energy audit report · web viewpetroleum conservation research association, eastern region...
TRANSCRIPT
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
ACKNOWLEDGEMENT
Petroleum Conservation Research Association, Eastern Region (PCRA, ER), appreciates the interest, participation and collaboration by the management & engineers of the Oil India Limited (OIL) in carrying out Energy Audit at “Oil Collecting Station-Makum ( Makum OCS) in Tinsukia Districtin in upper Assam. Our special thanks to the Installation Manager and his team of Engineers, Supervisors and technicians involved for Makum OCS, who have extended their co-operation and courtesy to the energy audit team during the audit.
Petroleum Conservation Research Association, Eastern Region (PCRA, ER) appreciates the interest,
participation and support by the Management, Staff-members, Medical Administrators and Engineers of
M/s Oil India Limited (OIL) during the tenure of the field exercises, vis-à-vis, the Energy Audit, conducted
at Makum Oil Collecting Station during the period 07.08.14 – 10.08.14. Period of Audit: 07.08.2014 to
10.08.2014
We want to put on record our thankfulness to the Administration of Technical Audit, OIL, Duliajan and
Field Engineers and Technical Staff Members, attached with Oil Collecting Station, Makum, which have
been extended during the observation of facilities and measurement of field data during the period.
Our sincere thanks and gratitude are also to be put on record for the Management and Auditors of M/s
Oil India Limited, Department of Technical Audit, for their initiative for the audit and the support and
cooperation, received during the data collection, liaison and availability of necessary documents
required for the field exercises.
Finally, special thanks are due to all members of the Audit team for their planning, field data collection,
and all sorts of related exercises.The Audit team comprising the following team member from OIL and
PCRA ER are as stated below:
The Energy Audit Team for Makum Oil Collecting Station :Station:
On behalf of M/s Oil India Limited On behalf of M/s Petroleum Conservation .
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 1
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Research Ass.ociation
Er. Ranen Mandal, Chief Manager- tech. Audit
Er. Debabrata Tamuly, Installation Manager,
Makum OCS
Er. Kishore Deka, Sr. Tech. Auditor
Mr. Ranen Mandal, Chief Manager- Tech. Audit
Mr. Debabrata Tamuly, Inst. Manager, Makum OCS
Mr. Kishore Deka, Sr. Tech. Auditor
Mr. Pranab Dutta, Tech. Auditor
Er. Abhijit Chanda, Addl. Director, PCRA
Er. Dabasis Ransingh, Jt. Director, PCRA
Mr. Abhijit Chanda, Addl. Director, PCRA
Mr. Dabasis Ransingh, Jt. Director, PCRA
ErMr. Subrata Sanyal, Certified Energy Auditor
INDEX
Chapter Title Page
1.0 Executive Summaery 3
2.0 SummerySummary of Savings Potential 4
3.0 Introduction to the Report 6
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 2
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
4.0 Scope of Work 9
5.0 Methodology of the Audit 10
6.0 Present Energy Scenario 12
7.0 Study of Electrical Power Consumption 15
8.0 Study of Pumps 18
9.0 Study of Electric Motors 23
10.0 Study of Air Compressor 25
11.0 Study of Performance & Efficiency of Gas Engines 27
12.0 Study of Crude Oil/ Natural Gas Consumption 30
13.0 Study of Illumination 33
14.0 General Observations of the Audit 35
15.0 Notes & Conclusion
Annexur
e
A1 Line Diagram of Material Flow
A2 List of Energy Efficient Equipment Suppliers
EXECUTIVE SUMMARY
1.1.1 Major Recommendations and Savings potentials :
Short and Medium Terms :Terms:
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 3
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Recommendations Savings per Annum Estimated Investment (Rs.)
Simple pay backpayback periodkKWHrh/Cum Rs.
Savings of Natural Gas by running 125 KVA Gen. Set through-out the day
3,50,400 m3 22,70,592.00 Nil Immediate
By By iimproving the efficiency and flow rate of COD Pumps #1,2& 3
1,36,129 m3 9,12,113.00 Nil Immediate
By By mmaintenance of valves (#5) & increasing speed (#6)
63,773 m3 4,13,249.00 Nil Immediate
By By iimproving efficiency and flow-rate of F.W. pumps
1,43,631 KWHrkWh
6,53,521.00 Nil Immediate
By By oover-hauling of Booster pumps, running hours be reduced
18,746 KWHrkWh
85,294.00 Nil Immediate
By changing consumption pattern of gas by installing compressor to convert 10 psi to 30 psi
21,90,000 m3 1,41,91,200.00 2,37,12,300.00 1 year 8 months
By replacing fluorescent Tube lamps by T-5 lamps
6,407.94 KWHrkWh
29,156.00 32,494.00 13 months
[1.1.2] Medium / Long Terms :Terms:
[1.1.3] No recommendation
Energy metering for measuring the different types of utility i.e. electrical, crude oil, natural gas,
water to be installed at the installation for effective utilization of energy.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 4
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
SUMMARY OF SAVINGS POTENTIAL
Maximize the use of 125KVA Run only 125 KVA Generator Set through-out the day, in place of
250 KVA generatorgenerator in the night. It will improver the loading on the generator, improve
its electrical parameters.
and reduce the load of utility attached with 250 KVA generator.
Adjust the running speed of gas-engines, attached with Crude Oil Disposal Pumps by adjusting
the governors. It will increase the lives durability of the engines.
Over-hauling of Crude Oil Disposal Pumps is solicited need to improve the efficiency and flow-
rate. The total running hours of the pumps will thus be reduced substantially. At present, the
flow rate is around 67% of the rated flow. The actual flow-rate is desired to be improved to 80%
of the rated.
Replacement of suction and delivery valves of Crude Oil Disposal Pumps is solicited along with
increasing of engine #6 speed to 1500 RPM by adjusting the governor. The flow rates/ hour will
be increased, along with reduction of fuel consumption at engine for same rate of delivery.
Over-hauling of Formation Water Pumps is urgently required to increase the flow rate and water
leakage. Actual working hours for the pump to complete the task will be substantially reduced.
Over-hauling of Booster pumps is required to reduce the running hours and to increase the flow.
Present pattern of usage of natural gas at 30 PSI and 10 PSI needs to be revisited. The present
level of flaring should be reduced by utilizing them for internal purpose of feed to the grid with
the compression at 3rd . party level.
Crude oil leakage at Crude oil Despatch (COD) Pump should be investigated and
checkedarrested.
Illumination inside the compound and at operation sheds to be increased, either by replacing
faulty fittings or adding new fittings.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 5
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Existing 36 watts Fluorescent Tube Lamps are to be replaced by T-5f energy saving efficient
fittings.
Meter facility to be incorporated at strategic levels to have regular checks and thereby, to take
appropriate measures, as required.
Operation log-book is to be maintained at operation level, namely, generator set, gas engine,
etc.
S ummary of above Efficiency Measures
Items Actions Remarkssults
125 KVA Gen Set to in p l ace of 250 KVA Gen Set
Load can be taken drawn by 125 KVA Gen set
-Improve the loading of Gen set - Improve its electrical parameters - Reduced the load of on attached with 2 2 50 KVA Genset
COD – Pumps Overhauling of pumps & crude oil leakage to be arrested
- Improve the efficiency - - flow rate- Flow rate is around 67% whereas actionual
at flow rate is desired to be 80%Suction & deliver valves
Replacement of valves & increasing the speed of engine # 6 to 1500 RPM
Flow rate / hour will increased
F.W pumps + Booster pumps
Over-hauling - Actual working hours will reduced
30 PSI & 10 PSI Gas Present pattern of Natural Gas to revisit
- To utilized them for internal purpose ofand fueedel to the gas grid on boosting
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 6
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Illumination By replacing the faulty fittings or Add new light fittings
- For improving the Illumination to desired lev a e l
36 Wat FTL Replaced with TS5 energy saving fittings
- Save energy
Meter facility
&
Operation L og-book
-Energy Meter to be fitted
- Operation Log-book to be maintained
- For regular checkmonitoring
- For taking appropriate action in future
- Monitoring operating data Log-book s s pecially for Gen Set, Gas Engine etc.
