e zonal&l hirf principles
TRANSCRIPT
-
8/13/2019 E Zonal&L HIRF Principles
1/66
5 - 1XM33 Training MARCH 07
Maintainability & Maintenance Engineering + Maintenance Planning & Services
XM33 TrainingXM33 Training
5..Zonal L/HIRF logiconal L/HIRF logic
Principlesrinciplesbased on Airbus experience
-
8/13/2019 E Zonal&L HIRF Principles
2/66
5 - 2XM33 Training MARCH 07
Page 2AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
THIS PAGE INTENTIONALLY LEFT BLANK
-
8/13/2019 E Zonal&L HIRF Principles
3/66
5 - 3XM33 Training MARCH 07
Page 3AIRBU
SDEUTSCHLANDG
M
BH.
Allrigh
tsreserved.
Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal & L/HIRF logic - Principles
1. Introduction 4
2. Zonal & L/HIRF Analysis 9
3. MWG Review Process 61
4. Summary 64
Table of Contents
-
8/13/2019 E Zonal&L HIRF Principles
4/66
-
8/13/2019 E Zonal&L HIRF Principles
5/66
5 - 5XM33 Training MARCH 07
Page 5AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
1. Introduction MSG-3 Background
-
8/13/2019 E Zonal&L HIRF Principles
6/66
5 - 6XM33 Training MARCH 07
Page 6AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal inspections may be developed from application of the
Zonal Analysis Procedure. This requires a summary review of
each zone on the aircraft and normally occurs as the MSG-3
analyses of structures, systems,and powerplants are being
concluded. These inspections may subsequently be included in
the Zonal Inspections.
In top down analyses conducted under MSG-3, many support
items such as plumbing, ducting, Other Structure,wiring, etc.,
may be evaluated for possible contribution to functional failure.
In cases where a general visual inspection is required to assess
degradation, the zonal inspection is an appropriate method.
1. Introduction MSG-3 Background
Zonal Analysis Procedure
-
8/13/2019 E Zonal&L HIRF Principles
7/66
5 - 7XM33 Training MARCH 07
Page 7AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
1. Introduction MSG-3 Background
Changes of MSG-3 methodology since revision 2
New sections on:
Enhanced zonal analysis
L/HIRF analysis
Revised sections on:
Enhanced zonal analysis
ATA MSG-3
Operator/Manufacturer
Scheduled
Maintenance
Development
Revision 2005.1
ATA MSG-3
Operator/Manufacturer
Scheduled
Maintenance
Development
Revision 2003.1
ATA MSG-3
Operator/Manufacturer
Scheduled
Maintenance
Development
Revision 2002.1
ATA MSG-3
Operator/Manufacturer
Scheduled
Maintenance
Development
Revision 2001.1
ATA MSG-3
Operator/Manufacturer
Scheduled
Maintenance
Development
Revision 2
Changes of MSG-3 methodology since revision 2
Enhanced Zonal Analysis :
Allows appropriate attention to be given to safety related deterioration of wiring, particularly in zoneswith potential for combustible material accumulation
The main intent is to reduce existence of electrical ignition sources and combustible material throughmaintenance tasks
Changes in maintenance regulations have been addressed through an Aging Transport Systems
Rulemaking Advisory Committee (ATSRAC)
The Enhanced Zonal Analysis Procedure (EZAP) was developed by the ATSRAC Task 3 Sub-Committee
L/HIRF Analysis :
The intend of the L/HIRF protection tasks is to reduce the possibility that a single failure cause (e.g.lightning strike) and the occurrence of a common failure cause such as Environmental or Accidental
Damage (ED/AD) across (functional) redundant channels could impact aircraft airworthiness
-
8/13/2019 E Zonal&L HIRF Principles
8/66
5 - 8XM33 Training MARCH 07
Page 8AIRBU
SDEUTSCHLANDG
M
BH.
Allrigh
tsreserved.
Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal & L/HIRF logic - Principles
1. Introduction 4
2. Zonal & L/HIRF Analysis 9
2.1 Generic Process
2.2 Standard zonal Analysis
2.3 Enhanced zonal analysis
2.4 L/HIRF zonal analysis
2.5 Consolidation/transfer/interface
1. MWG Review Process 61
2. Summary 64
Table of Contents
-
8/13/2019 E Zonal&L HIRF Principles
9/66
5 - 9XM33 Training MARCH 07
Page 9AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
Zonal & L/HIRF general principles
MSG-3 document treats Zonal & L/HIRF in two independent sections
Zonal and L/HIRF analyses are performed as one unique proceduretaking advantage of the similarity between both processes
Zones are sensitive or not sensitive to L/HIRF threats. As per MSG-3,most of the L/HIRF protection and in particular the aircraft structurecontinuity are covered by the Standard Zonal Analysis
The Zonal L/HIRF analysis consists of the following sub-processes: Zone description
Zonal Analysis:
- Standard Zonal Analysis part (applies to all zones)
- Enhanced Zonal Analysis part (applies to zones with wiring)
Lightning/High Intensity Radiated Field (L/HIRF) Zonal Analysis(applies to L/HIRF protection elements)
Consolidation
-
8/13/2019 E Zonal&L HIRF Principles
10/66
5 - 10XM33 Training MARCH 07
Page 10AIRBUSD
EUTSCHL
ANDG
MBH.
Allrightsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
Any Airbus aircraft is divided into 9 major zones as follows:
Major Zones (External)
100 Lower half of fuselage (below cabin floor), including radome to ramp
Major Sub-Zones (Internal)
Sub-divisions of major zones, e.g. 100 is divided into 110, 120, 130
Zones (Internal)
Sub-divisions of major sub-zones, e.g.120 is divided into121,122,123...
