electrical and its engineering - british columbia · 2019-07-22 · electrical and its engineering...

278
PROGRAMMING GUIDE ECONOLITE COBALT CONTROLLER Electrical and ITS Engineering June 2019

Upload: others

Post on 30-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

PROGRAMMING GUIDE ECONOLITE COBALT CONTROLLER

Electrical and ITS Engineering

June 2019

Page 2: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

INTRODUCTION ..................................................................................................................................................... 5

GUIDE SCOPE AND USE ............................................................................................................................................. 5 EXAMPLE INTERSECTIONS ......................................................................................................................................... 5 GUIDE AUDIENCE AND TRAINING GOALS .................................................................................................................. 6

COBALT SETUP AND NAVIGATION ......................................................................................................................... 7

CLASSIC VIEW ............................................................................................................................................................ 7 NAVIGATION IN CLASSIC VIEW .................................................................................................................................. 7 DATA ENTRY IN CLASSIC VIEW ................................................................................................................................... 8 TRANSACTION MODE ................................................................................................................................................ 8 HELP SCREEN ............................................................................................................................................................. 8

CONFIGURATION DATA PROGRAMMING............................................................................................................. 10

PHASE RING SEQUENCE AND ASSIGNMENT DATA MENU (MM-1-1-1) ................................................................... 12 PHASE COMPATIBILITY DATA MENU (MM-1-1-2) ................................................................................................... 14 BACKUP PREVENT PHASES DATA MENU (MM-1-1-3) .............................................................................................. 16 SIMULTANEOUS GAP PHASES DATA MENU (MM-1-1-4) ......................................................................................... 18 PHASE IN USE/PED DATA MENU (MM-1-2) ............................................................................................................. 20 LOAD SWITCH ASSIGNMENT DATA MENU (MM-1-3) .............................................................................................. 22 PORT 1 (SDLC) DATA MENU (MM-1-4-1) ................................................................................................................. 27 MMU PROGRAM DATA MENU (MM-1-4-2)............................................................................................................. 29 COLOUR CHECK DATA MENU (MM-1-4-3) ............................................................................................................... 31 SECONDARY STATIONS/TESTS DATA MENU (MM-1-4-4) ........................................................................................ 33 ETHERNET DATA MENU (MM-1-5-1) ....................................................................................................................... 37 PORT2/C50S DATA MENU (MM-1-5-2) ................................................................................................................... 39 NTCIP DATA MENU (MM-1-5-5) .............................................................................................................................. 41 ECPIP DATA MENU (MM-1-5-6) ............................................................................................................................... 43 WIRELESS DATA MENU (MM-1-5-7) ........................................................................................................................ 45 EVENT LOGGING DATA MENU (MM-1-6-1) ............................................................................................................. 47 ADMINISTRATION DATA MENU (MM-1-7-1) ........................................................................................................... 51 DISPLAY OPTIONS DATA MENU (MM-1-7-2) ........................................................................................................... 53 SECURITY ACCESS DATA MENU (MM-1-7-3) ........................................................................................................... 55 LOGIC STATEMENT CONTROL DATA MENU (MM-1-8-1) ......................................................................................... 59 LOGIC STATEMENTS DATA MENU (MM-1-8-2)........................................................................................................ 61

CONTROLLER DATA PROGRAMMING ................................................................................................................... 64

TIMING PLANS DATA MENU (MM-2-1) ................................................................................................................... 66 VEHICLE OVERLAPS DATA MENU (MM-2-2) ............................................................................................................ 68 VEH/PED OVERLAPS DATA MENU (MM-2-3) ........................................................................................................... 70 GUAR MIN TIME DATA MENU (MM-2-4) ................................................................................................................. 72 START/FLASH DATA MENU (MM-2-5) ..................................................................................................................... 74 CONTROLLER OPTIONS DATA MENU (MM-2-6-1) ................................................................................................... 77 PRE-TIMED DATA MENU (MM-2-7) ......................................................................................................................... 79 PHASE RECALL DATA MENU (MM-2-8) .................................................................................................................... 81

COORDINATOR DATA PROGRAMMING ................................................................................................................ 84

COORDINATOR OPTIONS DATA MENU (MM-3-1) ................................................................................................... 85 COORDINATOR PATTERNS DATA MENU (MM-3-2) ................................................................................................. 87 SPLIT PATTERNS DATA MENU (MM-3-3) ................................................................................................................. 89 AUTO PERM MIN GREEN DATA MENU (MM-3-4) .................................................................................................... 91 SPLIT DEMAND DATA MENU (MM-3-5) ................................................................................................................... 93

PREEMPTOR/TSP DATA PROGRAMMING ............................................................................................................. 96

Page 3: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

PREEMPT PLAN 1-10 DATA MENU (MM-4-1) .......................................................................................................... 97 PREEMPT PLAN 1-10 DATA MENU CONTINUED (MM-4-1) ...................................................................................... 99 ENABLE PREEMPT FILTERING & TSP/SCP DATA MENU (MM-4-2) ......................................................................... 101 TSP/SCP PLAN DATA MENU (MM-4-3) .................................................................................................................. 103 TSP/SCP SPLIT PATTERN DATA MENU (MM-4-4) ................................................................................................... 105

TIME BASE DATA PROGRAMMING ..................................................................................................................... 108

CLOCK/CALENDAR DATA MENU (MM-5-1) ........................................................................................................... 109 ACTION PLAN DATA MENU (MM-5-2) ................................................................................................................... 111 ACTION PLAN DATA MENU CONTINUED… (MM-5-2) ............................................................................................ 113 DAY PLAN/EVENT DATA MENU (MM-5-3) ............................................................................................................. 115 SCHEDULE NUMBER DATA MENU (MM-5-4) ......................................................................................................... 117 EXCEPTION DAYS DATA MENU (MM-5-5).............................................................................................................. 119

DETECTOR DATA PROGRAMMING ..................................................................................................................... 122

VEHICLE DETECTOR PHASE ASSIGNMENT DATA MENU (MM-6-1) ........................................................................ 123 VEHICLE DETECTOR SETUP DATA MENU (MM-6-2) ............................................................................................... 125 PED DETECTOR PHASE ASSIGNMENT DATA MENU (MM-6-3) ............................................................................... 127 LOG INTERVAL/SPEED DETECTOR SETUP DATA MENU (MM-6-4) ......................................................................... 129 VEHICLE DETECTOR DIAGNOSTICS DATA MENU (MM-6-5) ................................................................................... 131 PEDESTRIAN DETECTOR DIAGNOSTICS DATA MENU (MM-6-6) ............................................................................ 133

PROGRAMMING EXAMPLE: PEDESTRIAN ACTIVATED SIGNAL ........................................................................... 135

SIGNAL DESCRIPTION ............................................................................................................................................ 135 SIGNAL DISPLAY DIAGRAM .................................................................................................................................... 135 SIGNAL TIMING SHEET (STS) .................................................................................................................................. 136 PHASE RING SEQUENCE AND ASSIGNMENT (MM-1-1-1) ...................................................................................... 137 BACKUP PREVENT PHASES (MM-1-1-3) ................................................................................................................. 137 SIMULTANEOUS GAP PHASES (MM-1-1-4) ............................................................................................................ 139 PHASE IN USE/PED (MM-1-2) ................................................................................................................................ 139 LOAD SWITCH ASSIGN (MM-1-3) .......................................................................................................................... 141 SDLC OPTIONS (MM-1-4-1) ................................................................................................................................... 141 MMU PROGRAM (MM-1-4-2) ............................................................................................................................... 143 LOGIC STATEMENT CONTROL (MM-1-8-1) ............................................................................................................ 143 LOGIC STATEMENTS (MM-1-8-2) .......................................................................................................................... 145 TIMING PLANS (MM-2-1) ...................................................................................................................................... 147 VEHICLE OVERLAPS (MM-2-2) ............................................................................................................................... 149 VEH/PED OVERLAPS (MM-2-3) .............................................................................................................................. 149 START/FLASH (MM-2-5) ........................................................................................................................................ 151 CONTROLLER OPTIONS (MM-2-6-1) ...................................................................................................................... 151 PHASE RECALL (MM-2-8) ...................................................................................................................................... 153 CLOCK/CALENDAR DATA (MM-5-1) ...................................................................................................................... 155 ACTION PLAN (MM-5-2) ........................................................................................................................................ 155 DAY PLAN/EVENT (MM-5-3) .................................................................................................................................. 157 SCHEDULE NUMBER (MM-5-4) ............................................................................................................................. 157 VEH DET PHASE ASSIGNMENT (MM-6-1) .............................................................................................................. 159

PROGRAMMING EXAMPLE: GEOMETRICALLY CONFLICTING PROTECTED LEFT TURNS ON THE HIGHWAY ........ 161

SIGNAL DESCRIPTION ............................................................................................................................................ 161 SIGNAL DISPLAY DIAGRAM .................................................................................................................................... 161 SIGNAL TIMING SHEET (STS) .................................................................................................................................. 163 LOOP ASSIGNMENT SHEET (LAS) ........................................................................................................................... 164 PHASE RING SEQUENCE AND ASSIGNMENT (MM-1-1-1) ...................................................................................... 165

Page 4: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

PHASE COMPATIBILITY (MM-1-1-2) ...................................................................................................................... 165 BACKUP PREVENT PHASES (MM-1-1-3) ................................................................................................................. 167 SIMULTANEOUS GAP PHASES (MM-1-1-4) ............................................................................................................ 167 PHASES IN USE (MM-1-2) ...................................................................................................................................... 169 LOAD SWITCH ASSIGNMENT (MM-1-3) ................................................................................................................. 169 SDLC OPTIONS (MM-1-4-1) ................................................................................................................................... 171 MMU PROGRAM (MM-1-4-2) ............................................................................................................................... 171 TIMING PLANS (MM-2-1) ...................................................................................................................................... 173 START/FLASH (MM-2-5) ........................................................................................................................................ 175 CONTROLLER OPTIONS (MM-2-6-1) ...................................................................................................................... 175 PHASE RECALL (MM-2-8) ....................................................................................................................................... 177 COORDINATOR OPTIONS (MM-3-1) ...................................................................................................................... 177 COORDINATOR PATTERNS (MM-3-2) .................................................................................................................... 179 SPLIT PATTERNS (MM-3-3) .................................................................................................................................... 187 PREEMPT PLAN 1-10 (MM-4-1) ............................................................................................................................. 191 CLOCK/CALENDAR DATA (MM-5-1)....................................................................................................................... 197 ACTION PLAN (MM-5-2) ........................................................................................................................................ 199 ACTION PLAN (MM-5-2) ........................................................................................................................................ 207 DAY PLAN/EVENT (MM-5-3) .................................................................................................................................. 215 SCHEDULE NUMBER (MM-5-4) ............................................................................................................................. 217 VEHICLE DETECTOR SETUP (MM-6-2) .................................................................................................................... 219 VEHICLE DETECTOR PHASE ASSIGNMENT (MM-6-1) ............................................................................................. 221

PROGRAMMING EXAMPLE: EIGHT PHASE SIGNAL WITH RAIL PREEMPTION ..................................................... 223

SIGNAL DESCRIPTION ............................................................................................................................................ 223 SIGNAL DISPLAY DIAGRAM .................................................................................................................................... 223 SIGNAL TIMING SHEET (STS) .................................................................................................................................. 225 LOOP ASSIGNMENT SHEET (LAS) ........................................................................................................................... 226 PHASE RING SEQUENCE AND ASSIGNMENT (MM-1-1-1) ...................................................................................... 227 PHASE COMPATIBILITY (MM-1-1-3) ...................................................................................................................... 227 SIMULTANEOUS GAP PHASES (MM-1-1-4) ............................................................................................................ 229 PHASE IN USE/PED (MM-1-2) ................................................................................................................................ 229 LOAD SWITCH ASSIGN (MM-1-3) .......................................................................................................................... 231 SDLC OPTIONS (MM-1-4-1) ................................................................................................................................... 231 MMU PROGRAM (MM-1-4-2) ............................................................................................................................... 233 LOGIC STATEMENT CONTROL (MM-1-8-1) ............................................................................................................ 233 LOGIC STATEMENTS (MM-1-8-2) .......................................................................................................................... 235 TIMING PLANS (MM-2-1) ...................................................................................................................................... 243 VEHICLE OVERLAPS (MM-2-2) ............................................................................................................................... 247 START/FLASH (MM-2-5) ........................................................................................................................................ 249 CONTROLLER OPTIONS (MM-2-6-1) ...................................................................................................................... 249 PHASE RECALL (MM-2-8) ....................................................................................................................................... 251 PREEMPT PLAN 1-10 (MM-4-1) ............................................................................................................................. 253 CLOCK/CALENDAR DATA (MM-5-1)....................................................................................................................... 265 ACTION PLAN (MM-5-2) ........................................................................................................................................ 267 DAY PLAN/EVENT (MM-5-3) .................................................................................................................................. 271 SCHEDULE NUMBER (MM-5-4) ............................................................................................................................. 273 VEHICLE DETECTOR SETUP (MM-6-2) .................................................................................................................... 275 VEHICLE DETECTOR PHASE ASSIGNMENT (MM-6-1) ............................................................................................. 277

Page 5: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5

INTRODUCTION

This Cobalt programming guide was originally distributed as part of a one-day Cobalt programming course provided by the BC Ministry of Transportation and Infrastructure Electrical and ITS Engineering.

It is not the intent of this guide to show how to utilize every aspect of the Econolite Cobalt controller unit. Rather the intent is to standardize the process of programming a Cobalt unit to MoTI signal operation standards. This includes interpreting the documentation provided by MoTI Traffic Engineering and the traffic controller assembly design and applying it via the Cobalt user interface.

GUIDE SCOPE AND USE This guide is limited to the programming of the Econolite Cobalt controller unit via its front panel interface. The Cobalt has two display modes: a full-colour touchscreen graphical display, and the classic text-based view similar to that of the Econolite ASC/3 controller interface. This guide requires the use of the classic view as its layout and interface is better suited for training and instruction.

The core of this guide is divided into six main sections: Configuration Data, Controller Data, Coordinator Data, Preemptor Data, Time Base Data and Detector Data. These sections directly correspond to the six programming sub-menus found on the Cobalt’s Main Menu. Each section is presented on an exhaustive screen-by-screen basis outlining the appropriate programming process.

MoTI programming standards requires that only data needed at an intersection be entered. Therefore data fields in the controller unit not used shall be left disabled or at default settings as described in this guide. This guide does not provide instruction on how to program features not currently used for standard MoTI signal operation. Instead it is indicated that the features are not used and the appropriate data entry to disable the features is given.

Note that the instructions within this guide are not meant to modify or replace information provided by the Cobalt’s manufacturer. You are strongly urged to refer to the manufacturer’s documentation for further detail on Cobalt operation. Additionally this guide is not a stand-alone Cobalt guide or reference. It is to be used in conjunction with formal training where participants can discuss and learn the content from a technical expert.

EXAMPLE INTERSECTIONS The final sections of this manual present completed and proven Cobalt programs for example intersections. Each section begins with the documentation you should expect to have before starting to program a controller unit: a TE series intersection site plan including a Signal Display Diagram, a MoTI approved Signal Timing Sheet (STS) and a Loop Assignment Sheet (LAS). After the documentation the Cobalt program for these intersections is presented on a screen-by-screen basis for your reference.

The example intersections provided are:

1. A pedestrian activated crosswalk signal. 2. A 5-phase intersection with conflicting dual left-turns on the highway. This intersection also has

3-way directional emergency pre-emption.

