00072773: Pakistarn Sustainable Transport Project (PAKSTRAN) Annual Progress Report January – December 2013
Project Management Unit (PMU) Pakistan Sustainable Transport Project (PAKSTRAN)
4th Floor, ENERCON Building, Islamabad
Annual Progress Report 2014
2
PROJECT SNAPSHOT Date: 10th December 2013
Award ID: 00058561
Project ID: 00072773
Project Title: Pakistarn Sustainable Transport Project (PAKSTRAN)
Project Start Date: June 2011
Project End Date: June 2016
Implementing Partner: Ministry of Water & Power, Islamabad (ENERCON)
Responsible Parties: Government of Punjab (P&D Department) Government of Sindh (Transport Department) Planning Commission of Pakistan International Union for Conservation of Nature (IUCN)
Project Budget (all years): US $ 7.8 Million
Core Resources: Non-Core Resources: Government contribution: Donor 1 UNDP Donor 2 GEF
US $ 3 Million US $ 4.8 Million
Project Brief Description and Outputs: Project Brief Description : The objective of the project is to reduce the growth of the energy consumption
and related greenhouse gas emissions from the transport sector in Pakistan, while simultaneously improving urban environmental conditions and improving Pakistan’s trade competitiveness by 1) creating an enabling investment environment for sustainable urban transport; 2) creating an institutional and policy framework that is supportive of urban transit development; 3) improving the fuel efficiency of trucking freight transport; and 4) increasing awareness and capacity in Pakistan on sustainable transport.
Outputs: Reduction of greenhouse gas (GHG) emissions associated with urban transportation.
Overall Project Quality Rating (mark on the scale of 1 to 5 as per the following criteria):
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
All outputs are rated High or Exemplary
All outputs are rated Satisfactory or
higher, and at least two criteria are rated High or
Exemplary
One output may be rated Poor, and all other criteria are
rated Satisfactory or higher
Two outputs are rated Poor, and all other criteria are
rated Satisfactory or higher
One output is rated Inadequate, or more than two criteria are
rated Poor
Budget 2013 US$ 1,699,371
Expenditure 2013 US$ 278,219
Delivery % 16.37%
Annual Progress Report 2014
3
CONTENTS
1. Introduction
2. Situation Analysis
3. Project Performance and Results
3.1 Contribution toward Country Programme Outcome
3.2 Achievement of Project Results/Outputs
4. Lessons Learnt
5. The Way Ahead/Key Priorities for 2014
Annex 1: AWP Based reporting matrix
Annex 2: Annual Project Quality Assurance Assessment
Annual Progress Report 2014
4
ACRONYMS
Acronym Meaning
SUT Sustainable Urban Transport
PMU Project Management Unit
CIU Component Implementation Unit
BRT Bus Rapid Transit
UNDP United Nations Development Programme
CP Country Programme
CPAP Country Programme Action Plan
EAD Economic Affair Division
ENERCON National Energy Conservation Center, Ministry of Water & Power
FERTS Fuel Efficiency in the Road Transport Sector (UNDP-GEF Project completed in 2005)
GEF Global Environment Facility
GoP Government of Pakistan
IUCN International Union for the Conservation of Nature
UU Urban Unit, Planning & Development Department, Punjab
MoW&P Ministry of Water & Power
GoPb Punjab Provincial Government
GoPbTD Punjab Provincial Transport Department
Pro-Doc UNDP Project Document
SPG Sindh Provincial Government
STD Sindh Provincial Transport Department
ToR Terms of Reference
NED UET Nadirshaw Edulji Dinshaw University of Engineering and Technology, Karachi
SUPARCO Pakistan Upper Atmosphere and Space Research Commission
Annual Progress Report 2014
5
1. INTRODUCTION Pakistan Sustainable Transport (PAKSTRAN) project is an initiative of UNDP-GEF that aims to provide technical assistance to reduce the growth of energy consumption & related greenhouse gas (GHG) emissions from transport sector in Pakistan, while simultaneously improving urban environmental conditions and improving Pakistan’s trade competitiveness. The global objective of PAKSTRAN is to reduce the GHG emissions from transport sector in Pakistan. However, the developmental objectives of PAKSTRAN are: to improve urban environmental conditions (i.e. improved air quality, urban mobility, equity, and city aesthetics); and to improve energy security for Pakistan. The project is funded by UNDP & GEF (Total Budget is US$ 7.8 million with US$ 3.0 million from UNDP & US$ 4.8 million from GEF). The project was approved by GEF and Government of Pakistan in June 2011, which is expected to be completed in 2016. ENERCON, Ministry of Water and Power is the Implementing Partner (IP) of the project. Moreover, the project has four components (to achieve outcomes), which are given below: Outcome 1: An operational sustainable urban transport system in Punjab province (Punjab P&D Department is the responsible partner for this outcome); Outcome 2: An operational sustainable urban transport system in Sindh province (Sindh Transport Department is the responsible partner for this outcome); Outcome 3: Improved fuel efficiency in truck freight transport (Planning Commission of Pakistan is the responsible partner for this outcome); & Outcome 4: Increased public awareness and institutional capacity on sustainable transport concepts (IUCN-Pakistan is the responsible partner for this outcome). The Project Management Unit (PMU) is established at ENERCON, Ministry of Water & Power. The organization structure of PAKSTRAN project is given below;
Annual Progress Report 2014
6
Project Management Unit (PMU)
National Project Manager
Project Assurance (E&CC Unit, UNDP)
ENERCON
CIU-1 P& D (Urban Unit)
Annual Work plan
/ Report
Quarterly
Work plan/ Report
Expenditure plan/
Financial report
Consolidated
AWP/Report
Consolidated Expenditure
Plan/Report
Annual Work plan
/ Report
Quarterly
Work plan/ Report
Expenditure plan/
Financial report
Annual Work plan
/ Report
Quarterly
Work plan/ Report
Expenditure plan/
Financial report
CIU-2 Transport Dept-Sindh
CIU-3 MoIP
CIU-4 IUCN
Quarterly advance Quarterly advance Quarterly advance
Project Board
Provincial Govts. Ministry of Water & Power UNDP
Annual Work plan
/ Report
Quarterly
Work plan/ Report
Expenditure plan/
Financial report
Quarterly advance
Annual Progress Report 2014
7
2. SITUATION ANALYSIS
PAKSTRAN project aims to adopt holistic planning approaches towards successful ‘demonstration’ BRT systems in Punjab & Sindh provinces. BRT planning includes: physical integration of BRT and feeder routes with the urban transport network; organized parking lots near bus stations & user-friendly transfer points; economic incentive for commercial development near BRT; financial sustainability of integrated BRT system, and outreach and involvement through public-private partnerships. PAKSTRAN project is: streamlining institutions in Punjab & Sindh provinces; strengthening strategic plans and the regulatory policy frameworks at the provincial levels by using BRT project demonstration experiences. It is facilitating: development of sustainable transport policies; and building capacity within responsible provincial agencies to adopt sustainable transport principles in planning. Moreover, PAKSTRAN project aims to: utilize holistic approaches to: demonstrate implementation of the Trucking Policy (holistic approaches include innovative financial mechanisms, strengthening/supporting institutions and regulations); create an enabling environment to reduce fuel consumption in the trucking sector). Also, PAKSTRAN project is raising awareness and knowledge levels of issues related to, and measures to achieve sustainable urban transport and fuel efficiency of commercial vehicles (this include targeted publicity campaigns and supporting curriculum development in technical and academic institutions). There is an overall consensus that the implementation of BRT systems in Punjab and Sindh will serve as a viable short and medium-term option to improve the efficiency of urban transport mobility. Also, the implementation of an integrated BRT system will support the outputs of UNDP CPAP. The Government of Punjab (GoPb) has already constructed corridor-1 for BRT project in Lahore. Ulasim - a Turkish Company (along with local consultant NESPAK) has designed BRT corridor-1 on Ferozepur Road, Lahore. Following are the main features of Metrobus System in Lahore;
Two lane - limited access corridor
Total length is27.86 Kms from Gajjumatta to Shahdra
Headway- 3 to 6 minutes
27 Stations (Two platforms each with three docking bays)
9 elevated and 18 at-grade stations
Signal priority for Metrobuses at Intersections
Sliding doors
Escalators
Total length of elevated portion is 8.5kms from Canal to Data Darbar
Off board ticketing
Annual Progress Report 2014
8
Automated Fare Collection / Bus Scheduling System (AFC/BSS)
Passenger Information System (PIS)
Intelligent Traffic System (ITS)
Elevators
45 articulated air conditioned buses (seating capacity 38, total passenger capacity 160)
Precision docking
Level boarding
Expected peak hour ridership - 3000 passengers The work on other corridors related to BRT in Lahore is moving on a fast track. Moreover, the City District Government of Karachi has also initiated their 1st corridor of BRT from Korangi to Saddar. Therefore, in order to augment BRT planning and design and to support implementation of BRT-1 in Lahore and BRT planning in Karachi, the CIUs of Punjab & Sindh developed their annual work plans-2013. Their work plans were included highly requisite technical activities and management costs for their CIUs. IUCN Pakistan, being responsible for increased public awareness and institutional capacity on sustainable urban transport (SUT) concepts, also developed its annual work plan in January 2013. PAKSTRAN PMU (having the responsibility to coordinate all project related activities; building collaborative arrangements with related initiatives; providing a clearing house mechanism (CHM) information and communication; and carrying out monitoring and evaluation) also developed its annual work plan-2013, based on highly needed actions, for smooth functioning of various project activities. Although PAKSTRAN project activities have still to be initiated/implemented (release/utilization of budget to CIUs/PMU awaited) in full swing in 2014, it is safe to state that there are no changes in the project’s external context that have positively or negative impacted the achievement of project results.
