electricity metering code - escosa - home

30
ELECTRICITY METERING CODE EMTC/08 February 2013

Upload: others

Post on 07-Dec-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

ELECTRICITY METERING CODE

EMTC/08

February 2013

AMENDMENT RECORD

Issue No. Commencement Date

EMTC/01 01/01/2003

EMTC/02 01/01/2003

EMTC/03 14/07/2003

EMTC/04 01/07/2005

EMTC/05 01/01/2009

EMTC/06 01/10/2009

EMTC/07 23/12/2010

EMTC/08 07/02/2013

Electricity Metering Code

EMTC/08

iii

TABLE OF CONTENTS

1. Preliminary 1

1.1. Definitions 1

1.2. Authority 1

1.3. Application 1

1.4. Obtaining a Copy of this Industry Code 1

1.5. Other Acts, Industry Codes and guidelines 2

2. Metering provision Services for connection points not in the national electricity market 3

2.1. Application of Chapter 2 3

2.2. Responsibility for metering provision 3

2.3. Unmetered Connection Points 3

2.4. Non-Market Generators 4

2.5. Changing Tariffs 4

2.6. Installation 4

2.7. Metering installations 5

2.8. Meter Testing and Maintenance 5

2.9. Repair or Replacement of Defective Meters 6

2.10. Switching and Time Keeping 6

2.11. Seals 7

2.12. Broken Seals 7

3. Metering provision services for all connection points 8

3.1. Application of Chapter 3 8

3.2. Installing meters of a higher standard 8

3.3. Installation 8

3.4. Meter Testing and Maintenance Plan 9

4. Metering Data Services for connection points not in the national electricity market 11

4.1. Application of Chapter 4 11

4.2. Non-reversion in metering data services 11

4.3. Collection of Metering Data 11

4.4. Validation and Substitution of Metering Data 13

4.5. Calculation of Metering Data for Unmetered Connection Points 14

4.6. Access to Metering Installation 14

4.7. Storage of Metering Data 14

4.8. Access to Metering Data 15

5. Metering Data Services for all connection points 16

5.1. Application of Chapter 5 16

iv

5.2. Collection of Metering Data 16

5.3. Access to data 16

5.4. Confidentiality 17

6. SCHEDULE: Definitions and Interpretation 20

6.1. Definitions 20

6.2. Interpretation 24

Electricity Metering Code

EMTC/08

1

1. PRELIMINARY

1.1. Definitions

1.1.1. Words appearing in bold like this are defined in the Schedule.

1.1.2. References to Australian Standards are references to standards existing from

time to time, or where they are superseded, their replacements.

1.2. Authority

1.2.1. This industry code is made by the Commission under section 28 of the

Essential Services Commission Act 2002.

1.3. Application

1.3.1. This industry code regulates standards for meters and metering installations

at customer connection points and connection points for non-market

generators:

(a) in respect of chapters 3 and 5 for all connection points; and

(b) in respect to chapters 2 and 4 for;

(i) unmetered connection points that have not been classified as

market load in accordance with the National Electricity Rules;

(ii) connection points to an embedded network where a child has not

chosen its own retailer; and

(iii) connection points to an off grid distribution system.

1.3.2. The persons bound by this industry code are retailers, distributors, persons

exempt from holding a distribution licence, operators of off grid distribution

systems and generators (to the extent provided in this industry code).

1.4. Obtaining a Copy of this Industry Code

1.4.1. A person responsible for the metering installation must, when asked by a

customer, send to that customer within 10 business days a copy of this

industry code (and any amendments from time to time), free of charge for the

first request.

1.4.2. A person responsible for the metering installation may impose a reasonable

charge for subsequent requests.

2

1.5. Other Acts, Industry Codes and guidelines

1.5.1. Not all aspects of a retailer’s, distributor’s, exemptee’s or generator’s

obligations are regulated by this industry code. The retailer’s, distributor’s,

person’s exempt from holding a distribution licence and generator’s

obligations and some aspects of the relationship with a customer are also

affected by:

(a) Acts of Parliament and Regulations (in particular, the Electricity Act 1996

and the Essential Services Commission Act 2002 (and associated

regulations));

(b) the National Electricity Rules National Energy Retail Law, National

Energy Retail Regulations and National Energy Retail Rules;

(c) the Electricity Distribution Price Determination;

(d) any guidelines or rules made by the Commission from time to time;

(e) the Electricity Distribution Code and Electricity Transmission Code; and

(f) relevant licences or authorisations (as the case may be).

Electricity Metering Code

EMTC/08

3

2. METERING PROVISION SERVICES FOR CONNECTION POINTS NOT IN THE NATIONAL ELECTRICITY MARKET

2.1. Application of Chapter 2

2.1.1. This chapter applies to each metering installation installed at a connection

point in accordance with clause 1.3.1(b).

2.1.2. Metering installations in service in South Australia immediately prior to

1 January 2003 will be deemed to comply with the requirements prescribed by

this industry code.

