ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio Isobo Tariah

Upload: others

Post on 11-Mar-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

ENCE 667Project Performance

MeasurementPatuxent Water Treatment Plant

Upgrade schedule analysis

Presented by:Luis Rubio

Isobo Tariah

Page 2: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Overview

• Location: Laurel, Maryland• Total Cost: $45 million• Capacity: 56 MGD• Owner: Washington Suburban Sanitary

Commission• Contractor: Danis Environmental

Industries• Phases: Stage I & Stage II

Page 3: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Stage I• Demolition of Filter Unit 1• Construction of 3 treatment trains

– Flocculation Basin– Sedimentation Basin– Chlorine contact chamber– Deep bed filters– Backwash tank– Chemical feed system

• Duration: 385 working days

Page 4: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Stage I Existing Filter Unit

Page 5: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Stage I Demolition of Filter Unit

Page 6: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Stage I Construction of new process structure

Page 7: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Stage II

• Demolition of Filter Unit 2, 3 & 4• Construction of 2 treatment trains

– Flocculation Basin– Sedimentation Basin– Chlorine contact chamber– Deep bed filters– Backwash tank– Chemical feed system

• Duration: 650 working days

Page 8: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Purpose of the Upgrade• Save $24 Million using High-rate

processes– Static Mixers for rapid mixing– Four-stage tapered-energy flocculation

shaft– Sedimentation plate settlers– Granular activated carbon– Sand filters with air backwash

• Capable to run at 72-80 MGD in emergency situation

Page 9: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Objectives

• To complete Stage I at the minimum time/cost tradeoff.– Develop a CPM schedule– Determine Critical Path– Crash activities in the critical path– Estimate cost associated with crashing

Page 10: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Performance Measurement Concepts Used

• CPM Schedule• Gantt Chart• Linear Programming

– Minimize project cost – Obtain optimal crashing time

• Time/Cost trade-off curve

Page 11: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project ActivitiesID Task Name Duration Predecessors3 Mobilization 10 -4 Process Testing 5 557 Soil Erosion Control 10 38 Install temp 16" Hs Line 8 711 Excavation for new treatment trains 15 2928 Shut down existing filter unit #1 4 829 Demolish existing filter unit #1 36 2831 Flocculation bsin bsae slab 27 1132 Sedimentation basin base slab 29 3133 Chlorine contct chamber base slab 28 3234 Filter / Filter gallery base slab 43 3338 Filter / Filter gallery lower slab 50 3445 Filtr control gallery slab 12 3847 Backwash tank slab 20 4848 Backwash tank walls 10 4555 Process tank water-lear test 5 8174 Install backwash drain valve 6 7979 Install backwash piping 30 4781 Install Control System / Electrical rough-in 90 74

Page 12: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Schedule

Page 13: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

AOA Diagram Original

ST A B C D E

I J K L H

G F

M N O

P Q R END

103 7 8 28 29 11 31

33 34 38 45 48 47 79

32

74

81 55 4

10 8 4 36 15 27

29

28 43 50 12 10 20 30

6

5 590

0 0 10 10 2020 28 28 32 32 6868 83 83 110 110

139 139 167 167 210 210 260 260 272 272 282 282 302 302 332 332

338338 428 428 433 433 438 438

Page 14: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Crashing

• Estimated duration: 438 days• Contractual required date: 385 days• Difference: 53 days• Penalty: $12,775 per day• Bonus: $4,000 per day

Page 15: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Crashing

ActivityOriginal Duration

Max. Crash duration

Cost per crash unit

3 10 2 8,000.00$ 4 5 1 5,500.00$ 7 10 1 8,000.00$ 8 8 3 13,500.00$

11 15 3 16,800.00$ 28 4 0 12,000.00$ 29 36 5 14,500.00$ 31 27 5 7,500.00$ 32 29 5 14,000.00$ 33 28 2 5,000.00$ 34 43 8 13,500.00$ 38 50 9 15,850.00$ 45 12 1 10,000.00$ 47 20 3 5,500.00$ 48 10 1 4,000.00$ 55 5 1 9,500.00$ 74 6 1 11,500.00$ 79 30 4 7,500.00$ 81 90 10 10,000.00$