Annual Progress Report 2014
9
3. PROJECT PERFORMANCE AND RESULTS 3.1. Contribution towards Country Programme Outcome1
CPAP Outcome: Industrial Development both urban and rural, emphasis small and medium enterprises/ small and medium industry development, women participation, clean development and sustainable energy supply and used at affordable cost ( CPAP outcome 2.2).
Indicator(s): Number of initiatives on green, clean industries and jobs and low cost energy and climate change measures; Number of rural and urban poor households with access to sustainable energy sources
Baseline: During the meeting in Serena dated November 21, 2013, UNDP informed that they will take care of entries related to CPAP
Target(s): During the meeting in Serena dated November 21, 2013, UNDP informed that they will take care of entries related to CPAP
Achievement(s): During the meeting in Serena dated November 21, 2013, UNDP informed that they will take care of entries related to CPAP
Description of output level high/outcome level results achieved in 2013: During the meeting in Serena dated 21, 2013, UNDP informed that they will take care of entries related to CPAP
Means of Verification During the meeting in Serena dated November 21, 2013, UNDP informed that they will take care of entries related to CPAP
1 Outcomes describe the intended changes in development conditions that result from the interventions of
governments and other stakeholders, including international development agencies such as UNDP. They are medium-term development results created through the delivery of outputs and the contributions of various partners and non-partners. Outcomes provide a clear vision of what has changed or will change globally or in a particular region, country or community within a period of time. They normally relate to changes in institutional performance or behavior among individuals or groups. Outcomes cannot normally be achieved by only one agency and are not under the direct control of a project manager.
Annual Progress Report 2014
10
3.2. Progress towards Project Results/Outputs2 Outcome 1: Operational sustainable urban transport system in Punjab Province
Project Output 1.1: Feasibility studies for a demonstration integrated BRT system in selected cities in Punjab Province
Indicator(s): Number of completed feasibility studies prepared for BRT in Punjab
Baseline: No complete feasibility study on BRT is available in Punjab
Target(s): 2 feasibility studies augmented for BRT in Lahore and Rawalpindi/Islamabad
Achievement(s): TA to Government of Punjab transport department
Description of output level results achieved in 2013: Government of Punjab has laid down one BRT corridor in Lahore from Shahdara to Gajumatta which has enhanced the public transport services in Lahore. Project through its Research Officers hired for R&D Unit providing assistance to the Transport Department, Government of Punjab in collecting field data for assessment of existing corridor and carrying out survey for new BRT project in Punjab.
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 3
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification: Specific studies & evaluation related to the feasibility studies
Project Output 1.2: : Plans for implementing demonstration integrated BRT system
Indicator(s): Number of approved integrated BRT implementation plans for selected cities in Punjab Province
Baseline: Lack of holistic planning for integrated BRT system in Punjab.
Target(s): 2 approved implementation plans for integrated BRT system in 2 cities of Punjab
Achievement(s): 3 consultancies to augment BRT corridor in Lahore have been floated
2 Outputs are short-term development results produced by project and non-project activities. They must be
achieved with the resources provided and within the time-frame specified (usually less than five years).
Annual Progress Report 2014
11
Description of output level results achieved in 2013: Government of Punjab has laid down one BRT corridor in Lahore from Shahdara to Gajumatta which has enhanced the public transport services in Lahore. The Component Implementing Unit-Punjab PAKSTRAN Project has floated the following consultancy services to integrate land use development along BRT corridor from Gajjumatta to Shahdara in Lahore and to align feeder routes connecting the said corridor.
1) Mapping of Land use & infrastructure along the BRT Corridore-1 from Gajjumatta to Shahdara in Lahore. 2) Mapping of environmental and socio-economic profile along the BRT Corridore-1 from Gajjumatta to
Shahdara in Lahore. 3) Survey of public transport deployed on the routes connecting with and running along the BRT Corridore-1
from Gajjumatta to Shahdara in Lahore. Technical and financial evaluation of proposals is in progress and award is expected by end of December 2013 The delay is due to non-release of funds by UNDP.
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 3
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification: Specific studies/plans and evaluation related to the plans for implementing demonstration integrated BRT system
Project Output 1.3: Infrastructure for demonstration BRT system
Indicator(s): Number of manuals and studies to improve infrastructure design for BRT system
Baseline: Existing BRT system in Punjab has deficiencies in its design and construction
Target(s): Govt. of Punjab adopted and implemented at least 3 manuals to improve infrastructure design and allied facilities required for the demonstration BRT system
Achievement(s): None
Annual Progress Report 2014
12
Description of output level results achieved in 2013: Government of Punjab has laid down one BRT corridor in Lahore from Shahdara to Gajumatta and has installed ITS and TCCC system to facilitate public transport riders in Lahore. Due to delay in release of funds by UNDP to CIU-Punjab no activity could be carried out in 2013.
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 2
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification : Specific studies/manuals, evaluation, field observations and surveys
Project Output 1.4: An operational demonstration BRT system
Indicator(s): Number of operational frameworks and standard operating procedures for increased efficiencies of BRT operations Cumulative GHG reductions from the BRT demos in Lahore- ktonnes CO2
Baseline: Existing BRT system in Punjab has deficiencies in its operations. Also, no emission calculation is available along the existing corridor in Lahore
Target(s): 1. Govt. of
Punjab adopted and implemented at least 3 SOPs and NEQs to increase efficiencies in BRT operations
2. 304 ktonnes CO2 ( direct reduction from BRT demonstrations in Lahore
Achievement(s): None
Annual Progress Report 2014
13
Description of output level results achieved in 2013: Government of Punjab has laid down one BRT corridor in Lahore from Shahdara to Gajumatta and has installed ITS and TCCC system to facilitate public transport riders in Lahore. Due to delay in release of funds by UNDP to CIU-Punjab no activity could be carried out in 2013.