Page 6: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE SETUP AND NAVIGATION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-6

3. An 8-phase intersection with protected/permissive left-turns on the highway and protected/permissive left turns on the cross-street. This intersection has 4-way directional emergency pre-emption. It also has rail pre-emption on one cross-street approach where the protected/permissive left turns are only activated during rail preemption.

Note that the example program sections only describe those data entries that require analysis and entry by the user. If details are not given for any entries it is assumed the default value is used as indicated in the general programming section.

GUIDE AUDIENCE AND TRAINING GOALS The audience for Cobalt programming training and this guide are journeymen electricians and senior electrical apprentices actively involved in highways electrical maintenance. All training attendees are expected to complete the training course before applying the contents of this guide at their workplace.

Training participants that have completed the course and learned the contents of this manual should be able to:

1. Interpret standard MoTI signal design documentation: a. TE series intersection site plan and signal display diagram b. Signal Timing Sheet c. Loop Assignment Sheet

2. Locate the appropriate Cobalt programming screen for each type of data gathered from the signal design documentation.

3. Describe the purpose of all used Cobalt programming fields. 4. Enter the appropriate data into the Cobalt based on the signal design documentation. 5. Verify and test the validity of the programmed data and backup the program to a USB device.

Page 7: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 4-7

COBALT SETUP AND NAVIGATION

CLASSIC VIEW Before using this manual to aid you in programming an Econolite Cobalt controller unit you will need to put it in its classic view mode. If it is in the graphics mode (shown above) follow these steps:

1. Press the Main Menu button in the top right corner of the controller unit. 2. Press the Settings icon on the touchscreen display. 3. Press Switch to Classic View on the touchscreen display. 4. Press OK on the right side of the touchscreen display. 5. Press the Main Menu button again.

NAVIGATION IN CLASSIC VIEW To navigate classic view menus simply press the numeric button on the Cobalt that corresponds to the number of the menu item you wish to access. To return to the previous menu press the Sub button located beside the Main Menu button. Note that Cobalt documentation and this programming guide make use of Econolite’s short-notation to describe how to find a sub-menu or data screen. For example, to program the Cobalt phase sequence you need to get to its data screen by: starting at the Main Menu, press 1 to access the Configuration Sub-Menu, press 1 again to access the Controller Sequence Sub-Menu, and press 1 again to access the Phase Ring Sequence and Assignment Data Screen. In short-notation you would describe getting to this data screen as MM-1-1-1.

Page 8: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE SETUP AND NAVIGATION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 4-8

Once you are in a data screen you will need to move the screen cursor around to those data fields you wish to program. To do so simply use the directional pad on the Cobalt to move the cursor up, down, left & right.

DATA ENTRY IN CLASSIC VIEW Once you have moved the cursor under the field you wish to change, you will need to enter data to program the Cobalt controller unit. There are two types of programming fields that you will encounter: toggle fields and numeric fields.

1. Toggle Field – A toggle field is a field with a limited number of pre-defined options. To cycle (toggle) through the available options you can press the 0 button or use the + and – toggle buttons located immediately below the directional pad. Refer to the Cobalt help screen for a list of the available options for each field.

2. Numeric Field – In a numeric field you can use the numeric keypad to enter your data provided it is within the allowable range for that field. Refer to the Cobalt help screen for the allowable numeric range for each field.

TRANSACTION MODE Some fields that you change are considered critical by the Cobalt. They are considered critical because they could affect the safe operation of an intersection if you were making these changes on a ‘live’ controller unit.

If you try to move away from a critical field or press Enter after changing a critical field the Cobalt will immediately display its Transaction Mode warning screen. A summary of this screen is as follows:

1. The changes you made are not yet saved and will be deleted if you do not save them in the next 20 minutes.

2. If you have more changes to make and don’t want to be bothered by the Transaction Mode warning screen after every programming change you can: press the Clear button (F button) to get rid of the warning screen, continue making programming changes, and then press the Spec Func followed by the Enter key to save all the changes.

3. If you wish to delete the change you made press the Spec Func key followed by the Clear key.

Note that in (2) above if you leave the Transaction Mode warning screen to make more changes you will still see a message in the top line of the display reminding you that you are still in Transaction Mode and will need to press the appropriate keys to either save or clear your changes.

HELP SCREEN This guide is intended to be as comprehensive as possible in describing how to program a Cobalt to MoTI standards. However on occasion you may be required to program a feature that is not normally used or program it in a non-standard way. In these instances it is recommended that you refer to the Cobalt manufacturer’s documentation. One of the most accessible forms of documentation is the Cobalt’s context sensitive help screens. When programming a Cobalt you can move the cursor under any field on the screen and press the Help key to get a detailed description of the programming feature and its allowable programming values. This is an invaluable source of programming knowledge and you are

Page 9: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE SETUP AND NAVIGATION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 4-9

urged to make use of it regularly when programming. To leave a help screen back to the menu you were in, simply press the Help key again.

Page 10: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-10

CONFIGURATION DATA PROGRAMMING

SELECTION: Enter ‘1’ to access Configuration Sub-Menus

SELECTION: Enter ‘1’ to access Controller Sequence Sub-Menus

Page 11: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-11

SELECTIONS: Menus ‘1’, ‘2’, ‘3’ & ‘4’ are used. The following pages describe typical programming for these menus. Option ‘5’ is not used.

Page 12: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-12

PHASE RING SEQUENCE AND ASSIGNMENT DATA MENU (MM-1-1-1)

CONTROLLER SEQUENCE # Enter 1. If more than one controller sequence is needed then enter another sequence number and program it as required.

SEQUENCE COMMANDS

You can toggle though the following commands if needed: Copy current sequence configuration to higher Controller Sequence numbers, Select Barrier mode for entering the sequence, and Select Compatibility mode for entering the sequence. ENTER selects the option.

HW ALT SEQ ENA Enter NO.

BC

Indicates if the controller sequence is shown in Barrier (B) or Compatibility (C) mode. Default NEMA Dual-Ring is shown in the example and will work for most intersections. Compatibility mode may be required for non-standard controller sequences and requires the phase compatibilities be programmed in the ‘Phase Compatibility’ Menu (MM-1-1-2). In Barrier mode you can move the cursor along the BC row to insert more barriers in the sequence.

R1-4 Enter the phases assigned to each ring. Most intersections will operate with the standard NEMA Dual Ring configuration shown.

Page 13: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-13

Default NEMA Dual-Ring Controller Sequence Data Screen in Barrier Mode

(MM-1-1-1)

Page 14: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-14

PHASE COMPATIBILITY DATA MENU (MM-1-1-2) (Note this menu is unavailable if Controller Sequence is in barrier mode in MM-1-1-1)

PHASE COMPATIBILITY MATRIX

Enter an X for all compatible phases. Phases 1-16 are listed from right-to-left on top row and top-to-bottom on left column. Toggle an X for all phases that may be on at the same time (compatible) in the Controller Sequence programmed in MM-1-1-1. The image shown gives the same compatibilities as the Barrier Mode sequence shown in the previous data screen.

Page 15: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-15

Default NEMA Dual-Ring Phase Compatibilities (MM-1-1-2)

Page 16: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-16

BACKUP PREVENT PHASES DATA MENU (MM-1-1-3)

BACKUP PREVENT PHASE MATRIX

Toggle a B for any phase (row number) to apply an all-red period when backing up to re-service a protected/permissive left turn phase (column number) without automatically setting field displays to all-red first. This is used to prevent any potential left-turn trap scenarios. E.g. if phase 1 is a protected/permissive left turn enter a B in Row 2 & Column 1. The all-red time is determined by the Red Revert time programmed under the current Timing Plan (MM-2-1). Note - if you would rather go to another phase before servicing the backup phase rather than going to all-red: Place the B in the location described above but also place a C in the same row beneath the phase number you wish to service before the backup phase.

Page 17: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-17

Default Backup Prevent Data Screen (MM-1-1-3)

Page 18: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-18

SIMULTANEOUS GAP PHASES DATA MENU (MM-1-1-4)

SIMULTANEOUS GAP PHASES MATRIX

Toggle an X in the row and column of the recall phases as indicated on the STS. E.g. if highway phases 2 & 6 are the recall phases: enter an X on Row 2 under Column 6 and enter an X on Row 6 under Column 2.

Page 19: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-19

Default Simultaneous Gap Phases Data Screen (MM-1-1-4)

SELECTION: After entering the data above return to the Configuration Sub-Menu by pressing the Sub key or by entering MM-1.

SELECTION: Enter ‘2’ to access the Phase In Use Data Screen

Page 20: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-20

PHASE IN USE/PED DATA MENU (MM-1-2)

IN USE Toggle an X under all active phases in the controller sequence. All phases set as ON in the STS are set as in use.

EXCLUSIVE PED

Toggle an X under any phases to be used as an exclusive pedestrian movement phase. An exclusive pedestrian movement times only the pedestrian intervals for that phase. No vehicle timings for that phase will be timed and no concurrent vehicle phases will operate at the same time as an exclusive ped.

Page 21: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-21

Default Phases In Use / Exclusive Ped Data Screen (MM-1-2)

SELECTION: After entering the data above return to the Configuration Sub-Menu by pressing the Sub key or by entering MM-1.

SELECTION: Enter ‘3’ to access the Load Switch Assignment Data Screen.

Page 22: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-22

LOAD SWITCH ASSIGNMENT DATA MENU (MM-1-3)

PHASE/OVLP

Use the cursor and the numeric keypad to assign phase and overlap numbers to the Load Switch number in column LD. The typical Load Switch Assignment convention:

Load Switch Phase/Ovlp/Ped Load

Switch Phase/Ovlp/Ped

1 Vehicle Phase 1 9 Ped Phase 2

2 Vehicle Phase 2

or Overlap 2 (B) if AW

10 Ped Phase 4

3 Vehicle Phase 3 11 Ped Phase 6

4 Vehicle Phase 4

or Overlap 4 (D) if AW

12 Ped Phase 8

5 Vehicle Phase 5 13 Spare Overlap/Phase

6 Vehicle Phase 6

or Overlap 6 (F) if AW

14 Spare Overlap/Phase

7 Vehicle Phase 7 15 Spare Overlap/Phase

8 Vehicle Phase 8

or Overlap 8 (H) if AW

16 Spare Overlap/Phase

Note: If this is a Cobalt TS2-Type 2 to be retrofit into a TS1 cabinet (M or S) it is important to note that regardless of what phase you choose to drive each Load Switch, a TS1 cabinet and its CMU see each Load Switch as:

a) Load Switch 1-8 = TS1 Phases 1-8 b) Load Switch 9-12 = TS1 Phases 2,4,6&8 Peds c) Load Switch 13-16 = TS1 Overlaps A-D

E.g. In a Cobalt retrofit Type S Cabinet, if you assign a program phase/overlap to Load Switch 13 in this screen, that phase/overlap will control the Overlap A Load Switch as noted in the Controller Plans.

TYPE

Toggle the type of controller outputs assigned to the load switch. V for vehicle outputs, O for overlap outputs and P for pedestrian outputs. Refer to the table above for typical TYPE assignment for each Load Switch.

DIMMING – R, Y, G Enter ‘.’.

DIMMING – D Enter ‘.’.

FLASH – PWR Enter A.

FLASH – AUT Enter flash colour for each phase. Flash colour is indicated on the STS under Intersection Flash.

Page 23: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-23

Overlaps used for the traffic signal displays of an Advance Warning phase should flash the Intersection Flash colour indicated for the corresponding phase on the STS.

FLASH – TGR

Not used. All load switches with an X will flash together in automatic flash. All load switches with an ‘.’ will flash together in automatic flash, but on an alternate cycle to those marked X.

Page 24: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-24

Default Load Switch Assignment Data Screen (MM-1-3)

SELECTION: After entering the data above return to the Configuration Sub-Menu by pressing the Sub key or by entering MM-1.

SELECTION: Enter ‘4’ to access the Port 1 (SDLC) Sub-Menu.

Page 25: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-25

THIS PAGE IS LEFT INTENTIONALLY BLANK

Page 26: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-26

Port 1 (SDLC) Sub-Menu (MM-1-4)

SELECTION: Enter ‘1’ to access the Port 1 (SDLC) Options Data Screen.

Page 27: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-27

PORT 1 (SDLC) DATA MENU (MM-1-4-1)

TERM & FACILITY

TS2 Installation: Toggle an X under BIUs 1 if only one detector rack is present or BIU 1 & 2 as shown if two racks are present. This indicates to the Controller Unit that there are BIUs used for critical inputs and outputs. These correspond to the two Load Switch BIUs. The controller unit WILL go into fault and put the intersection in flash if communications to these BIUs is not present. TS1 Retrofit Installation: Leave all entries blank. There are no BIUs in NEMA TS1 Cabinets.

DETECTOR RACK

TS2 Installation: Toggle an X under BIUs 1 & 2 as shown. This indicates to the Controller Unit that there are BIUs used for detector inputs. This is not required at signals with no vehicle detection such as a pedestrian actuated signal. TS1 Retrofit Installation: Leave all entries blank. Detectors are hardwired to the controller inputs.

ENABLE TS2/MMU TYPE CABINET

TS2 Installation: Enter YES. TS1 Retrofit Installation: Enter NO.

ENABLE MMU EXTENDED STATUS Enter NO.

ENABLE SDLC STOP TIME TS2 Installation: Enter YES. TS1 Retrofit Installation: Enter NO.

ENABLE 3 CRITICAL RFEs LOCKUP

TS2 Installation: Enter YES. TS1 Retrofit Installation: Enter NO.

MMU TO CU SDLC EXTERNAL START Enter ENABLED.

Page 28: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-28

Default Port 1 (SDLC) Data Screen (MM-1-4-1)

SELECTION: After entering the data above return to the Port 1 (SDLC) Sub-Menu by pressing the Sub key or by entering MM-1-4.

SELECTION: Enter ‘2’ to access the MMU Program Data Screen.

Page 29: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-29

MMU PROGRAM DATA MENU (MM-1-4-2)

MMU PROGRAM

TS2 Installation; Toggle to MANUAL. The other useful option is CLEAR if you wish to clear all compatibility matrix entries and start over. AUTO should not be used as it has the controller unit determine what it thinks the compatibilities should be. COPY MMU should not be used as it uses SDLC communications to the MMU to copy the compatibilities on the MMU Program Card to the Compatibility Matrix on this data screen. TS1 Retrofit Installation: Disabled Screen. As the TS2/MMU Type Cabinet option was disabled in the last screen, you will be unable to access this screen.

MMU PROGRAM COMPATIBILITY MATRIX

TS2 Installation; For each channel row place an X under each channel column which is compatible. i.e. their green (or walk for peds) displays are permitted to be on at the same time. Note each MMU channel number typically corresponds to the same load switch number, i.e. MMU channel 4 monitors load switch 4’s outputs. It is recommended to use your understanding of intersection operation as well as the Signal Display Diagram in the intersection TE drawings to determine concurrent (compatible) field outputs. This is the best method to determine MMU compatibilities. Important: Ensure you enter the compatibilities for the pedestrian output channels as well (9-12). The MMU does not assume that vehicle phases are output on channels 1-8 and their corresponding pedestrian movements are output on channels 9-12. Therefore you will need to add compatibilities here between vehicle phases and any concurrent pedestrian movements. E.g. if phases 2 & 6 are concurrent you will need to ensure channels 2 & 6 are compatible with each other as well as with ped channels 9 & 11. Channels 9 & 11 will also have to be compatible with each other. TS1 Retrofit Installation: Disabled Screen. As the TS2/MMU Type Cabinet option was disabled in the last screen, you will be unable to access this screen.