2.2. Responsibility for metering provision

2.2.1. The person responsible for the metering installation at each connection point

is:

(a) the distributor for an unmetered connection point to its distribution

system;

(b) the person exempt from holding a distribution licence for that

embedded network for a connection point to an embedded network

where the customer has not chosen its own retailer; and

(c) the distributor or operator, as the case may be, in regard to an off grid

distribution system for connection points to its off grid distribution

system.

2.2.2. The person responsible for the metering installation must ensure that each

connection point has a metering installation provided, installed,

commissioned, tested and maintained in accordance with this industry code

except for the metering installations in clause 2.2.3.

2.2.3. The person responsible for a metering installation in embedded networks is

only required to install an interval meter when requested to do so by the

customer or the customer’s retailer.

2.3. Unmetered Connection Points

2.3.1. A connection point must be metered in accordance with this industry code

unless the person responsible for the metering installation determines that

the connection point meets the criteria for the classification as a metering

installation type 7 in accordance with Schedule S7.2.3 of the National

Electricity Rules.

4

2.4. Non-Market Generators

2.4.1. The person responsible for the metering installation must ensure that the

metering installation for a non-market generator meets the requirements of

the National Electricity Rules and this industry code unless otherwise agreed

to by the Commission.

2.4.2. A new metering installation for a non-market generator must be installed in

accordance with this industry code and any reasonable requirements of the

distributor.

2.5. Changing Tariffs

2.5.1. If the distributor or retailer wants to introduce a new distribution or retail

tariff, or change an existing distribution or retail tariff, which requires new or

different metering installations or for existing metering installations to be

operated in a different manner, the distributor or retailer must seek

agreement with the person responsible for the metering installation prior to

the introduction of the new tariff or change to an existing tariff.

2.5.2. The person responsible for the metering installation must not unreasonably

withhold its agreement to a request made under clause 2.5.1.

2.6. Installation

2.6.1. The person responsible for the metering installation must install a metering

installation at or as near as practicable to the connection point.

2.6.2. The person responsible for the metering installation must ensure that new

metering installations are installed and commissioned for:

(a) connections points under clause 1.3.1(b) (ii) in a safe manner only by a

registered metering provider; and

(b) connections points under clause 1.3.1(b) (iii) in a safe manner by an

appropriately qualified person.

2.6.3. The person responsible for the metering installation must install a metering

installation in a position which allows safe and unimpeded access to any

person whose obligation it is to test, adjust, maintain, repair, replace or collect

metering data from the metering installation.

2.6.4. If the distribution or retail tariff payable for the supply of electricity in respect

of a connection point of a customer changes, and the metering installation is

thereafter incapable of appropriately measuring and recording the amount of

electricity supplied to that connection point, the person responsible for the

metering installation must provide, install, commission, test and maintain the

Electricity Metering Code

EMTC/08

5

new metering installation to appropriately measure and record the amount of

electricity supplied to the customer’s connection point.

2.6.5. The cost of providing and installing a new metering installation under clause

2.6.4 shall, to the extent permitted by this industry code or an applicable

regulatory instrument, be paid by the party that initiates the change.

2.6.6. A meter and data logger (where required) must be mounted on an

appropriately constructed panel in accordance with clause 7.3.1(b)(4) of the

National Electricity Rules.

2.7. Metering installations

2.7.1. Subject to clause 2.1.2, the person responsible for the metering installation

must ensure that each metering installation incorporates all the relevant

requirements of the National Electricity Rules and the Metrology Procedure

including, but not limited to,:

(a) the design and pattern approval requirements of Schedule S7.2 of the

National Electricity Rules;

(b) the minimum standards of accuracy in accordance with Schedule S7.2 of

the National Electricity Rules taking into account, among other things,

the annual electricity consumption level at the connection point;

(c) display, settings and suitability in accordance with clause 7.3.1(a) and

Schedules S7.2 5 and S7.4.1(e) of the National Electricity Rules; and

(d) the capability to store internally records of the amount of electricity

supplied in accordance with clause 7.3.1(a)(6) of the National Electricity

Rules.

2.7.2. The person responsible for the metering installation must ensure that when a

metering installation is installed, it is checked in accordance with clause

2.7.1(c) of Part A of the Metrology Procedure.

2.7.3. A person bound by this industry code must not tamper with or calibrate a

meter with the purpose of introducing bias in the meter.

2.8. Meter Testing and Maintenance

2.8.1. The person responsible for the metering installation must ensure that

metering installations are maintained and tested for:

(a) connections points under clause 1.3.1(b) (ii) in a safe manner only by a

registered metering provider; and

6

(b) connections points under clause 1.3.1(b) (iii) in a safe manner by an

appropriately qualified person.

2.8.2. The person responsible for metering installations must carry out tests of

metering installations in accordance with the relevant inspection and testing

requirements of clause 7.6 and Schedule S7.3 of the National Electricity Rules

and clause 2.6 of Part A of the Metrology Procedure.

2.8.3. The person responsible for the metering installation must keep records of

tests under this clause 2.8 in accordance with clause 7.6.4 of the National

Electricity Rules.

2.8.4. The person responsible for the metering installation must provide copies of

the results from any testing of meters, or unmetered connection points, to the

retailer on request.

