Page 1: Economical Guidelines for Design  of Structural Steel

1

Economical Guidelines for Design of Structural Steel

By Gary Glenn 07/30/13

Page 2: Economical Guidelines for Design  of Structural Steel

2

Structural Steel Costs (Where is the Money?)

Page 3: Economical Guidelines for Design  of Structural Steel

3

Breakdown of Structural Steel Costs (by % )

Material, 33.6%

Erection, 22.7%

Fabrication, 19.5%

BRB, 7.7%

Freight, 4.4%

Detailing, 3.9%

Tax, 3.5%Other, 4.8%

Page 4: Economical Guidelines for Design  of Structural Steel

4

Breakdown of Structural Steel Costs (in Dollars)

Material, $1,781,490

Erection, $1,204,564

Fabrication, $1,037,316

BRB, $406,899

Freight, $235,420

Detailing, $205,599Tax, $184,008

Other, $254,526

Above is based on 1,773 ton avg project, $5,309,823 avg price,$3,117/ton avg.

Page 5: Economical Guidelines for Design  of Structural Steel

5

Conclusions from Steel Costs1. Fabrication and Erection costs are same magnitude as

Material. In addition to Material costs, Fabrication and Erection costs should be a consideration in design.

2. Detailing costs are significantly lower than the cost of Fabrication and Erection (by a factor of 10). Efforts to minimize Detailing costs at the expense of Fabrication and Erection costs should be avoided.

Page 6: Economical Guidelines for Design  of Structural Steel

6

Material Availability Factors1. Domestic vs Offshore (or Single Source) Material

2. A36 (Flatbar) vs A572 Gr 50 (Sheet)

3. A529 Gr 50/55 (Flatbar) vs A572 Gr 50 (Sheet)

4. Anchor Bolt Grades

5. A325 vs A490 Bolts and Diameters

6. Sole Source Product

Page 7: Economical Guidelines for Design  of Structural Steel

7

WF Availability

Page 8: Economical Guidelines for Design  of Structural Steel

8

Domestic WF Mills1. Nucor Yamato – WF mill located in Arkansas.

– W6 to W44s. W14s up to W14x730 (A992) (50 yield). – W14x550s and larger may be rolled based on tonnage accumulation. – Check w/ Fabricator for availability.

2. Steel Dynamics Inc. (SDI) `– WF mills located in Indiana. – Lighter WF sections from W6 to W36.

3. Chapparel – WF mill located in Texas.– Smaller, lighter WF sections.

4. Warehouses (PDM, Gerdue Ameristeel, R&S, etc) – – Lighter WF sections.– Premium in cost to purchase through warehouses.– Some fabricators do you have credit with mills, thus purchase thru warehouse.

5. Mill material is normally shipped via rail to fabricator yard. Warehouse is normally shipped via truck.

Page 9: Economical Guidelines for Design  of Structural Steel

9

Offshore WF Mills1. Arcelor / Mittal – Mills located in Luxemburg.

– W14x550 thru 730s, in A992 (50 ksi yield) that may not be domestically produced.– Also, various WF sections in A913 Gr 65.

2. Nippon - Mills located in Japan. – WF sections including W14x550 thru 730s in A992 (50 ksi yield) that may not be domestically

produced.– Currently developing equivalent to A913 Gr 65, but not yet approved by ASTM.

3. Pros of Offshore Material– Availability of larger sections not domestically produced in lieu of builtup WF or box columns.– Availability of A913 Gr 65 that is not domestically produced.

4. Cons of Offshore Material– Prone to schedule problems (no commitment is literally written into their Purchase Agreements;

Fabricators have little influence over offshore mills). (Rolls are based on tonnage accumulation; mills are shutdown for maintenance; vessels depart once a month; vessels can offload at wrong port; delays in customs/offloading, etc).

– Cost premium. For example, W14x730 A913 Gr 65 at $.75/#. W14 A992 domestic sizes might be around $.39/#.

– Sole source material.– Welding of A913 Gr 65 requires E80 electrodes or qualification of welding procuedures to achieve

high yield at welds. Only applies when welding Gr 65 to Gr 65 material (splicing).

Page 10: Economical Guidelines for Design  of Structural Steel

10

Specifying WF1. Desirable to specify domestic (not offshore),

unless domestic size will not work.

2. In general, you can check Nucor Yamato website for produced sections. For heavier sections, suggest checking w/ fabricator to confirm.

