Emergency planning

flooding response and

community resilience

Page 2: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

The team

• John Carter – Head of Service

• Graham Steady – Line Manager

• Jane Browning – Senior PPO, training and exercises

• Nick Bate – Senior PPO, welfare and community resilience

• Nick Bancroft – Senior PPO, business continuity & communications

• Caroline Parfitt – PPO, technical support.

Page 3: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Emergency planning role • Plan for, train, exercise and respond to emergencies which affect the

public, the environment and/or the security of the UK, including recovery.

• Covering: – Top tier hazardous sites – Flooding and reservoirs – Welfare issues – Communications – Business continuity – Community resilience – Public events – Fatalities and excess death

Page 4: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Programme

• Flood warnings – phone, email, pager • Duty engineer • Trigger levels • Operational, tactical, strategic plans • Recovery • LA incident officer • Incident room • Emergency planning co-ordinated sites • Community resilience

Page 5: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Flood warnings Emergency planning receives the following from the Environment Agency

• Pager – for alert, warning and severe flood warnings • Email • Text

From the Met Office:

• Email • Text

No action taken except watching brief unless warning or severe flood warning received.

Page 6: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Duty engineer

Liaison with duty engineer – on call – one number Benefits: • information from site from other operatives • links in to works team • important point of contact during flooding or during other

incident

Page 7: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Triggers

Red: High consequence – Plan active High level resources are required and multiple council services are required. • (risk of) loss of life • (risk of) damage to critical infrastructure • responders at full capacity. • further flooding anticipated

Green: Low consequence – Plan not activated This will result in the normal duty engineer response. • Local flooding, small geographical area, minimal risk to life and property Amber: Medium consequence – Plan (or sections thereof) activated The Duty Engineer will escalate the response above the normal level. • larger geographical area affected. • risk to life and property increased. • businesses affected. • critical infrastructure affected

Page 8: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Operational plans

• 20 operational plans for most at risk sites.

1. Salisbury 1988 11. Downton 157 2. Chippenham 633 12. Ashton Keynes 156 3. Melksham 408 13. Cricklade 149 4. Calne 306 14. Pewsey 133 5. Wilton 286 15. Dauntsey 96 6. Trowbridge 284 16. Tisbury 74 7. Warminster 277 17. Shrewton 70 8. Marlborough 271 18. Mere 64 9. B-on-A 228 19. Monkton Park 58 10. Malmesbury 177 20. Corsham 54

Page 9: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Tactical council plan

Emergency Planning will help co-ordinate the council response by taking the following actions as required: •Cascade information and call out •Co-ordinate command and control •Establish and oversee the council incident room •Establish and oversee rest centres •Establish centres relating to media, evacuations, etc •Assist with recovery as per the Wiltshire Council Recovery Plan •Contacting and activating Community Emergency Volunteers (CEVs) as required for their local knowledge.

Page 10: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Strategic Plan Local Resilience Forum Strategic flood plan for multi-agency response.

Multi-agency response will be started using the following trigger levels: • Receipt of a Red Flood Guidance

Statement for Wiltshire and/or Swindon • A total of five Flood Warnings for the

county of Wiltshire or Swindon • Receipt of one Severe Flood Warning • Surface Water Flooding – each agency to

have their own internal trigger points

Page 11: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Recovery The recovery phase is to: • to assist the community affected to return to normality • commence as soon as possible after the initial response.

The recovery plan outlines the structure and responsibilities for: • Strategic coordinating board • The tactical recovery groups • Operational recovery teams.

Page 12: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Local Authority Incident Officer

From Public Protection Service • Trained officer on 24 hour call out (activated by emergency planning) • Attends scene at operational (bronze) level • Liaises with emergency services • Reports back to emergency planning • Requests resources • Supplies information • Keep a log of actions.

Page 13: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

County incident room

• Opened for any major incident. • Opened whenever evacuation is

required over a certain scale. • Liaison centre for all agencies. • Information point for Rest Centres.

Page 14: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

Emergency planning co-ordinated sites

Beyond cordons • Rest Centres • Humanitarian Assistance Centres • County Incident Room • Media Centre • Emergency Mortuary

Page 15: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using

• Community Emergency Volunteers (CEVs) • Flood Wardens • Parish plans • Community Area Boards - 18 • Exercises

Community Resilience

Page 16: Emergency planning flooding response and community resilience · Local Resilience Forum Strategic flood plan for multi -agency response. Multi-agency response will be started using