energy management and planning msj0210 energy generation 2 eduard latõšov
TRANSCRIPT
Energy Management and PlanningMSJ0210
Energy generation 2
Eduard Latõšov
TECHNOLOGY SPECIFICATION
Technical figures Economic figures
Energy generation
TECHNICAL FIGURES
Technology specification(technical figures)
Efficiency (heat, electrical, total) – main, well known
Availability, reliability
Level of automation
Efficiency drop working at partial load
Efficiency drop working at specific conditions
Minimum achievable capacity
Wood chips boiler minimum achievable capacity is about 25 – 35% of nominal capacity. For electrical boilers starting from almost 0.
Minimum achievable capacity
Technology specification(technical figures)
Wood chips boiler. Nominal capacity 55 MW.Minimum about 15 MW
Minimum achievable capacity
Solution 1
Technology specification(technical figures)
Wood chips boiler. Nominal capacity 100 MW.Minimum about 25 MW
Minimum achievable capacity
Solution 2
Technology specification(technical figures)
Solution 1 in comparison with Solution 2Lose Win
Minimum achievable capacity
Does additional production for Solution 2 justifies construction of 100 MW boiler instead of 55 MW?In this case it seems not
Technology specification(technical figures)
If no hot tap water production exist
(district heating network does not operate outside district heating
season).
Does additional production for Solution 2 justifies construction of 100 MW boiler instead of 55 MW?In this case it seems so
Technology specification(technical figures)
Minimum achievable capacity
Efficiency drop
COP
Technology specification(technical figures)
Efficiency drop
Steam turbine
ORC plant
Technology specification(technical figures)
STEAM TURBINE AND ORC (capacity 1 – 2 MWel the same cooling temperature, ca 85oC)
Efficiency drop
Electrical efficiency
Nominal capacity
100%30%
15%
10%
5%
Technology specification(technical figures)
Efficiency drop Technology specification(technical figures)
ECONOMIC FIGURES
Main inputs and outputs
INPUTS OUTPUTS
TECHNOLOGICAL PROCESS
HEATFUEL
ELECTRICITY
WATER
MAN POWER ELECTRICITY
SEWERAGE
AIR EMISSIONS
ASH
OTHER PRODUCTS
OTHER EMISSIONS ANDENVIRONMENTAL IMPACTS
Kaasnevad INCOMES and COSTS. Some of inputs and outputs
can serve as INCOMES and COSTS
OTHER ACTIVITIESAND CONSUMABLES
Technology specification(economic figures)
Cash flowsHow to estimate?
2. USE REFERENCE VALUES1. CALCULATE ALL COMPONENTS
3. USE BOTH
Main inputs and outputs Technology specification(economic figures)
Main types of costs
Fixed costs, €/MW Other variable costs, €/MWh Fuel, €/MWh
X
Production, MWh
X
Production, MWh
/
Efficiency
X
Capacity, MW
Costs, €
MAINLY FIXED INCOMES, €/MW ENERGY SELLS
Energy price, €/MWh x
Volume/amount, MWh
X
Capacity, MW
Incomes, €
Example: reserve capacity
Economic and technical figures are important.
Where to find them?
Data sources
ExperiencePrevious projects
ResearchesReports
Presentations
Databases
Internal competence
Specific sources
Basic statistics
LITERATUREINTERNET
Data sources
KogemusVarasemad tööd
UuringudRaportid
Presentatsioonid
Andmebaasid
ExperiencePrevious projects
ResearchesReports
Presentations
Databases
Internal competence
Specific sources
Basic statistics
LITERATUREINTERNET
Experienced CONSULTANT
(company)
Need for consultants
- Availability of internal competence;
- Sufficiency (man power);
- Money availability.
Need = f
Reduction of planning and project management risks
Experienced CONSULTANT
(company)
Data sources. Examples.
https://www.energinet.dk/SiteCollectionDocuments/Danske%20dokumenter/Forskning/Technology_data_for_energy_plants.pdf
Data sources. Examples.
http://www3.epa.gov/chp/documents/catalog_chptech_full.pdf
Data sources. ExamplesDescription and evaluation of the new 1,000 kWel Organic Rankine Cycle process integrated in the biomass CHP plant in Lienz, Austria
FINDING OF ECONOMIC AND TECHNICAL DATA IS NOT ALWAYS EASY WORK
MAINLY IT IS NECESSARY TO CHECK AND COMPARE DIFFERENT SOURCES.
DATA ACCURANCE STRONGLY AFFECT TO PLANNING RESULTS.