earned value calculation worksheet (1)
TRANSCRIPT
![Page 1: Earned Value Calculation Worksheet (1)](https://reader031.vdocuments.net/reader031/viewer/2022020101/552a929b4a7959496d8b4683/html5/thumbnails/1.jpg)
Earned Value Calculation Worksheet and Exercise
Earned Value Statistic Earned Value Description/Formula
Answer to exercise #1
Actual Cost (AC) How much money has been spent for work that is completed?
$47,500
Budget at Completion (BAC) How much is budgeted for total project?
$100,000
Earned Value (EV) What is the value of the work already performed?(% complete * BAC)
$40,000 (40% complete)
Planned Value (PV) What is the value of the work expected to be done?
$50,000 (50% complete)
Cost Variance (CV) EV - AC -$7,500 (Bad, negative)
Schedule Variance (SV) EV - PV -$10,000 (Bad Negative)
Cost Performance Index (CPI) EV ÷ AC 0.84 (Bad < 1)
Schedule Performance Index (SPI) EV ÷ PV 0.80 (Bad < 1)
Estimate at Completion (EAC)
Use bolded formula!
BAC ÷ CPI used if no variance has occurred or expect to continue at the same rate as currently: OrAC + ETC used if original estimate was flawed and you developed a new oneOrAC + (BAC – EV) used when current variances won’t be continued into the futureOr(AC + (BAC – EV)) ÷ CPI
Estimate To Complete (ETC) EAC - AC
Variance at Completion BAC - EAC
![Page 2: Earned Value Calculation Worksheet (1)](https://reader031.vdocuments.net/reader031/viewer/2022020101/552a929b4a7959496d8b4683/html5/thumbnails/2.jpg)
Exercise 1We are consulting with 10 physician groups across the country. We have budgeted $100,000 ($10K per physician office). The schedule calls for us to visit one physician office per week.
At week 5 we have visited 4 physician offices and spent $47,500 to date.
What is cost and schedule performance of our consulting project?
Exercise 2:We are purchasing and installing an EHR. The cost of all components (software, labor, hardware, fees) is budgeted at $84,000 and is expected to take 6 months.Assume that the work and costs are evenly distributed throughout the schedule.
At the end of month 3 we have completed 60% of the work and spent $50,000.
What is cost and schedule performance of our EHR project?
Exercise 3:We are implementing a health information exchange. The cost of all components (software, labor, hardware, fees) is budgeted at $6,000,000 and is expected to take 2 years.Assume that the work and costs are evenly distributed throughout the schedule.
At the end of month 9 we have completed 20% of the work and spent $2,000,000.
What is cost and schedule performance of our HIE project?