![Page 1: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/1.jpg)
BUILDING STRONG®
PUBLIC INFORMATION MEETINGApril 20, 2016
Johnsonburg, PA
US Army Corps of Engineers, Pittsburgh District
East Branch Dam Safety Modification Project
![Page 2: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/2.jpg)
BUILDING STRONG®
Meeting Agenda
2
• Opening Remarks – District Commander, Colonel Bernard R. LindstromWhat’s Done – Mike Rattay, Project ManagerConstruction Update – Kim Warner, East Branch
Resident EngineerEmergency Management– Mike McAllister, Elk County
Emergency Services Director & Jim Christ, Readiness Office East Branch Lake Facilities – Autumn Rodden, East
Branch Lake Resource ManagerQuestions
![Page 3: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/3.jpg)
BUILDING STRONG®3
FLOW
Soil
Rock
Grouted Cavity
Muddy Seepage Flowing from Rock Drain During Incident
WHAT’S DONE1957 Emergency Repair
Dam failure averted in 1957, but risk for re-initiation of internal erosion remains.
Untreated, Jointed Bedrock in Cutoff Trench Walls
![Page 4: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/4.jpg)
BUILDING STRONG®4
WHAT’S DONE• 1957 to 2008 – Monitor Dam
• 2008 to 2019 - Interim Risk Reduction
• 2008 to 2010 – Dam Safety Study
• 2010 to 2014 – Preconstruction, Engineering & Design
• 2011 - Initiate Construction
![Page 5: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/5.jpg)
BUILDING STRONG®5
WHAT’S DONESite Development Construction Contracts
![Page 6: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/6.jpg)
BUILDING STRONG®
WHAT’S DONEInstrumentation
• 2012 – Nine new Piezometers Installed• 2013 – Data Loggers Installation• 2013 - 2014 – Automated Data Acquisition and communicationsfor Critical Instruments
SIREN
WARNING BEACON
DataLogger
Green: within normal ranges
![Page 7: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/7.jpg)
BUILDING STRONG®7
WHAT’S DONECutoff Wall Design
![Page 8: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/8.jpg)
BUILDING STRONG®8
WHAT’S DONECutoff Wall Contract Award
• 26 Aug 2014 – Award made to Layne Christensen Company
Amount: $132,504,348
• 17 Sep 2014 – Notice To Proceed
1740 day Period of Performance
• 16 Sep 2015 – Contract Novation to Keller Walls, Inc.
• 04 Feb 2016 – Contractor’s Name Change to Bencor Global, Inc
![Page 9: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/9.jpg)
BUILDING STRONG®9
WHAT’S DONECutoff Wall Contract Status Update
17 Sep 2014 NTP 0 23-Jun-19 $132,504,348
14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001
20 Apr 2016 Public Meeting 26% 30-Jun-19 $135,511,185
DATE CONTRACT COST CONTRACT EARLY FINISH
CONTRACT % COMPLETE
![Page 10: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/10.jpg)
BUILDING STRONG®10
Bencor Global Inc.Frisco, TX
• Tim Myers
Director of Operations
• Jeff Garon
Project Manager
![Page 11: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/11.jpg)
BUILDING STRONG®
CONSTRUCTION UPDATE
11
![Page 12: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/12.jpg)
BUILDING STRONG®
• Instrumentation Automated & manual readings
• Visual Inspection Continued 24-hour government presence
• USACE & Contractor Emergency Action Plans
• Joint Instrumentation Monitoring Plan
• Data Management System
CONSTRUCTION UPDATEDam Safety Monitoring & Exercises
12
![Page 13: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/13.jpg)
BUILDING STRONG®
Support Area (~1 Acre)
Support Area (~1 Acre)
Support Area(~1 Acre) Vehicle
Turnaround
Work PlatformGrouting, Soil Mixing, Cutoff Construction
Overlook Parking Support Area
(~1.8 Acre)
Existing Boat Launch (~0.9 Acre)
16 Sep to 14 Apr
Support Area(~.7 Acre)
CONSTRUCTION UPDATEContractor Work Area Utilization
RE Office
Construction Access Government Road
Maple Lane
Campground
13
![Page 14: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/14.jpg)
BUILDING STRONG®14
CONSTRUCTION UPDATEIncreased Traffic
• Amount of traffic is dependent upon construction activity.
• Road Permits & Bonds will be in accordance with PennDOT and local requirements.