2.8.5. The person responsible for the metering installation must conduct tests in

respect of unmetered connection points in accordance with clauses 3.9.4 to

3.9.9 of Part A of the Metrology Procedure.

2.8.6. For the purpose of this clause 2.8, all references in the Metrology Procedure

to:

(a) affected Rule Participants is a reference to affected parties;

(b) a responsible person is a reference to the person responsible for the

metering installation;

(c) the financially responsible market participant are references to the

relevant retailer;

(d) an asset management strategy are references to a maintenance plan;

(e) the local network service provider are references to the distributor; and

(f) type 7 metering installation are references to an unmetered connection

point.

2.9. Repair or Replacement of Defective Meters

2.9.1. Unless otherwise agreed by the Commission, if a test conducted in accordance

with this industry code demonstrates that any meter is defective, the person

responsible for the metering installation must repair or replace that meter in

accordance with clause 7.11.2(a) of the National Electricity Rules.

2.10. Switching and Time Keeping

2.10.1. Unless otherwise agreed by the Commission, where tariffs for the sale of

electricity to a customer are based on different rates according to the time of

Electricity Metering Code

EMTC/08

7

day, the person responsible for the metering installation must install and

maintain an interval meter, or a meter that:

(a) includes a clock complying with AS 1284.7;

(b) has a clock that is automatically adjusted on each occasion it is accessed

electronically, and effectively remain within the time-keeping standards

imposed by AS 1284.7; or

(c) for multiple rate induction type meters, includes a time switch which has

a tolerance of timekeeping of +/- 30 minutes.

2.10.2. Where tariffs for the sale of electricity are based on 30-minute demand

integration period, then the start of each integration period will be on the

hour, and on the half-hour.

2.11. Seals

2.11.1. The person responsible for the metering installation must:

(a) in respect of new meters provide seals or other appropriate devices to

detect interference; and

(b) maintain a register of all relevant security fitting tools and seals.

2.12. Broken Seals

2.12.1. Following notification that a seal has been broken the person responsible for

the metering installation must replace a broken seal on the earlier of:

(a) the first occasion the metering installation is visited to take a reading;

or

(b) 70 business days.

2.12.2. The costs of replacing seals which are broken are borne:

(a) if the seal was broken by the retailer, by the retailer; or

(b) otherwise by the person responsible for the metering installation.

2.12.3. If as a result of or in connection with the breaking of a seal, the relevant

metering installation can no longer meet the relevant minimum standards of

accuracy, the person responsible for the metering installation must:

(a) test the metering installation in accordance with clause 2.8; or

(b) replace the metering installation in accordance with clause 2.9.

8

3. METERING PROVISION SERVICES FOR ALL CONNECTION POINTS

3.1. Application of Chapter 3

3.1.1. This chapter applies to metering installations at all connection points.

3.1.2. In this chapter the person responsible for the metering installation may be the

responsible person or the person responsible for the metering installation

determined in accordance with clause 2.2.1.

3.1.3. The obligations on responsible persons in this chapter for metering

installations at connection points are in addition to the obligations for

responsible persons under the National Electricity Rules for those connection

points.

3.2. Installing meters of a higher standard

3.2.1. The person responsible for the metering installation must not unreasonably

withhold its consent to the request of a customer or a customer’s retailer to

install a metering installation of a type that is different from that already

installed, or that the person responsible for the metering installation

otherwise would install, provided that the metering installation satisfies any

applicable technical requirements (including those reasonably required by the

distributor).

3.2.2. The cost of providing and installing a new metering installation under

clause 3.2.1 shall, to the extent permitted by this industry code or an

applicable regulatory instrument, be paid by the party that initiates the

change.

3.3. Installation

3.3.1. The person responsible for the metering installation must ensure that all

wiring for a metering installation complies with AS 3000 or, if AS 3000 is not

applicable, good industry practice. All wiring must be undertaken with at least

2.5mm2 copper equivalent cross-sectioned area single insulated cable.

3.3.2. The person responsible for the metering installation must ensure that where

current transformers or voltage transformers form part of the metering

installation, the test blocks and potential fuses are installed so as to allow

future modification to the metering installation without interruption to the

customer’s supply.

3.3.3. The person responsible for the metering installation must ensure that new

metering panels meet the following requirements of AS 3000:

Electricity Metering Code

EMTC/08

9

(a) ‘Construction of Switchboards’, clause 2.22; and

(b) ‘Material’, clause 2.22.1.2.

3.3.4. The person responsible for the metering installation must not allow panels to

be constructed of materials containing asbestos.

3.3.5. The person responsible for the metering installation must ensure that any

new metering installation does not interfere with the distributor’s distribution

system.

3.4. Meter Testing and Maintenance Plan

3.4.1. Unless otherwise agreed by the Commission, the person responsible for the

metering installation must annually prepare and submit to the Commission for

approval a maintenance plan for metering installations for which it is

responsible.

3.4.2. A maintenance plan prepared under clause 3.4.1 must be prepared in

accordance with clause 2.6 of Part A of the Metrology Procedure.

