earned value management ncma workshop_june08

Upload: ajayikayode

Post on 02-Jun-2018

239 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    1/71

    1

    BASICS OF

    EARNED VALUEMANAGEMENT

    National Contract Management Association

    Colorado Springs ColoradoJune 19, 2008

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    2/71

    2

    Earned Value Management(EVM) Training Objectives

    Understand basic concepts What EVM is and basic terms

    How to evaluate performance What does it all mean?

    How to manage using Earned Value Now that we know what it is and what it means,

    what do we do with it?

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    3/71

    3

    Earned Value ManagementSystems measure progress

    Progress = Movement Forward

    to measure progress,there must be a standard

    against which the forward

    movement may be

    compared

    EVMS establishes a baseline

    to measure progress

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    4/71

    4

    EVM can provide answers to the

    following questions: How much have we spent?

    How much did we get for our money?

    How much more will be have to spend to complete thetasks we wanted to accomplish?

    How much longer will it take?

    How efficiently is the work being done?

    What has happened? (Why are we off schedule/cost?) What is happening? (What are the impacts?)

    What is going to happen? (What are we doing to fix it?)

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    5/71

    5

    Why use Earned ValueManagement Systems?

    The Bottom Line

    EVM can focus program management attention oncritical issues and risks during the project life

    cycle How are you doing, and how do you know how you

    are doing? Early problem identification

    Completion Estimates How far along are you? (64%, 50%, >40%) What is your productivity/efficiency? Work remaining

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    6/71

    6

    Earned Value ManagementIs Not:

    Guarantee of profit

    Restricted to projects for the production ofa products EVM can be used in servicecontracts

    Solution for a poorly written statement ofwork

    Magic Bullet

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    7/71

    7

    Five Basic Elements

    BCWS Budgeted Cost of Work Scheduled

    BCWP Budgeted Cost of Work Performed

    ACWP Actual Cost of Work Performed

    BAC Budget at Completion

    EAC Estimate at Completion

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    8/71

    8

    5 Basic Performance Data

    Questions & Answers

    QUESTION ANSWER ACRONYM

    How much work should Budgeted Cost for BCWSbe done? Work Scheduled

    How much work is done? Budgeted Cost for BCWPWork Performed

    How much did the is done Actual Cost of ACWPwork cost? Work Performed

    What was the total job Budget at Completion BACsupposed to cost?

    What do we now expect the Estimate at Completion EACtotal job to cost?

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    9/71

    9

    What do we measure progress against?and Why?

    Performance measurement baseline Budgetthat is spread over . . .

    Time, to accomplish the scope of

    Work, against which progress can be measured

    Earned Value is key concept how much progress did I make against my original

    plan?

    expressed in dollars or hours Why? early warning

    $

    time

    baseline

    earned value

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    10/71

    10

    Why do we need

    Early Warn ing?

    Small course corrections areeasier when made early

    If you wait until you reach

    the Iceberg, its too late!!!

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    11/71

    11

    Terms and Definitions associated withEVM:

    It starts with the Work Breakdown Structure(WBS)

    Based on the WBS a total budget is assigned

    Work packages are developed and priced

    A process to measure the results of thosework packages is put into place

    Work packages are tracked for both thedollars and time spent

    The result of this effort is developing a Budget atcompletion (BAC)

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    12/71

    12

    Work Breakdown Structure

    1.0 Project New Marketing Campaign

    for Dog Food

    1.1 PrintedMedia

    1.2 ElectronicMedia

    1.3 Radio

    1.3.1LocalSpots

    1.3.2Regional

    Spots

    1.1.2Newspaper

    inserts

    1.1.1Magazines

    1.2.2TV

    1.2.1Website

    First Level

    Second Level

    ThirdLevel

    Systematic approach to ensuring all program work is recognized and defined intoa viable work plan should include labor and materials for complete picture

