernable difference between JI1 and JI2.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 15.5 ha of suitable wolverine habitat.
No boulder fields or blowdown areas representing potential den habitat were observed within the access road footprint during 2016 and 2017 field surveys.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 14.6 ha of suitable wolverine habitat.
Two boulder fields or blowdown areas representing areas representing potential den habitat were observed within the access road footprint during the 2016 and 2017 field surveys.
No discernable difference in habitat crossed by JI1 or JI2, however, two areas representing potential den habitat were observed within the access road footprint of JI2.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 3.8 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 2.5 ha of suitable maternity roosting habitat for little brown myotis.
No discernable difference between JI1 and JI2.
Socio-economic Archaeology and Cultural Heritage
The access road footprint intersects 1.7 ha of land with archaeological potential in the access road footprint.
Archaeology and Cultural Heritage
The access road footprint intersects 2.9 ha of land with archaeological potential in the access road footprint.
No discernable difference between JI1 and JI2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-73
Table 3.11B-16: Access Plan Refinement Analysis – Connection to Wunnumin Lake First Nation
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Wunnumin Lake First Nation
(Segment J-I)
JI1 (Refined Access Plan)
JI2 (Preliminary Access Plan)
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
Kingfisher Lake First Nation
▪ The access road footprint crosses a public works yard, winter and summer trails, five traplines, and fur trapping areas.
Wunnumin Lake First Nation
▪ The access road footprint crosses one trapline and a trail.
Traditional Land and Resource Use (TLRU)
Kingfisher Lake First Nation
▪ The access road footprint crosses winter and summer trails, five traplines, and fur trapping areas.
Wunnumin Lake First Nation
▪ The access road footprint crosses one trapline and a trail.
JI1 intersects one more TLRU feature than JI2.
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types e) Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure f) Natural disturbance includes forest depletion-burns
As shown in Table 3.11B-16, the refined access plan proposed in the Final ESR (JI1) presents similar key factor
metrics when compared with the preliminary access plan (JI2) presented in the Draft ESR. Both Project footprints
cross comparable areas of natural land cover and wildlife habitat, although two potential wolverine den habitats
were observed within the access road footprint of JI2. In addition, through alignment with the refinements made to
the 40 m wide ROW to avoid wet areas, as well as defining additional off-ROW access to avoid wet areas, JI1
intersects a smaller area of wetlands and fewer waterbodies and watercourses compared to JI2.
The potential effects of the Project that include the revised access plan are predicted to reach the same
conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration of implementation of the commitments
and monitoring in Section 12.0 and the environmental and social management plan in Section 9.0. This includes
applying mitigation to limit disturbance to active wolverine dens if active den sites are observed during Project
construction. Therefore, Wataynikaneyap will be implementing the JI1 access plan for the connection to Wunnumin
Lake First Nation (Segment J-I).
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-74
3.11B-3.2.8 Connection to Wawakapewin First Nation (Segment J-K)
This segment of the Project extends from the Kingfisher Lake Transformer Station to the Transformer Station in
Wawakapewin First Nation. The revised access plan for this segment of the Project is shown in Annex B
(Figure 3.11B-52 and Figures 3.11B-56 to 3.11B-60). The high-level baseline characterization for the revised
access road footprint for the connection to Wawakapewin First Nation (Segment J-K) is presented in Table 3.11B-
17. Changes made in the access plan for this segment of the Project between the draft and final ESR includes
access within the 40-m-wide ROW rather than via the nearby existing winter road as well as defining access spurs
between the ROW and nearby existing winter road, as well as additional off-ROW access around wet areas or
obstacles such as steep slopes or large waterbodies where the installation of crossings is not practical. The metrics
for the access road footprint initially identified for this segment in the Draft ESR, the metrics for the access road
footprint proposed in the Final ESR, and a comparison between the two are also presented in Table 3.11B-17.
The full set of analysis metrics that were considered are presented in Annex A. Generally, habitat for wildlife criteria
is similarly abundant and distributed along both access road footprints. No bald eagle nests, potential
bat hibernacula features, or potential wolverine den habitat were observed along either of the access road
footprints during field surveys in 2016 and 2017.
