Page 1: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

EN50549-1 EN50549-2 Intent & Scope COMPILED BY THOMAS SCHAUPP ( K ACO newenergy )

PRESENTED TO 9 TH ACER GR ID CONNECTION ESC

CENELEC TC8X AHG

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 1

Page 2: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

EN 50549-1: Requirements for generating plants to be connected in parallel with distribution networks - Part 1: Connection to a LV distribution network – Generating plants up to and including Type B EN 50549-2: Requirements for generating plants to be connected in parallel with distribution networks - Part 2: Connection to a MV distribution network – Generating plants up to and including Type B

COMPILED BY THOMAS SCHAUPP ( K ACO newenergy )

PRESENTED TO 9 TH ACER GR ID CONNECTION ESC

CENELEC TC8X AHG

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 2

Page 3: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

AGENDA 1 Intent, Framework and Scope

2 Correspondence RfG – EN 50549

3 How can EN 50549 support RfG implementation in a member state

4 Conclusion

A1 Question regarding definition of “new power-generation module“

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 3

Page 4: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

Please keep in mind

2018-01-31 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 4

Directive 714/2009 8(7)

As issues regarding cross border trade of electricity are covered in RfG, topics not covered in RfG are, on a legal perspective, not understood as affecting cross border trade of electricity.

Page 5: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

European foreword of EN 50549-1 and EN 50549-2

This European Standard relates to both the RfG European Network Code and current technical market needs. Its purpose is to give detailed description of functions to be implemented in products.

This European Standard is also intended to serve as a technical reference for the definition of national requirements where the RfG European Network Code requirements allow flexible implementation.

Intent

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 5

Page 6: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

Updated Planning EN 50549-1; -2

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 6

Today

Jun

-17

Jul-

17

Au

g-1

7

Sep

-17

Oct

-17

No

v-1

7

De

c-1

7

Jan

-18

Feb

-18

Mar

-18

Ap

r-1

8

May

-18

Jun

-18

Jul-

18

Au

g-1

8

Sep

-18

Oct

-18

No

v-1

8

De

c-1

8

Jan

-19

Feb

-19

Mar

-19

Ap

r-1

9

May

-19

Jun

-19

Jul-

19

CENELEC Schedule

Enquiry (3m)

Dealing with comments form NC's

CCMC editing and translation (3m) 1

Voting by NC's (2m) 7 11

Voting result 15

Final editorial review by CCMC

EN publishing

Certifiers

Manufacturers and Certifiers preperation time

NC RfG regulatory Schedule

Submission proposals (FTR, Gen Req, Type limits) (May17th) 17

Decision competent Authorities (Nov 17th) 17

Apllication NC RfG (May 17th) 17

Page 7: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

EN 50549 is written to be compliant and used in conjunction with COMMISSION REGULATION 2016/631 (RfG)

EN 50549-1 and -2 cover all technical (essential) requirements (Title II) of RfG applicable for type A and type B generating modules and as such will support technical requirements of RfG

EN 50549-10 (in development) will cover tests to provide compliance with requirements of part 1 and part 2 and as such will support the compliance procedures (Title IV) of RfG

EN 50549 series does not address

general requirements and type thresholds (Title I)

procedures (Title III)

derogation, classification as emerging technology (Title V to VII)

Framework and Scope

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 7

Page 8: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

All RfG articles of Title II relevant for type A and type B generating modules correspond to clauses in EN 50549 part 1 and 2

EN 50549 clauses provide requirements being

detailed

exact

verifiable

standardized applicable all over Europe

EN 50549-1 and -2 clauses provide configurability of functions to allow all flexibility of RfG by maintaining verifiability

EN 50549-10 clauses will support conformity assessment to provide evidence of conformity

Framework and Scope

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 8

Page 9: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

EN 50549 intends to include all capabilities of generating plants necessary to operate generating plants in parallel to distribution grids

Therefore EN 50549-1 and -2 provides requirements needed for distribution grid management which are beyond the scope of RfG:

Connection scheme and coordination of switch gear,

voltage operation range (for type A and B),

reactive power capabilities and control modes (for type A and B),

interface protection (for type A and B) and anti-islanding function,

generation curtailment,

requirements to electrical energy storage systems (EESS),

requirements to generating plants below 800 W.

Framework and Scope

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 9

Page 10: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

EN 50549 intends to include all capabilities of generating plants necessary to operate generating plants in parallel to distribution grids

Therefore EN 50549-1 and -2 provides requirements needed for the stability of the interconnected system not yet included in RfG:

Robustness to voltage swells (OVRT),

Robustness to voltage sags (UVRT),

Recommended also for type A generators,

LFSM-U requirement,

explicitly required for EESS (Electrical Energy Storage Systems),

recommended for all other generating modules.

