earth retention brochure

Upload: danielgabrielbalea

Post on 07-Jul-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Earth Retention Brochure

    1/12

    H A Y W A R D B A K E R I N C .

    EARTH RETENTION

    ver the past forty years, earth retention technology hasevolved from relatively simple methods of temporary shoring

    for excavation support to complex subterranean reinforce-

    ment for permanent stabilization of deep cuts and slopes. When exca-

    vations are planned near existing structures, Hayward Baker can

    employ underpinning techniques to support the adjacent structures.

    Better equipment, use of the latest soil and rock anchoring techniques,

    and innovative use of soil nailing allow cost-effective and safe support

    of excavations as well as slope stability control. The innovative use of 

    micropiles, often in combination with anchors, to construct walls hasproven to be a valuable tool for increasing the factor of safety of land-

    slide prone areas.

    Crucial to the successful use of these technologies is a thorough un-

    derstanding of geotechnical engineering as well as the structural

    mechanics of the retention system itself. That is why Hayward Baker

    should be the first company that you call. We are highly experienced

    in earth retention and are able to apply this experience to complex

    soil-structure interaction projects.

    Hayward Bakerprovides the widestrange of earth retentionoptions to give you acost-saving design.

     Above: Working at an elevation of 7,500 feet,

     Hayward Baker installed 2,200 linear wall

     feet of 20-foot exposed height soldier pile and

     lagging wall in the most unstable sloughing-

     prone section along a gas field access road

     near Parachute, CO. The project included a

     total of 350 soldier piles, 175 (200-kip)

     ground anchors, and 44,000 square feet of 

     permanent wood lagging.

     Right: This 120-foot-diameter drilled secant

     pile shaft provided earth retention for the

     construction of a new pump station in

     Austell, GA. Piles were 36-inch-diameter 

     and up to 55 feet deep.

    O

  • 8/18/2019 Earth Retention Brochure

    2/12

    Ground AnchorsGround anchors transfer loads

    using grouted thread bars or

    strand tendons connected to a

    structure and bonding into sta-

    ble soil or rock. These projects

    are typically for retaining walls,temporary shoring, or other

    grade separation requirements.

    Hayward Baker incorporates ground anchors into

    structural walls for additional support when required.

    Other applications include landslide stabilization, re-

    sistance of overturning, support of excavations, ma-

    rine bulkheads, and resistance of vertical uplift.

    Ground anchors offer a cost-effective solution for ei-

    ther temporary or permanent applications.

    Technique

    Drill hole.

    Insert thread bar or strand tendon.

    Grout in place.

    Extract casing (if used).

    Connect anchor head to structure face.

    Post-tension.

    Geotechnical ConsiderationsSuitable soil or rock in which to bond the anchors be-

    yond any instability on failure plane must be identified.

    ayward Baker provides design-build solutions using retaining

    walls consisting of soldier piles with lagging, sheet piles, secant

    piles, tangent piles, and diaphragm walls. The structural mem-

    bers resist lateral pressures from the retained soil and adjacent structures

    and prevent soil raveling. Ground anchors or bracing can be incorporated

    into the design for additional lateral support. The anchors transfer latera

    loads from earth pressures and adjacent structures into competent zones

    of soil or rock behind the potential failure plane of the retained soil.

    CantileverCantilever walls provide lateral earth support solely by the bending and

    shear strength of the wall and by passive resistance of the soil in which

    the wall’s vertical elements are embedded.

    Braced and AnchoredInternally braced lateral support can be provided by bracing with rakers

    into the excavation base to deadmen or by bracing with struts between ad

     jacent walls.

    Anchored walls resist lateral forces by incorporating ground anchors. The

    face of the wall may consist of soldier piles and lagging, sheet piles, secant

    piles, tangent piles, or a diaphragm wall. The anchors may be installed as

    coupled bars or coiled strands to minimize access requirements.

    Applications of Braced and Anchored Walls When lateral earth pressures are high and/or minimal passive soil

    resistance is available.