INTRODUCTION TO THE REPORT
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 7
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
[3.1] M/s Oil India Limited is the oldest oil exploration activities in India, starting from the inception of
digging for crude oil in 1889. Before the independence of the country, all activities were a private
initiative, rechristened into a public-private initiated under the present nomenclature, since the
establishment of M/s Oil India Limited in 1959, in collaboration of M/s British Oil Co. Ltd. The
Government of India bought back entire stake of the private company in 1981, leading the Company
to be the largest government initiative in this endeavour in north-eastern part of the country.
[3.2] M/s Oil India Limited (OIL), at present, is engaged in exploration of crude oil and natural gas in
north-east India, along with new ventures in the states of Rajasthan, Odisha, Andhra Pradesh,
Andaman and Gujarat.
[3.3] At present, there are 189 oil wells under OIL, spread over north-eastern India, mainly catering to
the crude oil exploration. As the by-product of the initiative, natural gas with pressure range from 10
psi to over than 250 psi are also mixed with crude oil.
[3.4] Makum Oil Collecting Station (Makum OCS) is handling around 25% of total explorationproduction,
where the output of 47 oil wells are pumped intocollected and processed. The main service function
of this OCS is to separate crude oil from the natural gas and , water and sediment/sludge, which are
produced as by-products of the crude oil explorationproduction..
[3.5] Makum OCS is handling 3,280 KL/ day of crude oil (as on 31.07.14) along with huge quantity of
natural gas. The natural gas over 250 psi is directly fed to the central gas supply network grid to
Hapjan Gas Collecting Station (Hapjan GCS). A portion of gas retrieved during process at 30-40 psi
pressure level is directed to gas compression station, where the pressure is increased to 250 psi
level and fed to the central grid. Another portion of the remaining quantum is utilized in-house for
running of gas engines for power generation, gas engine driven COD pumps, heating source
generation at Emulsion- treatoer (ET) and Indirect Heater(IH) and the rest portion is just flared up.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 8
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
There is no facility to utilize remaining portion of gas below 10 psi level and is totally being
flaredwasted.
The produced formation water disposed into the water disposal wells.
3.1[3.6] The Operational Capacity of Makum OCS is shown here :
SURFACE HANDLING CAPACITY OF MAKUM OCS
Well Fluid Processing Capacity : 3600 KL/day
Crude Oil Storage Capacity : 4930 KL
Formational Water Storage Capacity : 640 KL
Water Separation Capacity : 1800 KL/day
HP (250 PSI) Gas Processing Capacity : 0.82 Metric Million Std. Cum/day (MMSCUM)
LP (30 PSI) Gas Processing Capacity : 0.32 Million Std. Cum/day(MMSCUM)Metric Million
Cum/day
LP (10 PSI) Gas Processing Capacity : 0.15 Million Std. Cum/day(MMSCUM)Metric Million
Cum/day
3.2[3.7] The single line diagram for the process is shown here :
Natural Gas above 250 psi to Grid
Gas Grid
N.G. at 30 psi
Flare
From Wells N.G. 10 psi
Mixed Crude Oil
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 9
ID Heater G.U.-I G.U.-II E.T.
Booster Comp
Int. Cons.
E.E.T.
WaterStabilizer
Crude Tank
Pump
G.U.- Group Unit I/IIE.T. – Emulsion TreaterE.E.T. – Electrostatic Emulsion Treater
WDP
WDWell
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
3.3[3.8] The mixture of crude oil-water-natural gas (Well fluid) is tested periodically to determine the
production rate of liquid and gas of a particular well. Well fluid coming from different wells to OCS
are categorized as H.P. Dry, H.P. Wet and L.P. Wet based on well head pressure and water content in
well fluid. Similar category wells connected in one manifold. From manifold, well fluid goes to
Indirect Heater for improve flow-ability and enhance better phase separation in next stage
separation. Indirect Heater (Water Bath Type) maintains the temperature below 60o C.
3.4 From Indirect heater, HP (wet) fluid goes to GU-I(W) separator where gas and liquid separated.
Separates liquid then goes to GU-II(W) separator and gas goes to central gas grid(Distribution
Network) through HPMS(High Pressure Master Separator).The pressure maintain in GU-I(W),HPMS
& GU-II(W) around 20.0 Kg/cm2 ,19.5 Kg/cm2 and 5.5 Kg/cm2 respectively. GU-II(W) is a two phase
separator, separated liquid goes to Emulsion Treater and gas escape to Low Pressure Master
Separator(LPMS-30 psi). In LPMS, back pressure maintains around 30 psi. Major portion of LPMS(30
psi) gas goes to private owned booster compressor(BOO) for boosting 30 psi gas to 250 psi and then
the boosted gas(250 psi) gas fed to central gas grid. Other portion of 30 psi gas utilize for internal
consumption of OCS. Rest portion, if any flared up. Daily production of LP gas (30 psi) is around
1,30,000 to 1,50,000 SCUM, out of which, 72,000 SCUMPD is dispatched to private owned booster
compressor(BOO). Another 9,500 SCUM per day is used in-house for generation of electricity,
running of gas engines, burning as a fuel in IH, ETs & EETs and to maintain pneumatic pressure at
pneumatic control apparatus.
3.5 From GU-II(W), wet crude goes to Emulsion Treater. In Emulsion Treater(ET), wet crude (emulsified
crude) is treated by using Thermo-Chemical process for breaking emulsion and water is separated .
Separated Oil is goes to EET(Electrostatic Emulsion Treater) , gas goes to LPMS(30 psi) and water
goes to Formation water tank. Pressure maintain in ET and EET are 3.5 Kg/cm2 ,2.8 Kg/cm2
respectively. In ET, water content in crude reduced to 0.5%. For further reduction of water content ,
the treated crude goes from ET to EET ,where Electro-static process is used and water content
comes down to 0.1%. The separated oil, water and escape gas goes to Stabilizer, Formation water
tank and LPMS (10 psi) respectively. In stabilizer back pressure maintain around 1.0 Kg/cm2 . From
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 10
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
stabilizer, oil enters to Crude oil storage tank (height: 12mtr) and gas escape to LPMS (10 psi). Water
produced thus dispose into water disposal well.
3.6 The mixture of crude oil-water-natural gas is tested periodically to determine the percentage of
each component through Test Unit. One normal operation is resumed, the direct in-flow from the
wells are categorized as H.P. Dry, H.P. Wet and L.P. Dry and channelized through separate Indirect
Heater (I.D. Heaters) to maintain the temperature below 60oC. The heating at this stage ultimately
increases the flow of the liquid. The fuel used in indirect heating is Natural gas at pressure range of
30-40 psi.
Group Unit I separates liquid and gases and gas with pressure range above 250 psi is directly fed to the
gas grid through High Pressure Master Separator (HPMS). The Group Unit II is meant for low pressure,
where gas with pressure range between 30-40 psi is separated and a portion is dispatched to the
Booster Compressor Station, outside the OCS compound. Daily production of natural gas at 30-40 psi
level is around 1,30,000 to 1,50,000 cum, out of which, 72,000 cum per day is dispatched to 3 rd. party
booster station. Another 9,500 cum per day is used in-house for generation of electricity, running of gas
engines and to maintain pneumatic pressure at nipping apparatus.
In Emulsion Treater, oil (around 95%) and crude oil are separated by thermo-chemical process inside a
vessel, where as is charge for maintenance of flame inside and extra chemical is fed from outside.
Residual water (maximum 5%) is separated from crude oil (to maintain water content of 0.2% to be sent
to the refinery). Here electro-static process is used. The back pressure from the EET is 2.8 Kg/cm2, which
is further reduced to 1 Kg/cm2 at stabilizer. 1 Kg/cm2 back pressure pushes the oil upto a height of 12
Ft.
[3.9] The capacities of G.U. vessels are 910 KL/day, that of EET is 2,000 KL/day.
[3.10] Production profile of Makum OCS as on 31.07.2014 stands as :
PRODUCTION PROFILE OF MAKUM OCS
Crude Oil Production : 2,710 KL/day
Formation Water Production : 787 KL/day
HP (250 PSI) Gas Production : 350,000 scum/day
LP (30 PSI) Gas Production : 130,000 scum/day
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 11
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
LP (10 PSI) Gas Production : 11,500 scum/day
SCOPE OF WORK4.1 Pumps :
4.1.1 Determine Hydraulic Pressure, Efficiency of Motor-Driven Pumps.
4.1.2 Evaluate the performance of the Engine Driven Pumps including the study of the pumping and
allied Systems to evaluate their operational efficiencies and feasibility of reduction of in the
energy consumption, wherever possible.
