easygrants id: 39467 national fish and wildlife foundation ... · complex; (4) considered...

61
Easygrants ID: 39467 National Fish and Wildlife Foundation NFWF Project ID: 1401.13.039467 LI Sound Futures Fund 2013 - Planning All Types and Water Quality Monitoring - Submit Final Programmatic Report (New Metrics) Grantee Organization: National Wildlife Federation Project Title: Overcoming Barriers to Green Infrastructure Adoption (NY) Project Period 1/01/2014 - 2/28/2015 Project Location Description (from Proposal) Huntington/Northport Harbor Complex (Town of Huntington and Villages of Northport, Asharoken, and Huntington Bay). Project Summary (from Proposal) Use a collaborative planning process to identify and overcome barriers to the adoption of green infrastructure to reduce stormwater pollution into Northport/Huntington Harbor Complex. Summary of Accomplishments This project set out to fully understand why, in light of existing information and materials on the benefits and ways to incentivize and regulate the use of green infrastructure, the communities of the Northport/Huntington Harbor Complex are not integrating low impact development into land use planning activities. By conducting this project, we have achieved this primary objective by accomplishing the following: (1) provided a means to convene the Harbor Complex communities in a collaborative planning effort through workshops; (2) addressed and identified true barriers to broad-scale adoption of green infrastructure in Long Island; (3) developed a Green Infrastructure Action Agenda targeted for audiences within the Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as outlined in the Green Infrastructure Action Agenda; and (5) recommended a set of municipallyowned sites that are best-suited to serve as green infrastructure demonstration projects. By achieving these accomplishments, we have begun to catalyze the broader adoption of green infrastructure on Long Island. Lessons Learned As a brief summary, we had several areas of lessons learned during this project which NWF and CCE detail in the attached report narrative. These included: assumptions about perceived knowledge of green infrastructure; structuring workshops to be more participatory; extending the project to be more inclusive of the members of the community; providing incentives to participants; the need for the need for more representation from individual municipalities in inter-municipal agreements and inter-municipal councils; the value of connectivity as one municipality’s problem is also another municipality’s problem; the challenges municipalities face securing funding for green infrastructure; and also weather being a factor in our ability to schedule meetings and for maximum attendanceit was a cold, snowy winter in NYC and inclement weather was more of a challenge than we had anticipated.

Upload: others

Post on 30-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Easygrants ID: 39467 National Fish and Wildlife Foundation NFWF Project ID: 1401.13.039467

LI Sound Futures Fund 2013 - Planning All Types and Water Quality Monitoring - Submit Final Programmatic Report (New

Metrics)

Grantee Organization: National Wildlife Federation

Project Title: Overcoming Barriers to Green Infrastructure Adoption (NY)

Project Period 1/01/2014 - 2/28/2015

Project Location

Description

(from Proposal)

Huntington/Northport Harbor Complex (Town of Huntington and Villages of Northport, Asharoken,

and Huntington Bay).

Project

Summary (from

Proposal)

Use a collaborative planning process to identify and overcome barriers to the adoption of green

infrastructure to reduce stormwater pollution into Northport/Huntington Harbor Complex.

Summary of

Accomplishments This project set out to fully understand why, in light of existing information and materials on

the benefits and ways to incentivize and regulate the use of green infrastructure, the

communities of the Northport/Huntington Harbor Complex are not integrating low impact

development into land use planning activities. By conducting this project, we have achieved

this primary objective by accomplishing the following: (1) provided a means to convene the

Harbor Complex communities in a collaborative planning effort through workshops; (2)

addressed and identified true barriers to broad-scale adoption of green infrastructure in Long

Island; (3) developed a Green Infrastructure Action Agenda targeted for audiences within the

Complex; (4) considered modifications to codes, ordinances, and land use policies to

encourage LID techniques as outlined in the Green Infrastructure Action Agenda; and (5)

recommended a set of municipally–owned sites that are best-suited to serve as green

infrastructure demonstration projects. By achieving these accomplishments, we have begun to

catalyze the broader adoption of green infrastructure on Long Island.

Lessons Learned As a brief summary, we had several areas of lessons learned during this project which NWF

and CCE detail in the attached report narrative. These included: assumptions about perceived

knowledge of green infrastructure; structuring workshops to be more participatory; extending

the project to be more inclusive of the members of the community; providing incentives to

participants; the need for the need for more representation from individual municipalities in

inter-municipal agreements and inter-municipal councils; the value of connectivity as one

municipality’s problem is also another municipality’s problem; the challenges municipalities

face securing funding for green infrastructure; and also weather being a factor in our ability to

schedule meetings and for maximum attendance—it was a cold, snowy winter in NYC and

inclement weather was more of a challenge than we had anticipated.

Page 2: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Activities and Outcomes

Funding Strategy: Capacity, Outreach, Incentives

Activity / Outcome: LISFF - Outreach/ Education/ Technical Assistance - # gov’t entities participating

Description: Enter the number of municipalities or local governments participating in the project

Required: Recommended

Notes: Northport/Huntington Harbor complex, including the Town of Huntington, Villages of Asharoken,

Huntington Bay and Northport and the Suffolk County Planning Commission.

Funding Strategy: Capacity, Outreach, Incentives

Activity / Outcome: LISFF - Outreach/ Education/ Technical Assistance - # people reached

Description: Enter the number of people reached by outreach, training, or technical assistance activities

Required: Recommended

Notes: We will reach 60 people directly; 30 through in-person workshops, and another 30 for plan review and

feedback. In addition, CCE has 20,000 email members that will recieve the project results and NWF’s action

alerts reach over 20,000 members in NY.

Funding Strategy: Capacity, Outreach, Incentives

Activity / Outcome: LISFF - Outreach/ Education/ Technical Assistance - # people targeted

Description: Enter the number of people targeted by outreach, training, or technical assistance activities

Required: Recommended

Notes: This includes 30 workshop participants and another 20 people we will involve in the development of the

strategy document.

Funding Strategy: Capacity, Outreach, Incentives

Activity / Outcome: LISFF - Outreach/ Education/ Technical Assistance - # people with knowledge

Description: Enter the number of people demonstrating a minimum level of knowledge, attitudes, or skills

Required: Recommended

Notes: This includes 30 workshop participants and another 20 people we will involve in the development of the

strategy document.

Funding Strategy: Capacity, Outreach, Incentives

Activity / Outcome: LISFF - Outreach/ Education/ Technical Assistance - # workshops, webinars, meetings

Description: Enter the number of workshops, webinars, and meetings held to address project activity

Required: Recommended

# gov't entities participating - Current: 0.00

# gov't entities participating - Grant Completion: 5.00

# people reached - Current: 0.00

# people reached - Grant Completion: 40060

# people targeted - Current: 0.00

# people targeted - Grant Completion: 70

# people with knowledge - Current: 0.0

# people with knowledge - Grant Completion: 70

# workshops, webinars, meetings - Current: 0.00

# workshops, webinars, meetings - Grant Completion: 3.00

Page 3: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Notes: We will have formal two day meetings and one public meeting. There will be additional phone or in-

person meetings throughout the project as needed.

Funding Strategy: Planning, Research, Monitoring

Activity / Outcome: LISFF - Management or Governance Planning - # plans developed

Description: Enter the number of plans developed that had input from multiple stakeholders

Required: Recommended

Notes:

# plans developed - Current: 0.00

# plans developed - Grant Completion: 1.00

Page 4: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

The following pages contain the uploaded documents, in the order shown below, as provided by the grantee:

Other Documents

Other Documents

Photos - Jpeg

Photos - Jpeg

Photos - Jpeg

Other Documents

Other Documents

Other Documents

Other Documents

Other Documents

Final Report Narrative - Standard

The following uploads do not have the same headers and footers as the previous sections of this document in order to

preserve the integrity of the actual files uploaded.

Page 5: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Final Programmatic Report Narrative

Instructions: Save this document on your computer and complete the narrative in the format provided. The final

narrative should not exceed ten (10) pages; do not delete the text provided below. Once complete, upload this document

into the on-line final programmatic report task as instructed.

1. Summary of Accomplishments

In four to five sentences, provide a brief summary of the project’s key accomplishments and outcomes that were observed

or measured.

This project set out to fully understand why, in light of existing information and materials on the benefits and ways to

incentivize and regulate the use of green infrastructure, the communities of the Northport/Huntington Harbor Complex are

not integrating low impact development into land use planning activities. By conducting this project, we have achieved

this primary objective by accomplishing the following: (1) provided a means to convene the Harbor Complex

communities in a collaborative planning effort through workshops; (2) addressed and identified true barriers to broad-

scale adoption of green infrastructure in Long Island; (3) developed a Green Infrastructure Action Agenda targeted for

audiences within the Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID

techniques as outlined in the Green Infrastructure Action Agenda; and (5) recommended a set of municipally–owned sites

that are best-suited to serve as green infrastructure demonstration projects. By achieving these accomplishments, we have

begun to catalyze the broader adoption of green infrastructure on Long Island.

2. Project Activities & Outcomes

Activities

Describe and quantify (using the approved metrics referenced in your grant agreement) the primary

activities conducted during this grant.

Activity 1: Convene project team and establish regular check-in calls/meetings.

Observed: Project team was convened and regular check-in calls/meetings were held on a weekly basis.

Activity 2: Design survey questions and conduct pre-interviews with Suffolk County Planning Department

and/or Planning Commissioners.

Observed: Survey questions were designed and provided to the members of the Suffolk County Planning

Commission and/or Planning Commissioners as part of pre-interviews before the first workshop. Questions

were designed to gather first-hand information from local and county planning commission members,

municipal leaders, and highway leaders on what they perceived to be the barriers to green infrastructure

implementation, current green infrastructure projects, local codes and ordinances, and potential demonstration

sites.

Activity 3: Conduct survey.

Observed: Survey questions were provided to a total of 14 individuals representing the town of Huntington

and villages of Northport, Ashroken, Huntington Bay, as well as Suffolk County.

Activity 4: Analyze and compile survey results.

Observed: Survey responses were compiled into an excel matrix. All responses were input per question and

organized via towns/village and municipality. Please see attached results.

Activity 5: Work with facilitator to use survey results to develop workshop agenda.

Observed: All partners worked with the project facilitator to use the survey results to inform our formulation

of the first workshop’s agenda. Results were also used to assess the strengths, weaknesses, opportunities, and

threats that communities are facing with regard to the broad-scale adoption of green infrastructure.

Page 6: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Activity 6: Assemble attendee list, send invitations.

Observed: Workshop attendee list was assembled and invitations sent to members of the Suffolk County

Planning Commission and Planning Commissioners from municipalities and communities within the

Northport/ Huntington Harbor Complex. In addition, we extended invitations to local developers, NGOs,

universities, and others to participate in the workshop.

Activity 7: Host workshop.

Observed: The first project workshop was held on June 16, 2014 at the Northport Public Library. This

workshop included various presentations and discussions.

Activity 8: Work with facilitator to analyze results.

Observed: Partners collaborated with facilitator to analyze results based off of feedback collected and notes

taken during the workshop. Key issues that were discussed during this work were included in this summary.

Activity 9: Research potential Low Impact Development (LID) demonstration sites.

Observed: Potential LID demonstration sites were researched and identified in preparation for the second

workshop. Maps were then created to depict specific geographic areas, which includes various potential

demonstration sites that would then be identified. These maps were created via ArcGIS/ArcMap and included

the Town of Huntington, Village of Asharoken, Village of Harbor Bay, and Village of Northport.

Activity 10: Based on findings, draft guidance document, Managing Stormwater: Natural Vegetation and

Green Methodologies Guidance for Municipalities and Developers.

Observed: Findings and results from the first workshop and survey questions were summarized and used to

develop the draft guidance document, and the Green Infrastructure Action Agenda, detailing the barriers to

green infrastructure adoption.

Activity 11: Interviews and follow-up as needed to inform draft.

Observed: Follow-up with workshop participants were conducted to gather information pertaining to potential

LID demonstration sites.

Activity 12: Gather results of early feedback ahead of next meeting.

Observed: Results and feedback were collected to inform the agenda and program for the second workshop.

Activity 13: Host second project workshop to review draft plan and collect feedback.

Observed: Hosted second workshop on October 9, 2014, at the Unitarian Universalist Fellowship of

Huntington, Social Hall in Huntington, NY. Agenda included reviewing and presenting the draft guidance

document, presentations, and break out groups to discuss potential LID demonstration sites. NWF & CCE

also received additional feedback on the draft document, including review by the Suffolk County Planning

Commission, the EPA, and local municipal officials in the Huntington area. During the course of the design

charrette, we encouraged local agencies to commit to installing green infrastructure demonstration projects.

