Page 1: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

ENERGYACCESS

SUCCESS STORIES FROM INDONESIA’S OFF-GRID INSTALLATIONS

1

Page 2: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

OUR MISSIONEMPOWERING rural communities through INNOVATION

2

Page 3: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

DESIGNENGAGE

MONITORMANAGE

3

Page 4: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

INNOVATE

What our company, PT Inovasi does is to empower rural communities through innovation. We do this through four activities: Engage community members, design a plan for growth, manage the implementation, and monitor progress

4

Page 5: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

LET’S TALK MINIGRIDS

Enough about us, let’s talk mini grids

5

Page 6: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

CLOSE YOUR EYES

6

Page 7: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

NO PEEKING!!

7

Page 8: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

THE YEAR 1827

A village was born

8

Page 9: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

No modern access to electricity

9

Page 10: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

Next came this for $1 per night, 4 hours (18:00 to 22:00)

10

Page 11: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

The year 2015, the community came together to help the contractor install a solar PV system.

11

Page 12: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

190 years after the village was incorporated, they finally have modern access to electricity. 155kWp of solar PV system for 3 communities, 500 households in total finally have 24 hours access of electricity. Thanks to the Ministry of Energy and Mineral Resources, Directorate General of New and Renewable Energy and Energy Conservation (MEMR-DGNREEC).

12

Page 13: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

13

Page 14: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

PT Inovasi team members properly trained the local field operators for basic maintenance and operations. We also involved and encouraged women who are interested to be trained and be operators.

14

Page 15: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

Finally, the village received an equitable opportunity for growth. Instead of waiting for the utility company to come and provide them with electricity at the same, equal rate as everyone else, they are given the tool appropriate for their needs. So now they are in a more equitable position as many of us in the cities as far as energy access is concerned. Instead of 11 cents/kWh that people in the Indonesian cities are paying, the community is paying 34 cents/kWh. But at least they have access to energy now.

15

Page 16: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

HOW MANY?

Now help me think about this for a minute. How many minigrids have been installed in India? In Africa? How many institutions installed them? How many minigrids have a single entity installed?TANESCO – over 100 minigrids http://www.wri.org/blog/2017/10/electrifying-africa-mini-grids-five-lessons-TanzaniaSmart Power India – 106 minigrids http://www.powerforall.org/blog/2017/9/28/policy-spotlight-nigeria-india-lead-on-mini-grids

16

Page 17: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

INDONESIA:

9 MINIGRIDS ?

97 MINIGRIDS ?

ANSWER: 973

17

Page 18: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

Total solar PV minigrids: 28MWp

18

Page 19: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

WHO IS THE INVESTOR?

19

Page 20: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

MINISTRY OF ENERGY AND MINERAL RESOURCES

20

Page 21: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

Besides being a single entity that has implemented the most number of mini grids in the world, the directorate general of new and renewable energy and energy conservation have also challenged 3 myths about government funded minigrids:1. they’re not sustainable2. They’re low quality3. They’re expensive

21

Page 22: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

OPERATIONAL STATUS

22

Page 23: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

82% of the contacted sites are still operational. Some of the systems contacted are 3-4 years old. Compared to previous survey periods, most experienced no change in status, some have even recovered, and only 3% worsened

According to a GIZ study and presentation https://energypedia.info/images/e/e5/Report_Operational_Status_Survey_-_EnDev_Indonesia_ed.Dec_2016.pdf

23

Page 24: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

24

Page 25: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

They’re not low quality, using SMA inverters in many of their recent sites

25

Page 26: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

Or Schneider Electric

26

Page 27: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

GRANT BUILT MINIGRIDS

Location Size Technology Project Value Cost / Wp

Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp

Mamuju, West Sulawesi 598 kWp Solar PV $6,588,883 $11.02/Wp

Mentawai, West Sumatra 700 kW Biomass $13,417,229 $19.17/W

Sumba, East Nusa Tenggara 492 kWp Solar PV $10,091,279 $20.51/Wp

Lombok, West Nusa Tenggara 1,320 kW Hydro $10,845,788 $8.22/W

Berau, East Kalimantan 1,243 kWp Solar PV $10,705,875 $8.61/Wp

Source : Millennium Challenge Corporation

How much do you think is the government built ones?

27

Page 28: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

MEMR BUILTUS$8/Wp

Utility grade poles and cables, energy limiters at each house, street lighting, mostly at VERY remote areas, and in the last couple of years, long life batteries have been specified (requiring de facto use of lithium ion batteries or zinc-air batteries). Despite this high requirements, the cost remain competitive

28

Page 29: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

So what were the factors of success?

29

Page 30: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

ADVANCED TECHNOLOGY?

Technology? Nope, many of them still use lead acid batteries, good old AC coupled or DC coupled inverters (SMA, Schneider, Leonics). Technology is no longer an enabler, it’s just a tool. A particular technology may work really well in one situation. But if we replace it with another that may not work as well in certain aspects, it doesn’t mean that no other technology will work. There are others that will work okay but meets the needs just fine.

30

Page 31: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

PROFESSIONAL O&M?

Nope, they’re mostly operated by the community

31

Page 32: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

ADVANCED ROBOTICS?

Nope, not that either

32

Page 33: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

PRODUCTIVE USE OF ENERGY?

33

Page 34: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

PRODUCTIVE USE OF

ENERGY?

34

Page 35: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

PEOPLE

It’s the people. Finding the right stories, and how to work with them.

35

Page 36: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

MINISTRY OF ENERGY AND MINERAL RESOURCES

Throughout the years, not that many actually, since 2012, MEMR have learned how to engage the right people and put the risks and responsibilities to those who are best to bear them. And to give the benefits to the right people.

36

Page 37: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

MEMR REGULATION

39/2017

Updated in 2018 through MEMR Regulation 12/2018

37

Page 38: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

PROCESS

This regulation defines the process under which the province can request for the villages to be electrified with the national budget. They have to agree to certain conditions

38

Page 39: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

STEP 1 : PROPOSAL

The requirements really are just like a wedding vowAt this stage, the province (or other ministries) must declare that:1. Ready and willing to accept ownership and operate the assets2. Ready to support and assist the operators and end users of the assets through the local government budget3. Appoint the operating institution and the end users4. Provide the land as required5. Request permission from PLN

39

Page 40: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

6. Technical documents such as feasibility study

39

Page 41: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

STEP 2 : EVALUATION

Administrative and technical. Sometimes it includes site visits

40

Page 42: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

STEP 3 : APPOINTMENT

The sites are determined and budgeted for the next year’s cycle

41

Page 43: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

STEP 4 : PROCUREMENT

42

Page 44: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

STEP 5 : ASSET HANDOVER

Handover of the asset ownership to the institution who requested the minigrid to begin with. This is typically the province. In this case both the MEMR and the province will have to agree to the handover based on prevailing regulations and given that the assets are in good working order

43

Page 45: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

STEP 6 : MANAGEMENT

Operation and management of the assets :1. An entity must be appointed as the operator or end user of the asset. They can be cooperatives, local

government owned company, or a community group2. The appointed operator MUST ensure fund allocation for operation and maintenance

44

Page 46: ENERGY - d1jiktx90t87hr.cloudfront.net · GRANT BUILT MINIGRIDS Location Size Technology Project Value Cost / Wp Wakatobi, South Sulawesi 800 kWp Solar PV $8,833,169 $11.04/Wp Mamuju,

Andre Susanto

[email protected]

+62 811 911 0427

https://id.linkedin.com/in/andresusanto