200 Upper half of fuselage (above cabin floor) to end of main deck cargo
compartment300 Stabilizers and fuselage rear section400 Power plant (including propeller)
500 LH wing
600 RH wing
700 Landing gear & landing gear doors800 Doors
900 Special use (e.g. external fuel pods)
-
8/13/2019 E Zonal&L HIRF Principles
11/66
5 - 11XM33 Training MARCH 07
Page 11AIRBUSD
EUTSCHL
ANDG
MBH.
Allrightsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
Aircraft zoning principles (A340 example)
-
8/13/2019 E Zonal&L HIRF Principles
12/66
5 - 12XM33 Training MARCH 07
Page 12AIRBUSD
EUTSCHL
ANDG
MBH.
Allrightsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
Aircraft zoning principles (A340 example)
-
8/13/2019 E Zonal&L HIRF Principles
13/66
5 - 13XM33 Training MARCH 07
Page 13AIRBUSD
EUTSCHL
ANDG
MBH.
Allrightsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
Aircraft zoning principles (A340 example)
-
8/13/2019 E Zonal&L HIRF Principles
14/66
5 - 14XM33 Training MARCH 07
Page 14AIRBUSD
EUTSCHL
ANDG
MBH.
Allrightsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
Aircraft zoning principles (A340 example)
-
8/13/2019 E Zonal&L HIRF Principles
15/66
5 - 15XM33 Training MARCH 07
Page 15AIRBUSD
EUTSCHL
ANDG
MBH.
Allrightsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
Aircraft access panel numbering principles (A340 example)
-
8/13/2019 E Zonal&L HIRF Principles
16/66
5 - 16XM33 Training MARCH 07
Page 16AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
Inspection to be carried out from within touching
distance, unless otherwise stated
General Visual Inspection
(GVI)
The Zonal Inspection Program has one
single level of inspection!
Zonal Inspection Program (ZIP) principles
A mirror may be necessaryto ensure visual accessto all exposed surfaces in the inspection area
-
8/13/2019 E Zonal&L HIRF Principles
17/66
5 - 17XM33 Training MARCH 07
Page 17AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
The Zonal Inspection Program provides the General Visual Inspection
(GVI) requirements for each aircraft zone to inspect system and
powerplant installations for security and general condition and structure
for general condition
The Zonal Inspection Program is based on dividing the aircraft into
zones. Each zone is usually defined by a clearly defined physical
boundary, e.g. rib, bulkhead, frames, etc
Each zone is to be inspected as far as visible with the relevant access
open/removed
The extent of the inspection is defined by the access e.g. identification of
access doors, positioning of flight control surfaces, removal of lining and
insulation, etc
Inspections are recommended to be accomplished at or before stated
intervals
Zonal Inspection Program (ZIP) principles
-
8/13/2019 E Zonal&L HIRF Principles
18/66
5 - 18XM33 Training MARCH 07
Page 18AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.1 Zonal & L/HIRF Analysis - Generic Process
Each zone is analysed for type of damage/deterioration to
structure/systems located in the zone which may occur in-service
Zonal inspection tasks do notprovide a summary of all the individual
systems and structural items to be inspected in the affected zone
Therefore it is considered that a person performing inspections has an
adequate knowledge of overall aircraft construction and systems
Zones may need more than one inspection at different intervals due to
the depth at which the zone is to be examined requiring different levels
of accessibility
- e.g. The cargo compartment requires 3 ZIP inspections each
requiring a different level of access (1.5 MO - door, 5 YE specific
panels and 10YE all access open)
Zonal Inspection Program (ZIP) principles
-
8/13/2019 E Zonal&L HIRF Principles
19/66
5 - 19XM33 Training MARCH 07
Page 19AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
L/HIRF
2.1 Zonal & L/HIRF Analysis - Generic Process
Common Analysis Process
L/HIRF and Zonal analysis (Standard, Enhanced) procedures have beencombined to make maximum use of similar procedural steps & synergies
between the three zonal analysis parts
StandardZonal
Enhanced Zonal
-
8/13/2019 E Zonal&L HIRF Principles
20/66
5 - 20XM33 Training MARCH 07
Page 20AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
These visual
inspection
requirements
are covered
under the
Zonal
Inspection
Program
(ZIP)
Standard Zonal analysis:
- GVI (General Visual Inspection) Enhanced Zonal analysis:
- Stand-alone GVI, a GVI which is not performed as partof a zonal inspection
- RST (Restoration), cleaning being the most probable
- DET (Detailed Inspection)
L/HIRF protection analysis:
- Stand-alone GVI, a GVI which is not performed as partof a zonal inspection
- DET (Detailed Inspection)
- FNC (Functional Check), resistance measurement
Structure & System/Powerplant maintenancerequirements transferred for consolidation include:
- GVI (General Visual Inspection)
- VCK (Visual Checks), system/powerplant analysis only
2.1 Zonal & L/HIRF Analysis - Generic Process
Zonal Inspection Program task levels (ZIP)
-
8/13/2019 E Zonal&L HIRF Principles
21/66
5 - 21XM33 Training MARCH 07
Page 21AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
These non
ZIP tasks
will be listed
in the
systems &
powerplant
section(ATA
chapter 20)
2.1 Zonal & L/HIRF Analysis - Generic Process
Standard Zonal analysis:
- GVI (General Visual Inspection) Enhanced Zonal analysis:
- Stand-alone GVI, a GVI which is not performed as partof a zonal inspection
- RST (Restoration), cleaning being the most probable
- DET (Detailed Inspection)
L/HIRF protection analysis:
- Stand-alone GVI, a GVI which is not performed as partof a zonal inspection
- DET (Detailed Inspection)
- FNC (Functional Check), resistance measurement
Structure & System/Powerplant maintenancerequirements transferred for consolidation include:
- GVI (General Visual Inspection)
- VCK (Visual Checks), system/powerplant analysis only
Enhanced zonal & L/HIRF task levels (ATA20)
-
8/13/2019 E Zonal&L HIRF Principles
22/66
5 - 22XM33 Training MARCH 07
Page 22AIRBU
SDEUTSCHLANDG
M
BH.
