earth retention brochure
TRANSCRIPT
-
8/18/2019 Earth Retention Brochure
1/12
H A Y W A R D B A K E R I N C .
EARTH RETENTION
ver the past forty years, earth retention technology hasevolved from relatively simple methods of temporary shoring
for excavation support to complex subterranean reinforce-
ment for permanent stabilization of deep cuts and slopes. When exca-
vations are planned near existing structures, Hayward Baker can
employ underpinning techniques to support the adjacent structures.
Better equipment, use of the latest soil and rock anchoring techniques,
and innovative use of soil nailing allow cost-effective and safe support
of excavations as well as slope stability control. The innovative use of
micropiles, often in combination with anchors, to construct walls hasproven to be a valuable tool for increasing the factor of safety of land-
slide prone areas.
Crucial to the successful use of these technologies is a thorough un-
derstanding of geotechnical engineering as well as the structural
mechanics of the retention system itself. That is why Hayward Baker
should be the first company that you call. We are highly experienced
in earth retention and are able to apply this experience to complex
soil-structure interaction projects.
Hayward Bakerprovides the widestrange of earth retentionoptions to give you acost-saving design.
Above: Working at an elevation of 7,500 feet,
Hayward Baker installed 2,200 linear wall
feet of 20-foot exposed height soldier pile and
lagging wall in the most unstable sloughing-
prone section along a gas field access road
near Parachute, CO. The project included a
total of 350 soldier piles, 175 (200-kip)
ground anchors, and 44,000 square feet of
permanent wood lagging.
Right: This 120-foot-diameter drilled secant
pile shaft provided earth retention for the
construction of a new pump station in
Austell, GA. Piles were 36-inch-diameter
and up to 55 feet deep.
O
-
8/18/2019 Earth Retention Brochure
2/12
Ground AnchorsGround anchors transfer loads
using grouted thread bars or
strand tendons connected to a
structure and bonding into sta-
ble soil or rock. These projects
are typically for retaining walls,temporary shoring, or other
grade separation requirements.
Hayward Baker incorporates ground anchors into
structural walls for additional support when required.
Other applications include landslide stabilization, re-
sistance of overturning, support of excavations, ma-
rine bulkheads, and resistance of vertical uplift.
Ground anchors offer a cost-effective solution for ei-
ther temporary or permanent applications.
Technique
Drill hole.
Insert thread bar or strand tendon.
Grout in place.
Extract casing (if used).
Connect anchor head to structure face.
Post-tension.
Geotechnical ConsiderationsSuitable soil or rock in which to bond the anchors be-
yond any instability on failure plane must be identified.
ayward Baker provides design-build solutions using retaining
walls consisting of soldier piles with lagging, sheet piles, secant
piles, tangent piles, and diaphragm walls. The structural mem-
bers resist lateral pressures from the retained soil and adjacent structures
and prevent soil raveling. Ground anchors or bracing can be incorporated
into the design for additional lateral support. The anchors transfer latera
loads from earth pressures and adjacent structures into competent zones
of soil or rock behind the potential failure plane of the retained soil.
CantileverCantilever walls provide lateral earth support solely by the bending and
shear strength of the wall and by passive resistance of the soil in which
the wall’s vertical elements are embedded.
Braced and AnchoredInternally braced lateral support can be provided by bracing with rakers
into the excavation base to deadmen or by bracing with struts between ad
jacent walls.
Anchored walls resist lateral forces by incorporating ground anchors. The
face of the wall may consist of soldier piles and lagging, sheet piles, secant
piles, tangent piles, or a diaphragm wall. The anchors may be installed as
coupled bars or coiled strands to minimize access requirements.
Applications of Braced and Anchored Walls When lateral earth pressures are high and/or minimal passive soil
resistance is available.
Wall heights exceeding 12 to 15 feet in most soil types.
Limiting wall deflection and ground movement behind the wall
is critical.
Design Considerations Consider soil conditions and temporary and permanent water tables
when selecting wall types.
Design wall and lateral support for allowable deflection, especially if
adjacent structures or utilities are present.
Structural Retaining Walls
H
Design/BuildHayward Baker offers complete design-build serv-
ices for all of our earth retention systems. Ad-
vanced 3D modeling software assists with efficient
design on the complex projects, enabling avoid-
ance of subsurface conflicts between existing or
planned structures.
3D CAD modeling was undertaken to avoid conflicts between soldier
piles, grouted tiebacks, soil nails, and existing active utilities at the
Calumet Water Reclamation Plant in Chicago, IL.