    Wall heights exceeding 12 to 15 feet in most soil types.

    Limiting wall deflection and ground movement behind the wall

    is critical.

    Design Considerations Consider soil conditions and temporary and permanent water tables

    when selecting wall types.

    Design wall and lateral support for allowable deflection, especially if

    adjacent structures or utilities are present.

    Structural Retaining Walls

    H

    Design/BuildHayward Baker offers complete design-build serv-

    ices for all of our earth retention systems. Ad-

    vanced 3D modeling software assists with efficient

    design on the complex projects, enabling avoid-

    ance of subsurface conflicts between existing or

    planned structures.

     3D CAD modeling was undertaken to avoid conflicts between soldier 

     piles, grouted tiebacks, soil nails, and existing active utilities at the

    Calumet Water Reclamation Plant in Chicago, IL.

     Internally braced

     sheeting to allow for 

     construction of the

    10,000-cubic-yard

     concrete Trump

    Tower elevator

     core at the Trump

     International Hotel

    & Tower, Chicago, IL.

  • 8/18/2019 Earth Retention Brochure

    3/12

     Hayward Baker installed an anchored soldier pile and lagging wall for excavation

     support for construction of the new Ernie Davis Hall at Syracuse University inSyracuse, NY.

     Jet grouting created this internally braced secant pile wall for a WWTP addition

    in Providence, RI.

     Hayward Baker installed four levels of permanent ground anchors to support a

     diaphragm wall excavation for the construction of the Elm Road Generation

    Station Pump House in Oak Creek, WI.

    Consider if wall will be a part of the permanent structure

    when selecting type and corrosion protection.

    Consider global stability, as with all walls.

    Technique

    Soldier Piles & Lagging Drive steel H-sections or pipe piles

    with a vibratory or impact hammer,

    or insert into predrilled holes along

    planned excavation limits.

    Insert timber, concrete, or steel lagging

    between piles as excavation proceeds.

    Sheet Pile Walls Drive with a vibratory or impact

    hammer or press interlocking steel

    sheets along panned excavation limits

    or seawall alignment.

    Secant or Tangent Pile Walls Install overlapping or adjacent drilled

    shafts, jet grouted soilcrete or soil mix

    columns, or augercast piles along

    excavation limits.

    Stiff walls.

    Structural Slurry Walls Excavate slurry-filled trench.

    Upon reaching design depth, replace

    slurry with reinforced concrete.

    Stiff walls.

    Generally offered through our sister

    company, Case Foundation Company.

    Advantages Speedy excavation for project schedule acceleration.

    Effective in wide variety of subsurface conditions and

    work environments.

    Sheet pile, secant pile, and structural slurry walls provide

    ground water control.

    Variety of systems can be installed without vibration.

    PLANNED EXCAVATION

    PLANNED EXCAVATION

  • 8/18/2019 Earth Retention Brochure

    4/12

    4

    Grouted Soil Walls

    routed soil walls are created by cementing soil particles together

    in situ. Excavation can proceed once the grouted soil has cured

    sufficiently. Grouted soils can be formed beneath existing foun-

    dations to provide underpinning as well as excavation support.

    The two primary methods of creating grouted soil walls are jet grouting and

    soil mixing. These methods mix the binder and soil in situ to create soilcrete.

    Permeation grouting can also be used to inject chemical grout or cement

    grout into soils. All of these methods are suitable for vibration-sensitive sites.

    Applications

     Jet Grouting, Permeation Grouting When internal bracing is able to be avoided, it speeds up the

    excavation process. Restricted access construction, inside and outside.

    Grouting around in situ obstructions.

    Underpinning structures adjacent to excavations.

    Enhance or complete other retention systems where utilities

    interfere with their installation.

     Jet Grouting, Soil Mixing When internal bracing is able to be avoided, it speeds up the

    excavation process.

    Increase slope stability.

    Mitigate lateral spreading.

    Construct rings of columns that support access shafts, once excavated.