    O i ti l B kd

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    13/71

    13

    Organizational BreakdownStructure

    New Marketing Campaignfor Dog Food -

    assign to the Western Division

    ChucksDesignTeam

    RegionalMedia

    Support

    CentralizedNationalSupport

    StanIn

    Accounting

    RayBudget

    Juan forCustomerinterface

    SallyFor messageAnd theme

    JoshAudio

    John forComputerGraphics

    Identifies the functions and/or people that will do the work

    Beverlyin

    NationalAccounts

    Admin AsstChen

    Tanya Print

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    14/71

    14

    Responsibility MatrixAssigns WBS work to OBS labor

    design

    graphics

    accounting

    1.1.1 1.1.2 1.2.1

    AdminAsst

    audio

    budget

    1.1 1.2

    OBS WBS

    - - - - - - - - - - - - - - - - - - - - - - - - - -

    ----------

    -----------------------

    - - - - - - - - - - - - - - -

    - - - - - - - - - - - - - - - - - - - - - - - -

    - - - - - - - - - - - - - - - - - - - - - - - - -

    ----------

    -----------------------

    --------

    --------------

    -----------

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    15/71

    15

    CONTRACT BUDGETBASE

    CONTRACT

    PRICE

    CONTRACT

    BUDGET BASE

    PROFITS AND

    FEES

    MANAGEMENT

    RESERVE

    PERFORMANCE

    MEASUREMENT

    BASELINE

    WITHHELD

    FOR

    UNKNOWNS

    UNDISTRIBUTED

    BUDGET

    DISTRIBUTED

    (control accountS)

    WITHHELD FOR

    KNOWN EFFORT

    AUTHORIZED,

    UNPRICED

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    16/71

    16

    ORGANIZATION

    BUDGET LEDGER

    MASTER SCHEDULE

    GENERAL WORKAUTHORIZATION

    CONTRACT

    Control AccountWBS # ______________ ORG # ______________

    TASK DESCRIPTION________________________

    SCHEDULE _______________________________

    TOTAL BUDGET ________________

    WORK PACKAGE

    WP # ________ ORG # _________

    DESCRIPTION ________________

    ______________________________

    SCHEDULE _________________

    BUDGET ___________________

    WBS ELEMENT

    ORGANIZATION

    WORK AUTHORIZATION

    SCHEDULE

    BUDGET

    COST ACCUMULATION

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    17/71

    17

    The Control AccountA Key Management Control Point

    Specific functional responsibility

    Specific WBS responsibility

    Work planning and assignment

    Performance measurement

    Cost collection

    Variance analysis

    Corrective action

    Basis of data summarization

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    18/71

    18

    CONTRACT BUDGETBASE

    CONTRACT

    PRICE

    CONTRACT

    BUDGET BASE

    PROFITS AND

    FEES

    MANAGEMENT

    RESERVE

    PERFORMANCE

    MEASUREMENT

    BASELINE

    WITHHELD

    FOR

    UNKNOWNS

    UNDISTRIBUTED

    BUDGET

    DISTRIBUTED

    (control accountS)

    WITHHELD FOR

    KNOWN EFFORT

    AUTHORIZED,

    UNPRICED

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    19/71

    19

    PERFORMANCE MEASUREMENT

    DATA ELEMENTS

    UNDISTRIBUTED BUDGET (UB)

    Budget applicable to contract effortwhich has

    not yet been identified to CWBS elements at orbelow the lowest level of reporting to the

    Government.

    KEY: Only used for the effort associated

    with the contractual change.

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    20/71

    20

    PERFORMANCE MEASUREMENTDATA ELEMENTS

    MANAGEMENT RESERVE (MR)An amount of the total allocated budget

    withheld for management control purposesrather than designated for the

    accomplishment of a specific task or set of

    tasks.

    KEY: There is no scope of work associated

    with management reserve budget.

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    21/71

    21

    1. DEFINE THE WORK

    PLANNING AND BUDGETING

    ESTABLISH THE BASELINE - AN ITERATIVE, 3-STEP PROCESS

    10040

    60

    15

    25

    30

    30

    2. SCHEDULE THE WORK

    3. ALLOCATE BUDGETS

    $

    CONTRACT BUDGET BASE

    TIME

    MR

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    22/71

    22

    Work Budgeted and Earned

    The value of the budgeted workis called:Budgeted Cost of Work Scheduled(BCWS)

    The value of work earnedis called:Budgeted Cost of Work Performed(BCWP)

    BCWP is also called Earned Value (EV)

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    23/71

    23

    5 Basic Performance Data

    Questions & Answers

    QUESTION ANSWER ACRONYM

    How much work should Budgeted Cost for BCWSbe done? Work Scheduled

    How much work is done? Budgeted Cost for BCWPWork Performed

    How much did the is done Actual Cost of ACWPwork cost? Work Performed

    What was the total job Budget at Completion BACsupposed to cost?