Internally braced
sheeting to allow for
construction of the
10,000-cubic-yard
concrete Trump
Tower elevator
core at the Trump
International Hotel
& Tower, Chicago, IL.
-
8/18/2019 Earth Retention Brochure
3/12
Hayward Baker installed an anchored soldier pile and lagging wall for excavation
support for construction of the new Ernie Davis Hall at Syracuse University inSyracuse, NY.
Jet grouting created this internally braced secant pile wall for a WWTP addition
in Providence, RI.
Hayward Baker installed four levels of permanent ground anchors to support a
diaphragm wall excavation for the construction of the Elm Road Generation
Station Pump House in Oak Creek, WI.
Consider if wall will be a part of the permanent structure
when selecting type and corrosion protection.
Consider global stability, as with all walls.
Technique
Soldier Piles & Lagging Drive steel H-sections or pipe piles
with a vibratory or impact hammer,
or insert into predrilled holes along
planned excavation limits.
Insert timber, concrete, or steel lagging
between piles as excavation proceeds.
Sheet Pile Walls Drive with a vibratory or impact
hammer or press interlocking steel
sheets along panned excavation limits
or seawall alignment.
Secant or Tangent Pile Walls Install overlapping or adjacent drilled
shafts, jet grouted soilcrete or soil mix
columns, or augercast piles along
excavation limits.
Stiff walls.
Structural Slurry Walls Excavate slurry-filled trench.
Upon reaching design depth, replace
slurry with reinforced concrete.
Stiff walls.
Generally offered through our sister
company, Case Foundation Company.
Advantages Speedy excavation for project schedule acceleration.
Effective in wide variety of subsurface conditions and
work environments.
Sheet pile, secant pile, and structural slurry walls provide
ground water control.
Variety of systems can be installed without vibration.
PLANNED EXCAVATION
PLANNED EXCAVATION
-
8/18/2019 Earth Retention Brochure
4/12
4
Grouted Soil Walls
routed soil walls are created by cementing soil particles together
in situ. Excavation can proceed once the grouted soil has cured
sufficiently. Grouted soils can be formed beneath existing foun-
dations to provide underpinning as well as excavation support.
The two primary methods of creating grouted soil walls are jet grouting and
soil mixing. These methods mix the binder and soil in situ to create soilcrete.
Permeation grouting can also be used to inject chemical grout or cement
grout into soils. All of these methods are suitable for vibration-sensitive sites.
Applications
Jet Grouting, Permeation Grouting When internal bracing is able to be avoided, it speeds up the
excavation process. Restricted access construction, inside and outside.
Grouting around in situ obstructions.
Underpinning structures adjacent to excavations.
Enhance or complete other retention systems where utilities
interfere with their installation.
Jet Grouting, Soil Mixing When internal bracing is able to be avoided, it speeds up the
excavation process.
Increase slope stability.
Mitigate lateral spreading.
Construct rings of columns that support access shafts, once excavated.
When the columns toe into an impermeable layer or when a jet
grout bottom seal is constructed, ground water control is provided
so excavation can be completed in the “dry.”
Design ConsiderationsWith each soil wall grouting technique, care must be taken when laying
out the mixing and injection locations to ensure that the required soil-
crete geometry is achieved.
Ground anchors or internal bracing can be incorporated into grouted wallsif required, for lateral support.
Jet Grouting and Soil Mixing Can be performed in most soils.
Soil gradation affects binder selection and dosage as well as final
soilcrete strength.
A laboratory mix design using the soil from the site is often
performed prior to final soil mix design.
Permeation Grout Can only be used in granular soils with low fines content.
Jet grouting underpinned and provided earth retention for this wall at the
Bayer Healthcare facility in Walpole, MA.
This soil mix column and soldier pile retaining wall was constructed within
one foot of a reclaimed water line to facilitate construction of a new turning
lane near a strip mall in Davenport, FL.
Jet grouting was used to
create access shafts for the
construction of a new water
treatment plant in Frankfort,
KY (right), and for a storm
sewer relief tunnel project in
St. Louis, MO (below).
-
8/18/2019 Earth Retention Brochure
5/12
Techniques
Jet Grouting High-velocity jets erode and blend in situ
soils with grout slurry.
Process initiated at bottom of planned
column depth.
Consistent, uniform rotation and lifting.
Overlapped soilcrete columns form wall.