Table 3.11B-17: Access Plan Refinement Analysis – Connection to Wawakapewin First Nation (Segment J-K)
Key Factors
Access Plan Refinements
Access Plan Comparison
Connection to Wawakapewin First Nation (Segment J-K)
JK1 (Refined Access Plan)
JK2 (Preliminary Access Plan)
Technical Size
Access roads are 78.5 km in length.
The access road footprint is 47.1 ha.
Size
Access roads are 87.6 km in length.
The access road footprint is 52.5 ha.
The length of access roads for JK1 is shorter. JK1 has a smaller access road footprint.
Existing Infrastructure
Two existing roads cross the access road footprint.
Existing roads cross the access road footprint 40 times.
Existing Infrastructure
Three existing roads cross the access road footprint.
Existing roads cross the access road footprint 8 times.
JK1 has more existing road crossings than JK2.
Natural Environment Wetlands(a)
15.6 ha of mapped wetlands in the access road footprint.
Wetlands(a)
14.9 ha of mapped wetlands in the access road footprint.
No discernable difference between JK1 and JK2.
Waterbodies and Watercourses(b)
14 watercourses cross the access road footprint
Two waterbodies(c) are crossed by the access road footprint over an area of 0.0
Waterbodies and Watercourses(b)
29 watercourses cross the access road footprint
Four waterbodies(c) are crossed by the access road footprint over an area of 0.1 ha
JK1 crosses fewer mapped watercourses and waterbodies.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-75
Table 3.11B-17: Access Plan Refinement Analysis – Connection to Wawakapewin First Nation (Segment J-K)
Key Factors
Access Plan Refinements
Access Plan Comparison
Connection to Wawakapewin First Nation (Segment J-K)
JK1 (Refined Access Plan)
JK2 (Preliminary Access Plan)
Natural Environment (cont’d)
Areas of Natural and Scientific Interest (ANSI)
16.4 ha of ANSI in the access road footprint
Areas of Natural and Scientific Interest (ANSI)
16.7 ha of ANSI in the access road footprint
No discernable difference between JK1 and JK2
Vegetation(d)
The access road footprint crosses:
▪ 23.8 ha of natural landcover (terrestrial);
▪ 0.0 ha of anthropogenic disturbance; and
▪ 1.5 ha of natural disturbance.
Vegetation(d)
The access road footprint crosses:
▪ 29.0 ha of natural landcover (terrestrial);
▪ 0.0 ha of anthropogenic disturbance; and
▪ 1.7 ha of natural disturbance.
JK1 crosses a smaller area of natural landcover (terrestrial)
Wildlife Habitat
The access road footprint crosses 8.2 ha of potential suitable moose habitat
The access road footprint does not cross any potential suitable horned grebe habitat.
The access road footprint rosses 5.7 ha of potential suitable bald eagle habitat
The access road footprint crosses 8.1 ha of potential suitable Canada warbler habitat
The access road footprint crosses 15.9 ha of potential suitable common nighthawk habitat
The access road footprint crosses 6.4 ha of potential suitable olive-sided flycatcher habitat
Wildlife Habitat
The access road footprint crosses 8.5 ha of potential suitable moose habitat
The access road footprint crosses 0.4 ha of potential suitable horned grebe habitat
The access road footprint crosses 4.5 ha of potential suitable bald eagle habitat
The access road footprint crosses 10.5 ha of potential suitable Canada warbler habitat
The access road footprint crosses 19.8 ha of potential suitable common nighthawk habitat
The access road footprint crosses 6.4 ha of potential suitable olive-sided flycatcher habitat
No discernable difference between JK1 and JK2; however, JK1 avoids potential suitable habitat for horned grebe, and crosses slightly less potential suitable habitat for moose, Canada warbler and common nighthawk, and slightly more potential suitable habitat for bald eagle.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-76
Table 3.11B-17: Access Plan Refinement Analysis – Connection to Wawakapewin First Nation (Segment J-K)
Key Factors
Access Plan Refinements
Access Plan Comparison
Connection to Wawakapewin First Nation (Segment J-K)
JK1 (Refined Access Plan)
JK2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
4.3 ha of Category 1 (nursery) habitat
20.2 ha of Category 2 habitat
22.5 ha of Category 3 habitat
The access road footprint crosses 6.2 ha of mapped caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 11.9 ha of mapped caribou (Boreal population) travel corridors (Fall – November)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
3.7 ha of Category 1 (nursery) habitat
23.0 ha of Category 2 habitat
25.8 ha of Category 3 habitat
The access road footprint crosses 6.5 ha of mapped caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 14.1 ha of mapped caribou (Boreal population) travel corridors (Fall – November)
No discernable difference between JK1 and JK2; however, JK1 crosses a slightly smaller area of mapped caribou (Boreal population) travel corridors (Fall – November)
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 25.4 ha of potential suitable wolverine habitat.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 30.7 ha of potential suitable wolverine habitat.