Allrigh
tsreserved.
Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal & L/HIRF logic - Principles
1. Introduction 3
2. Zonal & L/HIRF Analysis 8
2.1 Generic Process
2.2 Standard zonal Analysis2.2 Standard zonal Analysis
2.3 Enhanced zonal analysis
2.4 L/HIRF zonal analysis
2.5 Consolidation/transfer/interface
1. MWG Review Process 60
2. Summary 63
Table of Contents
-
8/13/2019 E Zonal&L HIRF Principles
23/66
5 - 23XM33 Training MARCH 07
Page 23AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Standard Zonal
Zonal Inspection Program (ZIP) General Visual
Inspections (GVI) to detect visual degradation of thewhole zone content (structure, equipment, wiring,
L/HIRF protection, bonding leads, grounding points...)
2.1 Zonal & L/HIRF Analysis - Generic Process
-
8/13/2019 E Zonal&L HIRF Principles
24/66
5 - 24XM33 Training MARCH 07
Page 24AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.3 Zonal & L/HIRF Analysis - Standard Part
The standard zonal analysis process is based on four parameters:
- Accidental damage- Environmental damage
- Density
- Importance
The final rating in the matrix box provides guidance for the inspection
intervals (zonal guidance interval)
Intervals are defined according to applicable in-service experience
Standard zonal analysis principals
It is expected that the area to be inspected is clean enough to minimise
the possibility that accumulated dirt or grease might hide unsatisfactory
conditions Any cleaning that is considered necessary should be performed before
the zonal inspection task
Access is defined according to zone layout/installation
-
8/13/2019 E Zonal&L HIRF Principles
25/66
5 - 25XM33 Training MARCH 07
Page 25AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.3 Zonal & L/HIRF Analysis - Standard Part
321Low
443High
IMPORTANCE
HighModerateLow
432Moderate
DENSITY
ED FACTOR
4
4
33
211
433
ADFACTOR
21
322
24-48MO48-72MO72-96MO96-144MO2
48-72MO72-96MO96-144MO>144MO1
-
8/13/2019 E Zonal&L HIRF Principles
26/66
5 - 26XM33 Training MARCH 07
Page 26AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.3 Zonal & L/HIRF Analysis - Standard Part
Others
Others
Chemical (toilet fluids,..)
Contamination
Humidity
Vibration
Temperature
ENVIRONMENTAL
DAMAGE
N/A=0, Low=1, Moderate=2, High=3
Passenger traffic
Maintenance
Weather effects
Foreign objects
Fluid spillage
Ground Handling
ACCIDENTAL
DAMAGE
Cargo Handling
Although rarely used, the working group is notlimited to the given entries and may decide to
add further items to the given list entries
The highest rating will be taken into
consideration for the overall AD/ED rating
Zone accidental & environmental rating
Environmental Damage (ED):
This rating is a measure of howmuch the zone is subject to
temperature, vibration,
atmospheric exposure, moisture,
contamination
Accidental Damage (AD):
Each given and additionally
identified potential accidentaldamage cause will be rated in
respect of the possibility of
accidental damage to systemsand structure in the zone
-
8/13/2019 E Zonal&L HIRF Principles
27/66
5 - 27XM33 Training MARCH 07
Page 27AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
321Low
443High
IMPORTANCE
HighModerateLow
432Moderate
DENSITY
2.3 Zonal & L/HIRF Analysis - Standard Part
Density of equipment
Zone density and importance rating
This rating is a measure of how closethe various systems components(including wiring) are packed in a zone
The density is assessed relative to thesize of the zone
It provides indications about:
- The inspectability of the systeminstallation and structure
- The risk of common cause hazard
resulting in deterioration of multipleadjacent items (fire, burst, moisture,
fluid spillage)
The density refers to the number of
components and complexity
-
8/13/2019 E Zonal&L HIRF Principles
28/66
5 - 28XM33 Training MARCH 07
Page 28AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
321Low
443High
IMPORTANCE
HighModerateLow
432Moderate
DENSITY
2.3 Zonal & L/HIRF Analysis - Standard Part
Low:
System items whose anomalous behaviour may cause or contribute to failure
of system function with no effect on aircraft operational capability & pilotworkload but maybe undesirable economic impact and/or comfort reduction
Structure whose failure or detachment will not compromise continued safeflight or landing but where the potentially large size of released elements
needs to be considered
High:
PPH: Safety is considered asadversely affected if the
failure consequences wouldprevent the aircraft continued
safe flight and landing and/ormight cause serious or fatal
injury to human occupants
Moderate: Anomalous system behaviour may cause/contribute to fai lureresulting in adverse effect on aircraft operating capability
(delays, cancellations, ground/flight interruptions)
Structure whose failure or detachment could compromisecontinued safe flight or landing
Fuel tanks by default to limit frequent access and sub-sequent system disturbance/FOD
Anomalous system behaviour may cause or contribute to failure resulting in adverse effect on safety
Structure element whose integrity is essential
Zones where particular risks could affect several system items (hydraulic accumulator burst, wheel/tyrefailure, engine rotor failure, human error)
Fuel tank adjacent zones where failure of components (pneumatic system and/or ducting) could cause
localised heating of tank surfaces & consequently increase potential for auto-ignition of fuel Fuel leakage zones where temperature as result of failure (e.g. e lectric motors/transformers overload) could
increase and with potential ignition sources (electrical arcs , friction sparks) present
-
8/13/2019 E Zonal&L HIRF Principles
29/66
5 - 29XM33 Training MARCH 07
Page 29AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.3 Zonal & L/HIRF Analysis - Standard Part
INTERVAL EVALUATION
Access:Description/Boundaries:
GVI
Level ApplicabilityIntervalDescriptionAccessTask No.