3. 304 ktonnes CO2 ( direct reduction from BRT demonstrations in Lahore
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 2
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification : Surveys, specific studies/SOPs/NEQs, evaluation, field observations, interviews, spot checks
Project Output 1.5: Strengthened institutional framework that enables holistic urban transport development.
Indicator(s): Number of institutions available for carrying out advanced research and comprehensive planning and management exercise related to sustainable urban transport (SUT)
Baseline: Multiple entities in an uncoordinated manner are involved in SUT in Punjab
Target(s): 1 R&D unit operational for development of SUT in Punjab and its linkage with Sustainable Urban Transport Knowledge Management Database (SUT-KMD) Centre in Islamabad
Achievement(s): Establishment of R&D Unit Reports and data collected by ROs
Description of output level results achieved in 2013: MOU between the Urban Unit /CIU-Punjab and the UET Lahore has been signed to established R&D unit at DTEM, UET Lahore as part of activity 1.5 of AWP 2013. UET has allocated room in its Annexe Block and refurbishing work by CIU-Punjab is in progress, which shall be completed by Dec 15, 2013. Inauguration of the R&D unit is planned to be held on January 2014. Team Leader and ROs have been hired for the R&D unit since it is under refurbishing. ROs are providing assistance to the Transport Department, Govt: Punjab in collecting field data for assessment of existing corridor and carrying out survey for new BRT project in Punjab.
4. 304 ktonnes CO2 ( direct reduction from BRT demonstrations in Lahore
Annual Progress Report 2014
14
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 4
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification: Specific tools, plans, policies/planning and management exercise based on advanced research, evaluation, field observations.
Outcome 2: Operational sustainable urban transport system in Sindh Province
Project Output 2.1: Feasibility plans and approved financing with “integrated BRT plans” for cities in Sindh Province
Indicator(s): Number of completed feasibility plans/studies prepared for BRT in Sindh
Baseline: 2 feasibilities studies
Target(s): 1 bankable feasibility study
Achievement(s): Meetings were held with Provincial
representative of World Bank seeking assistance to implement BRT.
Meetings were held, with delegation of Asian Development Bank, in the office of Secretary Transport Government of Sindh seeking financial support to implement BRT.
Series of meetings were held by higher authorities of Government to implement BRT
The PPP Board headed by Chief Minister Sindh has approved the implementation of BRT yellow line.
The work on amendment of motor vehicle laws has been started and amendments concerning usage of CNG as a fuel have been approved by the Govt. Initial consultation are under way in form of series of meetings with stakeholders.
TORS , RFPs were prepared for hiring consultancy services
Annual Progress Report 2014
15
Description of output level results achieved in 2013: The CIU Sindh has prepared TORs and RFPs. However the consultancy services could not be hired due to non release of funds by UNDP.
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 3
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification : Specific studies & evaluation related to the feasibility studies
Project Output 2.2: Strengthened institutional framework that enables sustainable urban transport development in Sindh Province
Indicator(s): Number of institutions available for carrying out advanced research and comprehensive planning and management exercise related to sustainable urban transport (SUT)
Baseline: Multiple entities in an uncoordinated manner are involved in SUT in Sindh
Target(s): 1 R&D unit operational for development of SUT in Sindh and its linkage with Sustainable Urban Transport Knowledge Management Database (SUT-KMD) Centre in Islamabad
Achievement(s): In accordance with the approved AWP
2013. The Transport Department had constituted two committees i.e I) Legislation Sub-Committee and II) Technical Sub-committee with following composition.
Legislation sub-Committee. Chairman of Urban & Infrastructure
Engineering NED University Karachi. – Chairman.
Component Manager –Sindh (PAKSTRAN). -Member
Representative of DIG Traffic. -Member
Representative of DG Environment. –Member
Asst. Advocate General, Sindh High Court – Member
Technical sub-Committee. Chairman of Urban & Infrastructure
Engineering NED University Karachi. – Chairman
Component Manager –Sindh (PAKSTRAN). -Member
Annual Progress Report 2014
16
Representative of DG Karachi Mass Transit.-Member
Following meetings have been conducted the committees referred above:
Eight meetings of above referred committees were held and prepared manuals bylaws policy documents concerning sustainable transportation to implement BRT.
Efforts are underway for establishment of Sindh mass transit authority besides opening of drivers training schools and R&D cell in NED University to Strengthen institutional framework
Description of output level results achieved in 2013: The committees were formed and initial work for opening of training institutes in transport department and R&D cell in NED University have been completed.
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 3
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification: Specific tools, plans, policies/planning and management exercise based on advanced research, evaluation, field observations
Project Output 2.4: Approved and enforced Sindh provincial policy that enables development and operation of sustainable urban transport systems
Indicator(s): Number of provincial policies for developing sustainable urban transport for Sindh Province
Baseline: Lack of comprehensive urban transport policy
Target(s): 1 approved Sindh provincial policy on sustainable urban transport with associated
Achievement(s): The principal guide lines with regard to urban transport policy have been prepared and forwarded to committee members through seeking their advice for preparation of TOR.
Annual Progress Report 2014
17
framework in Sindh
implementing rules and regulation (IRRs)
Description of output level results achieved in 2013: The principal guidelines with regard to urban transport policy have been prepared and forwarded to committee members through seeking their advice for preparation of TOR.
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 3
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification: Sindh provincial policy on SUT, IRRs, evaluation, field observation, mentoring events
Outcome 4: Increased public awareness and institutional capacity on sustainable transport concepts
Project Output 4.1: Completed awareness raising campaigns on sustainable transport concepts
Indicator(s): Number of completed awareness raising campaigns Number of cities benefiting from awareness raising campaigns
Baseline: No focused awareness campaigns
Target(s): 5 awareness raising campaigns
3 cities where awareness raising campaigns conducted
Achievement(s): a. An awareness raising strategy has been
developed through a wider consultative process that aims to sensitize all the stakeholders, including different decision-influencing and decision-making players, and the general public, regarding their respective roles in shaping the way for planning and development decisions that are to be taken in Pakistan regarding sustainable urban transport.
The draft of this awareness raising strategy has been developed by IUCN using the organization’s expertise in environmental communications. Necessary input from IUCN’s Office (Education, Communications & Outreach Unit) and IUCN Asia Region was obtained, where necessary to obtain a quality document.
Annual Progress Report 2014
18
A thorough review of best practices, tools and techniques for raising awareness has been conducted to identify the best approaches that are suitable for local conditions and which can be applied for raising awareness in Pakistan on sustainable urban transport.
The draft of the strategy was discussed and feedback was obtained from the Project IP and all PASKTRAN partners. A consultative workshop was organized on Thursday, November 28, 2013 in Islamabad to seek feedback from all relevant stakeholders on the draft Strategy.
The final (revised) strategy document is under publication. IUCN has also prepared site specific awareness raising action plans under the strategy.
Specific awareness raising action plans are also being developed through partner’s consultation to identify province specific awareness raising activities under the strategy.
b. The awareness raising/publicity material has been developed for PASKTRAN including; project brochure, posters, folders, calendars (year 2014) note books, and stickers have been developed. High-class expertises were drawn for development of material with high impact. The material has been finalized with input from partners.
The material has been widely disseminated to all stakeholders/masses as appropriate and through input from project partners.
c. In order to raise awareness among masses about need for sustainable transport, a ‘mega cycle rally’ was organized under PAKSTRAN, on December 01, 2013 at Fatimah Jinnah Park Islamabad. The event was jointly organized with Capital Development Authority, Islamabad Traffic Police, Critical Mass and Shehrsaaz. About 200 cyclists from all over Pakistan participated in the rally. The vent was covered in local and national press.
d. Considering the role that the media is playing for raising awareness is considered crucial to further compliment these efforts through effectively
Annual Progress Report 2014
19
engaging the media to promote understanding about the sustainability concepts related to urban transport sector, which can influence a wider cross section of the society in Pakistan.