JK1 crosses a smaller area of potential suitable habitat for wolverine
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 3.1 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 2.9 ha of suitable maternity roosting habitat for little brown myotis.
No discernable difference between JK1 and JK2; however, JK1 crosses a slightly larger area of potential suitable maternity roosting habitat for little brown myotis.
Socio-economic Archaeology and Cultural Heritage
1.7 ha of land with archaeological potential in the access road footprint
Archaeology and Cultural Heritage
2.4 ha of land with archaeological potential in the access road footprint
No discernable difference between JK1 and JK2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-77
Table 3.11B-17: Access Plan Refinement Analysis – Connection to Wawakapewin First Nation (Segment J-K)
Key Factors
Access Plan Refinements
Access Plan Comparison
Connection to Wawakapewin First Nation (Segment J-K)
JK1 (Refined Access Plan)
JK2 (Preliminary Access Plan)
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
Kingfisher Lake First Nation
▪ The access footprint crosses summer and winter use trails, traplines, fish spawning areas, fur trapping areas, hunting areas and moose calving areas.
Traditional Land and Resource Use (TLRU)
Kingfisher Lake First Nation
▪ The access footprint crosses summer and winter use trails, traplines, fish spawning areas, fur trapping areas, hunting areas and moose calving areas.
No discernable difference between JK1 and JK2
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
As shown in Table 3.11B-17, the refined access plan proposed in the Final ESR (JK1) presents similar key factor
metrics when compared with the preliminary access plan (JK2) presented in the Draft ESR; however, the access
road footprint for JK1 is smaller. JK1 has more existing road crossings within the access road footprint, and this is
attributed to the fact that the proposed access road for JK1 is mostly on-ROW and primarily follows the existing
winter road from Kingfisher Lake First Nation to Wawakapewin First Nation, and the ROW crosses the existing
winter road in several instances along its length. On the other hand, a large proportion of the access plan proposed
for JK2 included the use of the existing winter roads (identified as “to be upgraded” in the Draft ESR). This resulted
in less existing road crossings for JK2. Overall, the changes in the access road footprint has resulted in JK1
crossing fewer watercourses and waterbodies, a smaller area of natural landcover (terrestrial), and a smaller area
of potential suitable habitat for wolverine. For all the other metrics, there were minor variations in the areas crossed
by each of the access road footprints, leading to no discernable differences between the two.
The potential effects of the Project that include the revised access footprint are predicted to reach the same
conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration of implementation of the commitments
and monitoring in Section 12.0 and the environmental and social management plan in Section 9.0. Therefore,
Wataynikaneyap will be implementing the JK1 access road footprint for the connection to Wawakapewin First
Nation (Segment J-K).
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-78
3.11B-3.2.9 Connection to Kasabonika First Nation (Segment K-L)
This segment of the Project extends from the Wawakapewin First Nation Transformer Station to the Transformer
Station in Kasabonika Lake First Nation. The revised access plan for this segment of the Project is shown in
Annex B (Figures 3.11B-60 to 3.11B-62). The high-level baseline characterization for the revised access road
footprint for the connection to Kasabonika Lake First Nation (Segment K-L) is presented in Table 3.11B-18.
