earned schedule application to project management schedule application to project...project...

28
Earned Schedule …application to Project Management Walt Lipke PMI - Oklahoma City +1 405 364 1594 [email protected] www.earnedschedule.com $$ 5 Pl anned Val ue E arned Value 7 1 2 3 4 6 8 9 10 Earned Schedule Time Periods PV cum EV cum = Actual Time The ES idea is to determine the time at which the EV accrued should have occurred.

Upload: voquynh

Post on 22-Mar-2018

231 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

Earned Schedule…application toProject Management

Walt LipkePMI - Oklahoma City

+1 405 364 1594

[email protected]

www.earnedschedule.com

$$

5

Planned Value

Earned Value

71 2 3 4 6 8 9 10

EarnedSchedule

Time Periods

PVcum

EVcum=

ActualTime

The ES idea is to determinethe time at which the EVaccrued should have occurred.

Page 2: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 20112

Abstract

A review of Earned Schedule, focusing onproject management control areas forwhich the methodology provides anadvance in practice.

Page 3: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 20113

Overview

Background

Review of ES Metric

Indicators & Terminology

Forecasting & Prediction

Project Control

Schedule Adherence

Rework

Application Aids

Supplemental Remarks

Summary

Page 4: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 20114

Background

“We need to maintain our attention on scheduledelivery. Data tells us that since July 2003, realcost increase in projects accounted for lessthan 3 percent of the total cost growth.

…Therefore, our problem is not cost, it isSCHEDULE.”

- Dr. Steve Gumley, CEO

Defence Materiel Organization (Australia)

Quote taken from DMO Bulletin, July 2006, Issue 61, page

Page 5: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 20115

Background

Page 6: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 20116

ES Metric

$$

5

Planned Value

Earned Value

71 2 3 4 6 8 9 10

EarnedSchedule

Time Periods

PVcum

EVcum=

ActualTime

The ES idea is to determinethe time at which the EVaccrued should have occurred.

Page 7: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 20117

ES Metric

ES measure requires the PMB and EV accrued

Determined from formula, ES = C + I

where C is number of periodic time units of thePMB for which EV PVC

and I = [(EV – PVC) / (PVC+1 – PVC)] 1 period

At completion, just as EV = BAC, ES = PD

where PD = Planned Duration

Page 8: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 20118

ES Indicators

The ES measure leads to reliable indicators forthe entire duration of the project

SV(t) = ES – AT

SPI(t) = ES / AT

SV(t)n = (ESn – ESn-1) – 1

SPI(t)n = (ESn – ESn-1) / 1

where AT is the number of status periods

cumulative

periodic

Page 9: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 20119

ES Terminology

Page 10: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201110

Forecasting

EVM forecast of final cost: IEAC = BAC / CPI

ES forecast of project duration:

IEAC(t) = PD / SPI(t)

Goodness of forecast has been verified by Application

Statistical testing

Simulation

Useful to compare forecast from Critical PathEV data to project forecast

Page 11: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201111

Forecasting

Range of possible outcomes – confidence limits

Project #1 - Schedule

0

10

20

30

40

20 30 40 50 60 70 80 90 100

Percent Complete

Mo

nth

s

IEAC(t)H

IEAC(t)L

IEAC(t)

Final Duration

Page 12: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201112

Prediction

Calculation of TSPI provides informationconcerning whether to attempt corrective actionor negotiate a change with the customer

Page 13: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201113

Project Control

Using EVM & ES leads to general strategies

Page 14: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201114

Project Control

Improved project recovery tactics

Page 15: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201115

Project Control

Better project management decisions

Page 16: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201116

Schedule Adherence

ES facilitates measuring how well projectexecution follows the plan

Page 17: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201117

Schedule Adherence

Independent from schedule efficiency (SPI(t))

Measured as ratio of EV conforming to the PVwhich should have been earned (P-Factor)