4.2 Electric Motors :
4.2.1 Study of Loading and Efficiency of Motors,
4.2.2 Performance parameters of motors, Economics of Replacement of Under-loaded and in-efficient
motors.
4.3 Air Compressors :
4.3.1 Determine FAD of air Compressor
4.3.2 Determine the compression ratio
4.3.3 Specific Power Consumption,
4.3.4 Isothermal efficiency of Air Compressor,
4.3.5 Evaluate the Utilization pattern of the compressed air, leakage in the system, feasibility for
pressure optimization.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 12
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
4.4 Study the loading / % impedance of transformers
4.5 Study the performance & Efficiency of Gas Engine
4.6 Study of Natural Gas Consumption :
4.6.1 Study the consumption of natural gas by Indirect Heaters, Emulsion Treaters, Electro-static E.T.,
Gas Turbines for power generation and pumping system, etc.
4.6.2 Calculate specific Fuel Consumption of all the equipments running in the installation,
4.6.3 Determine total Gas consumption of the Installation,
4.6.4 Determine the Energy Index of the Installation.
4.7 Area Lighting/ Shed Lighting/ Control Room Lighting :
4.7.1 Determined Installed Load Efficiency & Installed Load Efficacy Ratio (ILER)
4.7.2 Study the Illumination system at the installation and suggest measures for improvement
wherever possible
METHODOLOGY OF AUDIT
5.1 In Makum Oil Collecting Station, direct out putoutput from the wells are fed to the manifold. The
conglomeration of the input is a mixture of crude oil, mudsludge / sediment, water and natural gas.
Through the indirect heater, the mixture is heated up to 60o deg C to maintain the flow and resist
the deposition of sludge / sedimentmud inside the pipes, which would reduce the flow pressure.
5.2[5.1] Prior to the field study at Makum OCS, a detail list of the scope of work had been provided by
OIL, which became the basis of the field measurement and the parameter testing. For proper
measurement and testing, understanding of the process is a must. So the method applied during the
study are a chronological of the given below :
5.2.1[5.1.1] Understanding of the process and identification of the Units.5.2.2[5.1.2] Study of the electrical power generation and measurement of electrical parameters at site,
during day time and evening time.5.2.3[5.1.3] Measurement of other electrical equipments at the site, namely, electric motors,
transformers, lighting loads and illumination level.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 13
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
[5.1.4] Measurement of mechanical parameters of the crude oil pumps and , formation water/ and booster pumps, namely, head, flow, RPM, etc.
5.2.4[5.1.5] Measurement of mechanical and electrical parameters of Air Compressors.[5.1.6] Study and measurement of speed, flow, etc of the gas engines at crude oil pump and power
generator.5.2.5[5.1.7] Study of the material flow for natural gas and crude oil at various points to prepare a
material balance of the OCS.5.2.6[5.1.8] Certain deficiencies were observed and documents were lacking, who deter during the
performance measurements of the following :
[5.1.9] There is no flow meter for gas flow measurement and High speed dieselelectricity at any point of
the network.
[5.1.10] The operational log-book of the Gas-alternator station has never been maintained. So, the
performances evaluation of the power generator is previous period could not be
possibleassessed.; tEven, the power curve for 24 hours basis could not be prepared. During the
field study, electrical parameters during day and evening time were measured, high highlighted
the connected electrical load through-out the day (load was mostly constant and day-time load
for 12 hours was less than evening time load for 12 hours)
5.2.7[5.1.11] A number of gas engines, connected directly with COD pumps were age-old, no operational
or maintenance manual was available.
5.2.8[5.1.12] There are two air compressors, one runs at a time. There is single unit to be catered by the
air compressor, half-an-hour, twice a day (morning and evening).
[5.1.13] Measurement of flow up to the stabilizer level could not be verified as the fluid contains crude
oil, natural gas and waterwas not a fruitful venture, as due to high rate of sedimentation of mud
inside the pipes deters and the ultra-sonic flow-meter is not able to to sense properly flow.
5.2.9[5.1.14] Few equipments could not be tested due to operational constraint.
5.3[5.2] The following Equipments were deployed during the field study :
Three Phase power Analyzer,
Single Phase Power Analyzer,
Lux Meter
Ultra-sonic flow meter,
Non-contact type Infra-red Thermometer,
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 14
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Non-contact type Tachometer
PRESENT ENERGY SCENARIO
6.1 At present, in Makum OCS, energy is utilized in three forms :
(i) Electrical Energy, generated in gas engine-alternator combined, to run electric motors of various
sizes, illumination and small electrical gadgets,
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 15
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
(ii) Mechanical Energy, generated in gas based engines to run ‘Crude Oil Delivery (COD)’ pumps;,
alternator, as well as directly by usinedg natural gas to pressurizemaintain a pneumatic controls
pressures for nipping of vessels..
(iii) Thermal EnergyThermal Energy, by using burning natural gas to develop a flame in side Indirect
Heaters and Emulsion Treaters.
[6.2] There is no electricalElectrical connection power is not drawn from the State electricity grid
network. The required electrical power required at various points equipments/insidemachines
inside the OCS is met by running gas engine driven -Aalternator set. There are two 250 KVA gas
genitor generator sets (of same rating, one runs at a time) and one 125 KVA gas-generator set.
During the day time, generally normally 125 KVA gas generator is used to cater the load but often
runs, but often, it was replaced by 250 KVA gen-set is utilized instead of 125 KVA gen-set. running.
After sun-set, when station lighting is switched onAt night, 250 KVA gen-set is utilized for the total
load. set is run. The gas supply to any of the gas-generator set is continuous through pipeline, when
natural gas with pressure 30-40 psi is directly fed to the engines. Natural gas required for the gas
engines for power generation is supplied from the 30/40 psi gas network available inside the
installation. Power is generated at 415 volt, 3 Ph, 50 Hz level, which is connected connected to the
power control centre to be fedfeed to the individual feeder. There is no metering system to
measure the gas flow at individual pointgas engines directly.
[6.3] At present, natural gas of pressure between 30-40 psi is utilized for in-house requirement. There is
no metering system to measure the gas flow at individual point directly.
[6.4] Details of energy consuming installations equipment/machineries are :
Sl Equipment Total capacity Energy Used Energy requirement
01 Indirect Heater (6 nos)
Separate for HP Dry & wet, LP wet
Natural gas is used to maintain the heat temperature of crude oil to 40o-50oC
2,700 cum/day
02 Group Unit I ( 2 nos) 1820 KL/day Practically nil N.A.
03 Group Unit II (2 nos) 1820 KL/day Practically nil N.A.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 16
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
042
Emulsion Treater (3 nos)
2730 KL/day Natural gas is used continuously to maintain the flame in the thermo-chemical process
????
053
Electro-static Emul-sion Treater (1 no)
2000 KL/ day Electricity supply is required here to maintain the voltage potential for the electro-static process
Load is fluctuating, power drawn varies from 2.73- to 4.8 KW
06 Stabilizer (2 nos) 3600 KL/day Practically nil N.A.
057
Crude Oil Delivery Pump (6 nos)
1-3 : 40 KL/hr4 : 100 KL/hr5-6 : 60 KL/hr
Mechanical power to run the pump is met by gas engine
37.0 scum/hr
068
Formation Water Pump (4 nos) Note : 2 pumps run operate at a time
1000 cum/hr Pumps run operates by 3 Ph electric motors of capacity 30 KW each
Electric power drawn by each motor = 22 KW, total power = 44 KW
079
Booster Pump ( 5 nos), 1 pump continuously + 1 pump occasionally
75 cum/hr Pumps run by 3 Ph electric motors of capacity 15 KW
Electric power drawn by each motor 11.54 KWKW, av power drawn = 17.31 KW
108 Circulating Pump ( 3 nos), one runs at a time intermittently
23 cum/hr Pump run by 3 Ph electric motor of 7.5 KW (run hr- 5 hrs/day)
Electric power drawn = 4.5 KW
119 Cooling Tower ( 2nos), one with each Gas generator
50 cum/hr Pump power = 3.75 KWFan power = 3.75 KW,Run by electric power
Available with 250 KVA set only, runs for 15 hrs a day with electric power drawn = 4.88 KW
102
Air Compressor ( 2 nos) one stand-by
Receiver cap.=225 litre
Run by electric motor of 3.75 KW, runs 10 mins x 2 times/day
Power drawn = 2.25 KW
113
Illumination (for 3 high-masts)
24 KW Run by three phase power, distributed to single phase to individual fittings
Total capacity = 8 KW eachTotal power drawn = 17.59 KW
124
Illumination (other than high masts)
11.5 KW Single phase electrical power, rated capacity-
Actual power drawn = 9.81 KW
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 17
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
not known135
Misc Mechanic Utility, e.g. submp pump,
N.A. Three phase electrical power, capacity – 7.5 KW
Actual power drawn =4.5 KW at certain intervals
6.2[6.5] Details of Energy consumption per day :
Daily Electricity consumption = 59.1 KW x 12 hours + 86.5 KW x 12 hours = 1,747.2 KWHr.