Changes made in the access plan for this segment of the Project between the draft and final ESR includes access
within the 40-m-wide ROW rather than via the nearby existing winter road, off-ROW access spurs between the
ROW and the nearby existing winter road, as well as defining additional off-ROW access around wet areas or
obstacles such as steep slopes or large waterbodies where the installation of crossings is not practical. The metrics
for the access road footprint initially identified for this segment in the Draft ESR, the metrics for the access road
footprint proposed in the Final ESR, and a comparison between the two are also presented in Table 3.11B-18.
The full set of analysis metrics that were considered are presented in Annex A. Generally, habitat for wildlife criteria
is similarly abundant and distributed along both access road footprints. No bald eagle nests or potential
bat hibernacula features were observed along either of the access road footprints during field surveys in 2016
and 2017.
Table 3.11B-18: Access Plan Refinement Analysis – Connection to Kasabonika First Nation (Segment K-L)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Kasabonika First Nation
(Segment K-L)
KL1 (Refined Access Plan)
KL2 (Preliminary Access Plan)
Technical Size
Access roads are 39.3 km in length.
The access road footprint is 23.6 ha.
Size
Access roads are 38.8 km in length.
The access road footprint is 23.3 ha.
No discernable difference between KL1 and KL2
Existing Infrastructure
There are 2 existing roads that cross the access road footprint.
Existing roads cross the access road footprint 26 times.
There is 1 other linear corridor that crosses the access road footprint.
Existing Infrastructure
There are 3 existing roads cross the access road footprint.
Existing roads cross the access road footprint 6 times.
There are 2 other linear corridors that cross the access road footprint
KL1 is crossed more times by existing roads than KL2
Natural Environment Wetlands(a)
Area of mapped wetlands in the access road footprint is 4.2 ha.
Wetlands(a)
Area of mapped wetlands in the access road footprint is 4.9 ha.
No discernable difference between KL1 and KL2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-79
Table 3.11B-18: Access Plan Refinement Analysis – Connection to Kasabonika First Nation (Segment K-L)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Kasabonika First Nation
(Segment K-L)
KL1 (Refined Access Plan)
KL2 (Preliminary Access Plan)
Waterbodies and Watercourses(b)
The access road footprint crosses 3 watercourses.
The access road footprint is not intersected by any waterbodies.
Waterbodies and Watercourses(b)
The access road footprint crosses 14 watercourses.
The access road footprint intersects 1 waterbody for an area of 0.0 ha
KL1 intersects fewer watercourses and waterbodies than KL2.
Natural Environment (cont’d)
Vegetation(c)
The access road footprint crosses:
▪ 21.0 ha of natural landcover (terrestrial);
▪ 0.2 ha of anthropogenic disturbance; and
▪ 1.5 ha of natural disturbance.
Vegetation(c)
The access road footprint crosses:
▪ 21.5 ha of natural landcover (terrestrial);
▪ 0.0 ha of anthropogenic disturbance; and
▪ 0.9 ha of natural disturbance.
No discernable difference between KL1 and KL2.
Wildlife
The access road footprint crosses 7.0 ha of suitable moose habitat
The access road footprint does not cross any suitable horned grebe habitat.
The access road footprint rosses 4.6 ha of suitable bald eagle habitat
The access road footprint crosses 8.1 ha of Canada warbler habitat
The access road footprint crosses 13.4 ha of suitable common nighthawk habitat
The access road footprint crosses 6.6 ha of olive-sided flycatcher habitat
Wildlife
The access road footprint crosses 6.7 ha of suitable moose habitat
The access road footprint crosses 0.1 ha of suitable horned grebe habitat
The access road footprint crosses 2.5 ha of suitable bald eagle habitat
The access road footprint crosses 8.6 ha of Canada warbler habitat
The access road footprint crosses 13.1 ha of suitable common nighthawk habitat
The access road footprint crosses 5.1 ha of olive-sided flycatcher habitat
No discernable difference between KL1 and KL2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-80
Table 3.11B-18: Access Plan Refinement Analysis – Connection to Kasabonika First Nation (Segment K-L)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Kasabonika First Nation
(Segment K-L)
KL1 (Refined Access Plan)
KL2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 8.9 ha of Category 2 habitat
The access road footprint crosses 14.9 ha of Category 3 habitat.
