DUKE  ELLINGTON  SCHOOL  OF  THE  ARTS    PROJECT  UPDATES  

THURSDAY,  APRIL  7,  2016  

AGENDA    

A.  Introduc<on  B.   Agenda  

•  Site  Overview  and  Site  Plan  

•  Project  Overview  

•  Exterior  Eleva<ons  

•  Floor  Plans  

•  School  Construc<on  Update  /  Progress  Photos  

C.   Ques<ons  &  Answers      

SITE  OVERVIEW  AND  PLAN      

   SITE  OVERVIEW  

   SCHOOL  SITE  PLAN  

R  STREET  NW  

RESERVOIR  ROAD  NW  

35TH  STREET  N

W  36

TH  STR

EET  NW  

EXTERIOR  ELEVATIONS      

   EAST  ELEVATION  –  VIEW  FROM  35TH  STREET  NW  

   NORTH  ELEVATION  –  VIEW  FROM  R  STREET  NW  

   WEST  ELEVATION  –  VIEW  FROM  36TH  STREET  NW  

   SOUTH  ELEVATION  –  VIEW  FROM  RESERVOIR  ROAD  NW  

INTERIOR  FLOOR  PLANS      

LOWER  LEVEL  1  

FLOOPLAN  

GROUND  FLOOR  

PLAN  

FIRST  FLOOR  

PLAN  

SECOND  FLOOR  

PLAN  

THIRD  FLOOR  

PLAN  

FOURTH  FLOOR  

MEZZANINE  

PLAN  

CONSTRUCTION  PROGRESS  PHOTOS      

   CONSTRUCTION  PROGRESS  PHOTOS  –  FOUNDATION  WORK  

   CONSTRUCTION  PROGRESS  PHOTOS  –  FOUNDATION  PILES  

   CONSTRUCTION  PROGRESS  PHOTOS  –  HOISTING  OF  STRUCTURAL  STEEL    

   CONSTRUCTION  PROGRESS  PHOTOS  –  STRUCTURAL  STEEL  IN  PLACE  

   CONSTRUCTION  PROGRESS  PHOTOS  –  FUTURE  PERFORMANCE  HALL  

QUESTIONS  &  ANSWERS