    What do we now expect the Estimate at Completion EACtotal job to cost?

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    24/71

    Budgeted Cost of Work Scheduled

    (BCWS)

    Total Budget = $5,000to be spent over 5 monthsI plan to lay 1 sectionof track each month at an

    estimated cost of $1,000.BCWS each month = $1,000Total BCWS = $5,000

    Month 1BCWS = $1,000

    Month 4BCWS = $1,000

    Month 3BCWS = $1,000

    Month 5BCWS = $1,000

    Month 2BCWS = $1,000

    sum of all BCWS = performance baseline

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    25/71

    25

    5 Basic Performance Data

    Questions & Answers

    QUESTION ANSWER ACRONYM

    How much work should Budgeted Cost for BCWSbe done? Work Scheduled

    How much work is done? Budgeted Cost for BCWPWork Performed

    How much did the is done Actual Cost of ACWPwork cost? Work Performed

    What was the total job Budget at Completion BACsupposed to cost?

    What do we now expect the Estimate at Completion EACtotal job to cost?

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    26/71

    26

    Budgeted Cost of Wo rk Performed

    (BCWP)

    aka. Earned Value

    Were at the end of

    February, Track 1 is

    complete and track 2 is done.

    BCWS = $1,000

    Track 1

    Track2

    BCWS = $1,00050% done

    Value of workperformed = $1,500

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    27/71

    27

    Schedule Variance

    BC WS

    BC WP

    of the work I scheduled to have done,how much did I budget for it to cost?

    of the work I actually performed,how much did I budget for it to cost?

    SCHEDULE VARIANCEis the difference between work scheduledand work performed (expressed in terms of budget dollars)

    formula: SV $ = BCWP - BCWS

    B

    UDGETBASED

    example: SV = BCWP - BCWS = $1,500 - $2,000SV= -$500 (negative = behind schedule)

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    28/71

    28

    Schedule Variance

    $

    BCWSthe baseline

    BCWPearned value

    TIME

    5,000

    sv

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    29/71

    29

    5 Basic Performance Data

    Questions & Answers

    QUESTION ANSWER ACRONYM

    How much work should Budgeted Cost for BCWSbe done? Work Scheduled

    How much work is done? Budgeted Cost for BCWPWork Performed

    How much did the is done Actual Cost of ACWPwork cost? Work Performed

    What was the total job Budget at Completion BACsupposed to cost?

    What do we now expect the Estimate at Completion EACtotal job to cost?

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    30/71

    30

    Actual Cost of Work Performed(ACWP)

    Value is earned as the work is completedand gauged against the schedule proposedfor the work

    When all work is completedit will haveearned its full budgeted valuebut the actualcostof that work may be different that the

    amount budgeted this is referred to asActual Cost of Work Performed (ACWP)

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    31/71

    ACTUAL COST FOR WORK PERFORMED (ACWP)

    The costs actually incurred and recorded in accomplishingthe work performed (BCWP) within a given time period

    Labor Material (Subcontractor/vendor)

    Other, computer costs, etc.

    Indirect Costs

    PERFORMANCE MEASUREMENTDATA ELEMENTS

    Actual Cost of Work Performed

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    32/71

    32

    Actual Cost of Work Performed(ACWP)

    Track 1 Cost = $1,500!

    Track 2 Cost = $750 cost todate

    Total Cost to Date = $2,250

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    33/71

    33

    Cost Variance

    BC WP

    AC WP

    of the work I actually performed,how much did I budget for it to cost?

    of the work I actually performed,how muchdid it actually cost?

