egc requests approval of the proposed license amendment by … › docs › ml1324 ›...

14
RS-13-092 September 5, 2013 10 CFR 50.90 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374 Subject: License Amendment Request to Revise Peak Calculated Primary Containment Internal Pressure In accordance with 10 CFR 50.90, "Application for amendment of license, construction permit, or early site permit," Exelon Generation Company, LLC (EGC) requests an amendment to Facility Operating License Nos. NPF-1 1 and NPF-18 for LaSalle County Station (LSCS), Units 1 and 2. The proposed change would revise the peak calculated primary containment internal pressure for the design basis loss-of-coolant accident (LOCA) described in TS 5.5.13, "Primary Containment Leakage Rate Testing Program." The peak calculated primary containment internal pressure, Pa, is increased from 39.9 psig to 42.6 psig. The proposed increase in Pa is the result of a LOCA- Drywell Temperature sensitivity analysis performed by General Electric Hitachi (GEH). Plant operations in TS 5.5.13 are currently administratively controlled under the provisions of NRC Administrative Letter (AL) 98-10, "Dispositioning of Technical Specifications that are Insufficient to Assure Plant Safety," to assure that plant safety is maintained. This license amendment request is submitted in accordance with the guidance in AL 98-10. In accordance with the guidance of AL 98-10, EGC submits the proposed change as a required license amendment request to resolve a non-conservative TS. As such, this is not a "voluntary request from a licensee to change its licensing basis" and should not be subject to "forward fit" considerations. The attached request is subdivided as follows: Attachment 1 provides an evaluation of the proposed change. Attachment 2 provides the current TS page with the proposed change indicated. The proposed amendment has been reviewed by the LSCS Plant Operations Review Committee and approved by the Nuclear Safety Review Board in accordance with the requirements of the EGC Quality Assurance Program. EGC requests approval of the proposed license amendment by September 5, 2014. Once approved, the amendment will be implemented within 60 days. 1 RS-13-092 September 5, 2013 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374 :2000 10 CFR 50.90 Subject: License Amendment Request to Revise Peak Calculated Primary Containment Internal Pressure In accordance with 10 CFR 50.90, "Application for amendment of license, construction permit, or early site permit," Exelon Generation Company, LLC (EGC) requests an amendment to Facility Operating License Nos. NPF-11 and NPF-18 for LaSalle County Station (LSCS), Units 1 and 2. The proposed change would revise the peak calculated primary containment internal pressure for the design basis loss-of-coolant accident (LOCA) described in TS 5.5.13, "Primary Containment Leakage Rate Testing Program." The peak calculated primary containment internal pressure, P a , is increased from 39.9 psig to 42.6 psig. The proposed increase in P a is the result of a LOCA- Drywell Temperature sensitivity analysis performed by General Electric Hitachi (GEH). Plant operations in TS 5.5.13 are currently administratively controlled under the provisions of NRC Administrative Letter (AL) 98-10, "Dispositioning of Technical Specifications that are Insufficient to Assure Plant Safety," to assure that plant safety is maintained. This license amendment request is submitted in accordance with the guidance in AL 98-10. In accordance with the guidance of AL 98-10, EGC submits the proposed change as a required license amendment request to resolve a non-conservative TS. As such, this is not a "voluntary request from a licensee to change its licensing basis" and should not be subject to "forward fit" considerations. The attached request is subdivided as follows: - Attachment 1 provides an evaluation of the proposed change. - Attachment 2 provides the current TS page with the proposed change indicated. The proposed amendment has been reviewed by the LSCS Plant Operations Review Committee and approved by the Nuclear Safety Review Board in accordance with the requirements of the EGC Quality Assurance Program. EGC requests approval of the proposed license amendment by September 5, 2014. Once approved, the amendment will be implemented within 60 days.

Upload: others

Post on 03-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

RS-13-092

September 5, 2013

10 CFR 50.90

U. S. Nuclear Regulatory CommissionATTN: Document Control DeskWashington, DC 20555-0001

LaSalle County Station, Units 1 and 2Facility Operating License Nos. NPF-11 and NPF-18NRC Docket Nos. 50-373 and 50-374

Subject:

License Amendment Request to Revise Peak Calculated Primary ContainmentInternal Pressure

In accordance with 10 CFR 50.90, "Application for amendment of license, construction permit, orearly site permit," Exelon Generation Company, LLC (EGC) requests an amendment to FacilityOperating License Nos. NPF-1 1 and NPF-18 for LaSalle County Station (LSCS), Units 1 and 2.The proposed change would revise the peak calculated primary containment internal pressure forthe design basis loss-of-coolant accident (LOCA) described in TS 5.5.13, "Primary ContainmentLeakage Rate Testing Program." The peak calculated primary containment internal pressure, Pa,is increased from 39.9 psig to 42.6 psig. The proposed increase in Pa is the result of a LOCA-Drywell Temperature sensitivity analysis performed by General Electric Hitachi (GEH).

Plant operations in TS 5.5.13 are currently administratively controlled under the provisions ofNRC Administrative Letter (AL) 98-10, "Dispositioning of Technical Specifications that areInsufficient to Assure Plant Safety," to assure that plant safety is maintained. This licenseamendment request is submitted in accordance with the guidance in AL 98-10. In accordancewith the guidance of AL 98-10, EGC submits the proposed change as a required licenseamendment request to resolve a non-conservative TS. As such, this is not a "voluntary requestfrom a licensee to change its licensing basis" and should not be subject to "forward fit"considerations.

The attached request is subdivided as follows:

Attachment 1 provides an evaluation of the proposed change.

Attachment 2 provides the current TS page with the proposed change indicated.

The proposed amendment has been reviewed by the LSCS Plant Operations Review Committeeand approved by the Nuclear Safety Review Board in accordance with the requirements of theEGC Quality Assurance Program.

EGC requests approval of the proposed license amendment by September 5, 2014. Onceapproved, the amendment will be implemented within 60 days.

1

RS-13-092

September 5, 2013

U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374

:2000

10 CFR 50.90

Subject: License Amendment Request to Revise Peak Calculated Primary Containment Internal Pressure

In accordance with 10 CFR 50.90, "Application for amendment of license, construction permit, or early site permit," Exelon Generation Company, LLC (EGC) requests an amendment to Facility Operating License Nos. NPF-11 and NPF-18 for LaSalle County Station (LSCS), Units 1 and 2. The proposed change would revise the peak calculated primary containment internal pressure for the design basis loss-of-coolant accident (LOCA) described in TS 5.5.13, "Primary Containment Leakage Rate Testing Program." The peak calculated primary containment internal pressure, Pa ,

is increased from 39.9 psig to 42.6 psig. The proposed increase in Pa is the result of a LOCA­Drywell Temperature sensitivity analysis performed by General Electric Hitachi (GEH).