321Low
443High
IMPORTANCE
HighModerateLow
432Moderate
DENSITY
ED F ACTOR
4
4
3
3
211
433
AD
FACTOR
21
322
24-48MO48-72MO72-96MO96-144MO2
48-72MO72-96MO96-144MO>144MO1
-
8/13/2019 E Zonal&L HIRF Principles
30/66
5 - 30XM33 Training MARCH 07
Page 30AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
The Zonal Inspection Program has inspection parameters in terms of
letter check and calendar time, as follows:
A - Check and multiples up to 4A
C - Check and multiples up to 4C
6Y/5Y and 10Y/12Y
The lower thresholds/intervals are mainly driven by the likelihood of
accidental damage and systems reliability aspects. The access is usually
limited to specific areas.
The higher intervals usually have a more significant access
requirement and are mainly concerned with the type of damage which
has propagated over time or cycles to the point where it is large enoughto be detected by a GVI.
7 Zonal Inspection Program2.3 Zonal & L/HIRF Analysis - Standard Part
-
8/13/2019 E Zonal&L HIRF Principles
31/66
5 - 31XM33 Training MARCH 07
Page 31AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.3 Zonal & L/HIRF Analysis - Standard Part
Standard zonal analysis summary
The Standard Zonal Analysis Part considers:
Overall rating results ina task interval guidance
Deterioration (e.g. corrosion, accidental damage, wear, ageing,fatigue) on systems components & airframe structures
Any deterioration of bonding & shielding of structure & equipment
(including wiring & L/HIRF protection) detectable by GVI
Evaluation is performed for
entire zone
any additionally dedicated access/area(s) of the zone can be
identified where appropriate
Using rating tables for:
Density
Importance Accidental Damage
Environmental Damage
-
8/13/2019 E Zonal&L HIRF Principles
32/66
5 - 32XM33 Training MARCH 07
Page 32AIRBU
SDEUTSCHLANDG
M
BH.
Allrigh
tsreserved.
Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal & L/HIRF logic - Principles
1. Introduction 3
2. Zonal & L/HIRF Analysis 8
2.1 Generic Process
2.2 Standard zonal Analysis
2.3 Enhanced zonal analysis2.3 Enhanced zonal analysis
2.4 L/HIRF zonal analysis
2.5 Consolidation/transfer/interface
1. MWG Review Process 60
2. Summary 63
Table of Contents
-
8/13/2019 E Zonal&L HIRF Principles
33/66
-
8/13/2019 E Zonal&L HIRF Principles
34/66
5 - 34XM33 Training MARCH 07
Page 34AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.4 Zonal & L/HIRF Analysis - Enhanced Part
The Enhanced Zonal Analysis Procedure (EZAP) permits appropriate
attention to be given to electrical wiring installation within a zone(particularly in zones having the potential for combustible material
being present)
The logic provides a means to identify applicable and effective tasks tominimise combustible material accumulation and to address significant
wiring discrepancies that may not be reliably detected through Zonal
Inspection Program (ZIP) tasks
The enhanced zonal analysis must be performed for all zones thatcontain wiring
Enhanced zonal analysis principals
-
8/13/2019 E Zonal&L HIRF Principles
35/66
5 - 35XM33 Training MARCH 07
Page 35AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Answers and explanations toquestions:
Justification for Interval:
Fuel leakage
Fuel vapour
Lint
Dust
CommentsY/NMaterial
Hydraulic mist
Oil mist
Level ApplicabilityIntervalDescriptionAccessTask No.
List if others..
Combustible material table
Description/Illustration:
2.4 Zonal & L/HIRF Analysis - Enhanced Part
Continue with EnhancedZonal Analysis Evaluation
Sheet 2
Standard Zonal Analysis isadequate. Continue with Task
Summary & Consolidation Sheet
Continue with L/HIRFZonal Analysis
Evaluation Sheet
NO
YES
Define task & interval
Is wiringclose to both
primary & back-uphydraulic, mechanical,
or electricalflight
controls?
combustible
material in thezone ?
Describe combustible material in table
Zone
contains wiring
?
Is therean effective task
to significantly reduce thelikelihood of accumulation of
combustiblematerials
?
NO
NO
YES
YES
YES
NO
NO
YES
Describe combustible material in table
L/HIRFprotection elements
installed in thezone?
-
8/13/2019 E Zonal&L HIRF Principles
36/66
5 - 36XM33 Training MARCH 07
Page 36AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Tasks that avoidaccumulation of
combustibles(mostly cleaning)
Wiring inspectability
EE Bay?
Feeder (Route G)?
Flight compartment?
Wiring close to bothprimary and back-up
hydraulic, or electrical
flight controls?