Page 30: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-30

MMU Program Data Screen (MM-1-4-2)

SELECTION: After entering the data above return to the Port 1 (SDLC) Sub-Menu by pressing the Sub key or by entering MM-1-4.

SELECTION: Enter ‘3’ to access the Colour Check Data Screen.

Page 31: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-31

COLOUR CHECK DATA MENU (MM-1-4-3)

ENABLE COLOUR CHECK Enter ‘.’ to disable this feature.

Page 32: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-32

Colour Check Enable Data Screen (MM-1-4-3)

SELECTION: After entering the data above return to the Port 1 (SDLC) Sub-Menu by pressing the Sub key or by entering MM-1-4.

SELECTION: Enter ‘4’ to access the Secondary Stations/Tests Data Screen.

Page 33: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-33

SECONDARY STATIONS/TESTS DATA MENU (MM-1-4-4)

TERMINAL & FACILITY SECONDARY TO SECONDARY

ADDRESSING Enter ‘.’ to disable this feature for all columns as shown.

DETECTOR RACK SECONDARY TO SECONDARY

ADDRESSING Enter ‘.’ to disable this feature for all columns as shown.

ENABLE SDLC DIAGNOSTIC TEST Enter NO to disable.

Page 34: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-34

Secondary Stations/Tests Data Screen (MM-1-4-4)

SELECTION: After entering the data above return to the Configuration Sub-Menu by pressing the Sub key twice or by entering MM-1.

SELECTION: Enter ‘5’ to access the Communications Sub-Menu.

Page 35: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-35

THIS PAGE IS LEFT INTENTIONALLY BLANK

Page 36: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-36

Communications Sub-Menu (MM-1-5)

SELECTION: Enter ‘1’ to access the Ethernet Data Screen.

Page 37: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-37

ETHERNET DATA MENU (MM-1-5-1)

MAC Read only. MAC address in hexadecimal. To be used as a reference when networking controller units.

CONTROLLER IP

Default shown. Internet Protocol (IP) address of controller unit on ENET-1 (WAN) port. Can be set and used in the setup of networked controller units.

SUBNET MASK Default shown. Mask used when setting up network subnets.

DEFAULT GATEWAY IP Default shown. Address of network gateway. To be used as a reference when networking controller units.

SERVER IP Default shown. Address of FTP server on network. Only used if file download options are being used with the controller unit.

LINK SPEED/DUPLEX Read only. Current speed and communications configuration on ENET-1 (WAN) port.

DROP-OUT TIME

Default shown. If the controller unit does not receive a valid command from central control software within the drop-out time from the last command it will revert to local programmed control. Time is in seconds.

ENET-2 IP

Default shown. Read only Internet Protocol (IP) address of controller unit on the ENET-2 port.

Page 38: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-38

Default Ethernet Communications Data Screen (MM-1-5-1)

SELECTION: After entering the data above return to the Communications Sub-Menu by pressing the Sub key or by entering MM-1-5.

SELECTION: Enter ‘2’ to access the Port 2 Data Screen.

Page 39: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-39

PORT2/C50S DATA MENU (MM-1-5-2)

ENABLE Set to ON if serial communications via Serial Port 2 are needed. This port is typically not used.

PROTOCOL Set to the appropriate communications protocol being used on Serial Port 2.

BIT RATE Set to the Bit Rate (per second) being used on Serial Port 2.

ADDRESS Address of the controller unit when NTCIP or AB3418 communications protocols are used. Typically 0 (off).

D/P/S Setting for number of Data Bits (D), Parity (P) and Stop Bits (S) in serial communications. Applies to Terminal and NTCIP communications protocols.

GROUP ADDRESS Group address setting for NTCIP/AB3418 communications protocols.

DUPLEX Set for Half Duplex (shared comm. lines) or Full Duplex (independent comm. lines).

DROP-OUT TIME

If the controller unit does not receive a valid command from central control software within the drop-out time from the last command it will revert to local programmed control. Time is in seconds.

FLOW CONTROL Set to Yes or No depending on serial communications network.

SINGLE FLAGGED

Set to Yes or No depending on how communications frames are dealt with on the communications network. Used with NTCIP.

Page 40: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-40

Default Port 2 Communications Data Screen (MM-1-5-2)

SELECTION: After entering the data above return to the Communications Sub-Menu by pressing the Sub key or by entering MM-1-5.

SELECTION: Skip screens 3 & 4 as Port 3 is not included in Ministry standard Cobalts. Enter ‘5’ to access the NTCIP Data Screen.

Page 41: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-41

NTCIP DATA MENU (MM-1-5-5)

BACKUP TIME Default = 0.

ETHERNET UDP PORT Default = 501.

ETHERNET PRIORITY Default = 1.

Page 42: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-42

Default NTCIP Communications Data Screen (MM-1-5-5)

SELECTION: After entering the data above return to the Communications Sub-Menu by pressing the Sub key or by entering MM-1-5.

SELECTION: Enter ‘6’ to access the ECPIP Data Screen.

Page 43: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-43

ECPIP DATA MENU (MM-1-5-6)

CONTROLLER ADDRESS Default = 0. Address of local controller unit on a network of controller units.

EXPANDED SYSTEM DETECTOR ADDRESS

Default = 0. Address used by central control software to access local detector inputs 9-16. Local detectors 1-8 only require the Controller Address for access.

LOCAL DET/SYSTEM DET ASSIGNMENT

Default = 0. Used to map local detector inputs to system-wide (e.g. Centracs control software) detector numbers.

Page 44: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-44

Default ECPIP Communications Data Screen (MM-1-5-6)

SELECTION: After entering the data above return to the Communications Sub-Menu by pressing the Sub key or by entering MM-1-5.

SELECTION: Enter ‘7’ to access the Wireless Data Screen.

Page 45: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-45

WIRELESS DATA MENU (MM-1-5-7)

WIRELESS CHANNEL # Default = 1. Wireless channel (1-11).

WIRELESS ACCESS CODE Default = 327423274. WPA wireless security code.

Page 46: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-46

Default Wireless Communications Data Screen (MM-1-5-7)

SELECTION: After entering the data above return to the Communications Sub-Menu by pressing the Sub key or by entering MM-1-5.

SELECTION: Enter ‘8’ to access the Peer to Peer Data Screen.

Page 47: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-47

EVENT LOGGING DATA MENU (MM-1-6-1)

ALL ITEMS ON SCREEN Default =YES.

Page 48: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-48

Default Event Logging Data Screen (MM-1-6-1)

SELECTION: After entering the data above return to the Configuration Sub-Menu by pressing the Sub key twice or by entering MM-1.

SELECTION: Enter ‘6’ to access the Display/Access Sub-Menu.

Page 49: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-49

THIS PAGE IS LEFT INTENTIONALLY BLANK

Page 50: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-50

Display/Access Sub-Menu (MM-1-7)

SELECTION: Enter ‘1’ to access the Administration Data Screen.

Page 51: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-51

ADMINISTRATION DATA MENU (MM-1-7-1)

ENABLE CU/CABINET INTERLOCK CRC Enter NO.

CU/CABINET INTERLOCK CRC VALUE Read only.

CU/CABINET INTERLOCK HW VALUE Read only.

REQUEST DOWNLOAD CONTROLLER DATA Enter NO.

CONTROLLER DATABASE CRC Read only.

AUTOMATIC BACKUP TO DATAKEY/SD CARD Enter NO.

Page 52: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-52

Administration Data Screen (MM-1-7-1)

SELECTION: After entering the data above return to the Display/Access Sub-Menu by pressing the Sub key or by entering MM-1-7.

SELECTION: Enter ‘2’ to access the Display Options Sub-Menu.

Page 53: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-53

DISPLAY OPTIONS DATA MENU (MM-1-7-2)

KEY CLICK ENABLE Default = YES. Set this to NO if you do not want to hear a click every time a button on the controller unit is pressed.

SWITCH TO GRAPHICS MODE

Default = NO. Set this to YES if you wish to use the Cobalt’s touchscreen graphical user interface. For the purpose of this programming manual it should be set to NO.

LED MODE Enter AUTO. MAIN STATUS DISPLAY

MODE Enter ADVANCED.

TRANS MODE POP-UP DISABLE Enter NO.

Page 54: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-54

Default Event Logging Data Screen (MM-1-7-2)

SELECTION: After entering the data above return to the Display/Access Sub-Menu by pressing the Sub key or by entering MM-1-7.

SELECTION: Enter ‘2’ to access the Security Access Sub-Menu.

Page 55: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-55

SECURITY ACCESS DATA MENU (MM-1-7-3)

ALL ENTRIES

Leave as shown. Changing these values may add password restrictions to the controller unit which could interfere with traffic signal operation troubleshooting.

Page 56: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-56

Default Security Access Data Screen (MM-1-7-3)

SELECTION: After entering the data above return to the Configuration Sub-Menu by pressing the Sub key twice or by entering MM-1.

SELECTION: Enter ‘8’ to access the Logic Processor Sub-Menu.

Page 57: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-57

THIS PAGE IS LEFT INTENTIONALLY BLANK

Page 58: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-58

Logic Processor Sub-Menu (MM-1-8)

SELECTION: Enter ‘1’ to access the Logic Statement Control Data Screen.

Page 59: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-59

LOGIC STATEMENT CONTROL DATA MENU (MM-1-8-1)

LOGIC STATEMENT CONTROL MATRIX

Toggle E for any Logic Processor (LP) logic statements you wish to have Enabled.

Page 60: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-60

Default Logic Statement Control Data Screen (MM-1-8-1)

SELECTION: After entering the data above return to the Logic Processor Sub-Menu by pressing the Sub key or by entering MM-1-8.

SELECTION: Enter ‘2’ to access the Logic Statements Data Screen.

Page 61: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-61

LOGIC STATEMENTS DATA MENU (MM-1-8-2)

LP# Enter the statement # you wish to edit and press Enter. This statement number corresponds to the LP number Enabled or Disabled in the Logic Statement Control Data Screen (MM-1-8-1).

COPY FROM If you wish to copy another Logic Processor statement into your current statement enter the number you wish to copy from and press ENTER.

IF/THEN/ELSE

The Logic Processor statement in an IF/THEN/ELSE format based on controller unit internal timers and states as well as its Inputs and Outputs (I/Os). If you press a key adjacent to the IF, THEN or ELSE the Cobalt will give a list of all timers, states and I/Os that can be used in the statement. After an item is added, more detail is needed. For example if you add ‘VEH GREEN ON PH’ beside an IF, you will need to add in two more details: which phase #, and whether it is ON or OFF. The typical application for the Logic Processor is for activating the Advance Warning Flashers before a phase terminates. TS2 Cabinet Advance Warning The most recent TS2 cabinets use the normally un-used yellow output of the pedestrian load switches (LS9-12) to activate the advance warning flashers. Below are 2 sample Logic Processor statements used to actuate Advance warning flashers for the highway phases 2 & 6 in a standard TS2 NEMA Dual Ring controller. In this case phases 2 & 6 in the controller unit activate the advance warning flashers and the field displays for phases 2 & 6 are delayed overlaps (OLB & OLF) of phases 2 & 6. Activating the advance warning for phase 2: IF VEH GREEN ON PH 2 IS ON THEN SIG SET PH PED CLR 2 OFF ELSE SIG SET PH PED CLR 2 ON And activating the advance warning for phase 6: IF VEH GREEN ON PH 6 IS ON THEN SIG SET PH PED CLR 6 OFF ELSE SIG SET PH PED CLR 6 ON These examples assume Load Switches 9 and 11 are used for the Phase 2 & 6 pedestrian outputs respectively. TS1 Cabinet Advance Warning The NEMA TS1 Type M & S cabinets require some cabinet modifications including Controller Unit I/O re-mapping, re-wiring the advance warning flashers, and the addition of an adapter cable when retrofitting a Cobalt into them. Refer to Volume 1 of the Traffic Controller Assembly Manual for instructions on how to perform this retrofit before continuing. If the TS1 cabinet has been properly modified for the Cobalt the following statements will actuate Advance Warning:

Page 62: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-62

Using the previous examples, activating the advance warning for phase 2: IF VEH GREEN ON PH 2 IS ON THEN LP SET COB OFF 521 ELSE LP SET COB ON 521 And activating the advance warning for phase 6: IF VEH GREEN ON PH 6 IS ON THEN LP SET COB OFF 525 ELSE LP SET COB ON 525 These statements can be used for Advance Warning on any phase. The COB codes for Advance Warning Phases 1-8 are COB 520-527 respectively. Refer to the ASC/3 Programming Manual Appendix on the Logic Processor at the end of this manual for more information on using the Logic Processor.

Page 63: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONFIGURATION DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 5-63

Default Logic Statement Data Screen (MM-1-8-2)

SELECTION: After entering the data above return to the Main Menu.

Page 64: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-64

CONTROLLER DATA PROGRAMMING

SELECTION: Enter ‘2’ to access Controller Sub-Menus

SELECTION: Enter ‘1’ to access the Timing Plans Data Screen

Page 65: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-65

THIS PAGE IS LEFT INTENTIONALLY BLANK

Page 66: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-66

TIMING PLANS DATA MENU (MM-2-1)

TIMING PLAN # Enter the Timing Plan #. The timing plan # is used in the Time Base section to call different timing plans by time of day.

MIN GRN Enter the Minimum Green times for each phase as shown on the STS.

BK MGRN, CS MGRN, DLY GRN Enter 0. Not used.

WALK Enter the Walk times for each phase as shown on the STS.

WALK2, WLK MAX

Enter 0 if no Walk time changes are specified by time of day on the STS. If a change is requested by time of day enter it in Walk 2 to be activated by a scheduled Action Plan (MM-5-2).

PED CLR Enter the Pedestrian Clear times for each phase as shown on the STS.

PD CLR2, PC MAX, PED CO Enter 0. Not used.

VEH EXT Enter the Passage times for each phase as shown on the STS.

VH EXT2

Enter 0 if no Passage time changes are specified by time of day on the STS. If a change is requested by time of day enter it here to be activated by a scheduled Action Plan (MM-5-2).

MAX1, MAX2, MAX3 Enter the Max 1, Max 2 and Max 3 times as indicated on the STS.

DYM MAX Enter the Dynamic Max limit as specified on the STS. If dynamic max is specified on the STS, enter the highest max time allowable here.

DYM STP

Enter the Dynamic Max Step value from the STS. If dynamic max is specified on the STS, enter the amount the max time is increased after 3 successive ‘max-outs’ of the given phase.

YELLOW Enter the Yellow times for each phase from the STS.

RED CLR Enter the Red times for each phase from the STS.

RED MAX Enter 0. Not used.

RED RVT

Enter 2.0s unless otherwise specified on STS. This is the red time applied before the phase is re-serviced. The red revert time is only applied if a re-service of the phase is not inhibited by the Backup Prevent Phases matrix previously programmed (MM-1-1-3).

ACT B4, SEC ACT, MAX INT, TIME B4, CARS WT, STPTDUC,

TTREDUC, MIN GAP Enter 0. Not used.

Page 67: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-67

Timing Plan Data Screen

(MM-2-1)

SELECTION: After entering the data above return to the Controller Sub-Menu by pressing the Sub key or by entering MM-2.

SELECTION: Enter ‘2’ to access the Vehicle Overlaps Data Screen.

