draft hazop study

16
Sample-Cokeoven Licensed To : HAMSAGARS HAMS-GPS : HAZOP Study for : ACTION REPORT Project/Plant stage at HAZOP : Detailed engineering stage Date: 14/01/2012:53:45 PM Part-1a Action by Report- Design intension wise Design intention (Operation): A.0 Description of design intention: Whether Cokeoven Technology procured with HAZOP Study Report? Node: A.0 Sop reference: N.A. Hazop study Number: A.0 P and I Dwg. No. N.A. Parameter : A.0 HAZOP GUIDE WORD RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department Action Date For future Technology Procurement agreements, may make it mandatory for all Projects to include HAZOP study as part of Technology package. (1) NO (NOT OR NONE) Future Project Authorities Action taken: For future Technology Procurement agreements, may make it mandatory for all Projects to include HAZOP study as part of Technology package. SIL/LOP: 1 Design intention (Operation): A. Separate Gas and Liquid at required Temperature Description of design intention: Separate Gas and Liquid at required Temperature Node: A.1 Gas from Battery to byproduct Sop reference: N.A. Hazop study Number: A.1 P and I Dwg. No. PD-1055 Parameter : A.1 Temperature HAZOP GUIDE WORD RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department Action Date 1. Consider HT Alarm for gas 2. Provide LP Alarm for ammonia liquor in CCR 3. Bleeding of gas requires ignition and auto ignition to be provided (2) MORE OF Project authority Action taken: 1. Consider HT Alarm for gas 2. Provide LP Alarm for ammonia liquor in CCR 3. Bleeding of gas requires ignition and auto ignition to be provided SIL/LOP: 1 Provide on all cases of piping & all Flanges as per OISD-110. Normally bonding is done using round wires. Ihis is not correct. It is necessary to follow for Strip specs IS-3043 & IS-7689 and OISD-108. (17) STATIC CHARGE Project authority Action taken: Provide on all cases of piping & all Flanges as per OISD-110. Normally bonding is done using round wires. Ihis is not correct. It is necessary to follow for Strip specs IS-3043 & IS-7689 and OISD-108. SIL/LOP: 1 Design intention (Operation): A.1 Separate Gas and Liquid at required Pressure Description of design intention: Separate Gas and Liquid at required Pressure Node: A.1 Gas fro Battery to Byproduct Sop reference: N.A. Hazop study Number: A.1.1 P and I Dwg. No. PD-1055 Parameter : A.1 Pressure HAZOP GUIDE WORD RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department Action Date As under High Temperature (2) MORE OF Project authority Action taken: As under High Temperature SIL/LOP: N.A. Friday, January 14, 2012 Page 1 of 11 Friday, January 14, 201 Licensed To : HAMSAGARS 30

Upload: mac1677

Post on 25-Nov-2015

43 views

Category:

Documents


0 download

DESCRIPTION

HAZOP

TRANSCRIPT

  • Sample-CokeovenLicensed To : HAMSAGARS

    HAMS-GPS : HAZOP Study for :

    ACTION REPORT

    Project/Plant stage at HAZOP : Detailed engineering stage

    Date: 14/01/2012:53:45 PM

    Part-1a Action by Report- Design intension wise

    Design intention (Operation): A.0

    Description of design intention:

    Whether Cokeoven Technology procured with HAZOP Study Report?

    Node: A.0

    Sop reference: N.A.Hazop study Number: A.0P and I Dwg. No. N.A.

    Parameter : A.0

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    For future Technology Procurement agreements, may make it mandatory for all Projects to include HAZOP study as part of Technology package.

    (1) NO (NOT OR NONE)

    Future Project Authorities

    Action taken:

    For future Technology Procurement agreements, may make it mandatory for all Projects to include HAZOP study as part of Technology package.

    SIL/LOP: 1

    Design intention (Operation): A. Separate Gas and Liquid at required Temperature

    Description of design intention:

    Separate Gas and Liquid at required Temperature

    Node: A.1 Gas from Battery to byproduct

    Sop reference: N.A.Hazop study Number: A.1P and I Dwg. No. PD-1055

    Parameter : A.1 Temperature

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    1. Consider HT Alarm for gas2. Provide LP Alarm for ammonia liquor in CCR 3. Bleeding of gas requires ignition and auto ignition to be provided

    (2) MORE OF Project authority

    Action taken:

    1. Consider HT Alarm for gas2. Provide LP Alarm for ammonia liquor in CCR 3. Bleeding of gas requires ignition and auto ignition to be providedSIL/LOP: 1

    Provide on all cases of piping & all Flanges as per OISD-110. Normally bonding is done using round wires. Ihis is not correct. It is necessary to follow for Strip specs IS-3043 & IS-7689 and OISD-108.