In this regard, a media sensitization seminar is being organized under PAKSTRAN on ‘Transport Sector and Related Issues in Pakistan’ on Monday, December 23rd, 2013 at Karachi. Eminent experts in the field have been invited to deliberate on various dimensions of the issue. The aim of the event is to sensitize select media representatives about the social, economic / developmental and environmental issues related to transport sector in Pakistan. It is expected that this would help in effective involvement of media with PAKSTRAN partners to support this common enhanced awareness is expected to eventually shape the way for planning and development decisions that are to be taken in Pakistan regarding sustainable urban transport concepts, thus influencing the achievement of PAKSTRAN’s objective.
The seminar will be attended by about 35 key representative from print electronic and cyber media from cities of Karachi, Lahore and Islamabad (target cities under PASKTRAN), while carful participation is also invited from cities of Quetta and Peshawar.
e. The PAKSTRAN’s website (www.pakstran.pk) has been developed and deployed in cyberspace during the year. The website has been developed using web 2.0 technologies and social media platforms. The website is supported by open source technologies and is hosted in United States with an up time of 99.7 percent.
The website includes; dynamic image gallery, flikr sets and a blogging platform. It also contains link to specific social media websites including Facebook, twitter, LinkedIn. It also has mailing groups for project staff, media and academia.
The website was launched by the National Project Director on Thursday, November 28, 2013 in Islamabad. The
Annual Progress Report 2014
20
content is still under developed as activities conducted by PAKSTRAN partners are progressing.
Description of output level results achieved in 2013: Due to late release of funds in year 2013 (releases were done in September, 2013) many activities there were planned under year 2013 work plan could not be timely done. However since, the release of funds, IUCN has made best efforts to complete significant activities since then.
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 3
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification: Field observation, interviews and related to urban transport awareness raising campaigns, and implementation results and evaluations
Project Output 4.2: : Completed training program on strategic urban land use and transportation planning conducted at various training, academic and vocational institutes in Pakistan
Indicator(s): Number of completed training courses on strategic urban land use and sustainable urban transport planning (SUTP) Number of cities and provincial planners and students trained on land use planning (LUP) and SUTP Number of educational institutes where LUP and SUTP courses are offered
Baseline: . No capacities exists in Pakistan regarding urban land use and sustainable urban transport planning
Target(s): 8 training courses of strategic urban land use and sustainable urban transport planning 30 city and provincial planners and students trained
Achievement(s): a. As part of the 2013 work plan
IUCN has done a capacity need assessment exercise targeting the project partners and key stakeholders in Punjab, Sindh and Islamabad/Rawalpindi to ass the level to knowledge/capacity with regards to sustainable urban transport concepts in Pakistan. This exercise has been very instrumental in identifying the capacity needs that are eventually be addressed during the course of PAKSTRAN implementation. High class professional expertises have been utilized for conducting the exercise utilizing IUCN’s expertise available at the national level. Globally tested methodologies have been deployed for the capacity needs assessment to
Annual Progress Report 2014
21
4 educational institutes where LUP and SUTP courses offered
PAKSTRAN. b. Through the conducted capacity
need assessment, a Capacity Development Plan has been developed by CIU-IUCN. The objective of the Capacity Development Plan is to target the PAKSTRAN implementing partners, policy makers, planners, engineers and academicians who are directly or indirectly linked with the Pakistan Sustainable transport project to build their capacity on sustainable transport concepts to facilitate them in strengthening their skills and capabilities to design, implement and successfully/ sustainably manage the project.
The Capacity Development Plan has been developed through a five steps continuous process/ cycle adopted from UNDP’s Capacity Development Process. The draft of the plan is under consultation for finalization with input from PAKSTRAN partners.
c. On the basis of identified capacity building needs during the capacity need assessment and urgent demand of PAKSTRAN partners (CIU Sindh), two training sessions (2 and a half day each) have been planned to be conducted (during 30, December 2013 to 3, January 2014) at Karachi on ‘Land use and Urban Transport Planning with Special context to Bus Rapid Transit (BRT) System’.
The objective of the training is to build the capacity of PAKSTRAN partners and key stakeholders to better plan and implement the sustainable urban transport interventions, taking the case of planned BRT system in Sindh Province as an example.
High class technical expertise (from
within Pakistan) are being utilized to conduct these training sessions. Formal collaborations have been developed; trainings are being organized in collaborations with Department of Urban and Infrastructure Engineering, Nadirshaw Edulji Dinshaw University for Engineering and Technology (NEDUET) and Institute of Space Technology, Pakistan Space and Upper Atmosphere
Annual Progress Report 2014
22
Research Commission (SUPARCO). About 30 participants will be trained,
primarily PAKSTRAN partners and select institutions from Punjab, Sindh and Islamabad/Rawalpindi. While, carefully selected representatives are also being invited from Quetta and Peshawar.
Description of output level results achieved in 2013: Despite the late release of funds, sufficient progress has been achieved during the last quarter of 2013. The two proposed trainings would greatly help in filling the capacity gaps that are essential to meet the overall objective of PAKSTRAN and meet the urgent capacity demands of PAKSTRAN partners.
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 3
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification : Field observations, interviews, surveys, spot checks
Project Output 4.3: Sharing experiences/building collaborative arrangements on integrated BRT development and implementation of the Trucking Policy
Indicator(s): Number of completed workshops on integrated BRT development Number of completed workshops on the implementation of the Trucking Policy
Baseline: No completed workshops on Integrated BRT and Trucking Policy
Target(s): 8 workshops on integrated BRT development 8 workshops on Trucking Policy implementation completed
Achievement(s): The progress on this Component is withheld, till a decision is taken on the Component Implementation Unit for this output on Trucking policy/implementation No progress has been made during 2013, since this is directly related to progress that was expected to be made by CIU-Punjab and CIU-Sindh.
Annual Progress Report 2014
23
Description of output level results achieved in 2013: The progress on this Component is withheld, till a decision is taken on the Component Implementation Unit for this output on Trucking policy/implementation .No progress has been made during 2013, since this is directly related to progress that was expected to be made by CIU-Punjab and CIU-Sindh..
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 2
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification: Specific trainings /workshops, field observations, evaluation, minutes of the workshops conducted.
Outcome 5: Project Management
Project Output 5.1: Management, Coordination, Monitoring and Evaluation
Indicator(s): Number of sustainable urban transport knowledge management databases Number of collaborative arrangements with related initiatives
Baseline: No SUT knowledge management databases are available in Pakistan to promote SUT concepts No experiences/collaborative arrangements exist in Pakistan regarding SUT and trucking that could be shared for replication
Target(s): 1 Sustainable Urban Transport Knowledge Management Database (SUT-KMD) Centre in Islamabad for informed decision-making at national & provincial levels
2 related projects collaborating with PAKSTARN for lessons learnt and knowledge sharing
Achievement(s): • Preparation of TORs for hiring a
consultancy related to SUT-KMD centre
• Concept Note for SUT-KMD centre prepared.
• Preparation of TORs for arrangement of a consultative workshop to build collaborative arrangements with CDA
• Finalization of appointments/contracts as per ProDoc
• Coordination and management activities of PMU along with CIUs and other stakeholders
• Arrangement of basic office equipment for PMU and CIUs
• Meetings/presentations – Ministry of Water & Power, MD ENERCON, UNDP, IUCN, Sindh Transport Deptt, Urban Unit Punjab, stakeholders, etc.