Allows analysis which identifies tasks havingimpediments or constraints

Identifies tasks which are likely to have futurerework and enhances forecasting

Leads to Schedule Adherence Index andimproved control

Facilitates calculation of induced rework

Page 18: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201118

SA - Analysis Example

PV

BAC

1

3

2

4

5

6

7

8

ES AT

Task PV PV@ES EV@AT EV - PV I/C or R

1 10 10 10 0

2 12 9 5 -4 I/C

3 10 10 10 0

4 5 5 3 -2 I/C

5 5 2 5 +3 R

6 8 4 3 -1 I/C

7 7 0 1 +1 R

8 5 0 3 +3 R

Total 62 40 40 0

Page 19: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201119

SA - Enhanced Forecasting

Example Data

5

10

15

20

0 0.25 0.5 0.75 1

Fraction Complete

Pre

dic

ted

Du

rati

on

IEAC(te) PD IEAC(t)

Reverse Data

5

10

15

20

0 0.25 0.5 0.75 1

Fraction Complete

Pre

dic

ted

Du

rati

on

IEAC(te) PD IEAC(t)

Good Prediction Area Good Prediction Area

Page 20: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201120

Rework

Schedule Adherence Index

SAI = R / (BAC – EV)

where R = f(P, EV, BAC)

SAI is useful for detecting trends …thus amanagement tool for gauging actions taken SAI increasing with EV SA worsening

SAI decreasing with EV SA improving

Allows for calculation of out of sequence EV

Facilitates forecast of project rework cost

Page 21: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201121

Rework

Ability to determine amount of out of sequenceEV and forecast rework cost heightensmanagement attention to schedule execution

Increases ability of oversight functions toidentify EV “gaming”

Improved schedule adherence hypothesized toimprove both cost and schedule performanceefficiencies

Page 22: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201122

Rework - Real Example

BAC $2.5 million, P = 0.930 0.995

CPI 1.05, SPI(t) 0.98

EV(r) $80K, Rework Forecast $40K

Page 23: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201123

Application Aids

Calculation of ES, indicators, and forecast –available from ES website (es calculator page)and several EVM tools

Small Projects (Down Time & Stop Work)– ES website

Range of possible outcomes (confidence limits)– ES website

Schedule Adherence (P-Factor) – ES website,Project Flight Deck, and ProTrack

Out of Sequence EV & Rework – ES website

Page 24: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201124

Summary

Managing schedule may be more difficult thancost and has more repercussions

ES is derived from the PMB and EV accrued

ES makes possible – reliable scheduleperformance indicators, forecasting, prediction

Amplifies ability to control project using EVM &ES

Facilitates identifying process logjams andassess & minimize rework

Application aids are available and coming

Page 25: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201125

Supplemental Remarks

Data for analysis comes from EVM …no newdata is required

Provides top down approach to assessingschedule performance

Equally usable for re-planned projects, andsmall projects having stop work and down-timeconditions

Page 26: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201126

Supplemental Remarks

ES methodology is growing ES website is receiving 40K hits per month

Project management and EVM books now include ES

Included in university coursework & research

Evidence of use is global

Usage is occurring in several industries

Included in PMI EVM Practice Standard (Oct 2011)

Page 27: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201127

Supplemental Remarks

ES has had its share of detractors …andproponents, as well

British philosopher, John Stuart Mill, once madethis observation that new ideas pass throughthree phases of denial:

First – They are wrong

Second – They are against religion

Third – They are old news, trivial, commonsense, and we all would have thought of them ifwe had had the time, money, and interest

Page 28: Earned Schedule Application to Project Management Schedule Application to Project...Project Management Walt Lipke PMI ... performance indicators, forecasting, prediction ... “Schedule

EVM Europe 2011Copyright Lipke 201128

References

“Earned Schedule Application to Small Projects,” PM WorldToday, April 2011 (Vol. XIII, Issue IV)

“Schedule Adherence and Rework,” The Measurable News,2011 Issue 1: 9-14

Earned Schedule, Rayleigh, NC, Lulu Publishing 2009

Earned Schedule Website: www.earnedschedule.com