• As of 01 April: 13,912 Trucks for a total of 330,310 tons of stone delivered to the dam.
![Page 15: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/15.jpg)
BUILDING STRONG®
CONSTRUCTION UPDATEExploratory Holes / Drilling & Grouting
15
• Embankment• Rock
![Page 16: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/16.jpg)
BUILDING STRONG®
CONSTRUCTION UPDATERock Drills
16
![Page 17: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/17.jpg)
BUILDING STRONG®
CONSTRUCTION UPDATEPlatform Work
Bencor is working 2 shifts,6 days per week.
17
![Page 18: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/18.jpg)
BUILDING STRONG®
CONSTRUCTION UPDATEPlatform Work
Silos for Material Storage
18
![Page 19: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/19.jpg)
BUILDING STRONG®
CONSTRUCTION UPDATE
WHAT’S NEXT?
• Complete Slurry Ponds and Finish Platform Slab.• Complete Exploratory, Drilling & Grouting Operations.• Begin Cutoff Wall Test Sections
19
![Page 20: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/20.jpg)
BUILDING STRONG®
CONSTRUCTION UPDATE
Hydromill & Secant Pile Wall Test Sections20
CUTOFF WALL TEST SECTIONS
![Page 21: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/21.jpg)
BUILDING STRONG®
ECONOMIC IMPACTSPOSITIVES!
• Upgraded facilities at East Branch.• Local hiring.• Use of Local Contractors & Suppliers.• Housing Rentals, Hotels.• Restaurants, grocery, gas stations, etc.• Fuel & oil, machine parts, equipment rentals.• Road Repairs on SR 1001 and 1004.• East Branch Lake still contributes to flood protection,
fisheries and water quality benefits while under repair.• Once complete, the Lake will continue serving the
region in public safety, flood protection, recreation, and water quality for generations to come.
21
![Page 22: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/22.jpg)
BUILDING STRONG®
Glen Hazel
East Branch Dam
EMERGENCY MANAGEMENT
![Page 23: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/23.jpg)
BUILDING STRONG®23
EMERGENCY MANAGEMENT• Activities since last public meeting:• 21 Jan – USACE - Presentation to Elk County
Commissioner’s.• 4 Feb – USACE - Discussions with DOMTAR Corp. regarding
impact of Dam Failure to Johnsonburg facility.• 6 Feb – Elk County - Johnsonburg Press newspaper article on
Emergency Management presentation on the status of East Branch Lake Dam construction project.
• 18 Feb - East Branch Lake Dam – Dam Safety Fact Sheet finalized for distribution to public.
• 28 Feb – Elk County - Discussions with Sen Toomey’s staff on the need for East Branch NWS Warning Systems funding.
• 28 Feb – Elk County - PENN DOT and Pennsylvania State Police meeting’s conducted.
![Page 24: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/24.jpg)
BUILDING STRONG®24
EMERGENCY MANAGEMENT
• Future Activities:• Warning Notification Systems determination: Sirens; NWS
Warning Radio; and or telephone notification system.
• Planning meeting with Jones, Johnsonburg, and Ridgway Emergency Managers.
• Creation of County and Twp. Emergency Action Plans for Dam Failure Emergency Notification and Evacuation.
• Exercising of above Emergency Action Plans.
![Page 25: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/25.jpg)
BUILDING STRONG®
EAST BRANCH LAKE FACILITIES 41 Site Campground
► Closed for Construction ► Electrical Upgrades coming soon!!
Overlook Day Use Area► Closed for Construction
Boat Launch & Parking Lot ► OPEN!!!!!!!!!!!!
Kilgus Road Canoe/Kayak Launch► Open year-round
Instanter Boat Launch Elk State Park► waiting on pool to rise
No public access across the dam.