3. Avoid offshore material, except when domestic sizes will not work. Suggest reviewing w/ fabricator when considering offshore steel.

Page 11: Economical Guidelines for Design  of Structural Steel

11

Flatbar (FB)

Page 12: Economical Guidelines for Design  of Structural Steel

12

Plate (PL) or Sheet

Page 13: Economical Guidelines for Design  of Structural Steel

13

FB Availability1. Available in std widths of ½” or 1” increments, and thickness

increments of 1/8”

2. A36 FB readily available from warehouse. (A36 also available in plate (sheet)).

3. A529 Gr 50/55 – FB available from mills and usually must be ordered in bundle qnty or

min tonnage.– Available widths and thickness is more limited than what is available

for A36. – A529 Gr 50/55 is a material now specified in AISC Steel Construction

Manual (13th Ed Black).

4. A572 Gr 50 is not generally produced in FB. Instead, it is available in Plate or Sheet (5’ x 12’, 10’ x 12’, 10’ x 20’, etc).

Page 14: Economical Guidelines for Design  of Structural Steel

14

Example of Widths/Thickness Used for Detailing FB Parts

Chart 1 - Use this for A36 material.Thickness 1/8 3/16 1/4 5/16 3/8 1/2 5/8 3/4 7/8 1 > 1**

Chart 2 - Use this for Gr 50 material.Thickness 3/16* 1/4 5/16 3/8 1/2 5/8 3/4 7/8* 1 > 1 **

4 44 1/2 4 1/2

5 5 5 56 6 6 6 6 6 67 7 7 78 8 8 8 8 8 8

9 910 10 10 10 10 10

12 12 12 12 12

** For material that is > 1", material is available in 1 1/8", 1 1/4", and 1/4" increments above 1 1/4".

678

Deta

iled

Widt

h

See

Char

t 1

91012

11 1/2

2De

taile

d W

idth

2 1/23

3 1/24

4 1/25

Page 15: Economical Guidelines for Design  of Structural Steel

15

FB vs Plate

Page 16: Economical Guidelines for Design  of Structural Steel

16

Advantages of FB over PL (Sheet)

1. By multing shear PLs, Stiffeners, etc. into lengths of FB, only one edge of part must be cut.

2. FB is easier to handle than PL (sheet), and takes up less floor space.

3. There is less drop in producing parts from FB over PL (mult end to end out of FB where as parts nested in PL)

4. There is slight premium in Gr 50 PL over A36. Probably $.01/# premium.

Page 17: Economical Guidelines for Design  of Structural Steel

17

Multing vs Nesting

4 ½ x 5/8 x 20' - 0 Flat Bar

Shear PL, 4 ½” long, 5/8" thick

Shear PLs “Multed” in Flat Bar

Shear PLs “Nested” in PL

Mill Rolled Edges Only Ends are Cut

Ends and Sides are Cut

Page 18: Economical Guidelines for Design  of Structural Steel

18

Specifying PL and FB Material1. Spec A36 where possible. Allows fabricator to produce parts out

of A36 FB widths.

2. Spec that A529 Gr 50/55 or A572 Gr 50 may be utilized in lieu of A36 as fabricator option. Allows fabricator max flexibility to utilize materials on hand and to minimize drop.

3. Where 50 ksi Fy is necessary, spec A529 Gr 50/55 and A572 Gr 50. Allows fabricator flexibility to use FB as an option in lieu of having to cut from PL where possible.

4. Make it very clear where 50 ksi Fy is required so fabricator need not have to clarify extent in RFI (specify it right at details??).

Page 19: Economical Guidelines for Design  of Structural Steel

19

Anchor Bolt (AB) Availability1. A36 Rod or F1554 A36 (all thread) –

– Most readily available and cost effective. – Specify either, giving fabricator flexibility.

2. High Strength ABs - – Heat treated, increasing cost and leadtime.– F1554 Gr 55 or 105 or A354 BD are common and available.– A307, A325, A490 are generally bolt (fastener) specifications and

should not be used at anchor bolts (due to lack of availability).– A449 and A572 are less commonly available and should be avoided.

3. Double Nut End is desirable over a Headed or J End -– Head or J end must be fabricated by supplier and has leadtime.– Double Nut End allows straight bolts to be used with all thread or

threaded shaft, which is more economical.– Exception is short anchor bolts at ledger angles. In this situation,

headed A307 bolts may be desirable.