The access road footprint crosses 1.3 ha of caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 3.2 ha of caribou (Boreal population) travel corridors (Fall – November)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 9.3 ha of Category 2 habitat
The access road footprint crosses 14.0 ha of Category 3 habitat
The access road footprint crosses 1.2 ha of caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 3.3 ha of caribou (Boreal population) travel corridors (Fall – November)
No discernable difference between KL1 and KL2
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 22.5 ha of suitable wolverine habitat.
One boulder field or blowdown area representing potential den habitat was observed within the access road footprint during 2016 and 2017 field surveys.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 22.4 ha of suitable wolverine habitat.
One boulder field or blowdown area representing potential den habitat was observed within the access road footprint during 2016 and 2017 field surveys.
No discernable difference between KL1 and KL2
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 2.2 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 0.9 ha of suitable maternity roosting habitat for little brown myotis.
No discernable difference between KL1 and KL2
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-81
Table 3.11B-18: Access Plan Refinement Analysis – Connection to Kasabonika First Nation (Segment K-L)
Key Factors
Access Plan Refinements
Access Plan Comparison Connection to Kasabonika First Nation
(Segment K-L)
KL1 (Refined Access Plan)
KL2 (Preliminary Access Plan)
Socio-economic Archaeology and Cultural Heritage
The access road footprint intersects 0.8 ha of land with archaeological potential.
Tourism and Recreation
The access road footprint intersects 1 Bait Harvest Area for an area of 16.1 ha
Archaeology and Cultural Heritage
The access road footprint intersects 1.4 ha of land with archaeological potential.
Tourism and Recreation
The access road footprint intersects 1 Bait Harvest Area for an area of 15.1 ha
No discernable difference between KL1 and KL2.
Aboriginal considerations
Traditional Land and Resource Use (TLRU)
Kasabonika Lake First Nation
▪ The access road footprint crosses one trapline and a proposed landfill area.
Wawakapewin First Nation
▪ The access road footprint crosses one trapline and a firewood collection area.
Traditional Land and Resource Use (TLRU)
Kasabonika Lake First Nation
▪ The access road footprint crosses one trapline and a proposed landfill area.
Wawakapewin First Nation
▪ The access road footprint crosses one trapline and a firewood collection area.
No discernable difference between KL1 and KL2
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-82
As shown in Table 3.11B-18, the refined access plan proposed in the Final ESR (KL1) presents similar key factor
metrics when compared with the preliminary access plan (KL2) presented in the Draft ESR. JK1 has more existing
road crossings within the access road footprint, and this is attributed to the fact that the proposed access road for
JK1 is mostly on-ROW and primarily follows the existing winter roads from Wawakapewin First Nation to
Kasabonika Lake First Nation, and the ROW crosses the existing winter roads in several instances along its length.
On the other hand, a large proportion of the access plan proposed for JK2 included the use of the existing winter
roads (identified as “to be upgraded” in the Draft ESR). This resulted in less existing road crossings for JK2. JK1
has significantly less watercourse crossings compared to KL2. This is primarily due to the realignment of access
plan for KL1 within the 40-m-wide ROW rather than via the nearby existing winter road, as well as additional off-
ROW access which has been included to link between the ROW and existing winter road, as well as to avoid wet
areas. For all the other metrics, there were minor variations in the areas crossed by each of the access road
footprints, leading to no discernable differences between the two.
The potential effects of the Project that include the revised access footprint are predicted to reach the same
conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration of implementation of the commitments
and monitoring in Section 12.0 and the environmental and social management plan in Section 9.0. This includes
applying mitigation to limit disturbance to active wolverine dens if active den sites are observed during Project
construction. Therefore, Wataynikaneyap will be implementing the JK1 access road footprint for the Connection
to Kasabonika Lake First Nation (Segment K-L).