    COST VARIANCEis the difference between budgeted costand actual cost

    formula: CV $ = BCWP - ACWP

    PERF

    ORMANCE

    BASED

    example: CV = BCWP - ACWP = $1,500 - $2,250CV= -$750 (negative = cost overrun)

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    34/71

    34

    Cost Variance

    $

    TIME

    BCWPearned value

    ACWPactual cost

    5,000

    cv

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    35/71

    35

    Variance Summary

    The difference between the BCWP and theACWP is called a cost variance

    The difference between the BCWP andBCWS is called schedule varianceand isprovided in terms of dollars

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    36/71

    36

    5 Basic Performance Data

    Questions & Answers

    QUESTION ANSWER ACRONYM

    How much work should Budgeted Cost for BCWSbe done? Work Scheduled

    How much work is done? Budgeted Cost for BCWPWork Performed

    How much did the is done Actual Cost of ACWPwork cost? Work Performed

    What was the total job Budget at Completion BACsupposed to cost?

    What do we now expect the Estimate at Completion EACtotal job to cost?

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    37/71

    37

    Budget at Completion (BAC)

    $

    time

    BAC

    $

    $

    $

    $

    $

    $

    $

    when all work has been phased, cumulative BCWS = BAC

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    38/71

    38

    Est imate at Complet ion

    (EAC)

    Just a few littleglitches. We should

    be able to do thecomplete job.ack

    lets see, for about

    $7,000

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    39/71

    39

    Variance at Completion (VAC)

    B AC what the total job is supposedto cost

    E AC what the total job is expected

    to cost

    VARIANCE AT COMPLETIONis the difference between what the totaljob is supposed to cost and what the total job is now expected to cost.

    FORMULA: VAC = BAC - EAC

    Example: VAC = $5,000 - $7,000VAC = - $2,000 (negative = overrun)

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    40/71

    40

    Earned Value Management(EVM) Training Objectives

    Understand basic concepts What EVM is and basic terms

    How to evaluate performance What does it all mean?

    How to manage using Earned Value Now that we know what it is and what it means,

    what do we do with it?

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    41/71

    41

    Formulas

    Cost varianceBCWP ACWP

    Schedule variance

    BCWP BCWS

    Cost variance inpercentage

    BCWP ACWP x 100

    BCWP

    Schedule variance inpercent

    BCWP BCWS x 100

    BCWS

    Negat ive var iance = cos t overrun or behin d sch edule

    Posit ive var iance = cost und errun or ahead of sch edule

    d l

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    42/71

    42

    Trend Analysis

    Cost Performance Index (CPI) measure of cost efficiency

    CPI = Value of Work Completed (BCWP)Cost of Work Completed (ACWP)

    Schedule Performance Index (SPI) measure of schedule efficiencySPI = Value of Work Completed (BCWP)

    Value of Work Planned (BCWS)

    Closer to 1 the better

    Less than 1 = overrun (CPI); behind schedule (SPI)

    Greater than 1 = underrun (CPI); ahead of schedule (SPI)

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    43/71

    43

    DO I THINK THE CONTRACTOR WILL COME IN ON BUDGET?

    COST PERFORMANCE INDEX:

    CPI = cost efficiency for work performed to date(The value of work accomplished for each dollar spent)

    SCHEDULE PERFORMANCE INDEX:

    SPI = schedule efficiency with which work has been accomplished

    (The rate at which work is being accomplished)

    Performance Eff iciencies

    WORK= ACCOMPLISHED

    ACTUALS

    WORK= ACCOMPLISHED

    WORKSCHEDULED

    WORK

    BCWP ACCOMPLISHED $1500

    = BCWS = WORK = $2000 = .75

    SCHEDULED

    WORK

    BCWP ACCOMPLISHED $1500

    = ACWP = ACTUAL = $2250 = .67

    COST

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    44/71

    44

    EXERCISES

    Attendees Go to your ExercisePacket

    EVM E i

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    45/71

    45

    EVM Exercise

    BAC = 500BCWS = 300BCWP = 320ACWP = 330

    What is the cost variance? What is the Schedule variance?

    What is the Cost Performance Index? What is the Schedule Performance Index? How would you describe this project?

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    46/71

    46

    Solution

    BAC = 500

    BCWS = 300

    BCWP = 320

    ACWP = 330

    What is the cost variance?