Daily Natural Gas Consumption as fuel and for pneumatic purpose = 6,800 cum + 2,700 cum = 9,500
cum, @ 8,700 Kcal/Kg x 580 Kg/cum = 47,937 x 106 Kcal, which is equivalent to 5,57,40,698 KWHr.
A slight quantity of High Speed Diesel is required for running Drenching pump, but the consumption
level is not at par.
Daily Energy Consumption Curve :
Electricity Consumed Natural Gas Consumed0.00
10.0020.0030.00
40.0050.00
60.0070.0080.0090.00
100.00
Series1
Study of Transformer :Transformer:
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 18
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
DETAILS OF TRANSFORMER
Isolation Transformer, 200 KVA, Dry-type, 415 Volt/415 Volt, 278.24 Amp, AN, Dyn11, impedance -
4.73%, Sr. No. DT/1693/01, Yr. 2008
Note :Note: Since the transformer is not a power transformer, but an isolation transformer, no
detail study is required.
STUDY OF ELECTRICAL POWER CONSUMPTION
[7.1] As said earlier, the source of electrical power is through captive power generation by using gas-
generator. The Gas-Generator generates power at 415 volt, 3 Ph, 50 Hz level. There are five three
gas-Generators : 250 KVA x 2 nos + 125 KVA x 1 no + 125 KVA old generators x 2 nos.
7.1[7.2] The details of Gas-Generators are :
250 KVA ( 2 nos) Generators 125 KVA New Generator 125 KVA (2 nos) Old Generators
Gas Engine : Model – CJ250G5P, Sr. No. CJX-SGG-10020327, 313 BHP, 1500 RPM, Battery volt- 24 V, make- Jackson, 2010Alternator : A.C., 3 Ph, 50 Hz, 250 KVA, 1500 RPM, 348 RPM, 415 volt, 48 volt excitation, type-HC143401, Sr. No. N10B01905, make- Stamford
Engine : Model – CJ125G5P, Sr.
No. 25321873, 157 BHP, 1500
RPM, 24 volt battery, Make-
Jackson, Year- 2007
Alternator : A.C., 3 Ph, 50 Hz,
125 KVA, 1500 RPM, 174 Amp,
58 volt excitation, make-
Stamford
125 KVA, NGEF sets, currently
disconnected.
NOTE : 125 KVA new Generator generally runs during day time, often relieved to be taken over by
250 KVA generator. During evening time, either of the 250 KVA runs continuously.
7.2[7.3] There is no operational log-book maintained by the Generator Operators. So, the electrical and
mechanical parameters could not be checked.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 19
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
7.3[7.4] The single line diagram for the power distribution is shown :
E.E.T. Lighting W/F. Pump Comp. Lightg Booster Utility Panel I Panel II Pump
[7.5] During the field study at OCS, the load was checked twice, i.e. at day time and at evening time. The
reason of checking waschecking :was: though the electrical load at the process was constant, the
load used to increase during evening time due to campus illumination. On the basis of the same, the
measurement, as given below was found :
Reading during day time Reading during evening time
Parameters Phase R Phase Y Phase B Phase R Phase Y Phase B
Voltage (v) 238.8 238.2 240.7 236.6 238.3 238.8
Current (A) 103.6 109.4 101.4 142.2 126.7 152.9
Power (KW) 18.3 18.4 22.4 28.2 26.4 31.9
Powr Factor 0.766 0.79 0.87 0.84 0.87 0.91
Observations :
During day time, if 125 KVA Gen. Set runs, loading becomes 59.1%
During day time, if 250 KVA Gen set runs, loading becomes 29.55%
During night time, when 250 KVA Gen set runs, loading becomes 43.25%
During night time, when 125 KVA Gen set runs, loading becomes 86.5%
Poor loading on Gen set causes P.F. below rated value. Lower P.F. demands higher
excitation currents and results in increased losses.
Unbalancing of load observed during evening time due to single phase lighting loads. It
causes over-heating of alternator.
7.4[7.6] Energy Saving Potential :
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 20
3 Ph, A.C. Generator
POWER DISTRIBUTION CENTRE
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
[7.6.1] Rationalize the loading on gen-set during day and night. If 125 KVA gen-set is capable to cater the
entire load of OCS at night also, 125 KVA gen-set to be utilized for effective loading of gen-set.
Run entire station load on 125 KVA Generator only, as it is capable of taking load of plant. Even
during the evening time, when the load becomes 86.5 KW, 125 KVA set is sufficient to take load
at 86%.
[7.6.2]
7.4.1 The rated consumption of Natural Gas for 250 KVA is 77 Scum/Hr, whereas that for 125 KVA is
37 cum/Hr. So, by running 125 KVA in place of 250 KVA, gas consumption can be reduced by 40
Scum/hr. Considering 24 hours run for 365 days a year, the yearly savings in gas = (77-37)
Scum/hr x 24 hrs/day x 365 days = 3,50,400 Scum @ Rs.6.48/cum, the yearly monetary savings is
Rs.22,70,592.00( Rupees Twenty two lacs Seventy thousand Five hundred Ninety two).
[7.6.3] Moreover, by replacing 250 KVA gen set, total electrical load of cooling tower, @7.5 KW can be
eliminated, which will ultimately reduce total load within safe margin of Alternator.
[7.7] Details of Electrical Connected Load with Rated Capacity, Maximum Load and Av. Load are :
Location Rated Load on continuous basis
Rated Load on intermittent basis
Av. loading Actual Load
[A.] A.Day-time Load
Isolation Transformer
160 KW Nil 25% 0.75 KW
Formation Water Pump
60 KW Nil 73% 44 KW
Booster Pump1 15 KW Nil 57.7% 8.66 KWCirculating Pump 7.5 KW Nil 60% 4.5 KWCooling Tower.2 7.5 KW Nil 65% 4.88 KWAir Compressor 3.75 KW Nil Nil 3.75 KW 20% 0.75 KWMisc. Mechanical Utility
7.5 KW Nil Nil 7.5 KW 20% 1.5 KW
Total connected Load during day time
65.04 KW
[B.] B.Evening Time Load
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 21
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Day-time load Calculation as before
65.04 KW
Illumination3 15.35 KW Nil 97% 14.89 KWTotal load during Evening Time
79.93 KW
NOTES :
1. One Booster pump runs at a time, if COD Pump #5 or 6 runs. It won’t run, if COD Pumps # 1-4 run
2. The cooling tower runs when 250 KVA Gen. Set in operation. If 125 KVA Gen set replaces 250 KVA gen set, cooling tower with total load of 7.5 KW won’t run.
3. Total single phase lighting load is 46.05 KW
Electrical Connected Load Summary :
If 250 KVA Gen Set runs If 125 KVA Gen set runs
Connected Load in Day Time 65.04 KW 60.16 KW
Connected Load in Night Time 79.93 KW 75.05 KW
STUDY OF PUMPS
[8.1] There are pumps to handle two kinds of stuffs liquids : Crude Oil and Formation Water.