3.4.3. The Commission will accept SA Power Networks’ annual Meter Testing and

Maintenance Plan approved by AEMO. The AEMO approved plan must be

provided to the Commission by SA Power Networks within 2 weeks of

receiving AEMO’s approval.

3.4.4. The person responsible for the metering installation must, upon request by

the Commission, provide the Commission with the results of any test

conducted in accordance with this industry code or the National Electricity

Rules.

3.4.5. A retailer or a customer may request that the person responsible for a

metering installation make arrangements for the testing of a metering

installation.

3.4.6. If the request for a test of a metering installation under clause 3.4.4 is

reasonable the testing must be carried out:

(a) in accordance with clause 2.8.2 for connection points under clause

1.3.1(b); or

(b) in accordance with clause 7.6 of the National Electricity Rules for

connection points registered under the National Electricity Rules.

3.4.7. If, as a result of the test requested by a retailer or a customer under clause

3.4.5 the metering installation is found to be:

(a) defective, the person responsible for the metering installation must

bear the cost incurred in conducting the test; or

10

(b) not defective, the person responsible for the metering installation may

seek to recover the cost incurred in conducting the test.

3.4.8. The person responsible for the metering installation must, upon request,

provide the customer with the results of the test conducted under clause 3.4.5

or clause 2.8.2 in accordance with National Electricity Rules clause 7.6.1

paragraphs (h) and (i).

3.4.9. If a test carried out under clause 3.4.5 or clause 2.8.2 requires the injection of

current, then the person responsible for the metering installation must ensure

that the subsequent bill issued to the customer is adjusted so that no material

amount is payable by the customer in respect of electricity consumed during

the test.

3.4.10. If a test carried out under clause 3.4.5 or clause 2.8.2 is based on actual

customer loads, then no adjustment is required under this clause.

Electricity Metering Code

EMTC/08

11

4. METERING DATA SERVICES FOR CONNECTION POINTS NOT IN THE NATIONAL ELECTRICITY MARKET

4.1. Application of Chapter 4

4.1.1. This chapter applies to metering data services for metering installations

installed at connection points in accordance with clause 1.3.1(b).

4.2. Non-reversion in metering data services

4.2.1. where an interval meter is installed the person responsible for the metering

installation must ensure that interval energy data is collected from that

interval meter in accordance with clause 4.3 unless otherwise approved by

the Commission.

4.3. Collection of Metering Data

4.3.1. The person responsible for the metering installation must collect data stored

in a metering installation by reading the meter at the customer’s supply

address in accordance with this Chapter 4.

4.3.2. A customer may arrange with the person responsible for the metering

installation or its retailer that the data stored in the metering installation be

collected by the person responsible for the metering installation:

(a) by inspecting the metering installation;

(b) where the metering installation is capable of providing data by

electronic means, by electronic means; or

(c) where the metering installation is capable of providing data by any

other means, by any other means.

4.3.3. The person responsible for the metering installation may charge a customer

for the collection of metering data under clause 4.3.2 to the extent that its

costs of collection are higher than they would otherwise be.

4.3.4. The person responsible for the metering installation must use its best

endeavours to ensure that interval energy data or accumulated energy data

is:

(a) collected from all metering installations at least quarterly or, where a

greater frequency has been agreed with a customer or a customer’s

retailer, at that greater frequency; and

(b) collected from each manually read metering installation by means of an

actual meter reading at least once in each 12 month period.

12

4.3.5. Where the person responsible:

(a) is required under clause 4.3.4(a) to use its best endeavours to collect

interval energy data or accumulated energy data from a metering

installation at least quarterly; and

(b) has not obtained an actual meter reading in respect of that metering

installation for three successive quarters by reason of the denial of

access to the metering installation by the customer,

then the person responsible must use its best endeavours to obtain an actual

meter reading in respect of that metering installation for the subsequent

quarter.

4.3.6. When interval energy data or accumulated energy data is not collected by a

person responsible for the metering installation from a metering installation

by way of an actual meter reading at the applicable meter reading frequency

under clause 4.3.4(a), an estimated read must be obtained by the person

responsible for the metering installation.

4.3.7. An estimated read obtained for the purposes of clause 4.3.5 must be provided

to the retailer within 10 business days of the scheduled meter reading date

under clause 4.3.4(a).

4.3.8. The person responsible for the metering installation must perform a special

meter read at the request of a customer or a customer’s retailer.

4.3.9. The person responsible for the metering installation must perform a final read

at the request of a customer or a customer’s retailer.

4.3.10. Where the metering data held in the metering installation is protected from

direct or remote access by suitable password and security controls, such

passwords and security controls must be used.

4.3.11. Passwords must be treated as confidential information in accordance with

clause 5.4.

4.3.12. The original stored data in a meter must not be altered except when the meter

is reset to zero as part of a repair or reprogramming.

4.3.13. If there is any discrepancy between:

(a) the data stored in a metering installation, or where the metering

installation is not capable of storing data, data collected from the

metering installation; and

(b) metering data in respect of that metering installation;

Electricity Metering Code

EMTC/08

13

the data contained in the metering installation is to be prima facie evidence of

the amount of electricity supplied to the facilities of the relevant connection

point.