During that charette several types of sites were identified as potential areas to use green infrastructure. This

included town and private beaches, parking lots along the harbor, Main Street parking lots and businesses (for

green roofs). As a result, in part, of project activities, the Town of Huntington is developing engineering plans

for a green infrastructure project at Centerport Beach. This was one of the sites community members

identified at the charette. The Town is currently looking to secure funds for the project and have committed

town funds of 50% towards it. We also worked closely with municipal leaders, stakeholders, and members of

the community to develop the plan, including the action agenda and site specific projects. This all helped

develop municipal buy-in to the plan.

Activity 14: Assemble invite list, send invitations for public meeting.

Observed: Invite list was assembled and sent for attendance at the public meeting.

Activity 15: Hold public meeting.

Observed: Held public meeting at the Suffolk County Legislative Building on February 5, 2015 in

Hauppauge, NY. Presentations were provided on topics relating to various types of green infrastructure,

funding opportunities, local programs, and potential demonstration sites. The meeting was opened with

Page 7: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

welcoming remarks from two legislators and members of the Suffolk County Planning Commission, one of

which was Chairman David Calone. Approximately 40 individuals were in attendance.

Activity 16: Use workshop findings to revise plan and broadly disseminate.

Observed: Findings and results were used to inform and make final revisions to the Green Infrastructure

Guidance document and Green Infrastructure Action Agenda. This document was subsequently adopted by

the Suffolk County Planning Commission and broadly disseminated by the Suffolk County Planning

Commission to all local municipalities and local planning boards. It was also disseminated to the public via

CCE’s website, Facebook page, and Twitter account.

Briefly explain discrepancies between the activities conducted during the grant and the activities

agreed upon in your grant agreement.

Activity 6: Assemble attendee list, send invitations.

Explanation: We extended invitations to the workshops beyond just the members of the Suffolk County

Planning Commission, local planning boards and Huntington/Northport municipal officials to gain additional

insight on the barriers related to these communities within the Complex and gain additional feedback on the

Action Agenda. We also included developers, which we had not anticipated doing at first. After the first

workshop we partnered with the Suffolk County Planning Commission. This allowed us to reach all Suffolk

County Long Island Sound municipalities, while still being able to produce a local action agenda, specific to

the Northport Huntington Harbor region. The end product was official adopted by the Suffolk County

Planning Commission and is now used as a guidance document for all projects within the LIS watershed that

goes in front of the Suffolk County Planning Commission. This scope went beyond what we had originally

promised and produced a more widely used document.

Outcomes

Describe and quantify progress towards achieving the project outcomes described in your grant

agreement. (Quantify using the approved metrics referenced in your grant agreement or by using more

relevant metrics not included in the application.)

Outcome 1: Number of municipalities or local governments participating in the project

Anticipated: 5

Observed: 5

Outcome 2: Number of people reached by outreach, training, or technical assistance activities

Anticipated: 40,060

Observed: At least 40,600, based on the following estimates: CCE’s website generates approximately 5,000

new hits per week and they have 4,000 fans on Facebook, and 1,500 Twitter followers. We also have a

database of over 20,000 email members. CCE posted the action agenda on its website, emailed it to their

listserve of 20,000 members, and posted in on social media. In addition, The Suffolk County Planning

Commission distributed the document to all Long Island Sound municipalities within Suffolk County and

printed 150 hard copies that were distributed to members of the public.

Outcome 3: Number of people targeted by outreach, training, or technical assistance activities

Anticipated: 50

Observed: Because of the additional targeted outreach by Suffolk County, we believe at least 200 were

targeted.

Outcome 4: Number of people demonstrating a minimum level of knowledge, attitudes, or skills

Anticipated: 50

Observed: 70

Outcome 5: Number of workshops, webinars, and meeting held to address project activity

Anticipated: 3

Observed: We held three workshops as discussed above. Please see attached meeting materials.

Page 8: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Outcome 6: Number of plans developed that had input from multiple stakeholders

Anticipated: 1

Observed: We produced one plan, MANAGING STORMWATER: Natural Vegetation and Green

Methodologies Guidance for Municipalities and Developers V.2.0 (attached). This plan included an Action

Agenda that was specific to the Northport/Huntington harbor region.

Briefly explain discrepancies between what actually happened compared to what was anticipated to

happen.

Outcome 4: Number of people demonstrating a minimum level of knowledge, attitudes, or skills

Anticipated: 50

Discrepancy: Our original goal of 50 people demonstrating a minimum level of knowledge, attitudes, or skills

pertaining to the adoption of green infrastructure was exceeded with 70 individuals participating in the

workshops and public meetings.

Provide any further information (such as unexpected outcomes) important for understanding project

activities and outcome results.

Outcome 6: Number of plans developed that had input from multiple stakeholders

Discrepancy: We had not originally planned to create a Guidance Document that went geographically beyond

the Huntington area, but saw an opportunity to partner with Suffolk County Planning Commission and

ultimately created a product that goes even further than we had promised, while still being able to create a

local Action Agenda, which is based on community and municipal feedback we received in the workshops.

Through our ongoing conversations with the Town of Huntington, we know that are in the process of working

to implement some of the action agenda’s recommendations.

3. Lessons Learned

Describe the key lessons learned from this project, such as the least and most effective conservation practices or

notable aspects of the project’s methods, monitoring, or results. How could other conservation organizations adapt

their projects to build upon some of these key lessons about what worked best and what did not?

Perceived Knowledge of Green Infrastructure – At the beginning of this project, it was assumed that there was an

adequate baseline of knowledge and understanding about green infrastructure. Yet, upon administering our preliminary

survey questions to the members of the Suffolk County Planning Commission and Planning Commissioners, we quickly

found that many of the technical questions were difficult for many of the members to answer (e.g. What is green

infrastructure? What are the costs and benefits? When can green infrastructure be implemented?). For this reason, it was

decided to focus the first workshop on more of a “Green Infrastructure 101” session, where details relating to cost,

benefits, and types of green infrastructure were outlined and presented. We learned that not everyone participating in a

project such as this will have a same level of knowledge about the subject matter.

Participation – As follow-up, the second workshop was designed as a charrette-style brainstorming session where

attendees were presented with further costs/benefits, available financial incentives, local ordinances pertaining to their

communities, and maps of various locations meant to depict potential LID demonstration sites. By conducting this style of

participatory workshop, we learned that providing the attendees with these maps and dividing them into various

roundtables allowed for more interactive and productive discussions, both within and among the groups. Organizing in

this manner allowed for optimal brainstorming, collaboration, and a general sense of comradery amongst the different

municipalities.

Additional Outreach – We originally planned to only involve individuals who were official members of the municipalities

and commissions, yet decided to reach out to those beyond just city staff to include workshops included local citizens,

stakeholders, developers, and technology companies. We found this to be very beneficial and provided a lot of great input

during our workshop discussions and added valuable insight and information for the Guidance document and Action

Agenda.

Page 9: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Incentives are Important – Incentives are important to motivate people. It was found that even when information is readily

available, people still need to be motivated to widely adopt green infrastructure. Example incentives for green roofs could

include easing parking requirements (zoning regulations) or abatement on sanitary bills.

Representation – As part of our second workshop, we divided participants into various groups by town and/or village. The

participants included both stakeholders and those that actually lived in the communities within the Northport/Huntington

Harbor Complex. We found that inviting these individuals and breaking them up into various groups created an

environment for very productive discussions and provided critical insight into the most important barriers facing their

communities. A major lesson learned during this process was the need for more representation from individual

municipalities in inter-municipal agreements and inter-municipal councils where representatives could work together to

address many of these barriers to green infrastructure implementation. For example, the Oyster Bay/Cold Spring Harbor

committee is looking for more representation from people in the Huntington-Harbor region.

Support for Funding – While inter-municipal groups are looking for more representation from individual municipalities,

there is also a need for support from these groups to aid communities in seeking funding for green infrastructure projects.

Based on information provided by workshop participants, we learned that funding is a serious challenge with many of the

municipalities and needs to be addressed. Inter-municipal groups can play a huge and vital role in seeking, applying, and

securing funding. The villages and towns that reside within this Complex lack sufficient staff and resources to even

prepare grant proposals and applications, not to mention providing matching funds if they were to be awarded with a

grant. We also learned that these inter-municipal groups not only have the ability, but currently want to act in this type of

role for the municipalities. This relationship needs to be facilitated and formulized.

Weather – NWF and CCE were excited to partner with the Suffolk County Planning Commission during this project. This

allowed us to broaden our reach within Long Island Sound communities and to utilize the expertise of planning

commission members, who gave input into the content of the Action Agenda. Through this process, we learned that

holding a public meeting with the Suffolk County Planning Commission in February proved to be challenging due

inclement weather conditions. There was a significant decrease in attendance due to the threat and potential snow storm

which wreaked havoc on the Northeast last winter. We had over 70 participants pre-registered for the event, but with the

threat of a snowstorm only 40 attended. While timing for the meeting was based on the availability of the members of the

planning commission, and completion of the Guidance document, we would be hesitant to hold a public meeting in

February again.

Connectivity – Every participant and attendee of the survey, workshops, and public meetings were individually selected to

act as representatives of each municipality within the Northport/Huntington Harbor Complex. Yet these workshops and

meetings provided a venue for a collaborative effort in which the municipalities had to work together in order to identify

potential LID demonstration sites and provide insight into many of the barriers of adopting green infrastructure. Their

participation and collaboration provided one of most important lessons learned pertaining to the idea of connectivity. We

learned that individually, municipalities would not be able to understand and identify all of the challenges, barriers, and

subsequently, potential opportunities and solutions to these barriers. But by working and brainstorming together, they

were able to see existing and potential green infrastructure projects interconnect and aid in mitigating many of the

Complex’s stormwater issues. The theme of connectivity is important because one municipality’s problem is also another

municipality’s problem, especially in terms of environmental quality. By the same logic, this theme also applies to

potential solutions. The need for collaboration becomes imperative.

4. Dissemination

Briefly identify any dissemination of lessons learned or other project results to external audiences, such as the

public or other conservation organizations.

CCE has uploaded and posted a PDF version of the Action Agenda to their website. They have also emailed the guidance

document through their listerve and have posted it to their Facebook and Twitter accounts. CCE’s website generates

approximately 5,000 new hits per week. They have over 4,000 fans on Facebook and 1,500 followers on Twitter. The

Suffolk County Planning Commission has also distributed the document to all Long Island Sound municipalities within

Suffolk County. The County has printed 150 hard copies of the guide that we distributed to members of public.

Page 10: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as
Page 11: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as
Page 12: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as
Page 13: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Green Infrastructure Survey Town of Huntington Village of Northport

Town of Huntington--

Highway Superintendent

Phone Interview with Damon personal interview with peter

1. What to you perceive as the biggest barriers to

GI in your community

Northport is very built up, there is not

a lot of new development.

Pushback from local development

Yes, there is pushback from developers because of

the cost. Yes

Lack of awareness by the development community

on the benefits

Comes down to pre-cast structure vs. bio-retention,

developer wants easy, cheap pre-cast structure. Yes

lack of understanding about the benefits and

application of GI

there should be more public awareness, there is

lack of understanding by the public on the benefits

of GI

Yes--not a lot of awareness in

community, need more education Yes

Lack of education/technical expertise

Yes* (seemed to lack a clear

understanding of GI.)

Yes--He is new and lacks the

education and technical

expertise, but he is willingly and

open to learn.

Lack of resources

We have the engineering capability, but not always

the money to implement the project. We do

consider GI in new capital projects. Concerned about who pays

2. Are there any current projects/proposals in your

community that use GI Yes, Coral Park

NO. They did not use permeable

pavement when they re-did walkways

in village park because of cost, hard to

get product, does not last as long.

unknown--He is new and doesn't

know of any.

provide brief description Just put in two bio-swales.

How have they been successful

is there public ed component

Not yet, but they are considering signage. The

conservation board is also looking to develop a

welcome packet for new homeowners that includes

the environmental regulations in the town.

is there staff training

Other Projects

a. A new Huntington Hotel is looking at putting in a

green roof. B. Town installed a new rain garden by

train station. There is currently no signage. C.

Town installed a new rain garden by the bridge D.

Sweet Hollow Park is looking at using a gravel

parking lot. E. Town installed 2-3 new Vortex

separators F-NYS DOT improvement project--might

have done a surface sand filter on RT 110

3. Do you incorporate GI into your public spaces,

right-a-ways, or municipal parking?

The town does try to incorporate GI in new

projects, if funding available. The town has an open

space program, which dedicates monies to

neighborhood enhancements. Money can be used

for GI

No, there was one code change that

mandated homeowners to capture

run-off from there driveways when

they re-pave.

The Highway Department is

responsible for roadways,

sidewalks, and right-of-ways.

They follow state regulations,

not town code.

4. Do you require new development to incorporate

GI?

Commercial buildings have to attain LEED

certification is they are over 4,000 sq ft. This could

include GI, but the town does not require it.

Commercial sites also need to design for 3 inches of

stormwater--this usually leads to pre-cast drainage

or leeching pools. NO

State regulations do not require

it so they do not incorporate it

into new projects.

