drwg june 10, 2013 holyoke , ma

14
DRWG JUNE 10, 2013 HOLYOKE, MA Doug Smith MANAGER OF DEMAND RESOURCE ADMINISTRATION Active Resource Audit Results Passive Resource Performance December 2012 and January 2013 Winter Performance Update for Demand Resources

Upload: dorit

Post on 05-Jan-2016

40 views

Category:

Documents


3 download

DESCRIPTION

DRWG June 10, 2013 holyoke , MA. Doug Smith. Manager of Demand Resource Administration. Active Resource Audit Results Passive Resource Performance December 2012 and January 2013. Winter Performance Update for Demand Resources. Presentation Notes. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: DRWG June 10, 2013 holyoke , MA

DRWG JUNE 10, 2013 HOLYOKE, MA

Doug SmithMANAGER OF DEMAND RESOURCE ADMINISTRATION

Active Resource Audit Results

Passive Resource Performance

December 2012 and January 2013

Winter Performance Update for Demand Resources

Page 2: DRWG June 10, 2013 holyoke , MA

Presentation Notes• For comparability, All performance is reported in DRV and all CSO is

reported as Net CSO, which is a non-grossed up value (typically CSO/1.08 except for multi-year obligations incurred in FCA1 and 2.)

• In the rare cases of multiple audits for a resource, highest performance was used. The impact from this is trivial.

• MW values and % data are rounded.

• Performance from the RTDR Dispatch on 1/28/13 covered in May DRWG – see http://www.iso-ne.com/committees/comm_wkgrps/mrkts_comm/dr_wkgrp/mtrls/2013/may12013/a04_rtdr_performance_on_1_28_2013.ppt.

2

Page 3: DRWG June 10, 2013 holyoke , MA

ACTIVE (RTDR AND RTEG) AUDIT RESULTS DURING WINTER 2012 - 2013

Page 4: DRWG June 10, 2013 holyoke , MA

Audit Results by Resource TypeWinter 2012-2013

Resource Type

Performance (MW)

Net CSO (MW)

Percent Net CSO

RTDR 446 377 118%

RTEG 258 261 99%

Total 703 638 110%

4

Page 5: DRWG June 10, 2013 holyoke , MA

RTDR Audit ResultsWinter 2012 - 2013

Load Zone Dispatched

MW (net CSO)Performance

(MW)Percentage

CT 75 86 116%ME 141 207 146%

NEMA 19 28 146%NH 22 17 75%RI 18 22 122%

SEMA 13 15 112%VT 36 36 99%

WCMA 51 35 68%

Total 377 446 118%5

Page 6: DRWG June 10, 2013 holyoke , MA

Winter 2012 - 2013 RTDR Audit Results Capped at Load Zone Net CSO

Load Zone Dispatched

MW (net CSO)

Performance Capped at Load Zone Net CSO

(MW)

Percentage

CT 75 75 100%

ME 141 141 100%

NEMA 19 19 100%

NH 22 17 75%

RI 18 18 100%

SEMA 13 13 100%

VT 36 36 99%

WCMA 51 35 68%

Total 377 354 94%6

Page 7: DRWG June 10, 2013 holyoke , MA

RTDR Audit Results – Winter 2012 - 2013

7

Page 8: DRWG June 10, 2013 holyoke , MA

RTEG Audit ResultsWinter 2012 - 2013

Load Zone Dispatched MW

(net CSO)Performance

(MW)Percentage

CT 115 116 101%ME 11 14 126%

NEMA 34 33 96%NH 22 22 98%RI 20 18 90%

SEMA 19 18 93%VT 6 7 120%

WCMA 34 30 88% Total 261 258 99%

8

Page 9: DRWG June 10, 2013 holyoke , MA

RTEG Audit Results Capped at Load Zone NET CSO – Winter 2012 - 2013

Load Zone Dispatched

MWPerformance

(MW)Percentage

CT 115 115 100%ME 11 11 100%

NEMA 34 33 96%NH 22 22 98%RI 20 18 90%

SEMA 19 18 93%VT 6 6 100%

WCMA 34 30 88% Total 261 252 97%

9

Page 10: DRWG June 10, 2013 holyoke , MA

RTEG Audit Results – Winter 2012 - 2013

10

Page 11: DRWG June 10, 2013 holyoke , MA

PASSIVE (ON PEAK AND SEASONAL PEAK) RESOURCES - PERFORMANCE

Average of Performance Months (Dec 2012 -Jan 2013)

Page 12: DRWG June 10, 2013 holyoke , MA

Total Passive Winter Performance & Net CSO by Load Zone

Load Zone Winter 2012-13

Performance (MW)Winter 2012-13

Net CSO (MW)

Percentage of Performance vs

Net CSO

CT 488 301 162%ME 131 59 223%

NEMA 293 164 179%NH 66 52 126%RI 84 59 142%

SEMA 162 99 164%VT 98 59 168%

WCMA 189 110 173% Total 1,513 903 168%

12

Page 13: DRWG June 10, 2013 holyoke , MA

Total Passive Winter 2012-2013 - Range of Performance & Net CSO

13

Page 14: DRWG June 10, 2013 holyoke , MA

14