draft nuclear energy series document: workforce planning for new nuclear power programmes tom mazour...

19
Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power [email protected]

Upload: marjorie-allen

Post on 30-Dec-2015

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Draft Nuclear Energy Series Document:Workforce Planning for

New Nuclear Power Programmes

Tom MAZOUR

IAEA, Division of Nuclear Power

[email protected]

Page 2: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Workforce Planning: part of “how to” implement the Milestones Approach

Page 3: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Preparing for assuming commitments & obligations

Infr

astr

uct

ure

dev

elop

men

t p

rogr

am1st

. NP

P P

roje

ct

Commissioning

Operation / decommissioning

Nuclear power option included within the

national energy strategy

10 – 15 years

PHASE 2

PHASE 3

PHASE 1

MILESTONE 1Ready to make a knowledgeable

commitment to a nuclear programme

MILESTONE 2Ready to invite bids

for the first NPP

MILESTONE 3Ready to commission and

operate the first NPP

Feasibility study Bidding process

Pre project Project decision making Construction

Considerations before a decision to launch a nuclear power programme is taken

Preparatory work for the construction of a NPP after a policy decision has been taken

Activities to implement a first NPP

Maintenance and continuous infrastructure improvement

INFRASTRUCTURE DEVELOPMENT PROGRAMME

Page 4: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Key Infrastructure Issues

• National position• Nuclear safety• Management• Funding and financing• Legislative framework• Safeguards• Regulatory framework• Radiation protection• Electric grid• Human resource

development (cross-cutting)

• Stakeholder involvement• Site and supporting

facilities• Environmental protection• Emergency planning• Security and physical

protection • Nuclear fuel cycle• Radioactive waste• Industrial involvement• Procurement

Page 5: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Human Resource Development-Milestone 1

• Competencies needed to support a nuclear programme are identified by NEPIO

• Initial Workforce/Staffing Plans are developed

Page 6: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Human Resources for NEPIO (example)

Environmental assessment & siting team

Economic & technology localization assessment team

Responsible Minister

Director of NEPIO

Legal & regulatory team

Public information & public consultation officer

Electric market & generation mix assessment team

NPP technology & fuel cycle assessment team

Technical, commercial & policy consultants

Page 7: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

WORKFORCE PLANNING

• Definition: the systematic identification and analysis of what an organization/nation is going to need in terms of the size, type, and quality of workforce to achieve its objectives.

• Identifies the steps that should be taken to get the right number of the right people in the right place at the right time.

Page 8: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

IAEA Document, WORKFORCE PLANNING FOR NEW NP PROGRAMMES

• The main activities to be undertaken to address each issue, together with an indication of the responsibilities of key organisations in completing these activities;

• An indication of the competencies needed to implement these activities

• Education/professional capabilities needed to support achievement of these competencies, and

• Suggestions for the Workforce Planning needed to deliver these competencies within the project.

• Final review meeting: 31 Mar-2 Apr 2009

Page 9: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Define the Objectives of the national Nuclear Power programme

Determine the HR needs of the programme based on these Objectives

Compare HR needs to existing and expected national HR resources

(Gap Analysis)

Can Gaps be addressed?

Determine how gaps will be addressed

Develop workforce plan

Review/Revise workforce plan as phases progress

Yes

No

WorkforcePlanningProcess

Page 10: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Sample of Competencies Matrix

Activity Responsibilities of key organizations

NP specific competencies

Probable education sources/

professions

Inputs regarding Workforce Planning,

education and training

Comments

Study of grid capability/ capacity re nuclear power

NEPIO: Take a lead role in

the studyGrid Operator: Provide information

regarding the stability and reliability of the grid, and anticipated grid growth/changes and suitability for NPPs

Knowledge of grid characteristics that are important re an NPP Thorough understanding of electrical O/P characteristics of an NPP and their impact on existing grid/necessary upgrades

Nuclear power engineerElectrical Power Engineer with Nuclear Power training module