Plant operations in TS 5.5.13 are currently administratively controlled under the provisions of NRC Administrative Letter (AL) 98-10, "Dispositioning of Technical Specifications that are Insufficient to Assure Plant Safety," to assure that plant safety is maintained. This license amendment request is submitted in accordance with the guidance in AL 98-10. In accordance with the guidance of AL 98-10, EGC submits the proposed change as a required license amendment request to resolve a non-conservative TS. As such, this is not a "voluntary request from a licensee to change its licensing basis" and should not be subject to "forward fit" considerations.

The attached request is subdivided as follows:

- Attachment 1 provides an evaluation of the proposed change.

- Attachment 2 provides the current TS page with the proposed change indicated.

The proposed amendment has been reviewed by the LSCS Plant Operations Review Committee and approved by the Nuclear Safety Review Board in accordance with the requirements of the EGC Quality Assurance Program.

EGC requests approval of the proposed license amendment by September 5, 2014. Once approved, the amendment will be implemented within 60 days.

Page 2: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

September 5, 2013U. S. Nuclear Regulatory CommissionPage 2

In accordance with 10 CFR 50.91, "Notice for public comment; State consultation," paragraph (b),EGC is notifying the State of Illinois of this application for license amendment by transmitting acopy of this letter and its attachments to the designated State Official.

There are no regulatory commitments contained in this letter. Should you have any questionsconcerning this letter, please contact Ms. Lisa A. Simpson at (630) 657-2815.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 5th dayof September 2013.

Respectfully,

David M. GullottManager - LicensingExelon Generation Company, LLC

Attachments:1) Evaluation of Proposed Change2) Markup of Technical Specifications Page

cc:

NRC Regional Administrator, Region IIINRC Senior Resident Inspector, LaSalle County StationIllinois Emergency Management Agency - Division of Nuclear Safety

September 5, 2013 U. S. Nuclear Regulatory Commission Page 2

In accordance with 10 CFR 50.91, "Notice for public comment; State consultation," paragraph (b), EGC is notifying the State of Illinois of this application for license amendment by transmitting a copy of this letter and its attachments to the designated State Official.

There are no regulatory commitments contained in this letter. Should you have any questions concerning this letter, please contact Ms. Lisa A. Simpson at (630) 657-2815.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 5th day of September 2013.

Respectfully,

Z?/41c:t:/ David M. Gullott Manager - licenSing Exelon Generation Company, LLC

Attachments: 1 ) Evaluation of Proposed Change 2) Markup of Technical Specifications Page

cc: NRC Regional Administrator, Region III NRC Senior Resident Inspector, LaSalle County Station Illinois Emergency Management Agency - Division of Nuclear Safety

Page 3: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

Subject:

License Amendment Request to Revise Peak Calculated Primary ContainmentInternal Pressure

1.0 SUMMARY DESCRIPTION

2.0 DETAILED DESCRIPTION

3.0 BACKGROUND

4.0 TECHNICAL EVALUATION

5.0 REGULATORY EVALUATION

5.1

Applicable Regulatory Requirements/Criteria

5.2

No Significant Hazards Consideration

5.3

Conclusions

6.0 ENVIRONMENTAL CONSIDERATION

7.0 REFERENCES

1 of 10

ATTACHMENT 1 Evaluation of Proposed Change

Subject: License Amendment Request to Revise Peak Calculated Primary Containment Internal Pressure

1.0 SUMMARY DESCRIPTION

2.0 DETAILED DESCRIPTION

3.0 BACKGROUND

4.0 TECHNICAL EVALUATION

5.0 REGULATORY EVALUATION

5.1 Applicable Regulatory Requirements/Criteria

5.2 No Significant Hazards Consideration

5.3 Conclusions

6.0 ENVIRONMENTAL CONSIDERATION

7.0 REFERENCES

1 of 10

Page 4: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

1.0 SUMMARY DESCRIPTION

This evaluation supports a request to amend Facility Operating License Nos. NPF-1 1 andNPF-1 8 for LaSalle County Station, Units 1 and 2.

Exelon Generation Company, LLC (EGC) proposes to revise the peak calculated primarycontainment internal pressure for the design basis loss-of-coolant accident (LOCA) described inTechnical Specifications (TS) 5.5 .13, "Primary Containment Leakage Rate Testing Program."The proposed change would revise the peak calculated primary containment internal pressure,Pa, from 39.9 psig to 42.6 psig.

The proposed increase in Pa is the result of a LOCA-Drywell Temperature sensitivity analysisperformed by General Electric Hitachi (GEH). The GEH sensitivity analysis (2012 GEH Analysis,Reference 1) indicated that Pa is higher when using an initial lower drywell temperature (98 °F)versus the maximum allowable drywell temperature (135 °F). The proposed increase alsoincorporates various secondary issues affecting the analysis of record (AOR) (Reference 2). Theresult of utilizing a drywell temperature input of 98 OF and the effect of the secondary issues is aPa of 42.6 psig.

EGC requested GEH to perform the sensitivity analysis in support of the LSCS Extended PowerUprate (EPU) project. On June 11, 2013, EGC announced the cancellation of its LSCS EPUproject; however, the cancellation of EPU does not negate the need for the proposed change.

In accordance with NRC Administrative Letter (AL) 98-10, "Dispositioning of TechnicalSpecifications that are Insufficient to Assure Plant Safety," (Reference 3), administrative controlsimplemented under EGC Operability Evaluation OE 11-002 (Reference 4) assure that plantsafety is maintained. In accordance with the guidance of AL 98-10, EGC submits the proposedchange as a required license amendment request to resolve a non-conservative TS. As such,this is not a "voluntary request from a licensee to change its licensing basis" and should not besubject to "forward fit" considerations.

Approval of this amendment application is requested by September 5, 2014. Once approved,the amendment will be implemented within 60 days.

2.0 DETAILED DESCRIPTION

TS 5.5.13.b currently states:

"The peak calculated primary containment internal pressure for the design basis loss ofcoolant accident, Pa, is 39.9 psig."

The proposed change would revise TS 5.5.13.b by replacing the Pa value of 39.9 psig with avalue of 42.6 psig.

2 of 10

ATTACHMENT 1 Evaluation of Proposed Change

1.0 SUMMARY DESCRIPTION

This evaluation supports a request to amend Facility Operating License Nos. NPF-11 and NPF-18 for LaSalle County Station, Units 1 and 2.

Exelon Generation Company, LLC (EGC) proposes to revise the peak calculated primary containment internal pressure for the design basis loss-of-coolant accident (LOCA) described in Technical Specifications (TS) 5.5.13, "Primary Containment Leakage Rate Testing Program." The proposed change would revise the peak calculated primary containment internal pressure, Pa, from 39.9 psig to 42.6 psig.

The proposed increase in Pais the result of a LOCA-Drywell Temperature sensitivity analysis performed by General Electric Hitachi (GEH). The GEH sensitivity analysis (2012 GEH Analysis, Reference 1) indicated that Pais higher when using an initial lower drywell temperature (98 OF) versus the maximum allowable drywell temperature (135 OF). The proposed increase also incorporates various secondary issues affecting the analysis of record (AOR) (Reference 2). The result of utilizing a drywell temperature input of 98 of and the effect of the secondary issues is a Pa of 42.6 psig.