5. Have you changed your codes to encourage the

use of GI?

No, but GI is supported in our comprehensive plan.

The DEC requires that new SPDES permits need to

treat a certain % in pre-treatment. NO No

6. We plan to host a GI workshop--what issues

would you like us to address to help you implement

GI projects?

a- Developer perspective: How do we engage

developers? How do we talk to people that have

been doing it the same way for years? B-Grass--

opportunities that might be available. C-New

Resources that might be available for projects D-

How can projects be cost-efficient? E-Homeowner

component, what can people do? How will it help?

We need a clearer understanding of

GI. Need funding. There workers

comp went up 26%, they have state

mandates, they do not have any extra

funds for maintentence. Education--what is available

7. Please identify a specific site in your municipality

that would be a good demo site for GI?

a. Working on bio-retention project in Gerard St.

Parking lot. The project would pre-treat

stormwater. B. Armory--might be good site for

green roof C-Look at Crab Meadow watershed D-

Catch basin inserts for Eaton's Neck doesn't know.

Interesting in pursuing catch

basin filters with water quality

committee. Need to figure out

funding to do so. Also

interested in closing off

stormawater drains and re-

directing stormwater into a

leeching field

Page 14: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Plannning Board members

Adrienne Esposito, Vice Chair

Suffolk County Planning

Commission

Dave Calone, Chair Suffolk

County Planning Commission

Sarah Lansdale, Suffolk County

Planning Department

Rich Boziwick, Village of Northport

Planning Chair

*The Village Planning board can make

recommendations to the Village of

Northport for code changes. He would like

to kept in the loop on the project.

1. Are you seeing an increase use of GI in

development proposals? Yes, a little bit Yes Yes

2. What types of projects do you see?

permeable pavement, bio-swales,

rain gardens. The Suffolk County

planning commission sees projects

of regional signifinance.

mostly rain gardens, bio-swlaes,

some permeable pavement, no green

roofs

they mostly see applications for residential

homes. Applications coming in use more

efficient building materials, and the

landscaping is more in line with less run-off

3. Do you require all projects to incorporate

GI? Are their incentives to include?

No. It is recommended but not

required. They have developed a

guiding document that is

recommended to every proposal

that goes to the planning

department and planning

commission

There is no specific requirement, just

recommendations. No current

incentives

No, the project must meet the Village code.

They can recommend that the project use

GI, but can not mandate. The codes are

always one step behind. More muncipal

education is needed. They need to

incorporate GI into codes. They have some

pro-active aritects. If the project does not

meet codes, it must go through zoning

board.

4. Why do you feel developers are not

embracing and utilizing GI?

Lack of knowledge and lack of

mandates.

There needs to be a carrot/stick

approach--there should be

requirements for use of such

technology. Villages will reach out to

the County when they need

assistance, but they haven't reached

out on this. The County will be

testing innovative septic system at

Northport Yacht Club.

Money--dollars and cents. If project is

more money upfront, client is apt to not

take recommendations.

Page 15: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Contact Affliation Email phone

Margo Myles Town of Huntington, Planning & Environment [email protected]

Joy Squires EOSPA [email protected]

Damon McMullen Village of Northport [email protected] (631) 261-7502

Theresa Kingsley Town of Huntington, Sustainability officer [email protected] (631) 351-3191

Philip Ingerman

Town of Huntington, Director of Intergovernmental

Relations [email protected]

Nicholas Jimenez

Town of Huntington, Department of Engineering

Services [email protected]

Joseph Cline

Town of Huntington, Department of Engineering

Services, Director [email protected]

Mayor Greg Letica Village of Ashroken [email protected] 631-261-7098

Mayor Herb Morrow Village of Huntinton Bay [email protected] 631-427-2843

Adrienne Esposito Suffolk County Planning Commissioner [email protected] 516-390-7150

Sarah Lansdale Suffolk County Department of Planning [email protected] 631-853-5191

Dave Calone Chair-Suffolk County Planning Commission [email protected]

Peter Gunther Town of Huntington, Highway Superintendant [email protected] 631-499-0444)

Rich Boziwick Planning Board Chair, Village of Northport [email protected] 516-353-7198

Page 16: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Draft May 22,2104

Long Island Sound Green Infrastructure Workshop Northport Public Library, 151 Laurel Ave, Northport, NY 11768

June 16, 2014 Purpose

Create a baseline of understanding of Green Infrastructure.

Discuss opportunities and obstacles for promoting Green Infrastructure on Long Island. Agenda 12:30 Arrival, Lunch 1:00 Welcome and Introductions 1:15 Presentation: Introduction to Green Infrastructure

What is Green Infrastructure and why should we consider it on Long Island?

Examples of effective uses of Green Infrastructure

Costs and Benefits

Q&A 1:45 Presentation and Discussion: Potential Uses of Green Infrastructure

Opportunities and constraints specific to Long Island

Suffolk County Planning Commission’s Green Methodologies Guidance Document, David L. Calone, Chairman Suffolk County Planning Commission

Lindenhurst Library Project, Peter Ward

Additional speakers TBD

Q&A

Group discussion of opportunities and obstacles to Green Infrastructure 2:45 Break 3:00 Table Conversations

Think about your communities and the types of situations where green infrastructure makes sense, what kind of projects would be beneficial to the community and the environment if modest resources were available?

3:45 Share Results of Table Conversations 4:00 Presentation: Resources to Make Green Infrastructure Work

Creating realistic policy

Creating incentives

Funding sources and approaches to affordability 4:15 Table Conversations

What actions and/or resources are needed for communities to give more serious attention to Green Infrastructure?

What are realistic next steps for communities to begin informing, promoting and incentivizing the use of Green Infrastructure?

Are there possible project sites that make sense to explore? 4:45 Share Results of Table Conversations 5:00 Adjourn

Page 17: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Copyright:© 2013 Esri, DeLorme, NAVTEQ, TomTom, Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community

A

Ü

Huntington #1

Page 18: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Draft 10/1/2104

Long Island Sound 2nd Green Infrastructure Workshop Unitarian Universalist Fellowship of Huntington, Social Hall

109 Browns Road, Huntington, NY 11743 October 9, 2014

Purpose

Provide an overview of the Draft Action Agenda and Guidance documents, which will focus on the ways in which Green Infrastructure (GI) can be used to reduce stormwater pollution in Long Island. Green Infrastructure includes rain gardens, green roofs, permeable paving, and other features.

Incorporate your feedback for a final document that will be publically released in December.

Agenda 8:30 Arrival, Coffee and light breakfast 9:00 Welcome and Introductions 9:15 Introduction and Overview of the Green Infrastructure Project

Purpose

What we have heard to date

Overview of what is in the document 9:30 Presentation and Discussion: Implementing Green Infrastructure on Long Island

Technical Considerations

Examples of successful policies and approaches

Sources of Funding

Examples of successful projects

Group discussion: What additional information or resources do we need to be able to take action? What else should be addressed in the action plan?

10:15 Break 10:30 Mini-Charrette: Applying Green Infrastructure at Huntington Harbor

Short Presentation on opportunities for Green infrastructure, locations and types of projects.

Small group activity to identify preferred locations, community desired activities, potential partnerships, and priorities for green infrastructure. Explore and discuss opportunities such as:

o Bigger tree boxes and green spaces o Permeable parking lots and pavements o Green roofs o Bioswales o Graywater projects o Food gardens.

11:45 Share Results of Green Infrastructure Mini-Charrette 12:00 Identify Next Steps and Adjourn

Page 19: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

1

Long Island Sound 2nd Green Infrastructure Workshop Unitarian Universalist Fellowship of Huntington, Social Hall

109 Browns Road, Huntington, NY 11743 October 9, 2014

DRAFT SUMMARY

I. Purpose of the Workshop

Provide an overview of the Draft Action Agenda and Guidance documents, which will focus on the ways in which Green Infrastructure (GI) can be used to reduce stormwater pollution in Long Island. Green Infrastructure includes rain gardens, green roofs, permeable paving, and other features.

Incorporate participant feedback into a final document that will be publically released in December.

II. Agenda Topics

Introduction and Overview of the Green Infrastructure Project

Purpose of the Green Infrastructure Project

Comments received to date

Overview of what is in the draft document

Technical Considerations

Examples of successful policies and approaches to Green infrastructure

Sources of Funding to Green infrastructure

Examples of green infrastructure products

Mini-Charrette: Applying Green Infrastructure in Local Communities

This small group activity discussed and identified preferred locations, community desired activities, potential partnerships, and priorities for green infrastructure in Huntington, Huntington Bay and Northport Village.

Page 20: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

2

III. Results of the Mini-Charette Group 1. Huntington A wide range of possible projects and locations were discussed:

Red’s Restaurant o Plans to put in one story apartment above the restaurant o Neighbor wants to put in solar panels, rain garden, etc (going to the site

plan, no official plans)

Old Town Hall o Currently a hotel o Putting in green roof o Circled in Orange

Several development projects going in with 2-3 story apartments, could be targets for GI

Gerard Street o Already installing bioswales; getting ready to plant

Municipal Parking Lots o Could mix permeable pavement with green spaces to maintain current

level of parking spaces o More cost-effective to rip up tar and put in green islands o There are products of pervious pavement that don’t use gravel which

would make it more cost effective

Green roofs o Down sprouts connect to bioswales in the streets o Planting areas on corners

Roundabouts with rain gardens in the center

Hotels o Well-being program where GI could meet the standards

Biggest problem in the village is parking o Parking lanes along NY avenue and Main street could have permeable

pavement; OR o put rain gardens in front of the gutters, so overflows will be cleaner going

into gutters.

Expand and elongate tree boxes on Main street o Can also put pavement on top of tree boxes to save for sidewalk space

TD Bank is a culvert

NY and Spring Road o Big depression area o Retention area?

Space behind Red’s Restaurant o Looks like a dead space o Could be used for something

Could use permeable pavement on hotel roof to create more parking spaces

West side of town is all downhill, so you can retain the stormwater there

Page 21: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

3

Culvert runs down NY Avenue and Main Street

Looking to construct a parking lot o Prime opportunity to put GI along Main street o Could create a tax incentive to fund projects o Water infiltrates into pipes; figure out how much it costs to treat the water

and then create a tax around that

A lot of issues are centered around people have the skills and ability to construct green roofs and permeable pavement effectively

More important to have permeable pavement uphill rather than downhill

Harbor Bay o Beach clubs o High tide; catch basins aren’t enough o Large parking lots attached o Larger projects have educational purpose as well

Overall considerations:

Need incentives to motivate people o Financial, zoning (parking), rebates

Educate developers and constructors

Funding o Help people with the grant writing process

Conservation/restoration of natural resources o Protecting wetlands

Connectivity o How projects are all connected

Inter-municipal council o Northport, Huntington, and Asharoken o Go after more funding/grants o Trying to partner with other organizations

Inter-municipal agreements o Interested in Huntington and Northport Bay o Let’s work together to save water o Representatives of the municipalities (mayor, trustees, contracted

engineer)

Page 22: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

4

Group 2. Huntington Bay

Several beach clubs are in hilly areas directly across from the Sound, and could use GI projects in and around the parking lots. These areas are visible and frequented, which would be good for not only reducing runoff but also for visibility and public education.

Fleet’s Cove – this is a public beach/outdoor area with a parking lot on the beach front across from a Town-owned pond. There is not only a problem with runoff but also with saltwater intrusion. Ideas are for a backflow protector or tide gate to prevent saltwater intrusion, and for the lot to install porous pavement, bioswales, and tree boxes.

Bay Hills Club – this club is private, but they have a real need since there is an outdated outfall pipe and serious runoff problem, as well as issues with saltwater intrusion. Like Fleet’s Cove, a backflow protector and GI projects in a parking lot are an option. Since doing GI projects in the parking lot may be an issue since it is private property and could be costly, one idea was to offer a Town or Village program for residents across/on the road of the club and parking lot so that homeowners could install rain gardens.

Vineyard Road Tidal Pond – this pond falls near an outfall pipe between two beaches (Nathan Hale and Bay Crest), and would benefit from GI projects on the roads leading to the pond. Ideas include incentives for homeowners to install rain gardens or native vegetation on their property.

Mill Pond – problem area off of major road (25A) – could also do home rain gardens along pond.

Crescent Club could do a green roof, but the club is private and it sits in the middle of golf course, so not great for public visibility or a pilot project.

Across from the harbor in Centerport Beach there is steep decline that leads right to a picnic area and the beach. There is need for wetland restoration, and a rain garden could be helpful by the picnic area.

Overall considerations:

There were some issues figuring out what was Town vs. Village vs. private home association jurisdiction, so projects in this area may require some coordination between different agencies/entities.

The Village already has in their code that homeowner’s drainage pipes must run into dry well.

The idea of a homeowner incentive for rain gardens or residential installation project for native vegetation was brought up several times – the Village could cover some costs with a GI revolving loan fund and may be able to get money from Suffolk County under the water quality fund created by a quarter-cent sales tax (GI projects are eligible). The Town may be able to aid as well with funding from open spaces and parks programs.