4.3.14. For an unmetered connection point, if there is an inconsistency between the

data held in the metering installation database and the physical inventory, the

physical inventory is to be taken as prima facie evidence of the actual data.

4.4. Validation and Substitution of Metering Data

4.4.1. The person responsible for the metering installation must ensure that

metering data collected from a metering installation type 5 or type 6 under

clause 4.3:

(a) is validated in accordance with clause 3.4.1 of Part A of the Metrology

Procedure; and

(b) where necessary, is substituted in accordance with clause 3.5 of Part A

of the Metrology Procedure.

4.4.2. The person responsible for the metering installation must ensure that

metering data collected from a metering installation type 1, 2, 3 or 4 under

clause 4.3:

(a) is validated in accordance with section 9 of Part B of the Metrology

Procedure; and

(b) where necessary, is substituted in accordance with section 2 of Part B of

the Metrology Procedure.

4.4.3. Where tests under clause 4.4.1(a) or clause 4.4.2(a) demonstrate that there

has been a failure of the metering installation or that a measurement error

exists, the metering data must be substituted in accordance with clause

4.4.1(b) or clause 4.4.2(b) and the person responsible for the metering

installation must provide the substituted metering data to the retailer so that

the retailer can meet its billing obligations.

4.4.4. The person responsible for the metering installation must maintain a separate

record of the substitution made under clauses 4.4.1 and clause 4.4.2 for 7

years and provide access to the record at reasonable times to the relevant

customer.

4.4.5. For the purposes of this clause 4.4, all references in the Metrology Procedure

to the responsible person are references to the person responsible for the

metering installation.

14

4.5. Calculation of Metering Data for Unmetered Connection Points

4.5.1. Where it has been determined that a connection point does not require a

meter in accordance with clause 2.3, the person responsible for the metering

installation must ensure that metering data for the unmetered connection

point is calculated in accordance with the distributor’s procedure which should

be based on a methodology in the Metrology Procedure. If the unmetered

connection point does not have a predictable load pattern, then the person

responsible for that metering data must have regard to the methodology in

the Metrology Procedure when calculating the metering data at such

connection points

4.5.2. The person responsible for the metering installation must ensure that the

metering data for an unmetered connection point, which is calculated in

accordance with 4.5.1, is validated in accordance with the distributor’s

procedure which should be based on a methodology in the Metrology

Procedure.

4.5.3. The person responsible for an unmetered connection point must ensure that

the metering data is substituted in accordance with the distributor’s

procedure, which should be based on a methodology in the Metrology

Procedure, where the metering data calculated for an unmetered connection

point fails the validation test conducted in accordance with paragraph 4.5.2.

4.6. Access to Metering Installation

4.6.1. The person responsible for the metering installation must give a customer

access to data stored in a metering installation used to measure and record

the amount of electricity supplied to its connection point, either by inspecting

the metering installation or, where available, by electronic access to the

metering installation.

4.6.2. The person responsible for the metering installation must, on request from a

customer or a customer’s retailer, provide the customer with access to the

energy data and the metering data in respect of the metering installation

which measures and records the amount of electricity supplied to the

connection point of the customer.

4.7. Storage of Metering Data

4.7.1. The person responsible for the metering installation must store metering data

in respect of each metering installation and metering data in respect of each

unmetered connection point, for a period of 7 years, in the form in which it

was collected under clause 4.3 or calculated under clause 4.5.

Electricity Metering Code

EMTC/08

15

4.8. Access to Metering Data

4.8.1. The person responsible for the metering installation must ensure that access

is provided to metering data (whether actual or substituted under clause 4.4

at the frequency agreed under clause 4.3.4(a)).

4.8.2. The format of metering data provided under clause 4.8.1 must be in

accordance with Schedule 4 reference 1.8 of Part A of the Metrology

Procedure,

4.8.3. For the purposes of this clause 4.8, all references in the Metrology Procedure

to:

(a) a Financially Responsible Market Participant are references to a retailer;

(b) “each metering installation for which the financially responsible

Market Participant has registered with AEMO” in Metrology Procedure

clause 3.8.1 are references to each metering installation associated with

a customer’s supply address; and

(c) type 7 metering installations are references to unmetered connection

points.

16

5. METERING DATA SERVICES FOR ALL CONNECTION POINTS

5.1. Application of Chapter 5

5.1.1. This chapter applies to metering installations at all connection points.

5.1.2. In this chapter the person responsible for the metering installation may be the

responsible person or the person responsible for the metering installation

determined in accordance with clause 2.2.1.

5.1.3. The obligations in this chapter in regard to metering installations at

connection points for responsible persons are in addition to the obligations for

responsible persons under the National Electricity Rules.

5.2. Collection of Metering Data

5.2.1. If a substitution is made to metering data, the person responsible for the

metering installation or the retailer must ensure that a bill issued to the

relevant customer informs that customer that a substitution has been made.

5.3. Access to data

5.3.1. Where a sample meter has been installed at a connection point by the

distributor, the person responsible for the metering installation must give a

customer access to the data stored in that sample meter as accumulated

energy data and not as interval energy data.