Page 68: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-68

VEHICLE OVERLAPS DATA MENU (MM-2-2)

TMG VEH OVLP Toggle to the overlap you want to edit. Overlaps A to P are available.

TYPE Enter OTHER/ECONOLITE. This enables the Lagging Green feature needed to program Advance Warning.

INCLUDED Enter an X for all phases that are included for the overlap.

PROTECT Leave blank for typical Ministry overlaps. Refer to the Help Screen for details of this feature if complex overlap operation is required.

PED PRTC Leave blank for typical Ministry overlaps. Refer to the Help Screen for details of this feature if complex overlap operation is required.

NOT OVLP Leave blank for typical Ministry overlaps. Refer to the Help Screen for details of this feature if complex overlap operation is required.

FLASH GRN Enter ‘.’, 1, 2 or 5 for solid, 1fps, 2.5fps or 5fps green display.

LAG X PH

Enter an X under each Included phase where the overlap green terminates after (lags) the Included phase green has terminated. The amount of time after the Included phase green terminates that must expire before the overlap green terminates is determined by the LAG GRN time. Lagging Vehicle Overlaps are used to provide the advance warning function. E.g. Advance warning for phase 2 can be achieved by using a lagging overlap A to control the phase 2 field displays. When phase 2 green in the controller terminates this is the beginning of the advance warning period but the lagging green overlap is still on until LAG GRN expires. This works for phase 2 advance warning provided LAG GRN is set to the phase 2 advance warning time and the YEL and RED times are set to the phase 2 yellow and red times as shown on the STS.

LAG 2 PH Leave blank for typical Ministry overlaps. Refer to the Help Screen for details of this feature if complex overlap operation is required.

LAG GRN Enter time after the Included phase green terminates that the overlap green terminates. If used for advance warning this is programmed with the AWF TIME as shown on the STS.

YEL Enter the yellow time for the overlap. When used for advance warning enter the yellow time of the phase the advance warning is applied to as shown on the STS.

RED Enter the red time for the overlap. When used for advance warning enter the red time of the phase the advance warning is applied to as shown on the STS.

ADV GRN Leave as 0 for typical Ministry overlaps. Refer to the Help Screen for details of this feature if complex overlap operation is required.

Page 69: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-69

Vehicle Overlaps Data Screen (MM-2-2)

SELECTION: After entering the data above return to the Controller Sub-Menu by pressing the Sub key or by entering MM-2.

SELECTION: Enter ‘3’ to access the Veh/Ped Overlaps Data Screen.

Page 70: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-70

VEH/PED OVERLAPS DATA MENU (MM-2-3)

VEH/PED OVERLAPS MATRIX

Provides a summary of all Included Phases for each programmed overlap. While included phases can be added or deleted on this screen it is not recommended. It is better to modify overlaps in the Vehicle Overlaps section (MM-2-2) where all of the overlap details can be managed rather than just the included phases.

Page 71: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-71

Veh/Ped Overlaps Data Screen (MM-2-3)

SELECTION: After entering the data above return to the Controller Sub-Menu by pressing the Sub key or by entering MM-2.

SELECTION: Enter ‘4’ to access the Guar Min Time Data Screen.

Page 72: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-72

GUAR MIN TIME DATA MENU (MM-2-4)

GUARANTEED MINIMUM TIME DATA

Leave as default values shown in image. These are the ‘safety net’ values for all phase/overlap: minimum green, walk, pedestrian clear, yellow, red and overlap green timings. If lower values for these parameters are programmed elsewhere on the controller unit these guaranteed min time values will prevail. This is to protect against programming critical timing values too low where it may impact public safety.

Page 73: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-73

Guaranteed Min Time Data Screen (MM-2-4)

SELECTION: After entering the data above return to the Controller Sub-Menu by pressing the Sub key or by entering MM-2.

SELECTION: Enter ‘5’ to access the Start/Flash Data Screen.

Page 74: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-74

START/FLASH DATA MENU (MM-2-5)

START UP

PHASE

TS2 Installation: Enter the state of the last timed intervals before the controller unit leaves flash and enters 3-colour operation. These should be set such that the controller enters 3-colour operation into the First Green Display as indicated on the STS. If it is left as ‘.’ it is assumed the phase is red and is not timing. TS1 Installation: Enter the state of the last timed interval before the hardwired FOP is true and the ELB card initiates 3-colour operation. E.g. FOP is set to phase 2 & 6 red so phase 4 green is the First Green Display. Set the Cobalt to start in phase 2 & 6 yellow.

OVERLAP Enter an X for all overlaps that are to be active when the controller enters 3-colour operation. Enter an X for all used overlaps unless the STS explicitly says not to.

FLASH>MON Enter YES. This tells the controller unit to use its CVM output and the TS2 assembly flash transfer circuitry to flash the intersection.

FL TIME TS2:Enter 10. TS1: Enter 5. This is the time the controller unit will wait after power-up to assert its CVM output and allow the signal to enter 3-colour operation.

ALL RED TS2:Enter 6 if all displays flash red. Enter 0 otherwise. TS1: Enter 0. All red time applied to all phases after exiting flash.

PWR START SEQ. Typically 1. Controller sequence to use on startup as programmed in MM-1-1-1.

MUTCD Enter NO.

AUTOMATIC FLASH

PHASE ENTRY Enter X beneath the last phases to be timed through to their red intervals before the controller enters remote or automatic flash. It is recommended to choose cross-street phases for flash entry.

PHASE EXIT

Enter X beneath the phase(s) the controller unit must be in when exiting remote or automatic flash. The interval the exit phase(s) are timing when the controller exits flash is determined by the EXIT FL. parameter. To maintain the First Green Display setting on the STS it is recommended to have the exit phases the same as the start up phases.

OVERLAP EXIT

Enter an X for all overlaps that are to be active when the controller exits to remote or automatic flash. Enter an X for all used overlaps unless the STS explicitly says not to.

FLASH>MON Enter YES. This tells the controller unit to use its CVM output and the TS2 assembly flash transfer circuitry for flash.

EXIT FL.

Enter the interval that the programmed PHASE EXIT phase(s) will start in when exiting remote or automatic flash. To maintain the First Green Display setting on the STS it is recommended to have this interval the same as the start up phase intervals.

MIN FLASH TS2 Enter 5. TS1 Enter 8. Minimum time the controller will stay in flash. MINIMUM RECALL Enter NO. Vehicle demand is used after exiting auto flash.

Page 75: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-75

CYCLE THRU PHASE Enter NO. Vehicle demand is used after exiting auto flash.

Page 76: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-76

Start/Flash Data Screen (MM-2-5)

SELECTION: After entering the data above return to the Controller Sub-Menu by pressing the Sub key or by entering MM-2.

SELECTION: Enter ‘6’ to access the Option Data Sub-Menu. Enter ‘1’ to access the Controller Options Data Screen.

Page 77: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-77

CONTROLLER OPTIONS DATA MENU (MM-2-6-1)

PED CLEAR PROTECT Enter X.

UNIT RED REVERT Enter 2.0. This is the default red revert time for all used phases. The larger of this value or the one programmed for each phase in the Timing Plans (MM-2-1) is used.

MUTCD 3 SECONDS DON’T WALK Enter NO.

FLASHING GRN PH Toggle to ‘.’ if the phase green is a solid green. Toggle to F2 if the phase is protected/permissive. This flashes the protected/permissive arrow at 2fps.

GUAR PASSAGE Enter ‘.’. Not used.

NON-ACT I, NON-ACT II Enter ‘.’. Not used.

DUAL ENTRY Enter X beneath the concurrent cross-street (street without recall programming) through phases.

COND SERVICE Enter ‘.’. Not used.

COND RESERVICE Enter ‘.’. Not used.

PED RESERVICE Enter ‘.’. Not used.

REST IN WALK Enter ‘.’. Not used.

FLASHING WALK Enter ‘.’. Not used.

PED CLR>YELLOW Enter ‘.’. Not used.

PED CLR>RED Enter ‘.’. Not used.

IGRN + VEH EXT Enter ‘.’. Not used.

Page 78: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-78

Controller Options Data Screen (MM-2-6-1)

SELECTION: After entering the data above return to the Controller Sub-Menu by pressing the Sub key or by entering MM-2.

SELECTION: Enter ‘7’ to access the Pre-Timed Data Screen.

Page 79: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-79

PRE-TIMED DATA MENU (MM-2-7)

ENABLE PRE-TIMED MODE Enter NO. Not used. FREE INPUT DISABLES PRE-

TIMED Enter NO. Not used.

PRETIMED Leave all phases unchecked. Not used.

Page 80: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-80

Pre-Timed Data Screen (MM-2-7)

SELECTION: After entering the data above return to the Controller Sub-Menu by pressing the Sub key or by entering MM-2.

SELECTION: Enter ‘8’ to access the Phase Recall Data Screen.

Page 81: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-81

PHASE RECALL DATA MENU (MM-2-8)

TIMING PLAN NUMBER Enter the timing plan number (MM-2-1) these recall settings apply to.

LOCK DET Typically unchecked for new controllers. If detection is losing vehicles (i.e. video detection) you can set a detector lock for the phase affected.

VE RECALL Enter an X for all phases showing RECALL as EXT or MIN on the STS.

PD RECALL Leave unchecked. Not used.

MX RECALL Enter an X for all phases showing RECALL as MAX on the STS.

SF RECALL Leave unchecked. Not used.

NO REST Leave unchecked. Not used.

AI CALC Leave unchecked. Not used.

Page 82: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-82

Pre-Timed Data Screen (MM-2-8)

SELECTION: After entering the data above return to the Main Menu.

Page 83: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE CONTROLLER DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 6-83

THIS PAGE IS LEFT INTENTIONALLY BLANK

Page 84: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-84

COORDINATOR DATA PROGRAMMING

SELECTION: Enter ‘3’ to access Coordinator Sub-Menus

SELECTION: Enter ‘1’ to access the Coordinator Options Data Screen

Page 85: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-85

COORDINATOR OPTIONS DATA MENU (MM-3-1)

MANUAL PATTERN Select AUTO. This allows coordination to be controlled via Time Base schedules (MM-5).

ECPI COORD Select YES.

SYSTEM SOURCE Select TBC unless the STS specifies an external source to be used to control coordination rather than the Time Base Clock.

SYSTEM FORMAT Select STD.

SPLITS IN Select SECONDS unless the STS shows the splits as percentages of the cycle length.

OFFSET IN Select SECONDS.

TRANSITION Select SMOOTH.

MAX SELECT Select MAXINH.

DWELL/ADD TIME Select 0.

ENABLE MAN SYNC Enter NO.

DLY COORD WK-LZ Enter NO.

FORCE OFF Enter FLOAT.

OFFSET REF Enter YELLOW unless the STS specifies otherwise.

CAL USE PED TM Enter NO for typical Ministry operation. However in areas with very high pedestrian activity it may be necessary to set this to YES at a traffic engineer’s discretion.

PED RECALL Enter NO.

PED RESERVE Enter YES.

LOCAL ZERO OVRD. Enter NO.

FO ADD INI GRN. Enter NO.

RE-SYNC COUNT Enter 0.

MULTISYNC Enter NO.

Page 86: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-86

Coordinator Options Data Screen (MM-3-1)

SELECTION: After entering the data above return to the Coordinator Sub-Menu by pressing the Sub key or by entering MM-3.

SELECTION: Enter ‘2’ to access the Coordinator Patterns Data Screen.

Page 87: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-87

COORDINATOR PATTERNS DATA MENU (MM-3-2)

COORDINATOR PATTERN

Enter the coordinator pattern number being programmed. A new pattern is required for every unique cycle/split/offset combination. This pattern number will be used when scheduling coordination in the Time Base Action Plan (MM-5-2).

USE SPLIT PATTERN Select the split pattern to be used in this coordination pattern as programmed in MM-3-3.

CYCLE Enter the Cycle length for this pattern as shown on the STS.

STD (COS) Enter 0 if there is no external master. Cycle/Split/Offset command that will call this coordinator pattern if an external master controller is used for coordination.

OFFSET VAL Enter the Offset for this pattern as shown on the STS.

DWELL/ADD TIME Enter 0.

ACTUATED COORD Enter YES.

TIMING PLAN Enter 0.

ACT WALK REST Enter NO.

SEQUENCE Select 0.

PHASE RESRVCE Enter NO.

ACTION PLAN Enter 0.

MAX SELECT

Enter NONE. The MAX SELECT programmed in COORDINATOR OPTIONS (MM-3-1) will determine this value. If you enter anything else it will override the setting in MM-3-1.

FORCE OFF

Enter NONE. The FORCE OFF programmed in COORDINATOR OPTIONS (MM-3-1) will determine this value. If you enter anything else it will override the setting in MM-3-1.

SPLIT PREFERENCE SETTINGS Leave all values as 0. Not used.

SPLIT DEMAND SETTINGS Do not enter values here. The Split Pattern Data (MM-3-3) from the above USE SPLIT PATTERN will automatically appear here.

Page 88: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-88

Coordinator Patterns Data Screen (MM-3-2)

SELECTION: After entering the data above return to the Coordinator Sub-Menu by pressing the Sub key or by entering MM-3.

SELECTION: Enter ‘3’ to access the Split Patterns Data Screen.

Page 89: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-89

SPLIT PATTERNS DATA MENU (MM-3-3)

SPLIT PATTERN Enter the split pattern number being programmed. The split pattern number is called by a coordination pattern in MM-3-2.

SPLIT Enter the splits for each phase as shown on the STS.

COORD Enter an X beneath the coordinated phases as shown on the STS.

VE RCALL Enter an X beneath the recall phases as shown on the STS.

PD RCALL Not used.

MX RCALL Not used.

OMIT Not used.

Page 90: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-90

Split Patterns Data Screen (MM-3-3)

SELECTION: After entering the data above return to the Coordinator Sub-Menu by pressing the Sub key or by entering MM-3.

SELECTION: Enter ‘4’ to access the Auto Perm Min Green Data Screen.

Page 91: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-91

AUTO PERM MIN GREEN DATA MENU (MM-3-4)

MIN GRN Enter 0. Coordination will rely on the MIN GRN setting in the timing plan (MM-2-1).

Page 92: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-92

Auto Perm Min Green Data Screen (MM-3-4)

SELECTION: After entering the data above return to the Coordinator Sub-Menu by pressing the Sub key or by entering MM-3.

SELECTION: Enter ‘5’ to access the Split Demand Data Screen.

Page 93: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-93

SPLIT DEMAND DATA MENU (MM-3-5)

DEMAND 1 Leave blank. Not used.

DEMAND 2 Leave blank. Not used.

DETECTOR Enter 0 for both columns.

CALL TIME (SEC) Enter 0 for both columns.

CYCLE COUNT Enter 0 for both columns.

Page 94: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-94

Split Demand Data Screen (MM-3-5)

SELECTION: After entering the data above return to the Main Menu.

Page 95: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE COORDINATOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 7-95

THIS PAGE IS LEFT INTENTIONALLY BLANK

Page 96: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-96

PREEMPTOR/TSP DATA PROGRAMMING

SELECTION: Enter ‘4’ to access Preemptor/TSP Sub-Menus

SELECTION: Enter ‘1’ to access the Preempt Plan 1-10 Data Screen

Page 97: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-97

PREEMPT PLAN 1-10 DATA MENU (MM-4-1)

PREEMPT PLAN Enter the Preempt Plan #. Corresponds to the preemption input number on the STS.