25
![Page 26: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/26.jpg)
BUILDING STRONG®
EAST BRANCH LAKE FACILITIES
26
![Page 27: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/27.jpg)
BUILDING STRONG®
EAST BRANCH LAKE FACILITIESTraffic Control Measures/Install Barrier Float
27
1. STOP SIGN: top of hill intersection with access road
2. YIELD SIGN: near lower gate (traffic leaving the dam)
3. CAUTION SIGN: near upper gate
4. 10 MPH SIGN: before horseshoe curve
12
3-4
![Page 28: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/28.jpg)
BUILDING STRONG®
EAST BRANCH LAKE FACILITIESAlternatives to Closures:
28
Bendigo State Park Complex
Allegheny National Forest► Twin Lakes Campground► Cook Forest► Private campgrounds in the area
Other USACE facilities► Kinzua – Warren, PA► Tionesta – Tionesta, PA
![Page 29: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/29.jpg)
BUILDING STRONG®29
EAST BRANCH LAKE FACILITIESAuthorized Project Purposes
• FLOOD RISK REDUCTION
• LOW-FLOW AUGMENTATION
• WATER QUALITY
• FISH & WILDLIFE MANAGEMENT
• RECREATION
![Page 30: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/30.jpg)
BUILDING STRONG®30
![Page 31: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/31.jpg)
BUILDING STRONG®31
EAST BRANCH LAKE FACILITIESold steps to the boat docks
![Page 32: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/32.jpg)
BUILDING STRONG®32
EAST BRANCH LAKE FACILITIESnew steps to the boat docks
![Page 33: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/33.jpg)
BUILDING STRONG®33
LIMESTONE SAND TREATMENTS benefit lake water quality
![Page 34: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/34.jpg)
BUILDING STRONG®34
24/7 Dam Monitor spots a Spotted Salamander
![Page 35: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/35.jpg)
BUILDING STRONG®35
MACROINVERTEBRATE SURVEYS
![Page 36: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/36.jpg)
BUILDING STRONG®36
GILL NETTING SURVEYS
![Page 37: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/37.jpg)
BUILDING STRONG®37
24 nets set; 195 fish captured
Northern Pike► 33.8% of the total catch► 54 of the 66 pike, were of legal size► Largest - 32 inches 7.9 lbs
GILL NETTING SURVEYS
![Page 38: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/38.jpg)
BUILDING STRONG®38
NORTHERN PIKE – 32 INCHES 7.9 LBS
![Page 39: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/39.jpg)
BUILDING STRONG®39
24 nets set; 195 fish captured
White Sucker► 27.7% of the total catch► Mostly in the shallows spawning► Provide important forage for the
larger sport fish – Bass, Pike, Walleye
GILL NETTING SURVEYS
![Page 40: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/40.jpg)
BUILDING STRONG®40
24 nets set; 195 fish captured
Walleye 17.4% of the total catch► Total of 34 walleye sizes 17-25 inches► All legal size and in good health!
GILL NETTING SURVEYS
![Page 41: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/41.jpg)
BUILDING STRONG®41
FEMALE WALLEYE - 24 INCHES 4.6 LBS
![Page 42: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/42.jpg)
BUILDING STRONG®42
24 nets set; 195 fish captured
Other species captured with gill nets:► Rock Bass – 24► Smallmouth bass – 10 (all greater than 12 inches) ► Brook Trout – 5 ► Lake Trout – 2 ► Tiger Musky – 1► Yellow perch – 1
GILL NETTING SURVEYS
![Page 43: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/43.jpg)
BUILDING STRONG®43
SMALLMOUTH BASS – 17 INCHES 3 LBS
![Page 44: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/44.jpg)
BUILDING STRONG®44
LAKE TROUT – 27 INCHES 6.5 LBS
![Page 45: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/45.jpg)
BUILDING STRONG®45
TIGER MUSKY – 31 INCHES 5.9 LBS
![Page 46: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/46.jpg)
BUILDING STRONG®
Community Information SystemWebsites: www.lrp.usace.army.mil/Missions/Planning,ProgramsProjectManagement/HotProjects/EastBranchDamRepair
www.facebook.com/EastBranchLakeUSACE
CONTACT INFORMATIONEast Branch Dam OperationsAutumn RoddenEast Branch Resource Manager, 814.965.2065E-mail: [email protected]
East Branch Resident OfficeKim WarnerEast Branch Construction Office, 814.965.4750E-mail: [email protected]
Media and General InquiriesCarol DavisPublic Affairs, 412.395.7500 E-mail: [email protected]
46
![Page 47: East Branch Dam Safety Modification Project · 17 Sep 2014 NTP 0 23-Jun-19 $132,504,348 14 Oct 2015 Public Meeting 11% 23-Jun-19 $132,953,001 20 Apr 2016 Public Meeting 26% 30-Jun-19](https://reader036.vdocuments.net/reader036/viewer/2022071007/5fc48b099d874a1353265814/html5/thumbnails/47.jpg)
BUILDING STRONG®47
QUESTIONS ?