    (17) STATIC CHARGE

    Project authority

    Action taken:

    Provide on all cases of piping & all Flanges as per OISD-110. Normally bonding is done using round wires. Ihis is not correct. It is necessary to follow for Strip specs IS-3043 & IS-7689 and OISD-108.SIL/LOP: 1

    Design intention (Operation): A.1 Separate Gas and Liquid at required Pressure

    Description of design intention:

    Separate Gas and Liquid at required Pressure

    Node: A.1 Gas fro Battery to Byproduct

    Sop reference: N.A.Hazop study Number: A.1.1P and I Dwg. No. PD-1055

    Parameter : A.1 Pressure

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    As under High Temperature(2) MORE OF Project authority

    Action taken:

    As under High Temperature

    SIL/LOP: N.A.

    Friday, January 14, 2012 Page 1 of 11Friday, January 14, 201

    Licensed To : HAMSAGARS 30

  • Part-1a Action by Report- Design intension wise

    Design intention (Operation): A.2 To cool the gas by 2-stage Process water chilled water from 80 to 22 Deg C.

    Description of design intention:

    To cool the gas by 2-stage Process water chilled water from 80 to 22 Deg C.

    Node: A.2 Primary Gas cooler

    Sop reference: N.A.Hazop study Number: A.2P and I Dwg. No. PD-1055

    Parameter : A.2 Temperature

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    Provide Nitrogen injection facility for purging at PGC(1) NO (NOT OR NONE)

    Project authority

    Action taken:

    Provide Nitrogen injection facility for purging at PGC

    SIL/LOP: N.A.

    Ptovide Steam line to lines CLLG-10abc & 18abc(2) MORE OF Project authority

    Action taken:

    Ptovide Steam line to lines CLLG-10abc & 18abc

    SIL/LOP: N.A.

    Provide drain point for water line in PGC(16) MAINTENANCE

    Project authority

    Action taken:

    Provide drain point for water line in PGC

    SIL/LOP: N.A.

    Provide Air vent at CWRLG01abc(19) SAFETY Project authority

    Action taken:

    Provide Air vent at CWRLG01abc

    SIL/LOP: 2

    Design intention (Operation): A.3 To eliminate tar residue from gas

    Description of design intention:

    None

    Node: A.3 ETP

    Sop reference: N.A.Hazop study Number: A.3P and I Dwg. No. PD-1055

    Parameter : A.3 Voltage

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    Provide positive isolation of Gas Equipment to ensure LOTO.(16) MAINTENANCE

    Project authority

    Action taken:

    Provide positive isolation of Gas Equipment to ensure LOTO.

    SIL/LOP: 1

    Design intention (Operation): A.3.1 To ensure Oxygen content in the gas ;ess than 0.8% vy vol.

    Description of design intention:

    To ensure Oxygen content in the gas ;ess than 0.8% vy vol.

    Node: A.3.1 ETP

    Sop reference: N.A.Hazop study Number: A.3.1P and I Dwg. No. ES.LG1.GY.22-0103

    Parameter : A.3.1 Oxygen

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    Friday, January 14, 2011 Page 2 of 11Friday, January 14, 2012

    Licensed To : HAMSAGARS 31

  • Part-1a Action by Report- Design intension wise

    1. Consider airtight explosion flap or a rupture disk as appropriate that automatically relieves explosion pressure.

    (2) MORE OF Project authority

    Action taken:

    1. Consider airtight explosion flap or a rupture disk as appropriate that automatically relieves explosion pressure.

    SIL/LOP: 1

    Design intention (Operation): B.1 To suck the gas from cokeoven battery and supply to byproduct unit for cleaning

    Description of design intention:

    None

    Node: B.1.1 Exhauster

    Sop reference: N.A.Hazop study Number: B.1.1P and I Dwg. No. ES.LG1.GY.22-0104

    Parameter : B.1.1 Output Pressure

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    Provide independent drain valves CLLG25ab, 29ab.(1) NO (NOT OR NONE)

    Project authority

    Action taken:

    Provide independent drain valves CLLG25ab, 29ab.