Page 23: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

5

Group 3. Northport Village

A variety of sites were discussed:

Main Street Parking Lots o Challenges: 4ft water level would make any kind of underground storage

of storm water very difficult. Buried utilities and outfall pipes are also a challenge. In addition, there are extremely old pipes under parking lots and roads downtown.

o Large volumes of water all end up at this point during major storms, so there is a real need to capture storm water uphill before it reaches this point. A feasibility study would be needed to see what could realistically be done.

o The group noted that there is a lot of wasted space in the Main Street parking lots, particularly the lot adjacent to the Park with the Gazebo. Redesigning these parking lots could incorporate green infrastructure for a more efficient use of space while reducing impervious cover and maintaining the same number of parking spaces.

Downtown Northport o Sidewalks are already smaller than regulation, and so adding tree boxes

or plantings along sidewalks would be difficult. o Install additional catch basins along Main Street (Village has a grant for

this) o The group identified three Village-owned parking lots on Main Street that

could be used for Green Infrastructure projects: One lot located next to print shop; Union Place parking lot; The lot across from the Northport Fire Department

o Church Parking Lots-St. Philip Neri, Presbyterian Church and the Methodist Church

Chosen because these parking lots are likely underutilized most days of the week

Village is already working with St. Philip Neri and the Presbyterian Church to install additional catch basins to their parking lots (grant funded). The Methodist Church is not working with them

o Green Roofs in Northport Village Would need to figure out where the roof drains are currently going

Upstream Locations o Main Street and Church Street identified as a potential location upstream o Pocket Park and triangle located at bottom of James Street hill near Bluff

Point Road and Woodbine o Valley Road and Ocean Avenue would be a good upstream location for a

Green Infrastructure project Challenge: buried utilities

o Ocean Avenue Elementary School Cornell Cooperative Extension offers a free educational program

about storm water and green infrastructure for schools. For

Page 24: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

6

elementary schools, they offer an educational component combined with the hands on activity of building a rain garden.

o Scudder Beach Area o Route 25A especially near Britania Marina where runoff enters the base of

Northport Harbor. (State owned) o Waterside Road and Locust Road- there is a triangular shaped road

divider that could be converted into a GI project o Laurel Avenue School

Large parking lot that is not used to capacity The Village got a grant to install a number of catch basins and

would like to install them in this parking lot, but so far school has been totally unresponsive

o Laurel Avenue- Traffic median could be extended o Northport Library

Overall considerations:

Incentives needed for any residential green infrastructure projects

Funding is a serious challenge for the Village o NYS Tax cap coupled with cost of upgrading Northport STP is a constraint

Matching funds would be difficult to impossible for Village o Village needs help writing grants

Village lacks sufficient staff and resources to prepare grant proposals.

o Potential sources of funding considered: Storm water fees? Rebate program for residents similar to MS4 program? When someone sells a house, require them to upgrade/add a storm

drain? Something similar to Real Estate Transfer Tax?

Page 25: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

7

IV. Summary Discussion A number of key points were raised in the summary discussion among participants:

Incentives are important to motivate people o Example incentives for green roofs could include easing parking

requirements (zoning) or abatement on sanitary bill

Hold an education forum to deal with government push-back o Could invite government leaders and consultants and their staff o Discuss environmental benefits, financial benefits of GI

Some of the unwillingness to embrace GI that is coming from the government side may be due to funding and money

o Provide more information about funding options, e.g., what is required to apply for grants? What are the steps?

o The Inter-Municipal Council (Northport, Asharoken, Huntington) was just formed, so maybe could work together to apply for funds, do group purchasing, etc.

Conservation and restoration of natural systems as a GI approach needs to be better emphasized – e.g., enhancing wetlands for flood protection

Connectivity should be a key theme – how existing and potential projects interconnected and how do they fit together

An education component is needed -a GI tour of the area could be a good way to educate the public and government officials about GI

o Could include educational signage

The Oyster Bay/Cold Spring Harbor Committee is looking for more representation from people in the Huntington-Harbor region

o Committee is composed of representatives from the municipalities who are invited to serve (not necessarily government representatives)

Page 26: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

MANAGING STORMWATER Natural Vegetation and Green Methodologies Guidance for Municipalities and Developers V.2.0 2015 Suffolk County, New York

Page 27: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

2

About National Wildlife Federation

The National Wildlife Federation is the United States' largest private, nonprofit conservation education and advocacy organization, with over four million members and supporters, and 48 state and territorial affiliated organizations.

About Citizens Campaign for the Environment (CCE) CCE is a non-partisan advocacy organization supported by over 80,000 members working to protect public health and the natural environment. For more about CCE please visit our website at www.citizenscampaign.org

Suffolk County Planning Commission Under state and county law, the Suffolk County Planning Commission is responsible for identifying and promoting county-wide land use values and planning priorities. This includes creating Suffolk County’s Comprehensive strategic plan, reviewing major development projects proposed within the County, making recommendations to local municipalities about policies that have regional impact, and developing common municipal approaches to address issues affecting the future of Suffolk County. The County Planning Commission is comprised of 15 members who are nominated by the County Executive and are confirmed by the County Legislature.

Report Contributors Primary Report Author Kara Reeve—National Wildlife Federation, Manager, Climate-Smart Communities Program Dominique Kone—National Wildlife Federation, Climate and Wildlife Safeguards Program

Report Contributors and Editors Maureen Dolan Murphy—CCE Executive Programs Manager Annie McClelland — CCE Long Island Program Coordinator

Acknowledgements We would like to thank the Long Island Sound Futures Fund, NFWF and the Long Island Sound Study for their generous grant support for this guidance document.

Page 28: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

3

I. Stormwater Challenges on Long Island................................................................................... 4

What is Stormwater Management? ............................................................................................ 5

Checklist for Addressing Stormwater .......................................................................................... 6

II. Managing Wet Weather with Green Infrastructure ............................................................... 7

Green Infrastructure Practices ..................................................................................................... 8

III. Costs and Benefits of Green Infrastructure ......................................................................... 10

Costs ........................................................................................................................................... 10

Benefits ...................................................................................................................................... 11

IV. Policies and Incentives to Catalyze the Use of Green Infrastructure.................................... 16

Regional/Local ............................................................................................................................ 16

Local Case Studies ...................................................................................................................... 18

National ...................................................................................................................................... 19

V. Funding Sources ................................................................................................................. 20

Regional/Local ............................................................................................................................ 20

National ...................................................................................................................................... 22

VI. Actions and Activities ........................................................................................................ 23

Updates to Land Using Planning and Zoning Requirements & Incentives ................................ 23

Educate and Recognize Leadership in the Development Community ...................................... 23

Build Greater Public Awareness about Green Infrastructure .................................................... 24

Partner with Schools and Universities ....................................................................................... 24

VII. Opportunities for Green Infrastructure in Huntington-Harbor Complex ............................. 25 Potential Green Infrastructure Demonstration Sites................................................................. 25

Opportunities for Partnerships, Outreach, etc. ......................................................................... 26

VIII. Additional Resources ....................................................................................................... 28

General Information on Green Infrastructure ........................................................................... 28

Information on School and University Programs ....................................................................... 28

IX. Sample Site Plan ................................................................................................................ 29

X. Literature Cited .................................................................................................................. 31

Table of Contents

Page 29: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

4

I. Stormwater Challenges on Long Island

Stormwater pollution is a cause of water quality impairment

throughout Long Island’s bays, harbors, estuaries, lakes, and

rivers. As polluted stormwater runs into water systems, it

degrades our water quality, threatening marine life, closing

beaches and contributing to closed shellfish beds that help

support the local economy. Runoff from stormwater is defined

by the U.S. EPA as “generated when precipitation from rain

and snowmelt events flows over land or impervious surfaces

and does not percolate into the ground. As the runoff flows

over the land or impervious surfaces (paved streets, parking

lots, and building rooftops), it accumulates debris, chemicals,

sediment or other pollutants that could adversely affect water

quality if the runoff is discharged untreated” (United States

Environmental Protection Agency). In a highly developed area

like Long Island there is a high percentage of impervious

surfaces, which contributes to more stormwater runoff and

limits the ability of water to infiltrate into the ground.

When stormwater runoff travels too quickly over impervious

surfaces and flows into harbors, bays and streams, it picks up

and carries with it a higher amount of sediment and other

pollutants. Pollutants include motor oil, pesticides, debris,

harmful bacteria, and nutrients such as nitrogen and

phosphorus. This swiftly traveling stormwater can also worsen

erosion and flooding, and contributes to the loading of

nonpoint source pollutants into harbors, bays, and rivers.

The existing stormwater runoff problem is worsening due to

climate change. According to the National Climate Assessment

(www.globalchange.gov), “The Northeast has experienced a

greater increase in extreme precipitation than any other region

in the U.S.; between 1958 and 2010, the Northeast saw more

than a 70% increase in the amount of precipitation falling in

very heavy events.” In the summer of 2014, Long Island

experienced a record setting rainfall of 11 inches within 24

hours. As the region experiences wetter weather and more

extreme storms, existing stormwater management plans and

infrastructure are not designed to account for these changes,

but green infrastructure can help manage the current and

future precipitation in the region.

Page 30: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

5

What is Stormwater Management?

Under natural conditions, stormwater is absorbed into the

ground, where it is filtered and ultimately replenishes

aquifers or flows into streams, rivers and estuaries. In

developed areas, however, impervious surfaces, such as

pavement and building roofs, prevent precipitation from

naturally soaking into the ground. Instead, the water runs

rapidly into storm drains and drainage ditches. The

resulting rush of stormwater discharge can cause

infrastructure damage, downstream flooding, and stream

bank erosion.

Stormwater management addresses these concerns

through a variety of techniques, including strategic site

design, measures to control the sources of runoff, and

thoughtful landscape planning. Managing stormwater has

multiple benefits which include environmental, economic,

and human health, including the following:

Reduced Maintenance & Repair Costs

Reduced and Delayed Runoff Volumes

Enhanced Groundwater Recharge

Pollutant Reductions into rivers, stream, tributaries

and bays

Reduced Sewer Overflow Events

Increased Carbon Sequestration (ie., carbon storage)

Urban Heat Island Mitigation and Reduced Energy

Demands

Improved Air Quality

Additional Wildlife Habitat and Recreational Space.

Improved Human Health

Stormwater runoff is regulated under the National

Pollutant Discharge Elimination System (NPDES), however

most states implement the NPDES program as a state

program – SPDES. The NPDES program covers the

following activities: Municipal Separate Storm Sewer

Systems, Construction Activities, and (Large) Industrial

activities (United States Environmental Protection Agency).

Stormwater runoff from these activities is considered point

source pollution, or direct discharge.

Page 31: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

6

Checklist for Addressing Stormwater

Reducing stormwater runoff from direct discharge activities (e.g. pipes that release water directly

to waterways) is only part of the solution. Protecting, enhancing, and restoring native vegetation

and providing incentives to use green infrastructure to protect groundwater and surface water

quality is a key part of successful stormwater management. Groundwater recharge is important

to the long-term health and sustainability of communities, and therefore efforts to protect

vegetation and recharge areas can result in cost savings for municipalities. The following is a quick

checklist to help you start assessing what measures can be taken to protect ground and surface

water:

□ Do you have zoning overlay districts specifically devoted to groundwater protection?

□ Do you have written standards for handling storm water to incorporate with deed covenants

and restrictions associated with zoning changes?

□ Do your subdivision regulations allow for alternative design, storage and reuse of storm

water on development parcels, on planned rights-of-way, and within engineered structures, such as leaching basins, catch basins, recharge basins, or perforated pipe?

□ Do your site plan review requirements permit alternative stormwater design and rainscaping

techniques such as temporary parking pavement waivers, roof and pavement drainage structures such as porous pavement, rain gardens, bio-retention basins, bio-swales, and green roofs?

□ Do your codes contain incentives for the retention or re-establishment of existing native

plantings and non-disturbance of natural recharge areas?

□ Do your codes contain disincentives to discourage extensive fertilized vegetation, automatic

irrigation, impervious surface and urban heat island effect and, conversely, to encourage drought-tolerant plants, no-mow meadowland, upgrade and renewal of natural process for site work?

Page 32: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

7

Green Infrastructure (GI) is described by the

Environmental Protection Agency (EPA) as a solution

that, “…uses vegetation, soils, and natural processes to

manage water and create healthier urban

environments” (United States Environmental Protection

Agency). Green Infrastructure could include retaining

our remaining natural landscapes; restoring or re-

creating an environment similar to pre-development

conditions, or mimicking natural systems.

Green infrastructure is an approach to wet weather

management that is cost-effective, sustainable, and

environmentally friendly. Green Infrastructure

management approaches and technologies infiltrate,

evapotranspire, capture, and reuse stormwater to

maintain or restore natural hydrologic systems.