3.11B-3.2.10 Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation (Segment K-M-N)
This segment of the Project extends from the Wawakapewin First Nation Transformer Station to the transformer
stations in both Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation. The revised access plan for this
segment of the Project is shown in Annex B (Figure 3.11B-60 and Figures 3.11B-63 to 3.11B-67). The high-level
baseline characterization for the revised access road footprint for the connection to Kitchenuhmaykoosib
Inninuwug and Wapekeka First Nation (Segment K-M-N) is presented in Table 3.11B-19. Changes made in the
access plan for this segment of the Project between the Draft and Final ESR includes adjustment of the access
plan to align with refinements to the ROW, and as well as defining additional off-ROW access around wet areas
or obstacles such as steep slopes or large waterbodies where the installation of crossings is not practical. Within
the Draft ESR, the access road between Kitchenuhmaykoosib Inninuwug and Wapekeka was defined as a
potential existing winter road to be upgraded by the Project. Within the Final ESR, it is defined that this road could
be used in its current condition if required. As noted in Section 4.0, there is an ongoing project, the Proposed DGS
Upgrade and Micro Grid Connection (DGS Upgrade and Micro Grid Connection) to connect the two communities
with a 25 kV connection. Based on the current status of the Project, it is likely that the Phase 2 project will connect
to this project at the KI/Wapekeka junction switching Station, rather than requiring extension to both communities,
The metrics for the access road footprint initially identified for this segment in the Draft ESR, the metrics for the
access road footprint proposed in the Final ESR, and a comparison between the two are also presented in
Table 3.11B-19. The full set of analysis metrics that were considered are presented in Annex A. Generally, habitat
for wildlife criteria is similarly abundant and distributed along both access road footprints. No bald eagle nests or
potential bat hibernacula features were observed along either of the access road footprints during field surveys in
2016 and 2017.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-83
Table 3.11B-19: Access Plan Refinement Analysis – Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation (Segment K-M-N)
Key Factors
Access Plan Refinements
Access Plan Comparison
Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation
(Segment K-M-N)
KMN1 (Refined Access Plan)
KMN2 (Preliminary Access Plan)
Technical Size
Access roads are 64.5 km in length.
The access road footprint is 38.8 ha.
Size
Access roads are 77.3 km in length.
The access road footprint is 46.4 ha.
KMN1 has shorter access roads and covers less area than KMN2.
Existing Infrastructure
There are 4 existing roads that cross the access road footprint.
Existing roads cross the access road footprint 12 times.
There is 1 other linear corridor that crosses the access road footprint.
Existing Infrastructure
There are 6 existing roads cross the access road footprint.
Existing roads cross the access road footprint 23 times.
There are 8 other linear corridors cross the access road footprint
KMN1 is crossed fewer times by existing roads than KMN2.
Natural Environment Wetlands(a)
Area of mapped wetlands in the access road footprint is 12.7 ha.
Wetlands(a)
Area of mapped wetlands in the access road footprint is 16.7 ha.
No discernable difference between KMN1 and KMN2.
Waterbodies and Watercourses(b)
The access road footprint crosses 16 watercourses.
The access road footprint intersects 2 waterbodies for an area of 0.0 ha
Waterbodies and Watercourses(b)
The access road footprint crosses 26 watercourses.
The access road footprint intersects 7 waterbodies for an area of 0.2 ha
KMN1 intersects fewer watercourses and waterbodies than KMN2.
Vegetation(c)
The access road footprint crosses:
▪ 9.4 ha of natural landcover (terrestrial);
▪ 0.0 ha of anthropogenic disturbance; and
▪ 0.1 ha of natural disturbance.
▪ 0.6 ha of mapped occurrences of provincially tracked vegetation species.
Vegetation(c)
The access road footprint crosses:
▪ 16.8 ha of natural landcover (terrestrial);
▪ 0.0 ha of anthropogenic disturbance; and
▪ 0.1 ha of natural disturbance; and
▪ 3.4 ha of mapped occurrences of provincially tracked vegetation species.