    SIL/LOP: 2

    Down straem SOP adherence will keep down stream pressure under control

    (2) MORE OF Production

    Action taken:

    Down straem SOP adherence will keep down stream pressure under control

    SIL/LOP: 1

    Provide CO detector in the Exhauster house(19) SAFETY Project authority

    Action taken:

    Provide CO detector in the Exhauster house

    SIL/LOP: 1

    Design intention (Operation): C.1 To cool the Gas before sending to Desulphurizer columns from 45 deg. C to 25 Deg. C

    Description of design intention:

    To cool the Gas before sending to Desulphurizer columns from 45 deg. C to 25 Deg. C

    Node: C.1 Precooling Tower of Desulphurizer

    Sop reference: N.A.Hazop study Number: C.1P and I Dwg. No. ES.TL1.GY.22-0104

    Parameter : C.1 Pressure drop across column

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    1. Provide positive isolation system to enable short duration maintenance under LOTO.

    (16) MAINTENANCE

    Project authority

    Action taken:

    1. Provide positive isolation system to enable short duration maintenance under LOTO.

    SIL/LOP: 1

    Design intention (Operation): D.1 To remove H2S from Cokeoven gas

    Description of design intention:

    To remove H2S from Cokeoven gas

    Node: D.1 Desulphurization tower

    Sop reference: N.A.Hazop study Number: D.1P and I Dwg. No. ES.TL1.GY.22-0104

    Parameter : D.1 Pressure

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    Friday, January 14, 2011 Page 3 of 11Friday, January 14, 2012

    Licensed To : HAMSAGARS 32

  • Part-1a Action by Report- Design intension wise

    Provide Nitrogen inlet point at gas inlet line to both towers(1) NO (NOT OR NONE)

    Project authority

    Action taken:

    Provide Nitrogen inlet point at gas inlet line to both towers

    SIL/LOP: 1

    Provide positive isolation system to enable short duration maintenance under LOTO.

    (16) MAINTENANCE

    Project authority

    Action taken:

    Provide positive isolation system to enable short duration maintenance under LOTO.

    SIL/LOP: N.A.

    Provide isolation valves for both towers at outlet lines of water seal outlet VTL-01AB for both towers

    (19) SAFETY Project authority

    Action taken:

    Provide isolation valves for both towers at outlet lines of water seal outlet VTL-01AB for both towers

    SIL/LOP: N.A.

    Design intention (Operation): D.1 To remove H2S from Cokeoven gas

    Description of design intention:

    To remove H2S from Cokeoven gas

    Node: D.1 Desulphurization tower

    Sop reference: N.A.Hazop study Number: D.1.1P and I Dwg. No. ES.TL1.GY.22-0104

    Parameter : D.1 Temperature of Solution

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    Provide Steam flushing at scrub liquor side and water flushing facilities at water side of heat exchanger tubes

    (2) MORE OF Project authority

    Action taken:

    Provide Steam flushing at scrub liquor side and water flushing facilities at water side of heat exchanger tubes

    SIL/LOP: 1

    Design intention (Operation): E.1 To regenerate Sulphur from H2S solution

    Description of design intention:

    To regenerate Sulphur from H2S solution

    Node: E.1 Sulphur production

    Sop reference: N.A.Hazop study Number: E.1P and I Dwg. No. ES.TL1.GY.22-0104 (2)

    Parameter : E.1 Air flow

    HAZOP GUIDE WORD

    RECOMMENDATION FOR BETTER HAZARD CONTROL Action by: Name , Designation, Department

    Action Date

    Provide Air flow controller for Tower A also(1) NO (NOT OR NONE)

    Project authority

    Action taken:

    Provide Air flow controller for Tower A also

    SIL/LOP: N.A.

    As under No-Air flow(3) LESS OF Project authority

    Action taken:

    As under No-Air flow

    SIL/LOP: N.A.

    Provide a Exhaust Hood above the Sulphur Foam Tank and release the vapours at suitable height or send to scrubber as appropriate

    (19) SAFETY Project authority

    Action taken:

    Provide a Exhaust Hood above the Sulphur Foam Tank and release the vapours at suitable height or send to scrubber as appropriate

    SIL/LOP: 0

    Friday, January 14, 2011 Page 4 of 11Friday, January 14, 2012

    Licensed To : HAMSAGARS 33

  • HAMS-GPS : HAZOP Study for : Sample-CokeovenHAMS-GPS : HAZOP Study for : Project/Plant stage at HAZOP : Detailed engineering stage

    Part-2a HAZOP Report-Recommendations only

    Design intention (Operation):

    A.0

    Hazop study Number: A.0

    Licensed To : HAMSAGARS

    P and I Dwg. No. : N.A.

    Sop reference: N.A.