At the largest scale, the preservation and restoration of

natural landscape features (such as forests, floodplains

and wetlands) are critical components of green

stormwater infrastructure. By protecting these

ecologically sensitive areas, communities can improve

water quality while providing wildlife habitat and

opportunities for outdoor recreation.

On a smaller scale, green infrastructure practices include rain gardens, porous pavements, green roofs, bio-

retention basins, bio-swales, conservation and restoration of natural systems, and native/natural

landscaping. All of these practices play a vital role in stormwater management while improving and

maintaining the environmental quality of surrounding communities.

Green infrastructure is often used inter-changeably with the term low-impact development (LID). The EPA

defines LID as “a land development approach that works with nature to manage stormwater as close to its

source as possible. This development approach aims to conserve and restore natural landscape features,

which reduces imperviousness to create functional and appealing site drainage that treats stormwater as a

resource rather than a waste product. By implementing LID principles and practices, water can be managed

in a way that lessens the impact of built areas and supports the natural movement of water within an

ecosystem or watershed” (United States Environmental Protection Agency).

II. Managing Wet Weather with Green Infrastructure

Page 33: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

8

Green Infrastructure Practices

BIO-RETENTION BASIN – An area designed to accept and retain

stormwater, to slow or block either its discharge to surface water

or its recharge to groundwater, to lessen erosion, allow for filtering

of sediments, plant root uptake of nutrients, and biologically

control the water. It may be equipped with various overflows or

high water level bypasses to transport amounts of water exceeding

its holding capacity.

BIO-SWALE – A linear area designed to capture, slow, and

distribute flowing water so that plants can absorb the water.

These vegetated areas may be supplemented by under drains,

overflows or other engineering devices to cope with unusual

storm events.

GREEN ROOF – A building roof that is engineered to be

covered with low-maintenance growing plants that

insulate in winter, cool the building in summer, reduce

solar absorption, reduce precipitation run-off surfaces,

and improve interior Heating, Ventilating and Air

Conditioning (HVAC) efficiency.

GREEN STREETSCAPE — Although streetscapes are

traditionally constructed with asphalt or concrete, streets,

sidewalks, curbs, and other features can be retrofitted and/

or constructed to incorporate more permeable, natural

surfaces. Green streetscapes incorporate sustainable design

practices that not only improve the management of

stormwater on-site, but have additional benefits, such as

improved air quality. Planting of street trees and expanding

tree box size, “greening” medians, using porous pavement,

and incorporating bioswales and rain gardens into the

streetscape design are all be considered features of a green

streetscape.

Page 34: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

9

NATIVE/NATURAL LANDSCAPING – This practice encompasses

techniques such as planting native plant species, urban forests,

drought-tolerant plant species, and native grasses with minimal

mowing activity. Typical plant or grass species used in native/

natural landscaping practices are those that have the capacity to

thrive with minimal water and are able to store water during

extended dry periods, are not introduced from outside the

geographical area, and are genetically suited to thrive with little to

no maintenance, in the original soils to which it is accustomed.

POROUS/PERMEABLE PAVEMENT – A hard surface with load bearing

capacity engineered to allow for the passage of water through pores.

Porous pavements are often underlain by carefully engineered layers of

crushed rock, fabric filter cloth, piping, or drains. Types of porous

pavement may include paving blocks with open corners, lattices, or

edges or asphalt/concrete mixes without fine sediments.

RAIN GARDEN – A vegetated area designed to capture and

retain stormwater so that plants may absorb the water. These

areas are often outfitted with under drains, overflows, or other

engineering devices to cope with extreme storm events.

CONSERVATION AND RESTORATION OF NATURAL

SYSTEMS – The conservation of natural features in their

original state. Natural features that are particularly

important in addressing stormwater issues include riparian

areas, wetlands, and steep hillsides. The EPA provides an

educational and comprehensive report on this at: http://

water.epa.gov/infrastructure/greeninfrastructure/upload/

gi_action_strategy.pdf

Page 35: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

10

III. COSTS AND BENEFITS OF GREEN INFRASTRUCTURE

One of the biggest issues in recognizing the full potential of using green infrastructure practices in

stormwater management is taking into account all of the costs and benefits. This is especially true for

identifying the vast benefits that green infrastructures provides for coastal communities because they are

difficult to value. Additionally, the full cost of pollution, such as pollutants in stormwater, are externalized

and difficult to connect to the polluter, undermining the full costs. These factors can often result in a

disconnect between perceived costs and benefits.

Despite these barriers, there are many costs and benefits that have been identified:

Costs

INSTALLATION COSTS – The overall costs to implement a project will vary depending on various factors

such as size, design, equipment/materials, purpose, and labor requirements. Furthermore, bio-retention

basins, bioswales, green roofs, porous pavement, and rain gardens, all have varying costs per square unit

because of their different construction, maintenance, and material needs. These factors not only result in

cost variations between the different types of green infrastructure, but also among different project sites of

the same infrastructure type. In Prince George’s County, Maryland, the cost of installing a bio-retention basin

on a residential lot subdivision was estimated at $1,075, while the cost of installing a basin on a commercial

subdivision lot was estimated at $10,357 (Department of Environmental Resources, Maryland, 2007). This

difference in price is due to a difference in size, design, and purpose of the lots.

Estimated costs of installing a green roof start at $10 per square foot for simpler roofing, and $25 per square

foot for intensive roofs. Likewise, the installation cost per square yard of porous pavements varies depending

on the type of materials used—porous asphalt was quoted at $31.00, porous pavers at $104.31, and porous

concrete at $60.75 (Rowe 2009).

Costs Installation Costs

Maintenance & Lifecycle

Consumer Aesthetic Appeal & Usability

Benefits Reduced Maintenance & Repair Costs

Reduced Runoff Volume & Overflow Events

Environment & Human Health

Wildlife Habitat & Recreational Space

Urban Heat Island Mitigation & Reduced Energy Demands

Job Creation

Page 36: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

11

MAINTENANCE & LIFECYCLE – The cost of maintenance also depends on the type of green infrastructure

and lifecycle. Green infrastructure maintenance may be more or less expensive than gray infrastructure

maintenance when taking into account these two factors. The annual maintenance cost of green roofs range

from $0.75 - $1.50 per square foot, which is typically higher than a conventional black roof by $0.21 - $0.31 per

square foot (Peck & Kuhn, 2003). These higher costs are a result of maintenance needs of the rooftop

vegetation. Porous pavements also incur maintenance costs, especially during winter months when sand and

salt can clog pores. Regular maintenance is required to clear these areas. Property owners should provide a

budget for maintenance at an annual rate of 1-2% of construction costs (Metropolitan Area Planning Council).

In contrast, native/natural landscaping practices, such as planting native and drought tolerant plants, incur

almost zero maintenance costs as these plants are suitably adapted for the geographic area.

CONSUMER AESTHETIC APPEAL & USABILITY – While aesthetic appeal and usability are difficult to

monetize, consumer satisfaction is an important factor in identifying perceived costs. Consumers or members

of the community may be dissatisfied with either the look of green infrastructure or the quality. Many

consumers have struggled with getting consistent quality out of porous pavement as it tends to wear out faster

than concrete (Clean Water America Alliance, 2011). In the case of native/natural landscaping, uprooting turf

grass and replacing lawns with native species typically takes 2-3 years to mature (United States Environmental

Protection Agency, 2004). Until then, the area may look sparse or patchy, resulting in dissatisfied consumers.

Benefits

ENVIRONMENT & HUMAN HEALTH – One of the biggest benefits of green infrastructure is the ability to

improve and maintain the quality of the environment, specifically water and air. By infiltrating, absorbing,

and retaining stormwater, green infrastructure prevents pollutants and nutrients from entering into nearby

water systems, subsequently improving water quality. These trends can have huge implications for

improved human health as a result of a healthier environment. Many studies have found a strong positive

relationship between the amount of green space and human well-being and health in various communities

(Tzoulas et al., 2007).

Bio-retention basins, bioswales, rain gardens, porous

pavement, and native/natural landscaping, all remove

suspended solids, phosphorus, nitrogen, and heavy metals,

such as cadmium, copper, lead, and zinc from stormwater.

Systems such as bio-retention basins, bioswales, and rain

gardens, can remove an average of 80% of the total

suspended solids, 60% of total phosphorous, 50% of total

nitrogen, and 80% of heavy metals (Upstate Forever). A

study in Greenbelt, MD, found removal rates of more than

90% for copper, lead, and zinc, 65-75% removal of

phosphorus, and 45-60% removal of nitrogen (United States

Environmental Protection Agency, 2000).

Page 37: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

12

WILDLIFE HABITAT & RECREATIONAL SPACE –

Green infrastructure practices are often referred to as

“multifunctioning natural habitats” because of their

ability to act as both stormwater management tools

and conservation tools. Through the use of native plant

species, they provide natural habitats for and attract

wildlife, as well as serving as an aesthetic commodity to

the landscape. The use of bio-retention basins, natural

systems, bioswales, green roofs, rain gardens, and

native/natural landscaping, have huge implications for

butterfly, moth, bird, and insect species that depend

upon the services provided. Many of these species are

particularly crucial to the health of the environment as

they play vital roles as pollinators. Furthermore,

building off this idea of improved water quality, green

infrastructure also supports many aquatic wildlife, such

as fish and invertebrate species, which can only survive

under specific ranges in water quality and temperature.

REDUCED MAINTENANCE & REPAIR COSTS –

Many of these features (bio-retention basin, bioswales,

rain gardens, native/natural landscaping) have lower

maintenance (e.g. landscaping, watering, pesticides,

and fertilizers) and repair (e.g. replacement, and longer

lifecycle) costs in comparison to gray infrastructure.

Specifically, bio-retention basins tend to have lower

maintenance and liability costs; primarily due to

facilities being located at the source rather than at the

end of the pipe (Department of Environmental

Resources, Maryland, 2007). Bio-retention basins and

bioswales only incur maintenance costs of 5-7% of

overall construction costs of the infrastructure (United

States Environmental Protection Agency, 2006).

Likewise, in regions of the country like Long Island that

require plowing of snow, porous pavements tend to

require little maintenance because melt water is

allowed to infiltrate rather than freeze as an ice layer.

Sylvan Avenue Permeable

Project

In 2010, this project was implemented in

Ann Arbor, MI, which installed an 800-

foot long, 20-foot wide residential

porous roadway. After the installation, it

was found there was a significantly lower

amount of ice and snow which required

less plowing and salting of the roadway

(Buckley et al., 2011).

Page 38: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

13

Additionally, native/natural landscaping and techniques (rain garden, bioswales, and bio-retention basins) that incorporate native and drought tolerant plants have lower long-term maintenance costs due to reduced irrigation, pesticide, and fertilizer needs. A project in Illinois found a significant decrease in maintenance costs associated with native/natural landscaping than conventional turf grass. The 10-year average maintenance costs per acre of turf grass was estimated at $5,550, while the 10-year average maintenance costs per acre of native/natural landscaping was estimated at only $1,600 (United States Environmental Protection Agency, 2004).

REDUCED RUNOFF VOLUME & OVERFLOW EVENTS – It is estimated that 25% of the $1 billion in annual

damages from flooding are linked to stormwater (Federal Emergency Management Agency, 2005). Therefore

the infiltration, absorption, and retention abilities of green infrastructure could and currently does have a huge

impact on mitigating stormwater damages. Increasing infiltration, absorption, and retention reduces the

amount of water energy flowing through local storm sewers and stormwater systems and reduces flooding-

related impacts, such as decreased property value, damages to public infrastructure, and repair costs.

In farming operations and the use of greenhouses, phosphorus and nitrogen that crops use and dispense can

create run-off with poor water quality. Farmers can use GI to mitigate and filter this run-off. In Eastern Suffolk

County, farmers such as Gabrielsen’s Country Farm have used bio-swales surrounding greenhouses to control

run-off.

Rain gardens reduce stormwater runoff volume by temporarily

storing water and returning it to the ground, reducing the

immediate volume load on water bodies and the storm drain

system by up to 98% which in turn helps to reduce the risk of

flash floods (Upstate Forever). In 2008, the Saylors Grove bio-

retention basin intercepted 73% (25.4 of 34.8 million gallons) of

stormwater runoff and resulted in a significant reduction in

rainfall intensity peak flow (Howley).

Porous pavements also play a vital role in reducing runoff. Analyzing the percent of rainfall converted to runoff

volume for various pavement scenarios, porous pavement coupled with a bioswale (10%) is much more

effective at preventing rainfall from converting to runoff than asphalt (51%), asphalt with a bioswale (34%), and

even cement with a bioswale (32%) (Clark & Acomb).

Jordan Cove Watershed

In 2003, a study conducted in this watershed

(Waterford, CT), which drains into Long

Island Sound, investigated the average

infiltration rates of porous pavement in

comparison to asphalt. The study concluded

that porous pavement (8.1 inches per hour)

had a higher average infiltration rate than

asphalt (0 inches per hour) (Interlocking

Concrete Pavement Institute, 2004).