EGC requested GEH to perform the sensitivity analysis in support of the LSCS Extended Power Uprate (EPU) project. On June 11, 2013, EGC announced the cancellation of its LSCS EPU project; however, the cancellation of EPU does not negate the need for the proposed change.

In accordance with NRC Administrative Letter (AL) 98-10, "Dispositioning of Technical Specifications that are Insufficient to Assure Plant Safety," (Reference 3), administrative controls implemented under EGC Operability Evaluation OE 11-002 (Reference 4) assure that plant safety is maintained. In accordance with the guidance of AL 98-10, EGC submits the proposed change as a required license amendment request to resolve a non-conservative TS. As such, this is not a "voluntary request from a licensee to change its licensing basis" and should not be subject to "forward fit" considerations.

Approval of this amendment application is requested by September 5, 2014. Once approved, the amendment will be implemented within 60 days.

2.0 DETAILED DESCRIPTION

TS 5.5.13.b currently states:

"The peak calculated primary containment internal pressure for the design basis loss of coolant accident, Pa, is 39.9 psig."

The proposed change would revise TS 5.5.13.b by replacing the P a value of 39.9 psig with a value of 42.6 psig.

2 of 10

Page 5: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

The revised TS 5.5.13.b would state as follows:

"The peak calculated primary containment internal pressure for the design basis loss ofcoolant accident, Pa, is 42.6 psig."

Attachment 2 provides mark-ups of the affected TS pages for the proposed change.

3.0 BACKGROUND

Peak containment internal pressure during a LOCA is calculated to determine, in part, whetherthe design pressure limit for the containment building would be exceeded during a design basisaccident. LSCS TS 5.5.13, "Primary Containment Leakage Rate Testing Program," describesthe peak calculated primary containment internal pressure during the design basis LOCA, Pa-

A LOCA is initiated by the rupture of the primary coolant system piping. The primary coolantflashes to steam and escapes through the pipe break. As the steam is released to containment,containment atmosphere pressure and temperature quickly increase. During a LOCA event, theinitial blow down of the primary coolant system adds mass and energy to the containment.

The current LSCS AOR peak calculated primary containment internal pressure, Pa, is 39.9 psig,as stated in the LSCS UFSAR and TS (Reference TS 5.5.13 and UFSAR 6.2.1.1.3). Results ofthe 2012 GEH Analysis concluded that the peak calculated primary containment internalpressure, Pa, is 42.6 psig, which is 2.7 psig higher than the value determined in the AOR (i.e.,42.6 psig - 39.9 psig = 2.7 psig). This proposed increase to Pa includes both the effects of usingthe lower drywell temperature and the secondary issues regarding the AOR.

The proposed increase in Pa is the result of a LOCA-Drywell Temperature sensitivity analysis

performed by GEH (2012 GEH Analysis) in support of the LSCS EPU project. The 2012 GEHAnalysis indicated that Pa is higher when using an initial lower drywell temperature (98 °F) versus

the maximum TS allowable drywell temperature (135 °F). The effect of using the lower drywelltemperature increases Pa by 1.3 psig.

During the process of GEH conducting and EGC reviewing the analysis, additional secondaryissues were identified regarding the AOR that also impact Pa. These issues include the MainSteam Safety Relief Valve (SRV) setpoints, the closure time for the Main Steam Isolation Valves(MSIVs), the core flow conditions permitted by the Power/Flow Map, and the reactor power level.The new Analysis corrects these issues. GEH has addressed each issue through their correctiveaction program. The cumulative effect of these secondary issues increases Pa by 1.4 psig.

Although EGC canceled the EPU project for LSCS, this does not negate the need for theproposed change. In accordance with the guidance of AL 98-10, EGC submits the proposedchange as a required license amendment request to resolve the non-conservative TS.

4.0 TECHNICAL EVALUATION

The proposed increase to Pa incorporates an increase resulting from using the lower drywelltemperature and an increase resulting from secondary issues regarding the AOR.

3 of 10

ATTACHMENT 1 Evaluation of Proposed Change

The revised TS 5.5.13.b would state as follows:

liThe peak calculated primary containment internal pressure for the design basis loss of coolant accident, Pa , is 42.6 psig."

Attachment 2 provides mark-ups of the affected TS pages for the proposed change.

3.0 BACKGROUND

Peak containment internal pressure during a LOCA is calculated to determine, in part, whether the design pressure limit for the containment building would be exceeded during a design basis accident. LSCS TS 5.5.13, "Primary Containment Leakage Rate Testing Program," describes the peak calculated primary containment internal pressure during the design basis LOCA, Pa.

A LOCA is initiated by the rupture of the primary coolant system piping. The primary coolant flashes to steam and escapes through the pipe break. As the steam is released to containment, containment atmosphere pressure and temperature quickly increase. During a LOCA event, the initial blow down of the primary coolant system adds mass and energy to the containment.

The current LSCS AOR peak calculated primary containment internal pressure, Pa , is 39.9 psig, as stated in the LSCS UFSAR and TS (Reference TS 5.5.13 and UFSAR 6.2.1.1.3). Results of the 2012 GEH Analysis concluded that the peak calculated primary containment internal pressure, Pa, is 42.6 psig, which is 2.7 psig higher than the value determined in the AOR (Le., 42.6 psig - 39.9 psig = 2.7 psig). This proposed increase to Pa includes both the effects of using the lower drywell temperature and the secondary issues regarding the AOR.

The proposed increase in Pa is the result of a LOCA-Drywell Temperature sensitivity analysis performed by GEH (2012 GEH Analysis) in support of the LSCS EPU project. The 2012 GEH Analysis indicated that Pa is higher when using an initial lower drywell temperature (98 OF) versus the maximum TS allowable drywell temperature (135 OF). The effect of using the lower drywell temperature increases Pa by 1.3 psig.

During the process of GEH conducting and EGC reviewing the analysis, additional secondary issues were identified regarding the AOR that also impact Pa . These issues include the Main Steam Safety Relief Valve (SRV) setpoints, the closure time for the Main Steam Isolation Valves (MSIVs), the core flow conditions permitted by the Power/Flow Map, and the reactor power level. The new Analysis corrects these issues. GEH has addressed each issue through their corrective action program. The cumulative effect of these secondary issues increases Pa by 1.4 psig.

Although EGC canceled the EPU project for LSCS, this does not negate the need for the proposed change. In accordance with the guidance of AL 98-10, EGC submits the proposed change as a required license amendment request to resolve the non-conservative TS.

4.0 TECHNICAL EVALUATION

The proposed increase to P a incorporates an increase resulting from using the lower drywell temperature and an increase resulting from secondary issues regarding the AOA.