    When the columns toe into an impermeable layer or when a jet

    grout bottom seal is constructed, ground water control is provided

    so excavation can be completed in the “dry.”

    Design ConsiderationsWith each soil wall grouting technique, care must be taken when laying

    out the mixing and injection locations to ensure that the required soil-

    crete geometry is achieved.

    Ground anchors or internal bracing can be incorporated into grouted wallsif required, for lateral support.

     Jet Grouting and Soil Mixing Can be performed in most soils.

    Soil gradation affects binder selection and dosage as well as final

    soilcrete strength.

    A laboratory mix design using the soil from the site is often

    performed prior to final soil mix design.

    Permeation Grout Can only be used in granular soils with low fines content.

     Jet grouting underpinned and provided earth retention for this wall at the

     Bayer Healthcare facility in Walpole, MA.

    This soil mix column and soldier pile retaining wall was constructed within

     one foot of a reclaimed water line to facilitate construction of a new turning

     lane near a strip mall in Davenport, FL.

     

     Jet grouting was used to

     create access shafts for the

     construction of a new water 

     treatment plant in Frankfort,

     KY (right), and for a storm

     sewer relief tunnel project in

    St. Louis, MO (below).

  • 8/18/2019 Earth Retention Brochure

    5/12

    Techniques

     Jet Grouting High-velocity jets erode and blend in situ

    soils with grout slurry.

    Process initiated at bottom of planned

    column depth.

    Consistent, uniform rotation and lifting.

    Overlapped soilcrete columns form wall.

    Wet Soil Mixing Advance drill rod while injecting cement

    slurry grout through mixing paddles.

    Overlapped soil mix columns form wall.

    Trench Remixing Deep (TRD) Walls Innovative deep soil mixing method.

    Uses vertical chainsaw-like mixing tool.

    Simultaneously cut and mix in place without

    open trench.

    Creates high-quality wall up to 170 feet deep.

    Operable where other methods would be

    exceedingly difficult.

    Permeation Grout Walls Grout injected into granular soils through

    ports along sleeve port pipes for accurate

    placement.

    Grout cements the soil particles together.

    Spheres of grouted soil overlap to create the

    required geometry.

    Advantages

     Jet Grouting and Permeation Grouting

    Effective and safe methods of direct underpinning of structuresand utilities.

    Can double as earth retention/excavation support system.

    Suitable for open or restricted access.

    Targeted treatment of specific depth intervals possible.

    No harmful vibrations imparted to surrounding structures.

    Permeation grouting produces no appreciable waste.

    Soil Mixing Suitable for nearly all soil types.

    No harmful vibrations imparted to surrounding structures.

     Above: The TRD machine

     constructing a cutoff wall

     within the Herbert Hoover 

     Dike surrounding Lake

    Okeechobee in central

     Florida. TRD soil mix

     walls are also used for 

     excavation support.

     Right: Jet grouting 

     provided permanent in

     situ erosion mitigation

     between conventional

     drilled shafts along this

     coastal seawall at

    Vandenberg AFB, CA,

     without disturbing the

     geology or ecology.

     A Hayward Baker engineer inspects a chemically grouted break-out that was

     constructed prior to excavation of the tunnel access shaft for construction of 

     twin subway tunnels at the LACMTA Eastside Extension (Goldline) project

    in Los Angeles, CA.

    LANNED EXCAVATION

    PLANNED EXCAVATION

  • 8/18/2019 Earth Retention Brochure

    6/12

    6

    oil nail walls utilize patterns of soil nails

    installed across the face of a cut or a

    slope to provide stabilization and earth

    retention. Soil nails are passive, tension-resisting

    steel elements installed in the ground to create a

    reinforced soil mass that provides lateral support.

    The completed wall face can follow the existing

    curvature of the soil mass for an aesthetically

    pleasing appearance.