Wiring
Combustible material
dust, lint, fuel vapours, fuel leakage, insulation
blanket (contaminated), oil mist, hydraulic mist
2.4 Zonal & L/HIRF Analysis - Enhanced Part
Dedicated WiringInspection
Enhanced zonal analysis principals
-
8/13/2019 E Zonal&L HIRF Principles
37/66
5 - 37XM33 Training MARCH 07
Page 37AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Contamination with combustible material
Equipment and wiring are subject to dust and lint accumulation due to:
Air movement (natural, forced; typical areas are recirculation, galley & toilet etc.) Attraction by magnetic fields from electric current surrounding wiring and equipment
Combustible material impact:
2.4 Zonal & L/HIRF Analysis - Enhanced Part
Moisture trapping and subsequent corrosion
Changes in electrical characteristics (dust &
lint can act as conductor, e.g. with presence of
moisture, they can provide a path for a short
circuit)
Heat insulation which can cause overheat andpremature failure or contribute to fire ignition
Fire propagation in case of severe dust andlint accumulation
Wiring cleaning task are selected based on manufacturer/operators experience
Airbus has service condition experience from enhanced zonal exercises for legacy (Wide Body, Single Aisle,Long Range)
-
8/13/2019 E Zonal&L HIRF Principles
38/66
5 - 38XM33 Training MARCH 07
Page 38AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.4 Zonal & L/HIRF Analysis - Enhanced Part
It is considered useful to know the standard zonal GVI interval in order
to harmonise the overall access requirements
The assessment of DENSITY, SIZEand POTENTIAL EFFECT OF FIRE
IN ZONEprovides guidance on whether the zonal inspection program
GVI is adequate for all wiring in the zone, or if these GVI task(s) must be
augmented with stand-alone GVI(s) or DET inspection(s)
Most of the wiring is considered adequately addressed with the Zonal
Inspection Program (ZIP) GVI tasks
Some portion of wiring in the zone/area may require a dedicated
maintenance task (e.g. stand-alone GVI or DET) in respect to potential
fire ignition and/or potential for loss of multiple functions to the extend
that continued safe operation may not be possible
Dedicated wiring inspection task principles
-
8/13/2019 E Zonal&L HIRF Principles
39/66
5 - 39XM33 Training MARCH 07
Page 39AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Size Comments:
Density Comments:
Potential Effect C omments:
INSPECTION LEVEL DEFINITIONZone Title:
Zone(s):
XXX/YYY/ZZZEnhanced Zonal Analysis Evaluation Sheet 2
Wiring inspection task level definition
2.4 Zonal & L/HIRF Analysis - Enhanced Part
3
3
2
High
11Small
33Large
SIZE
ModerateLow
21Medium
DENSITYENTIRE ZONE
EZAEZAEZAHigh
EZAEZAZIPModerate
ZIPZIPZIPLowPOTENTIALEFFECT OF FIREON ADJACENTWIRING AND
SYSTEMS IN THEZONE
SIZE / DENSITYFACTOR
321
Continue with Enhanced Zonal
Anal ysis Evalua tion Sheet 3
Continue with L/HIRF Zonal Anal ysis
Evaluation Sheet 1, i f protection installed
YESNO ZIP
adequate?
GVI
Dedicated
access
ZIP GVI for
the wholezone
Enhanced Zonal Analysis Evaluation Sheet 3(Stand-alone GVI or DET) for dedicated area
The need for a specific inspectiontask (Stand-alone GVI or DET) is
influenced by:
Size of the zone/area
Density of wiring/equipment
Potential effect of fire in the zone
Specific wiring installationwithin the zone
GVI or
DET
GVI or
DET
-
8/13/2019 E Zonal&L HIRF Principles
40/66
5 - 40XM33 Training MARCH 07
Page 40AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Justification for Interval outside the guidance:
AreaComm ents/Illustration:
Potential Effect Comments:
Density Comments:
Size Comments:
LevelDescription ApplicabilityIntervalAccessTask No.
Zone Title:
Zone(s):
XXX/YYY/ZZZEnhanced Zonal Analysis Evaluation Sheet 3
Dedicated wir ing inspection taskExample
2.4 Zonal & L/HIRF Analysis - Enhanced Part
ENVIROMENTAL FACTOR
72MO1
24-12MO48-24MO3
ACCIDENTAL
FACTOR
21
48-24MO72-48MO2
SIZE / DENSITY FACTOR
POTENTIA L
EFFECT OF
FIRE ON
ADJACENT
WIRING AND
SYSTEMS IN
THE AREA DETDET
Stand
alone GVI
Stand
alone GVI
3
Stand
alone GVI
Stand
alone GVIStand
alone
GVI
High
21
Stand
alone
GVI
Moderate
Select the highest rating !
Others
Others
Chemical (toilet f luids,..)
Contamination
Humidity
Vibration
Temperature
ENVIRONMENTAL
DAMAGE
N/A=0, Low=1, Moderate=2, High=3
Passenger t raffic
Maintenance
Weather effects
Foreign objects
Fluid spillage
Ground Handling
ACCIDENTAL
DAMAGE
Cargo Handling
3
3
2
High
11Small
33Large
SIZE
ModerateLow
21Medium
DENSITYDEDICATED AREA
Continue with an additional Enhanced
Zonal Analysis Evaluation Sheet 3
Continue with L/HIRF Zonal Anal ysis
Evaluation Sheet 1, i f protection installedIs there an additional specific
access/area to be analysed?
NOYES
of boundaries and content of
dedicated area
-
8/13/2019 E Zonal&L HIRF Principles
41/66
5 - 41XM33 Training MARCH 07
Page 41AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.4 Zonal & L/HIRF Analysis - Enhanced Part
Comments on stand-alone GVIsZIP GVI Tasks:Zonal Inspection Programme GVI does not focus on particular
item or feature (the GVI task defined by the zone reference,access requirements and interval)
ATA20 GVI Tasks:
The term stand-alone GVI is used to identify GVI tasks
covering items or features that require particular attention in the
frame of the EZAP and/or L/HIRF analysis
All system (including wiring) and structure features evident with
the quoted access are subject to the inspection
Consequently stand-alone GVI are the same inspection level as any other ZIP,SSI or MSI GVI task
The difference to ZIP GVI tasks is that stand-alone GVIs focus on dedicated
items/issues whereas ZIP GVIs cover all items visible with the given access
Stand alone GVI tasks are listed in ATA chapter 20 (System &
Powerplant Section of Maintenance Program)
Stand alone GVI tasks focus on items clearly defined by the
task description (e.g. General Visual Inspection of P WiringRoute installed in the Main Deck Forward Cabin Overhead Area,
LH/RH)
-
8/13/2019 E Zonal&L HIRF Principles
42/66
5 - 42XM33 Training MARCH 07
Page 42AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.4 Zonal & L/HIRF Analysis - Enhanced Part
Enhanced zonal analysis summary
The Enhanced Zonal Analysis consists of two main parts:
Together from the assessment for the inspectabilitycriteria of a zone /dedicated area
1. Evaluation of combustible materialand possible reduction of arcingrelated risk All combustible material in the zone is listed
The related Description, Answers, Remarks, Comments and Justification
sections provide clear detail on the assessment
2. The wiringinspection level is evaluated using rating tables for:
Density
Size
Potential effect of fire on adjacent wiring and systems in the zone
As result, the analysis identifies if the ZIP GVI is sufficient for the whole
zone plus additional dedicated tasks (GVI-stand alone and/or DET) where
applicable
Note: The actual task interval is based on environment & accidental
damage assessment (as for the ZIP GVIs)
-
8/13/2019 E Zonal&L HIRF Principles
43/66
5 - 43XM33 Training MARCH 07
Page 43AIRBU
SDEUTSCHLANDG
M
BH.
