dutch approach to levee reliability and flood risk · timo schweckendiek deltares & delft...

26
PFHA Workshop, Washington DC, January 29-31, 2013 Dutch Approach to Levee Reliability and Flood Risk Timo Schweckendiek Deltares & Delft University of Technology

Upload: others

Post on 12-Oct-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

PFHA Workshop, Washington DC, January 29-31, 2013

Dutch Approach to Levee Reliability and Flood Risk

Timo Schweckendiek

Deltares & Delft University of Technology

Page 2: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

Outline

1. Historical Background

2. Reliability and Risk Analysis

3. System Effects

PFHA Workshop, Washington DC 2

Page 3: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

1953 Flood

PFHA Workshop, Washington DC 3

Page 4: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

Risk-based optimization

PFHA Workshop, Washington DC 4

Van Dantzig, D. (1953). "Economic Decision Problems for Flood Prevention."

Econometrica 24(3): 276-287.

levee crest level

costs

investment

risk

total

= probability ×damage potential

Page 5: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

Delta Committee 1953-1955

PFHA Workshop, Washington DC 5

1. Delta works

2. Reliability target(for Central Holland):

1/125,000 or 8 x 10-6(annual probability)

Page 6: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

Storm surge barriers (delta works)

PFHA Workshop, Washington DC 6

Risk-based approaches in

Design an Construction Planning:

• hydraulic loads

• structural elements

• geotechnics

• operation and maintenance

Oosterschelde Dam, 1970

Maeslant Barrier, 1990

Page 7: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

Safety Standards (Water Act, 1990)

3600km of “primary” flood defenses

57 polders (“dike rings”)

reliability targets per polder

safety assessments every 5 years

PFHA Workshop, Washington DC 7

RISK ANALYSIS PER POLDER /

DIKE-RING

RISK ANALYSIS PER POLDER /

DIKE-RING

Page 8: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

Risk Analysis – Basic Steps (VNK2)

1. Define homogeneous reaches

2. Probability of failure per reach

3. Flood scenarios

4. Damage estimates

5. Combine probabilities and consequences

January 29-31, 2013PFHA Workshop, Washington DC 8

Page 9: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

Define homogeneous reaches

January 29-31, 2013PFHA Workshop, Washington DC 9

Page 10: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

Most important:

opbarsten en piping

beschadigingbekleding

opbarsten en piping

beschadigingbekleding

Piping Erosion outer

slope

Overtopping Slope instability overloop en golfoverslagOvertopping Non-closure

Piping Structural failure

Levees Hydraulic structures

Dunes: Dune erosion

Failure Modes

January 29-31, 2013PFHA Workshop, Washington DC 10

Page 11: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

Probabilistic Framework

model uncertainties

statistics

statistics

January 29-31, 2013

Reliability per Failure Mode (per Reach)

PFHA Workshop, Washington DC 11

loads on levee

loads on levee

river dischargeriver discharge

sea water levelsea water level

windwind

hydrodynamic model(s)

hydrodynamic model(s)

failure modelfailure model

levee resistance

levee resistance

soil cohesionsoil cohesion

crest levelcrest level

slope angleslope angle

probability of failure

probability of failure

P(R<S)

Page 12: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

What do the results look like?

PFHA Workshop, Washington DC 12

Annual probability of failure

>

<

Page 13: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

System Modeling & Fault Tree

PFHA Workshop, Washington DC 13

pipingpiping overtoppingovertopping slope failureslope failure ……

failure

element #1

failure

element #1

Flooding(system failure)

Flooding(system failure)

levee section

dunes

sluice

failure

element #2

failure

element #2

Page 14: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

Correlations / Length-Effect

1. BETWEEN FAILURE MODES (correlated through common variables)

2. BETWEEN REACHES (LENGTH-EFFECT)

3. IN TIME

PFHA Workshop, Washington DC 14

Page 15: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

Hydra-Ring / DAM / FEWS / …

PFHA Workshop, Washington DC 15

Page 16: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

FEWS-DAM: Real-time Levee Safety

Flood Forecasting System

in Indonesia

Warning levels

Water level

history

Water level forecast

(ensemble)

1

2

3

Predicted probability of failure for failure mechanism piping,

based on the predicted outer water level

Actual probability of failure for failure mechanism piping

January 29-31, 2013PFHA Workshop, Washington DC 16

Page 17: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

Real-time Levee Monitoring

January 29-31, 2013PFHA Workshop, Washington DC 1717

Page 18: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

Inundation Scenarios

PFHA Workshop, Washington DC 18

scenarioReach

probability1 2

scenario 1 X P1

scenario 2 X P2

scenario 3 X X P3

Ptot

levee reach

dunes

sluice

Page 19: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

Inundation Simulation

January 29-31, 2013PFHA Workshop, Washington DC 19

Page 20: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

Flood

simulation

+ Evacuation

effectiveness

Consequences per scenario

January 29-31, 2013PFHA Workshop, Washington DC 20

Page 21: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

Risk Integration (e.g. economic damage)

PFHA Workshop, Washington DC 21

scenarioReach

probability damage1 2

scenario 1 X P1 C1

scenario 2 X P2 C2

scenario 3 X X P3 C3

Ptot

levee reach

dunes

sluice

Page 22: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

Dimensions of Risk

Page 23: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

System Effects

January 29-31, 2013PFHA Workshop, Washington DC 23

Page 24: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

System Effects

Van Mierlo, M.C.L.M. et al, 2007, Assessment of floods risk accounting for River System Behaviour, Intl J. River Basin Management Vol 5, No 2 (2007), pp 93-104.

Courage, W., Vrouwenvelder, A.C.W.M., van Mierlo, T. & Schweckendiek, T. (2013): System Effects in

Flood Risk Calculations. Georisk, special issue on “Levee Reliability and Flood Risk”. (in press)

PFHA Workshop, Washington DC 24

Page 25: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

January 29-31, 2013

In a nutshell

1. Approach historically grown since the 1950s.

2. Risk analyses for all major flood defenses.

3. Reliability part based on physics-based computational models.

4. Expert judgment mostly at the level of basic random variables.

5. Account for dependencies / correlations.

6. Failure probabilities in the order of 10-6.

7. Current efforts:

• upgrade / revision (methods and software)

• improve shortcomings (e.g. system effects).

8. International experience: Singapore, Germany, Indonesia, US, …

PFHA Workshop, Washington DC 25

Page 26: Dutch Approach to Levee Reliability and Flood Risk · Timo Schweckendiek Deltares & Delft University of Technology. January 29-31, 2013 Outline 1. Historical Background 2. Reliability

PFHA Workshop, Washington DC, January 29-31, 2013

Dutch Approach to Levee Reliability and Flood Risk

Timo Schweckendiek

Deltares & Delft University of Technology

[email protected]

www.linkedin.com/in/tschw