    BCWPACWP = -10 What is the Schedule variance?

    BCWPBCWS = +20

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    47/71

    47

    Solution

    BAC = 500

    BCWS = 300

    BCWP = 320

    ACWP = 330

    What is the Cost Performance Index?

    BCWP/ACWP = .97

    What is the Schedule Performance Index?BCWP/BCWS = 1.07

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    48/71

    48

    Solution

    Cost Variance = -10

    Schedule Variance = + 20

    CPI= .97SPI= 1.07

    How would you describe this project?Over budget, ahead of schedule

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    49/71

    The table that follows presents keyinformation for several elements of the

    contract WBS

    Example Of PerformanceAnalysis By WBS Element.

    What can it tell us?

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    50/71

    50

    Cost Performance Report Work reakdown Structure

    Budget

    Baseline

    Cumulative Cost To Date (in $000) Cost At Completion (in $000)

    $1.5 mil Budgeted Cost ActualCost

    Variance

    WBSElement

    WorkScheduled

    WorkPerformed Schedule Cost Budgeted Estimated Variance

    1.1 250 250 260 0 (10) 250 260 (10)

    1.2 90 85 84 (5) 1 100 100 01.3 130 150 155 20 (5) 330 340 (10)

    1.4 200 200 185 0 15 250 235 15

    1.5 300 310 320 10 (10) 400 415 (15)

    1.6 120 120 140 0 (20) 120 140 (20)

    Subtotal 1,090 1,115 1,144 1,450 1,490 (40)

    Mgt. Reserve 50 50

    Total 1,090 1,115 1,144 1,500 1,490 10

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    51/71

    Graphical Depictions of EVM

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    52/71

    PERFORMANCE MEASUREMENTDATA ELEMENTS

    TIME

    $

    BUDGET

    Contract

    Complete

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    53/71

    TIME

    $

    BUDGET

    CV

    PERFORMANCE MEASUREMENTDATA ELEMENTS

    Contract

    Complete

    BCWP All I l ti f

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    54/71

    BCWP Allows Isolation ofSchedule and Cost Variances

    schedule variance = BCWP - BCWS = negative numbercost variance = BCWP - ACWP = negative number

    behind schedule,over cost

    BCWS

    BCWP

    ACWP

    TIME

    5,000

    sv

    cv$

    Budget at Complete (BAC), Estimate at Complete (EAC)

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    55/71

    55

    Budget at Complete (BAC), Estimate at Complete (EAC)and Variance at Complete (VAC)

    $

    TIME

    BAC= Sum of BCWS

    (Planned cost of all work)

    BAC = $5,000

    EAC(kr)*= ACWP plus estimated

    to complete (ETC)(Actual cost to date plus expected

    cost to finish all work)

    EAC = $7,000

    BAC

    EAC

    ETC

    VAC= BAC-EAC

    VAC = $5,000-$7,000

    VAC = -$2,000

    VAC

    Schedule

    Delay

    * EAC(kr) = Contractor EAC

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    56/71

    PERFORMANCE MEASUREMENTDATA ELEMENTS

    TIME

    $

    BUDGET

    CV

    VAC

    Contract

    Complete

    SV

    T d A l i U i

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    57/71

    57

    Trend Analysis UsingPerformance Indexes

    Time

    Time

    Time

    1.0

    1.0

    1.0

    CPI

    CPI

    CPI

    SPISPI

    SPI

    Trend Analysis Using Performance

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    58/71

    58

    Trend Analysis Using PerformanceIndexes

    Time

    Time

    Time

    1.0

    1.0

    1.0

    CPI

    CPI

    SPI

    CPISPI

    SPI

    E d V l M t

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    59/71

    59

    Earned Value Management

    Trend Analysis

    Time

    Time

    Time

    1.0

    1.0

    1.0

    CPI

    CPI

    SPI

    CPISPI

    SPI

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    60/71

    Sample combined numerical

    and graphical display

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    61/71

    61

    Earned Value Management

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    62/71

    62

    Earned Value Management(EVM) Training Objectives

    Understand basic concepts What EVM is and basic terms

    How to evaluate performance What does it all mean?