5.3.2. The person responsible for the metering installation must, on written request

from a customer, provide facilities to enable the customer to access data

stored in a metering installation by remote electronic means.

5.3.3. Where the person responsible for the metering installation has provided

facilities to enable the customer to access data stored in a metering

installation by remote electronic means, if remote electronic access to the

metering installation is unavailable for a period of 5 consecutive business days

due to the actions within the control of the person responsible for the

metering installation, the person responsible for the metering installation

must, if requested by the customer, obtain data locally from the metering

installation and provide that data to the customer at the person responsible

for the metering installation’s cost.

5.3.4. For connection points at which the annual electricity consumption level is less

than 160MWh per annum, the energy data or metering data provided to the

customer or the customer’s retailer must be provided within the timeframes

Electricity Metering Code

EMTC/08

17

to enable a retailer to discharge its minimum obligations under the National

Energy Retail Law.

5.4. Confidentiality

5.4.1. The distributor, a person responsible for the metering installation and

retailers must keep metering data confidential and use reasonable

endeavours to protect and preserve the confidential nature of the metering

data and must comply with any applicable regulatory instrument.

5.4.2. The distributor, the person responsible for the metering installation and

retailers:

(a) must not disclose a customer’s metering data to any person except as

permitted by this industry code, the National Electricity Rules or the

Metrology Procedure;

(b) must only use or reproduce a customer’s metering data for the purpose

for which it was collected under this industry code or another purpose

contemplated by any other code, the National Electricity Rules or the

Metrology Procedure;

(c) must not permit unauthorised persons to have access to a customer’s

metering data;

(d) must not disclose a customer’s metering data to any person without the

explicit informed consent of the customer; and

(e) must ensure that the metering data and other information obtained

from a customer is treated in accordance with the explicit informed

consent of the customer and in accordance with any applicable

regulatory instrument.

5.4.3. This clause 5.4 does not prevent:

(a) the disclosure, use or reproduction of metering data if the metering

data is at the time generally and publicly available otherwise then as a

result of breach of confidence by the distributor, a person responsible

for the metering installation or a retailer or its disclosees;

(b) the disclosure of metering data by the distributor, a person responsible

for the metering installation or a retailer or its disclosees to:

(i) its employees or the employees of its related bodies corporate

subject to any applicable regulatory instrument;

18

(ii) or its legal or other professional advisor, auditor or other

consultant, requiring the metering data for the purposes of this

industry code or any other code or for the purpose of advising the

distributor, the person responsible for the metering installation

or the retailer or disclosee in relation to those purposes;

(c) the disclosure, use or reproduction of metering data with the explicit

informed consent of the relevant customer;

(d) the disclosure, use or reproduction of metering data to the extent

required by law or by lawful requirement of:

(i) any government or governmental body, authority or agency

having jurisdiction over the distributor, a person responsible for

the metering installation or a retailer or its related bodies

corporate;

(ii) any stock exchange having jurisdiction over the distributor, a

person responsible for the metering installation or a retailer or its

related bodies corporate; or

(iii) the Commission;

(e) the disclosure, use or reproduction of metering data required in

connection with legal proceedings, arbitration, expert determination or

other dispute resolution mechanism under this industry code or any

other code, the National Electricity Rules or the Metrology Procedure;

(f) the disclosure, use or reproduction of metering data which is trivial in

nature;

(g) the disclosure use or reproduction of metering data required to protect

the safety of personnel or equipment; or

(h) the disclosure use or reproduction of metering data by or on behalf of

the distributor, the person responsible for the metering installation or a

retailer to the extent it is reasonably required in connection with the

distributor’s, the person responsible for the metering installation’s or

the retailer’s financing arrangements, investment in the distributor, the

person responsible for the metering installation or the retailer or

disposal of the distributor, the person responsible for the metering

installation or the retailer.

5.4.4. In the case of a disclosure under clause 5.4.3(b) and clause 5.4.3(h), the

distributor, a person responsible for the metering installation or the retailer

making the disclosure must inform the relevant disclosee of the confidentiality

Electricity Metering Code

EMTC/08

19

of the metering data and use reasonable endeavours to ensure that the

disclosee keeps the metering data confidential.

20

6. SCHEDULE: DEFINITIONS AND INTERPRETATION

6.1. Definitions

In this industry code:

“accumulation meter” means equipment capable of measuring and recording electricity supplied

to a connection point in periods in excess of a trading interval;

“accumulated energy data” means the data that results from the measurement of the flow of

electricity in a power conductor where the data represents a period in excess of a trading

interval. The measurement is carried out at a connection point;

“actual meter reading” means the physical collection of energy data by way of a scheduled

meter reading or a special meter reading and, in the case of an interval meter, includes the

collection of energy data by remote means;

“annual electricity consumption level” has the meaning given to that term in the Act;

“applicable regulatory instrument” means any Act or regulatory instrument made under an Act,

or regulatory instrument issued by the Commission, which applies to a distributor, a retailer or a

generator;

“Act” means the Electricity Act 1996;

“AEMO”) means the Australian Energy Market Operator A.C.N. 072 010 327, the company which

operates and administers the wholesale energy market in accordance with the National