Allrigh
tsreserved.
Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal & L/HIRF logic - Principles
1. Introduction 3
2. Zonal & L/HIRF Analysis 8
2.1 Generic Process
2.2 Standard zonal Analysis
2.3 Enhanced zonal analysis
2.4 L/HIRF zonal analysis2.4 L/HIRF zonal analysis
2.5 Consolidation/transfer/interface
1. MWG Review Process 60
2. Summary 63
Table of Contents
-
8/13/2019 E Zonal&L HIRF Principles
44/66
5 - 44XM33 Training MARCH 07
Page 44AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
G Route
(feeders)
P Route
Crossover
M & SRoutes to
Engine
L/HIRF
To detect L/HIRF protection degradation
2.1 Zonal & L/HIRF Analysis - Generic Process
-
8/13/2019 E Zonal&L HIRF Principles
45/66
5 - 45XM33 Training MARCH 07
Page 45AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Lightning (L)
High Intensity Radiated Fields
(HIRF)
Radars
(ground &
airborne)
Radio
transmitters
2.5 Zonal & L/HIRF Analysis - L/HIRF Part
L/HIRF zonal analysis principals
The intend of the L/HIRFprotection tasks is to reduce the
possibility that a single failurecause (e.g. lightning strike) andthe occurrence of a common
failure cause such asEnvironmental or AccidentalDamage (ED/AD) across(functional) redundant channelscould impact aircraftairworthiness
-
8/13/2019 E Zonal&L HIRF Principles
46/66
5 - 46XM33 Training MARCH 07
Page 46AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.5 Zonal & L/HIRF Analysis - L/HIRF Part
L/HIRF protection principalsEquipment protection
In addition to the equipment inherent protection (circuit layout and box design),clamping, filtering and transient protection devices (tranzorbs) prevent damagefrom induced voltage/current resulting from L/HIRF encounter
Hidden failure of these features is unlikely due to:
- High reliability figures of the transient suppressor
- Methodical shop testing after each unscheduled removal
- Build In Test Equipment (BITE)
System architecture
Is designed to achieve systems safety and availability objectives and contributesto increase the non-susceptibility of systems to L/HIRF effects
Main features are:
- Segregation of electrical wiring routes and equipment installation
- Redundancy and dissimilarity.
- Systems and functions monitoring (comparison, data coherence)
-
8/13/2019 E Zonal&L HIRF Principles
47/66
5 - 47XM33 Training MARCH 07
Page 47AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.5 Zonal & L/HIRF Analysis - L/HIRF Part
L/HIRF protection principals
Aircraft structure continuity
Is ensured by metal to metal contact, bonding leads and meshes for compositestructure
Degradation (corrosion, broken strands) is covered by the standard zonal
analysis
Braided conduits and race ways (wings)
Provide wiring protection in exposed areas
Degradation is partially addressed with the standard zonal analysis and with
dedicated GVI and DET wiring inspection tasks defined through the enhancedzonal
The zonal L/HIRF protection analysis procedure will allow identification ofinspection tasks to augment these inspections
-
8/13/2019 E Zonal&L HIRF Principles
48/66
5 - 48XM33 Training MARCH 07
Page 48AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Equipment protection:
Boxes designed with good EM
attenuation
Inputs and outputs fitted with
filters and transient
suppression devices
Electrical wiring protection:
Overbraiding/raceways in exposed
areas (wings, engines, landing
gear, belly fairing, )
Aircraft structure continuity:
Metal to metal contact
Metallic grid screen (mesh,
strip) on composite
Bonding leads
Systems architecture:
Segregation and routing of
electrical wiring routes
Different location of equipments
Redundancy and dissimilarity
System &powerplant analysis
Standard zonal,enhanced zonal &
L/HIRF analysis
Standard zonal &L/HIRF analysis Standard zonal analysis
2.5 Zonal & L/HIRF Analysis - L/HIRF Part
Structure &standard zonal
analysis
L/HIRF protection principals
-
8/13/2019 E Zonal&L HIRF Principles
49/66
5 - 49XM33 Training MARCH 07
Page 49AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
MSG-3 zonal L/HIRF protection analysis scope
2.5 Zonal & L/HIRF Analysis - L/HIRF Part
Electrical wiring protection:
Overbraiding/raceways in exposed
areas (wings, engines, landing
gear, belly fairing)
Exposed areas:
Open areas (landing gear, wing trailing
edge, )
Under low conductive material (titanium,
stainless steel, composite)
Wiring installed in the following areas are
protected:
Wings
Engine
Horizontal/vertical tail plane
Nose and main landing gear legs and gearcompartment
Radome
Sponson
Fairings
Tail area
-
8/13/2019 E Zonal&L HIRF Principles
50/66
5 - 50XM33 Training MARCH 07
Page 50AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
INSPECTION LEVEL
Description/Illustration:
INSPECTION INTERV ALL/HIRF key c haracteristics:
Justification for Interv al:
LevelDescription ApplicabilityIntervalAccessTask No.