• DPRs (Direct Payment Requests) arrangement for interim period
Annual Progress Report 2014
24
• Review of project document – budget revision approval; approval of replacing Ministry of Environment with Ministry of Water & Power; approval of replacing Ministry of Industry with Planning Commission of Pakistan
• Contact/follow up with CIUs for preparation of their Annual/Quarter Work Plans
• Preparation of PMU Annual/Quarter Work Plans 2013
• Project bank accounts opening of PMU & CIUs under section 10-E(2) of PCOM
• Convening of 2nd
Project Board (PB) meeting on 1.1.2013
• Approval of annual work plans/budgets for 2013
• Preparation of consolidated Logs (risk log; issues log; communication & monitoring plan; lessons-learned)
• Finalization of 2013 output-specific ‘baseline’, ‘indicators’, ‘targets’ & related ‘CP outcomes’ for all CIUs ( Revised RRF)
• Preparation of draft guidelines related to the PAKSTRAN project Recruitment, Procurement, Financial Disbursement and Contract Renewal/ Performance Appraisal Reports
• Preparation of draft Letters of Understanding (LoUs) with CIUs (UNDP new requirement)
• Preparation and submission of GEF PIR 2013
• Preparation and submission of UNDP APR 2013
Description of output level results achieved in 2013: In order to maintain a repository of information, technologies, methodologies, standards and best practices used in the Sustainable Urban Transport (SUT) domain, PMU prepared TORs for hiring a consultancy service so that a Concept Note is prepared for setting up Pakistan’s first Sustainable Urban Transport Knowledge Management Database (SUT-KMD) Centre in Islamabad (one of the approved activities of AWP-2013). The Concept Note is now prepared. However, the related detailed framework of SUT-KMD will be prepared in 2014. Moreover, in backdrop of the current accelerated progress being made by Capital Development Authority (CDA), Asian Development Bank (ADB) & Punjab Metrobus Authority (PMA), and as per one of the activities of approved Annual Work Plan (AWP) of PAKSTRAN project for 2013, PAKSTRAN PMU prepared 2 sets of TORs for arranging a consultative workshop in Islamabad. This workshop will be organized as soon as funds are functional to be disbursed by the PMU.
Annual Progress Report 2014
25
Overall Output Status (mark the output on the scale of 1 to 5 as per the following criteria): 3
Exemplary (5) *****
High (4) ****
Satisfactory (3) ***
Poor (2) **
Inadequate (1) *
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality, and there is evidence that
outputs are contributing to
targeted outcomes
The project is expected to over-achieve targeted
outputs and/or expected levels of
quality
The project is expected to achieve
targeted outputs with expected levels
of quality
The project is expected to partially
achieve targeted outputs, with less
than expected levels of quality
Project outputs will likely not be
achieved and/or are not likely to be
effective in supporting the achievement of
targeted outcomes
Means of Verification: Specific studies, evaluation, field observation, surveys, interviews, spot checks
Annual Progress Report 2014
26
4. LESSONS LEARNT
PAKSTRAN project is in initial stage of implementation so it is early to ascertain the learning points at this stage. However, it is pertinent to mention that the progress against the approved AWP for 2013 has not been very significant so far, as all of the activities which required expenses to be incurred are still withheld for lack of funds to be released by UNDP. In the meanwhile, however, some of the activities which could be undertaken in-house without incurring external expenses (preparation of TORs, etc.) have already been initiated by PMU and all CIUs of PAKSTRAN project. In brief, the delay in release of funds has caused significant impediment in implementing the planned activities envisaged by PAKSTRAN project. Moreover, the general status of project expenditures in relation to annual budget is quite low as the project has no funds in hand to implement the planned active under 2013-approved AWP. Below are some of the key reasons for slow progress of the project:
• Recruitment of staff for PMU & CIUs took extraordinary time (process involved many organizations, including: CIUs, PMU, IP, UNDP & EAD before any contract is issued/signed)
• Project organized first Project Board (PB) meeting on 4th October 2012; Annual Work Plans of CIU-Punjab, CIU-Sindh, CIU-IUCN and PMU could not be approved by the Board as there were some discrepancies related to the financial allocations in the basic/original PAKSTRAN ProDoc signed by Ministry of Environment, UNDP and EAD
• PMU made efforts and organized meetings along with CIUs and EAD in October/November 2012 for justifiable/appropriate financial allocations amongst CIUs & PMU. PMU was successful in November 2012 for bringing consensus amongst CIUs/Provincial RPs & PMU/Federal IP (in presence of UNDP & EAD) related to financial allocations in ProDoc
• Due to efforts by the Project, 2nd PB meeting was held in Islamabad on 1st January 2013. Annual Work Plans of CIU-Punjab, CIU-Sindh and PMU was got approved by the Board (Except CIU-IUCN Annual Work Plan which was not approved by the Board on 1st January 2013 meeting)
• Due to the efforts of PMU along with CIU-IUCN in January & February 2013, CIU-IUCN Annual Work Plan 2013 was also approved by the Project Board on 27 February 2013
• Project prepared, reviewed, & consolidated documents (Quarterly Progress Report, Travel Detail, M&C Log, Risk Log, Lessons-Learned Log and Issues Log, Financial Reports (FRs), Quarterly Work Plan, Travel Plan, List of Planned Sundries Expenditures, FACE Form) for first advance release of funds for PMU, CIU Punjab and CIU Sindh and submitted to UNDP on 12 February 2013 for release of funds, except for CIU-IUCN as their AWP was not approved as of 12 February 2013
Annual Progress Report 2014
27
• Project Board (PB) approved CIU-IUCN AWP-2013 on 27 February 2013, therefore,
documents for first advance release of all CIUs and PMU, including CIU-IUCN as well, were once again prepared/reviewed/consolidated by PMU & forwarded to UNDP
• PMU and CIU-IUCN actively arranged opening of their Project Bank Accounts (PMU account was opened on 18 September 2012). However, opening of CIU-Punjab and CIU-Sindh Project Bank Accounts took extraordinary delays, which were opened on 14 May 2013
• After opening of Project Bank Accounts of Punjab & Sindh, advance requests for 1st quarter 2013 (consolidated version) were forwarded to UNDP once again for rerelease of funds to all CIUs and PMU
• UNDP forwarded a new format of Annual Work Plan-AWP (as per their CPAP) and requested the project to forward them the consolidated AWP-2013 as per CPAP; due to efforts made by Project, PAKSTRAN AWP-2013 as per new format under CPAP was forwarded to UNDP and was got approved by the NPD and UNDP in early April 2013
• Mr. Amjad Nazir (NPD-PAKSTRAN) was transferred on 4 April 2013
• UNDP new requirement emerged on 4 July 2013 for release of funds i.e. signing of LOAs with CIUs before issuance of first releases to all CIUs (even without NPD at that time, PMU prepared draft LoAs and shared with UNDP)
• Government appointed Mr. Arif Alauddin as NPD-PAKSTRAN on 7 May 2013 (after one month of transfer of Mr. Amjad Nazir)
• PMU forwarded the case of change of signatory to UNDP for Mr. Arif Alauddin as NPD PAKSTRAN on 30 May 2013
• However, Government then appointed Mr. K. M. Zubair as NPD-PAKSTRAN on 20 June 2013
• PMU once again forwarded the case of change of signatory to UNDP for Mr. K. M. Zubair as NPD PAKSTRAN on 27 June 2013
• Government again appointed Mr. Arif Alauddin as NPD-PAKSTRAN on 17 July 2013
• PMU once again forwarded the case of change of signatory to UNDP for Mr. Arif Alauddin as NPD PAKSTRAN on 29 July 2013
• Change of signatory case for Mr. Arif Alauddin as NPD PAKSTRAN is still pending with UNDP since 29 July 2013.