8.1[8.2] There are six crude oil delivery pumps, run by gas engines, directly coupled. The details of the
pumps are :
Parameters COD #1 COD #2 COD # 3 COD # 4 COD # 5 COD #6
Delivery
Max Discharge Pr
Input BHP
Rated RPM
Make
40 KLPH
1585 PSI
205 BHP
370 RPM
Copper
40 KLPH
1865 PSI
205 BHP
370 RPM
Cooper
40 KLPH
1865 PSI
205 BHP
370 RPM
Cooper
100 KLPH
70 Kg/cm2
11.09 KW
227 RPM
BPCL
60 KLPH
1865 PSI
205 BHP
370 RPM
Cooper
60 KLPH
1047 PSI
250 BHP
400 RPM
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 22
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Year
Gear Box Ratio
N.A.
6.2:1
N.A.
5.6 :1
N.A.
5.6:1
N.A.
5.6:1
N.A.
5.6:1
N.A.
5.6:1
8.2[8.3] The measured parameters of COD Pumps are :
Parameters COD #1 COD #2 COD # 3 COD # 4 COD # 5 COD #6
Flow (m3/hr
Discharge Pr (Kg/cm2)
Suction Pr.(Kg/cm2
Hydraulic Power (KW
Shaft power input (KW Pump Effici-ency (%)
Remarks
27.3
40.0
0.5
25.83
118.61
21.78%
Discharge is 68.25% of rated, eff is low
34.6
40.0
0.5
32.74
117.17
27.94%
Discharge is 86.5% of rated, eff is moderate
46.49
40.0
0.5
43.99
129.89
33.87%
Discharge is 116% (due to higher eng. speed
Under B/down
40.4
35.0
4.0
30.00
163.39
18.36%
Discharge is 67% of rated, eff too low
45.31
31.0
4.0
29.31
146.41
20%
Discharge is 75.5% of rated, spe-ed too low
8.3 Energy Saving Potential for COD Pumps :
[8.3.1] Out of five pumps under observation, pumps #1-3 are of equal rating. The flow in pump # 3 is
higher than others due to higher prime-mover speed. But the efficiency level for #3 is much
higher than other twos. Considering pump efficiency of 40% (av)- for the pumps of age group,
10-15 years, with same shaft power input, the hydraulic power output and the discharge
(considering common discharge line) for the pumps should increase by 18%, 12%, and 12%
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 23
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
respectively. This can be achieved by (i) regular maintenance of the pump, (ii) sequential
matching of lower capacity pumps with higher capacity pumps, vis-à-vis, common delivery line,
and (iii) replacing by impellor plunger of lower flow design. Thereby, the running hours of pumps
# 1,2 & 3 can be reduced by 18%, 12% and 12% respectively. (Note : Prime Mover #3 is at
present running at 1715 RPM against 1500 RPM rated and fresh consideration is based on its
running at 1500 RPM only)
8.3.1[8.3.2] Energy Savings per year for Pumps # 1, 2& 3 :
(i) For Pump #1 : 37 m3/hr (N.G. consumption at prime mover)x 24 hours/ day x 365 days x
18% = 58,341 m3/year @ Rs.6.48/m3 = Rs.3,78,050.00
(ii) For Pump #2 : 37 m3/hr x 24 hours/day x 365 days/year x 12% =38,894 m3/year @
Rs.6.48/m3 = Rs.2,52,033.00
(iii) For Pump #3 : Same as Pump #2 = Rs.2,52,033.00/Year
[8.3.3] Observations for Pumps #5 &6 :6: These are of same capacity (discharge @60 KL/Hour). But
their discharge rates depend upon running of Pump #4 (discharge @100 KL/hour). When Pump
#4 is not running, the discharge pressure is 31 Kg/cm2, with running of #4, it increases to 37
Kg/cm2. The prime mover speed of #6 is also low (1337 RPM), compared to rated. The efficiency
of both at present is very low (18.36% -20%), whereas the pumps are only 4-5 years old. As per
the information gathered daily pumping rate of crude oil varies between 150-200 KL/Hr. General
operation sequence of the pumps is – (i) run two of #1-3 along with #4, or (ii) run all of #1-3 with
either of #5 &6. The inner diameter of delivery pipeline (starting from #1side) is 10ӯ, throttled
to 4ӯ at the outlet of #4, increased to 6ӯ at the outlet of #5&6. The delivery of # 5& 6 is
always less, necessitating the service of Booster pump, which otherwise not required if #1-4 run.
But the running of #5 & 6 is not economical, given by the present rate of pump output and fuel
consumption at engine. The recommendations are :
(a) Take up total overhauling of #4 by replacing its suction and delivery valves,
(b) Take up overhauling of #5 by repairing/replacing its suction and delivery valves, thereby
increasing the flow rate from 40.4 m3/hr to 52 m3/hr, i.e. around 30%. The corresponding
savings potential (for same range of delivery with average 8 hours duty per day) is – 30% x
52 m3/hr x 8 hrs/day x 365 days/year = 45,552 m3/year, @ Rs.6.48/m3 = Rs.2,95,177.00)
(c) Adjust engine speed of #6 to its rated speed of 1500 RPM, whereby its delivery will be
increased to 52 m3/hr., leading to increase of flow rate by around 12% and subsequent
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 24
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
reduction of fuel consumption for present rate of crude oil discharge. (Savings : 12% x 52
m3/hr x 8 hours/day x 365 days/year = 18,221 m3/year, @ Rs.6.48/m3 = Rs.1,18,072.00)
(d) Avoid running #1-3 along with #5 &6, as the discharge pressure of #1-3 is 40 Kg/cm 2,
whereas that for 5&6 is below 35 Kg/cm2. COD Pumps #5 & 6 can be run with the previous
ones, if the discharge pressure is increased above 40 Kg/cm2 (which is possible by increasing
engine speed of #6 and by replacing suction/delivery valves of #5).
(e) Adjust the throttle valve (near #4) to allow more delivery from #5 &6, if #4 is run along with
either of #5 &6 is running.
8.4 Details of Formation Water (F.W.) Pumps : There are four F.W. pumps, out of which, one was found
in out of order situation. Two pumps run at a time. The details of F.W. pumps are given :
Formation Water Pump with Motor :
Pump : Multi (7)-stages pump, total head- 200 mtrs, Capacity -25 m3/Hr., Efficiency -58%, BKW-23.29
KW, RPM-2940, NPSH required – 1.6 mtr, Bare shaft- 166 Kg, make-Kirlosker Brothers
Electric Motor (Drive) : 3 Ph, 50 Hz, 30 KW, 2955 RPM, Efficiency -91%, make-KEC
8.5 Measured Parameters of F.W. Pumps :
Parameters F.W.Pump #1 F.W.Pump #2 F.W.Pump #3 F.W.Pump #4
Flow (m3/hr)
Discharge Pr (Kg/cm2)
Suction Pr.(Kg/cm2)
Hydraulic Power (KW)
Shaft power input (KW), eff-91%
Pump Effici-ency (%)
% discharge of rated capacity
9.96
21.5
0.5
5.68
19.838
28.63%
39.84%
13.38
21.5
0.5
7.626
22.75
33.52%
53.52%
Efficiency low,
Under B/down 4.36
16.0
0.5
1.834
21.476
8.54%
17.44%
Eff. extremely low,
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 25
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Remarks Efficiency low, impeller at every stage to be checked, gland leakage
impeller at every stage to be checked, leakage to be arrested
profuse gland leakage, impeller at every stage to be checked
8.6 General Observation of Formation Water Pump : As found during the testing, there were (i)
mechanical noise from the pump, (ii) excessive leakage from the gland, and (iii) discharge in # 1 & 4
is poor, and (iv) for almost same power input, hydraulic power output is varying widely and at low
level. The discharge is to be improved by checking and replacement (if necessary) of impeller at
every stage and arresting any loss of alignment.
[8.7] Savings potential :potential: The rated efficiency of the pumps is 58%, whereas the actual
efficiency is varying between 28.36%-33.52% (for pumps 1 & 2) and at lowest of 8.54% (for #4).