Page 39: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

14

URBAN HEAT ISLAND MITIGATION & REDUCED ENERGY DEMANDS – Green infrastructure

dramatically increases energy efficiency by reducing heating and cooling demands of buildings, resulting in

lower energy bills. Additionally, green infrastructures that incorporate the use of trees and urban forests

provide added shading that can mitigate the effect of urban heat islands. A typical medium-sized tree absorbs

70-90% of sunlight and reduces the maximum surface temperature of roofs and walls of buildings by 11-25

degrees Celsius (Foster et al., 2011).

Green roofs, in particular, show huge reductions in energy use and costs. Vegetation on green roofs lower the

absorption of solar radiation and thermal conductance, which can substantially lower building temperatures

during warm periods and decrease energy consumption. During cooler periods, green roofs act as extra

insulation, reducing heat loss and increasing energy efficiency. In 2006, commercial and industrial energy costs

in the U.S. totaled $202.3 billion, with roughly 50% due to indoor heating and lighting. Widespread

implementation of green roofs, with their ability to reduce indoor energy consumption by 7-10% per year,

could save the U.S. economy $7-$10 billion per year (US EPA 2006).

American Society of Landscape Architects

In 2006, the American Society of Landscape Architects replaced their existing roof in

Washington, DC, with a green roof (pictured below). They observed a 10% reduction in building

energy use during the winter months and a 59 degree (F) reduction in temperature during the

summer months compared to the previous conventional roof (American Society of Landscape

Architects 2012).

Page 40: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

15

The Center for Neighborhood Technology and American Rivers has created a helpful guide describing the steps

necessary to value many environmental, social, and public health benefits of green infrastructure. The guide

includes simple, the illustrative examples to assist municipalities and developers in performing their own

calculations. The guide can be found here: http://www.cnt.org/repository/gi-values-guide.pdf

JOB CREATION – Due to the vast number of green infrastructure techniques that hold the capability

of mitigating stormwater management issues, capacity and expertise is needed in the installation and

design, operations and maintenance, and supply chain of these techniques. Similarly, it was found

that an investment of $166 million in stormwater projects between 2009-2011 produced an

estimated 2,075 jobs in Los Angeles, CA (Burns & Flaming, 2011). Looking at specific types of green

infrastructure, installing green roofs on 5% of Chicago’s buildings would create almost 8,000 jobs

from an investment of $403 million (Hewes, 2008).

PlaNYC

PlaNYC is a sustainability and resilience plan which consists of 127 initiatives to transform New

York City into a more sustainable and resilient city. The use of green infrastructure (e.g. green

roofs, bioswales, and pervious pavement) was outlined and included in many of the plan’s

programs to address the city’s stormwater issues (PlaNYC, 2014). In 2008, an analysis

anticipated the creation of 266 total jobs from investing $23 million in green roofs and 1,446

direct jobs from a $346 million investment in PlaNYC’s watershed protection programs (The

Louis Berger Group, Inc., 2008).

Page 41: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

16

Summaries of policies and incentives are included below, with links to the full text.

Regional/Local

CROTON-ON-HUDSON, NY – Croton-on-Hudson’s Wetlands and Watercourses ordinance protects

wetlands and other natural stormwater management areas in order to prevent water contamination. Croton-

on-Hudson uses this ordinance to establish a Water Control Commission. http://www.stormwatercenter.net/

Model%20Ordinances/misc__wetlands.htm

TOWN OF EAST HAMPTON, NY – The Town of East Hampton established a Harbor Overlay District to

maintain or improve surface water quality. The district is also intended to maintain or improve wildlife

habitat in these areas and to maintain or restore these waterways as closely as possible to their natural

condition. http://ecode360.com/10414586?highlight=overlay%20districts,overlay%

20district,districts,district,harbors,overlay,harbor#10414586

TOWN OF NORTH HEMPSTEAD, NY – The Town of North Hempstead, NY established a Stormwater

Control ordinance which requires the consideration and implementation of a stormwater pollution

prevention plan (SWPPP) with any land development activity. Specific on-site retention requirements apply

with any increase in impervious surface area. http://ecode360.com/9298140

ONONDAGA COUNTY, NY – The Save the Rain program is a comprehensive stormwater management plan

intended to reduce pollution to Onondaga lakes and tributaries. This program offers two funding resources

directed toward the owners of private property and other municipalities within the county’s sewer district;

the Green Infrastructure Fund (GIF) and the Suburban Green Infrastructure Program (SGIP). http://

savetherain.us/

TOWN OF OYSTER BAY, NY – Oyster Bay’s Stormwater Management and Erosion and Sediment Control

ordinance seeks to establish minimum stormwater requirements and controls to protect and safeguard the

general health, safety, and welfare of the public by reducing stormwater runoff rates and volumes, soil

erosion, and nonpoint source pollution through stormwater management practices. http://

ecode360.com/26884711?highlight=stormwater

IV. POLICIES AND INCENTIVES TO CATALYZE THE USE OF GREEN INFRASTRUCTURE

Page 42: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

17

CITY OF BRIDGEPORT, CT – In 2010, the City of

Bridgeport launched the BGreen 2020 Initiative, a

Sustainability Plan that outlines the policies and

actions to be implemented in the next 10 years to

improve the quality of life, social equity, and economic

competitiveness of the city, while reducing harmful

impacts to the environment. Part of the plan addresses

making improvements to the region’s waterways

through enhanced stormwater management and use

of green infrastructure.

http://www.bgreenbridgeport.org/storage/documents/Bgreen-2020-2013-Progress-Report.pdf

VERNON, CT – The Town of Vernon has made it a policy to required LID to the maximum extent

practicable (MEP) for all projects that fall within current Town regulatory jurisdiction, with the intent

of managing stormwater. In the construction, design, and implementation of various gray

infrastructures, many Zoning and Subdivision Regulations mandate and suggest the use of low impact

development stormwater management practices with the consultation of the Town LID Manual.

http://www.vernon-ct.gov/files/VernonGuidelinesStormWater_2013.pdf

Page 43: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

18

Local Case Studies:

PERMEABLE PAVEMENT, LINDENHURST, NY – The Lindenhurst Library is home to Long Island’s

first permeable pavement parking lot. The parking lot is designed with permeable paving stones,

set in-between gravel, which sits atop 4 layers of different sized gravel. The water is able is

infiltrate through the pavement and then the various layers of gravel. This water would otherwise

run-off as polluted stormwater into the Great South Bay. The parking lot also has bio-swales

surrounding the perimeter with drought resistant plants that help to capture rain water to

recharge it into the aquifer. The project was built using $200,000 in stimulus funds, which covered

90% of the construction and engineering costs. To complement the project, solar power is used to

light the parking lot at night.

GREEN BUILDING DESIGN, WESTBURY, NY – The “Yes We Can” Community Center is a

platinum LEED certified building in North Hempstead that utilizes native vegetation, rainwater

collection, permeable paving, recycled water for toilets, a photovoltaic roof, geothermal heating,

and solar trees in the parking lot to decrease environmental impacts and lower energy costs. The

Center now serves as a leader in green infrastructure and energy efficiency on Long Island and has

been featured at several LEED and green infrastructure conferences.

GREEN ROOF INSTALLATION, OLD WESTBURY, NY – A 1,000 foot living green roof was

installed at the SUNY Old Westbury campus only a few days before Superstorm Sandy hit in 2012.

The roof cost $23,000 to install. The roof withstood a direct hit from the Superstom and

successfully drained water and reduced flooding on the campus.

GERARD STREET PARKING LOT, HUNTINGTON, NY – The Town of Huntington has

incorporated 6,020 square feet of bioretention areas as part of the reconstruction of the Gerard

Street Parking Lot to reduce and treat stormwater runoff. The total cost of constructing these

bioretention areas is $262,715, or $43.64 per square foot, representing 18% of the total

construction costs for this project. Stormwater quality benefits include the pretreatment of

stormwater prior to entering waterways and removal of pollutants such as phosphorus, nitrogen,

various dissolved and particulate metals (cadmium, copper, lead, zinc) and some pathogens

(coliform, streptococci, E. Coli). Environmental benefits include the reduction of CO2 emissions

that would be created by manufacturing conventional precast concrete drainage structures;

reduction of the heat-island effect by increasing the amount of landscaping and shade trees; and

utilization of recycled plastics in the manufacture of the HDPE drainage structures and pipes

installed in bioretention areas.

Page 44: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

19

National

ANNAPOLIS, MD – The City of Annapolis, MD, raised its Stormwater Utility Fee in 2011, and offers a 50%

discount on this fee if residential or commercial properties install stormwater management structures or

devices on their properties (e.g. green roofs, rain gardens, and infiltration trenches). http://

www.ci.annapolis.md.us/government/city-departments/neighborhood-environmental/stormwater-

management

LOWER COLORADO RIVER AUTHORITY, TX – The Lake Travis Nonpoint Source Pollution Control

Ordinance is aimed at reducing nonpoint source pollution in the Lake Travis area (a watershed near Austin,

TX). The Lake Travis watershed is a sub-watershed of the Lower Colorado River. http://

www.stormwatercenter.net/Model%20Ordinances/misc__lake_travis.htm

MONTGOMERY COUNTY, MD – Montgomery County has a Rainscapes Program that offers rebates to

residential and commercial properties that implement eligible rainscaping techniques to reduce stormwater

pollution. The funding comes from the County’s Water Quality Protection Charge, a tax property owners pay

for the amount of impervious surface on their property. http://www.montgomerycountymd.gov/DEP/water/

rainscapes.html

NAPA, CA – Napa’s Riparian Habitat ordinance is focused on protecting and restoring native vegetation.

Napa’s ordinance also takes additional measures to prevent streambank hardening which is detrimental to

habitat and accelerates erosion. http://water.epa.gov/polwaste/nps/upload/nps-ordinanceuments-a2c-

napa.pdf

RHODE ISLAND – Rhode Island’s program is focused on vegetated coastal zone buffers. Rhode Island seeks

to protect ecologically sensitive areas and prevent contaminated runoff from non-point source pollution.

http://water.epa.gov/polwaste/nps/upload/nps-ordinanceuments-a2b-rhode-island.pdf

WASHINGTON, DC – Washington, DC, offers monetary incentives to homeowners who implement

landscape enhancements, such as rain gardens or pervious pavers, which reduce stormwater runoff.

Homeowners apply to the program and receive a free audit to determine the best options for their

properties and the potential incentive amount. http://green.dc.gov/riversmarthomes

Page 45: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

20

Since green infrastructure projects provide a variety of benefits beyond simply stormwater management, the

funding required to implement projects may come from a variety of sources, such as those related to

sustainability, community revitalization, urban wildlife habitat, climate mitigation, and climate resilience and

adaptation.

Regional/Local

LONG ISLAND SOUND FUTURES FUND – The Long Island Sound Futures Fund (LISFF) is a competitive

grant program administered by the National Fish and Wildlife Foundation. In particular, the Clean Waters and

Healthy Watersheds priority area provides funds to, “plan and implement Low Impact Development (LID) and

green infrastructure or green street projects.” http://www.nfwf.org/lisff/Pages/home.aspx#.VBdHGGO5R6I

NEW YORK GREEN INNOVATION GRANT PROGRAM – The New York Green Innovation Grant Program

(GIGP) supports projects across the State of New York that utilize unique stormwater infrastructure design

and create cutting-edge green technologies. GIGP-funded projects may be found from Buffalo to the end of

Long Island, and range from rain gardens to stream "daylighting" projects. http://www.efc.ny.gov/

Default.aspx?tabid=461

SUFFOLK COUNTY DRINKING WATER PROTECTION PROGRAM – The purpose of the program is to

fund implementation projects that will result in the protection and restoration of surface water quality. This

program was extended 13 years through the use of dedicated sales tax extensions. A portion of the total

revenues generated annually by the sales tax were dedicated to offsetting the costs associated with

implementing environmental programs. http://efc.muskie.usm.maine.edu/conservation_finance/

LESSON_5.htm

V. FUNDING SOURCES

Conscience Bay

In 2012, $1.6 million in grants were awarded to state and local government and community

groups in New York and Connecticut to improve the health of Long Island Sound. (Long Island

Sound Study, 2012). A portion of these funds were allocated to the Conscience Bay Stormwater

Treatment & Wetland Enhancement project in the Village of Old Field. With a grant amount of

$200,000, 35 subsurface infiltration units connected to 4 curbside basins, and 4 bioswales were

installed to treat 194 million gallons of polluted stormwater (National Fish and Wildlife

Foundation, 2012).