Annual Progress Report 2014
28
However, PAKSTRAN PMU, CIUs, UNDP-CO & EAD are actively making every possible effort to initiate project related operational activities as soon as possible. Some of the key results achieved so far by the project are given below:
• Organizing Inception Workshop of PAKSTRAN project along with UNDP and other partners
• Office space for PMU at ENERCON-Islamabad, CIU-Punjab at Urban Unit-Lahore, CIU-
Sindh at Sindh Transport Department-Karachi, and CIU-IUCN at IUCN-Islamabad Office • Finalization of appointments/contracts of NPM , Component Managers and other
professional staff (hiring of additional technical staff as per ProDoc is in-progress by CIUs) • Coordination and management activities of PMU along with CIUs • Arrangement of basic office equipment for PMU and CIUs • Meetings/presentations – Ministry of Water & Power, MD ENERCON, UNDP, IUCN, Sindh
Transport Deptt, Urban Unit Punjab, stakeholders, etc. • DPRs (Direct Payment Requests) arrangement for interim period • Issuance of National Project Director and Component Project Directors notifications • Review of project document – budget revision approval; approval of replacing Ministry of
Environment with Ministry of Water & Power; approval of replacing Ministry of Industry with Planning Commission of Pakistan
• Preparation/consolidation of the project Annual/Quarter Work Plans 2013 • Project bank accounts opening of PMU & CIUs under section 10-E(2) of PCOM • Issuance of Project Board (PB) notification • Convening of 1st Project Board (PB) meeting • Convening of 2nd Project Board (PB) meeting on 1.1.2013 • Approval of annual work plans/budgets for 2013 • Preparation/review/consolidation of 1st, 2nd, 3rd and 4th quarter 2013 work plans/budgets
for release to PMU and CIUs (as per UNDP new format under CPAP)
Annual Progress Report 2014
29
• Preparation/consolidation of Logs (risk log; issues log; communication & monitoring plan; lessons-learned)
• Preparation/finalization of 2013 output-specific ‘baseline’, ‘indicators’, ‘targets’ & related
‘CP outcomes’ for all CIUs (Revised RRF as per UNDP advice) • Preparation of draft guidelines related to the PAKSTRAN project Recruitment,
Procurement, Financial Disbursement and Contract Renewal/ Performance Appraisal Reports
• Preparation of draft Letters of Understanding (LoUs) with CIUs (UNDP new requirement) • Preparation/finalization of various TORs for awarding studies as per approved AWP-2013 • Preparation/finalization of Concept Note for SUT-KMD Centre (Islamabad) and CIU-
Punjab R&D Unit at UET • Preparation/finalization of PAKSTRAN Awareness Raising Strategy
Despite all impediments in the last one year, it is worth mentioning that in the course of establishment of PMU and CIUs, good environment of coordination and facilitation has been evolved amongst all implementing & responsible partners and stakeholders (PMU, CIUs, UNDP, EAD) of the PAKSTRAN Project. This is good for productive working and successful implementation of PAKSTRAN project by all parties in times to come.
Annual Progress Report 2014
30
5. THE WAY FORWARD/ KEY PRIORITIES FOR 2014
The project is expected to achieve its major environmental objectives (reducing GHG emissions associated with urban transport sector) with minor shortcomings till the closure of the project, as there have been some procedural delays in the start-up of the project (mentioned in the previous Section of APR-2014). However, within all these constraints, the project progress towards meeting the objective is one of the strategic priorities of the project in 2014. The detailed annual work plan/budget for 2014 is being prepared/finalized by all CIUs/PMU so that the same could be presented before the 3rd meeting of PAKSTRAN Project Board (PB) for its approval in early 2014. Once approved, CIUs along with PMU will start implementing their various planned activities in 2014. During 2014, PAKSTRAN project aims to improve its progress towards objectives by various activities, including: surveys (boarding & alighting, traffic count and vehicle occupancy) to optimize the operations of BRT-1 in Lahore; BRT feeder routes studies; study on integration of land use along the Lahore BRT-1 corridor and design of other missing components; review of existing feasibility study for the selected BRT route in Karachi; review and re-align institutional framework for Sindh province; implement PAKSTRAN awareness strategy and design action plan for SUT in Punjab and Sindh; develop & implement comprehensive capacity development plans for the target groups in Punjab and Sindh about SUT; prepare & implement monitoring and communication plan-2014 for PAKSTRAN components; build collaborative arrangements with related initiatives; and develop detailed framework for Pakistan’s first sustainable urban transport knowledge management centre (SUT-KMC) in Islamabad for informed decision-making at national & provincial levels.
Annual Progress Report 2014
31
Annex 1: AWP based Reporting Matrix
EXPECTED OUTPUTS (CIU-Punjab) And baseline, associated indicators and annual targets
PLANNED ACTIVITIES (as per AWP) Activity Status Completed, Ongoing, Delayed, Cancelled
AWP Budget ($)
Expenditure ($)
% Delivery
Project Output 1.1: Feasibility studies for a demonstration integrated BRT system in selected cities in Punjab Province Indicators: Number of completed feasibility studies prepared for BRT in Punjab Baseline: No complete feasibility study on BRT is available in Punjab Targets: 2 feasibility studies augmented for BRT in Lahore and Rawalpindi/Islamabad
Activity Result 1.1.1: International workshop on Sustainable Urban Transport (Policy, Planning, Management and BRT).
Delayed 50,000 None 0
Activity Result 1.1.2:Project launching Workshop in Lahore to introduce PAKSTRAN Project to CDGL, LDA, C&W, Transport Department, LTC,TPU, TEPA,UET etc
Delayed 3,000 None 0
Activity Result 1.1.3: Surveys (Boarding & Alighting, Traffic Count and Vehicle Occupancy surveys) to optimize the operations of BRT-1.
Cancelled 40,000 None 0
Activity Result 1.1.4: Feasibility for BRT-2 in Rawalpindi.
Cancelled 20,000 None 0
Project Output 1.2: Plans for implementing demonstration integrated BRT system Indicators: Number of approved integrated BRT implementation plans for selected cities in Punjab Province Baseline: Lack of holistic planning for integrated BRT system in Punjab. Targets: 2 approved implementation plans for integrated BRT system in 2 cities of Punjab
Activity Result 1.2.1: BRT Feeder routes studies including: 1. Assessment of existing ridership, public transport on the these routes; 2. Develop plan for BRT integration with feeder routes and also with other public transport systems along the BRT and feeder routes; and 3. Planning of multimodal facilities for integration of other transports with BRT-1.
Ongoing 45,000 200 10%
Activity Result 1.2.2: Study on integration of land use along the BRT-1 corridor and design of missing components
On going 45,000 200 10%
Annual Progress Report 2014
32
EXPECTED OUTPUTS (CIU-Punjab) And baseline, associated indicators and annual targets
PLANNED ACTIVITIES (as per AWP) Activity Status Completed, Ongoing, Delayed, Cancelled
AWP Budget ($)
Expenditure ($)
% Delivery
Project Output 1.3: Infrastructure for demonstration BRT system Indicators: Number of manuals and studies to improve infrastructure design for BRT system Baseline: Existing BRT system in Punjab has deficiencies in its design and construction Targets: Govt. of Punjab adopted and implemented at least 3 manuals to improve infrastructure design and allied facilities required for the demonstration BRT system
Activity Result 1.3.1: Design, installation and operation (1 year) of Traffic Command and Control Centre (TCCC) for Metro Bus Service and ITS.