Zone Title:
Zone(s):
XXX/YYY/ZZZL/HIRF Zonal Analysis Evaluation Sheet
DET
FNC
DET
FNC
DET
FNC
High
DENSITY
Standalone GVI
Standalone GVI
High
ZIPZIPLow
L/HIRFPROTECTION
DETERIORATIONCRITERIA
ModerateLow
Standalone GVI
ZIP orStand
alone GVI
2.5 Zonal & L/HIRF Analysis - L/HIRF Part
End of Zonal Analysis.
Continue with Task Summary
& Consolidation Sheet
ENVIRONMENTAL FACTOR
72MO1
24-12MO48-24MO3
ACCIDENTAL
DAMAGE FACTOR
21
48-24MO72-48MO2
Select the highest rating !
Others
Others
Chemical (toilet fl uids...)
Contamination
Humidity
Vibration
Temperature
ENVIRONMENTAL DAMAGE
N/A=0, Low=1, Moderate=2, High=3
Passenger t raffic
Maintenance
Weather effects
Foreign objects
Fluid spillage
Ground Handling
ACCIDENTAL DAMAGE
Cargo Handling
YES
NO
ZIPapplicable
?
Determine Inspection
Requirements for ED/AD
Continue with an additional L/HI RF Zonal Analysis
Evaluation Sheet for additional specific protection itemsNOYES Are addi tional prot ection
items to be inspected?End of L/HIRF Zonal Analysis. Continue with
Task Summary & Consolidation Sheet
-
8/13/2019 E Zonal&L HIRF Principles
51/66
5 - 51XM33 Training MARCH 07
Page 51AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Type Certification
process
Requirements/
compliance
Assurance
plan(TBD)
L/HIRF Assurance Plan is usually
implemented under the responsibility of theCivil Type Certificate holder and serves twopurposes:
To confirm that the design of the L/HIRF
protection is adequate to maintain TypeCertification objectives throughout aircraft life,
and
To identify specific locations within theL/HIRF protection system where there may
be a need for scheduled maintenance in
order to address any systematic deterioration
that could eventually impact the Type
Certification protection level
2.5 Zonal & L/HIRF Analysis - L/HIRF Part
Type certificate relationship
Continued
Airworthiness
-
8/13/2019 E Zonal&L HIRF Principles
52/66
5 - 52XM33 Training MARCH 07
Page 52AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.5 Zonal & L/HIRF Analysis - L/HIRF Part
Zonal L/HIRF protection analysis summary
The L/HIRF zonal analysis consists of 2 main parts
1. Assessment of required inspection level:
Density and potential effect of L/HIRF protection deterioration define
required level (ZIP or dedicated ATA chapter 20 L/HIRF task)
2. Evaluation of specific L/HIRF protection element if required
The task interval is based on assessment of environment & accidentaldamage similar to the enhanced zonal analysis
Density and potential reduction of overall L/HIRF protection define
required level (GVI stand alone, DET or FNC for each additional specifictask)
-
8/13/2019 E Zonal&L HIRF Principles
53/66
5 - 53XM33 Training MARCH 07
Page 53AIRBU
SDEUTSCHLANDG
M
BH.
Allrigh
tsreserved.
Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal & L/HIRF logic - Principles
1. Introduction 3
2. Zonal & L/HIRF Analysis 8
2.1 Generic Process
2.2 Standard zonal Analysis
2.3 Enhanced zonal analysis
2.4 L/HIRF zonal analysis
2.5 Consolidation/transfer/interface2.5 Consolidation/transfer/interface
1. MWG Review Process 60
2. Summary 63
Table of Contents
-
8/13/2019 E Zonal&L HIRF Principles
54/66
5 - 54XM33 Training MARCH 07
Page 54AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Failure modes not identified
through the SSI/MSI
analysis but naturally
inspected by the zonal
2.6 Zonal & L/HIRF Analysis - Consolidation
Failure modes identified
through the SSI/MSI
analysis but naturally
inspected by the zonal(e.g. corrosion, obvious
deterioration)
MSI/SSI tasks transferred
into the zonal program
-
8/13/2019 E Zonal&L HIRF Principles
55/66
5 - 55XM33 Training MARCH 07
Page 55AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal Analysis
AIRCRAFT STRUCTURE
To be
consideredby Zonal WG
Significant?
OTHER
STRUCTURE
SIGNIFICANT STRUCTURE
Definition of
SAFE LIFE
LIMITS
FATIGUE
DAMAGE
ANALYSIS
ACCIDENTAL DAMAGE
ANALYSIS
ED/CPCP
ANALYSIS
ACCIDENT
AL
DAMAGE
ANALYSIS
ED
(Aging)
ANALYSI
S
Metallic or
Non Metal lic?
SAFE
LIFE
STRUCTU
RE
DAMAGE
TOLER ANT
STRUCTURE
METALLIC STRUCTURE
NONMETALLICSTRUCTUR
E
Safe Life or
Damage
Tolerant?
Y
2.6 Zonal & L/HIRF Analysis - Consolidation
N
The Zonal Analysis covers the entire aircraft regardless of the SSI selection
Thus the complete aircraft structure is considered by the zonal analysis!!!
TRANSFER
SSIsSSI analysis
-
8/13/2019 E Zonal&L HIRF Principles
56/66
5 - 56XM33 Training MARCH 07
Page 56AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
The zonal inspection will detect obvious unsatisfactory
conditions/discrepancies (accidental damage,
environmental deterioration, fatigue damage, ageing,general condition of fasteners, ) in all visible structure
(primary, secondary, fairing, panels, doors, )
2.6 Zonal & L/HIRF Analysis - Consolidation
-
8/13/2019 E Zonal&L HIRF Principles
57/66
5 - 57XM33 Training MARCH 07
Page 57AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Systems evaluations are based upon the functional failures and the failure causes
Function(Normal
characteristicactions of an item)
Functional Failure(How an item failed to
perform its function)
Causes(Why the functional
failure occurs)
Failure effects(What is the result of
the functional failure)
Pipework and wiring are part of system installation,
but the related failure causes are normally not
considered by system analysis
All tubing, wiring installed in a zone is subject to
the zonal analysis and the resulting ZIP GVI
together with all other system and structure
However, the systems working group may select
MSI tasks for specific wiring/tubing in particularcases
The cause show functionaldegradation characteristics:
Mechanical fault
Electrical fault
Failing in open or closed position
Open or short circuit
Jammed linkage
Contaminated orifice
Broken housing etc.