Considering average efficiency of 50% for such pumps, running hours for electric motors can be
reduced (considering same volume of water to be pumped daily). By proper over-hauling of pumps,
the flow rate can be increased by 21% & 16% (in case of pump I & II respectively) and 40% (in case of
pump #4). The reduction of running hours for pump # 1 is 21%, #2 is 16% and that for Pump #4 is
40%. The corresponding savings in electricity : For Pump #1 - 19.838 KW x 21% x 24 hours/day x 365
days = 36,494 KWHr/year, @ Rs.4.55/KWHr = Rs.1,66,048.00
For Pump #2 : 22.75 KW x 16% x 24 hours/day x 365 days =31,886 KWHr/year, @ Rs.4.55/KWHr =
Rs.1,45,081.00
For Pump # 4 : 21.476 KW x 40% x 24 hours x 365 days = 75,251 KWHr/year, @ Rs.4.55/KWHr=
Rs.3,42,392.00
Total Yearly savings : 1,43,631 KWHr or Rs.6,53,521.00
8.7[8.8] Measured Parameters of Booster Pumps : There are three booster pumps, out of which, one is
out of order. One runs at a time. The Booster pump runs, if crude oil delivery pump # 5 and/or 6
runs.
Parameters Booster Pump #1 Booster Pump #2 Booster Pump #3
Flow (m3/hr)
Discharge Pr (Kg/cm2)
Suction Pr.(Kg/cm2)
42.78
4.0
0.5
Under B/down 39.73
3.5
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 26
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Hydraulic Power (KW)
Shaft power input (KW), eff-93%
Pump Effici-ency (%)
Remarks
4.06
10.66
38%
Rated efficiency level is 62%, present efficiency is to be improved with maintenance of suction, discharge lines and impeller
0.5
3.23
10.72
30.13%
Rated efficiency is 62%, present efficiency to be improved by thorough over-hauling
Savings Potential :Potential: By over-hauling of Booster pumps, 20% reduction in running hours of
the pumps can be achieved (note :note: The rated flow for the Booster pump is 52 m3/hr at 5
Kg/cm2. The estimation is based on the assumption of over-hauling of the pump and considering
performance improvement in COD Pumps #5 &6). The reduction in power drawn in one pump
(running) = 10.7 KW x 20% = 2.14 KW. Yearly savings = 2.14 KW x 24 hours x 365 days = 18,746
KWHr, @ Rs.4.55/KWHr = Rs.85,294.00
[8.9] Circulating Pump (Rotto Pump) : Used as sump/pit pump
Pump Details :Sr. No. NH111400, rated delivery- 23 m3/Hr, 6 bar, 7.5 KW, 720 RPM, make- Rotto
Motor Details : 7.5 KW, PF-0.78, 710 RPM, Efficiency -86%, 5.5 Amps.
The electrical and Mechanical parameters could not be checked as there was no water in the circuit.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 27
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
STUDY OF ELECTRIC MOTORS9.1 Electric motors with rated capacity of 7.5 H.P .and above were taken up for testing, because,
efficiency of lower H.P. motors are generally less, as designed.
9.2 Testing of Electric Motors : All are 3 Ph, 50 Hz motors.
Parameter Phase R Phase Y Phase B RemarksFormation Water Pump #1Voltage (Volt) 236.1 232.7 234.6Current (Amp) 35.4 35.9 36.7Power (KW) 6.7 7.5 7.6Power Factor 0.84 0.862 0.865 Low P.F.
Formation Water Pump #2Voltage (Volt) 235.3 232.5 239.1Current (Amp) 44 41.1 43.5Power (KW) 8.3 7.8 8.9Power Factor 0.818 0.873 0.831 Low P.F.
Formation Water Pump #4Voltage (Volt) 235 231.8 238.5Current (Amp) 39 38.8 40Power (KW) 7.7 8.3 7.6Power Factor 0.852 0.887 0.856
Booster Pump #1Voltage (volt) 234.7 235.2 236.9Current (Amp) 18.1 18.7 19Power (KW) 3.82 3.85 3.8Power Factor 0.876 0.88 0.87
Booster Pumo #3Voltage (Volt) 235 232.9 239Current (Amp) 18.4 18.4 18.7Power (KW) 3.84 3.87 3.82Power Factor 0.876 0.869 0.88
NOTE : The low power factor and unbalance current in three phases cause over-heating of Motor.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 28
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Abstract of Measurement of Motor Performances :
Location Rated Load/ RPM/Efficiency
Measured Load
% loading Remarks
Formation Water Pump #1
30 KW, 2970 RPM, Eff.-91%
21.8 KW 79.85% Adequately loaded
Formation Water Pump #2
30 KW, 2970 RPM, Eff.-91%
25 KW 91.57% Over-loaded, over-heating observed
Formation Water Pump #4
30 KW, 2970 RPM, Eff.-91%
23.6 KW 86.45% Adequately loaded
Booster Pump #1 15 KW, 2880 RPM, eff.-93%
11.47 KW 82.15% Adequately loaded
Booster Pump #3 15 KW, 2880 RPM, eff.-93%
11.53 KW 82.65% Adequately loaded
9.3 Motor performances :
9.3.1 A.C., 3 Ph motors’ efficiency improves with loading improves over 50% of loading. But the safe
region for motor operation is 60%-85%, as over 85% loading, motor tends to over-heat.
9.3.2 In Makum OCS, majority of big motors are related to pumps with RPM around 2880 and are
directly coupled. Hence, little mechanical loss is observed at the couple point.
9.3.3 All of the motors are started by Y-Δ starters, though excessive cable congestion could be
observed inside the starter panel and bus-bar area.
9.3.4 During day time, if 250 KVA Gen Set runs, power factor reduces due to low loading on the
generator, which improves with increasing load after sun-set. With increasing P.F., loading
pattern on the motor also improves.
9.3.5 Electrical load on F.W. #2 motor is to be checked further, to reduce the loading within safe 85%.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 29
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
STUDY OF AIR COMPRESSOR
10.1 There are two air compressors of same rating, one runs at a time. The details of the air
compressor are given below :
Compressor : Model – 2475, Sr. no. 3012004, year- 2006, receiver capacity – 225 litre, maximum
working pressure- 12.3 Kg/cm2, make- Elgi.
Drive Motor : A.C., 3 Ph., 50 Hz, 5 H.P. (3.75 KW), 1430 RPM, efficiency -84%, make- Crompton
Greaves.
10.2 Calculation of Free Air Deliver(FAD) :
Final pressure after filling of Air Receiver (P2)– 4.5 Kg/cm2
Initial pressure after bleeding (P1) – 0 Kg/cm2
Atmospheric Pressure (P0) – 1.026 Kg/cm2
Storage Volume (V) – 225 Litre = 0.225 cum
Time taken (T) – 2 mins 19.74 secs = 2.329 min.
(P2-P1) x VActual Free Air Delivery = Q= P0 x T = [(4.5 -0) x 0.225] / 1.026 x 2.329 Nm3/min
= 0.424 Nm3/min10.3 Calculation of Compression Ratio :
Compression Ratio = Receiver Pressure / Inlet pressure
= 4.5 Kg/cm2/ 1.026 Kg/cm2 = 4.5/1.026 = 4.386
10.4 Calculation of Specific Power Consumption :
Specific Power Consumption = Actual Power Consumption by the compressor (KW) Actual Free Air Delivery (m3/Hr)
Actual Power consumption by the compressor = electrical load of motor x efficiency of motor = 2.325 KW x 0.84 = 1.953 KW
Actual Free Air Deliver = 0.424 cum/min = 25.44 cum/hr.
Specific Power Consumption = 1.953 KW 25.44 cum/Hr = 0.0768 KW/cum/Hr
10.5 Calculation of Isothermal Efficiency :
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 30
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Calculation of Isothermal Power (KW) = P1 x Qf x ln r36.7
Where P1 = Inlet pressure = 1.026 Kg/cm2
Qf = Free Air Delivery (cum/Hr)r = compression Ratio 1.026 x 25.44 cum/hr x ln 4.386 38.58Isothermal Power = 36.7 = 36.7 = 1.05 KW
Isothermal Efficiency = (Isothermal power ) / (Compressor Input Power) = 1.05 KW / 1.953 KW = 53.76%
10.6 Air Compressor Performance :
Figures in Summary
Actual Free Air Delivery : 0.424 Nm3/min = 25.44 cum/hr
Compression Ratio : 4.386
Specific Power Consumption : 0.0786 KW/Cum/Hr
Isothermal Power : 1.05 KW
Isothermal Efficiency : 53.76%
10.7 Observation of Performances in Air Compressor :
[10.7.1] The compressor runs twice a day, morning and evening for the cleaning purposeIR filter plant
for internal consumption of water (with duration of running each time 45 mins to 1 hour).