ENABLE Enter YES if this preempt input is included on the STS.

TRKCLR V Enter the track clearance phase(s) as shown on the STS. Place an X for solid or F2 for flashing green.

TRKCLR O Enter the track clearance overlap(s) as shown on the STS.

ENA TRL Enter the trailing (lagging) overlap(s) that will remain active during preemption. At a minimum all overlaps used in conjunction with advance warning should have an X.

DWEL VEH Enter the vehicle phases that will be serviced after track clearance. Place an X for solid or F2 for flashing green.

DWEL PED Enter the ped movements that will be serviced after track clearance.

DWEL OLP Enter the overlaps that will be serviced after track clearance. Place an X for solid or F2 for flashing green.

CYC VEH Enter the vehicle phases that will be serviced after the dwell period. Place an X for solid or F2 for flashing green.

CYC PED Enter the ped movements that will be serviced after the dwell period.

CYC OLP Enter the overlaps that will be serviced after the dwell period. Place an X for solid or F2 for flashing green.

EXIT PH Place an X beneath the phases that the controller will exit to when the preemption call has ended.

EXIT CAL Place an X beneath the phases that the controller will place a vehicle call to when the preemption call has ended.

SP FUNC Place an X beneath one of the 8 special function outputs to be activated when the preemption sequence is active.

ENABLE Enter YES if this preempt input is included on the STS.

PMT OVRIDE

TS2: Place an X for preempt plans 1 & 2 (assumed rail preempts). Place an ‘.’ for preempt plans 3 to 5 (assumed equal priority emergency preempts). Enter X for preempt plan 6. TS1: Add an X for preempt plan 6 only. The Pre-Empt Input Modifier Card will assign priority to simultaneous pre-empt calls.

INTERLOCK Enter NO.

DET LOCK Enter X.

DELAY Enter DELAY TIME value from the STS.

INHIBIT Enter 0.

OVERIDE FL Not used. Automatic flash is not used by the Ministry.

DURATION Enter 10 unless the STS specifies another minimum preemption activation time.

Page 98: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-98

Preempt Plan 1-10 Data Screen (2 of 3 screens) (MM-4-1)

Page 99: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-99

PREEMPT PLAN 1-10 DATA MENU CONTINUED (MM-4-1)

CLR>GRN Enter NO.

TERM OLP Enter NO.

PC>YEL Enter NO.

TERM PH Enter YES if the STS calls for All Red at the beginning of the preempt sequence.

PED DARK Enter NO.

TC RSRV Enter NO.

DWEL FL Enter: 0 if this is not for rail. MON if this is used for a failed supervisory circuit 6-wire rail preemption call.

LINK PMT Enter 0.

X FLCOLR Default = RED.

EXIT OPT Enter OFF.

X TMG PLN Enter 0.

RE-SERV Enter 0.

FLT TYPE Enter HARD.

FREE DUR PMT Enter NO for all rings.

ENTRANCE TIMING

Enter WALK = 0. Enter PED CLR = 0 (if rail PE) or 255 (if emergency PE). Enter preemption minimum green as per the STS. Enter YEL = 25.5 to use timing plan programmed yellow. Enter RED = 25.5 to use timing plan programmed red.

TRACK CLEAR TIMING

Enter MIN GR as per track clearance green time on STS. Enter EXT GR as per STS. Enter 0 if not on STS. Enter MX GR as per STS. Enter 0 if not on STS. Enter YEL = 25.5 to use timing plan programmed yellow. Enter RED = 25.5 to use timing plan programmed red.

DWL/CYC EXIT TIMING

Enter MIN DL = 0. Enter PMT EXT = 0. Enter MX TM = 0 (for rail PE) or 180 (for emergency PE). Enter YEL = 25.5 to use timing plan programmed yellow. Enter RED = 25.5 to use timing plan programmed red.

PMT ACTIVE OUT Enter ON.

PMT ACT DWELL Enter YES.

OTHER – PRI PMT Enter OFF.

NON-PRI PMT Enter OFF.

INH EXT TIME Enter 0.

Page 100: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-100

PED PR RETURN Enter OFF.

PRIORITY RETURN Enter OFF.

QUEUE DELAY Enter OFF.

COND DELAY Enter OFF.

PR RTN% Enter 0 for all phases.

Preempt Plan 1-10 Data Screen (3rd of 3 screens) (MM-4-1)

SELECTION: After entering the data above return to the Preemptor/TSP Sub-Menu by pressing the Sub key or by entering MM-4.

SELECTION: Enter ‘2’ to access the Enable Preempt Filtering Data Screen.

Page 101: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-101

ENABLE PREEMPT FILTERING & TSP/SCP DATA MENU (MM-4-2)

PREEMPT FILTER SETTINGS

TS2: Ensure the controller unit is programmed as per the image. This program ensures all PE inputs are used in accordance with Ministry standards:

• PE inputs 1 & 2 are rail only and call PE sequences 1 & 2. They will not accept a 6.25Hz pulse to call a low-priority PE input.

• PE inputs 3-6 call emergency PE sequences 3-6 with a steady call and low-priority PE sequences with a 6.25Hz pulsing call.

TS1: This program ensures all PE inputs are used in accordance with Ministry standards:

• PE inputs 3 & 6 are rail only and call PE sequences 3 & 6. They will not accept a 6.25Hz pulse to call a low-priority PE input.

• PE inputs 1, 2, 4 & 5 call emergency PE sequences 1, 2, 4 & 5 with a steady call and low-priority PE sequences 7, 8, 9 & 10 with a 6.25Hz pulsing call.

Page 102: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-102

Enable Preempt Filtering & TSP/SCP Data Screen (MM-4-2)

SELECTION: After entering the data above return to the Coordinator Sub-Menu by pressing the Sub key or by entering MM-4.

SELECTION: Enter ‘3’ to access the TSP/SCP Plan Data Screen.

Page 103: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-103

TSP/SCP PLAN DATA MENU (MM-4-3)

TSP/SCP PLAN SETTING Program as per Transit Signal Priority plans on STS. Leave values as-is if no TSP plan is specified and low-priority PE inputs 7-10 are not used.

Page 104: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-104

TSP/SCP Plan Data Screen (MM-4-3)

SELECTION: After entering the data above return to the Coordinator Sub-Menu by pressing the Sub key or by entering MM-4.

SELECTION: Enter ‘4’ to access the TSP/SCP Split Pattern Data Screen.

Page 105: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-105

TSP/SCP SPLIT PATTERN DATA MENU (MM-4-4)

TSP/SCP SPLIT PATTERN Program as per Transit Signal Priority plans on STS. Leave values as-is if no TSP plan is specified and low-priority PE inputs 7-10 are not used.

Page 106: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-106

TSP/SCP Split Pattern Data Screen (MM-4-4)

SELECTION: After entering the data above return to Main Menu.

Page 107: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE PREEMPTOR/TSP DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 8-107

THIS PAGE IS LEFT INTENTIONALLY BLANK

Page 108: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-108

TIME BASE DATA PROGRAMMING

SELECTION: Enter ‘5’ to access Time Base Sub-Menus

SELECTION: Enter ‘1’ to access the Clock/Calendar Data Screen

Page 109: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-109

CLOCK/CALENDAR DATA MENU (MM-5-1)

DATE & TIME Ensure the current date and time is correct.

ENA ACTION PLAN Enter 0 to allow automatic selection of Action Plans by Day Plan.

SYNC REF TIME Enter 00:00.

SYC REF. Enter REF TIME.

TIME FROM GMT Enter -08.

DAY LIGHT SAVE Enter USDLS.

TIME RESET INPUT SET TIME Enter 03:30:00.

Page 110: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-110

Clock/Calendar Data Screen (MM-5-1)

SELECTION: After entering the data above return to the Time Base Sub-Menu by pressing the Sub key or by entering MM-5.

SELECTION: Enter ‘2’ to access the Action Plan Data Screen.

Page 111: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-111

ACTION PLAN DATA MENU (MM-5-2)

ACTION PLAN #

Enter the Action Plan number being programmed. This number is referenced in the Day Plan/Event screen (MM-5-3) when entering Time of Day settings from the STS. Typically one Action Plan will be needed for each unique entry in the STS Time of Day section.

PATTERN

Enter the Coordination Pattern (MM-3-2) to be run in this Action Plan. If coordination is not required you should enter 0 which will set the pattern to AUTO. In AUTO the controller unit will run all the other Action Plan settings indicated but without coordination. Pattern numbers 254 and 255 are reserved for Free and Automatic Flash operation respectively.

SYS OVERRIDE Enter NO.

TIMING PLAN Enter the Timing Plan number (MM-1) to be used in this Action Plan. As per the STS Time of Day section.

SEQUENCE

Enter the Controller Phase Sequence (MM-1-1-1) to be used in this Action Plan. Typically this is Sequence 1 unless a sequence change is asked for in the STS Time of Day section.

VEH DETECTOR PLAN Enter the Detector Plan (MM-6-2) to be used in this Action Plan. Typically this is Detector Plan 1 unless a detection change is asked for in the STS Time of Day section.

DET LOG Enter 15.

FLASH Leave blank.

RED REST Enter NO.

VEH DET DIAG PLN Enter 0 for default plan. Vehicle Detector Diagnostics Plans (MM-6-5) are not typically used. If one has been setup, enter its number here for use in the Action Plan.

PED DET DIAG PLN Enter 0 for default plan. Ped Detector Diagnostics Plans (MM-6-6) are not typically used. If one has been setup, enter its number here for use in the Action Plan.

DIMMING ENABLE Enter NO.

PRIORITY RETURN Enter NO.

PED PR RETURN Enter NO.

QUEUE DELAY Enter NO.

PMT COND DELAY Enter NO.

PED RCL Leave blank unless Pedestrian Recall has been requested in the STS Time of Day section.

WALK 2 Check all phases that will use their alternate walk time. Placing an X under a phase here will select the WALK 2 time

Page 112: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-112

in the indicated Timing Plan rather than the default WALK time.

Action Plan Data Screen 1 (MM-5-2)

Page 113: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-113

ACTION PLAN DATA MENU CONTINUED… (MM-5-2)

VEX 2

Check all phases that will use their alternate extension time. Placing an X under a phase here will select the VH EXT2 time in the indicated Timing Plan rather than the default VEH EXT time.

VEH RCL Enter an X beneath the phases which have MIN indicated in the RECALL row of the STS.

MAX RCL Check all phases that will be set to max recall.

MAX 2 Check all phases that will use their Max 2 time. Placing an X under a phase here will select the MAX2 time in the indicated Timing Plan rather than the default MAX1 time.

MAX 3 Check all phases that will use their Max 3 time. Placing an X under a phase here will select the MAX3 time in the indicated Timing Plan rather than the default MAX1 time.

CS INH Leave blank.

OMIT Check all phases that will be omitted in this Action Plan.

SPC FCT Typically left blank. If a Special Functions output is to be activated during this Action Plan place an X under the output to be active.

AUX FCT Typically left blank. If an Auxiliary Function output is to be activated during this Action Plan place an X under the output to be active.

LOGIC PROCESSOR ENABLE

Enter an E to enable specific logic programming statements for this Action Plan not already enabled in MM-1-8-1. Enter a D to disable specific logic programming statements for this Action Plan not already disabled in MM-1-8-1. Leave as a ‘.’ if Logic Processor statement control is enabled/disabled by MM-1-8-1. Note that LP statement control at the Action Plan level will not override LP statement control in MM-1-8-1.

Page 114: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-114

Action Plan Data Screen 2 (MM-5-2)

SELECTION: After entering the data above return to the Time Base Sub-Menu by pressing the Sub key or by entering MM-5.

SELECTION: Enter ‘3’ to access the Day Plan/Event Data Screen.

Page 115: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-115

DAY PLAN/EVENT DATA MENU (MM-5-3)

DAY PLAN Enter the Day Plan number. The days this Day Plan number is associated with are determined in the Schedule Number (MM-5-4).

ACTION PLAN

Enter the Action Plan numbers (MM-5-2) to be active in this Day Plan. Note that Day Plan Action Plans expire at midnight (00:00) which is the beginning of a new day. If you wish to have an Action Plan span midnight you will need to add it as the last Action Plan of the day and the first Action Plan of the day at 00:00.

START TIME Enter the Start Time for each Action Plan in this Day Plan. Entered in 24hr format.

Page 116: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-116

Day Plan/Event Data Screen (MM-5-3)

SELECTION: After entering the data above return to the Time Base Sub-Menu by pressing the Sub key or by entering MM-5.

SELECTION: Enter ‘4’ to access the Schedule Number Data Screen.

Page 117: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-117

SCHEDULE NUMBER DATA MENU (MM-5-4)

SCHEDULE NUMBER

Enter the Schedule Number. You will typically need a Schedule Number for every unique Day of Week entry in the STS Time Clock Settings section. E.g. Schedule Number 1 for MON-FRI and Schedule Number 2 for SAT-SUN.

DAY PLAN NUMBER

Enter the Day Plan Number (MM-5-3) to be linked to this schedule. This is the Day Plan that will be executed on the days indicated in this schedule.

CLEAR ALL FIELDS Use this function to clear all selections on this screen.

SELECT ALL MONTHS Use this function to select all the months.

SELECT ALL DAYS OF WEEK Use this function to select all the days of the week. SELECT ALL DAYS OF

MONTH Use this function to select all days of the month.

MONTH Select the months that have days when this Schedule program will apply.

DAY (DOW) Select the days of the week when this Schedule program will apply for the selected months.

DAY (DOM) Select the days of the month when this Schedule program will apply for the selected months.

Page 118: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-118

Schedule Number Data Screen (MM-5-4)

SELECTION: After entering the data above return to the Time Base Sub-Menu by pressing the Sub key or by entering MM-5.

SELECTION: Enter ‘5’ to access the Exception Days Data Screen.

Page 119: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-119

EXCEPTION DAYS DATA MENU (MM-5-5)

FLOAT/FIXED Indicate if the date is floating or fixed. A fixed day is like New Year’s Day (Jan 1st) and a floating day is like Thanksgiving (2nd Monday of October).

MON/MON Select the month the exception day occurs in (1-12). A zero disables the exception day.

DOW/DOM Select the Day of Week the exception day occurs on. 1-7 if floating, 1-31 if fixed and a zero disables the exception day.

WOM/YEAR Select the Week of Month (1-5) if floating or Year (1970-2105) if fixed. A zero repeats the exception day each year.

DAY PLAN Enter the Day Plan (MM-5-3) that the exception day applies to.

Page 120: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-120

Exception Days Data Screen (MM-5-5)

SELECTION: After entering the data above return to the Main Menu.

Page 121: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE TIME BASE DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 9-121

THIS PAGE IS LEFT INTENTIONALLY BLANK

Page 122: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-122

DETECTOR DATA PROGRAMMING

SELECTION: Enter ‘5’ to access Time Base Sub-Menus

SELECTION: Enter ‘1’ to access the Vehicle Detector Phase Assignment Data Screen

Page 123: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-123

VEHICLE DETECTOR PHASE ASSIGNMENT DATA MENU (MM-6-1)

VEHICLE DETECTOR PLAN NUMBER

Enter the Vehicle Detector Plan number. Detector Plans are applied in Action Plans (MM-5-2).

PH COLUMN

The primary phase the detector input (as indicated in read-only detector column) will call and extend. This information is provided on the Traffic Controller Loop Assignment Sheet (LAS) created during design for the traffic signal.

ADDITIONAL PHASE CALLS COLUMNS Additional phases the detector will call and extend.