Wet Soil Mixing Advance drill rod while injecting cement
slurry grout through mixing paddles.
Overlapped soil mix columns form wall.
Trench Remixing Deep (TRD) Walls Innovative deep soil mixing method.
Uses vertical chainsaw-like mixing tool.
Simultaneously cut and mix in place without
open trench.
Creates high-quality wall up to 170 feet deep.
Operable where other methods would be
exceedingly difficult.
Permeation Grout Walls Grout injected into granular soils through
ports along sleeve port pipes for accurate
placement.
Grout cements the soil particles together.
Spheres of grouted soil overlap to create the
required geometry.
Advantages
Jet Grouting and Permeation Grouting
Effective and safe methods of direct underpinning of structuresand utilities.
Can double as earth retention/excavation support system.
Suitable for open or restricted access.
Targeted treatment of specific depth intervals possible.
No harmful vibrations imparted to surrounding structures.
Permeation grouting produces no appreciable waste.
Soil Mixing Suitable for nearly all soil types.
No harmful vibrations imparted to surrounding structures.
Above: The TRD machine
constructing a cutoff wall
within the Herbert Hoover
Dike surrounding Lake
Okeechobee in central
Florida. TRD soil mix
walls are also used for
excavation support.
Right: Jet grouting
provided permanent in
situ erosion mitigation
between conventional
drilled shafts along this
coastal seawall at
Vandenberg AFB, CA,
without disturbing the
geology or ecology.
A Hayward Baker engineer inspects a chemically grouted break-out that was
constructed prior to excavation of the tunnel access shaft for construction of
twin subway tunnels at the LACMTA Eastside Extension (Goldline) project
in Los Angeles, CA.
LANNED EXCAVATION
PLANNED EXCAVATION
-
8/18/2019 Earth Retention Brochure
6/12
6
oil nail walls utilize patterns of soil nails
installed across the face of a cut or a
slope to provide stabilization and earth
retention. Soil nails are passive, tension-resisting
steel elements installed in the ground to create a
reinforced soil mass that provides lateral support.
The completed wall face can follow the existing
curvature of the soil mass for an aesthetically
pleasing appearance.
Drainage systems are incorporated into the soil nailed wall, reducing
hydrostatic pressure and preventing saturation of the reinforced
ground. Drainage systems often utilized are geotextile faced drain
board, drilled-in-place relief wells, and slotted plastic collection piping.
Surface drainage control above and behind the retaining wall is also
critical to the system.
Applications Embankment stabilization.
Temporary and permanent excavation support/retaining walls.
Where some movement can be tolerated.
Above the water table.
Retaining wall repair.
Design Considerations Suitable for firm clays, heterogeneous and stratified soils,weathered rock, and talus slope deposits.
Not practical in very soft clays, organics/peat, cohesionless
soils, low density and/or saturated soils, certain fills (rubble,
cinder, ash, etc.).
Since limited movement of the retained soil occurs during
excavation, consideration must be given to adjacent structures.
Drainage.
Installation Excavate 3 to 6 feet of soil.
Drill near-horizontal holes into exposed face, typically on
3- to 6-foot centers.
Place grout and steel bar.
Install drainage system on exposed face.
Install facing, typically reinforced shotcrete.
Fix bearing plates.
Repeat process until design wall depth is reached.
Apply second coating of shotcrete for aesthetics and corrosion
protection of permanent wall, if desired.
Soil Nail Walls
S
When the original segmental block retaining wall failed, Hayward Baker
constructed a soil nail and anchor remediation with an attached new
mechanically stabilized earth face preserving the look of the original wall, in
Tallahassee, FL.
Completed soil nail wall with shotcrete facing for temporary excavation
support at the Patewood Medical Center in Greenville, SC.
Advantages Cost effective.
Versatile.
Easily constructed over curved faces and in
restricted access.
Soil nails and shotcrete stabilized 5,000 square feet of a failing MSE wall behind apartment buildings in Owings Mills, MD.
-
8/18/2019 Earth Retention Brochure
7/12
Soil Nail Installation Sequence
Completed Soil Nail Walls
This 3,300-square-foot permanent shotcrete faced soil nail
wall was constructed on the property line to support a
sidewalk and highway immediately adjacent to the site of a
new drugstore in Dayton, TN.
1. Excavate 2. Drill 3. Insert nail and grout
4. Drainage board and reinforcement 5. Shotcrete, then repeat 1 through 5 This completed soil nail wall with shotcrete facing provided
permanent excavation support once faced with concrete for
the Dallas Cowboys Stadium in Arlington, TX.