Page 16: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Penalty/Bonus

$(100,000)

$-

$100,000

$200,000

$300,000

$400,000

$500,000

$600,000

$700,000

373 378 383 388 393 398 403 408 413 418 423 428 433 438

Duration

Cos

t

Penalty / Bonus

$268,275

406

Page 17: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Crashing Cost

$-

$100,000

$200,000

$300,000

$400,000

$500,000

$600,000

$700,000

$800,000

373 378 383 388 393 398 403 408 413 418 423 428 433 438

Duration

Cost

Crashing Cost

$258,500

406

Page 18: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Crashing For optimal duration (406 days)

ActivityOriginal Duration

Max. Crash duration

Crash duration

Cost per crash unit Crashing Cost

3 10 2 2 8,000.00$ 16,000.00$ 4 5 1 1 5,500.00$ 5,500.00$ 7 10 1 1 8,000.00$ 8,000.00$ 8 8 3 13,500.00$ -$

11 15 3 16,800.00$ -$ 28 4 0 12,000.00$ -$ 29 36 5 14,500.00$ -$ 31 27 5 5 7,500.00$ 37,500.00$ 32 29 5 14,000.00$ -$ 33 28 2 2 5,000.00$ 10,000.00$ 34 43 8 13,500.00$ -$ 38 50 9 15,850.00$ -$ 45 12 1 1 10,000.00$ 10,000.00$ 47 20 3 3 5,500.00$ 16,500.00$ 48 10 1 1 4,000.00$ 4,000.00$ 55 5 1 1 9,500.00$ 9,500.00$ 74 6 1 1 11,500.00$ 11,500.00$ 79 30 4 4 7,500.00$ 30,000.00$ 81 90 10 10 10,000.00$ 100,000.00$

Total 438 65 32 258,500.00$

Page 19: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Sensitivity Analysis

$500,000

$550,000

$600,000

$650,000

$700,000

$750,000

373 378 383 388 393 398 403 408 413 418 423 428 433 438

Duration

Tota

l Cos

t

Total Cost

$526,775

406

Total cost = Crashing Cost + Penalty/Bonus

Total cost = $258,500 + $268,275 = $526,775

Page 20: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

AOA Diagram Original – Crashed

ST A B C D E

I J K L H

G F

M N O

P Q R END

83 7 8 28 29 11 31

33 34 38 45 48 47 79

32

74

81 55 4

9 8 4 36 15 22

29

26 43 50 11 9 17 26

5

4 480

0 0 8 8 1717 25 25 29 29 6565 80 80 102 102

131 131 157 157 200 200 250 250 261 261 270 270 287 287 313 313

318318 398 398 402 402 406 406

Page 21: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Schedule Alternative

• Some activities relations were changed in order to have parallel activities.

• Possible changes in the critical path.• Estimated duration should decrease.• Crashing: 53 days less than the

estimated duration.

Page 22: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Schedule

Page 23: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

AOA Diagram Alternative

ST A

B

C

D

E G

H

I

J

F

K M

103 7

8 28

29

11 31

33

34

38

45 48

47

79

32

7481 55 4

10

8 4

36

15 27

29 28

43

50

12 10

20

30

6 5 590

L

O END N

0 0 10 10 2222 6464 93 93 121 121

164 164

176 176 264 264

214 214 234234 324324 330330 335335 340 340

Page 24: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Crashing For contractual date (287 days)

ActivityOriginal Duration

Max. Crash duration

Crash duration

Cost per crash unit Crashing Cost

3 10 2 2 8,000.00$ 16,000.00$ 4 5 1 1 5,500.00$ 5,500.00$ 7 10 1 1 8,000.00$ 8,000.00$ 8 8 3 3 13,500.00$ 40,500.00$