    Existing controls:Units:

    Control Range:

    Description of design intention:

    Whether Cokeoven Technology procured with HAZOP Study Report?

    A.0

    Parameter. : A.0Node:

    HAZOP GUIDE WORD

    LIKELY DEVIATION LIKELY CAUSES LIKELY CONSEQUENCES

    PRESENT CONTROLS THEIR

    LIMITATIONS

    RECOMMENDATI-ON FOR BETTER

    HAZARD CONTROL

    HAZOP GUIDE WORD

    Cokeoven technolohy has not been procured with HAZOP study

    Technology procurements did not include requirement of HAZOP study

    Hazards and Operability issues required to be addressed at technology procurement stage not covered may result in retention of certain Hazaeds and operability issues

    Pre-detailed Engineering HAZOP being done.

    For future Technology Procurement agreements, may make it mandatory for all Projects to include HAZOP study as part of Technology package.

    (1) NO (NOT OR NONE)

    (1) NO (NOT OR NONE)

    Action by: Future Project AuthoritiesRISK LEVEL: Risk level: MEDIUM DAMAGE and LOW CHANCE SIL/LOP 1Documentation

    Friday, January 14, 2011 Page 1 of 56Friday, January 14, 2012

    Licensed To : HAMSAGARS 52

  • Part-2a HAZOP Report-Recommendations only

    Any other observations

    Nil

    Nil

    n

    Any other observations

    Nil

    Nil

    n

    Design intention (Operation):

    A. Separate Gas and Liquid at required Temperature

    Hazop study Number: A.1

    Licensed To : HAMSAGARS

    P and I Dwg. No. : ES.LG1.GY.22-0103

    Sop reference: N.A.

    Existing controls: Temperature PressureUnits: Deg C mm WC

    Control Range: 75-85 -120 to -300

    Description of design intention:

    Separate Gas and Liquid at required Temperature

    A.1 Gas from Battery to byproduct

    Parameter. : A.1 TemperatureNode:

    HAZOP GUIDE WORD

    LIKELY DEVIATION LIKELY CAUSES LIKELY CONSEQUENCES

    PRESENT CONTROLS THEIR

    LIMITATIONS

    RECOMMENDATI-ON FOR BETTER

    HAZARD CONTROL

    HAZOP GUIDE WORD

    Friday, January 14, 2011 Page 2 of 56Friday, January 14, 2012

    Licensed To : HAMSAGARS 53

  • Part-2b HAZOP Full Report

    Any other observations

    Nil

    Nil

    Nil

    Any other observations

    Nil

    Nil

    Nil

    HAZOP team: Name, Designation, Department

    1. Dr. Ram S. Hamsagar, Chair person,2. Mr. Sunil Hamsagar, Softer Simulation Expert,3. Mr. Amar Bountra, Process,4. Mr. Sukumar, Process,5. Mr. Yogendra Babu, Engg,6. Mr. Rakesh Kumar, Engg (Electrical),7. Mr. Sethu Madhavan, Engg (Aut

    8. Mr. L. N. Kumar, Engg (Safety), 9. Mr. Pramod, Engg-Env, 10. Mr. KB Panchal, Safety11. Ms. Shikha Sirohi, HSE, 12. Mr. Ankur, Proj Planning - EPIL, 13. Mr. Eldose, Proj quality, EPIL14. Mr. Bhaskar, Proj Maint, EPIL15. Mr. V. Subramanium, EPIL

    SIL Generalized View

    4 Potential for fatalities in the community

    3 Potential for multiple fatalities

    2 Potential for major serious injuries or one fatality

    1 Potential for minor injuries

    Friday, January 14, 2012 Page 36 of 36Friday, January 14, 2011

    Licensed To : HAMSAGARS 143

  • HAMS-GPS : HAZOP Study for : Sample -CokeovenLicensed To : HAMSAGARS

    HAMS-GPS : HAZOP Study for :

    Part-3 RBI-matrix.

    Summary of RISK BASED INVESTIGATION (RBI) MATRIX

    0

    0

    0

    0

    0

    5

    30

    5

    0

    0

    2

    0

    0

    0

    0

    0

    0

    0

    0

    0

    556 0 0 0 0

    40 2 0 0

    5

    32

    5

    0

    556

    556 598

    93.0 6.7 0.3 0.0 0.0

    93.0

    0.8

    5.4

    0.8

    0.0

    TOTAL

    %

    TOTAL %

    HIGH

    MEDIUM HIGH

    MEDIUM

    LOW

    0

    0

    7

    35

    0.00

    0.00

    1.17

    5.85

    598

    100.0

    100.00

    Chance levels ----------->

  • HAMS-GPS : HAZOP Study for : Sample -CokeovenLicensed To : HAMSAGARS

    HAMS-GPS : HAZOP Study for :

    Summary of RBI-Matrix (conforming to European Process Safety Center's Standard) for selected HAZOP Studies: Date: 11/6/2010 1:00:42 PM

    Design intention (Operation):

    Number of Risk (Damage-Consequence) level areasMEDIUMMEDIUM

    HIGHHIGH LOWNum.

