QUALITY MANAGEMENT PROCEDURE Doc. No. : F Q MNT 02 P
ELECTRICAL MAINTENANCE Page No. : 1 of 8
1. PURPOSE:
To establish the system for the maintenance of electrical equipments and to ensure that the equipments are available continuously for preventive maintenance.
2. SCOPE:
This is applicable to the preventive & breakdown Maintenance of electrical equipment of Foil.
3. DEFINITIONS:
Dy.General Manager - Deputy General ManagerAsst.Manager - Assistant ManagerPMI - Preventive Maintenance InchargeI.D. No. - Identification NumberP.M - Preventive Maintenance
4. RESPONSIBILITY:
4.1 Head of department is over all responsible for implementing this procedure.4.2 Personal performing breakdown maintenance shall not carry out preventive
maintenance.4.3 Individual responsibilities of specific activities are described here after.
5. PROCESS INPUT:
5.1 Work instruction for carrying out maintenance activities.5.2 Intimation of breakdown by work order5.3 P.M.Slippage Record5.4 P.M.Schedule5.5 PM Checklist5.6 P.M.Schedule cum check sheet
Approved By:
Issued By: Edition No. 01
Date: 01. 12. 2001 Date: 01.12. 2001 Revision No. 02
QUALITY MANAGEMENT PROCEDURE Doc. No. : F Q MNT 02 P
ELECTRICAL MAINTENANCE Page No. : 2 of 8
6. PROCESS DESCRIPTION & INTERFACES:
A. Preventive maintenance: -
Sr. No.
Activity Responsibility Ref. Doc.
1All the equipments requiring periodic maintenance will be identified and a list will be prepared.
Asst.Manager FQMNT02F01
2 A unique I.D.No. Will be given to them. Asst.Manager FQMNT02F01
3
The frequency of maintenance will be decided on the basis of
• Manufacture recommendation Decided by maintenance Department
Asst.Manager
Operation & Maintenance Manual FQMNT02F06
4The P.M. schedule/P.M.Schedule cum check sheet will be made as per the identified frequency above.
Asst.Manager FQMNT02F06 FQMNT02F18
5
The equipment will be spared and the preventive maintenance will be carried out as per P.M check list/ P.M.Schedule cum check sheet & relevant work instruction.
Asst.Manager/PMI/ Sr.Formen/Foreman
FQMNT02F07, FQMNT02W03, FQMNT02W10, FQMNT02W12 FQMNT02F18,FQMNT02W05
6The P.M. checklist / P.M.Schedule cum check sheet will be filled up after completing maintenance.
PMIFQMNT02F07, FQMNT02F18
7
In case of any schedule getting delayed due to any reasons or preventive action if not carried out, should be recorded in the P.M slippage record.
PMI FQMNT02F08
8Review the P.M. schedule at least Six monthly for types of checks & frequency on the basis of its effectiveness.
Asst.Manager/PMIFQMNT02F03, FQMNT02F04
Approved By:
Issued By: Edition No. 01
Date: 01. 12. 2001 Date: 01.12. 2001 Revision No. 02
QUALITY MANAGEMENT PROCEDURE Doc. No. : F Q MNT 02 P
ELECTRICAL MAINTENANCE Page No. : 3 of 8
9Review the P.M.slippage record monthly & to avoid the frequency of slippage.
Asst.Manager/PMI
FQMNT02F08
10
In a case of overhauling required, for the equipment, follow the respective work instruction/Vendor instruction manual and filled the over hauling check list.
Sr. Foreman/ Foreman
Operating and maintenance manual, FQMNT02W09, FQMNT02W07FQMNT02F19
11
Operation of DG SET, Circuit breaker, 66KVSwithyard,HT Capacitor bank and power changeover done as per work instruction.
Shift foremanFQMNT02W01FQMNT02W02FQMNT02W04FQMNT02W08 FQMNT02W11
B. BREAKDOWN: -
Sr. No.
Activity Responsibility Ref. Doc.
1Receiving work order from user department regarding breakdown of any equipment.
Shift Incharge
2Review the problem and allocate the job to concern person.
Asst.Manager/Shift Incharge
3Carry out the breakdown maintenance. As per work instruction.
Sr.Forman/ Shift Incharge/Foreman
FQMNT02W06
4Prepare daily breakdown report and sent copy to Dy.GM (Mech) & GM (F&A).
Sr.Forman /Foreman
FQMNT02F03
5Prepare monthly breakdown report and sent copy to V.P. (foils), all Deptt. Heads, MIS & PPC.