Framework and Scope

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 10

Page 11: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

EN 50549-1 and -2 scope excludes aspects of system integration:

Selection of point of connection,

power system impact assessment e.g. assessment of effects on power quality, local voltage increase, impact on line protections operation,

connection assessment, the set of technical verifications made as part of the planning of the connection.

These issues depend on the structure of the distribution grid and the management procedures of the DSO.

Framework and Scope

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 11

Page 12: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

AGENDA 1 Intent, Framework and Scope

2 Correspondence RfG - EN50549

3 How can EN 50549 support RfG implementation in a member state

4 Conclusion

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 12

Page 13: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

Annex C and H provide an overview over all described functions and the relevance in view of RfG

Annex C

lists all parameters providing flexibility in the clauses and typical ranges,

might be used as a template to publish national parameters.

Annex H

is structured similar to a CENELEC Annex ZZ,

provides a clear overview which Articles of RfG are covered in the Standard.

Generating plants compliant with the clauses of this European Standard are considered to be compliant with the relevant Article of COMMISSION REGULATION (EU) 2016/631, provided, that all settings as provided by the DSO and the responsible party are complied with.

Correspondence RfG – EN50549

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 13

Page 14: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

Annex H provides a clear overview which Articles of RfG are covered in the Standard

Correspondence RfG – EN 50549

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 14

Article

Clause(s) / subclause(s)

of this EN

13.1(a) 4.4.2 Operating frequency range

13.1(b) 4.5.2 Rate of change of frequency (ROCOF) immunity

13.2 4.6.1 Power response to overfrequency

13.3

4.4.3 Minimal requirement for active power delivery at

underfrequency

13.4

4.4.3 Minimal requirement for active power delivery at

underfrequency

13.5

4.4.3 Minimal requirement for active power delivery at

underfrequency

….. …..

Page 15: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

Correspondence RfG – EN50549

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 15

Article Clause(s) / subclause(s)

of this EN

13.1(a) 4.4.2 Operating frequency range

13.1(b) 4.5.2 Rate of change of frequency (ROCOF) immunity

13.2 4.6.1 Power response to overfrequency

13.3 4.4.3 Minimal requirement for active power delivery at underfrequency

13.4 4.4.3 Minimal requirement for active power delivery at underfrequency

13.5 4.4.3 Minimal requirement for active power delivery at underfrequency

13.6 4.11.1 Ceasing active power

13.7 4.10 Connection and starting to generate electrical power

14.1 4.4.2, 4.5.2, 4.6.1, 4.4.3, 4.11.1 and 4.10

14.2(a) 4.11.2 Reduction of active power on set point

14.2(b) 4.12 Remote information exchange

14.3 4.5.3 Under-voltage ride through (UVRT)

14.4. 4.10 Connection and starting to generate electrical power

14.5(a) 4.6, 4.7, 4.9, 4.10, 4.11, 4.12

14.5(b) 4.9 Interface protection,

14.5(c) 4.1 General

14.5(d) 4.12 Remote information exchange

17.1 4. as applicable above

17.2 4.7.2 Voltage support by reactive power

17.3 4.5.3 Under-voltage ride through (UVRT)

20.1 4. as applicable above

20.2 (a) 4.7.2 Voltage support by reactive power

20.2 (b) (c) 4.7.4.2 Short circuit current requirements on generating plants

20.3 4.5.3 Under-voltage ride through (UVRT)

Page 16: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

How does EN 50549 clauses provide configurability of functions to allow all flexibility of RfG by maintaining verifiability

Example Clause 4.5.2, corresponding to Article 13. 1(b)

With regard to ROCOF withstand capability a power generating module shall be capable of staying connected to the network and operate at ROCOF up to a value as specified by the relevant TSO,…

The generating modules in a generating plant shall have ROCOF immunity for a ROCOF equal or exceeding the value specified by the responsible party. If no ROCOF immunity value is specified, the following ROCOF immunity shall apply, making distinction between generating technologies:

Non-synchronous generating technology: at least 2 Hz/s

Synchronous generating technology: at least 1 Hz/s

The ROCOF immunity is defined with a sliding measurement window of 500 ms.

Correspondence RfG – EN50549

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 16

Page 17: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

How does EN 50549 clauses provide additional detail

Example Clause 4.11.2, corresponding to Article 14. 2(a)

To control active power output, the power generating module shall be equipped with an interface in order to be able to reduce active power output following an instruction at this input port.