TYPE The type of detector input. This should be STANDARD. NOTE: Although data entry in this screen is possible it is not recommended. This screen is best used as a summary to ensure all detector inputs (DET) are assigned to the correct phase numbers (PH) as per the Traffic Controller’s Loop Assignment Sheet. It is recommended to use the Vehicle Detector Setup screen (MM-6-2) instead as this screen allows more detailed programming of each controller unit detector input.

Page 124: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-124

Vehicle Detector Phase Assignment Data Screen (MM-6-1)

SELECTION: After entering the data above return to the Detector Sub-Menu by pressing the Sub key or by entering MM-6.

SELECTION: Enter ‘2’ to access the Vehicle Detector Setup Data Screen.

Page 125: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-125

VEHICLE DETECTOR SETUP DATA MENU (MM-6-2)

VEHICLE DETECTOR Enter the Vehicle Detector number. This directly corresponds to the controller unit’s input as shown on the Traffic Controller’s Loop Assignment Sheet (LAS)

VEHICLE DETECTOR PLAN Enter the Vehicle Detector Plan number this vehicle detector is assigned to. Detector Plans are applied in Action Plans (MM-5-2).

TYPE Enter STANDARD.

TS2 DETECTOR Enter X if the Controller Unit is to be installed in a TS2 controller assembly.

ECPI LOG Enter YES if the Loop Assignment Sheet shows that counting should be on for this detector input.

PHASE Enter the primary phase number that this detector is to call and extend as per the Loop Assignment Sheet.

ADDITIONAL PHASES Enter any additional phases the detector will call and extend.

EXTEND TIME Enter the Extend (Stretch) time for this detector input as shown on the Loop Assignment Sheet.

DELAY TIME Enter the Delay time for this detector input as shown on the Loop Assignment Sheet.

USE ADDED INITIAL Leave unchecked.

CROSS SWITCH PHASE

Enter any cross switch phases for this detector. Enter another phase that this detector input will call and extend when the primary phase is not green and the cross switch phase is green.

LOCK IN Typically NONE. Allows the detector state to be locked-in when the primary call/extend phase is Yellow or Red.

NTCIP VOL/OCC Not used. Leave unchecked.

PMT QUEUE DELAY Enter NO.

Page 126: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-126

Vehicle Detector Setup Data Screen (MM-6-2)

SELECTION: After entering the data above return to the Detector Sub-Menu by pressing the Sub key or by entering MM-6.

SELECTION: Enter ‘3’ to access the Ped Detector Input Assignment Data Screen.

Page 127: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-127

PED DETECTOR PHASE ASSIGNMENT DATA MENU (MM-6-3)

MODE Enter NTCIP.

DETECTOR

Enter as shown for standard phase 2, 4, 6 & 8 ped movements. The Ministry standard TS2 assembly only uses ped detectors 2, 4, 6 & 8. If the STS calls for an odd-phase pedestrian movement you will have to map one of the four ped detectors to this odd-phase.

Page 128: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-128

Ped Detector Phase Assignment Data Screen (MM-6-3)

SELECTION: After entering the data above return to the Detector Sub-Menu by pressing the Sub key or by entering MM-6.

SELECTION: Enter ‘4’ to access the Log Interval/Speed Detector Setup Data Screen.

Page 129: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-129

LOG INTERVAL/SPEED DETECTOR SETUP DATA MENU (MM-6-4)

NTCIP LOG Enter 0. Not used.

ECPI LOG Enter TBAP. This allows the Time Base Action Plan (MM-5-2) to determine the log interval.

SPEED DETECTOR SETTINGS Leave as shown in image. Not used.

Page 130: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-130

Log Interval/Speed Detector Setup Data Screen (MM-6-4)

SELECTION: After entering the data above return to the Detector Sub-Menu by pressing the Sub key or by entering MM-6.

SELECTION: Enter ‘5’ to access the Vehicle Detector Diagnostics Data Screen.

Page 131: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-131

VEHICLE DETECTOR DIAGNOSTICS DATA MENU (MM-6-5)

DIAGNOSTIC PLAN NUMBER The Diagnostic Plan number. This number is referenced in the Time Base Action Plan (MM-5-2). Detector diagnostics are not used by the Ministry.

COUNT The number of detections per minute required before the controller unit assumes the detector is failed. Enter 0 to disable this diagnostic.

ACT The number of minutes of no detection before the controller unit assumes the detector is failed. Enter 0 to disable this diagnostic.

PRES The number of minutes of continuous detection before the controller unit assumes the detector is failed. Enter 0 to disable this diagnostic.

X’S Toggle to select a multiplier for the ACT and PRES entries.

TIME The amount of time in seconds the failed detector is allowed to call/extend its phase. Enter 0 to disable and 255 to place max recall on the phase.

CL DELAY The amount of time in seconds the failed detector is not allowed to call its phase after its green has terminated. Enter 0 to disable.

Page 132: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-132

Vehicle Detector Diagnostics Data Screen (MM-6-5)

SELECTION: After entering the data above return to the Detector Sub-Menu by pressing the Sub key or by entering MM-6.

SELECTION: Enter ‘6’ to access the Pedestrian Detector Diagnostics Data Screen.

Page 133: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-133

PEDESTRIAN DETECTOR DIAGNOSTICS DATA MENU (MM-6-6)

DIAGNOSTIC PLAN NUMBER The Diagnostic Plan number. This number is referenced in the Time Base Action Plan (MM-5-2). Detector diagnostics are not used by the Ministry.

COUNT The number of detections per minute required before the controller unit assumes the detector is failed. Enter 0 to disable this diagnostic.

ACT The number of minutes of no detection before the controller unit assumes the detector is failed. Enter 0 to disable this diagnostic.

PRES The number of minutes of continuous detection before the controller unit assumes the detector is failed. Enter 0 to disable this diagnostic.

MULTIPLIER Toggle to select a multiplier for the ACT and PRES entries.

Page 134: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE DETECTOR DATA

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 10-134

Pedestrian Detector Diagnostics Data Screen (MM-6-6)

SELECTION: After entering the data above return to the Main Menu.

Page 135: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-135

PROGRAMMING EXAMPLE: PEDESTRIAN ACTIVATED SIGNAL

SIGNAL DESCRIPTION This is an example of a pedestrian actuated traffic signal controlled by a TS2-P6 cabinet. A summary of this intersection configuration and operational requirements:

• A single phase on the highway for movements A1 & A2 which will always be on at this same time.

• A single pedestrian only phases for the pedestrian crossing.

Note that for this example there is no Loop Assignment Sheet (LAS) as there is for the other examples. This is because no vehicle detection is required at a pedestrian actuated signal.

Only data entries that require analysis and entry by the user are described. If details are not provided it is assumed the default value is used as indicated in the general programming section.

SIGNAL DISPLAY DIAGRAM The signal display diagram is typically found on the Traffic Engineering (TE) electrical plans for each traffic signal. It is an important tool for quickly understanding: signal sequence, concurrent phases, phase and pedestrian output compatibilities and preemption sequences. The figure below is the signal display diagram for this example program.

Signal Display Diagram for Example Pedestrian Actuated Signal

Page 136: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-136

SIGNAL TIMING SHEET (STS) Below is the signal timing sheet to be used as a reference for this example program.

Page 137: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-137

PHASE RING SEQUENCE AND ASSIGNMENT (MM-1-1-1)

BARRIER CONTROL Enter B for Barrier Control.

CONTROLLER SEQUENCE #1 Enter phases 1-8 in sequence in Ring 1 with no barrier. This creates an 8-phase sequential controller although only two phases will be used.

BACKUP PREVENT PHASES (MM-1-1-3)

BACKUP PREVENT MATRIX Leave empty. There is no possibility of a left-turn trap in a two phase sequential controller. No backup prevent required.

Page 138: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-138

Page 139: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-139

SIMULTANEOUS GAP PHASES (MM-1-1-4)

SIMULTANEOUS GAP PHASES Leave matrix empty.

PHASE IN USE/PED (MM-1-2)

PHASES IN USE Enable phases 2 and 4 for use. Phase 2 will be the vehicle phase. Phase 4 will be the pedestrian crossing phase.

EXCLUSIVE PED

Enable phase 4 as an exclusive ped. Enabling phase 4 as an exclusive ped makes it a ped only phase. There will be no associated vehicle phase running concurrently when this is set.

Page 140: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-140

Page 141: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-141

LOAD SWITCH ASSIGN (MM-1-3)

LOAD SWITCH TO PHASE/OVERLAP MAPPING

Assign Overlap 1 to load switch 2. Assign Phase 4 Pedestrian to load switch 10. No other load switches need be installed for this signal.

SDLC OPTIONS (MM-1-4-1)

DETECTOR RACK Leave unchecked. No vehicle detectors are required for this signal, therefore no detector racks either.

Page 142: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-142

Page 143: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-143

MMU PROGRAM (MM-1-4-2)

MMU COMPATIBILITY MATRIX

Leave all unchecked. No phases are allowed to be on together.

LOGIC STATEMENT CONTROL (MM-1-8-1)

LOGIC PROCESSOR STATEMENT #1 CONTROL

Enable statement #1. This logic statement is required to be enabled at all times.

Page 144: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-144

Page 145: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-145

LOGIC STATEMENTS (MM-1-8-2)

LOGIC PROCESSOR STATEMENT #1

Use logic statement shown in image. This statement explained: IF the flashing phase 2 green signal is off AND IF The lagging overlap A green is still on THEN Force the overlap A green output on steady rather than flashing as it is programmed to do.

Page 146: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-146

Page 147: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-147

TIMING PLANS (MM-2-1)

TIMING PLAN #1

Enter timing values from STS for Phases 2 & 4. Phase 2 MIN GRN determines the minimum ped re-service time. Phase 4 WALK and PED CLR determines the pedestrian crossing times.

Page 148: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-148

Page 149: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-149

VEHICLE OVERLAPS (MM-2-2)

VEHICLE OVERLAP A

Enter X for INCLUDED under Phase 2. This will ensure Overlap A is only on when Vehicle Phase 2 is on. Enter 1 for FLSH GRN under Phase 2. This will make the overlap (field display) green flash at 60fpm. Enter X for LAG X PH under Phase 2. This will ensure Overlap A green will stay (lag) on for a time after Vehicle Phase 2 green has terminated. Enter 5.0 for LAG GRN. This is the time that the vehicle signal display green will be on solid after a pedestrian call. Enter 3.0 for YEL. This is the yellow time for the vehicle signal display. It must match the STS yellow time for Phase 2. Enter 2.0 for RED. This is the red time for the vehicle signal display. It must match the STS red time for Phase 2.

VEH/PED OVERLAPS (MM-2-3)

OVERLAP MATRIX Do not enter anything. This is a summary screen and should show the link between Overlap A and Phase 2.

Page 150: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-150

Page 151: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-151

START/FLASH (MM-2-5)

START UP SETTINGS

Enter Y under Phase 2. Signal will exit flash into 3-colour when the vehicle signal display cycles to yellow. It will then proceed to red and service the ped crossing before resting on the phase 2. Enter X under Overlap A. We want overlap A to behave coming out of flash as it would during normal 3-colour operation.

CONTROLLER OPTIONS (MM-2-6-1)

CONTROLLER OPTIONS Do not enter anything. There are no phases requiring Dual Entry to be enabled.

Page 152: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-152

Page 153: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-153

PHASE RECALL (MM-2-8)

VE RECALL

Enter X under Phase 2. This ensures the signal will return to the highway traffic phase after the pedestrian phase is served.

Page 154: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-154

Page 155: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-155

CLOCK/CALENDAR DATA (MM-5-1)

CLOCK/CALENDAR SETTINGS

Ensure the correct date and time is entered.

ACTION PLAN (MM-5-2)

ACTION PLAN Do not enter any Action Plans. No action plans are required as this signal will run a single timing plan 24/7 as per the STS.

Page 156: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-156

Page 157: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-157

DAY PLAN/EVENT (MM-5-3)

DAY PLAN SETTINGS

Do not enter any Day Plans. No day plans or action plans are required as this signal will run a single timing plan 24/7 as per the STS.

SCHEDULE NUMBER (MM-5-4)

SCHEDULE SETTINGS

Do not enter Schedules. No schedules, day plans or action plans are required as this signal will run a single timing plan 24/7 as per the STS.

Page 158: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-158

Page 159: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-159

VEH DET PHASE ASSIGNMENT (MM-6-1)

DETECTOR SETTINGS

Do not enter any Detectors. There are no vehicle detectors at this signal and the detector racks were disabled under MM-1-4-1.

Page 160: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE – PED ACTIVATED SIGNAL

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 11-160

Page 161: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-161

PROGRAMMING EXAMPLE: GEOMETRICALLY CONFLICTING PROTECTED LEFT TURNS ON THE

HIGHWAY

SIGNAL DESCRIPTION This program is currently controlling the traffic signal at Highway 7 and Meadowtown Way in Pitt Meadows. The signal is controlled by a TS2-P6 cabinet.

A summary of this intersection configuration and operational requirements:

• Protected left turns on the highway (Ax/Ay) which may not be on at the same time due to intersection geometry.

• Ay is a typical leading left turn while Ax lags its adjacent through movement A1. • There is a weekday time clock schedule and a weekend time clock schedule. • This signal is in coordination with other Highway 7 intersections for most of the day. It runs free

in the late evening and early morning. • There is emergency preemption for each intersection approach.

Only data entries that require analysis and entry by the user are described. If details are not provided it is assumed the default value is used as indicated in the general programming section.

SIGNAL DISPLAY DIAGRAM The signal display diagram is typically found on the Traffic Engineering (TE) electrical plans for each traffic signal. It is an important tool for quickly understanding: signal sequence, concurrent phases, phase and pedestrian output compatibilities and preemption sequences.

The following figure is the signal display diagram for this example program.

Page 162: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-162

Signal Display Diagram for Lougheed Hwy at Meadowtown Way, Pitt Meadows

Page 163: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-163

SIGNAL TIMING SHEET (STS) Below is the signal timing sheet to be used as a reference for this example program.

Page 164: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-164

LOOP ASSIGNMENT SHEET (LAS) Below is the loop assignment sheet to be used as a reference for this example program.

Page 165: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-165

PHASE RING SEQUENCE AND ASSIGNMENT (MM-1-1-1)

BARRIER CONTROL Enter C for Compatibility Control.

CONTROLLER SEQUENCE #1

Enter phase sequences for Ring 1 & 2 as shown. This creates a NEMA Dual Ring configuration but there is no barrier shown as we are using compatibility mode to ensure the geometrically conflicting left turns may not be on together. Note that Ring 2 has phases 5 and 6 reversed to create the lagging left turn as required by the STS.

PHASE COMPATIBILITY (MM-1-1-2)

PHASE COMPATIBILITY MATRIX

Enter as shown. This shows the typical NEMA Dual Ring Compatibilities for Phases 1, 2, 5 & 6 with the exception of 1 & 5 as these phases are incompatible due to intersection geometrics.

Page 166: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-166

Page 167: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-167

BACKUP PREVENT PHASES (MM-1-1-3)

BACKUP PREVENT MATRIX Leave empty. There is no possibility of a left-turn trap with protected left turns on the highway and a single cross-street phase.

SIMULTANEOUS GAP PHASES (MM-1-1-4)

SIMULTANEOUS GAP PHASES Enter an X under 2 on row 6. Enter an X under 6 on row 2.