Sr.Forman /Foreman
FQMNT02F04
7. PROCESS OUT PUTS:7.1. Continue availability of machine.7.2. Relevant reports & records of equipments.
Approved By:
Issued By: Edition No. 01
Date: 01. 12. 2001 Date: 01.12. 2001 Revision No. 02
QUALITY MANAGEMENT PROCEDURE Doc. No. : F Q MNT 02 P
ELECTRICAL MAINTENANCE Page No. : 4 of 8
7.3 P.M.Slippage Record.
8. PROCESS MONITORING:
Sr. No.
Description Frequency Responsibility
1 Review of P.M. schedule. Six monthly Asst.Manager
2 Review P.M.slippage record. Monthly Asst.Manager
9. RECORDS:
Approved By:
Issued By: Edition No. 01
Date: 01. 12. 2001 Date: 01.12. 2001 Revision No. 02
QUALITY MANAGEMENT PROCEDURE Doc. No. : F Q MNT 02 P
ELECTRICAL MAINTENANCE Page No. : 5 of 8
Approved By:
Issued By: Edition No. 01
Date: 01. 12. 2001 Date: 01.12. 2001 Revision No. 02
Sr.No. Record No. Record TitleRetention
periodLocation
Disposal authority
1 FQMNT02F01COMPREHENSIVE EQUIPMENT LIST
Till the equipment Last
ELECTRICAL SHOP FLOOR
Dy. General Manager
2 FQMNT02F02EQUIPMENT HISTORY RECORD
Till the equipment Last
ELECTRICAL SHOP FLOOR, MSDS&ERS
Dy. General Manager
3 FQMNT02F03DAILY BREAKDOWN REPORT
Six Months
ELECTRICAL SHOP FLOOR
Dy. General Manager
4 FQMNT02F04MONTHLY BREAKDOWN REPORT
1YearELECTRICAL SHOP FLOOR
Dy. General Manager
5 FQMNT02F05
MAJOR BREAKDOWN ANALYSIS REPORT
1YearELECTRICAL SHOP FLOOR
Dy. General Manager
6 FQMNT02F06 PM SCHEDULE 1YearELECTRICAL
SHOP FLOOR/MSDS
Dy. General Manager
QUALITY MANAGEMENT PROCEDURE Doc. No. : F Q MNT 02 P
ELECTRICAL MAINTENANCE Page No. : 6 of 8
Approved By:
Issued By: Edition No. 01
Date: 01. 12. 2001 Date: 01.12. 2001 Revision No. 02
7 FQMNT02F07FQMNT02F07/ 01FQMNT02F07/ 02FQMNT02F07/ 03FQMNT02F07/ 04FQMNT02F07/ 05FQMNT02F07/ 06FQMNT02F07/ 07FQMNT02F07/ 08FQMNT02F07/ 09FQMNT02F07/ 10FQMNT02F07/ 11FQMNT02F07/ 12FQMNT02F07/ 13FQMNT02F07/ 14FQMNT02F07/ 15FQMNT02F07/ 16FQMNT02F07/ 17FQMNT02F07/ 18FQMNT02F07/ 19FQMNT02F07/ 20FQMNT02F07/ 21FQMNT02F07/ 22FQMNT02F07/ 23FQMNT02F07/ 24FQMNT02F07/ 25FQMNT02F07/ 26FQMNT02F07/ 27FQMNT02F07/ 28FQMNT02F07/ 29FQMNT02F07/ 30FQMNT02F07/ 31
P.M.CHECK LIST:-MILL M50MILL M51MILL M52MILL Q4MILL Q5CRANE # 1CRANE # 2CRANE # 3CRANE # 4CRANE # 5CRANE # 6CRANE # 7CRANE # 8CRANE # 4AREWIND LINE # 1REWIND LINE # 2REWIND LINE # 3BAILING PRESSROLL GRINDERANN. FURNACE # 1ANN. FURNACE # 2ANN. FURNACE # 3ANN. FURNACE # 4OVEN # 1OVEN # 2OVEN # 3SEPARATOR # 25SEPARATOR # 26DOWN ENDERFUME EXH. SYSTEMH G SLITTER
1Year ELECTRICAL SHOP FLOOR/MSDS
Dy. General Manager
QUALITY MANAGEMENT PROCEDURE Doc. No. : F Q MNT 02 P
ELECTRICAL MAINTENANCE Page No. : 7 of 8
Approved By:
Issued By: Edition No. 01
Date: 01. 12. 2001 Date: 01.12. 2001 Revision No. 02
FQMNT02F07/ 32FQMNT02F07/ 33FQMNT02F07/ 34FQMNT02F07/ 35FQMNT02F07/ 36FQMNT02F07/ 37FQMNT02F07/ 38FQMNT02F07/ 39FQMNT02F07/ 40FQMNT02F07/ 41FQMNT02F07/ 42FQMNT02F07/ 43 FQMNT02F07/ 44
M G SLITTERL G SLITTERDOCTOR REWINDERDRY BOND LAM.PRINTING MACHINEEXTRUDER COATERMAIN PUMP HOUSECOOLING TOWERNITROGEN GEN.FIRE HYDRANTW.T.P.VENT. SYSTEMCOMP. HOUSE