10.7.1[10.7.2] The pressure release station is around 30 mtrs from the air receiver, air pipe line ID is
1ӯ. During the operation of the compressor, no air leakage could be found, either physically or
through the operation of the compressor.
10.7.2[10.7.3] The required pressure at the discharge location is merely 2.5 -3 Kg/cm2. The pressure
switch is fixed at 4.5 Kg/cm2 (cut-off) and 3 Kg/cm2 (start-in).
10.7.3[10.7.4] No alteration is suggested for the air compressor, which is running effectively .
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 31
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
STUDY OF GAS ENGINES
11.1.1 The gas engines are located at two points : (i) at Power House to run A.C. alternator to generate
electricity at 415 volt level, and (ii) at Crude Oil Delivery Pumping station to run the pumps.
[11.1.2] In power-house, there are three engines, suitable for run alternatelyone run at a time, 2 nos x
333 BHP engines and one 157 BHP engine. The 157 BHP engine is air cooled, whereas the bigger
333BHP engines are water-cooled, for which separate cooling tower is maintained.
11.1.2[11.1.3] All of the three gas generators are pretty new and are running on continuous basis.
During the field study, nothing abnormal could be found.
11.2 The details of the Prime-movers for Generator Sets are :
Engine # Model Make Rated BHP at 1500 RPM Rated Fuel Consumption (m3/hr)
250 KVA G-1150 Cummins 333 77.0
125 KVA G-855-G-BC Cummins 157 37.0
Note : The fuel consumption of 250 KVA Gen set at 45% is 37.98 m3/hr and that for 125 KVA at 60%
loading is 24.64 m3/hr.
Gas Gen. set Electrical Power Output (kw)
Fuel consumption (m3) per Hr.
Specific Fuel Consumption (m3/Kw/Hr)
Remarks
250 KVA 86.5 37.98 0.439 Load is too low, current S.F.C. is not indicative of performance, though at 45% loading, S.F.C. is satisfactory
125 KVA 59.1 24.64 0.417 Load is low, current S.F.C. is indicative of performance, which is satisfactory
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 32
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Note : Both of the gas generating sets are new. The flow of gas consumed by the engines was not
measured and the present calculations are based on rated consumption figures, which should be
figure at present. It is highly advisable to put adequate load and calculate the specific fuel
consumption at 75-80% of the rated load.
11.3 The ratings of the natural gas fuelled engines (prime mover) for Crude Oil Delivery Pumps are
given :
Engine # Model Make Rated BHP at 1500 RPM Rated Fuel Consumption (m3/hr)
1 G-855 Cummins 157 37.0
2 G-855 Cummins 157 37.0
3 G-855 Cummins 157 37.0
4 GV-1710 NA 480 103.0
5 GTA-855 Cummins 227 52.0
6 GTA-855 Cummins 227 52.0
11.4 The speeds of the Gas Engines along with the COD Pump speeds as measured :
COD Pump/ Engine #
Engine speed measured
Rated Speed of Engine
Pump Speed measured
Rated Pump Speed
# 1 1,566 RPM 1500 RPM 246.5 RPM 242 RPM
# 2 1,547 RPM 1500 RPM 253.3 RPM 268 RPM
# 3 1,715 RPM 1500 RPM 275.6 RPM 268 RPM
# 4 B/down 1500 RPM Not running 227 RPM
# 5 1,492 RPM 1500 RPM 254.6 RPM 268 RPM
# 6 1337 RPM 1500 RPM 242.7 RPM 268 RPM
Observations : The speed of engine no. 3 is much higher than rated, whereas that for engine # 6 is
much lower. Governor settings of the engines are to be adjusted as close as 1500 RPM.
11.5 During the testing of the Natural Gas fuelled engines, the shaft mechanical power output and
the corresponding fuel consumption (ideal) have been found as :
Engine # Mechanical Power Output (kw)
Fuel consumption (m3) per Hr.
Specific Fuel Consumption (m3/Kw/Hr)
Recommended sp. Fuel consum-ption (m3/Kw/Hr)
1 122.27 38.628 0.315 0.23
2 161.92 38.16 0.2356 0.23
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 33
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
3 179.50 42.30 0.2356 0.23
4 Not running NA NA NA
5 225.79 51.72 0.2290 0.22
6 202.33 46.35 0.2290 0.22
Note : As per the manufacturer’s guideline, the S.F.C. should be around 12.2 MJ/KW/Hr (G-855) and
12 MJ/KW/Hr (GTA-855) at 100% loading and 14.0 MJ/KW/Hr (G-855) and 12.8 MJ/KW/Hr (GTA-
855) at 75% loading.
11.6 General Observations during Audit for the Engines (attached with COD pumps) :
11.6.1 Individual flow meter should be incorporated at the feeding of each engine.
11.6.2 Mechanical noise could be observed at engine nos. #2 & 3, as well as in #5.
11.6.3 There is starting problem in engine #6.
11.6.4 The speed for engines #3 & 6 are either higher or lower than rated. Adjust the governor setting
for engines # 3 & 6, so as to match the speed as close as its rated speed.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 34
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
STUDY OF CRUDE OIL & NATURAL GAS CONSUMPTION
12.1 The Flow-line of the Natural Gas inside the Station is :
Natural Gas above 250 psi to Grid
Gas Grid
N.G. at 30 psi
Flare
From Wells N.G. 10 psi
Mixed Crude Oil
Flare
12.2 Study of Crude Oil Consumption : (Figures are per day basis)
Location/Stage Liquid Received (KL) Liquid Output (KL)
ManifoldID Heater
G.U.I
G.U.II
E.T.
E.E.T.
Stabilizer
Oil Water3,497 Mixed with oil3,497 Mixed with oil,
3,427 Mixed with oil,
3,376 Mixed with oil
3,342 Mixed with oil
2,960 45 (1.5% est.)
Oil Water
3,427 Mixed with oil, 2% water loss
3,376 Mixed with oil, 1.5% water loss
3,342 Mixed with oil, 1% water loss
2,960 733 (water loss occur, not quantified)
2,9,15 30 (rest lost in EET, not quantified, residual level 0.2%
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 35
ID Heater G.U.-I G.U.-II E.T.
Booster Comp
Int. Cons.
E.E.T.
G.U.- Group Unit I/IIE.T. – Emulsion TreaterE.E.T. – Electrostatic Emulsion Treater
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Tank & COD Pump
Dispatch to Refinery
2,915 Nil
2,880 (+ loss in tank)
Nil
2,612
2,915 Nil
2,640 (+loss in pump & fittings)
Nil
Note : The material balance is prepared on the basis of flow measurement, input from the
Installation Manager & information from the Hand-book.
12.3 Study of Natural Gas Generation/Consumption : (Figures are in m3/day)
Stages Generation of Natural Gas
Consumption /Flare Remarks
Manifold (inflow to the Station)
491,500 N.A. Actual amount is very hard to ascertain, as the flow was mix with crude oil and continuously changing
Group Unit I 3,50,000 350,000 At 250 PSI and higher level, directly fed to grid through HPMS
Group Unit II 110,000 Internal Consumption as Fuel – 6,800Internal Consumption for instrument- 2,700Flaring Up = (110,000-72,000-6,800-2,700)= 28,500
At 30 PSI, 72,000 of which is sent to 3rd. party for boosting.
Emulsion Treater
20,000 Flaring Up = 20,000 Generation at 30 PSI
Electro-static E.T.
4,000 Flaring Up = 4,000 Generation at 10 PSI
Stabilizer 7,500 Flaring Up = 7,500 Generation at 10 PSI
Distribution of Natural Gas generated
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 36
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
m3/day
Fed to Grid at 250 PSIBoosting through 3rd. PartyInternal consumption at 30 PSIFlaring up at 30 PSIFlaring up at 10 PSI
So, daily quantum of flare up at 30 PSI level is 20,000 cum/day and at 10 PSI level is 11,500 cum/day.