11 15 3 3 16,800.00$ 50,400.00$ 28 4 0 12,000.00$ -$ 29 36 5 2 14,500.00$ 29,000.00$ 31 27 5 5 7,500.00$ 37,500.00$ 32 29 5 5 14,000.00$ 70,000.00$ 33 28 2 2 5,000.00$ 10,000.00$ 34 43 8 8 13,500.00$ 108,000.00$ 38 50 9 9 15,850.00$ 142,650.00$ 45 12 1 10,000.00$ -$ 47 20 3 3 5,500.00$ 16,500.00$ 48 10 1 4,000.00$ -$ 55 5 1 1 9,500.00$ 9,500.00$ 74 6 1 1 11,500.00$ 11,500.00$ 79 30 4 7,500.00$ -$ 81 90 10 10 10,000.00$ 100,000.00$

Total 56 655,050.00$

Contractual date = Estimated duration - 53 days = 287 days

Page 25: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Penalty/Bonus

$-

$100,000

$200,000

$300,000

$400,000

$500,000

$600,000

$700,000

$800,000

287 292 297 302 307 312 317 322 327 332 337

Duration

Cos

t

Penalty / Bonus

$357,700

315

Page 26: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Crashing Cost

$-

$100,000

$200,000

$300,000

$400,000

$500,000

$600,000

$700,000

287 292 297 302 307 312 317 322 327 332 337

Duration

Cost

Crashing Cost

$206,500

315

Page 27: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Sensitivity Analysis

$550,000

$575,000

$600,000

$625,000

$650,000

$675,000

$700,000

287 292 297 302 307 312 317 322 327 332 337

Duration

Tota

l Cos

t

Total Cost

$564,200

Total cost = Crashing Cost + Penalty/Bonus

Total cost = $206,500 + $357,700 = $564,200

315

Page 28: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Project Crashing For optimal duration (315 days)

ActivityOriginal Duration

Max. Crash duration

Crash duration

Cost per crash unit Crashing Cost

3 10 2 2 8,000.00$ 16,000.00$ 4 5 1 1 5,500.00$ 5,500.00$ 7 10 1 8,000.00$ -$ 8 8 3 13,500.00$ -$

11 15 3 16,800.00$ -$ 28 4 0 12,000.00$ -$ 29 36 5 14,500.00$ -$ 31 27 5 5 7,500.00$ 37,500.00$ 32 29 5 14,000.00$ -$ 33 28 2 2 5,000.00$ 10,000.00$ 34 43 8 13,500.00$ -$ 38 50 9 15,850.00$ -$ 45 12 1 10,000.00$ -$ 47 20 3 3 5,500.00$ 16,500.00$ 48 10 1 4,000.00$ -$ 55 5 1 1 9,500.00$ 9,500.00$ 74 6 1 1 11,500.00$ 11,500.00$ 79 30 4 7,500.00$ -$ 81 90 10 10 10,000.00$ 100,000.00$

Total 25 206,500.00$

Page 29: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

AOA Diagram Alternative – Crashed

ST A

B

C

D

E G

H

I

J

F

K M

83 7

8 28

29

11 31

33

34

38

45 48

47

79

32

7481 55 4

10

8 4

36

15 22

29 26

43

50

12 10

17

30

5 4 480

L

O END

N

0 0 8 8 2020

16 16 35 35

57 57 86 86 112 112

155 155

167 195 252 302

205 205 222222 302302 307307 311 311 316 316

Page 30: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Conclusions

• Optimal duration should be 406 days– Cost: $526,775

• When estimating the project bid, scheduling analysis should be perform to evaluate the necessity of crashing the project. If that is the case, the cost should be included in the bid.

Page 31: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Future Extensions

• PERT Analysis

• Limited resources allocation

Page 32: ENCE 667 Project Performance Measurement · ENCE 667 Project Performance Measurement Patuxent Water Treatment Plant Upgrade schedule analysis Presented by: Luis Rubio ... Total cost

Questions