3 of 10

Page 6: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

Initial Drywell Temperature

The current LSCS containment AOR (GE Project Task Report GE-NE-A1300384-02-01-R3,which is documented in Design Analysis L-002874) used an initial drywell temperature of 135 OF,which is the maximum value allowed by TS (Reference TS 3.6.1.5). The 2012 GEH Analysisindicated that the peak calculated primary containment internal pressure is higher when using aninitial lower drywell temperature (98 °F) versus the maximum TS allowable drywell temperature(135 °F).

The 2012 GEH Analysis uses an initial drywell temperature of 98 OF based upon historical bulkaverage drywell temperature data for the time period of June 1, 2007, through March 22, 2011.The evaluation examined the bulk average drywell temperature in one hour increments to ensurethat time of the day and operating variations were captured. The evaluation included 2 sigmastandard deviation and found that when the plant operates at >_ 90% power level, the drywelltemperature will be >_ 100 OF. The drywell temperature of 98 OF was selected to addconservatism.

The use of the TS limiting drywell temperature as input for the containment analysis isconservative in the determination of the peak drywell temperature; however, the use of themaximum TS allowable drywell temperature is not conservative in relation to the peak calculatedprimary containment internal pressure, Pa. The effect of using the lower initial drywelltemperature increases Pa by 1.3 psig.

Secondary AOR Issues

During the process of GEH conducting and EGC reviewing the analysis, additional secondaryissues were identified regarding the AOR that also impacts Pa. Exelon requested that GEHevaluate the secondary issues used in the containment analysis to determine how they mayaffect Pa. GEH has addressed each of the secondary issues through their corrective actionprogram. The 2012 GEH Analysis corrects these issues. The cumulative effect of thesesecondary issues increases Pa by 1.4 psig. The issues identified during the review of the2012 GEH Analysis include the following:

• Main Steam Safety Relief Valve (SRV) Setpoints

The Main Steam SRV setpoints used in the 2012 GEH Analysis impact the Pa resultsbecause the opening of the SRVs directs energy from the reactor pressure vessel(RPV) to the suppression pool instead of releasing the energy to the drywell throughthe break. Higher SRV setpoints result in the SRVs remaining closed longer, thusdirecting more energy to the drywell. The LSCS SRVs are designed to open in safetymode (i.e., as safety valves with spring mode of operation) or relief mode (i.e., apneumatic piston/cylinder actuator providing the mode of operation). SRV operationin the safety mode has a higher opening setpoint than in the relief mode. Therefore,in order to provide a bounding calculated primary containment internal pressure, Pa,the 2012 GEH Analysis uses the higher Main Steam SRV spring setpoints credited inTS 3.4.4, "Safety / Relief Valves (S/RVs)." This differs from the AOR which used thelower SRV relief mode setpoints.

4 of 10

Initial Drywell Temperature

ATTACHMENT 1 Evaluation of Proposed Change

The current LSCS containment ADR (GE Project Task Report GE-NE-A1300384-02-01-R3, which is documented in Design Analysis L-002874) used an initial drywell temperature of 135 of, which is the maximum value allowed by TS (Reference TS 3.6.1.5). The 2012 GEH Analysis indicated that the peak calculated primary containment internal pressure is higher when using an initial lower drywell temperature (98 OF) versus the maximum TS allowable drywell temperature (135 OF).

The 2012 GEH Analysis uses an initial drywell temperature of 98 of based upon historical bulk average drywell temperature data for the time period of June 1, 2007, through March 22, 2011. The evaluation examined the bulk average drywell temperature in one hour increments to ensure that time of the day and operating variations were captured. The evaluation included 2 sigma standard deviation and found that when the plant operates at 2: 90% power level, the drywell temperature will be 2: 100 of. The drywell temperature of 98 of was selected to add conservatism.

The use of the TS limiting drywell temperature as input for the containment analysis is conservative in the determination of the peak drywell temperature; however, the use of the maximum TS allowable drywell temperature is not conservative in relation to the peak calculated primary containment internal pressure, Pa . The effect of using the lower initial drywell temperature increases Pa by 1.3 psig.

Secondary AOR Issues

During the process of GEH conducting and EGC reviewing the analysis, additional secondary issues were identified regarding the AOR that also impacts Pa• Exelon requested that GEH evaluate the secondary issues used in the containment analysis to determine how they may affect Pa. GEH has addressed each of the secondary issues through their corrective action program. The 2012 GEH Analysis corrects these issues. The cumulative effect of these secondary issues increases Pa by 1.4 psig. The issues identified during the review of the 2012 GEH Analysis include the following:

• Main Steam Safety Relief Valve (SRV) Setpoints

The Main Steam SRV setpoints used in the 2012 GEH Analysis impact the Pa results because the opening of the SRVs directs energy from the reactor pressure vessel (RPV) to the suppression pool instead of releasing the energy to the drywell through the break. Higher SRV setpoints result in the SRVs remaining closed longer, thus directing more energy to the drywell. The LSCS SRVs are designed to open in safety mode (Le., as safety valves with spring mode of operation) or relief mode (Le., a pneumatic piston/cylinder actuator providing the mode of operation). SRV operation in the safety mode has a higher opening setpoint than in the relief mode. Therefore, in order to provide a bounding calculated primary containment internal pressure, Pa ,

the 2012 GEH Analysis uses the higher Main Steam SRV spring setpoints credited in TS 3.4.4, "Safety / Relief Valves (S/RVs)." This differs from the ADR which used the lower SRV relief mode setpoints.

4 of 10

Page 7: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

• Main Steam Isolation Valve (MSIV) Closure Time

The MSIV closure time assumed in the 2012 GEH Analysis impacts the Pa resultssince the longer time it takes the MSIVs to close, the longer RPV mass and energy isdirected to the turbine. Conversely, a shorter MSIV closure time means that moreRPV mass and energy will be released to the drywell via the break, resulting in ahigher Pa. The AOR uses a MSIV closure time of 5 seconds, which is the maximumMSIV closure time allowed in TS Surveillance Requirement (SR) 3.6.1.3.6. In order toprovide a bounding peak calculated primary containment internal pressure, the 2012GEH Analysis uses a shorter MSIV closure time of 3.5 seconds, based on theminimum TS SR 3.6.1.3.6 MSIV isolation time with an assumed 0.5 second frombreak occurrence to initiation of MSIV closure.

• Core Flow Conditions Permitted by the Power/Flow Map

Core flow conditions assumed in the analysis affect the mass and energy released tothe drywell through the break. GEH evaluated plant operation at Rated Core Flow(RCF), Increased Core Flow (ICF), and Maximum Extended Load Limit Analysis(MELLA) conditions to ensure that the condition which maximizes the energy beingreleased to the drywell and provides a bounding Pa is accounted for. Additionally,feedwater temperature affects the energy released through the break, therefore boththe Final Feedwater Temperature Reduction (FFWTR) and Normal FeedwaterTemperature (NFWT) were considered. The 2012 GEH Analysis considered thedifferent core flow and feedwater temperature conditions, and the results are basedupon the conditions that yield the highest Pa.