Cancelled 20,000 None 0
Project Output 1.4: : An operational demonstration BRT system Indicators: Number of operational frameworks and standard operating procedures for increased efficiencies of BRT operations Cumulative GHG reductions from the BRT demos in Lahore- ktonnes CO2 Baseline: Existing BRT system in Punjab has deficiencies in its operations. Also, no emission calculation is available along the existing corridor in Lahore Targets: Govt. of Punjab adopted and implemented at least 3 SOPs and NEQs to increase efficiencies in BRT operations 304 k tonnes CO2 ( direct reduction from BRT demonstrations in Lahore
Activity Result 1.4.1: Successful deployment and operation (1year) of ITS on BRT-1:
Cancelled 25,000 None 0
Activity Result 1.4.2: Workshop to review the design and implementation of BRT system and sharing of experience with other components of PAKSTRAN
Delayed 4,000 None 0
Activity Result 1.4.3: Third party evaluation of design of BRT system
Delayed 5,000 None 0
Annual Progress Report 2014
33
EXPECTED OUTPUTS (CIU-Punjab) And baseline, associated indicators and annual targets
PLANNED ACTIVITIES (as per AWP) Activity Status Completed, Ongoing, Delayed, Cancelled
AWP Budget ($)
Expenditure ($)
% Delivery
Project Output 1.5: Strengthened institutional framework that enables holistic urban transport development. Indicators: Number of institutions available for carrying out advanced research and comprehensive planning and management exercise related to sustainable urban transport (SUT) Baseline: Multiple entities in an uncoordinated manner are involved in SUT in Punjab Targets: 1 R&D unit operational for development of SUT in Punjab and its linkage with Sustainable Urban Transport Knowledge Management Database (SUT-KMD) Centre in Islamabad
Activity Result 1.5.1: Stakeholder consultations for institutional framework for BRT system (Establishment of BRTA and ITS wing etc) and 2. Consultancy Services for: . Institutional framework for development of BRT Authority . Redefining or refining the role, Lahore Transport Company (LTC) .Re-organization of Transport Department and TEPA
Cancelled 35,000 None 0
Activity Result 1.5.2: Training, capacity development program
Delayed 40,000 None 0
Activity Result 1.5.3: Establishment of Centre of Excellence for BRT research at UET Lahore:
On going 40,000 40,000 plus 100%
Project Output 2.1: Feasibility plans and approved financing for integrating federal bus purchases with “integrated BRT plans” for cities in Sindh Province. Indicators: Number of completed feasibility plans/studies prepared for BRT in Sindh. Baseline: 2 feasibilities studies Targets: 1 bankable feasibility study
Activity Result 2.1.1: Existing feasibility study for the selected BRT route reviewed and updated, including land use study, in consultation with relevant stakeholders
Delayed ,due to non release of funds by UNDP
55,000 Nil 0%
Activity Result 2.1.2: Project Launch Workshop in Karachi
Delayed ,due to non release of funds by UNDP
19,000 Nil 0%
Activity Result 2.1.3: surveys /boarding and lighting, Traffic count and vehicle occupancy surveys of various modes. To optimize the operations of BRT
Delayed ,due to non release of funds by UNDP
55,000 Nil 0%
Annual Progress Report 2014
34
EXPECTED OUTPUTS (CIU-Punjab) And baseline, associated indicators and annual targets
PLANNED ACTIVITIES (as per AWP) Activity Status Completed, Ongoing, Delayed, Cancelled
AWP Budget ($)
Expenditure ($)
% Delivery
Project Output 2.2: Strengthened institutional framework that enables sustainable urban transport development in Sindh Province. Indicators: Number of institutions available for carrying out advanced research and comprehensive planning and management exercise related to sustainable urban transport (SUT) Baseline: Multiple entities in an uncoordinated manner are involved in SUT in Sindh Targets: 1 R&D unit operational for development of SUT in Sindh and its linkage with Sustainable Urban Transport Knowledge Management Database (SUT-KMD) Centre in Islamabad
Activity Result 2.2.1: Review and re-align institutional framework for Sindh province to form BRT authority. (Initial consultation in the form of a series of meetings with all relevant stakeholders for collecting existing information and data related to already prepared BRT/mass transit networks feasibility plans in Sindh)
Delayed ,due to non release of funds by UNDP
45,000 Nil 0%
Annual Progress Report 2014
35
EXPECTED OUTPUTS (CIU-Punjab) And baseline, associated indicators and annual targets
PLANNED ACTIVITIES (as per AWP) Activity Status Completed, Ongoing, Delayed, Cancelled
AWP Budget ($)
Expenditure ($)
% Delivery
Project Output 2.4: Approved and enforced Sindh provincial policy that enables development and operation of sustainable urban transport systems. Indicators: Number of provincial policies for developing sustainable urban transport for Sindh Province Baseline: Lack of comprehensive urban transport policy framework in Sindh Targets: 1 approved Sindh provincial policy on sustainable urban transport with associated implementing rules and regulation (IRRs)
Activity Result 2.4.1: Consultation and drafting of provincial urban transport policy for Sindh. (Making provision for urban transits planning for integrated BRT system by holding meetings, conferences, consultation and legislation.)
Delayed ,due to non release of funds by UNDP
40,000
Nil 0%
Project Output 4.1: Completed awareness raising campaigns on sustainable transport concepts Indicators: Number of completed awareness raising campaigns Number of cities benefiting from awareness raising campaigns Baseline: No focused awareness campaigns Targets: 5 awareness raising campaigns 3 cities where awareness raising campaigns conducted
1. Activity. Develop awareness strategy through a wider consultative process, and design action plan for Punjab and Sindh
Completed 17,500 17,500 100
2. Activity. Implement site specific awareness-raising campaign action plan in Punjab and Sindh
On-going 78,000 60,000 77
3. Activity. Design, develop, disseminate awareness raising material and dynamically maintain a project webpage
Completed 37,000 37,000 100
Project Output 4.2: Completed training program on strategic urban land use and transportation planning conducted at various
1. Activity. Undertake training needs assessment of the target groups in Punjab and Sindh
Completed 10,000 10,000 100
Annual Progress Report 2014
36
EXPECTED OUTPUTS (CIU-Punjab) And baseline, associated indicators and annual targets
PLANNED ACTIVITIES (as per AWP) Activity Status Completed, Ongoing, Delayed, Cancelled
AWP Budget ($)
Expenditure ($)
% Delivery
training, academic and vocational institutes in Pakistan Indicators: Number of completed training courses on strategic urban land use and sustainable urban transport planning (SUTP) Number of cities and provincial planners and students trained on land use planning (LUP) and SUTP Number of educational institutes where LUP and SUTP courses are offered Baseline: No capacities exists in Pakistan regarding urban land use and sustainable urban transport planning Targets: 8 training courses of strategic urban land use and sustainable urban transport planning 30 city and provincial planners and students trained 4 educational institutes where LUP and SUTP courses offered
2. Activity. Develop a comprehensive capacity development plan for the target groups in Punjab and Sindh
On-going 7,000 7,000 100
3. Activity. Implement the capacity development plan for the target groups
On-going 22,000 18,700 85
Project Output 4.3: Sharing experiences/building collaborative arrangements on integrated BRT development and implementation of the Trucking Policy Indicators: Number of completed workshops on integrated BRT development
1. Activity. Documentation and dissemination of workshops reports and lessons learned from workshops in Punjab and Sindh to be conducted by all CIUs
Delayed 29,500 0 0
2. Activity. Organize sensitization visits for the relevant planners and officials to cities with good BRT examples
Delayed 30,000 0 0
Annual Progress Report 2014
37
EXPECTED OUTPUTS (CIU-Punjab) And baseline, associated indicators and annual targets
PLANNED ACTIVITIES (as per AWP) Activity Status Completed, Ongoing, Delayed, Cancelled
AWP Budget ($)
Expenditure ($)
% Delivery
Number of completed workshops on the implementation of the Trucking Policy Baseline: No completed workshops on Integrated BRT and Trucking Policy Targets: 8 workshops on integrated BRT development 8 workshops on Trucking Policy implementation completed :
Output 5.1: Management, Coordination Monitoring and Evaluation Indicators: Number of sustainable urban transport knowledge management databases Centre Number of collaborative arrangements with related initiatives Baseline: No Number of sustainable urban transport knowledge management databases and no collaborative arrangements available related to SUT. Targets: 1 sustainable urban transport knowledge management database centre in Islamabad 2 related projects collaborating with PAKSTARN for lessons learnt and knowledge sharing
Activity Result 5.1: Coordinate with CIUs for consolidation of AWPs. Oversee measurement of Means of Verification of CIUs progress on outputs and implementation. Oversee the hiring of specific studies/institutions of CIUs. Monitor events carried out by CIUs.