Page 168: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-168

Page 169: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-169

PHASES IN USE (MM-1-2)

IN USE Enter X under Phases 1, 2, 5, 6 and 8. These are the phases shown as ON in the STS.

LOAD SWITCH ASSIGNMENT (MM-1-3)

LOAD SWITCH TO PHASE/OVERLAP MAPPING

Assign Vehicle Phases 1, 2, 5, 6 and 8 to Load Switches 1, 2, 5, 6 and 8 respectively. There is no Advance Warning on the highway so vehicle phases can be used for load switches 2 and 6 rather than overlaps. Assign Pedestrian Outputs for Phases 2, 4, 6 and 8 to Load Switches 9, 10, 11 and 12 respectively as per default configuration.

Page 170: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-170

Page 171: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-171

SDLC OPTIONS (MM-1-4-1)

SDLC PORT 1 CONFIG Ensure configuration is at default settings as shown.

MMU PROGRAM (MM-1-4-2)

MMU COMPATIBILITY MATRIX

Enter compatibilities as shown. Note that these MMU compatibilities are exactly the same as the phase compatibilities in MM-1-1-2 with the exception that the pedestrian output compatibilities must be added for the MMU.

Page 172: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-172

Page 173: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-173

TIMING PLANS (MM-2-1)

TIMING PLAN #1 Enter timing values from STS.

Page 174: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-174

Page 175: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-175

START/FLASH (MM-2-5)

START UP

Enter R under Phases 2 & 5. The traffic signal will exit flashing red on phases 2 & 5 and enter 3-colour solid red on phases 2 & 5. The first green display will be phase 8 as indicated on the STS.

CONTROLLER OPTIONS (MM-2-6-1)

CONTROLLER OPTIONS Do not enter anything. There is only a single phase on the cross-street so Dual Entry is not required.

Page 176: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-176

Page 177: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-177

PHASE RECALL (MM-2-8)

VE RECALL Enter X under Phases 2 & 6. This will turn extendible min recall on for phases 2 & 6 as indicated on the STS.

COORDINATOR OPTIONS (MM-3-1)

COORDINATOR OPTIONS Enter default values as shown.

Page 178: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-178

Page 179: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-179

COORDINATOR PATTERNS (MM-3-2)

COORDINATOR PATTERN #1

Enter Split Pattern #1 to be used in the coordinator pattern. Split pattern 1 will be defined later in MM-3-3. Enter the Cycle Length and Offset Value for this pattern. Cycle Length and Offset Value is given on the STS. It is not recommended to enter data below the SPLIT REFERENCE PHASES heading on this screen. All of this information is entered in the split pattern screen in MM-3-3. It will automatically appear here afterwards.

Page 180: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-180

Page 181: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-181

COORDINATOR PATTERNS (MM-3-2)

COORDINATOR PATTERN #2

Enter Split Pattern #2 to be used in the coordinator pattern. Split pattern 2 will be defined later in MM-3-3. Enter the Cycle Length and Offset Value for this pattern. Cycle Length and Offset Value is given on the STS. It is not recommended to enter data below the SPLIT REFERENCE PHASES heading on this screen. All of this information is entered in the split pattern screen in MM-3-3. It will automatically appear here afterwards.

Page 182: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-182

Page 183: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-183

COORDINATOR PATTERNS (MM-3-2)

COORDINATOR PATTERN #3

Enter Split Pattern #3 to be used in the coordinator pattern. Split pattern 3 will be defined later in MM-3-3. Enter the Cycle Length and Offset Value for this pattern. Cycle Length and Offset Value is given on the STS. It is not recommended to enter data below the SPLIT REFERENCE PHASES heading on this screen. All of this information is entered in the split pattern screen in MM-3-3. It will automatically appear here afterwards.

Page 184: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-184

Page 185: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-185

COORDINATOR PATTERNS (MM-3-2)

COORDINATOR PATTERN #4

Enter Split Pattern #4 to be used in the coordinator pattern. Split pattern 4 will be defined later in MM-3-3. Enter the Cycle Length and Offset Value for this pattern. Cycle Length and Offset Value is given on the STS. It is not recommended to enter data below the SPLIT REFERENCE PHASES heading on this screen. All of this information is entered in the split pattern screen in MM-3-3. It will automatically appear here afterwards.

Page 186: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-186

Page 187: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-187

SPLIT PATTERNS (MM-3-3)

SPLIT PATTERN #1

Enter the splits for Coordinator Pattern #1. Splits are noted on the STS. Enter an X under Phases 2 & 6 for COORD. This makes 2 & 6 the coordinated phases as per the STS. After entry all this information will appear at the bottom of the coordinator pattern #1 screen (MM-3-2) as split pattern 1 was linked to coordinator pattern 1 on that screen.

SPLIT PATTERN #2

Enter the splits for Coordinator Pattern #2. Splits are noted on the STS. Enter an X under Phases 2 & 6 for COORD. This makes 2 & 6 the coordinated phases as per the STS. After entry all this information will appear at the bottom of the coordinator pattern #2 screen (MM-3-2) as split pattern 2 was linked to coordinator pattern 2 on that screen.

Page 188: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-188

Page 189: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-189

SPLIT PATTERNS (MM-3-3)

SPLIT PATTERN #3

Enter the splits for Coordinator Pattern #3. Splits are noted on the STS. Enter an X under Phases 2 & 6 for COORD. This makes 2 & 6 the coordinated phases as per the STS. After entry all this information will appear at the bottom of the coordinator pattern #3 screen (MM-3-2) as split pattern 3 was linked to coordinator pattern 3 on that screen.

SPLIT PATTERN #4

Enter the splits for Coordinator Pattern #4. Splits are noted on the STS. Enter an X under Phases 2 & 6 for COORD. This makes 2 & 6 the coordinated phases as per the STS. After entry all this information will appear at the bottom of the coordinator pattern #4 screen (MM-3-2) as split pattern 4 was linked to coordinator pattern 4 on that screen.

Page 190: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-190

Page 191: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-191

PREEMPT PLAN 1-10 (MM-4-1)

EMERGENCY PREEMPT PLAN #3

ENABLE Enter YES.

DWEL VEH Enter an X under phases 2 & 5. Phases called by each preemption input are noted under the phase description on the STS.

EXIT PH Enter an X under phases 2 & 5.

TERM PH

Enter NO. There is no possible left turn trap with this intersection configuration so an all-red at beginning of sequence is not required.

ENTRANCE TIMING

Enter 0s for walk. Enter 255s for ped clearance. Enter 4s for min green. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

DWL/CYC-EXIT

Enter 180s for max dwell time. This ensures that the controller will ignore a preemption input if it exceeds 180s in duration. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

Important: Using the maximum allowable yellow and red time here is important. The Cobalt will use the entrance phase’s Timing Plan (MM-2-1) yellow and red time or the ones programmed here – whichever is less. If you were to enter the max yellow and red time of any phase on the STS is would be correct but may cause error in the future. E.g. If a newer STS increased the maximum phase yellow and red times you would update it in the Timing Plan but could forget to change it here. The result would be inadequate yellow and red times when entering or exiting the preemption sequence.

Page 192: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-192

Page 193: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-193

PREEMPT PLAN 1-10 (MM-4-1)

EMERGENCY PREEMPT PLAN #4

ENABLE Enter YES.

DWEL VEH Enter an X under phases 1 & 6. Phases called by each preemption input are noted under the phase description on the STS.

EXIT PH Enter an X under phases 1 & 6.

TERM PH

Enter NO. There is no possible left turn trap with this intersection configuration so an all-red at beginning of sequence is not required.

ENTRANCE TIMING

Enter 0s for walk. Enter 255s for ped clearance. Enter 4s for min green. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

DWL/CYC-EXIT

Enter 180s for max dwell time. This ensures that the controller will ignore a preemption input if it exceeds 180s in duration. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

Important: Using the maximum allowable yellow and red time here is important. The Cobalt will use the entrance phase’s Timing Plan (MM-2-1) yellow and red time or the ones programmed here – whichever is less. If you were to enter the max yellow and red time of any phase on the STS is would be correct but may cause error in the future. E.g. If a newer STS increased the maximum phase yellow and red times you would update it in the Timing Plan but could forget to change it here. The result would be inadequate yellow and red times when entering or exiting the preemption sequence.

Page 194: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-194

Page 195: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-195

PREEMPT PLAN 1-10 (MM-4-1)

EMERGENCY PREEMPT PLAN #6

ENABLE Enter YES.

DWEL VEH Enter an X under phase 8. Phases called by each preemption input are noted under the phase description on the STS.

EXIT PH Enter an X under phase 8.

TERM PH

Enter NO. There is no possible left turn trap with this intersection configuration so an all-red at beginning of sequence is not required.

ENTRANCE TIMING

Enter 0s for walk. Enter 255s for ped clearance. Enter 4s for min green. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

DWL/CYC-EXIT

Enter 180s for max dwell time. This ensures that the controller will ignore a preemption input if it exceeds 180s in duration. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

Important: Using the maximum allowable yellow and red time here is important. The Cobalt will use the entrance phase’s Timing Plan (MM-2-1) yellow and red time or the ones programmed here – whichever is less. If you were to enter the max yellow and red time of any phase on the STS is would be correct but may cause error in the future. E.g. If a newer STS increased the maximum phase yellow and red times you would update it in the Timing Plan but could forget to change it here. The result would be inadequate yellow and red times when entering or exiting the preemption sequence.

Page 196: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-196

Page 197: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-197

CLOCK/CALENDAR DATA (MM-5-1)

CLOCK/CALENDAR SETTINGS

Ensure the correct date and time is entered.

Page 198: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-198

Page 199: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-199

ACTION PLAN (MM-5-2)

ACTION PLAN #1

Enter 254 for the pattern number. This defaults to free operation. When this action plan is called the controller will run using the default timing plan 1.

Page 200: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-200

Page 201: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-201

ACTION PLAN (MM-5-2)

ACTION PLAN #2

Enter 1 for the pattern number. When this action plan is called it will implement coordination using coordinator pattern 1.

Page 202: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-202

Page 203: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-203

ACTION PLAN (MM-5-2)

ACTION PLAN #3

Enter 2 for the pattern number. When this action plan is called it will implement coordination using coordinator pattern 2.

Page 204: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-204

Page 205: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-205

ACTION PLAN (MM-5-2)

ACTION PLAN #4

Enter 3 for the pattern number. When this action plan is called it will implement coordination using coordinator pattern 3.

Page 206: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-206

Page 207: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-207

ACTION PLAN (MM-5-2)

ACTION PLAN #5

Enter 254 for the pattern number. This defaults to free operation. When this action plan is called the controller will run using the default timing plan 1.

Note: Action Plan #5 is identical to Action Plan #1 on the STS. For this reason you could choose to not create this Action Plan and use Action Plan #1 in its place in the Day Plan schedule(s).

Page 208: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-208

Page 209: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-209

ACTION PLAN (MM-5-2)

ACTION PLAN #6

Enter 254 for the pattern number. This defaults to free operation. When this action plan is called the controller will run using the default timing plan 1. Enter X under Phases 1, 2, 5, 6 & 8 for MAX 2. When this action plan is called it will use the Max 2 times in timing plan 1 rather than Max 1.

Page 210: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-210

Page 211: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-211

ACTION PLAN (MM-5-2)

ACTION PLAN #7

Enter 4 for the pattern number. When this action plan is called it will implement coordination using coordinator pattern 4.

Page 212: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-212

Page 213: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-213

ACTION PLAN (MM-5-2)

ACTION PLAN #8

Enter 254 for the pattern number. This defaults to free operation. When this action plan is called the controller will run using the default timing plan 1. Enter X under Phases 1, 2, 5, 6 & 8 for MAX 2. When this action plan is called it will use the Max 2 times in timing plan 1 rather than Max 1.

Note: Action Plan #8 is identical to Action Plan #6 on the STS. For this reason you could choose to not create this Action Plan and use Action Plan #6 in its place in the Day Plan schedule(s).

Page 214: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-214

Page 215: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-215

DAY PLAN/EVENT (MM-5-3)

DAY PLAN #1

Enter the action plan schedule for weekdays. This corresponds to the weekday time clock settings on the STS.

DAY PLAN #2

Enter the action plan schedule for weekends. This corresponds to the weekend time clock settings on the STS.

Page 216: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-216

Page 217: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-217

SCHEDULE NUMBER (MM-5-4)

SCHEDULE #1

Enter an X under each weekday in the DOW row. This will ensure the linked day plan is used only on weekdays. Enter a 1 for Day Plan No. This will link day plan 1 to this weekday schedule.

SCHEDULE #2

Enter an X under each weekend day in the DOW row. This will ensure the linked day plan is used only on weekends. Enter a 2 for Day Plan No. This will link day plan 2 to this weekend schedule.

Page 218: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-218

Page 219: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-219

VEHICLE DETECTOR SETUP (MM-6-2)

NOTE: All detector inputs given on the Loop Assignment Sheet must be programmed. The three detectors shown here are examples on how these detectors are programmed.

VEHICLE DETECTOR #1

Enter 8 under PH. Detector calls/extends phase 8. Enter NO for ECPI LOG. Detector is not used for volume counts. Enter 3.0 beside DELAY TIME. Detector has a 3s delay.

VEHICLE DETECTOR #2

Enter 8 under PH. Detector calls/extends phase 8. Enter YES for ECPI LOG. Detector is used for volume counts.

VEHICLE DETECTOR #17

Enter 0 under PH. This is a free right turn loop and does not call any phases. Enter YES for ECPI LOG. This detector is used for volume counts.

Page 220: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-220

Page 221: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-221

VEHICLE DETECTOR PHASE ASSIGNMENT (MM-6-1)

VEHICLE DETECTOR ASSIGNMENT SUMMARY

As previously discussed it is not recommended to program detectors here as all the details are not present on this screen. However it is recommended that after programming all detectors you then compare the LAS with this screen as a quality control check.

Page 222: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –CONFLICTING LEFT TURNS ON THE HIGHWAY

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 12-222

Page 223: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-223

PROGRAMMING EXAMPLE: EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

SIGNAL DESCRIPTION This program is currently controlling the traffic signal at Highway 7 and Nelson Street in Mission. The signal is controlled by a TS2-P6 cabinet.

A summary of this intersection configuration and operational requirements:

• Protected/permissive left turns on the highway. • Advance warning on the highway. • Two different timing plans called by time of day. • There is rail preemption with a 6-wire interconnect. • There is emergency preemption for each intersection approach. • There are protected/permissive left turns on the cross-street that are only active during the rail

preemption sequence.

Only data entries that require analysis and entry by the user are described. If details are not provided it is assumed the default value is used as indicated in the general programming section.

SIGNAL DISPLAY DIAGRAM The signal display diagram is typically found on the Traffic Engineering (TE) electrical plans for each traffic signal. It is an important tool for quickly understanding: signal sequence, concurrent phases, phase and pedestrian output compatibilities and preemption sequences.

The following figure is the signal display diagram for this example program.

Page 224: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-224

Signal Display Diagram for Highway 7 at Nelson Street, Mission

Page 225: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-225

SIGNAL TIMING SHEET (STS) Below is the signal timing sheet to be used as a reference for this example program.

Page 226: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-226

LOOP ASSIGNMENT SHEET (LAS) Below is the loop assignment sheet to be used as a reference for this example program.

Page 227: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-227

PHASE RING SEQUENCE AND ASSIGNMENT (MM-1-1-1)

BARRIER CONTROL Enter B for Barrier Control.