    How to manage using Earned Value Now that we know what it is and what it means,

    what do we do with it?

    Ways of Earning Value

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    63/71

    63

    Earned Value techniques Discrete

    physical, tangible end product

    Apportioned discrete, dependent on another discrete work package

    example: quality assurance

    planned as historical estimating factor (e.g., 7%)

    Level of Effort no tangible end product

    basis of measurement: time

    when clock starts ticking, you automatically accumulate earned value

    no schedule variance

    example: management personnel

    Should be a quantitative and discrete way to measurethe work

    May tie in with success criteria or technical measure e.g., successful completion of a specific test, QPs

    Ways of Earning Value

    Contractor Reports

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    64/71

    64

    Contractor Reports

    Cost Performance Report (CPR)

    Format 1:cost and schedule progress byWBS(specified reporting level usually at level 3)

    Format 2: cost and schedule progress byorganization

    Format 3:changes to performance measurement

    baseline

    Format 4:manpower forecast

    Format 5: variance analysis

    Format 1 Block Descriptions

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    65/71

    65

    Block #

    1. Contractor Information - Tells you name and address of contractor

    2. Contract Information - Tells name, number, type and Share ratio of contract

    3. Program Information- Name and Phase of program4. Report Period - Beginning and end dates of the report data

    5. Contract Data - Includes quantities, prices, fees, profit, and ceilings

    6. Estimated cost - Estimated cost at completion and variance

    7. Contractor Representative - Name, Title, Signature, and Date signed

    8. Broken in to sections a through g and in 4 groups of data

    - Current period - BCWP, BCWS, ACWP, Cost and Schedule Variances- Cumulative to date - BCWP, BCWS, ACWP, Cost and Schedule Variances

    - Reprogramming Adjustments - Cost Variances and Budget

    - At Completion - Budgeted, Estimated, and Variance

    8a WBS cost data

    8b Cost of money

    8c General and administrative cost8d Undistributed money

    8e Subtotal (Total without Management Reserve)

    8f Management Reserve

    8g Total

    9a Variance adjustments (Cumulative to Date)

    9b Total Contract Variance (Cumulative to Date and At Completion)

    Format 1 Block Descriptions

    Format 2: Organizational

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    66/71

    66

    Format 2: OrganizationalCategories

    Used when contractor organizationalstructure does not mirror the WBSstructure

    Provides CPR data in an organizationalformat

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    67/71

    67

    Format 3: Baseline

    Used to track changes to the performancebaseline and future authorized work Identifies all changes to authorized work

    during the reporting period Identifies distribution of any undistributed

    budget during the reporting period

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    68/71

    68

    Format 4: Staff ing

    Provides planned staffing

    Current Period

    Cumulative to the end of Current Period

    Staffing forecast's to end of authorized work

    At Completion

    Broken down into organizational

    categories

    Format 5: Explanation and

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    69/71

    69

    Format 5: Explanation andProblem Analysis

    Also called Variance Analysis Report(VAR)

    Provides explanations, impact, andcorrective actions of WBS that exceed

    thresholds

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    70/71

    70

    Format 5 variance analysis shouldaddress: separate discussion of CV, SV (current and

    cum) and VAC

    clear description of reason for variance quantity variances (e.g., price vs. usage)

    be specific, not general

    corrective action

    technical, schedule, and cost impacts impact to estimate at completion

    Variance Exp lanat ions

    A big hammer fora big variance!

    Profit / Fees

    Contract Price

    Earned Value Management

  • 8/10/2019 Earned Value Management NCMA Workshop_June08

    71/71

    TERMINOLOGYNCC Negotiated Contract Cost Contract price less profit / fee(s)AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitizedCBB Contract Budget Base Sum of NCC and AUWOTB Over Target Baseline Sum of CBB and recognized overrun TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB BAC Budget At Completion Total budget for total contract thru any given levelPMB Performance Measurement Baseline Contract time-phased budget planMR Management Reserve Budget withheld by Ktr PM for unknowns / risk managementUB Undistributed Budget Broadly defined activities not yet distributed to CAsCA Control Account Lowest CWBS element assigned to a single focal point to plan & control