    Guide Words

    SAFE

    Part-4a Overall Risk levels-Design intension wise

    10A. Separate Gas and Liquid at required Temperature

    0 2110A. Separate Gas and Liquid at required Temperature

    0 212 11

    00A.0

    0 2200A.0

    0 221 11

    00A.1 Separate Gas and Liquid at required Pressure

    0 2300A.1 Separate Gas and Liquid at required Pressure

    0 230 00

    10A.2 To cool the gas by 2-stage Process water chilled water from 80 to 22 Deg C. 0 2210A.2 To cool the gas by 2-stage Process water chilled water from 80 to 22 Deg C. 0 221 00

    10A.3 To eliminate tar residue from gas

    0 2210A.3 To eliminate tar residue from gas

    0 221 00

    10A.3.1 To ensure Oxygen content in the gas ;ess than 0.8% vy vol.

    0 2210A.3.1 To ensure Oxygen content in the gas ;ess than 0.8% vy vol.

    0 221 00

    00B.1 To suck the gas from cokeoven battery and supply to byproduct unit for cleaning 0 2300B.1 To suck the gas from cokeoven battery and supply to byproduct unit for cleaning 0 230 00

    10B.1 To suck the gas from cokeoven battery and supply to byproduct unit for cleaning 0 2010B.1 To suck the gas from cokeoven battery and supply to byproduct unit for cleaning 0 203 22

    10C.1 To cool the Gas before sending to Desulphurizer columns from 45 deg. C to 25 Deg. C 0 2210C.1 To cool the Gas before sending to Desulphurizer columns from 45 deg. C to 25 Deg. C 0 221 00

    00D.1 To remove H2S from Cokeoven gas

    0 2200D.1 To remove H2S from Cokeoven gas

    0 221 11

    00D.1 To remove H2S from Cokeoven gas

    0 2200D.1 To remove H2S from Cokeoven gas

    0 221 11

    00E.1 To regenerate Sulphur from H2S solution

    0 2200E.1 To regenerate Sulphur from H2S solution

    0 221 11

    10F.1 To recover Ammonia from Coke oven gas

    0 2110F.1 To recover Ammonia from Coke oven gas

    0 212 11

    00F.1.1 To recover Ammonia from Coke oven gas

    0 2200F.1.1 To recover Ammonia from Coke oven gas

    0 221 11

    00G.1 To distill ammonia from Excess Ammonia Liquor

    0 2200G.1 To distill ammonia from Excess Ammonia Liquor

    0 221 11

    00G.1.1 To Distill ammonia from excess ammonia liquer

    0 2200G.1.1 To Distill ammonia from excess ammonia liquer

    0 221 11

    00H.1 To cool the Gas to ambient Temp

    0 2100H.1 To cool the Gas to ambient Temp

    0 212 22

    00H.1.1 To cool the gas to Ambient Temperature

    0 2200H.1.1 To cool the gas to Ambient Temperature

    0 221 11

    Friday, January 14, 2012 Page 1 of 2Friday, January 14, 2011

    Licensed To : HAMSAGARS 145

  • Design intention (Operation):

    Number of Risk (Damage-Consequence) level areasMEDIUMMEDIUM

    HIGHHIGH LOWNum.

    Guide Words

    SAFE

    Part-4a Overall Risk levels-Design intension wise

    00I.1 To compress air for different plants

    0 2200I.1 To compress air for different plants

    0 221 11

    00J.1 To Separate Tar and ammonia water from gas condensate & Recycle Ammonia Liq. To Battery 0 1900J.1 To Separate Tar and ammonia water from gas condensate & Recycle Ammonia Liq. To Battery 0 194 44

    00K.1 To generate Low Pressure Steam from gas Fired Boilers

    0 1700K.1 To generate Low Pressure Steam from gas Fired Boilers

    0 176 66

    00K.1.1 To generate low pressure steam from gas fired boilers

    0 2200K.1.1 To generate low pressure steam from gas fired boilers

    0 221 11

    00L.1 To store and Load Tar for Dispatch and Unload Caustic lye and H2SO4 from tankers 0 2000L.1 To store and Load Tar for Dispatch and Unload Caustic lye and H2SO4 from tankers 0 203 33