No discernable difference between KMN1 and KMN2. However, KMN1 intersects less area of natural landcover (terrestrial) and area of mapped occurrences of provincially tracked vegetation species than KMN2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-84
Table 3.11B-19: Access Plan Refinement Analysis – Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation (Segment K-M-N)
Key Factors
Access Plan Refinements
Access Plan Comparison
Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation
(Segment K-M-N)
KMN1 (Refined Access Plan)
KMN2 (Preliminary Access Plan)
Natural Environment (cont’d)
Wildlife
The access road footprint crosses 5.2 ha of suitable moose habitat.
The access road footprint crosses 0.0 ha of suitable horned grebe habitat.
The access road footprint rosses 5.2 ha of suitable bald eagle habitat.
The access road footprint crosses 3.3 ha of Canada warbler habitat.
The access road footprint crosses 2.9 ha of suitable common nighthawk habitat.
The access road footprint crosses 6.4 ha of olive-sided flycatcher habitat.
The access road footprint crosses 0.6 ha of mapped potential habitat supporting provincially tracked wildlife species.
Wildlife
The access road footprint crosses 4.1 ha of suitable moose habitat.
The access road footprint crosses 0.1 ha of suitable horned grebe habitat.
The access road footprint crosses 7.3 ha of suitable bald eagle habitat.
The access road footprint crosses 7.1 ha of Canada warbler habitat.
The access road footprint crosses 5.5 ha of suitable common nighthawk habitat.
The access road footprint crosses 6.0 ha of olive-sided flycatcher habitat.
The access road footprint does not cross any mapped potential habitat supporting provincially tracked wildlife species.
KMN1 crosses less habitat suitable for bald eagle, Canada warbler and common nighthawk.
KMN2 crosses less habitat suitable for moose and area of mapped potential habitat supporting provincially tracked wildlife species.
There is no discernable difference between the area of suitable habitat crossed for horned grebe and olive-sided flycatcher between KMN1 and KMN2.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-85
Table 3.11B-19: Access Plan Refinement Analysis – Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation (Segment K-M-N)
Key Factors
Access Plan Refinements
Access Plan Comparison
Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation
(Segment K-M-N)
KMN1 (Refined Access Plan)
KMN2 (Preliminary Access Plan)
Natural Environment (cont’d)
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 32.0 ha of Category 2 habitat.
The access road footprint crosses 6.7 ha of Category 3 habitat.
The access road footprint crosses 3.5 ha of caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 12.9 ha pf caribou (Boreal population) travel corridors (Fall – November).
Threatened and endangered species or their Habitat (Caribou (Boreal population))
The access road footprint crosses 38.4 ha of Category 2 habitat.
The access road footprint crosses 7.8 ha of Category 3 habitat.
The access road footprint crosses 3.8 ha of caribou (Boreal population) travel corridors (Spring – April).
The access road footprint crosses 13.2 ha of caribou (Boreal population) travel corridors (Fall – November)
No discernable difference between KM1 and KM2
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 9.4 ha of suitable wolverine habitat.
No boulder fields or blowdown areas representing potential den habitat were observed within the access road footprint during 2016 and 2017 field surveys.
Threatened and endangered species or their Habitat (Wolverine)
The access road footprint crosses 16.9 ha of suitable wolverine habitat.
One boulder field or blowdown area representing potential den habitat was observed within the access road footprint during 2016 and 2017 field surveys.
KMN1 crosses less habitat suitable for wolverine and no potential den habitat was observed within the access road footprint during 2016 and 2017 field surveys.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 1.9 ha of suitable maternity roosting habitat for little brown myotis.
Threatened and endangered species or their Habitat (Little brown myotis)
The access road footprint crosses 7.3 ha of suitable maternity roosting habitat for little brown myotis.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-86
Table 3.11B-19: Access Plan Refinement Analysis – Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation (Segment K-M-N)
Key Factors
Access Plan Refinements
Access Plan Comparison
Connection to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation
(Segment K-M-N)
KMN1 (Refined Access Plan)
KMN2 (Preliminary Access Plan)
Socio-economic Archaeology and Cultural Heritage
The access road footprint intersects 2.0 ha of land with archaeological potential.
Tourism and Recreation
The access road footprint does not cross any Bait Harvest Areas.