Page 20: Economical Guidelines for Design  of Structural Steel

20

Anchor Bolt Availability & Issues1. Nut Types –

– ASTM defines exactly which types of nuts are to be provided for grade of anchor bolt, such that the shaft fails prior to the nut. The supplier must follow ASTM.

– So, it should not be necessary to specify the exact nut grade and type (such as A563 Gr A for example), as this simply creates confusion and additional cost to fabricator.

2. Welding at Anchor Bolts – Should be avoided. Cannot occur at high strength bolts as it destroys the heat treatment properties.

3. Spoiling Threads – Double Nuts jambed together is preferable over spoiling threads.

Page 21: Economical Guidelines for Design  of Structural Steel

21

Field Bolts

Page 22: Economical Guidelines for Design  of Structural Steel

22

Field Bolts - A325 vs A490 Bolts1. Bolt Cost (based on 2” long TC bolts)

– 7/8” A325 $0.14– 7/8” A490 $0.16– 1” A325 $0.18– 1” A490 $0.22– 1 1/8” A325 $0.22– 1 1/8” A490 $0.28

2. Installation Cost of Bolts– 7/8” and 1” cost about same to install.– 1 1/8” costs about 15% more than 7/8” or 1” to install.– 1 ¼” costs about 30% more than 7/8” or 1” to install.

3. 1 ½” A325 or A490 bolts should be avoided due to tightening issues (if fully torqued, requires hydraulic gun vs TC gun or traditional impact wrench).

4. A325s tend to be more readily available than A490s. Minor risk in switching.

5. Conclusion – 1” dia. A325 may be most cost effective for typical connections.6. Minimize Different Diameters/Grades used on Project (use all 1” bolts). This allows:

– Erector to utilize one dia set of guns onsite.– Allows fabricator/erector to consolidate bolts together.– Simplifies detailing, fabrication, erection.– Reduces errors.

Page 23: Economical Guidelines for Design  of Structural Steel

23

Field Bolts – Other Consideration1. TC vs Std Hex Head

– Spec both giving fabricator/erector flexibility to use either.– Considerations such as length, access, equipment, thru bolts at HSS dictate which will be

used.

2. Bearing Type Bolts– Generally, there is no cost difference in X over N in the bolt or installation.– So, suggest specifying X so as to take advantage of higher bearing capacity.

3. Slip Critical Type Bolts– There is a slight cost difference in specifying SC, primarily due to inspection.– Suggest only specifying SC at SLRS (collectors, frames, etc) locations.

4. LIWs (Load Indicator Washers)– Can cost as much as the bolt itself. – Also, costly to install. – TC, Calibrated Wrench, or Turn of the Nut methods for achieving SC are cost effective and

reliable methods, so LIWs should be avoided.

5. Lock Washers – Not applicable to high strength bolts and should be avoided.

Page 24: Economical Guidelines for Design  of Structural Steel

24

Sole Source Products (Avoid)

Page 25: Economical Guidelines for Design  of Structural Steel

25

Tolerance and Deflection Issues

1. Variation in WF – Depth and out of squareness.

2. Anchor Bolt Tolerance & Oversize Holes –

3. Steel vs Finish System Tolerances –

4. Lack of Camber and Floor Deflection -

Page 26: Economical Guidelines for Design  of Structural Steel

26

Varying Depth of WFCJP,Typ

5/16 4-24Typ

1", typ.

PREFEREDCOSTLY

Page 27: Economical Guidelines for Design  of Structural Steel

27

Oversizing AB Holes1. Anchor Bolt Tolerance

– Patterns can be ¼” off from grid.– Patterns can be ¼” off relative to each other.– Bolts w/in pattern can be 1/8” off from each other.

2. Erection Tolerance – Column base can be ¼” off in location.

3. Oversized Holes in Base PLs (Necessary for 1 and 2 above)– Recommend oversized holes per AISC ASD 9th Ed (Green Manual pg 4-130).– Size is adequate for AB tolerances, yet not too large to where std washers

begin cupping.– Oversized holes per AISC 13th Ed (Black Manual pg 14-21) requires use of PL

washers in lieu of std washers, increasing costs.

4. DSA – We have seen DSA try to limit AB hole diameters to 3/16” oversized, creating substantial issues.

Page 28: Economical Guidelines for Design  of Structural Steel

28

Steel vs Finish System Tolerance1. Allowable Steel Tolerance Exceeds Finish

System Tolerances significantly.