In Progress 16,200 2,636 17
Activity Result 5.2: Build Collaborative Arrangements with related initiatives as detailed out under section “Collaborative Arrangements with Related Projects” of ProDoc.
Delayed 28,106 0 0
Activity Result 5.3: Establish Pakistan’s first Sustainable Urban Transport Knowledge Management Centre (SUT-KMC) for informed decision-making at national & provincial levels
In -Progress 16,206 0 0
Activity Result 5.4: Manage assistance to the project administratively, financially, logistically, professionally and technically
In –Progress 4,000 0 0
Annual Progress Report 2014
38
EXPECTED OUTPUTS (CIU-Punjab) And baseline, associated indicators and annual targets
PLANNED ACTIVITIES (as per AWP) Activity Status Completed, Ongoing, Delayed, Cancelled
AWP Budget ($)
Expenditure ($)
% Delivery
Operations and Management (PMU & CIUs) Salaries of the staff
Printing and publication
Procurement
Rental and maintenance
Travel
Miscellaneous
In- Progress 817,859 84,983 10.39
TOTAL 1,699,371 278,219 16.37%
Annual Progress Report 2014
39
Annex 2: Annual Project Quality Assurance Assessment ANNEX- 2
PAKSTRAN ANNUAL PROJECT QA ASSESSMENT
OVERALL PROJECT Is PAKSTRAN project responsive to country needs and priorities, and does it logically and justifiably support outcome-level results?
EXEMPLARY (5)
HIGH (4)
SATISFACTORY (3)
POOR (2)
INADEQUATE (1)
All criteria are rated High or Exemplary
All criteria are rated Satisfactory or higher,
and at least two criteria are rated High or
Exemplary
One criterion may be rated Poor, and all other criteria are rated Satisfactory or
higher
Two criteria are rated Poor, and all other criteria are rated
Satisfactory or higher
One criterion is rated Inadequate, or more than two criteria are rated Poor
HIGH (4)
STRATEGIC
Is PAKSTRAN project following a path consistent with UNDP strategic objectives and directions?
Aligned with UNDAF and country programme outcomes and corporate outcomes (UNDP Strategic Plan) and with UNDP’s
potential to contribute
Contributes to ‘transformational change’ in terms of depth and scale
EXEMPLARY (5)
HIGH (4)
SATISFACTORY (3)
POOR (2)
INADEQUATE (1)
The project is fully aligned to UNDP
strategic objectives and demonstrates
innovation
The project is fully aligned to UNDP
strategic objectives
The project is primarily aligned to UNDP strategic
objectives
The project is minimally aligned with UNDP strategic
objectives
The project is inconsistent with UNDP strategic
objectives
HIGH (4)
RELEVANT Does PAKSTRAN project address national development needs and priorities?
Addresses national and local priorities and opportunities for inclusive human development
Annual Progress Report 2014
40
Method of delivery is appropriate to the development context, and is adaptable and flexible to changing situations
Draws on knowledge and lessons learned, incorporates continuous learning and use of good practices and innovations
EXEMPLARY (5)
HIGH (4)
SATISFACTORY (3)
POOR (2)
INADEQUATE (1)
National counterparts see the project as a key
priority that is fundamental in
addressing national development
objectives
National counterparts see the project as an
important component to address national
development objectives
National counterparts see the project as supporting
national development objectives
National counterparts see the project as minimally
contributing to national development objectives
National counterparts believe the project is
inconsistent with national development objectives
HIGH (4)
MONITORING &
EVALUATION
Is PAKSTRAN project being managed and monitored effectively?
Sound results-based management logic showing a theory of change (‘development story’), SMART indicators, and
clear results
Systematic data gathering and agile decision making based on evidence (including use of baselines, sex-
disaggregated data and M&E plans and systems)
EXEMPLARY (5)
HIGH (4)
SATISFACTORY (3)
POOR (2)
INADEQUATE (1)
Project management regularly monitors project schedule,
budget, results achievement, and
risks; uses this information to drive
decision-making; and makes projections to model possible future
Project management regularly monitors
project schedule, budget, results achievement, and
risks; and uses this information to drive
decision-making
Project management regularly monitors project
schedule, budget, and results achievement
Project management infrequently monitors project schedule, budget, and results
achievement
Project management does not effectively
monitor project schedule, budget, and results
achievement
Annual Progress Report 2014
41
situations
HIGH (4)
EFFICIENT
Is PAKSTRAN project economically converting resources (funds, time, staff, procured products and services, etc.) into results (outputs)?
Cost-efficient use of resources and demonstrates maximum value for money
Clearly defined accountabilities for the management of resources and results
Outputs are delivered on time
EXEMPLARY (5)
HIGH (4)
SATISFACTORY (3)
POOR (2)
INADEQUATE (1)
The project follows innovative approaches to maximize resources,
and is projected to achieve outputs under budget and/or ahead
of schedule, or will over-achieve results
(outputs) within budget and schedule
The project is maximizing resources,
and is projected to achieve outputs on
budget and on schedule
The project is effectively managing resources to
produce targeted results
The project is somewhat effective in managing
resources, but has discrepancies
The project is not effectively managing resources to improve
efficiency
POOR (2)
EFFECTIVE
Is PAKSTRAN project producing results (outputs) with appropriate levels of quality to support the achievement of targeted outcomes?
Outputs make an effective contribution to outcomes and demonstrate maximum value for money
Implementation modalities are conducive to the achievement of outputs
Annual Progress Report 2014
42
Risk is mitigated and managed through clear accountabilities and appropriate management arrangements
Meets corporate social and environmental standards, including gender and human rights considerations
EXEMPLARY (5)
HIGH (4)
SATISFACTORY (3)
POOR (2)
INADEQUATE (1)
The project is expected to over-achieve
targeted outputs and/or expected levels of quality, and there is evidence that outputs
are contributing to targeted outcomes
The project is expected to over-achieve targeted outputs and/or expected
levels of quality
The project is expected to achieve targeted outputs
with expected levels of quality
The project is expected to partially achieve targeted
outputs, with less than expected levels of quality
Project outputs will likely not be achieved and/or
are not likely to be effective in supporting the achievement of targeted
outcomes
SATISFACTORY (3)
SUSTAINABILITY
& NATIONAL
OWNERSHIP
Is PAKSTRAN project producing results (outputs) that are sustainable, as well as nationally managed and owned?
Strong partnerships with key stakeholders throughout the project cycle
Institutional capacity development and strengthening of national systems to sustain results and build resilience
Phase-out plan developed and implemented with key stakeholders to sustain outcomes after UNDP’s contribution (i.e.
resources) ceases
EXEMPLARY (5)
HIGH (4)
SATISFACTORY (3)
POOR (2)
INADEQUATE (1)
The project is fully nationally owned and run, and is producing
results that are planned for
sustainability and are likely to be sustainable
The project is producing results that are planned
for sustainability and are under national
ownership
The project is on track to produce results that are sustainable, nationally
owned, and support national capacity
development
The project has unclear or problematic plans for
sustainability and transition to national ownership
The project does not have plans for sustainability
and transition to national ownership
Annual Progress Report 2014
43
SATISFACTORY (3)