Archaeology and Cultural Heritage
The access road footprint intersects 2.6 ha of land with archaeological potential.
Tourism and Recreation
The access road footprint intersects 4 Bait Harvest Areas for an area of 15.1 ha
KMN1 intersects a smaller area of archaeological potential and no BHAs.
Aboriginal Considerations
Traditional Land and Resource Use (TLRU)
K.I. First Nation
▪ The access footprint crosses one trapline, and a general hunting area.
Wapekeka First Nation
▪ The access footprint crosses a ski-doo trail, a trapline and an active hunting area,
Wawakapewin First Nation
▪ The access footprint crosses a firewood collection area an active fishing area.
Traditional Land and Resource Use (TLRU)
K.I. First Nation
▪ The access footprint crosses one trapline, a harvesting wood/picnic area, a blueberry harvesting area, and a general hunting area.
Wapekeka First Nation
▪ The access footprint crosses a trapline and an active hunting area,
Wawakapewin First Nation
▪ The access footprint crosses an active fishing area.
KM1 intersects fewer TLRU lines and polygons than KM2
a) All wetlands are understood to be unevaluated.
b) In employing a conservative approach, this assessment assumes that all waterbodies and watercourses have the potential to support fish and fish habitat.
c) Waterbodies not including watercourses. d) Natural landcover (terrestrial) includes bedrock, bog-open, bog-treed, fen-open, fen-treed, forest-dense deciduous, forest-dense coniferous, forest-dense mixed, forest-regenerating depletion, and forest-sparse landcover types. Anthropogenic disturbance includes forest depletion-cuts and settlement/infrastructure. Natural disturbance includes forest depletion-burns.
APPENDIX 3.11B Analysis of Access Plan Refinements
November 2018 Report No. 18102677 GAL-005-REP-V1
App3.11B-87
As shown in Table 3.11B-19, the refined access plan proposed in the Final ESR (KMN1) presents a moderate
decrease on the key factor metrics presented when compared with the preliminary access plan (KMN2) presented
in the Draft ESR. KMN1 intersects fewer existing roads, waterbodies and watercourses, while disturbing smaller
areas of suitable species at risk habitat and natural land cover. This decrease in footprint for the KMN1 access
plan can be attributed to minimizing the access road footprint through on-ROW access and utilization of the
existing winter roads between Kitchenuhmaykoosib Inninuwug and Wapekeka not anticipated to require upgrades.
The potential effects of the Project that include the revised access footprint are predicted to reach the same
conclusions for the EA criteria in Sections 5.0 to 8.0; and in consideration of implementation of the commitments
and monitoring in Section 12.0 and the environmental and social management plan in Section 9.0. This includes
applying mitigation to limit disturbance to active wolverine dens if active den sites are observed during Project
construction. Therefore, Wataynikaneyap will be implementing the KMN1 access road footprint for the Connection
to Kitchenuhmaykoosib Inninuwug and Wapekeka First Nation (Segment K-M-N).
REFERENCES
MNR (Ontario Ministry of Natural Resources). 2003. Class Environmental Assessment for MNR Resource
Stewardship and Facility Development Projects.
MNRF (Ministry of Natural Resources and Forestry). 2015. Land Information Ontario. Electronic data.
https://www.ontario.ca/page/land-information-ontario
MNRF. 2017. Land Information Ontario. Electronic data. https://www.ontario.ca/page/land-information-ontario
NHIC (Natural Heritage Information Centre). 2015. Natural Heritage Information Centre: Get Natural Heritage
Information. Electronic data. https://www.ontario.ca/page/get-natural-heritage-information.
NHIC. 2017. Natural Heritage Information Centre: Get Natural Heritage Information. Electronic data.
https://www.ontario.ca/page/get-natural-heritage-information.
NRCan (Natural Resources Canada). 2016. Earth Sciences Sector, GeoGratis, CanVec Data Product.
Electronic data. http://www.geogratis.gc.ca.
NRCan. 2017. Earth Sciences Sector, GeoGratis, CanVec Data Product. Electronic data.
http://www.geogratis.gc.ca.