1 Year ELECTRICAL SHOP
FLOOR/MSDS
Dy.GeneralManager
8 FQMNT02F08P.M.SLIPPAGE RECORD
1YearELECTRICAL SHOPFLOOR/
MSDS
Dy. General Manager
9 FQMNT02F09 WORK ORDER 3 MonthECR Q4/Q5, ERS& MSDS
Dy. General Manager
10 FQMNT02F10 WORK PERMIT 3MonthECR Q4/Q5, ERS& MSDS
Dy. General Manager
11 FQMNT02F11OVERHAULING SCHEDULE
1 Year MSDS / ERSDy.
General Manager
12 FQMNT02F12 SHIFT LOG BOOK 1YEARQ4/Q5
CONTROL ROOM
Dy. General Manager
13 FQMNT02F13
DAILY ENERGY GENERATION /CONSUMPTION REPORT
Six Months
MSDSDy.
General Manager
QUALITY MANAGEMENT PROCEDURE Doc. No. : F Q MNT 02 P
ELECTRICAL MAINTENANCE Page No. : 8 of 8
Approved By:
Issued By: Edition No. 01
Date: 01. 12. 2001 Date: 01.12. 2001 Revision No. 02
14 FQMNT02F14
STATEMENT SHOWING ENERGY GENERATED & CONSUMED INCLUDING CONSUMPTION OF DIESEL
1Year MSDSDy. General
Manager
15 FQMNT02F15 DG LOG BOOK 1Year MSDSDy. General
Manager
16 FQMNT02F16ANALYSIS OF MOTOR FAILURE 1Year ERS
Dy. General Manager
17 FQMNT02F17
ELECTRICAL POWER CONSUMPTION REPORT
1YearELECTRICAL SHOP FLOOR
Dy. General Manager
18 FQMNT02F18
FQMNT02F18/
01
FQMNT02F18/
02
FQMNT02F18/
03
FQMNT02F18/
04
FQMNT02F18/
05
FQMNT02F18/
06
FQMNT02F18/
07
FQMNT02F18/
08
FQMNT02F18/
09
FQMNT02F18/
10
FQMNT02F18/
11
PM SCHEDULE CUM CHECK SHEET: -
LT air circuit breaker
66 kv CT, PT, CVT & LA
LT APFC panel, HT
capacitor bank & reactor
Battery bank & battery
charger
11 kv & 132 kv MOCB
11 kv T.M.G. ACB
11 kv ABB (indoor &
outdoor) & Siemens VCB
66 kv Sf6 circuit breaker
22 kv Sf6 circuit breaker
11 kv, 22 kv & 66 kv
isolators
11 kv, 1500 kva DG set
1Year MSDSDy. General
Manager
QUALITY MANAGEMENT PROCEDURE Doc. No. : F Q MNT 02 P
ELECTRICAL MAINTENANCE Page No. : 9 of 8
10. REFERENCE :
Sr.No. Document no. Work instruction 1 FQMNT 02W01 OPERATION OF D.G.SET2 FQMNT 02W02 OPERATION OF 66KV SWITCH YARD3 FQMNT 02W03 OPERATION AND MAINTENANCE OF BATTERY BANK4 FQMNT 02W04 OPERATION OF H.T CAPACITOR BANK5 FQMNT 02W05 OPERATION AND MAINTENANCE OF TRANSFORMER6 FQMNT 02W06 BREAKDOWN MAINTENANCE7 FQMNT 02W07 OVER HAULING OF D.C. MOTOR8 FQMNT 02W08 POWER CHANGE OVER9 FQMNT 02W09 OVER HAULING OF A.C. SLIPRING MOTOR10 FQMNT 02W10 MAINTENANCE OF DIESEL GENERATOR11 FQMNT 02W11 OPERATION OF CIRCUIT BREAKER12 FQMNT 02W12 PREVENTIVE MAINTENANCE
Approved By:
Issued By: Edition No. 01
Date: 01. 12. 2001 Date: 01.12. 2001 Revision No. 02
FQMNT02F18/
12
FQMNT02F18/
13
FQMNT02F18/
14
FQMNT02F18/
15
Power & distribution
transformer
415 v, 125 kva DG set
Sub- station (monthly)
Sub- station (fortnight) 1Year MSDSDy. General
Manager
19 FQMNT02F19 OVER HAULING CHECK LIST
3 Years ERSDy. General
Manager