    Drainage systems are incorporated into the soil nailed wall, reducing

    hydrostatic pressure and preventing saturation of the reinforced

    ground. Drainage systems often utilized are geotextile faced drain

    board, drilled-in-place relief wells, and slotted plastic collection piping.

    Surface drainage control above and behind the retaining wall is also

    critical to the system.

    Applications Embankment stabilization.

    Temporary and permanent excavation support/retaining walls.

    Where some movement can be tolerated.

    Above the water table.

    Retaining wall repair.

    Design Considerations Suitable for firm clays, heterogeneous and stratified soils,weathered rock, and talus slope deposits.

    Not practical in very soft clays, organics/peat, cohesionless

    soils, low density and/or saturated soils, certain fills (rubble,

    cinder, ash, etc.).

    Since limited movement of the retained soil occurs during

    excavation, consideration must be given to adjacent structures.

    Drainage.

    Installation Excavate 3 to 6 feet of soil.

    Drill near-horizontal holes into exposed face, typically on

    3- to 6-foot centers.

    Place grout and steel bar.

    Install drainage system on exposed face.

    Install facing, typically reinforced shotcrete.

    Fix bearing plates.

    Repeat process until design wall depth is reached.

    Apply second coating of shotcrete for aesthetics and corrosion

    protection of permanent wall, if desired.

    Soil Nail Walls

    S

    When the original segmental block retaining wall failed, Hayward Baker 

     constructed a soil nail and anchor remediation with an attached new

     mechanically stabilized earth face preserving the look of the original wall, in

    Tallahassee, FL.

    Completed soil nail wall with shotcrete facing for temporary excavation

     support at the Patewood Medical Center in Greenville, SC.

    Advantages Cost effective.

    Versatile.

    Easily constructed over curved faces and in

    restricted access.

    Soil nails and shotcrete stabilized 5,000 square feet of a failing MSE wall behind apartment buildings in Owings Mills, MD.

  • 8/18/2019 Earth Retention Brochure

    7/12

    Soil Nail Installation Sequence

    Completed Soil Nail Walls

    This 3,300-square-foot permanent shotcrete faced soil nail

     wall was constructed on the property line to support a

     sidewalk and highway immediately adjacent to the site of a

     new drugstore in Dayton, TN.

    1. Excavate 2. Drill 3. Insert nail and grout

     4. Drainage board and reinforcement 5. Shotcrete, then repeat 1 through 5 This completed soil nail wall with shotcrete facing provided

     permanent excavation support once faced with concrete for 

     the Dallas Cowboys Stadium in Arlington, TX.

    This stained shotcrete facing over permanent

     soil nails covered 14,000 square feet to

     remediate failing timber cross-tie retaining 

     walls near residences in Atlanta, GA.

    Soil nail wall covering 3,600 square feet to provide earth

     retention for a new ramp for the Marquette Interchange in

     Milwaukee, WI. Permanent concrete face was cast against the

     soil nail wall.

  • 8/18/2019 Earth Retention Brochure

    8/12

    8

    nchored reaction block walls con-

    sist of discrete, anchored concrete

    blocks placed in a pattern on a slope

    to increase the slope stability. The blocks

    act with the soil to resist the movement of 

    the surrounding soil.

    Applications Landslide stabilization.

    Slope stability control.

    Repair of damaged or failing retaining walls.

    Design Considerations Identify failure plane location.

    Identify suitable soil or rock for stable anchor bonding.

    Determine anchor forces by calculating driving and

    resisting forces by means of a global stability analysis.

    The blocks are typically 5 feet by 5 feet to 12 feet by

    12 feet, depending on the allowable bearing pressure of 

    the soils.

    Depending on wall height, multiple rows of reaction

    blocks at different elevations may be required.

    TechniqueMultiple levels of anchored blocks are stepped to stabilize

    slopes, or are installed across the face of existing retaining

    walls for remediation.

    Excavate along slope to facilitate equipment access,

    if necessary.