• Reactor Power Level

A lower reactor power level results in less energy being released to the drywell via thebreak, resulting in a lower Pa.

The AOR states that the analyses were performed at a reactor power level of3559 MWt. However, it was subsequently determined that the AOR analyses wereactually performed at 3789 MWt. This discrepancy was addressed by GEH throughtheir corrective action program.

The 2012 GEH Analysis used a maximum reactor power level of 3559 MWt, which is102% of the stretch power uprate licensed thermal power (3489 MWt). As aconsequence of the decrease in reactor power level used in the 2012 GEH Analysiscompared to the AOR, the impact of this specific change was a decrease in Pa.

Summary of Changes to Peak Calculated Primary Containment Internal Pressure and Evaluation

The current LSCS AOR peak calculated primary containment internal pressure, Pa, is 39.9 psig,as stated in the LSCS UFSAR and TS (Reference TS 5.5.13 and UFSAR 6.2.1.1.3). Results ofthe 2012 GEH Analysis concluded that the peak calculated primary containment internalpressure, Pa, is 42.6 psig, which is 2.7 psig higher than the value determined in the AOR (i.e.,42.6 psig - 39.9 psig = 2.7 psig). The proposed increase of 2.7 psig to Pa incorporates anincrease resulting from using the lower drywell temperature (i.e., 1.3 psig) and an increaseresulting from secondary issues regarding the AOR (i.e., 1.4 psig).

5 of 10

ATTACHMENT 1 Evaluation of Proposed Change

• Main Steam Isolation Valve (MSIV) Closure Time

The MSIV closure time assumed in the 2012 GEH Analysis impacts the Pa results since the longer time it takes the MSIVs to close, the longer RPV mass and energy is directed to the turbine. Conversely, a shorter MSIV closure time means that more RPV mass and energy will be released to the drywell via the break, resulting in a higher Pa. The AOR uses a MSIV closure time of 5 seconds, which is the maximum MSIV closure time allowed in TS Surveillance Requirement (SR) 3.6.1.3.6. In order to provide a bounding peak calculated primary containment internal pressure, the 2012 GEH Analysis uses a shorter MSIV closure time of 3.5 seconds, based on the minimum TS SR 3.6.1.3.6 MSIV isolation time with an assumed 0.5 second from break occurrence to initiation of MSIV closure.

• Core Flow Conditions Permitted by the Power/Flow Map

Core flow conditions assumed in the analysis affect the mass and energy released to the drywell through the break. GEH evaluated plant operation at Rated Core Flow (RCF), Increased Core Flow (ICF), and Maximum Extended Load Limit Analysis (MELLA) conditions to ensure that the condition which maximizes the energy being released to the drywell and provides a bounding Pa is accounted for. Additionally, feedwater temperature affects the energy released through the break, therefore both the Final Feedwater Temperature Reduction (FFWTR) and Normal Feedwater Temperature (NFWT) were considered. The 2012 GEH Analysis considered the different core flow and feedwater temperature conditions, and the results are based upon the conditions that yield the highest P a.

• Reactor Power Level

A lower reactor power level results in less energy being released to the drywell via the break, resulting in a lower Pa.

The AOR states that the analyses were performed at a reactor power level of 3559 MWt. However, it was subsequently determined that the AOR analyses were actually performed at 3789 MWt. This discrepancy was addressed by GEH through their corrective action program.

The 2012 GEH Analysis used a maximum reactor power level of 3559 MWt, which is 102% of the stretch power uprate licensed thermal power (3489 MWt). As a consequence of the decrease in reactor power level used in the 2012 GEH Analysis compared to the AOR, the impact of this specific change was a decrease in P a.

Summary of Changes to Peak Calculated Primary Containment Internal Pressure and Evaluation

The current LSCS AOR peak calculated primary containment internal pressure, Pa , is 39.9 psig, as stated in the LSCS UFSAR and TS (Reference TS 5.5.13 and UFSAR 6.2.1.1.3). Results of the 2012 GEH Analysis concluded that the peak calculated primary containment internal pressure, Pa , is 42.6 psig, which is 2.7 psig higher than the value determined in the AOR (Le., 42.6 psig - 39.9 psig = 2.7 psig). The proposed increase of 2.7 psig to Pa incorporates an increase resulting from using the lower drywell temperature (Le., 1.3 psig) and an increase resulting from secondary issues regarding the AOR (Le., 1.4 psig).

5 of 10

Page 8: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

As defined in LSCS UFSAR Table 6.2-1, the containment design pressure is 45 psig. Since thepeak calculated primary containment internal pressure resulting from the non-conformingcondition (42.6 psig) is less than the containment design pressure (45 psig), the increased Pahas no effect upon the capability of the primary containment to accomplish its safety-relatedfunctions.

Containment leakage rate testing is addressed in UFSAR Section 6.2.6 and LSCS TS 5.5.13.The LSCS containment leakage rate testing program implements testing requirements inaccordance with 10 CFR 50 Appendix J, Option B, as modified by any approved exemptions,and criteria contained in RG 1.163, "Performance- Based Containment Leak Test Program."Tests that measure containment isolation valve leak rates (Type C tests) are performed using thepeak calculated primary containment internal pressure value of 42.6 psig.

As described in TS 5.5.13 and LSCS UFSAR Table 6.2-23, the test pressure used forcontainment leakage testing is based upon the Pa of 39.9 psig. The higher calculated peakpressure Pa will affect the containment leakage testing results. Leak rate testing based upon thehigher Pa of 42.6 psig would have increased the measured leakage. EGC Operability EvaluationOE 11-002 demonstrates that there is adequate margin to accommodate this increase.

As described in LSCS UFSAR 3.11.1.1.1, the environmental qualification of safety-relatedelectrical components and instrumentation located in the primary containment are based uponthe design pressure (45 psig), not the calculated Pa pressure (39.9 psig). Hence, the revision of

TS 5.5.13.b that increases the Pa value to 42.6 psig has no effect upon environmentalqualification.

The change in Pa does not affect the LSCS analysis of radiological consequences of a LOCAwith respect to radiological dose at the Exclusion Area Boundary (EAB), Low Population Zone(LPZ), Control Room (CR), or Technical Support Center (TSC). Calculated doses during aLOCA are dependent on the maximum allowable containment atmosphere leakage rate, which isnot affected by Pa.

5.0 REGULATORY EVALUATION

5.1

Applicable Regulatory Requirements/Criteria

The proposed change has been evaluated to determine whether applicable regulationsand requirements continue to be met.

General Design Criterion 4, "Environmental and Dynamic Effects Design Bases," statesthat structures, systems and components important to safety shall be designed toaccommodate the effects of, and to be compatible with, the environmental conditionsassociated with normal operation, maintenance, testing, and postulated accidents,including LOCAs.