    scope / schedule / budgetWP Work Package Near-term, detail-planned activities within a CAPP Planning Package Far-term CA activities not yet defined into WPsBCWS Budgeted Cost for Work Scheduled Value of work planned to be accomplished = PLANNED VALUEBCWP Budgeted Cost for Work Performed Value of work accomplished = EARNED VALUEACWP Actual Cost of Work Performed Cost of work accomplished = ACTUAL COSTEAC Estimate At Completion Estimate of total cost for total contract thru any given level;

    may be generated by Ktr, PMO, DCMA, etc. = EACKtr / PMO / DCMALRE Latest Revised Estimate Ktrs EAC or EACKtrSLPP Summary Level Planning Package Far-term activities not yet defined into CAsTCPI To Complete Performance Index Efficiency needed from time now to achieve an EAC

    EVM POLICY: DoDI 5000.2, Table E3.T2 . EVMS in accordance with ANSI/EIA-748 is required for cost or incentivecontracts, subcontracts, intra-government work agreements, & other agreements valued > $20M(Then-Yr$). EVMScontracts > $50M(TY $) require that the EVM system be formally validated by the cognizant contracting officer. Additional

    Guidance in Defense Acquisition Guidebook and the Earned Value Management Implementation Guide (EVMIG). EVMS isdiscouraged on Firm-Fixed Price, Level of Effort, & Time &Material efforts regardless of cost.

    EVM CONTRACTING REQUIREMENTS:Non-DoDFAR Clauses Solicitation 52.234-2 (Pre-Award IBR) or 52.234-3 (Post Award IBR)

    Solicitation & Contract52.234-4

    DoD( $20M) DFAR Clauses - 252.234-7001 for solicitations and 252.234-7002 for solicitations & contractsContract Performance Report DI-MGMT-81466A * 5 Formats (WBS, Organization, Baseline, Staffing & Explanation)

    Integrated Master Schedule DI-MGMT-81650 * (Mandatory for DoD EVMS contracts)Integrated Baseline Review (IBR)- Mandatory for all EVMS contracts

    * See the EVMIG for CPR and IMS tailoring guidance.

    ManagementReserve

    Work Packages Planning Packages

    OVERRUNAUW

    ControlAccounts

    NCC

    UndistributedBudget

    OTBCBB

    TAB Profit / Fees

    PMB

    Summary LevelPlanning Packages

    DoD TRIPWIRE METRICS Favorable is > 1.0, Unfavorable is < 1.0

    Cost Efficiency CPI = BCWP/ ACWPSchedule Efficiency SPI = BCWP/ BCWS

    VARIANCES Favorable is Positive, Unfavorable is NegativeCost Variance CV = BCWP ACWP CV %

    = (CV / BCWP) *100Schedule Variance SV = BCWP BCWS SV %

    = (SV / BCWS) *100Variance at Completion VAC = BAC EACOVERALL STATUS

    % Schedule = (BCWSCUM / BAC) *100% Complete = (BCWPCUM / BAC) *100% Spent = (ACWPCUM / BAC) *100

    BASELINE EXECUTION INDEX (BEI) (Schedule Metric)BEI = # of Baseline Tasks Actually Completed / # of Baseline Tasks Scheduled for Completion

    CPLI = (Critical Path Duration + Float Duration(to baseline finish)) / Critical Path DurationCRITICAL PATH LENGTH INDEX (CPLI) (Schedule Metric)

    TO COMPLETE PERFORMANCE INDEX (TCPI) #

    TCPIEAC = Work Remaining / Cost Remaining = (BACBCWPCUM)/ (EACACWPCUM)

    ESTIMATE AT COMPLETION #

    EAC = Actuals to Date+ [(Remaining Work) / (Efficiency Factor)]

    EACCPI = ACWPCUM + [(BACBCWPCUM) / CPICUM ] BAC / CPICUM

    Gold ard

    Management Reserve

    CostVariance

    Schedule Variance

    ACWP

    BCWP

    BCWS

    $

    EAC

    TimeNow

    CompletionDate

    PMB

    TAB

    BAC

    time