2. Suggest designing 1” to 1 ½” gap between studwall/window wall system and edge of steel horizontally and vertically.

3. Applies to perimeter of building, canopies, soffits, roof screens, etc.

Page 29: Economical Guidelines for Design  of Structural Steel

29

Example of Accumulation of Tolerances Affecting Elevations

+3/8"

-¾” -1"-¾”

-7/16

-1"-¾”

-1"-¾”

FLR 0

FLR 0+3/16"

+1/16"

-5/16" -¼”

+1/8"

-5/16"

-1/16"

-5/16"-¼”

-¼”

B A

-1/8"Elevation Along Grid AIn Summary:1. Flr to Flr height @ steel along grid A could be off up to 1 3/8" due to accumulation of steel tolerances + deflection of steel under concrete loading.2. Top of steel could vary from +3/8", -¾” @ grids, and up to -1" @ center of bays

AISC Tolerances:1. Base may be +/-1/8".2. Length may be +/- 1/16"3. Connection may be +3/16", -5/16" from splice.4. Outriggers can slope 1/500 = 1/8".Defection from Concrete Loading:5. Outrigger = -1/8"?6. Center Span of beam = ¼”?

= -1/8"-5/16"-¼”-1/16"= +1/8"-5/16"-¼”

0"

+1 3/8"

Page 30: Economical Guidelines for Design  of Structural Steel

30

Example of Deflection Issue

Page 31: Economical Guidelines for Design  of Structural Steel

31

Example of Deflection Issue

Page 32: Economical Guidelines for Design  of Structural Steel

32

Warpage and Distortion Considerations

Some items contributing to warpage/distortion:

1. Continuous Welding (vs Stitch Welding)

2. Unsymmetrical Sections

3. Relatively Thin Material

Page 33: Economical Guidelines for Design  of Structural Steel

33

Problematic Section

10GA Bent PL

C3x4.1

FinishSystem

HSS8x8x1/4

Page 34: Economical Guidelines for Design  of Structural Steel

34

Improved Section

¼” Bent PL

HSS 3 x 2 x 0.180

FinishSystem

HSS8x8x1/4

1/8 2-24

1/8 2-24

(1/8) 2-24

1/8 2-24

Page 35: Economical Guidelines for Design  of Structural Steel

35

Stitch Welding

Page 36: Economical Guidelines for Design  of Structural Steel

36

Weld Types

1. Fillet Welds

2. PJP Welds

3. CJP Welds

Page 37: Economical Guidelines for Design  of Structural Steel

37

Fillet Weld Guidelines1. AWS D1.1 - Single pass fillet welds up to 3/8”

in flat / horizontal positions allowed.2. In practicality, some 3/8” fillet welds cannot be

made in a single pass.3. ½” fillet weld ≈ 3 passes.4. 5/8” fillet weld ≈ 4 passes.5. ¾” fillet weld ≈ 6 passes.6. 1” fillet weld ≈ 10 passes.In summary, 5/16” or smaller fillet welds desirable.

Page 38: Economical Guidelines for Design  of Structural Steel

38

Minimum Fillet Weld SizePer AWS D1.1 2008 Structural Welding Code:

Base Metal Thickness Min Fillet Weld SizeT < ¼” 1/8”¼” < T < ½” 3/16”½” < T < ¾” ¼”¾” < T 5/16”

Page 39: Economical Guidelines for Design  of Structural Steel

39

PJP Weld vs Fillet Welds1. PJP (vs Fillet)

– Requires prepping.– Fitup is more costly.– Meeting inspection more costly.

2. 5/16” fillet weld generally desirable over PJP welds.

3. > 3/8” fillet welds require multipasses, so GMC starts reviewing as to whether a PJP or CJP may be more cost effective than the fillet weld.

4. Suggest reviewing fillet welds > 3/8” w/ fabricator as to cost effectiveness.

Page 40: Economical Guidelines for Design  of Structural Steel

40

CJP vs PJP vs Fillet

1. CJP (vs PJP or Fillet)– Requires beveling. – Either requires backup bar & runnoff tabs, or back

gouging (fitup is costly).– UT inspection is costly.– Again, this requires additional labor and process

over fillet welding.

2. Again, GMC starts to consider PJP or CJP welding when fillet welds are > 3/8”.

Page 41: Economical Guidelines for Design  of Structural Steel

41

SLRS Members, DC Welds, Charpy Electrode, and Preheat

1. SLRS Members– Clearly define which members are SLRS (show on plans,

frame elevations, and column schedule).2. DC Welds

– Clearly show DC in weld tails in design details to signify DC welds.