2.6 Zonal & L/HIRF Analysis - Consolidation
Basic systems & power plant principal
-
8/13/2019 E Zonal&L HIRF Principles
58/66
5 - 58XM33 Training MARCH 07
Page 58AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
The zonal inspection will detect obvious unsatisfactory
conditions/discrepancies (due to accidental damage,environmental deterioration, ageing, ...) for all visible
systemcomponents (wiring, tubing, actuators,
computers, sensors, )
2.6 Zonal & L/HIRF Analysis - Consolidation
-
8/13/2019 E Zonal&L HIRF Principles
59/66
5 - 59XM33 Training MARCH 07
Page 59AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
2.7 Zonal & L/HIRF Analysis - Transfer
Systems/powerplant and structure program GVI items may be
considered as being covered by the ZIP as long as the followingcriteria are met:
A list of all transferred MSI task(s) and SSI task(s) covered by the
Zonal Program is available for reference (e.g. MRBR appendix)
Therefore, a dedicated inspection is not required for these SSI task(s)
and MSI task(s) if the equivalent ZIP task is performed
The access requirements of the MSI/SSI are the same as or less
severe than the ZIP task in the same area
The ZIP task is performed as frequently or more frequently than
the thresholds/intervals of the relevant MSI / SSI
Transfer requirement acceptance criteria
-
8/13/2019 E Zonal&L HIRF Principles
60/66
5 - 60XM33 Training MARCH 07
Page 60AIRBU
SDEUTSCHLANDG
M
BH.
Allrigh
tsreserved.
Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal & L/HIRF logic - Principles
Table of Contents
1. Introduction 4
2. Zonal & L/HIRF Analysis 9
3.3. MWG Review ProcessMWG Review Process 6161
4. Summary 64
-
8/13/2019 E Zonal&L HIRF Principles
61/66
-
8/13/2019 E Zonal&L HIRF Principles
62/66
5 - 62XM33 Training MARCH 07
Page 62AIRBUSD
EUTSCHL
ANDG
MBH.
Allrightsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
5.2 Composition of the Maintenance Working Group
Chair Person
Is appointed by Airbus Is accepted bythe ISC
ISC Advisor
Represents the ISC in
the group
Is nominated to adviseon policy issues.
Customer
Representatives
Operators
Manufacturer
Representatives
Airframe manufacturer
Engine manufacturer Major suppliers
MWG members and advisorsshould possess an adequate
level of knowledge andexperience.
Airworthiness Authorities(MRB)
Represents the
authorities in the group Participates in an
advisorycapacity
ADVISORS MEMBERS
-
8/13/2019 E Zonal&L HIRF Principles
63/66
5 - 63XM33 Training MARCH 07
Page 63AIRBU
SDEUTSCHLANDG
M
BH.
Allrigh
tsreserved.
Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
Zonal & L/HIRF logic - Principles
Table of Contents
1. Introduction 4
2. Zonal & L/HIRF Analysis 9
3. MWG Review Process 61
4.4. SummarySummary 6464
-
8/13/2019 E Zonal&L HIRF Principles
64/66
5 - 64XM33 Training MARCH 07
Page 64AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
4. Summary
The Zonal Analysis is a integrated approach with:
Combined description section
Zonal analysis with standard and enhanced issues clearly identified in dedicatedsections (the standard section covering certain L/HIRF issues)
Integrated zonal L/HIRF analysis part
Final consolidation
The actual zonal analysis consists of 3 main parts:
1.Standard zonal analysis to develop the ZIP general visual inspections
2.Enhanced zonal analysis addressing potential fire risk of wiring and relatedaccumulation of combustible material concern for in service aircraft
3.Zonal L/HIRF analysis to develop related tasks in terms of susceptibility to
degradation (acc idental damage / environmental deterioration)
The consolidation will derive
Harmonised zonal analysis results for both, the ZIP and ATA-20 tasks
The Zonal Inspection Programme (ZIP) including the transfers from systems &
structure
-
8/13/2019 E Zonal&L HIRF Principles
65/66
5 - 65XM33 Training MARCH 07
Page 65AIRBUSD
EUTSCHL
ANDG
MBH.
Allrightsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
AIRBUS S.A.S. All rights reserved. Confidential and
proprietary document.
This document and all information contained herein is the sole
property of AIR BUS S.A.S.. No intellectual property rights are
granted by the delivery of this document or the disclosure of
its content. This document shall not be reproduced or
disclosed to a third party without the express written consentof AIRBUS S.A.S. This document and its content shall not be
used for any purpose other t han that for which it is supplied.
The statements made herein do not constitut e an off er. They
are based on the mentioned assumptions and are expressed
in good faith. Where the supporting grounds f or these
statements are not shown, AIRBUS S.A.S. will be pleased to
explain the basis thereof.
AIRBUS, its logo, A300, A310, A318, A319, A320, A321,
A330, A340, A350, A400M are regist ered t rademarks.
-
8/13/2019 E Zonal&L HIRF Principles
66/66
Page 66AIR
BUSD
EUTSCHLANDG
MBH.
Allrig
htsr
eserved.Confidentialandproprietarydocument.
XM33 Training - Zonal & L/HIRF Logic - Principles MARCH 07
THIS PAGE INTENTIONALLY LEFT BLANK