earned value management _ the world-wide leader in planning

Upload: k-m-sendhil

Post on 08-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 Earned Value Management _ the World-wide Leader in Planning..

    1/3

    Earned Value Management

    ned Value Management | The world-wide leader in p... http://www.planningplanet.com/wiki/422378/earned-v...

    f 3 4/28/2011 11:27 AM

  • 8/7/2019 Earned Value Management _ the World-wide Leader in Planning..

    2/3

    Posted Wed, 2009-02-04 10:26 by Technical Develop...

    Earned Value Management (EVM) is a project control process based on a structured approach to planning, cost

    collection and performance measurement. It facilitates the integration of project scope, time and cost objectives and

    the establishment of a baseline plan for performance measurement.

    Earned Value Analysis (EVA) is a proactive way of managing and controlling projects and is used extensively in a

    range of industries and is increasingly being used as a project management tool in construction. In principle EVA

    compares the amount of work planned and its budget against the amount of work actually carried out, its budget and

    its actual cost. The measurement of this can be used to show the current status of a project in terms of cost and timemeasured against the baseline plan and also to forecast the outturn positions.

    Preparation for using EVA should commence at the outset of a project. Initially a Work Breakdown Structure must be

    developed breaking down the work into appropriate elements reflecting the way the project is to be managed.

    Typically this will be in trade packages. The work elements are then developed, quantified and priced and resources

    allocated to activities on the programme schedule. This schedule forms the baseline for monitoring and control of the

    project using EVA.

    During the implementation of the project, progress percentages are assessed at regular intervals for each activity

    along with resource utilisation taken from allocation sheets and cost data taken from cost reports. Comparing the

    actual information collected in this manner against the baseline plan will allow the following indices to be calculated:

    Earned Value (EV) = % Complete x Budget for each activity

    Schedule Performance Index (SPI) = Earned Value / Planned Value

    Cost Performance Index (CPI) = Earned Value / Actual Cost

    Schedule Variance (SV) = Earned Value Planned Value

    Cost Varia nce (CV) = Earned Value Actual Cost

    EVA highlights trends and allows outturns to be predicted and has been shown to be a very accurate project

    management tool. Much of the reason for this is that it imposes good project management disciplines. In the

    development phase it requires detailed pre-planning and the preparation of a resourced programme linked to the price

    or budget for the project. Subsequently during the implementation phase, it requires the collection of as-built records

    and the analysis of actual performance against the plan.

    Practical difficulties, such as a potential reluctance by trade contractors to provide required information, must be

    anticipated and pre-empted. Tender documentation should be drafted to include a stipulation that detailed cost and

    resource information must be provided and in this way EVA can be used to manage trade packages as well as the

    project as a whole.

    Below is an example that w ill elaborate a simplistic explanation of EVM principle and application, it uses

    the PMBOK-4th edition acronyms.

    Tricia is the Planner in charge of 20 miles of sidewalk project.

    According to your plan, the cost of construction will be $15, 000 per miles and will take 8 weeks to complete.

    2 weeks into the project, you have spent $55, 000 and completed 4 miles of sidewalk, and you want to report

    performance and determine how much time and cost remain.

    Solution :

    BAC = [How much we originally expected this project to cost]-BUDGET

    = [20 miles of sidewalk] x [$15,000 per mile]

    = $300, 000.00

    PV = [How much work was planned for this point in time]

    = Planned % complete x BAC

    = [2 weeks completed on an 8 weeks schedule] x BAC

    = 2/8 x 300,000

    = $75, 000.00

    EV = [How much has been earned on the project]

    ned Value Management | The world-wide leader in p... http://www.planningplanet.com/wiki/422378/earned-v...

    f 3 4/28/2011 11:27 AM

  • 8/7/2019 Earned Value Management _ the World-wide Leader in Planning..

    3/3

    Website Development by Hunt Data Solutions and Vit-al Interactive. CMS: Drupal THEME:Acquia Marina

    ned Value Management | The world-wide leader in p... http://www.planningplanet.com/wiki/422378/earned-v...

    f 3 4/28/2011 11:27 AM