drwg january 8, 2014| holyoke ma

10
DRWG JANUARY 8, 2014| HOLYOKE MA DOUG SMITH MANAGER OF DEMAND RESOURCE ADMINISTRATION Demand Resource Performance on December 14 th 2013 Initial Results Subject to Data Corrections

Upload: sailor

Post on 04-Jan-2016

20 views

Category:

Documents


0 download

DESCRIPTION

DRWG January 8, 2014| Holyoke MA. Doug Smith Manager of Demand Resource Administration. Demand Resource Performance on December 14 th 2013. Initial Results Subject to Data Corrections. Presentation Notes. All performance based on meter data submitted for initial settlement - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: DRWG January 8, 2014| Holyoke MA

DRWG JANUARY 8, 2014| HOLYOKE MA

DOUG SMITH

MANAGER OF DEMAND RESOURCE ADMINISTRATION

Demand Resource Performance on December 14th 2013

Initial Results Subject to Data Corrections

Page 2: DRWG January 8, 2014| Holyoke MA

Presentation Notes

• All performance based on meter data submitted for initial settlement– There are some low-impact data validations pending

• Net CSO is the amount dispatched and is generally CSO less the gross-up for losses

2

Page 3: DRWG January 8, 2014| Holyoke MA

December 14th 2013 OP4 Event Background• Morning Report projected a 275 MW surplus based on a load forecast of 19,550 MW (actual

peak was 20,182 MW for hour ending 1800)

• Forced outages were about 400 MW greater than anticipated

• Deliveries to New England were about 686 MW lower than expected due to curtailments

• Through hour ending 1600, loads tracked forecast, but then began to exceed forecast, climbing rapidly

• At 1700 significant imports were curtailed, resulting in M/LCC 2 and OP#4 Action 1 being declared, as well as Winter Reliability Program DR Assets being dispatched (21 MW)

• At 17:07 OP#4 Action 2 was declared and 248 MW of RTDR was dispatched (the entire net CSO for all dispatch zones)

• At 17:40 Action 5 was declared; it was cancelled at 18:30 due to some imports coming back

• At 20:45 Action 2 was cancelled, releasing the RTDR demand resources

• At 21:46 the Winter Reliability Program DR assets were released

3

Page 4: DRWG January 8, 2014| Holyoke MA

Performance Reporting for Overlapping Winter Reliability Program DR and OP4 Action 2 Dispatch

• Some assets that are mapped to FCM Resources are also participating in the Winter 2013-14 Reliability Solutions program subject to Appendix K of Market Rule 1

• During a coincident dispatch such as on 12/14/2013, the Winter obligations of the assets are incremental to the FCM resource obligation.

• In coincident dispatch periods, performance for the Winter DR assets will be reported net of the portion of their performance required for the RTDR Resource to which they are mapped to reach 100% of its dispatched MW.

• FCM Settlement includes entire performance from winter assets, and will be reported in total as well as net of performance attributed to the Winter asset dispatch.

4

Page 5: DRWG January 8, 2014| Holyoke MA

Winter Reliability Program DR Asset Performance Across Entire Dispatch

Duration of the December 14th, 2013 Real Time Event

(Local Time)

MW Dispatched

Initial Performance

(net of performance allocated to coincident

OP4 Dispatch)

Percent Performance vs. Dispatch

Start Time (after 30

minute ramp) End Time

5:35 PM 9:50 PM 21 30.975 147.5%

5

Page 6: DRWG January 8, 2014| Holyoke MA

Hourly Integrated Winter Reliability Program DR Performance

Hour End

Winter Dispatched

MW *

Overall Performance

(MW)

FCM Net CSO Dispatched

**

Performance Attributed to

Winter Reliability Dispatch

Performance vs. Dispatch

18 8.75 37.5 8.4 29.1 332.4%

19 21 68.4 38.4 29.9 142.6%

20 21 62.2 38.9 23.4 111.4%

21 21 56.6 32.7 23.9 113.9%

22 17.5 46.6 0.0 46.6 266.5%

6

* Aggregate Winter Reliability Program obligation adjusted for number of dispatched intervals

** Adjusted for number of dispatched intervals and contributions from non-Winter Reliability assets

Page 7: DRWG January 8, 2014| Holyoke MA

7

OP#4 Action 2 RTDR Dispatch on December 14th, 2013Inclusive of all Winter Reliability Asset Performance

Effective Time of Dispatch December 14th, 2013 (Local

Time)

MW Dispatched (NET CSO)

Performance during 100%

Dispatch period (MW) Inclusive of Full Winter

DR Asset Performance

Percent Avg. Performance vs. Net CSO

Start Time (after 30

minute ramp) End Time5:40 PM 8:35 PM 247.8 191.4 77.2%

Page 8: DRWG January 8, 2014| Holyoke MA

8

RTDR Performance on December 14th, 2013 Including all Intervals of Dispatch (17:40 to 20:50)

Load ZonesDispatched MW (Net

CSO)

Initial Performance

(MW)

Percentage of Initial Performance to Dispatched MW

CT 52.1 19.3 37.0%

ME 126.9 133.5 105.2%

NEMA 3.5 1.6 44.0%

NH 3.2 1.4 45.1%

RI 10.2 6.1 59.6%

SEMA 7.0 0.3 3.9%

VT 25.9 23.2 89.5%

WCMA 19.0 6.0 31.8%

Total 247.8 191.3 77.2%

Page 9: DRWG January 8, 2014| Holyoke MA

9

RTDR Performance on December 14th, 2013 Including all Intervals of Dispatch (17:40 to 20:50)

Net of Performance Attributable to Winter Reliability Program

Load Zones Dispatched MW

Initial Performance

(MW) Percentage

CT 52.1 19.3 37.0%

ME 126.9 107.9 85.0%

NEMA 3.5 1.6 44.0%

NH 3.2 1.4 45.1%

RI 10.2 6.1 59.6%

SEMA 7.0 0.3 3.9%

VT 25.9 23.2 89.5%

WCMA 19.0 6.0 31.8%

Total 247.8 165.8 66.9%

Page 10: DRWG January 8, 2014| Holyoke MA

10