     Anchored Reaction Block Walls

     

     Initially, a costly anchored sheet pile wall was designed to permanently stabilize this

     250-foot-long, 50-foot-high cut slope in Montgomery, NY (top and above). Hayward

     Baker designed and constructed a value-engineered alternative consisting of

     43 anchored reaction blocks at three elevations for permanent stabilization.

     Drilling high-capacity ground anchors through the reaction blocks at the US-61 South permanent slope stabilization project near Vicksburg, MS.

  • 8/18/2019 Earth Retention Brochure

    9/12

    Place precast concrete or cast-in-place

    reaction block.

    Drill anchor hole, insert anchor tendon, and

    grout anchor.

    Tension anchor after grout cures.

    Advantages Cost-saving solution for landslide repair and

    slope stability control.

    Can be designed for permanent or temporary

    support.

    Crane-mounted equipment can reach even the

    most difficult access slopes.

     Hayward Baker designed and constructed 354 anchored reaction blocks to repair 

     three failing MSE walls behind a shopping complex in Hoover, AL (above). Access

     was via suspended drilling and work platforms (top). The tieback anchors

     averaged 110 feet long, each with a design capacity of 300 kips.

     Left and above: After a landslide closed US-6 in April 2008, the Colorado

     DOT contracted Hayward Baker to repair the landslide and stabilize the

     slope between I-70 and US-6. Hayward Baker installed 285 anchors, each

     with a capacity of 140 kips with pre-cast anchor blocks on five bench levels.

    The anchor work was completed almost a month ahead of schedule.

  • 8/18/2019 Earth Retention Brochure

    10/12

    10

    he micropile slide sta-

    bilization system (MS³)

    is typically a slope sta-

    bilization system as opposed to

    an excavation support system.

    MS3 retains soil by connecting an

    array of drilled and grouted mi-

    cropiles, sometimes in combina-

    tion with ground anchors, to a

    reinforced concrete beam constructed near the

    ground surface. Acting in tension and compression,

    the micropiles effectively create an integral, stabilized

    ground reinforcement system capable of resisting

    driving forces in the slope that could otherwise cause

    instability or failure.

    Applications Landslide stabilization.

    Side hill fill stabilization.

    Ideal for sites with limited access and/or

    restricted right-of-ways or creeping slopes,

    such as with highway cuts and remediation.

    Design Considerations

    The wall should be placed near the midpointof the failing mass.

    The landslide failure plane should typically

    be less than 50 feet in depth.

    Access required to reach the approximate

    midpoint of the failing slope with personnel

    and equipment.

    Some walls may also require tieback anchors

    to be installed and stressed against the

    concrete cap if landslide forces are large.

    Sequencing of pile and tieback installation

    is important.

    Micropile Slide Stabilization System (MS3 Walls)

    T

    Section view (above) of MS 3 walls Hayward Baker constructed to permanently repair a

     300-foot-wide unstable soil mass extending from a section of Highway 26-89 down to

    Snake River in Alpine, WY (top).

     Hayward Baker constructed 300 linear feet of MS 3 wall to stabilize the slope behind this resort

     development in Bridgetown, Barbados.

  • 8/18/2019 Earth Retention Brochure

    11/12

    Technique Construct concrete beam near ground surface. While it

    is typical to construct the concrete beam first, it may

    also be constructed after micropile installation.

    Drill angled micropiles in a fanned array through the

    beam and into competent stratum.

    Grout the micropiles.

    Install ground anchors through concrete beam for

    increased lateral resistance, if required.

    Advantages Micropiles are constructible in any soil type.

    Minimal excavation and environmental impact.

    Visibility of finished MS³ wall is little to none.

    Constructed without vibration.

    Quality Assurance/ Quality ControlQuality control is an integral part of any HaywardBaker project.

    Quality control begins with procedural inspection and

    documentation. Installation location and inclination are

    accurately performed, measured, and documented, as

    well are injection volumes, rates, and pressures. In cer-

    tain situations, proprietary equipment and software

    allow for real-time monitoring of installation parame-

    ters during construction.