6of10

ATTACHMENT 1 Evaluation of Proposed Change

As defined in LSCS UFSAR Table 6.2-1, the containment design pressure is 45 psig. Since the peak calculated primary containment internal pressure resulting from the non-conforming condition (42.6 psig) is less than the containment design pressure (45 psig), the increased Pa has no effect upon the capability of the primary containment to accomplish its safety-related functions.

Containment leakage rate testing is addressed in UFSAR Section 6.2.6 and LSCS TS 5.5.13. The LSCS containment leakage rate testing program implements testing requirements in accordance with 10 CFR 50 Appendix J, Option B, as modified by any approved exemptions, and criteria contained in RG 1.163, "Performance-Based Containment Leak Test Program." Tests that measure containment isolation valve leak rates (Type C tests) are performed using the peak calculated primary containment internal pressure value of 42.6 psig.

As described in TS 5.5.13 and LSCS UFSAR Table 6.2-23, the test pressure used for containment leakage testing is based upon the Pa of 39.9 psig. The higher calculated peak pressure P a will affect the containment leakage testing results. Leak rate testing based upon the higher Pa of 42.6 psig would have increased the measured leakage. EGC Operability Evaluation OE 11-002 demonstrates that there is adequate margin to accommodate this increase.

As described in LSCS UFSAR 3.11.1.1.1, the environmental qualification of safety-related electrical components and instrumentation located in the primary containment are based upon the design pressure (45 psig), not the calculated Pa pressure (39.9 psig). Hence, the revision of TS 5.5.13.b that increases the Pa value to 42.6 psig has no effect upon environmental qualification.

The change in Pa does not affect the LSCS analysis of radiological consequences of a LOCA with respect to radiological dose at the Exclusion Area Boundary (EAB), Low Population Zone (LPZ), Control Room (CR), or Technical Support Center (TSC). Calculated doses during a LOCA are dependent on the maximum allowable containment atmosphere leakage rate, which is not affected by Pa .

5.0 REGULATORY EVALUATION

5.1 Applicable Regulatory Requirements/Criteria

The proposed change has been evaluated to determine whether applicable regulations and requirements continue to be met.

General Design Criterion 4, "Environmental and Dynamic Effects Design Bases," states that structures, systems and components important to safety shall be designed to accommodate the effects of, and to be compatible with, the environmental conditions associated with normal operation, maintenance, testing, and postulated accidents, including LOCAs.

6 of 10

Page 9: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

General Design Criterion 16, "Containment Design," states that reactor containment andassociated systems shall be provided to establish an essentially leak-tight barrier againstthe uncontrolled release of radioactivity to the environment and to assure that thecontainment design conditions important to safety are not exceeded for as long aspostulated accident conditions require.

General Design Criterion 19, "Control Room," states that a control room shall be providedfrom which actions can be taken to operate the nuclear power unit safely under normalconditions and to maintain it in a safe condition under accident conditions, includingLOCAs, and that adequate radiation protection shall be provided. Adequate shielding isprovided to maintain tolerable radiation levels in the control room under accidentconditions for the duration of the accident.

General Design Criterion 38, "Containment Heat Removal," states that a system toremove heat from the reactor containment shall be provided that rapidly reduces,consistent with the functioning of other associated systems, the containment pressureand temperature following any LOCA and maintain them at acceptable low levels.

These General Design Criteria continue to be met by the change in Pa. Theenvironmental qualification of equipment within containment is not affected by the changein Pa following a LOCA. The change in Pa will be reflected in future 10 CFR 50Appendix J, Type A containment integrated leak rate testing, so containment integrity isnot impacted by the change. The change in Pa does not impact the maximum allowablecontainment leakage rate and therefore does not impact control room operator dose. Paremains below containment design pressure.

Based on the considerations above, (1) there is reasonable assurance that the health andsafety of the public will not be endangered by operation in the proposed manner; (2) suchactivities will continue to be conducted in accordance with the site licensing basis; and (3)the approval of the proposed change will not be inimical to the common defense andsecurity or to the health and safety of the public.

In conclusion, EGC has determined that the proposed change does not require anyexemptions or relief from regulatory requirements, other than the TS, and does not affectconformance with any regulatory requirements or criteria.

5.2

No Significant Hazards Consideration

In accordance with 10 CFR 50.90, "Application for amendment of license, constructionpermit, or early site permit," Exelon Generation Company, LLC (EGC) requests anamendment to Facility Operating License Nos. NPF - 1 1 and NPF-1 8 for LaSalle CountyStation (LSCS), Units 1 and 2. The proposed change would revise the peak calculatedprimary containment internal pressure for the design basis loss-of-coolant accident(LOCA) described in Technical Specifications (TS) 5.5 .13, "Primary ContainmentLeakage Rate Testing Program." The peak calculated primary containment internalpressure, Pa, is increased from 39.9 psig to 42.6 psig.

7 of 10

ATTACHMENT 1 Evaluation of Proposed Change

General Design Criterion 16, "Containment Design," states that reactor containment and associated systems shall be provided to establish an essentially leak-tight barrier against the uncontrolled release of radioactivity to the environment and to assure that the containment design conditions important to safety are not exceeded for as long as postulated accident conditions require.

General Design Criterion 19, "Control Room," states that a control room shall be provided from which actions can be taken to operate the nuclear power unit safely under normal conditions and to maintain it in a safe condition under accident conditions, including LOCAs, and that adequate radiation protection shall be provided. Adequate shielding is provided to maintain tolerable radiation levels in the control room under accident conditions for the duration of the accident.

General Design Criterion 38, "Containment Heat Removal," states that a system to remove heat from the reactor containment shall be provided that rapidly reduces, consistent with the functioning of other associated systems, the containment pressure and temperature following any LOCA and maintain them at acceptable low levels.

These General Design Criteria continue to be met by the change in Pa . The environmental qualification of equipment within containment is not affected by the change in Pa following a LOCA. The change in Pa will be reflected in future 10 CFR 50 Appendix J, Type A containment integrated leak rate testing, so containment integrity is not impacted by the change. The change in Pa does not impact the maximum allowable containment leakage rate and therefore does not impact control room operator dose. Pa remains below containment design pressure.

Based on the considerations above, (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner; (2) such activities will continue to be conducted in accordance with the site licensing basis; and (3) the approval of the proposed change will not be inimical to the common defense and security or to the health and safety of the public.

In conclusion, EGC has determined that the proposed change does not require any exemptions or relief from regulatory requirements, other than the TS, and does not affect conformance with any regulatory requirements or criteria.

5.2 No Significant Hazards Consideration

In accordance with 10 CFR 50.90, "Application for amendment of license, construction permit, or early site permit," Exelon Generation Company, LLC (EGG) requests an amendment to Facility Operating License Nos. NPF-11 and NPF-18 for LaSalle County Station (LSCS), Units 1 and 2. The proposed change would revise the peak calculated primary containment internal pressure for the design basis loss-of-coolant accident (LOCA) described in Technical Specifications (TS) 5.5.13, "Primary Containment Leakage Rate Testing Program." The peak calculated primary containment internal pressure, Pa, is increased from 39.9 psig to 42.6 psig.

