DSLNG Project Update
Andy Karamoy
PT Donggi Senoro LNG
4th LNG Supply, Transport and Storage Indonesia 19-21 May 2014 Bali, Indonesia
Table of Contents 1. Introduction of Donggi Senoro LNG Project
2. Keys to successful project execution
3. DSLNG’s effort for project integration
2 Strictly Confidential
Project Location Central Sulawesi
1. Introduction of Donggi Senoro LNG Project
Arun NGL
Badak NGL
Tangguh LNG
4th LNG Project in Indonesia
DSLNG
1862 km from Jakarta to Luwuk
( 3 hours flight B-737)
3 Strictly Confidential
Aerial Photo at LNG Plant Site Current
Material Offloading Facility LNG Jetty Air Fin Coolers Firewater Tank Main Control Room
Gas Turbine Generators Main Substation MCHE
Flare LNG Tank Refrigerant Storage
4 Strictly Confidential
EPC Construction Progress
Admin Building
EPC Construction Progress
Camp Area
Business Structure Indonesia’s first down stream LNG Business model to produce LNG
MGDP/ Matindok
DES
Upstream
JOB PMTS/ Senoro
DSLNG LNG Buyers
FOB
KOGAS
Kyushu Electric
Chubu Electric
Gas Sales Agreement
LNG SPA
LNG SPA
LNG SPA
TCA
85 mmscfd
250 mmscfd
1 mtpa
0.3 mtpa
0.7 mtpa
2 mtpa
Gas Sales Agreement
1. Introduction of Donggi Senoro LNG Project
5 Strictly Confidential
1. A good example of “Development of Stranded Natural Resources”
• Best-mix development provides an opportunity for development of natural resources which left undeveloped for more than decades.
2. “Front Runner” project in Eastern Indonesia (Sulawesi EC)
• One of the biggest projects in Sulawesi Economic corridor of which development is one of the objectives under “ACCELERATION AND EXPANSION OF INDONESIAN ECONOMIC DEVELOPMENT 2011-2015 MASTERPLAN”.
3. First downstream LNG project in Indonesia
• All investment and operating risk will be borne by PT DSLNG
• No cost recovery burden of considerable LNG Plant Development to GOI
4. Collaboration amongst Indonesia, Korea, Japan
• The first LNG project which stakeholders from upstream, midstream (LNG Plant Operator) up to LNG buyers are all Asian companies.
Highlights of Donggi Senoro LNG
1. Introduction of Donggi Senoro LNG Project
6 Strictly Confidential
Key Challenges of Donggi Senoro LNG
2. Key to successful project execution
Schedule Management and Cost Control
Coordination between upstream parties and DSLNG
Corporate Vision, Mission and Values
DSLNG is a joint venture with cross-culture and various backgrounds First Business Model (Downstream LNG Project) in Indonesia
Code of Conduct QHSE policy
Stakeholders Management
Strong Organization
Operation readiness Enterprise Risk Management
7 Strictly Confidential
Land Acquisition experience
2. Key to successful project execution
7 Strictly Confidential
1. Legal Basis
– Law Number 5 of 1960 concerning the Basis Agrarian Law
– Law Number 2 of 2012 concerning Land Procurement for Development of Public Interests; etc
2. The Principle of Indonesian Land Law
Indonesian land law recognize horizontal separation Principle
(separated ownership of the land and buildings/plants)
3. Type of Rights of Land: Land with individual rights and Tanah Negara (Indonesia still recognize Adat Land and Ulayat Right)
Land with individual rights, consists of:
– Hak Milik (Right of Ownership),
– Hak Guna Usaha (Rights of Cultivation),
– Hak Guna Bangunan (Rights of Use of Building),
– Hak Pakai (Right to Use)
Procedure to Obtain Land
Page 11
PT X Obtaining
Location Permit Land Acquisition, by:
Free State Land BPN
Transferring (the Land title
is same)
Releasing (the Land
title is different)
HGB in the name of PT X
Registration to Change the ownership name
Application for the HGB
Issued by Local
Government after
recommended by BPN
Land Deed Offiicer (PPAT)
-Kepala Desa
-Camat/Lurah
-Notaris
2. Key to successful project execution
FINANCIAL SPLIT GOVERNMENT REVENUEA AFTER COST RECOVERY AND TAX
CRUDE (NET GOVERNMENT SHARE)
100%
85% Government
15% Contractor
100%
85% Central
15% Local