This stained shotcrete facing over permanent
soil nails covered 14,000 square feet to
remediate failing timber cross-tie retaining
walls near residences in Atlanta, GA.
Soil nail wall covering 3,600 square feet to provide earth
retention for a new ramp for the Marquette Interchange in
Milwaukee, WI. Permanent concrete face was cast against the
soil nail wall.
-
8/18/2019 Earth Retention Brochure
8/12
8
nchored reaction block walls con-
sist of discrete, anchored concrete
blocks placed in a pattern on a slope
to increase the slope stability. The blocks
act with the soil to resist the movement of
the surrounding soil.
Applications Landslide stabilization.
Slope stability control.
Repair of damaged or failing retaining walls.
Design Considerations Identify failure plane location.
Identify suitable soil or rock for stable anchor bonding.
Determine anchor forces by calculating driving and
resisting forces by means of a global stability analysis.
The blocks are typically 5 feet by 5 feet to 12 feet by
12 feet, depending on the allowable bearing pressure of
the soils.
Depending on wall height, multiple rows of reaction
blocks at different elevations may be required.
TechniqueMultiple levels of anchored blocks are stepped to stabilize
slopes, or are installed across the face of existing retaining
walls for remediation.
Excavate along slope to facilitate equipment access,
if necessary.
Anchored Reaction Block Walls
Initially, a costly anchored sheet pile wall was designed to permanently stabilize this
250-foot-long, 50-foot-high cut slope in Montgomery, NY (top and above). Hayward
Baker designed and constructed a value-engineered alternative consisting of
43 anchored reaction blocks at three elevations for permanent stabilization.
Drilling high-capacity ground anchors through the reaction blocks at the US-61 South permanent slope stabilization project near Vicksburg, MS.
-
8/18/2019 Earth Retention Brochure
9/12
Place precast concrete or cast-in-place
reaction block.
Drill anchor hole, insert anchor tendon, and
grout anchor.
Tension anchor after grout cures.
Advantages Cost-saving solution for landslide repair and
slope stability control.
Can be designed for permanent or temporary
support.
Crane-mounted equipment can reach even the
most difficult access slopes.
Hayward Baker designed and constructed 354 anchored reaction blocks to repair
three failing MSE walls behind a shopping complex in Hoover, AL (above). Access
was via suspended drilling and work platforms (top). The tieback anchors
averaged 110 feet long, each with a design capacity of 300 kips.
Left and above: After a landslide closed US-6 in April 2008, the Colorado
DOT contracted Hayward Baker to repair the landslide and stabilize the
slope between I-70 and US-6. Hayward Baker installed 285 anchors, each
with a capacity of 140 kips with pre-cast anchor blocks on five bench levels.
The anchor work was completed almost a month ahead of schedule.
-
8/18/2019 Earth Retention Brochure
10/12
10
he micropile slide sta-
bilization system (MS³)
is typically a slope sta-
bilization system as opposed to
an excavation support system.
MS3 retains soil by connecting an
array of drilled and grouted mi-
cropiles, sometimes in combina-
tion with ground anchors, to a
reinforced concrete beam constructed near the
ground surface. Acting in tension and compression,
the micropiles effectively create an integral, stabilized
ground reinforcement system capable of resisting
driving forces in the slope that could otherwise cause
instability or failure.
Applications Landslide stabilization.
Side hill fill stabilization.
Ideal for sites with limited access and/or
restricted right-of-ways or creeping slopes,
such as with highway cuts and remediation.
Design Considerations
The wall should be placed near the midpointof the failing mass.
The landslide failure plane should typically
be less than 50 feet in depth.
Access required to reach the approximate
midpoint of the failing slope with personnel
and equipment.
Some walls may also require tieback anchors
to be installed and stressed against the
concrete cap if landslide forces are large.
Sequencing of pile and tieback installation
is important.
Micropile Slide Stabilization System (MS3 Walls)
T
Section view (above) of MS 3 walls Hayward Baker constructed to permanently repair a
300-foot-wide unstable soil mass extending from a section of Highway 26-89 down to
Snake River in Alpine, WY (top).
Hayward Baker constructed 300 linear feet of MS 3 wall to stabilize the slope behind this resort
development in Bridgetown, Barbados.
-
8/18/2019 Earth Retention Brochure
11/12
Technique Construct concrete beam near ground surface. While it
is typical to construct the concrete beam first, it may
also be constructed after micropile installation.