Electricity Rules;

“Australian Standard” or “AS” means a standard published by the Standards Association of

Australia;

“business day” has the meaning given to that term in the National Energy Retail Law;

“child” means a person other than a parent who has or seeks supply from an embedded network,

and children has a corresponding meaning;

“Commission” means the Essential Services Commission established under the Essential Services

Commission Act 2002;

“connection point” means:

(a) the same meaning given to that term in the National Electricity Rules;

(b) the agreed point of supply established between an off grid distribution system and a

customer; and

(c) until a date notified by the Commission, for the purposes of this industry code, where

a distribution network is operated pursuant to an exemption from holding a licence,

the connection point is the agreed point of supply between the embedded network

operator and a Registered Participant, Non-Registered Customer or customer;

“current transformer” has the meaning given to that term in AS 1675;

“customer” has the meaning given to that term in the Act;

Electricity Metering Code

EMTC/08

21

“data logger” means a metering installation database or a device that collects electronic signals

from a measurement element, and packages it in to 30 minute intervals (or sub-multiples) this

device may contain data storage capability, be a separate item of equipment and/or be combined

with the energy measuring components within one physical cycle;

“defective” means:

(a) in relation to a new meter, that it is not meeting the minimum standards; and

(b) in relation to an existing meter, that it is not meeting the minimum standards of accuracy

that it was designed to meet;

“disclosee” means a person to whom a distributor or a retailer has disclosed or wishes to disclose

metering data;

“distributor” means a person holding a licence under the Act to operate a distribution network;

“distribution licence” means the licence issued to a distributor under the Act to operate a

distribution network;

“distribution system” means a system of electric lines and equipment used in connection with the

distribution of electricity, and includes connection assets;

“embedded network” means a distribution system to which an end-use customer is connected

and where the energy supplied to that end-use customer (the child) has also been registered by a

meter used to record the consumption of another end-use customer (the parent);

“energy data” means interval energy data or accumulated energy data;

“estimated energy data” means the data that results from an estimation of the flow of electricity

in a power conductor where the data applies to a trading interval or a period in excess of a

trading interval. The estimation is made in relation to a market load and would not apply to a

metering point, where accumulated energy data or interval energy data is not ordinarily

available;

“estimated read” means an estimate used in lieu of a meter reading;

“explicit informed consent” has the meaning given to that term in the National Energy Retail

Law;

“generator” means a person holding a licence under the Act to generate electricity;

“guideline” means a guideline published by the Commission;

“interval energy data” means the data that results from the measurement of the flow of

electricity in a power conductor where the data is prepared by a data logger into intervals which

correspond to a trading interval or a sub-multiple of a trading interval;

“interval meter” means a meter that records interval energy data;

“load” means a connection point or defined set of connection points at which electrical power is

delivered to a person or to another network or the amount of electrical power delivered at a

defined instant at a connection point, or aggregated over a defined set of connection points;

“market load” has the meaning given to that term in the National Electricity Rules.

22

“meter” means equipment to measure, record and, in certain cases, read records of the amount

of electricity (active energy and/or reactive energy) supplied through a customer’s connection

point;

“metering data” means the data obtained from a metering installation, the processed data or

substituted data;

“metering data services” means the collection and collation of energy data from the meter or

meter and associated data logger, the processing of the energy data in the metering installation

database, storage of the energy data in the metering installation database and the provision of

access to the data for those parties that have rights of access to the data;

“metering installation” means a meter together with current transformers and voltage

transformers, wiring and any computing or communications equipment designed to facilitate

electronic access;

“metering installation type 1” means a metering installation installed at a connection point

through which the annual electricity consumption level is greater than 1,000 GWh that meets the

requirements specified for type 1 metering installations in the National Electricity Rules;

“metering installation type 2” means a metering installation installed at a connection point

through which the annual electricity consumption level is equal to or greater than 100 GWh and

less than or equal to 1,000 GWh that meets the requirements specified for type 2 Metering

installations in the National Electricity Rules;

“metering installation type 3” means a metering installation installed at a connection point

through which the annual electricity consumption level is equal to or greater than 750MWh and

less than or equal to 100 GWh that meets the requirements specified for type 3 Metering

installations in the National Electricity Rules;

“metering installation type 4” means a metering installation installed at a connection point

through which the annual electricity consumption level is less than 750 MWh that meets the

requirements specified for type 4 Metering installations in the National Electricity Rules;

“metering installation type 5” means a metering installation installed at a connection point

through which the annual electricity consumption level is less than 160 MWh that meets the

requirements specified in for type 5 Metering installations in the National Electricity Rules;

“metering installation type 6” means a metering installation installed at a connection point

through which the annual electricity consumption level is less than 160 MWh that meets the

requirements specified for type 6 Metering installations in the National Electricity Rules;

“metering installation type 7” means a metering installation installed at a connection point that

meets the requirements specified for type 7 Metering installations in the National Electricity

Rules;

“metering provider” has the meaning given to that term in the National Electricity Rules;

“meter provision services” means the supply, installation and maintenance of metering

installations;

“metering services” means meter provision services and metering data services;