Page 46: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

21

ONONDAGA COUNTY GREEN INFRASTRUCTURE FUND – As part of the Save the Rain Program, the

purpose of the Green Infrastructure Fund is to support the development of green infrastructure and

stormwater mitigation practices on private property. This fund applies to applicants and projects within the

Clinton, Harbor Brook and Midland Combined Sewersheds (CSS). http://savetherain.us/green-improvement-

fund-gif/

SUBURBAN GREEN INFRASTRUCTURE PROGRAM – The Suburban Green Infrastructure Program

supports the development of green infrastructure and stormwater management practices on public property

within the Onondaga County sewer district, but outside of the City of Syracuse. This funding option targets

municipal entities that are considering planning projects to reduce inflow and infiltration to sanitary sewer

systems. http://savetherain.us/sgip/

50/50 STORMWATER MANAGEMENT FUND – This program, funded by the National Fish and Wildlife

Federation Chesapeake Bay Stewardship Fund, assists landowners in implementing green infrastructure

practices to meet the requirements administered by the City of Binghamton’s Urban Runoff Reduction Plan.

http://www.binghamton-ny.gov/sites/default/files/files/50_50%20Stormwater%20Fund%20Matching%

20Grant%20FAQ.doc__0.pdf

LOCAL WATERFRONT REVITALIZATION PROGRAM – These programs establish a long-term partnership

among local government, community-based organizations, and the State to address local revitalization

issues. On an annual basis, the Department of State solicits grant applications from local governments for

50/50 matching grants that can be used to advance preparation, refinement, or implementation of these

programs. http://www.dos.ny.gov/opd/programs/lwrp.html

WATER QUALITY IMPROVEMENT PROJECT PROGRAM – This is a competitive, reimbursement program

that directs funds from the New York State Environmental Protection Fund to projects that reduce polluted

runoff, improve water quality, and restore habitat in water systems across New York State. These funds are

available to municipalities, municipal corporations, soil and water conservation districts, and non-profit

corporations. http://www.dec.ny.gov/pubs/4774.html

Save the Rain

The Onondaga County Save the Rain Green Improvement Fund (GIF) was created for private

property development and redevelopment. Since March 2010, 117 applications have been

submitted for grant funding. 36 projects have been completed and 54 projects are under

contract. There have been 14.2 million gallons of stormwater removed annually from

completed projects.

Page 47: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

22

National The US EPA has developed a green infrastructure portal that includes a number of non-federal funding sources

and tools. http://water.epa.gov/infrastructure/greeninfrastructure/gi_funding.cfm

CLEAN WATER STATE REVOLVING FUNDS – This program provides loan assistance for wastewater

treatment, stormwater management, nonpoint source abatement, and estuary protection projects. The

revolving nature of the program is maintained with loan repayments, interest, and federal capitalization

grants that are used to fund new projects. http://www.epa.gov/owm/cwfinance/cwsrf/green_if.pdf

NATIONAL DISASTER RESILIENCE COMPETITION – The U.S. Department of Housing and Urban

Development will be announcing a national competition that will be funded through the Community

Development Block Grant disaster recovery (CDBGDR) appropriation provided by the Disaster Relief

Appropriations Act, 2013 (PL 113-2). This program funds communities that have been struck by natural

disasters to implement innovative resilience projects to better prepare them for future storms and extreme

weather events. http://portal.hud.gov/hudportal/documents/huddoc?id=FactSheet_071514.pdf

ILLINOIS GREEN INFRASTRUCTURE GRANT PROGRAM – Administered by the Illinois EPA, this program’s

grants are available to local units of government and other organizations to implement green infrastructure to

control stormwater runoff for water quality protection in Illinois. The amount of funding available under this

program is administered as a reimbursement program. http://www.epa.state.il.us/water/financial-assistance/

publications/igig-progress-report.pdf

GREEN INFRASTRUCTURE FOR COASTAL RESILIENCE PILOT GRANT PROGRAM – Provides financial and

technical support to better understand and implement natural approaches to mitigating coastal and flooding

problems. Grants support the planning, feasibility assessment, design, permitting, construction, and

monitoring/evaluation of green infrastructure projects. Grants are available to 78 municipalities within the

Massachusetts coastal zone. http://www.mass.gov/eea/agencies/czm/program-areas/stormsmart-coasts/

green-infrastructure-grants/

URBAN WATERSHED STEWARDSHIP GRANTS – This program has partnered with the City’s Community

Challenge Grant Program (CCG) to offer grants for projects which help to manage stormwater using green

infrastructure within San Francisco’s watershed. Grants support the planning, design, and construction of

green infrastructure projects that address stormwater issues as well as provide recreational and education

values to the community. http://sfwater.org/index.aspx?page=104

COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM – This is a flexible program that provides

communities with resources to address a wide range of unique community development needs. This program

provides annual grants to local governments and States and is comprised of various sub-programs which

target more specific needs of the regions and local communities (e.g. climate change threats, water quality,

housing availability,etc.) http://portal.hud.gov/hudportal/HUD?src=/program_offices/comm_planning/

communitydevelopment/programs

Page 48: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

23

Citizens Campaign for the Environment and National Wildlife Federation hosted two workshops in 2014

focused on catalyzing the use of green infrastructure for stormwater management in the Huntington-Harbor

Complex. Included below are ideas that came from these meetings.

Updates to Land Using Planning and Zoning Requirements

& Incentives

Enhance the Department of Environmental

Conservation (DEC) approval process to

incentivize or require green infrastructure

Include incentives for green features in bids

Create model codes and standard

expectations

Develop draft language for municipalities to

incorporate into their comprehensive plans,

LWRP, and streetscape design

Downtown revitalization grants can include

green infrastructure components

Include provisions in SPDES permits

Allow for flexibility in site plans if developers

incorporate green infrastructure

Educate and Recognize Leadership in the Development

Community

Develop upfront guidance for developers

when they apply for a general permit so they

can better understand how their

development plans could incorporate green

infrastructure from the beginning

Create recognition and reward programs for

developers

Charge stormwater fees for impervious

surfaces

VI. ACTIONS AND ACTIVITIES

Page 49: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

24

Build Greater Public Awareness about Green Infrastructure

Develop communications and outreach plan

Create a green infrastructure tour, create an on-line

version as well, list all of the exemplary projects in

the area (Good examples include the Onondaga

County Program, Save the Rain;Town of Oyster Bay,

North Hempstead; and the City of Bridgeport)

Create a web site and pamphlets to help explain the

opportunities, options, and products that are

available

Collect and communicate about local progress on GI

to towns throughout Long Island

Partner With Schools and Universities Schools present an opportunity for GI projects like food or rain gardens; school parking lots can act as

possible demonstration sites

special construction funding can be available

Universities and Community Colleges could also be good sites for demonstration projects

Page 50: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

25

Included below are potential sites that could use green infrastructure to mitigate the area’s stormwater issues, as well as opportunities for partnerships and outreach efforts.

Potential Green Infrastructure Demonstration Sites

VII. OPPORTUNITIES FOR GREEN INFRASTRUCTURE IN HUNTINGTON-HARBOR COMPLEX

Huntington, NY

MUNICIPAL PARKING LOTS – Municipal parking lots are one of the leading contributors to

Huntington’s large amount of impervious surfaces, through which rainwater is unable to

infiltrate and percolate into the ground. These parking lots allow an immense amount of

stormwater to run across the surface, washing away pollutants, and nutrients. These sites have

the potential to incorporate permeable pavement with green spaces (e.g. bioswales,

bioretention basins, and rain gardens) to maintain the current level of parking spaces. Even

though the more cost-effective method may lie in removing tar and implementing green

islands, there are products of permeable pavement that use less expensive materials.

RED RESTAURANT – Red Restaurant, located at 417 New York Avenue, Huntington, NY

11743, and its neighboring building have been identified as prospective locations to implement

green roofs and solar panels. Red would gain great visibility as a demonstration site and is just

one of many multi-story redevelopment projects that are being planned in the area. Red’s plan

could be a leading example and be expanded to all other development projects that can

accommodate green roofs. This idea not only mitigates the town’s stormwater issues, but also

prevents the reduction in parking spaces.

MAIN STREET & NEW YORK AVENUE PARKING LANES – One of the biggest issues in the

village is available parking space. One solution that will maintain parking space and mitigate

stormwater issues is to replace the impervious pavement in parking lanes with permeable

pavement. Furthermore, implementing rain gardens in front of rain gutters will allow for

cleaner water to enter gutters when overflow events occur.

Page 51: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

26

Opportunities for Partnerships, Outreach, etc.

Key partnerships and outreach efforts were identified as means of advancing the implementation of green

infrastructure. These players include schools and universities, municipalities, and churches.

SCHOOLS & UNIVERSITIES – Not only could a number of green infrastructure techniques be installed

directly on school properties, but schools provide crucial opportunities to educate the local community.

Partnering with universities and colleges can also provide additional educational programs for local schools.

For example, the Cornell Cooperative Extension offers a free educational program about stormwater and

green infrastructure. For elementary schools, they offer an educational component combined with the

hands on activity of building various green infrastructures. Furthermore, local schools that achieve a net zero

environmental impact and ensure the environmental and sustainability literacy of their graduates are

eligible to receive a recognition award from the U.S. Department of Education through National Wildlife

Federation’s Green Ribbon Schools awards program. More information on this program is available. http://

www.nwf.org/Eco-Schools-USA/About-Eco-Schools-USA/Green-Ribbon-Schools.aspx

Huntington Bay, NY

FLEET’S COVE & BAY HILLS BEACH ASSOCIATION – Both of these clubs are particularly

important as demonstration sites because of their visibility to the public, frequent use, and

proximity to Long Island Sound. Each of them have issues related to saltwater intrusion and

runoff and have large impervious parking lots, which can exacerbate runoff issues. Suggestions

for both of these sites include the installation of permeable pavement, bioswales, and tree

boxes to deal with any runoff and decrease the potential for nutrients and pollutants leaching

into Long Island Sound. Implementation of backflow protectors and tide gates could prevent

saltwater intrusion.

Northport, NY

MAIN STREET PARKING LOTS – Bordering Northport Harbor, the Village of Northport has

many large parking lots, with impervious surfaces, directly along the harborfront and all along

Main Street, which runs downhill in the direction of the harbor. The elevation and topography

of this area poses some real challenges in mitigating stormwater issues as large amounts of

water run downhill during major storms. Stormwater collects in these parking lots, increasing

the potential of runoff. It is imperative to capture this stormwater uphill before it reaches the

harborfront. To add to the complexity of this situation, a 4-foot sea level makes any kind of

underground stormwater storage system very difficult to implement. Given these complexities,

many parking lots along Main Street, uphill from the harbor, have been identified as potential

green infrastructure sites to capture the stormwater before it runs downhill into the harbor.

Page 52: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

27

CHURCHES – Churches also act as valuable partners because of

their outreach capabilities and the fact that they typically own

parking lots that can act as possible demonstration sites. Much

like schools, churches have the capability to educate and inform

individuals directly within the community and to reach a broad

audience. The Village of Northport is already working with St.

Philip Neri and the Presbyterian Church to install additional catch

basins in their parking lots. Many churches have been identified as

potential sites because their lots are underutilized most days of

the week.

MUNICIPALITIES – A key theme in implementing green infrastructure should be focused on the idea of

connectivity – not only how existing and potential projects interconnect, but also how all of the

municipalities interconnect and work together to manage stormwater. By working together, municipalities

can help mitigate and solve issues related to funding, outreach, education, and recognition. Collaboration

amongst multiple municipalities will help to address the many water quality and stormwater issues of the

area and help us understand how all of the projects fit together to address these issues.

The Inter-municipal Council (Northport, Asharoken, and Huntington) was created to seek out more funding

and to form partnerships with other organizations in order to address many of these issues. Similarly, the

Oyster Bay-Cold Spring Harbor Committee is also composed of representatives from neighboring

municipalities with the goal of creating partnerships to improve the water quality of the watershed on the

North Shore. This committee, in particular, is seeking more representation from residents in the Huntington

Harbor region. There is a great opportunity for these councils and committees to work together to apply for

funds, potentially do group purchasing, and target the most opportune grants available.

Yet, unwillingness to fully embrace green infrastructure is a limiting factor to the fulfillment of these ideas

of connectivity and inter-municipal collaboration. This government push-back against implementation may

be due to the lack of information and understanding of the environmental benefits and funding

opportunities for green infrastructure. One option to improve on this lack of understanding and knowledge

is to hold educational forums to provide this crucial information to government leaders, consultants, and

their staff. Topics to be covered in these forums could

include funding opportunities, discussions on what’s

required to apply for grants and how to effectively

create an appealing grant proposal, teachings on the

steps required to apply for grants, and discussions on

the environmental and financial benefits associated with

green infrastructure. Furthermore, a “Green

Infrastructure Tour” of the area could be held as a

beneficial follow-up event in order for everyone to see

firsthand what is possible. The key is to educate the

leaders in the government who could have the greatest

impact.