Clause 4.11.2 Reduction of active power on set point provides further details:

Handling of minimum regulation level,

definition of adjustment increment at least 10%,

definition of a response envelop, response shall not be too fast, nor too slow,

definition of a required steady state accuracy.

Additional detail is necessary to design products and to provide conformity with the requirement.

Correspondence RfG – EN50549

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 17

Page 18: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

AGENDA 1 Intent, Framework and Scope

2 Correspondence RfG - EN50549

3 How can EN 50549 support RfG implementation in a member state

4 Conclusion

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 18

Page 19: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

Generating plants of type A and type B are mass market products

Example: In Germany more than 1,6 Million PV plants have been installed within the last 15 years.

Standardised

Requirements and

Compliance procedures are of high importance

to support efficient procedures for

generating unit manufactures,

generating plant developers,

distribution system operators.

How can EN 50549 support RfG implementation in a member state

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 19

Page 20: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

RfG does not foresee the support of harmonized standards, unlike regulations under the new approach

support to RfG depends on national implementation.

EN 50549 is the tool,

To become effective, the member state has to use it.

How can EN 50549 support RfG implementation in a member state

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 20

Page 21: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

EN 50549 is applicable for type A and B generating modules (mass market)

EN 50549-1 and -2 support the essential requirements of RfG (Title II)

EN 50549 -1 and -2 can be used as reference documents for the national implementation

EN 50549 -1 and -2 can be referenced by national documents clause by clause or as complete standard

If needed, parameters can be specified according RfG and used in EN 50549

Annex C can be used as template to publish national specification of non-exhaustive requirements

EN 50549-10 will support compliance process once in place

How can EN 50549 support RfG implementation in a member state

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 21

Page 22: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

AGENDA 1 Intent, Framework and Scope

2 Correspondence RfG - EN50549

3 How can EN 50549 support RfG implementation in a member state

4 Conclusion

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 22

Page 23: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

EN 50549 is written to be compliant and used in conjunction with COMMISSION REGULATION 2016/631 (RfG).

EN 50549-1 and -2 cover all technical (essential) requirements (Title II) of RfG applicable for type A and type B generating modules and as such will support technical requirements of RfG.

EN 50549 intends to include all capabilities of generating plants necessary to operate generating plants in parallel to distribution grids, therefore goes beyond the scope of RfG.

As RfG does not foresee the support of harmonized standards, support to RfG depends on national implementation of RfG.

EN 50549 -1 and -2 can be used as reference documents for the national implementation.

Conclusion

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 23

Page 24: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

AGENDA 1 Intent, Framework and Scope

2 Correspondence RfG - EN50549

3 How can EN 50549 support RfG implementation in a member state

4 Conclusion

A1 Question regarding definition of “new power-generation module“

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 24

Page 25: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

RfG Article 7(4) requires relevant TSOs to submit a proposal for requirements two years after the entry into force, May 17th 2018.

RfG Article 7(6) requires the competent entities to decide upon the proposal within 6 month resulting in November 17th 2018.

As a consequence, connection requirements will be, in general, available following Nov. 17th 2018

Question regarding definition of “new power-generation module“

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 25

Page 26: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

RfG Article 3(1) requires all new power-generation modules to be compliant with RfG

RfG Article 4(2)(b) defines that a generating module shall be considered “existing” if the “main generating plant” has been purchased (binding contract) two years after entry into force of RfG, resulting in May 17th 2018

Some mass market technologies have only several weeks between conclusion of a binding contract and commissioning of the plant.

Typical main components such as inverter or uCHP units are on stock even before a binding contract is concluded.

As a consequence, first “new” power generating plants will be connected in June 2018, 5 moths before the connection requirements must be decided upon.

These power generating plants need to be updated before May 17th 2019

Question regarding definition of “new power-generation module“

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 26

Page 27: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

Possible solutions:

RfG Article 4(2)(b) last paragraph states:

A Member State may provide that in specified circumstances the regulatory authority may determine whether the power-generating module is to be considered an existing power-generating module or a new power-generating module.

Some member states use this statement to define existing power generating modules as:

Generators that have presented a complete request for connection to DSO before May 2019

Generators whose Power-Generating Module(s) was already connected to the DNO’s Distribution Network before May 17th 2019

Member states not having decided upon requirements until today should consider similar solutions.

Question regarding definition of “new power-generation module“

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 27

Page 28: EN50549-1 EN50549-2 Intent & Scope...AGENDA 1 Intent, Framework and Scope 2 Correspondence RfG – EN 50549 3 How can EN 50549 support RfG implementation in a member state 4 Conclusion

Thank you for your attention.

Conclusion

2018-03-08 EN 50549 INTENT AND SCOPE THOMAS SCHAUPP / KACO NEW ENERGY 28