3. Charpy Electrode– Avoid specing Charpy rated electrodes at all welds.– Charpy rated electrodes should only be needed at SLRS

members and DC welds.4. Preheat, Interpass Temperature, Postheat Treatment

– Avoid calling out preheat or interpass temperature above and beyond typical AWS. Very costly to preheat.

– Postheat treatment is not practical.

Page 42: Economical Guidelines for Design  of Structural Steel

42

Charpy vs Non-Charpy Electrode

Page 43: Economical Guidelines for Design  of Structural Steel

43

Preheat

Page 44: Economical Guidelines for Design  of Structural Steel

44

Preheat

Page 45: Economical Guidelines for Design  of Structural Steel

45

Bolted vs Welded Connections

• Oftentimes, a field bolted connection is desirable over a field welded connection.

– Expedites erection considerably.

– Reduces inspection.

– Less skill required to install bolts.

– Improves safety.

Page 46: Economical Guidelines for Design  of Structural Steel

46

Expedited Erection!

Page 47: Economical Guidelines for Design  of Structural Steel

47

Expedited Erection!

Page 48: Economical Guidelines for Design  of Structural Steel

48

Expedited Erection!

Page 49: Economical Guidelines for Design  of Structural Steel

49

Bolted vs Field Welded Connection

Page 50: Economical Guidelines for Design  of Structural Steel

50

Dimensional Concerns (Location of Framing)

1. Lack of dimensional information on Structural Drawings is costly to Fabricators.

2. When GMC has to release partial packages into production due to missing dimensions, efficiency dramatically drops.

- Dbl handling of material due to beam multed in on mill stick- Can’t stage, fit, weld out all beams on floor at one time (must stage

twice)- Lost efficiency in loss of numbers.- Increased time needed for fabrication, requiring lost efficiency in

expediting work.- Disruption to flow of production of multiple projects through plants.

3. For example, releasing a 1,700 ton project for fabrication w/ 25% beams on hold may cost over $100 k in lost efficiency.

Page 51: Economical Guidelines for Design  of Structural Steel

51

Staged Floor

Page 52: Economical Guidelines for Design  of Structural Steel

52

Methods to Communicate Dimensions

1. Ideally, present dimensions to CL of all beams.

2. Alternatively, utilize EOS Drawings. Then, spec standard set back from EOS to centerline of WF or HSS members, and face of C or L at openings and perimeter steel.

3. Make clear orientation of C or L (toe in relative to edge of slab opening).

Page 53: Economical Guidelines for Design  of Structural Steel

53

Reinforcement of Sections vs Heavier Sections

1. Elimination of Continuity PLs – – May not be feasible if testing of SLRS system was done with

continuity plates.– Eight 1 ½” continuity PLs might cost $3,588.– Increasing W14x211 to W14x257 (45ft) might cost around $1,604.

2. Elimination of Doubler PLs –– Two 7/8” x 24” long doubler PLs might cost around $974. – Increase W14x211 to W24x257 (45ft) might cost around $1,604.

3. Offshore A913 Gr 65 Steel vs Plated Columns or Cruciform Columns –

– A913 is around $.75/# and poses risk. (Domestic A992 is around $.62/#).

– However, it is likely more cost effective than plating columns or constructing cruciform columns.

Page 54: Economical Guidelines for Design  of Structural Steel

54

Considerations for Standard Design Details

1. Show min/max dimensions (instead of fixed dimensions) at beam connection details. – Allows fabricator to detail in FB widths.– Allows fabricator to standardize parts.

2. Edge Distance –– Avoid showing, unless edge distance > AISC min is req’d (fabricator must use

AISC edge distance regardless). – Allows fabricator maximum flexibility to utilize FB and standardize parts.

3. Beam End Clearance – – Design at least ¾” clearance from end of beam to face of connecting surface. – Anything smaller requires control of weld size and cutting mill cut ends.– Avoid showing.

4. Shop vs Field Weld Symbols – – Avoid showing field vs shop symbol at welds on design. – Gives fabricator/erector maximum flexibility to do what is most economical

and safe.

Page 55: Economical Guidelines for Design  of Structural Steel

55

Example of Ideal Detail3" max

AISC min.

3",typ

Page 56: Economical Guidelines for Design  of Structural Steel

56

Paint and Galvanizing Considerations

Prime painting a beam w/ std primer, SP-2 preparation may increase cost of that member by 10% (example: $179 out of $1,992 for W24x55 x 25’ long girder).