    Material testing may include grout, soilcrete, concrete,

    or shotcrete samples collected on a regular basis for in-

    dependent laboratory testing for strength, homogeneity,

    or permeability if applicable. Corrosion protection of 

    steel elements ensures long-term performance of per-

    manent works.

    Anchor performance and proof testing follow industry

    accepted Post-Tensioning Institute test criteria. All an-

    chors are proof tested while selected anchors receive

    performance tests. Micropile design capacities may be

    verified by full-scale load testing on production piles or

    on sacrificial test piles.

    When required, inclinometers and optical surveys of

    fixed targets are installed to monitor vertical and lat-

    eral movements.

     Hayward Baker designed and constructed this MS 3 wall for slope stability along 

     I-271 NB near Cleveland, OH. The wall is approximately 430 feet long with 345

     micropiles and 35 anchors.

     Anchor proof testing.

    This MS 3 wall stabilized

     a failing slope adjacent to

     railroad tracks in San

     Juan Capistrano, CA.

  • 8/18/2019 Earth Retention Brochure

    12/12

    E A R T H R E T E N T I O N

     Advantages of a Hayward BakerEarth Retention System

     Full design/build service.

    Suitable for restricted access.

     Rapid mobilization.

     Fast excavation for project

     schedule acceleration.

    Wide range of options results

    in cost-effective design.

    Temporary or permanent

     systems available.

     If required, Hayward Baker 

     can also provide a full range

     of underpinning techniques.

     Why Should You Choose Hayward Baker’s Earth Retention?As North America’s largest geotechnical con-

    tractor, Hayward Baker has the resources to

    build your project efficiently, and at a competi-

    tive price. Our network of offices and full-ser-

    vice equipment yards means fast mobilization

    and reduced start-up costs. Our dedication to

    quality control ensures that project specifica-

    tions are achieved. We customize and design our

    equipment and tooling, ensuring that perform-

    ance and reliability are the best in the industry.

    Hayward Baker has the experience and inno-

    vation to assist engineers, contractors, and

    owners with identifying, developing, and im-

    plementing the best earth retention system,

    whether the situation is typical or unique.

    Hayward Baker Inc.

    MarylandCorporate Office 410-551-8200

    Bal timore 410-551-1980

    CaliforniaLos Angeles 805-933-1331

    San Francisco 925-825-5056

    San Diego 760-839-2870

    ColoradoDenver 303-469-1136

    FloridaTampa 813-884-3441

    Ft. Lauderdale 954-977-8117

    GeorgiaAtlanta 770-442-1801

    IllinoisChicago 630-339-4300

    Minnesota

    Minneapolis 952-851-5500MissouriSt. Louis 314-802-2920

    New YorkNew York City 201-489-1700

    Syracuse 315-834-6603

    North CarolinaGreensboro 336-668-0884

    Rhode IslandProvidence 401-334-2565

    TennesseeKnoxvil le 865-583-8212

    Nashv il le 615-883-6445

    TexasDallas/Ft. Worth 817-753-7000

    Houston 281-668-1870

    WashingtonSeattle 206-223-1732

    British ColumbiaVancouver 604-294-4845

    OntarioToronto 800-925-6612

    HB SubsidiaryCraig Olden, Inc. 800-422-4667

    Website   www.HaywardBaker.com

    Email   [email protected]

    Hayward Baker Inc.A member of the Keller WorldwideGroup of Companies

    © Hayward Baker Inc. 2009 

    Pub No: ER01

     Downtown South Boston’s revitalization included construction of retail shops

     with above apartments at Fan Pier. Hayward Baker designed, furnished, and

    installed 940 linear feet of braced sheetpile earth support to retain a 40-foot cut

     depth to facilitate the construction.

    When this MSE wall at a copper mine in Morenci, AZ, failed, Hayward Baker 

     performed an emergency ground anchor program to stabiliz e the wall. A

     combination of wire mesh and vertical whalers distributed the load to the anchors.