Page 1: Dugway Sewer Community Update: April 1, 2014

Dugway SewerCommunity MeetingApril 1, 2014

Page 2: Dugway Sewer Community Update: April 1, 2014

Tonight’s presentation

• About the project• Project schedule and locations• Looking ahead and what you’ll see• Benefits and partnerships in your

community• Future construction

Page 3: Dugway Sewer Community Update: April 1, 2014
Page 4: Dugway Sewer Community Update: April 1, 2014

44

Dry Weather Flow to treatment plant

Additional Conveyance Capacity Available for

wet-weather

Combined Sewer Overflow Discharge to

Stream/Lake

Page 5: Dugway Sewer Community Update: April 1, 2014

This project will…

• Capture and treat millions of gallons of pollution

Page 6: Dugway Sewer Community Update: April 1, 2014

This project will…

• Provide relief for larger storms

• Convey flow to current sewer, future tunnel

• Prepare for future projects

Page 7: Dugway Sewer Community Update: April 1, 2014

By the numbers

• 11,000 feet3’ to 6’ sewers in tunnel

• 2,700 feet15” to 7’ sewers in open-cut

• Plus structures, regulators, modifications

Page 8: Dugway Sewer Community Update: April 1, 2014

Schedule

• Construction Start Jan 2014• Substantial Completion Nov.

2016• Final Completion Sept.

2017

Page 9: Dugway Sewer Community Update: April 1, 2014
Page 10: Dugway Sewer Community Update: April 1, 2014
Page 11: Dugway Sewer Community Update: April 1, 2014

Dundee D

rive

E. 1

09th S

tree

t

St. Clair Ave.

E. 1

10th S

tree

t

Glenview Ave.

Elk Ave.

E. 1

08th S

tree

t

St. Clair Ave.

E. 1

07th S

tree

t

E. 1

06th S

tree

t

Dupont Ave.

CONSTRUCTION LOOK AHEAD

0 to 30 Days

• Road closure:– E. 110th St./Hazeldell Rd.

between Glenview Ave and Dundee Dr.

– Road closed on March 24, 2014

– Approximate duration:8 months

Page 12: Dugway Sewer Community Update: April 1, 2014

Detour Route

Page 13: Dugway Sewer Community Update: April 1, 2014

CONSTRUCTION LOOK AHEAD

0 to 30 Days• Utility relocation throughout • Work site prep• Preconstruction video, photos• CCTV inspection of existing

sewers

Page 14: Dugway Sewer Community Update: April 1, 2014

CONSTRUCTION LOOK AHEAD

30 to 60 Days

Dundee D

rive

E. 1

09th S

tree

t

St. Clair Ave.

E. 1

10th S

tree

t

Glenview Ave.

Elk Ave.

E. 1

08th S

tree

t

St. Clair Ave.

E. 1

07th S

tree

t

E. 1

06th S

tree

t

Dupont Ave.

• Road closure:– E. 109th St., north of St.

Clair

– Approximate duration:1 year

Page 15: Dugway Sewer Community Update: April 1, 2014

CONSTRUCTION LOOK AHEAD

30 to 60 Days

Detour route

Page 16: Dugway Sewer Community Update: April 1, 2014

CONSTRUCTION LOOK AHEAD

30 to 60 Days

• Exploratory work along St. Clair• Property surveys (Mainly along E.

109th)• Utility relocation, site prep• Start work on mainline sewer

structures along E. 110th/Hazeldell• Sheet pile and secant pile

construction

Page 17: Dugway Sewer Community Update: April 1, 2014

Sheet piling

• Traditional method• Vibratory hammer creates noise,

vibration• Sheeting extends above ground• Used where space is limited

Page 18: Dugway Sewer Community Update: April 1, 2014

Secant Pile Construction Alternative method for

supporting excavations

Holes are drilled with an auger and then filled with concrete

Requires slightly larger footprint than sheet piling

Installed flush with the surface

Drilling operation creates vibration noise

Page 19: Dugway Sewer Community Update: April 1, 2014

Dundee D

rive

E. 1

09th S

tree

t

St. Clair Ave.

E. 1

10th S

tree

t

Glenview Ave.

Elk Ave.

E. 1

08th S

tree

t

St. Clair Ave.

E. 1

07th S

tree

t

E. 1

06th S

tree

t

Dupont Ave.

CONSTRUCTION LOOK AHEAD

60 to 90 Days

• Road closure– Elk Ave. between E. 107th

and E. 107th Place– Approximately 8 months

Page 20: Dugway Sewer Community Update: April 1, 2014

Detour route

Page 21: Dugway Sewer Community Update: April 1, 2014

Dundee D

rive

E. 1

09th S

tree

t

St. Clair Ave.

E. 1

10th S

tree

t

Glenview Ave.

Elk Ave.

E. 1

08th S

tree

t

St. Clair Ave.

E. 1

07th S

tree

t

E. 1

06th S

tree

t

Dupont Ave.

CONSTRUCTION LOOK AHEAD

60 to 90 Days

• Road closure– Elk Ave. at E. 109th St.– Approximately 8 months

Page 22: Dugway Sewer Community Update: April 1, 2014

Detour route

Page 23: Dugway Sewer Community Update: April 1, 2014

CONSTRUCTION LOOK AHEAD

60 to 90 Days

• Utility relocation, site prep• Shafts, ground support• Begin microtunneling• Begin Elk Ave. sewer work

Page 24: Dugway Sewer Community Update: April 1, 2014
Page 25: Dugway Sewer Community Update: April 1, 2014
Page 26: Dugway Sewer Community Update: April 1, 2014

Paving Restoration LocationsEntire Project Area

Page 27: Dugway Sewer Community Update: April 1, 2014
Page 28: Dugway Sewer Community Update: April 1, 2014

Community benefits

• Pollution reduction–System will prevent 110 million

gallons of combined sewer overflow every year

Page 29: Dugway Sewer Community Update: April 1, 2014

Community benefits

• Final roadway restoration will include new pavement

• Enhanced restoration will be considered

Page 30: Dugway Sewer Community Update: April 1, 2014

Good Neighbor Ambassadors• Ambassador team will support

neighborhood projects, receive training, and serve as Sewer District representatives to residents.

Page 31: Dugway Sewer Community Update: April 1, 2014

Future projects

DST Overlap (DST) DST-4 Forest Hills Park DST-5 St. Clair/E 109th DST-7 Lakeview and Ada DST-8 Lakeview and

Superior East 140th Relief Sewer Doan Valley Tunnel (DVT)

Lakeview and Ada Superior Ave

Shoreline Storage Tunnel

(SST) Forest Hills Park Mining

Site

SST

E140

DWIRS

DST

DVT

Page 32: Dugway Sewer Community Update: April 1, 2014

The benefit

Page 33: Dugway Sewer Community Update: April 1, 2014

3900 Euclid Avenue | Cleveland, OH 44115 | (216) 881-6600 | neorsd.org

LEARN MORE.dugwaytunnel.blogspot.comneorsd.org/cleanlake

ASK [email protected]

TWEET US.@neorsd

Page 34: Dugway Sewer Community Update: April 1, 2014

Secant piling

Page 35: Dugway Sewer Community Update: April 1, 2014

Sheet piling

Page 36: Dugway Sewer Community Update: April 1, 2014
Page 37: Dugway Sewer Community Update: April 1, 2014
Page 38: Dugway Sewer Community Update: April 1, 2014
Page 39: Dugway Sewer Community Update: April 1, 2014