12.4 Energy Saving through Natural Gas Consumption :
Daily waste of natural gas as flare at 30 PSI = 48,500.00 cum/day
Internal consumption = 9,500.00 cum/day
Available natural gas at 30 PSI (if internal consumption were not there) = 58,500 cum/day
Suggestion for Energy Savings :
To develop any 3rd. Party to handle 50,000 cum/day natural gas at 30 PSI to convert into 250
PSI (vol.6000 cum/day) and to feed into the grid.
To convert available 10 PSI natural gas into 30 PSI natural gas for internal consumption
through installation of in-house booster compressor. Currently, 11500 cum at 10 PSI is
available, which is to be converted into 3,833 cum at 30 PSI level. The balance requirement
of gas at 30 PSI is to be available from the balance (8,500 cum/day) of gas left behind.
The volume of 50,000 cum/day at 30 PSI is equivalent to 6000 cum/day at 250 PSI level. The
selling price per year = 6,000 cum/day x 365 day x Rs.6.48/cum = Rs.1,41,91,200.00
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 37
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
STUDY OF ILLUMINATION
13.1 The illumination has been provided in open space, office (4 rooms) and machinery sheds (4
sheds). In rooms/ sheds, conventional tube light fittings of 36 watts have been provided with
standard electro-magnetic chokes.
13.2 The installed Illumination fittings at various points are
Location Fittings
No Lamp Wattage Fan No. WattageTotal Watt
Power Hous Old 8 FTL 36 0 0 288Power Hs New 5 FTL 36 0 0 180Water Pump Hs 3 FTL 36 1 60 168Drenching Pmp 3 FTL 36 0 0 108CISF Main Gate 1 FTL 36 0 0 36ET Shed 6 MVL 160 0 0 2880EET Shed 6 MVL 250 0 0 1500Flow Valve set 2 MVL 160 0 0 320Che. Pump Hs 4 MVL 160 0 0 640Filter Shed Hs 2 MVL 160 0 0 320High Mast I 24 HPSV 400 0 0 9600High Mast II 24 HPSV 400 0 0 9600High Mast III 24 HPSV 400 0 0 9600Office Room 5 FTL 36 2 60 300
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 38
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Staff Room 5 FTL 36 2 60 300Computer Rm 5 FTL 36 2 60 300Supervisor Rm 5 FTL 36 2 60 300Dining Hall 7 FTL 36 3 60 432Godown 4 FTL 36 0 0 144Puja Room 1 FTL 36 0 0 36Civil Office 1 IL 100 2 60 220CISF Camp 17 FTL 36 11 60 1452FWD Pump Hs 8 FTL 36 0 0 288COD Pump Hs 12 MVL 160 0 0 1920Booster Pump Hs 3 MVL 160 0 0 480Booster Pump Hs 2 MVL 160 0 0 320Deoiler Pump Hs 2 MVL 160 0 0 320Sump Pump Hs 2 MVL 160 0 0 320PIG Receiver 2 MVL 160 0 0 320Yard Light 10 HPSV 400 0 0 4000
Abbreviated Form : FTL : Fluorescent Tube Lamp ; IL : Incandescent Lamp ; MVL : Mercury Vapour
Lamp ; HPSV : High Pressure Sodium Vapour
13.3 In the open compound, three high masts are located with individual rated capacity of 9.6 KW
each through a number of high pressure sodium vapour lamps (12 fittings x 2 HPSV lamps/fittings x
400 watt /lamp).
13.4 Based on the lux-level measured, the observations are :
Area/Location Maximum Lux Average Lux Recommended RemarksOpen Yard 3 2 50 The lux level at every corner Walk-way 7 4 50 poor. Immediate attention is Walk-way in front of high mast
21 15.4 50 this regard is solicited. All conventional tube-light fit-
Generator Shed 23 11.5 100 tings are to be replaced by Heater Shed 26 16 50 T-5 fittings with electronicWalk-way in front of Heater/Testing
24 19.6 50 Ballast. Around 1/3 of halogen lights at high masts
Area around G.U. 18 14.8 50 non-functional, which are to Along Boundary wall
8 4.29 50 Be replaced immediately. Extra lights are to be providd
COD Pump Area 20 11 100 Along the boundary wall for security reason.
Booster Pump House
3 2 100
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 39
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Water Disposal Pump House
18 15.66 100
Walk-way in front of pump house
33 26.2 50
Office Verandah 72 56.5 100Office Room 172 80.16 200Workers’ room 90 59.5 200
13.5 Energy Savings :
13.5.1 Total conventional tube-lights of (36 + 12) watts are to be replaced by T-5 fittings (of 29
watts). There are total 77 nos of such fittings. Annual savings = (48 -29) watts x 77 nos x 12
hours/day x 365 days/year= 6407.94 KWHr, @ Rs.4.55/KWHr = Rs.29,156.00
13.5.2 Investment : 77 fittings x Rs.422.00 (cost of T5) = Rs.32,494.00. Simple pay-back period = 13
months.
13.5.3 40 watts Light Emmitting Diode (LED) fixtures can also be tested in place of 160 watt
mercury vapour lamp, but no specific recommendation is meted out in this sphere (the
concerned manufacturers should be consulted)
GENERAL OBSERVATIONS OF THE AUDIT
14.1 Makum Oil Collecting Station is a very compact and continuous type of operation, receiving
crude oil mix from 47 well exploration stations.
14.2 There is no metering facility at any consumption level, namely, electricity, natural gas, etc. Entire
range of natural gas at very low pressure (10 PSI) is being wasted and a part of 30 PSI is used for in-
house consumption, flaring up the remaining portion. As natural gas is abundant, the consumption
at any level is not meterized.
14.3 The electricity is generated at 415 volt level, but the loading on generator is not sufficient to
maintain electrical parameters of the generator. Optimum loading on the generator ultimately
increases the life of the generator.
14.4 The cooling tower with 7.5 KW load is connected with 250 KVA generator only. The effectiveness
of the cooling tower is not up to the mark due to low load on the generator.
14.5 Generator log-book should be maintained properly. At present, no such log-book is available.
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 40
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
14.6 Through over-hauling is water pumps are required, as high leakage from the gland has been
observed in all Formational Water Pumps.
14.7 Meter should be installed at every important junction to gauge the natural gas flow.
14.8 Starter panels for the pumps should be well dressed, so that measurement through outside
meters can be possible.
14.9 Over-load relays for the pumps should be periodically checked, as at certain points, Over-load
relay settings are not appropriate.
14.10 The gas engines for pumps are running at higher or lower speed than rated. Governor setting
should be done immediately.
14.11 Illumination level at every point should be improved, either by replacing faulty fittings, or adding
new fittings.
[14.12]
ANNEXURE : A2
ENERGY SAVINGS EQUIPMENT SUPPLIERS
1.0 LED LIGHTINGS : Synergy Solar (Pvt.) Ltd.,
SCO 133, Sector-28D, Chandigarh, Ph.-0172-6451133, www.synergysolars.com
2.0 OUTDOOR LIGHTINGS : Crompton Greaves Ltd.,
Lighting Business Group, 405, Concorde,R.C. Dutt Road, Vadodara- 390 007
Philips India Ltd.,Technopolis Knowledge Park,
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 41
ENERGY AUDIT REPORT- MAKUM OIL COLLECTING STATION
Nelco Complex, Mahakali Caves Road,Chakala, Andheri (East), Mumbai- 400 093Ph.-022-56912000
3.0 AUTOMATION & PANEL METERS : Selec controls Pvt Ltd
E – 121, Ansa Industrial Estate, Saki Vihar Road, Mumbai 400072Ph: 022-28471882, 28476443, www.selecindia.com
4.0 COMPRESSED AIR PIPINGS : Legris India Pvt Ltd.
Legris House, 99 Pace city –1, sector 37, Gurgaon- 122001 Ph : 9958297093 , 9811054826 www.transair.legris.com
5.0 LOW PRESSURE NATURAL GAS BOOSTER COMPRESSOR : G-Tech Pressure Booster
Ph.- 800-451-8294, 716-831-9695e-Mail : [email protected]
M/s Oil India Limited, A/c- Makum OCSM/s Petroleum Conservation Research Association, Kolkata Page 42