    00M.1 To produce coke and by product gas from coal

    0 1900M.1 To produce coke and by product gas from coal

    0 194 44

    00N.1 To provide water Pressure in the Firefighting network Min-8 Max-10 Bar 0 2100N.1 To provide water Pressure in the Firefighting network Min-8 Max-10 Bar 0 212 22

    00O.1 To ensure early detection of any fire in the offices

    0 2300O.1 To ensure early detection of any fire in the offices

    0 230 00

    700 35

    1.17.00.00 5.85

    TOTALPERCENT

    Applications of RBI-Risk Matrix: Following are the applications of an RBI-Risk matrix

    2. To establish risk mitigation measures and evaluate their effects,

    3. To compare units and processes on the basis of risk,

    4. To develop trends of risk development of a unit over time and during its life cycle.

    1. As an indicator of the risk level of the installation,

    556

    92.98

    Note:Col.-2 gives No. of guie words (Deviations) used out of a total of 23-possible deviations. Col.-3 to 6 give Risk Levels of applied deviations and Col.-7 gives No. safe i.e. no Risk of deviations. Total of Safe levels divided by total of Risks and Safe levels multiplied by total Safe levels gives % Safety pf the facility.

    Friday, January 14, 2012 Page 2 of 2Friday, January 14, 2011

    Licensed To : HAMSAGARS 146

  • Part-4b Overall Risk levels-Node wise

    HAMS-GPS : HAZOP Study for : Sample-Coke Oven Licensed To : HAMSAGARS

    Node:

    Number of Risk (Damage-Consequence) level areasMEDIUMMEDIUM

    HIGHHIGH SAFE

    Summary of RBI-Matrix (conforming to European Process Safety Center's Standard) for selected Nodes:

    Num. Guide Words

    LOW

    10A.1 Gas from Battery to byproduct 0 110A.1 Gas from Battery to byproduct 0 12 2121

    00A.0 0 100A.0 0 11 2222

    00A.1 Gas fro Battery to Byproduct 0 000A.1 Gas fro Battery to Byproduct 0 00 2323

    10A.2 Primary Gas cooler 0 010A.2 Primary Gas cooler 0 01 2222

    10A.3 ETP 0 010A.3 ETP 0 01 2222

    10A.3.1 ETP 0 010A.3.1 ETP 0 01 2222

    00B.1 Exhauster 0 000B.1 Exhauster 0 00 2323

    10B.1.1 Exhauster 0 210B.1.1 Exhauster 0 23 2020

    10C.1 Precooling Tower of Desulphurizer 0 010C.1 Precooling Tower of Desulphurizer 0 01 2222

    00D.1 Desulphurization tower 0 100D.1 Desulphurization tower 0 11 2222

    00D.1 Desulphurization tower 0 100D.1 Desulphurization tower 0 11 2222

    00E.1 Sulphur production 0 100E.1 Sulphur production 0 11 2222

    10F.1 Ammonium Sulphate Plant 0 110F.1 Ammonium Sulphate Plant 0 12 2121

    00F.1.1 Ammonium Sulphate Plant 0 100F.1.1 Ammonium Sulphate Plant 0 11 2222

    00G.1 Ammonia Distillation Column 0 100G.1 Ammonia Distillation Column 0 11 2222

    00G.1.1 Ammonia distillation column 0 100G.1.1 Ammonia distillation column 0 11 2222

    00H.1 Final Gas cooler 0 200H.1 Final Gas cooler 0 22 2121

    00H.1.1 Final Gas cooler 0 100H.1.1 Final Gas cooler 0 11 2222

    00I.1 Air compressor station 0 100I.1 Air compressor station 0 11 2222

    00J.1 Gas condensation Plant 0 400J.1 Gas condensation Plant 0 44 1919

    00K.1 Boiler 0 600K.1 Boiler 0 66 1717

    00K.1.1 Boiler 0 100K.1.1 Boiler 0 11 2222

    00L.1 Chemical Storage Area 0 300L.1 Chemical Storage Area 0 33 2020

    Friday, January 14, 2012 Page 1 of 2Friday, January 14, 2011

    Licensed To : HAMSAGARS 147

  • HAMS-GPS : HAZOP Study for : Sample-Coke OvenLicensed To : HAMSAGARS

    Node:

    Number of Risk (Damage-Consequence) level areasMEDIUMMEDIUM

    HIGHHIGH SAFE

    Summary of RBI-Matrix (conforming to European Process Safety Center's Standard) for selected Nodes:

    Num. Guide Words

    LOW

    00M.1 Coke Oven Battery 0 400M.1 Coke Oven Battery 0 44 1919

    00N.1 Fire fighting water Network 0 200N.1 Fire fighting water Network 0 22 2121

    00O.1 Offices 0 000O.1 Offices 0 00 2323

    700 35

    1.17.00.00 5.85

    TOTALPERCENT

    Applications of RBI-Risk Matrix: Following are the applications of an RBI-Risk matrix

    2. To establish risk mitigation measures and evaluate their effects,

    3. To compare units and processes on the basis of risk,

    4. To develop trends of risk development of a unit over time and during its life cycle.

    1. As an indicator of the risk level of the installation,

    556

    92.98

    556 x 100 / 598 = 92.98SAFE :

    35 x 100 / 598 = 5.85LOW :

    7 x 100 / 598 = 1.17MEDIUM :

    0 x 100 / 598 = .MEDIUM HIGH :

    0 x 100 / 598 = . HIGH :

    Friday, January 14, 2012 Page 2 of 2Friday, January 14, 2011

    Licensed To : HAMSAGARS 148

  • Count RemarksRisk Levels for HAZOP

    HAMS-GPS : HAZOP Study for : Sample-Coke OvenLicensed To : HAMSAGARS

    HAMS-GPS : HAZOP Study for :

    Part-4a SIL-LOP requirements-Overall

    Over all Risk Levels

    SIL/LOP Required

    1/14/2012 5:58:59 PM

    Risk level: MEDIUM DAMAGE and MEDIUM CHANCE 2 Medium Critical 2

    Risk level: MEDIUM DAMAGE and LOW CHANCE 29 Medium Low Critical 1

    Risk level: MEDIUM HIGH DAMAGE and LOW CHANCE 5 Medium Low Critical 1

    Risk level: LOW DAMAGE and LOW CHANCE 4 Low Critical 0

    Risk level: NO DAMAGE and NO CHANCE 29 Safe N.A.

    SIL Generalized View

    4 Potential for fatalities in the community

    3 Potential for multiple fatalities

    2 Potential for major serious injuries or one fatality

    1 Potential for minor injuries

    Note: Design team to check and ensure the SIL requirements for safety instruementation system and LOP for equipments safety as applicable are avaible. If not the SIL/LOP requirements to be provided.

    Friday, January 14, 2011 Page 1 of 1Friday, January 14, 2012 149

  • Count RemarksRisk Levels for HAZOP

    HAMS-GPS : HAZOP Study for : Sample-Coke OvenLicensed To : HAMSAGARS

    HAMS-GPS : HAZOP Study for :

    Part-5b SIL-LOP requirements-Category wise

    Summary of Category wise

    SIL/LOP Required

    1/14/2012 6:00:38 PM

    Category

    Engineering 1 Medium Critical 2

    Hazard. 1 Medium Critical 2

    Documentation 1 Medium Low Crit 1

    Hazard. 33 Medium Low Crit 1

    Hazard. 2 Low Critical 0

    Quality. 2 Low Critical 0

    Engineering 1 Safe N.A.

    Hazard. 10 Safe N.A.

    Maintenance 8 Safe N.A.

    Operability. 10 Safe N.A.

    SIL Generalized View

    4 Potential for fatalities in the community

    3 Potential for multiple fatalities

    2 Potential for major serious injuries or one fatality

    1 Potential for minor injuries

    Note: Design team to check and ensure the SIL requirements for safety instruementation system and LOP for equipments safety as applicable are avaible. If not the SIL/LOP requirements to be provided.

    Friday, January 14, 2012 Page 1 of 1Friday, January 14, 2011 150

  • Count RemarksRisk Levels for HAZOP

    HAMS-GPS : HAZOP Study for : Sample-Coke OvenLicensed To : HAMSAGARS

    HAMS-GPS : HAZOP Study for :

    Part-5c SIL-LOP requirements-Design Intention wise

    Risk Levels (Design intention wise)

    SIL/LOP Required

    1/14/2012 6:01:43 PM

    Design Intention

    A.1 Separate Gas and Liquid at required Pressure 1 Safe N.A.

    A.2 To cool the gas by 2-stage Process water chilled water from 80 to 22 Deg C. 3 Safe N.A.