Page 53: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

28

General Information on Green Infrastructure

EPA GREEN INFRASTRUCTURE TOOLKIT – http://water.epa.gov/infrastructure/greeninfrastructure/

index.cfm#tabs-1

EPA PLANNING AND MODELING GREEN INFRASTRUCTURE FOR COMBINED SEWER OVERFLOW (CSO)

CONTROL – http://water.epa.gov/infrastructure/greeninfrastructure/upload/Greening_CSO_Plans.PDF

FUNDING SOURCES – http://water.epa.gov/infrastructure/greeninfrastructure/gi_funding.cfm

Information on School and University Programs

EPA CAMPUS RAINWORKS CHALLENGE – Challenge for undergraduate and graduate students. Once again, EPA

is inviting student teams to design an innovative green infrastructure project for their campus showing how manag-

ing stormwater at its source can benefit the campus community and the environment. http://water.epa.gov/

infrastructure/greeninfrastructure/crw_challenge.cfm

GREEN STREETSCAPES – http://www.epa.gov/brownfields/sustain_plts/reports/Streetscapes_Final_7_31_09.pdf

VIII. ADDITIONAL RESOURCES

Page 54: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

29

IX. SAMPLE SITE PLAN

Page 55: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

30

This Page Intentionally Left Blank

Page 56: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

31

United States Environmental Protection Agency. Stormwater Homepage. <http://water.epa.gov/polwaste/npdes/stormwater/index.cfm>

United States Environmental Protection Agency. What Is Green Infrastructure? <http://water.epa.gov/infrastructure/greeninfrastructure/gi_what.cfm>

United States Environmental Protection Agency. Low Impact Development (LID). <http://water.epa.gov/polwaste/green/>

Department of Environmental Resources, Maryland. "Bioretention Manual." 2007. <http://www.aacounty.org/DPW/Highways/Resources/Raingarden/RG_Bioretention_PG CO.pdf>

Peck, S. and M. Kuhn. 2003. Design Guidelines for Green Roofs. Canada Mortgage and Housing Corporation and the Ontario Association of Architects.

Metropolitan Area Planning Council. Massachusetts Low Impact Development Toolkit. <http://www.mapc.org/sites/default/files/LID_Fact_Sheet_-_Permeable_Paving.pdf.>

Clean Water America Alliance. 2011. Barriers and Gateways to Green Infrastructure. <http://www.uswateralliance.org/pdfs/gireport.pdf>

United States Environmental Protection Agency. 2006. Costs and Benefits of Storm Water BMPs. <http://water.epa.gov/scitech/wastetech/guide/stormwater/upload/2006_10_31_guide_stormwater_usw_d.pdf>

Buckley, M., Souhlas, T., Hollingshead, A. 2011. Economic Benefits of Green Infrastructure. ECONorthwest. <http://www.americanrivers.org/assets/pdfs/reports-and-publications/20498-great-lakes-final-2011-1213.pdf>

United States Environmental Protection Agency. 2004. Landscaping with Native Plants. <http://www.epa.gov/greenacres/conf12_04/conf_knwldge.html>

Federal Emergency Management Agency. 2005. Reducing Damage from Localized Flooding. <http://www.fema.gov/media-library-data/20130726-1446-20490-0539/FEMA511-complete.pdf>

Upstate Forever. Rain Gardens. Low Impact Development Center. <http://upstateforever.org/pdfs/other/CAW_LIDFact_RainGardens.pdf>

Howley, Rick. Retrofitting Urban Stormwater Infrastructure for Treatment and Ecological Enhancement in Philadelphia, PA. Philadelphia Water Department. <https://www.fws.gov/chesapeakebay/masrc/MASRC%20PDFs/G_session_web/1_G_Rick%20Howley.pdf>

Clark, M., Acomb, G. Water Resources Roundtable: Low Impact Development and Integrated Management Practices. University of Florida. <http://publicfiles.dep.state.fl.us/dwrm/stormwater/stormwater_rule_development/docs/fl_asla_presentation.pdf>

Interlocking Concrete Pavement Institute. 2004. Glen Brook Green Subdivision, Waterford, Connecticut. <https://www.icpi.org/sites/default/files/ICPIAugust2004NEWp10_13.pdf>

X. LITERATURE CITED

Page 57: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

32

Tzoulas, K., Korpela, K., Venn, S., Yli-Pelkonen, V., Kazmierczak, A., Niemela, J., James, P. 2007. Promoting ecosystem and human health in urban areas using Green Infrastructure: A literature review. ScienceDirect. 81 (3), 167-178.

United States Environmental Protection Agency. 2000. Low Impact Development (LID): A Literature Review. <http://water.epa.gov/polwaste/green/upload/lid.pdf>

Foster, J., Lowe, A., Winkelman, S. 2011. The Value of Green Infrastructure for Urban Climate Adaptation. The Center for Clean Air Policy. <http://ccap.org/assets/The-Value-of-Green-Infrastructure-for-Urban-Climate-Adaptation_CCAP-Feb-2011.pdf>

Burns, P., Flaming, D. 2011. Water Use Efficiency and Jobs. Economic Roundtable. <http://www.cacoastkeeper.org/document/water-use-efficiency-and-jobs.pdf>

Hewes, W. 2008. Creating Jobs and Stimulating the Economy through Investment in Green Water Infrastructure. American Rivers & Alliance for Water Efficiency. <http://www.americanrivers.org/assets/pdfs/green-infrastructure-docs/green_infrastructure_stimulus_white_paper_final.pdf>

PlaNYC. 2014. Progress Report 2014. The City of New York. <http://www.nyc.gov/html/planyc2030/downloads/pdf/140422_PlaNYCP-Report_FINAL_Web.pdf>

The Louis Berger Group, Inc. 2008. Analysis of Job Creation in PlaNYC Final Report. <http://www.nyc.gov/html/om/pdf/2008/pr110_planyc_job_creation_analysis.pdf>

Stormwater Manager’s Resource Center. Wetlands and Watercourses Ordinance. Croton-on-Hudson, NY. <http://www.stormwatercenter.net/Model%20Ordinances/misc__wetlands.htm>

Town of East Hampton, NY. Harbor Protection Overlay District. <http://ecode360.com/10414586?highlight=overlay%20districts,overlay%20district,districts,district,harbors,overlay,harbor%2310414586>

Town of North Hempstead, NY. Stormwater pollution prevention plans. <http://ecode360.com/9298140>

Onondaga County. Save the Rain. Accessed November 12, 2014. <http://savetherain.us/>

Town of Oyster Bay, NY. Stormwater Management and Erosion and Sediment Control. <http://ecode360.com/26884711?highlight=stormwater>

BGreen 2020: A Sustainability Plan for Bridgeport, Connecticut. 2013. 2013 Progress Report. <http://www.bgreenbridgeport.org/storage/documents/Bgreen-2020-2013-Progress-Report.pdf>

Town of Vernon. 2013. Low Impact Development Stormwater Quality Manual. <http://www.vernon-ct.gov/files/VernonGuidelinesStormWater_2013.pdf>

The City of Annapolis, Maryland. Stormwater Management and Sediment and Erosion Control. <http://www.ci.annapolis.md.us/government/city-departments/neighborhood-environmental/stormwater-management>

Stormwater Manager’s Resource Center. Lake Travis Nonpoint Source Pollution Control Ordinance. Lower Colorado River Authority. <http://www.stormwatercenter.net/Model%20Ordinances/misc__lake_travis.htm>

Montgomery Country, MD: Environmental Protection. What are RainScapes? <http://www.montgomerycountymd.gov/DEP/water/rainscapes.html>

Page 58: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

33

United States Environmental Protection Agency. Ordinance on Riparian Habitat Areas: City of Napa, California. <http://water.epa.gov/polwaste/nps/upload/nps-ordinanceuments-a2c-napa.pdf>

United States Environmental Protection Agency. Rhode Island Coastal Zone Program. <http://water.epa.gov/polwaste/nps/upload/nps-ordinanceuments-a2b-rhode-island.pdf>

District Department of the Environment. RiverSmart Homes. <http://green.dc.gov/riversmarthomes>

National Fish and Wildlife Foundation. Long Island Sound Futures Fund. <http://www.nfwf.org/lisff/Pages/home.aspx#.VGoLs_nF-Sp>

Long Island Sound Study. 2012. $1.6 Million Awarded for Community-Based Projects to Improve Health of Long Island Sound. <http://longislandsoundstudy.net/2012/09/more-than-1-6-million-awarded-for-community-based-projects-to-improve-health-of-long-island-sound/>

National Fish and Wildlife Foundation. 2012. Long Island Sound Futures Fund 2012 Project Descriptions. <http://www.nfwf.org/lisff/Documents/lisff_2012_projects.pdf>

New York State Environmental Facilities Corporation. Green Grants. <http://www.efc.ny.gov/Default.aspx?tabid=461>

Public Works. Water Quality Protection and Restoration Program. <http://efc.muskie.usm.maine.edu/conservation_finance/LESSON_5.htm>

Save the Rain. Green Improvement Fund (GIF). <http://savetherain.us/green-improvement-fund-gif/>

Save the Rain. Suburban Green Infrastructure Program (SGIP). <http://savetherain.us/sgip/>

City of Binghamton, New York. City of Binghamton 50/50 Stormwater Management Fund. <http://www.binghamton-ny.gov/sites/default/files/files/50_50%20Stormwater%20Fund%20Matching%20Grant%20FAQ.doc__0.pdf>

United States Environmental Protection Agency. Funding Opportunities. <http://water.epa.gov/infrastructure/greeninfrastructure/gi_funding.cfm>

United States Environmental Protection Agency. Clean Water State Revolving Fund. <http://www.epa.gov/owm/cwfinance/cwsrf/green_if.pdf>

U.S. Department of Housing and Urban Development. National Disaster Resilience Competition. <http://portal.hud.gov/hudportal/documents/huddoc?id=FactSheet_071514.pdf>

Illinois Environmental Protection Agency. 2014. Illinois Green Infrastructure Grant Program from Stormwater Management Biannual Report. <http://www.epa.state.il.us/water/financial-assistance/publications/igig-progress-report.pdf>

Energy and Environmental Affairs. Green Infrastructure for Coastal Resilience Pilot Grant Program. <http://www.mass.gov/eea/agencies/czm/program-areas/stormsmart-coasts/green-infrastructure-grants/>

San Francisco Water Power Sewer. Urban Watershed Stewardship Grants. <http://sfwater.org/index.aspx?page=104>

National Wildlife Federation. Green Ribbon Schools. <http://www.nwf.org/Eco-Schools-USA/About-Eco-Schools-USA/Green-Ribbon-Schools.aspx>

Page 59: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

34

Page 60: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Download the Report:

http://bit.ly/1yvO08i

Acknowledgements We would like to thank the Long Island Sound Futures Fund, NFWF and the Long Island Sound Study for their generous grant support.

Thank you to our supporting vendors!

Green Solutions to Stormwater Pollution

Managing Stormwater with Natural

Vegetation and Green Methodologies

February 5, 2015 1pm – 4pm

Suffolk County Legislative Building Veterans Memorial Highway, Hauppauge, NY

Page 61: Easygrants ID: 39467 National Fish and Wildlife Foundation ... · Complex; (4) considered modifications to codes, ordinances, and land use policies to encourage LID techniques as

Green Solutions to Stormwater Pollution

February 5, 2015

1pm – 4pm

Suffolk County Legislative Building

Veterans Memorial Highway, Hauppauge, NY

1:00pm —Welcome

Suffolk County Executive Steve Bellone

Dave Calone, Chairman, Suffolk County Planning Commission

Legislator Kara Hahn, Suffolk County Legislature

1:30pm —Presentations

Why we need Green Infrastructure on Long Island

Adrienne Esposito, Executive Director, Citizens Campaign

for the Environment

Assessing Green Infrastructure

Maureen Krudner, Green Infrastructure Coordinator, U.S.

Environmental Protection Agency, Region 2

Green Infrastructure Funding Opportunities and Onondaga

County's Save-the-Rain Program Case Study

Melissa Young, Assistant Director, Syracuse University

Center for Sustainable Community Solutions (CSCS) /

Syracuse Environmental Finance Center (Syracuse EFC)

Sustainable Long Island’s “Reduce Rain Runoff” Initiative

Amy Engel, Executive Director, Sustainable Long Island

2:40pm —Case Examples of Green Infrastructure on Long

Island

Yes We Can Center

Michael Levine, North Hempstead, Commissioner of

Planning

Gerard Street Parking Lot

Nicholas P. Jimenez, Town of Huntington, Assistant Civil

Engineer

Green Roofs

Melissa Daniels, Vice President Plant Connection

Focal Point: High Performance Biofilter

John Markee, VP Sales and Marketing, FABCO Industries,

Inc.

Conscience Bay Restoration

Erin Brosnan, Ecologist/Restoration Specialist, GEI

3:55pm —Closing Remarks

Dominique Kone, Climate & Wildlife Safeguards Intern,

National Wildlife Federation