At least one nuclear power engineer with expert level competencyAt least one power engineer with expert level competency and Nuclear Power training

Core competence is Electrical Power Engineering, but training in specifics of NPP output characteristics would be necessary to address grid capability/upgrade requirements

Study of grid interconnection possibilities

Grid Operator: Provide information

re grid characteristics and the issues related to their interconnection

In-depth knowledge of principles for, and lessons learned, regarding grid interconnections

Power engineer

one power engineer with expert level competencyOne or more with working level competency

Infrastructure Issue 10. Electrical Grid Phase 1

Page 11: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Typical Phasing of Resources

0

200

400

600

800

1000

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Years (Indicative only)

No

. o

f p

eo

ple

NEPIO REG BODY OP ORG

<----------------- Phase 3 ---------------->Design, Construct, Comm'n

Co

mm

issi

on

ing

<-- Phase 1-->

<-------- Phase 2-------->Site Investigation, Bid

Preparations

<--Op Training-->2-3 yrs

MS1 MS2 MS3

Multi Units

1 Unit

1. NEPIO = 10 --> 50 (Depending on Expert Group Support) --> 0 (close to)2. REG BODY = 10 --> 50+Tech Support3. OP ORG = 0 --> 20 to 30 --> 600 to 1200

1 UnitMulti Units

Page 12: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Human Resource Development-Milestone 2

• Sufficient human resources are in place to be an intelligent customer

• Training of human resources needed for plant operation is initiated (Systematic Approach to Training (SAT))

• HR issues are addressed in requirements for suppliers (turnkey assumed)

• Workforce/Staffing Plan(s) updated

Page 13: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

an Intelligent Customer is:

• An organisation (or individual) that has the competence to specify the scope and standard of a required product or service and subsequently assess whether the supplied product or service meets the specified requirements.

Page 14: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Operations and Intelligent Customer

Owner / Operator

Major ProjectsContractors

Minor Projects

ComponentSupply

Consultants

Suppliers / General Industry

SUPPLY ‘PYRAMID’

Page 15: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Human Resource Development- Milestone 3

• All human resources to commission and operate the first NPP are in place

• Education and training programmes for continuing flow of qualified people are in place

• Workforce/Staffing Plan(s) updated

Page 16: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Typical Phasing of Resources

0

200

400

600

800

1000

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Years (Indicative only)

No

. o

f p

eo

ple

NEPIO REG BODY OP ORG

<----------------- Phase 3 ---------------->Design, Construct, Comm'n

Co

mm

issi

on

ing

<-- Phase 1-->

<-------- Phase 2-------->Site Investigation, Bid

Preparations

<--Op Training-->2-3 yrs

MS1 MS2 MS3

Multi Units

1 Unit

1. NEPIO = 10 --> 50 (Depending on Expert Group Support) --> 0 (close to)2. REG BODY = 10 --> 50+Tech Support3. OP ORG = 0 --> 20 to 30 --> 600 to 1200

1 UnitMulti Units

Page 17: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

Summary: How to effectively consider HR from

the beginning?

• Use an integrated, systematic approach toward considering and implementing a NP programme (The “Milestones” Approach)

• Develop workforce/staffing plans that are based upon activities in each of the 3 Phases

• Require a Systematic Approach to Training (SAT) for all training programmes

• Include SAT, and knowledge capture and transfer requirements in supplier contracts

• Maintain this integrated workforce planning approach through the entire lifecycle of the facilities/programmes

Page 18: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

TCTC

NENE

OLAOLA

NA NA

NENE

MTMT

NANA

SGSG

NSNS

NSNS

IAEAIAEA

Education Education and Training and Training

Support Support

GroupGroup (ETSG)(ETSG)

Page 19: Draft Nuclear Energy Series Document: Workforce Planning for New Nuclear Power Programmes Tom MAZOUR IAEA, Division of Nuclear Power t.mazour@iaea.org

IAEA

…atoms for peace.