Drill angled micropiles in a fanned array through the
beam and into competent stratum.
Grout the micropiles.
Install ground anchors through concrete beam for
increased lateral resistance, if required.
Advantages Micropiles are constructible in any soil type.
Minimal excavation and environmental impact.
Visibility of finished MS³ wall is little to none.
Constructed without vibration.
Quality Assurance/ Quality ControlQuality control is an integral part of any HaywardBaker project.
Quality control begins with procedural inspection and
documentation. Installation location and inclination are
accurately performed, measured, and documented, as
well are injection volumes, rates, and pressures. In cer-
tain situations, proprietary equipment and software
allow for real-time monitoring of installation parame-
ters during construction.
Material testing may include grout, soilcrete, concrete,
or shotcrete samples collected on a regular basis for in-
dependent laboratory testing for strength, homogeneity,
or permeability if applicable. Corrosion protection of
steel elements ensures long-term performance of per-
manent works.
Anchor performance and proof testing follow industry
accepted Post-Tensioning Institute test criteria. All an-
chors are proof tested while selected anchors receive
performance tests. Micropile design capacities may be
verified by full-scale load testing on production piles or
on sacrificial test piles.
When required, inclinometers and optical surveys of
fixed targets are installed to monitor vertical and lat-
eral movements.
Hayward Baker designed and constructed this MS 3 wall for slope stability along
I-271 NB near Cleveland, OH. The wall is approximately 430 feet long with 345
micropiles and 35 anchors.
Anchor proof testing.
This MS 3 wall stabilized
a failing slope adjacent to
railroad tracks in San
Juan Capistrano, CA.
-
8/18/2019 Earth Retention Brochure
12/12
E A R T H R E T E N T I O N
Advantages of a Hayward BakerEarth Retention System
Full design/build service.
Suitable for restricted access.
Rapid mobilization.
Fast excavation for project
schedule acceleration.
Wide range of options results
in cost-effective design.
Temporary or permanent
systems available.
If required, Hayward Baker
can also provide a full range
of underpinning techniques.
Why Should You Choose Hayward Baker’s Earth Retention?As North America’s largest geotechnical con-
tractor, Hayward Baker has the resources to
build your project efficiently, and at a competi-
tive price. Our network of offices and full-ser-
vice equipment yards means fast mobilization
and reduced start-up costs. Our dedication to
quality control ensures that project specifica-
tions are achieved. We customize and design our
equipment and tooling, ensuring that perform-
ance and reliability are the best in the industry.
Hayward Baker has the experience and inno-
vation to assist engineers, contractors, and
owners with identifying, developing, and im-
plementing the best earth retention system,
whether the situation is typical or unique.
Hayward Baker Inc.
MarylandCorporate Office 410-551-8200
Bal timore 410-551-1980
CaliforniaLos Angeles 805-933-1331
San Francisco 925-825-5056
San Diego 760-839-2870
ColoradoDenver 303-469-1136
FloridaTampa 813-884-3441
Ft. Lauderdale 954-977-8117
GeorgiaAtlanta 770-442-1801
IllinoisChicago 630-339-4300
Minnesota
Minneapolis 952-851-5500MissouriSt. Louis 314-802-2920
New YorkNew York City 201-489-1700
Syracuse 315-834-6603
North CarolinaGreensboro 336-668-0884
Rhode IslandProvidence 401-334-2565
TennesseeKnoxvil le 865-583-8212
Nashv il le 615-883-6445
TexasDallas/Ft. Worth 817-753-7000
Houston 281-668-1870
WashingtonSeattle 206-223-1732
British ColumbiaVancouver 604-294-4845
OntarioToronto 800-925-6612
HB SubsidiaryCraig Olden, Inc. 800-422-4667
Website www.HaywardBaker.com
Email [email protected]
Hayward Baker Inc.A member of the Keller WorldwideGroup of Companies
© Hayward Baker Inc. 2009
Pub No: ER01
Downtown South Boston’s revitalization included construction of retail shops
with above apartments at Fan Pier. Hayward Baker designed, furnished, and
installed 940 linear feet of braced sheetpile earth support to retain a 40-foot cut
depth to facilitate the construction.
When this MSE wall at a copper mine in Morenci, AZ, failed, Hayward Baker
performed an emergency ground anchor program to stabiliz e the wall. A
combination of wire mesh and vertical whalers distributed the load to the anchors.