7 of 10

Page 10: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

According to 10 CFR 50.92, "Issuance of amendment," paragraph (c), a proposedamendment to an operating license involves no significant hazards consideration ifoperation of the facility in accordance with the proposed amendment would not:

(1) Involve a significant increase in the probability or consequences of an accidentpreviously evaluated; or

(2) Create the possibility of a new or different kind of accident from any accidentpreviously evaluated; or

(3) Involve a significant reduction in a margin of safety.

EGC has evaluated the proposed change for LSCS, using the criteria in 10 CFR 50.92,and has determined that the proposed change does not involve a significant hazardsconsideration. The following information is provided to support a finding of no significanthazards consideration.

Criteria:

1.

Does the proposed change involve a significant increase in the probability orconsequences of an accident previously evaluated?

Response: No.

The proposed change to Pa does not alter the assumed initiators to any analyzedevent. The probability of an accident previously evaluated will not be increasedby this proposed change since this change does not modify the plant or how it isoperated.

The change in Pa will not affect radiological dose consequence analyses. LSCSradiological dose consequence analyses are based on the maximum allowablecontainment leakage rate. Even though the test pressure at which leak ratetesting is performed is Pa, the maximum allowable containment leakage rate isdefined in terms of a percentage of weight of the original content of containmentair, which is independent of the peak calculated primary containment internalpressure. The Appendix J containment leak rate testing program will continue toensure that containment leakage remains within the leakage assumed in theoffsite dose consequence analyses. The consequences of an accident previouslyevaluated will not be increased by this proposed change.

Therefore, operation of the facility in accordance with the proposed change to Pawill not involve a significant increase in the probability or consequences of anaccident previously evaluated.

8 of 10

ATTACHMENT 1 Evaluation of Proposed Change

According to 10 CFR 50.92, "Issuance of amendment," paragraph (c), a proposed amendment to an operating license involves no significant hazards consideration if operation of the facility in accordance with the proposed amendment would not:

(1) Involve a significant increase in the probability or consequences of an accident previously evaluated; or

(2) Create the possibility of a new or different kind of accident from any accident previously evaluated; or

(3) Involve a significant reduction in a margin of safety.

EGC has evaluated the proposed change for LSCS, using the criteria in 10 CFR 50.92, and has determined that the proposed change does not involve a significant hazards consideration. The following information is provided to support a finding of no significant hazards consideration.

Criteria:

1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated?

Response: No.

The proposed change to Pa does not alter the assumed initiators to any analyzed event. The probability of an accident previously evaluated will not be increased by this proposed change since this change does not modify the plant or how it is operated.

The change in Pa will not affect radiological dose consequence analyses. LSCS radiological dose consequence analyses are based on the maximum allowable containment leakage rate. Even though the test pressure at which leak rate testing is performed is Pa, the maximum allowable containment leakage rate is defined in terms of a percentage of weight of the original content of containment air, which is independent of the peak calculated primary containment internal pressure. The Appendix J containment leak rate testing program will continue to ensure that containment leakage remains within the leakage assumed in the offsite dose consequence analyses. The consequences of an accident previously evaluated will not be increased by this proposed change.

Therefore, operation of the facility in accordance with the proposed change to Pa will not involve a significant increase in the probability or consequences of an accident previously evaluated.

8 of 10

Page 11: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

2.Does the proposed change create the possibility of a new or different kind ofaccident from any accident previously evaluated?

Response: No.

The proposed change provides a higher Pa than currently described in the TS.This change is the result of a LOCA-Drywell Temperature sensitivity analysisperformed by General Electric Hitachi (GEH). The peak calculated primarycontainment internal pressure remains below the containment design pressure of45 psig. This change does not involve any alteration in the plant configuration(no new or different type of equipment will be installed) or make changes in themethods governing normal plant operation. The change does not create thepossibility of a new or different kind of accident from any accident previouslyevaluated.

Therefore, operation of the facility in accordance with the proposed change toTS 5.5.13 would not create the possibility of a new or different kind of accidentfrom any previously evaluated.

3.

Does the proposed change involve a significant reduction in a margin of safety?

Response: No.

The peak calculated primary containment internal pressure remains below thecontainment design pressure of 45 psig. LSCS radiological consequenceanalyses are based on the maximum allowable containment leakage rate. Thechange in the peak calculated primary containment internal pressure does notrepresent a significant change in the margin of safety.

Operation of the facility in accordance with the proposed change to TS 5.5.13does not involve a significant reduction in the margin of safety.

Based on the above evaluation, EGC concludes that the proposed amendment doesnot involve a significant hazards consideration under the standards set forth in10 CFR 50.92, paragraph (c), and accordingly, a finding of no significant hazardsconsideration is justified.

5.3

Conclusions

In conclusion, based on the considerations discussed above, (1) there is reasonableassurance that the health and safety of the public will not be endangered by the operationof LSCS Units 1 and 2 in the proposed manner, (2) such activities will be conducted incompliance with the Commission's regulations, and (3) the issuance of the amendmentwill not be inimical to the common defense and security or the health and safety of thepublic.

9 of 10

ATTACHMENT 1 Evaluation of Proposed Change

2. Does the proposed change create the possibility of a new or different kind of accident from any accident previously evaluated?

Response: No.

The proposed change provides a higher Pa than currently described in the TS. This change is the result of a LOCA-Drywell Temperature sensitivity analysis performed by General Electric Hitachi (GEH). The peak calculated primary containment internal pressure remains below the containment design pressure of 45 psig. This change does not involve any alteration in the plant configuration (no new or different type of equipment will be installed) or make changes in the methods governing normal plant operation. The change does not create the possibility of a new or different kind of accident from any accident previously evaluated.

Therefore, operation of the facility in accordance with the proposed change to TS 5.5.13 would not create the possibility of a new or different kind of accident from any previously evaluated.

3. Does the proposed change involve a significant reduction in a margin of safety?

Response: No.

The peak calculated primary containment internal pressure remains below the containment design pressure of 45 psig. LSCS radiological consequence analyses are based on the maximum allowable containment leakage rate. The change in the peak calculated primary containment internal pressure does not represent a significant change in the margin of safety.

Operation of the facility in accordance with the proposed change to TS 5.5.13 does not involve a significant reduction in the margin of safety.

Based on the above evaluation, EGC concludes that the proposed amendment does not involve a significant hazards consideration under the standards set forth in 10 CFR 50.92, paragraph (c), and accordingly, a finding of no significant hazards consideration is justified.

5.3 Conclusions

In conclusion, based on the considerations discussed above, (1) there is reasonable assurance that the health and safety of the public will not be endangered by the operation of LSCS Units 1 and 2 in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or the health and safety of the public.