CONTROLLER SEQUENCE #1 Enter phase sequences for Ring 1 & 2 as shown. This is a standard NEMA Dual Ring configuration.

PHASE COMPATIBILITY (MM-1-1-3)

BACKUP PREVENT PHASES

Enter B as shown. Phases 1 & 5 are protected/permissive left turns. These entries will ensure an all-red time is implemented when phases 2 or 6 backup in their ring to re-service phases 1 or 5 respectively.

Page 228: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-228

Page 229: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-229

SIMULTANEOUS GAP PHASES (MM-1-1-4)

SIMULTANEOUS GAP PHASES Enter 2 & 6 and 6 & 2 as shown.

PHASE IN USE/PED (MM-1-2)

PHASES IN USE Enable phases 1 to 8 for use.

Page 230: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-230

Page 231: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-231

LOAD SWITCH ASSIGN (MM-1-3)

LOAD SWITCH TO PHASE/OVERLAP MAPPING

Enter as shown. Load switch 2 and load switch 6 are assigned delayed (lagging) overlaps 1 & 2 as advance warning is required for phases 2 & 6 as per the STS.

SDLC OPTIONS (MM-1-4-1)

SDLC PORT 1 CONFIG Ensure configuration is at default settings as shown.

Page 232: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-232

Page 233: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-233

MMU PROGRAM (MM-1-4-2)

MMU COMPATIBILITY MATRIX

Enter compatibilities as shown. Compatibilities between vehicle and pedestrian field outputs must be entered.

LOGIC STATEMENT CONTROL (MM-1-8-1)

LOGIC PROCESSOR STATEMENT #1

Enable logic processor statements as shown. LP statements 1 to 6 are enabled for use in this program.

Page 234: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-234

Page 235: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-235

LOGIC STATEMENTS (MM-1-8-2)

LOGIC PROCESSOR STATEMENT #1

Use logic statement shown in image. This statement explained: IF rail preempt input 2 is on OR IF Rail preempt input 1 is on THEN Allow rail-only phases 3 & 7 to be serviced ELSE Do not allow rail-only phases 3 & 7 to be serviced.

LOGIC PROCESSOR STATEMENT #2

Use logic statement shown in image. This statement explained: IF rail preempt input 1 is on AND IF The rail flash is off OR IF Rail preempt input 2 is on THEN Turn on overlap 4 (D) green ELSE Turn off overlap 4 green. Overlap 4 green activates a No Left Turn and a No Right Turn LED sign.

Page 236: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-236

Page 237: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-237

LOGIC STATEMENTS (MM-1-8-2)

LOGIC PROCESSOR STATEMENT #3

Use logic statement shown in image. This statement explained: IF phase 4, 7 or 8 are timing AND IF Detector input 1 is timing its delay THEN Put a call in for phase 1 (don’t wait for delay timer)

LOGIC PROCESSOR STATEMENT #4

Use logic statement shown in image. This statement explained: IF phase 4, 7 or 8 are timing AND IF Detector input 9 is timing its delay THEN Put a call in for phase 1 (don’t wait for delay timer)

Page 238: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-238

Page 239: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-239

LOGIC STATEMENTS (MM-1-8-2)

LOGIC PROCESSOR STATEMENT #5

Use logic statement shown in image. This statement explained: IF phase 4, 7 or 8 are timing AND IF Detector input 5 is timing its delay THEN Put a call in for phase 5 (don’t wait for delay timer)

LOGIC PROCESSOR STATEMENT #6

Use logic statement shown in image. This statement explained: IF phase 4, 7 or 8 are timing AND IF Detector input 13 is timing its delay THEN Put a call in for phase 5 (don’t wait for delay timer)

Page 240: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-240

Page 241: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-241

LOGIC STATEMENTS (MM-1-8-2)

LOGIC PROCESSOR STATEMENT #7

Use logic statement shown in image. This statement explained: IF vehicle phase 2 is on THEN Turn off phase 2 advance warning (phase 2 ped clr) ELSE Turn on phase 2 advance warning.

LOGIC PROCESSOR STATEMENT #8

Use logic statement shown in image. This statement explained: IF vehicle phase 6 is on THEN Turn off phase 6 advance warning (phase 6 ped clr) ELSE Turn on phase 6 advance warning.

Page 242: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-242

Page 243: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-243

TIMING PLANS (MM-2-1)

TIMING PLAN #1 Enter timing values from STS.

Page 244: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-244

Page 245: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-245

TIMING PLANS (MM-2-1)

TIMING PLAN #2 Enter timing values from STS.

Page 246: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-246

Page 247: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-247

VEHICLE OVERLAPS (MM-2-2)

OVERLAP A

Enter timing values from STS. Overlap A is the phase 2 vehicle field display. It lags phase 2 by the LAG GRN time to achieve the Advance Warning function. LAG GRN is programmed to the phase 2 AWF time on the STS. YEL is programmed to the phase 2 Yellow time on the STS. RED is programmed to the phase 2 Red time on the STS.

OVERLAP B

Enter timing values from STS. Overlap B is the phase 6 vehicle field display. It lags phase 6 by the LAG GRN time to achieve the Advance Warning function. LAG GRN is programmed to the phase 6 AWF time on the STS. YEL is programmed to the phase 6 Yellow time on the STS. RED is programmed to the phase 6 Red time on the STS.

Page 248: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-248

Page 249: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-249

START/FLASH (MM-2-5)

START UP

Enter R under Phases 3 & 7. The traffic signal will exit flashing red on phases 3 & 7 and enter 3-colour operation on solid red for phases 3 & 7. The first green display will be phases 4 & 8 as indicated on the STS.

CONTROLLER OPTIONS (MM-2-6-1)

CONTROLLER OPTIONS

Enter an X under phases 4 & 8 for DUAL ENTRY. This way if a call to the cross-street is made for phase 4 only it will also activate phase 8 concurrently. Enter an F2 under phases 1, 3, 5 & 7 for FLASHING GRN PH. This will ensure the green arrows for these protected/permissive left turns flash at the appropriate rate.

Page 250: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-250

Page 251: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-251

PHASE RECALL (MM-2-8)

VE RECALL Enter X under Phases 2 & 6. This will turn extendible min recall on for phases 2 & 6 as indicated on the STS.

Page 252: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-252

Page 253: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-253

PREEMPT PLAN 1-10 (MM-4-1)

Note: this intersection uses a 6-wire rail interconnect where preempt input 1 is activated only if the rail interconnect supervisory circuit faults. As the controller unit must assume the worst with a faulting rail preemption signal this sequence will move to the track clearance phases and will then go into flash until the rail preemption call terminates.

RAIL PREEMPT PLAN #1

ENABLE Enter YES.

ENTRANCE TIMING

Enter 0s for walk and ped clearance. Rail pre-emption truncates all pedestrian movements. Enter 4s for min green. As dictated in programming comment #1 on the STS. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

TERM PH Enter YES. This will force an all-red period as dictated in comment #2 on the STS.

TRKCLR V Enter an F2 under phase 3 and an X under phase 8. This indicates phase 3 and 8 are the track clearance phases.

TRACK CLEAR TIMING

Enter 53s for min green. As dictated in programming comment #3 on the STS. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

Page 254: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-254

Page 255: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-255

PREEMPT PLAN 1-10 (MM-4-1) Note: this intersection uses a 6-wire rail interconnect where preempt input 2 is activated only if a train is approaching and there is no fault with the rail interconnect supervisory circuit. This is the true rail preemption sequence.

RAIL PREEMPT PLAN #2

ENABLE Enter YES.

ENTRANCE TIMING

Enter 0s for walk and ped clearance. Rail pre-emption truncates all pedestrian movements. Enter 4s for min green. As dictated in programming comment #1 on the STS. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

TERM PH Enter YES. This will force an all-red period as dictated in comment #2 on the STS.

TRKCLR V Enter an F2 under phase 3 and an X under phase 8. This indicates phase 3 and 8 are the track clearance phases.

TRACK CLEAR TIMING

Enter 53s for min green. As dictated in programming comment #3 on the STS. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

CYC VEH

Enter X under phases 2 & 6 and an F2 under phases 5 & 7. This indicates these vehicle phases can be cycled through while the preemption input is active. As per comment #4 and phase descriptions on STS.

CYC PED Enter an X under phases 2 & 6. This indicates these phases’ pedestrian displays can be cycled through while the preemption input is active.

CYC OLP

Enter an X under overlaps 1 & 2 (A & B). This enables the vehicle displays for phases 2 & 6 during this preemption input. This is required because there is advance warning for phases 2 & 6.

DWL/CYC-EXIT TIMING Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

Page 256: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-256

Page 257: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-257

PREEMPT PLAN 1-10 (MM-4-1)

EMERGENCY PREEMPT PLAN #3

ENABLE Enter YES.

DWEL VEH Enter an X under phase 2 and an F2 under phase 5. Phases called by each preemption input are noted under the phase description on the STS.

DWEL OLP

Enter an X under overlap 1 (A). This enables the vehicle display for phase 2 during this preemption input. This is required because there is advance warning for phase 2.

EXIT PH Enter an X under phases 2 & 5.

TERM PH Enter YES. There is a possible left turn trap if phase 6 is active when this preemption call is made.

ENTRANCE TIMING

Enter 0s for walk. Emergency pre-emption truncates the walk interval. Enter 255s for ped clearance. This ensures the controller uses the entrance phase programmed ped clearance time. Enter 4s for min green. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

DWL/CYC-EXIT

Enter 180s for max dwell. This ensures the controller ignores an emergency pre-emption call that last longer than 3 minutes. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

Page 258: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-258

Page 259: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-259

PREEMPT PLAN 1-10 (MM-4-1)

EMERGENCY PREEMPT PLAN #4

ENABLE Enter YES.

DWEL VEH Enter an F2 under phase 1 and an X under phase 6. Phases called by each preemption input are noted under the phase description on the STS.

DWEL OLP

Enter an X under overlap 2 (B). This enables the vehicle display for phase 6 during this preemption input. This is required because there is advance warning for phase 6.

EXIT PH Enter an X under phases 1 & 6.

TERM PH Enter YES. There is a possible left turn trap if phase 2 is active when this preemption call is made.

ENTRANCE TIMING

Enter 0s for walk. Emergency pre-emption truncates the walk interval. Enter 255s for ped clearance. This ensures the controller uses the entrance phase programmed ped clearance time. Enter 4s for min green. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

DWL/CYC-EXIT

Enter 180s for max dwell. This ensures the controller ignores an emergency pre-emption call that last longer than 3 minutes. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

Page 260: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-260

Page 261: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-261

PREEMPT PLAN 1-10 (MM-4-1)

EMERGENCY PREEMPT PLAN #5

ENABLE Enter YES.

DWEL VEH Enter an X under phase 4. Phases called by each preemption input are noted under the phase description on the STS.

EXIT PH Enter an X under phase 4.

TERM PH Enter YES. There is a possible left turn trap if phases 4 & 8 are active when this preemption call is made.

ENTRANCE TIMING

Enter 0s for walk. Emergency pre-emption truncates the walk interval. Enter 255s for ped clearance. This ensures the controller uses the entrance phase programmed ped clearance time. Enter 4s for min green. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

DWL/CYC-EXIT

Enter 180s for max dwell. This ensures the controller ignores an emergency pre-emption call that last longer than 3 minutes. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

Page 262: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-262

Page 263: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-263

PREEMPT PLAN 1-10 (MM-4-1)

EMERGENCY PREEMPT PLAN #6

ENABLE Enter YES.

DWEL VEH Enter an X under phase 8. Phases called by each preemption input are noted under the phase description on the STS.

EXIT PH Enter an X under phase 8.

TERM PH Enter YES. There is a possible left turn trap if phases 4 & 8 are active when this preemption call is made.

ENTRANCE TIMING

Enter 0s for walk. Emergency pre-emption truncates the walk interval. Enter 255s for ped clearance. This ensures the controller uses the entrance phase programmed ped clearance time. Enter 4s for min green. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

DWL/CYC-EXIT

Enter 180s for max dwell. This ensures the controller ignores an emergency pre-emption call that last longer than 3 minutes. Enter 25.5s for yellow and red. This ensures the phase yellow and red time is used from the timing plan.

Page 264: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-264

Page 265: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-265

CLOCK/CALENDAR DATA (MM-5-1)

CLOCK/CALENDAR SETTINGS

Ensure the correct date and time is entered.

Page 266: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-266

Page 267: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-267

ACTION PLAN (MM-5-2)

ACTION PLAN #1

Enter 0 for the pattern number. This defaults to AUTO operation. When this action plan is called the controller will run the specified timing plan 1. Enter 1 for the timing plan. Timing plan 1 from MM-2-1 will be used when this action plan is called by time of day. Enter an X under phases 3 & 7 for OMIT. This omits these ‘rail preemption only’ phases from normal controller operation. The logic processor is responsible for overriding these omits when rail preemption is called.

Page 268: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-268

Page 269: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-269

ACTION PLAN (MM-5-2)

ACTION PLAN #2

Enter 0 for the pattern number. This defaults to AUTO operation. When this action plan is called the controller will run the specified timing plan 2. Enter 2 for the timing plan. Timing plan 2 from MM-2-1 will be used when this action plan is called by time of day. Enter an X under phases 3 & 7 for OMIT. This omits these ‘rail preemption only’ phases from normal controller operation. The logic processor is responsible for overriding these omits when rail preemption is called.

Page 270: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-270

Page 271: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-271

DAY PLAN/EVENT (MM-5-3)

DAY PLAN #1

Enter the action plan schedule for weekdays. This corresponds to the weekday time clock settings on the STS.

DAY PLAN #2

Enter the action plan schedule for weekends. This corresponds to the weekend time clock settings on the STS.

Page 272: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-272

Page 273: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-273

SCHEDULE NUMBER (MM-5-4)

SCHEDULE #1

Enter an X under each weekday in the DOW row. This will ensure the linked day plan is used only on weekdays. Enter a 1 for Day Plan No. This will link day plan 1 to this weekday schedule.

SCHEDULE #2

Enter an X under each weekend day in the DOW row. This will ensure the linked day plan is used only on weekends. Enter a 2 for Day Plan No. This will link day plan 2 to this weekend schedule.

Page 274: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-274

Page 275: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-275

VEHICLE DETECTOR SETUP (MM-6-2)

NOTE: All detector inputs given on the Loop Assignment Sheet must be programmed. The two detectors shown here are examples on how these detectors are programmed.

VEHICLE DETECTOR #1

Enter 1 under PH. Detector calls/extends phase 1. Enter NO for ECPI LOG. Detector is not used for volume counts. Enter 10.0 beside DELAY TIME. Detector has a 10s delay.

VEHICLE DETECTOR #2

Enter 2 under PH. Detector calls/extends phase 2. Enter YES for ECPI LOG. Detector is used for volume counts.

Page 276: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-276

Page 277: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-277

VEHICLE DETECTOR PHASE ASSIGNMENT (MM-6-1)

VEHICLE DETECTOR ASSIGNMENT SUMMARY

As previously mentioned it is not recommended to program detectors here as all the details are not present on this screen. However it is recommended that after programming all detectors you then compare the LAS with this screen as a quality control check.

Page 278: Electrical and ITS Engineering - British Columbia · 2019-07-22 · ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 3-5 INTRODUCTION . This Cobalt programming guide was originally

COBALT PROGRAMMING GUIDE EXAMPLE –EIGHT PHASE SIGNAL WITH RAIL PREEMPTION

ELECTRICAL AND ITS ENGINEERING – JUNE 2019 Page 13-278