Galvanizing or Blast & Painting a member may increase cost of that member by 30% (example: $567 out of $2,380 for W24x55 x 25’ long girder).

So, minimize cost by:

• Spec no primer at steel enclosed in finish.

• Specify SP-2 or SP-3 (hand or hand tool cleaning) prep and primer for interior exposed to view conditions.

• Only specify SP-6 (sand blasting) zinc rich primers for steel exposed to weather.

• Galvanizing is often desirable over SP-6 zinc rich primer.

• Avoid priming over top of galvanized steel.

Page 57: Economical Guidelines for Design  of Structural Steel

57

AISC Regarding Priming Steel Enclosed in Finish

1. Steel Construction Manual, 13th Ed, pg 2-31 states:

– “Corrosion Protection – In building structures, corrosion protection is not required for steel that will be enclosed by building finish… When enclosed, the steel is trapped in a controlled environment and the products required for corrosion are quickly exhausted…”

2. Priming of member might increase it’s labor by $90, or increasing labor for that member by 20 to 90%.

Page 58: Economical Guidelines for Design  of Structural Steel

58

Galvanizing Considerations1. Fabricator will need to vent. Do not design venting, as

it will vary between fabricators and design details.

2. Avoid thin wall materials (< ¼” in most conditions; a larger wall may be desirable in some situations).

3. Avoid unsymmetrical sections.

4. End caps can be omitted at open ends of horizontals.

Page 59: Economical Guidelines for Design  of Structural Steel

59

Vent Holes

Page 60: Economical Guidelines for Design  of Structural Steel

60

Warpage from Galvanizing

Page 61: Economical Guidelines for Design  of Structural Steel

61

AESS ConsiderationsGrinding of welds at AESS member may increase cost of

that member by 30 to 50%. Removal of backup bars and filling of weld access holes can

further increase cost as well.

• AESS does not require grinding of welds. We generally make welds uniform and remove weld spatter, but do not grind smooth.

• Do not specify to grind welds.

• Desirable to leave Backup bars and weld access holes in place (not practical to fill WAHs)

Page 62: Economical Guidelines for Design  of Structural Steel

62

BIM

Page 63: Economical Guidelines for Design  of Structural Steel

63

BIM Considerations1. There is likely not significant savings in providing model to fabricator:

– Engineer rarely has work points set exactly, or members located in exact location.– Detailer must check model.– There are attributes and connections Detailer must incorporate into the fabrication model.

2. It is likely more cost effective for Detailer to create model from scratch due to above.

3. If Engineer provides model, do not connect. – Fabricators have their own connection macros that are unique to their operations. – Fabricator will follow connection details shown on S-dwgs.

4. Once model is handed off to Fabricator, Detailer cannot easily incorporate another model at a later date. Wait till LRM to push Fabricator to model building.

5. Utilization of Revit Model – – Revit model can be imported into Tekla so as to start a model. – Again, Detailer must check model, so there is not a significant advantage in doing this

(over simply creating model from scratch).– Also, there are attributes that Detailer will need to add to members that are unique to

fabricator. Such attributes must be added to imported members.

Page 64: Economical Guidelines for Design  of Structural Steel

64

LEED1. Recycled content of

steel for project on right is 30%.

2. This is reflective of projects in general.

3. Avoid requiring an exact recycled content in project specifications, as fabricator has very little control in the recycled content in steel (requiring a specific range is almost useless).

Page 65: Economical Guidelines for Design  of Structural Steel

65

OSHPD and DSA Concerns1. Develop relationship with OSHPD District

Engineer.

2. Fabricator will need OSHPD approved (stamped) S-dwgs prior to fabricating.

3. Clear documents and specifications help reduce confusion / issues arising from OSHPD IOR.

Page 66: Economical Guidelines for Design  of Structural Steel

66

Beam CamberCost to mechanically camber a beam may increase cost of that member by 3%

(example: $55 out of $1,868 for W24x55 x 25’ – 0).Cost to flame camber a beam may increase cost of that member by 18%

(example: $328 versus $2,141 for W24x55x25’ – 0).

So:

• Ability to mechanically camber is a function of camber, section, length.

• Avoid excessive cambers. For example, GMC can install up to ¾” camber in W24x55 up to 27’ – 6 length. GMC can install up to 1 ½” camber in W24xt55 from 27’ – 6 to 37’ – 6 length.GMC can install up to 2” camber in W24x55 from 37’ – 6 to 40’ – 6 length.

3. Check with Fabricator when designing large cambers.