9 of 10

Page 12: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 1Evaluation of Proposed Change

6.0 ENVIRONMENTAL CONSIDERATION

EGC has evaluated the proposed amendment for environmental considerations. The review hasresulted in the determination that the proposed amendment would change requirements withrespect to installation or use of a facility component located within the restricted area, as definedin 10 CFR 20, or would change an inspection or surveillance requirement. However, theproposed amendment does not involve (i) a significant hazards consideration, (ii) a significantchange in the types or significant increase in the amounts of any effluent that may be releasedoffsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure.Accordingly, the proposed amendment meets the eligibility criterion for categorical exclusion setforth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22, paragraph (b), noenvironmental impact statement or environmental assessment needs to be prepared inconnection with the proposed amendment.

7.0 REFERENCES

1)GEH Report 0000-0149-2311-R0, Revision 0, "LaSalle County Generating StationUnits 1 and 2, Short Term Containment Bounding Pa Assessment," datedAugust 2012

2)GE Project Task Report GE-NE-A1300384-02-01-R3, Revision 3, "LaSalle CountyStation Power Uprate Evaluation, Task 400: Containment System Response," datedMay 2002 (documented in Design Analysis L-002874, Revision 0)

3)

NRC Administrative Letter 98-10, "Dispositioning of Technical Specifications that areInsufficient to Assure Plant Safety," December 29, 1998

4)

Operability Evaluation OE 11-002, Revision 5, "Drywell Temp Used as Input for theContainment Analysis," April 9, 2013

10 of 10

ATTACHMENT 1 Evaluation of Proposed Change

6.0 ENVIRONMENTAL CONSIDERATION

EGC has evaluated the proposed amendment for environmental considerations. The review has resulted in the determination that the proposed amendment would change requirements with respect to installation or use of a facility component located within the restricted area, as defined in 10 CFR 20, or would change an inspection or surveillance requirement. However, the proposed amendment does not involve (i) a significant hazards consideration, (ii) a significant change in the types or significant increase in the amounts of any effluent that may be released offsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure. Accordingly, the proposed amendment meets the eligibility criterion for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22, paragraph (b), no environmental impact statement or environmental assessment needs to be prepared in connection with the proposed amendment.

7.0 REFERENCES

1) GEH Report 0000-0149-2311-RO, Revision 0, "LaSalle County Generating Station Units 1 and 2, Short Term Containment Bounding Pa Assessment," dated August 2012

2) GE Project Task Report GE-NE-A1300384-02-01-R3, Revision 3, "LaSalle County Station Power Uprate Evaluation, Task 400: Containment System Response," dated May 2002 (documented in Design Analysis L-002874, Revision 0)

3) NRC Administrative Letter 98-10, "Dispositioning of Technical Specifications that are Insufficient to Assure Plant Safety," December 29, 1998

4) Operability Evaluation OE 11-002, Revision 5, "Drywell Temp Used as Input for the Containment Analysis," April 9, 2013

10 of 10

Page 13: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

ATTACHMENT 2

Markup of Technical Specifications Page

LASALLE COUNTY STATIONUNITS 1 AND 2

Docket Nos. 50-373 and 50-374

Facility Operating License Nos. NPF-11 and NPF-18

REVISED TS PAGE

5.5-13

ATTACHMENT 2

Markup of Technical Specifications Page

LASALLE COUNTY STATION UNITS 1 AND 2

Docket Nos. 50-373 and 50-374

Facility Operating License Nos. NPF-11 and NPF-18

REVISED TS PAGE

5.5-13

Page 14: EGC requests approval of the proposed license amendment by … › docs › ML1324 › ML13249A231.pdf · 2013-09-16 · EGC is notifying the State of Illinois of this application

Programs and Manuals

5.5

5.5 Programs and Manuals

5.5.13

Primary Containment Leakage Rate Testing Program (continued)

2. NEI 94-01 - 1995, Section 9.2.3: The first Unit 2

Type A test performed after December 8, 1993 Type A

test shall be performed prior to startup following

L2R12.

3. The potential valve atmospheric leakage paths that are

not exposed to reverse direction test pressure shall be

tested during the regularly scheduled Type A test. The

program shall contain the list of the potential valve

atmospheric leakage paths, leakage rate measurement

method, and acceptance criteria. This exception shall

be applicable only to valves that are not isolable from

the primary containment free air space.

b.

The peak calculated primary containment internal pressure

for the design basis loss of coolant accident, Pa, is

3 9 - 4 p s i g .

42.6 c.

The maximum allowable primary containment leakage rate, La,

at Pa, is 1.0% of primary containment air weight per day.

d.

Leakage rate acceptance criteria are:

1. Primary containment overall leakage rate acceptance

criterion is <_ 1.0 La.

During the first unit startup

following testing in accordance with this program, the

leakage rate acceptance criteria are s 0.60 L, for the

combined Type B and Type C tests, and s 0.75 L, for

Type A tests.

2. Air lock testing acceptance criteria are:

a) Overall air lock leakage rate is < 0.05 L, when

tested at > Pa.

b) For each door, the seal leakage rate is <_ 5 scf

per hour when the gap between the door seals is

pressurized to > 10 psig.

e.

The provisions of SR 3.0.3 are applicable to the Primary

Containment Leakage Rate Testing Program.

(continued)

LaSalle 1 and 2

5.5-13

Amendment No. 44-7'

Programs and Manuals 5.5

5.5 Programs and Manuals

5.5.13 Primary Containment Leakage Rate Testing Program (continued)

2. NEI 94-01 - 1995, Section 9.2.3: The first Unit 2 Type A test performed after December 8, 1993 Type A test shall be performed prior to startup following L2R12.

3. The potential valve atmospheric leakage paths that are not exposed to reverse direction test pressure shall be tested during the regularly scheduled Type A test. The program shall contain the list of the potential valve atmospheric leakage paths, leakage rate measurement method, and acceptance criteria. This exception shall be applicable only to valves that are not isolable from the primary containment free air space.

b. The peak calculated primary containment internal pressure for the design basis loss of coolant accident, Pa, is ~ psig.

The maximum allowable primary containment leakage rate, La, at Pa , is 1.0% of primary containment air weight per day.

d. Leakage rate acceptance criteria are:

1. Primary containment overall leakage rate acceptance criterion is ~ 1.0 La. During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are ~ 0.60 La for the combined Type B and Type C tests, and ~ 0.75 La for Type A tests.

2. Air lock testing acceptance criteria are:

a) Overall air lock leakage rate is ~ 0.05 La when tested at ;::: Pa.

b) For each door, the seal leakage rate is ~ 5 scf per hour when the gap between the door seals is pressurized to ;::: 10 psig.

e. The provisions of SR 3.0.3 are applicable to the Primary Containment Leakage Rate Testing Program.

(continued)

LaSalle 1 and 2 5.5-13 Amendment No. 197/184