3% Province
12% Regent/ City
6% Producing Regent
6% Other Regents in the Province
100%
70% Government
30% Contractor
100%
70% Central
30% Local
6% Province
24% Regent/City
12% Producing Regent
12% Other Regents in the Province
GAS ( NET GOVERNMENT SHARE)
- Province tax
- Local Retribution
Less:
2. Key to successful project execution
Intensify the socialization of future local benefits
Schedule Management and Cost Control
Overall EPC progress
Good management of schedule and cost by progress measurement agreed by DSLNG and EPC contractor
3. DSLNG’s effort for the project integration - ”spent and schedule”
Weight Planned Actual
Engineering 11.05% 100% 100%
Procurement 44.93 98.56% 100%
Construction 44.02% 95.11% 96.50%
Overall Progress 100% 97.20% 98.46%
Physical Construction Progress
Last Month (Cummulative)
This Month This Month
(Cummulative)
Plan 90.5% 2.6% 93.1%
Actual 93.6% 1.5% 95.1%
Overall EPC progress
As of 25 April 2014
8 Strictly Confidential
Sulawesi LNG Development
59.9%
Pertamina Hulu Energi
29.0%
Medco LNG
11.1%
Donggi Senoro LNG
SENORO
MATINDOK
PHE Tomori
50%
Medco Tomori
30%i
Tomori EP UK
20%
Pertamina EP 100%
PERTAMINA MITSUBISHI MEDCO KOGAS
3. DSLNG’s effort for the project integration
Coordination between upstream parties and DSLNG Steering Committee is established amongst Ultimate Shareholders to monitor overall progress
Upstream Downstream Coordination Forum Coordination & Collaboration for interface matters by management level
Upstream Downstream Working Groups Technical Working Group/Commercial Working Group
CSR Working Group/QHSE Working Group
Tomori EP UK: MITSUBISHI 51%/ KOGAS 49%, Sulawesi LNG Development: MITSUBISHI 75%/KOGAS 25%
9 Strictly Confidential
Preparation for start-up and Operation Readiness
3. DSLNG’s effort for the project integration
Preparation for hand-over from EPC contractor and readiness for DSLNG’s independent operation
O&M Phase
First LNG Feed Gas
Operation Readiness
Mechanical completion
2011~2013 2014 2015
EPC Phase Start-Up
• Operation Organization • Process Safety Management • Production and Marine • Maintenance and Inspection • Technical Services • Operations Support • Gas & LNG Delivery Procedure • QHSE • ICT • Security • Assurance • Business Continuity
Commercial Operation Commissioning
11 Strictly Confidential
Thank you
Key Challenges of Donggi Senoro LNG
2. Key to successful project execution
MISSION
DSLNG is a joint venture with cross-culture, various backgrounds
To be a safe and reliable provider of LNG
• Build and operate a reliable LNG project • Ensure all stakeholders benefit from the LNG value chain • Be a socially and environmentally responsible LNG company
VISION
Strictly Confidential
LNG Plant Specifications
• Feed Gas Supply 335 million standard cubic feet per day
• LNG Sales 2 million tonnes per year
• Process Technology APCI – propane pre-cooled mixed refrigerant
• LNG Tank Capacity 170,000 cubic meters x 1 tank
• Refrigeration Compressor Driver
Gas Turbine (Frame 5)
• Generating Capacity 3 x 22.6 Mega Watts
• Cooling Media Air
• Loading Arms 2 LNG Loading, 1 Vapor Return
• LNG Loading Pumps 2 x 2,000 cubic meters per hour
• Jetties LNG Loading (Max. 155,000 m3) and MOF
Strictly Confidential
LNG Specifications
• Gross Heating Value 1,060 – 1,170 BTUs /scf
• Methane 85 mol % minimum
• Butane 2 mol % maximum
• Pentane 0.1 mol % maximum
• Nitrogen 1 mol % maximum
• Hydrogen Sulphide 0.25 grain /100scf
• Total Sulphur 1.3 grain/100scf
Strictly Confidential
Additional Informations
• Feed Gas
371,374 MMBTUD
335 MMSCFD
1,108.579 BTU/SCF
• LNG
319,634 MMBTUD
1,100.48 BTU/SCF
4,144 tons/day
• Condensate 2,313 bbl/day
• Own Utilities 40,850 MMTUD
41.9 MMSCFD
• Flare 176 MMBTUD
0.15 MMSCFD
• Plant Thermal Efficiency 88.95%
• Cargo Per Voyage
Hyundai Utopia
56,865 tons
126,086 m3
2,949,588 MMBTU
Northwest Swallow
56,660 tons
125,632 m3
2,938,954 MMBTU
Strictly Confidential