Electricity Metering Code

EMTC/08

23

“Metrology Procedure” means the Metrology Procedure, Parts A and B, published by AEMO

under the National Electricity Rules, as amended from time to time;

“minimum standards” means, in respect of relevant meters, the minimum standards referred to

in clause 2.7 in this industry code;

“MSATS” means AEMO’s Market Settlement and Transfer Solution system;

“National Energy Retail Law” has the meaning gien to that term in the National Energy Retail

Law (South Australia) Act 2011 as in force from time to time;

“National Energy Retail Regulations” means the Regulations made under Part 11 of the National

Energy Retail Law;

“National Energy Retail Rules” means the Rules made under Part 10 of the National Energy

Retail Law;

“National Electricity Rules” has the meaning given to that term in the National Electricity Law

referred to in the National Electricity (South Australia) Act 1996;

“National Metering Identifier” or “NMI” means a National Metering Identifier as described in

clause 7.3.1(d) of the National Electricity Rules;

“non-market generator” means a generator who has classified a generating unit as a “non-

market generating” unit as defined under the National Electricity Rules;

“off grid distribution system” means either a distribution system that is not connected to the

interconnected national electricity system as contemplated in the National Electricity Law or if the

distribution system is connected to the interconnected national electricity system then it is

exempt from the requirement of being a registered participant under clause 11(2)(b) of the

National Electricity Law set out in the Schedule to the National Electricity (South Australia) Act

1996.

“parent” means a person in an embedded network where the energy that passes through the

parent’s meter is apportioned to more than one end-use customer (child), and that

apportionment is made through the use of one or more children’s metering installations and the

parent’s metering installations;

“physical inventory” means a physical count of devices;

“rated current” has the meaning given to that term in AS 1284.9;

“related body corporate” means in relation to a body corporate, a body corporate that is related

to the first mentioned body by virtue of the Corporations Act 2000 (Cth);

“Responsible Person” has the meaning given to that term in the National Electricity Rules;

“retailer” means a person holding a licence under the Act or a retailer authorisation under the

National Energy Retail Law (as the case may be) for the sale of electricity;

“sample meter” means an interval meter that has been installed at a connection point for the

purpose of determining a controlled load profile under the Metrology Procedure;

“scheduled meter reading” means an actual meter reading on a cycle that equates to the end-

use customer’s billing cycle, usually monthly or quarterly;

24

“special meter reading” means an actual meter reading performed outside of the usual reading

cycle for the meter;

“supply address” means:

a) the address for which a customer purchases electricity from a retailer where there is only

one connection point at that address; or

b) where there is more than one connection point at the address, each connection point

through which the customer purchases electricity from the same retailer;

“trading interval” means a thirty minute period ending on the hour (EST) or on the half hour, and,

where identified by a time means the thirty minute period ending at that time;

“voltage transformer” has the meaning given to that term in AS 1243;

6.2. Interpretation

6.2.1. In this industry code, unless the context otherwise requires:

(a) headings and footnotes are for convenience or information only and

do not affect the interpretation of this industry code or of any term or

condition set out in this industry code;

(b) words importing the singular include the plural and vice versa;

(c) an expression importing a natural person includes any company,

partnership, trust, joint venture, association, corporation or other body

corporate and any governmental agency and vice versa;

(d) a reference to a clause or appendix is to a clause or appendix of this

industry code;

(e) a reference to any statute includes all statutes varying, consolidating,

re-enacting, extending or replacing them and a reference to a statute

includes all regulations, proclamations, ordinances, by-laws and

determinations issued under that statute;

(f) a reference to a document or a provision of a document includes an

amendment or supplement to, or replacement of or novation of, that

document or that provision of that document;

(g) a reference to a person includes that person’s executors,

administrators, successors, substitutes (including, without limitation,

persons taking by novation) and permitted assigns;

(h) other parts of speech and grammatical forms of a word or phrase

defined in this industry code have a corresponding meaning;

(i) a period of time:

(i) which dates from a given day or the day of an act or event is to

be calculated exclusive of that day; and

Electricity Metering Code

EMTC/08

25

(ii) which commences on a given day or the day or an act or event is

to be calculated inclusive of that day.

(j) a reference to:

(i) time in the National Electricity Market is a reference to the time

at the 150th meridian of longitude east of Greenwich in England,

or Co-ordinated Universal Time, as required by the National

Measurement Act (1960);

(ii) time, when not referring to the National Electricity Market, is a

reference to Standard Time within the meaning of the Daylight

Saving Act 1971 (SA) and not Summer Time within the meaning

of that Act;

(iii) a day is a reference to a period commencing immediately after

midnight and ending the following midnight; and

(iv) a month is a reference to a calendar month.

(k) an event which is required under any term or condition set out in this

industry code to occur on or by a stipulated day which is not a business

day, may occur on or by the next business day.

Electricity Metering Code

EMTC/08

1

The Essential Services Commission of South Australia Level 8, 50 Pirie Street Adelaide SA 5000 GPO Box 2605 Adelaide SA 5001 T 08 8463 4444 | F 08 8463 4449 E [email protected] | W www.escosa.sa.gov.au