Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks

Upload: others

Post on 10-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

Energy

Networks

AssociationFlexible Connection Offers

15 September 2015

The Voice of the Networks

Page 2: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

2 The Voice of the Networks

• Significant volumes of applications – often on the same parts of the network leading to interactive offers and queues

• Reinforcement required resulting in high connection costs and long lead times

• Reinforcement ahead of need generally not possible due to the risk of stranded asset cost falling onto domestic customers

• Interaction with National Grid – SoW process and total system concerns raised in their System Operability Statement are resulting in the need to add further conditions to connection offers

Background

Page 3: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

3 The Voice of the Networks

• Expanding our offers to include flexible connections allows customers willing to be

constrained to be connected more quickly and cheaply whilst maintaining network security

for existing customers

• This will optimise our networks, increasing the utilisation level of existing assets

• It is also an important step in the transition from passive to active networks and will require

us to have greater visibility and wider control in order to undertake actions similar to a

System Operator

Flexible Connections - why bother?

Page 4: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

4 The Voice of the Networks

Distribution Network Operators are looking at a range of

options to help mitigate the costs of reinforcement…

Page 5: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

5 The Voice of the Networks

• Generation curtailed within specific seasons or time- of-day

• Generally best suited to smaller DG

• Modelled seasonal capacity variations

• Localised control only

• No communications link needed

• Non-optimised

Timed Connections

Page 6: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

6 The Voice of the Networks

• Developers are required to keep their DG export levels within the Maximum Export Capacity

specified in their Connection Agreement

• The Developer may over install generation plant but cap the export in line with their

Connection Agreement

• Some DNOs will permit additional generation connections to be made to existing DG sites

subject to application and technical assessment

The Use of Export Capping Schemes

Page 7: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

7 The Voice of the Networks

• DNOs working with the ENA to create some consistency

• Should shortly be in a position to issue some interim criteria which may include:

• Fail-safe

• Not rely on wireless comms

• Meet all relevant power quality requirements

• Act within a defined timescale

• Commissioning witnessed

• Additional relays at HV

Export Limiting Devices

Page 8: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

8 The Voice of the Networks

• Releases pre-fault capacity with trip facility

• Triggers constraint in the event of minimum system demand coinciding with maximum export

• Suitable for small clusters of generation behind one simple pinch point

• Not suitable in areas with complex constraints

• 11kV and 33kV

• Real-time monitored values

• Existing monitoring with localised control

Intertrip

Page 9: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

9 The Voice of the Networks

• Fully optimises capacity based on all constraints

• Variable connection offers depending on dynamic network conditions

• Management of generation using LIFO principles

• Real-time granular control of output

• Requires new Active Network Management control and monitoring systems

Active Network Management

Page 10: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

10 The Voice of the Networks

• More complex networks, involving many generators across different circuits and voltage

levels require constant monitoring to ensure the capacity is available and is shared optimally

• In order to manage the risk effectively, the system must be secure, robust and encompass all

affected areas

• An advanced deployment of intelligent monitoring and distributed control systems will be

underpinned by a fail-safe communications network, allowing the network to accommodate

more connections, whilst maintaining the quality and security of supply for existing

customers

Active Network Management

Page 11: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

11 The Voice of the Networks

• Utilise historic load and generation data, together with the assumed profiles of future

generation in the area to estimate the level of curtailment an application will receive

• The curtailment tools can provide a generation developer an indication of the level of

constraints a site will experience and the associated risk

• DNOs would expect developers to also do their own estimates as part of due diligence before

committing to an investment

Estimating Curtailment

Page 12: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

12 The Voice of the Networks

Demand Side Management

Page 13: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

13 The Voice of the Networks

Dynamic Circuit Thermal Rating

Page 14: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

14 The Voice of the Networks

Dynamic Circuit Thermal Rating

Page 15: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

15 The Voice of the Networks

• Flexible Connections are generally based on a Last In, First Out (LIFO) principle

• Your position in the stack is secured on receipt of the minimum application information

required

• Each customers calculated curtailment is based on all connected, committed and offered

capacity which sits ahead of them in the queue at that moment in time

• If generation ahead of you in the stack drops out, you will move up the stack and the

potential for curtailment will reduce

• Committed and offered capacity within the stack changes daily

Stack Management

Page 16: Energy Networks Association Fora... · Energy Networks Association Flexible Connection Offers 15 September 2015 The Voice of the Networks. ... • The Developer may over install generation

16 The Voice of the Networks

• Financial incentives and reducing generator technology costs have resulted in a significant

increase in the applications for connection to the distribution network

• DNOs are focused on providing more publicly available information and better customer

service

• The use of consortiums is a method of sharing the costs of upstream reinforcement

• DNOs are introducing flexible connection offers and are developing other innovative

solutions to reduce reinforcement costs, but whole system issues need to be considered

Summary