    D.1 To remove H2S from Cokeoven gas 2 Safe N.A.

    E.1 To regenerate Sulphur from H2S solution 2 Safe N.A.

    F.1 To recover Ammonia from Coke oven gas 3 Safe N.A.

    F.1.1 To recover Ammonia from Coke oven gas 1 Safe N.A.

    G.1 To distill ammonia from Excess Ammonia Liquor 1 Safe N.A.

    G.1.1 To Distill ammonia from excess ammonia liquer 2 Safe N.A.

    H.1 To cool the Gas to ambient Temp 1 Safe N.A.

    I.1 To compress air for different plants 3 Safe N.A.

    K.1 To generate Low Pressure Steam from gas Fired Boilers 1 Safe N.A.

    K.1.1 To generate low pressure steam from gas fired boilers 1 Safe N.A.

    M.1 To produce coke and by product gas from coal 2 Safe N.A.

    N.1 To provide water Pressure in the Firefighting network Min-8 Max-10 Bar 5 Safe N.A.

    O.1 To ensure early detection of any fire in the offices 1 Safe N.A.

    A.2 To cool the gas by 2-stage Process water chilled water from 80 to 22 Deg C. 1 Medium Critical 2

    B.1 To suck the gas from cokeoven battery and supply to byproduct unit for cleaning 1 Medium Critical 2

    A. Separate Gas and Liquid at required Temperature 2 Medium Low Crit 1

    A.0 1 Medium Low Crit 1

    A.3 To eliminate tar residue from gas 1 Medium Low Crit 1

    A.3.1 To ensure Oxygen content in the gas ;ess than 0.8% vy vol. 1 Medium Low Crit 1

    B.1 To suck the gas from cokeoven battery and supply to byproduct unit for cleaning 2 Medium Low Crit 1

    C.1 To cool the Gas before sending to Desulphurizer columns from 45 deg. C to 25 Deg. C

    1 Medium Low Crit 1

    D.1 To remove H2S from Cokeoven gas 2 Medium Low Crit 1

    F.1 To recover Ammonia from Coke oven gas 2 Medium Low Crit 1

    Friday, January 14, 2012 Page 1 of 2Friday, January 14, 2011 151

  • Count RemarksRisk Levels for HAZOP

    HAMS-GPS : HAZOP Study for : Sample-Coke OvenLicensed To : HAMSAGARS

    HAMS-GPS : HAZOP Study for :

    Part-5c SIL-LOP requirements-Design Intention wise

    Risk Levels (Design intention wise)

    SIL/LOP Required

    1/14/2012 6:01:43 PM

    Design Intention

    F.1.1 To recover Ammonia from Coke oven gas 1 Medium Low Crit 1

    G.1 To distill ammonia from Excess Ammonia Liquor 1 Medium Low Crit 1

    G.1.1 To Distill ammonia from excess ammonia liquer 1 Medium Low Crit 1

    H.1 To cool the Gas to ambient Temp 1 Medium Low Crit 1

    H.1.1 To cool the gas to Ambient Temperature 1 Medium Low Crit 1

    I.1 To compress air for different plants 1 Medium Low Crit 1

    J.1 To Separate Tar and ammonia water from gas condensate & Recycle Ammonia Liq. To Battery

    4 Medium Low Crit 1

    K.1 To generate Low Pressure Steam from gas Fired Boilers 4 Medium Low Crit 1

    K.1.1 To generate low pressure steam from gas fired boilers 1 Medium Low Crit 1

    L.1 To store and Load Tar for Dispatch and Unload Caustic lye and H2SO4 from tankers

    2 Medium Low Crit 1

    M.1 To produce coke and by product gas from coal 4 Medium Low Crit 1

    N.1 To provide water Pressure in the Firefighting network Min-8 Max-10 Bar 1 Medium Low Crit 1

    E.1 To regenerate Sulphur from H2S solution 1 Low Critical 0

    K.1 To generate Low Pressure Steam from gas Fired Boilers 2 Low Critical 0

    N.1 To provide water Pressure in the Firefighting network Min-8 Max-10 Bar 1 Low Critical 0

    SIL Generalized View

    4 Potential for fatalities in the community

    3 Potential for multiple fatalities

    2 Potential for major serious injuries or one fatality

    1 Potential for minor injuries

    Note: Design team to check and ensure the SIL requirements for safety instruementation system and LOP for equipments safety as applicable are avaible. If not the SIL/LOP requirements to be provided.

    Friday, January 14, 2011 Page 2 of 2Friday, January 14, 201 152