Dragonfly Solar EP4-29 New Solar facility added to existing wind farm in Dodge Center, MN
![Page 2: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/2.jpg)
Introduction
• Dragonfly Solar completed construction of a 979.2 kWDC, 720 kWAC solar photovoltaic Project which began commercial operations on September 11, 2018.
• Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund.
• Power is being supplied to NSP through a Solar Energy Purchase Agreement
![Page 3: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/3.jpg)
Project Goals and Objectives
• Demonstrate Improvements in infrastructure efficiency
• Increase aggregate production that is closer to firm capability
• Increase knowledge of construction techniques
• Reduce interconnection costs
• Help increase market penetration of distributed generation
![Page 4: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/4.jpg)
Project Description
• Capacity: 979.2 kW/DC, 720 kW/AC
• (2,880) 340 watt PV modules, (12) 60 kW inverters
• Connected to 34.5kV collection system from the wind farm
• Built on an abandoned railroad right away
• 1,650’ x 75’8”
• Fixed tilt Unirac racking system on driven piers
• Power delivered to NSP through existing 69kV transmission line
![Page 5: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/5.jpg)
Overview of site
The array is located on an abandoned railroad right away
adjacent to the McNeilus wind farm.
![Page 6: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/6.jpg)
Site selction
• Privately owned abandoned railroad right away • Required a variance from set back restrictions from Dodge County • Zoning board was appreciative that we didn’t compete with agricultural interests • Created no hardships for the neighbors
• Required creative design and construction techniques • Managing drainage • Electrical design • Minimizing the impact from shading • Creative work flow
• Connecting with transmission system • Close proximity to AC line • Reduce scope and cost of MISO study
![Page 7: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/7.jpg)
Permitting and Legal Agreements • Conditional Use Permit
• Variance from Setback
• Zoning Permit
• MISO Interconnection Agreement Amendment
• NPDES
• Electrical Permit
• Solar Power Purchase Agreement
• Amended Generator Interconnection Agreement
• Land Lease
• Transmission and Interconnection Agreement
• Construction Agreements
![Page 8: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/8.jpg)
Site Design and Construction techniques
• Proximity of Wind Turbines • Shadows • Ice shedding
• Grading • Retaining existing water flow • Not affecting neighboring land
• Construction flow • Working in Zones • De-watering • Staging equipment
![Page 9: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/9.jpg)
Before Construction
The array is located on an former railroad bed which
served as a service drive for the McNeilus wind farm.
![Page 10: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/10.jpg)
Initial Grading
![Page 11: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/11.jpg)
Staging
Work was performed in zones. Here staging is begun for the first zone.
![Page 12: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/12.jpg)
Zone 1 completed
Racking, underground electric and modules installed in 1st zone.
![Page 13: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/13.jpg)
Water Diversion
• Here the trench that runs throughout the array is temporarily used to divert storm water from a work zone. It was later de-watered and back-filled to accommodate electrical conduit.
![Page 14: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/14.jpg)
Equipment area before and after water control procedures.
![Page 15: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/15.jpg)
Array Design
• Racking • Unirac GMT • Pier Driven
• Modules - Heliene
• Inverters – Chint Power Systems
• String Design • String layout • Multiple Maximum Power Point tracking
• Voltage drop considerations
![Page 16: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/16.jpg)
Project Benefits
• Doesn’t compete with agricultural interests
• Demonstrates construction techniques to keep construction costs down
• Non-traditional site use • Increases the supply of sites suitable for distributed generation • Increase affordability by increasing the supply of sites
• Reduce project cost and complexity by co-locating and utilizing existing wind infrastructure and interconnection agreements
• Increase supply of On-peak energy
• Environmental benefits
• Economic benefits
![Page 17: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/17.jpg)
Lessons learned
• Construction techniques for non-traditional sites • Shared Interconnection and infrastructure • Project timing
![Page 18: Dragonfly Solar EP4-29...• Dragonfly Solar completed construction of a 979.2 kW DC, 720 kW AC solar photovoltaic Project which began commercial operations on September 11, 2018](https://reader034.vdocuments.net/reader034/viewer/2022043009/5f9d24945c536c27d32c3450/html5/thumbnails/18.jpg)
Usefulness of Project Findings
• Using non-traditional sites can increase the supply of sites for solar generation facilities • The increased supply of sites can exert downward pressure on project costs • Reduce the cost of generation from solar
• Reduce amount of agricultural lands taken out of production for generation
• Increase market penetration of distributed generation • Shared interconnection will make more projects viable • Increases the efficiency of existing infra structure • Increased availability of suitable sites and downward pressure on pricing will lead to more developers able to participate
in the market
• Combining wind and solar makes the over all output more predictable and benefits grid managers
• Foster good relationships with local jurisdictions and the community by taking less crop land away from other uses